Similar Documents at Cook |
---|
Category:Meeting Summary
MONTHYEARML24183A2292024-07-0101 July 2024 Summary of Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 ML24103A1872024-04-16016 April 2024 Summary of Meeting with Indiana Michigan Power Co., Regarding Surveillance Capsule Program for DC Cook Nuclear Plant, Unit 2 ML24031A5872024-02-0202 February 2024 Summary of Meeting with Indiana Michigan Power Company Regarding Neutron Flux Instrumentation for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML23215A1662023-08-17017 August 2023 Summary of July 31, 2023, Meeting with Indiana Michigan Power Company Regarding Operating Power Sources for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML23199A2402023-07-19019 July 2023 Summary of the July 13, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 ML22355A6022023-01-0303 January 2023 Summary of December 14, 2022, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML22318A1992022-11-21021 November 2022 Summary of November 7, 2022, Meeting with Indiana Michigan Power Company Regarding Neutron Flux Instrumentation for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML22154A5342022-06-0909 June 2022 Summary of the June 1, 2022, Public Outreach to Discuss the NRC 2021 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant ML22011A2732022-01-13013 January 2022 Summary of Meeting with Indiana Michigan Power Company to Discuss Planned Final Response to Generic Letter 2004-02 for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21349B3092022-01-0303 January 2022 Summary of Meeting with Indiana Michigan Power Company to Discuss Potential Changes to the Quality Assurance Program for Donald C. Cook Nuclear Plant, Units 1 and 2 ML21202A1072021-07-23023 July 2021 Summary of July 20, 2021, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21196A5182021-07-15015 July 2021 July 8, 2021, Summary of Public Webinar to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of the Donald C. Cook Nuclear Plant ML21082A0052021-03-24024 March 2021 Summary of March 19, 2021, with Indiana Michigan Power Company Regarding Containment Water Level Channels for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20349A0152020-12-17017 December 2020 Summary of November 30, 2020, Teleconference with Indiana Michigan Power Company Regarding a Planned License Amendment Request to Extend the Containment Integrated Leak Rate Testing Interval for Donald C. Cook Nuclear Plant, Unit No. 2 ML20282A2712020-10-14014 October 2020 Summary of October 2, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML20248H4752020-09-10010 September 2020 Summary of August 6, 2020, Teleconference with Indian Michigan Power Company Related to Steam Generator Eddy Current Testing License Amendment Request ML20209A6032020-07-27027 July 2020 Summary of the July 21, 2020, Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of the Donald C. Cook Nuclear Plant, Units 1 and 2 ML20133K1282020-05-21021 May 2020 Summary of May 4, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20121A0692020-05-0404 May 2020 Summary of Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20041C9492020-02-13013 February 2020 Summary of February 6, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19350A0552019-12-30030 December 2019 Summary of 12/12/2019 Meeting with Indiana Michigan Power Company, License Amendment Request for D.C. Cook Nuclear Plant, Units 1 and 2 to Delete Surveillance Requirement Related to Diesel Generator Load Test Resistor Banks ML19212A5652019-07-30030 July 2019 Summary of Public Open House to Discuss NRC Activities and the 2018 End-Of-Cycle Performance Assessment of Donald C. Cook Nuclear Generating Plant, Units 1 and 2 ML19141A0622019-06-0606 June 2019 Summary of November 19, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19099A3262019-04-16016 April 2019 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19067A0482019-03-12012 March 2019 Summary of Public Teleconference with Indiana Michigan Power Co. (I&M) Review of LAR for Approval of Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping (EPID-2019-LLA-0054) ML18334A0402018-12-13013 December 2018 Summary of Meeting with Indian Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML18109A0692018-04-26026 April 2018 Summary of April 10, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML18052B0542018-02-26026 February 2018 Summary of February 15, 2018, Meeting with Indian Michigan Power Company Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 (EPID L-2018-LRM-0008 ML18018B1382018-01-22022 January 2018 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML17265A4922017-10-0404 October 2017 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 2 ML17235B1232017-08-23023 August 2017 Summary of the July 27, 2017, Open House to Discuss the 2016 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant ML17082A0762017-03-27027 March 2017 Summary of March 20, 2017, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML16308A1132016-11-16016 November 2016 Summary of October 27, 2016, Public Meeting with Indiana Michigan Power Company Regarding the Donald C. Cook Nuclear Plant, Units 1 and 2 ML16244A7062016-08-30030 August 2016 Summary of the August 22, 2016, Donald C. Cook Public Meeting ML16193A5912016-07-15015 July 2016 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML15271A0462015-10-0505 October 2015 Summary of Public Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML15237A3362015-09-0202 September 2015 Summary of August 24, 2015, Telephone Call to Provide Verbal Authorization of Relief Request ISIR-4-06, Alternate Repair of Socket Weld ML15107A0982015-04-24024 April 2015 April 14, 2015, Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML14311A3182014-11-14014 November 2014 Summary of Conference Call with Donald C. Cook Nuclear Plant, Unit 1 Regarding the Fall 2014 Steam Generator Inspections ML14231A0752014-08-27027 August 2014 Summary of the August 8, 2014, Pre-Application Meeting with American Electric Power Company to Discuss a Future License Amendment Request for Alternative Source Term and TSTF-490 ML14209A9422014-07-30030 July 2014 July 9, 2014, Summary of Category 1, Public Meeting with Indiana Michigan Power Company to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2.1 ML14199A0802014-07-18018 July 2014 Summary of July 8, 2014 Donald C. Cook Public Annual Assessment Meeting ML14023A3872014-01-30030 January 2014 Summary of Joint Steering Committee Meeting to Discuss Activities Related to Lessons-Learned from the Fukushima Dai-Ichi Nuclear Power Plant Event ML13210A2272013-08-0202 August 2013 6/26/13, Summary of Pre-Application Meeting to Discuss Pending License Amendment Request to Modify the CNP Unit 1 Normal Operating Pressure and Temperature ML13189A2322013-07-15015 July 2013 Summary of Conference Telephone Call Regarding the 2013 Steam Generator Tube Inspections ML13154A4062013-06-0303 June 2013 5/30/2013 - Summary of the D.C. Cook Public Meeting ML12159A4022012-06-0707 June 2012 May 31, 2012 Summary of Public Meeting to Discuss the 2011 Annual Assessment Results for D.C. Cook ML1133307782011-11-29029 November 2011 Record of Discussion by Phone on 10/5/11 Regarding Steam Generator Inspection ML11129A2422011-06-0808 June 2011 Summary of Meeting with Indiana Michigan Power Company to Discuss Issues Related to a Future Submittal Using NFPA 805 ML0931305572009-11-0909 November 2009 Summary of Public Meeting with Staff from the D.C. Cook Nuclear Power Plant Regarding the September 2008 Unit 1 Turbine Vibration Event 2024-07-01
[Table view] |
Text
~RREGIJ~
l"~c.'o\ UNITED STATES
~.. ~
I:
NUCLEAR REGULATORY COMMISSION
~ j WASHINGTON, D.C. 20555-0001
....,,,, ~&
,, ****i' March 12, 2019 LICENSEE: INDIANA MICHIGAN POWER COMPANY FACILITY: DONALD C. COOK NUCLEAR PLANT, UNIT 1
SUBJECT:
SUMMARY
OF FEBRUARY 27, 2019, PUBLIC TELECONFERENCE WITH INDIANA MICHIGAN POWER COMPANY (l&M) REGARDING REVIEW OF LICENSE AMENDMENT REQUEST FOR APPROVAL OF LEAK-BEFORE-BREAK METHODOLOGY FOR REACTOR COOLANT SYSTEM SMALL DIAMETER PIPING (EPID-2019-LLA-0054)
On February 27, 2019, a Category 1 public teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Indiana Michigan Power Company (l&M, the licensee). The teleconference was held at the NRC Headquarters located in Rockville, Maryland. The purpose of the teleconference was to discuss the licensee's proposed license amendment request (LAR) to apply leak-before-break (LBB) methods to certain reactor coolant system (RCS) small diameter branch lines at the Donald C. Cook Nuclear Plant (CNP), Unit 1.
Specifically, the NRC staff requested the licensee to clarify its proposed LBB approach under NUREG-0800, Standard Review Plan (SRP), Section 3.6.31 , by means of Westinghouse LBB methods. The LAR under review, dated March 7, 2018, is available in the NRC's Agencywide Documents Access and Management System (ADAMS) (Accession No. ML18072A012).
SRP 3.6.3 states, in part, that specific areas of review for the NRC staff to consider during performance of an LBB evaluation include, (1) deterministic fracture mechanics, and (2) leak rate evaluation. Regarding the fracture mechanics analysis, the NRC staff informed the licensee that the LAR provided sufficient information for the staff to make a safety determination. Regarding the leak rate evaluation, the NRC staff informed the licensee that additional information was needed. Specifically, the LAR requests NRC approval for LBB on all accumulator, safety injection (SI), and residual heat removal (RHR), piping segments.
Since portions of these piping segments are downstream of check valves, the staff stated it has questions related to RCS leakage detection guidance (i.e., SRP 3.6.3 and Regulatory Guide 1.452 ). The NRC staff and the licensee discussed the following regulatory guidance:
SRP 3.6.3,Section II, "Acceptance Criteria," states, in part:
LBB should only be applied to high energy, ASME Code Class 1 or 2 piping or the equivalent. Applications to other high energy piping will be considered based on an evaluation of the proposed design and in-service inspection requirements as compared to ASME Code Class 1 and 2 requirements.
1 NUREG-0800, "Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition," SRP 3.6.3, Revision 1, "Leak-Before-Break Evaluation Procedures," ADAMS Accession No. ML063600396, dated March 2007.
2 Regulatory Guide 1.45, Revision 1, "Guidance on Monitoring and Responding to Reactor Coolant System Leakage,"
ADAMS Accession No. ML0732002701, dated June 2007.
In response, the licensee stated that portions the proposed accumulator, SI, and RHR piping segments (under review) are considered to be moderate energy piping systems (vs. high energy),
and therefore an LBB analysis is not required, for those segments. Furthermore, the licensee stated that the portions of the moderate energy piping segments were not necessary for the evaluation of LBB to proceed. The NRC staff acknowledged this new information from the licensee and suggested for the LAR to be revised. The licensee concurred, and proposed a revision to the LAR which will reflect excluding portions of the accumulator, SI, and RHR piping segments, not meeting the LBB acceptance criteria, as stated above.
The staff informed the licensee that previously distributed RAl-8 and RAl-9 requests 3 would be altered to reflect the new information that had developed during the teleconference. The staff's revised RAls will request information to support the RCS leakage detection portion of the evaluation (i.e., sensitivity analysis, detector calculations, proximity of detector, detector redundancy, etc.). The revised RAls will also request the licensee to verify that the CNP, Unit 1 LBB analysis includes RCS activity related to current nuclear fuel performance.
All feedback or comments expressed by the NRC staff during the meeting does not establish a regulatory position or constitute the acceptability of methodologies or changes discussed. One member of the public was identified on the teleconference. No public meeting feedback forms or comments have been received by the NRC staff.
Please direct any inquiries to me at 301-415-1129 or Russell.Haskell@nrc.gov.
Russell Haskell II, Project Manager Plant Licensing Branch Ill Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-315
Enclosure:
List of Attendees cc: Listserv 3 ADAMS Accession No. ML19011A351, dated January 11, 2019.
LIST OF ATTENDEES FEBRUARY 27, 2019, PUBLIC TELECONFERENCE WITH INDIANA MICHIGAN POWER CO.
Name Affiliation Shaun Anderson U.S. Nuclear Regulatory Commission (NRC)
David Wrona NRC Russell Haskell NRC David Nold NRC John Tsao NRC Steve Jones NRC Garry Steven NRC Seung Min NRC Ravinder Grover NRC Khadijah West NRC Gerard Purciarello NRC Raymond Ng NRC John Ellegood NRC Eric Duncan NRC Jeffrey Poehler NRC Jay Wallace NRC Robert Tregoning NRC Patrick Ravnaud NRC Dan Widrevitz NRC Jud Winkler Indian Michigan Power Company (l&M)
Jeff Hudson l&M Ben Horner l&M Greg Hill l&M Michael Scarpello l&M Helen Levendosky l&M Joe Tanko l&M Doug Badgero l&M Eric Johnson l&M Dave Dolby l&M Sara Weindorf Westinahouse Todd Trygier State of Michi!::ian (Dept. of Environmental Quality)
Enclosure
ML19067A048 OFFICE NRR/D0RL/LPL3/PM NRR/D0RL/LPL3/LA NRR/D0RL/LPL3/BC NRR/D0RL/LPL3/PM NAME RHaskell SRohrer DWrona RHaskell DATE 3/7/19 3/7/19 3/12/19 3/12/19