April 14, 2015, Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2
ML15107A098
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 04/24/2015
From: Dietrich A
Plant Licensing Branch III
To:
Dietrich A
Shared Package
ML15105A181 List:
References
TAC MF5882, TAC MF5883
Download: ML15107A098 (4)


Text

LICENSEE: Indiana Michigan Power Company, LLC FACILITY: Donald C. Cook Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF APRIL 14, 2015, MEETING WITH INDIANA MICHIGAN POWER COMPANY REGARDING DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2 (TAC NOS. MF5882 and MF5883)

On April 14, 2015, a Category I public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Indiana Michigan Power Company (l&M, the licensee). This meeting was open to members of the public. No regulatory decisions were made at this meeting.

The purpose of the meeting was to discuss a planned license amendment request for Donald C.

Cook Nuclear Plant (CNP), Units 1 and 2. The licensee plans to submit a request to adopt Technical Specifications Task Force (TSTF) Standard Technical Specifications Change Traveler TSTF-425, Revision 3, "Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specifications Task Force (RITSTF) Initiative 5b." TSTF-425 is publicly-available at Agencywide Documents Access and Management System (ADAMS) Accession No. ML090850642. The proposed change would relocate most time-based surveillance frequencies to a licensee-controlled program, called the Surveillance Frequency Control Program (SFCP), and add the SFCP to the administrative controls section of the technical specifications (TSs). The meeting notice, agenda, and handouts are available at ADAMS Accession No. ML15105A181. A list of meeting attendees is provided as Enclosure 1.

The licensee presented information regarding its plan to submit a TSTF-425 license amendment request in July 2015, and to request approval by July 2016 in order to support the 2016 Unit 2 refueling outage. l&M discussed taking credit for Westinghouse SHIELD Passive Thermal Shutdown Seals for Reactor Coolant Pumps in their probabilistic risk assessment (PRA) model.

The PRA model for the SHIELD seals will be based on Pressurized Water Reactor Owners Group (PWROG)-14401-NP, Revision 1, "PRA Model for the Generation Ill Westinghouse Shutdown Seal," dated July 2014. The NRC staff noted that the licensee should discuss planned modifications that are incorporated into the PRA model, as well as permanent plant changes that could impact the TSTF-425 application that have not yet been incorporated into the PRA model.

The full-scope Internal Events PRA peer review for l&M's PRA model is expected to be completed in July 2015. The licensee confirmed that this peer review would be against the latest endorsed PRA standard and Regulatory Guide (RG) 1.200, Revision 2 (ADAMS Accession No. ML090410014), and that this would be documented in their submittal. l&M plans to submit the results of this review to the NRC as a supplement to the license amendment request in August 2015. The NRC staff stated that they should be able to accept the application and begin the technical review as long as the necessary PRA technical adequacy documentation is provided, and recognized that the supplement may supersede some of that information. The staff also asked the licensee if the supplement will include the licensee's

evaluation of the peer review Fact and Observation findings and their impact on the application.

The licensee stated that their submittal would include this information.

l&M stated that it intends to use Nuclear Energy Institute 04-10, Revision 1, "Risk-Informed Technical Specifications Initiative 5b, Risk-Informed Method for Control of Surveillance Frequencies" (ADAMS Accession No. ML071360456), and RG 1.200, Revision 1 (ADAMS Accession No. ML070240001), as the technical bases for the request to adopt TSTF-425. The NRC staff explained that their review would be performed using RG 1.200, Revision 2. The licensee asked if the NRC staff expected revised TS bases pages to be submitted with the amendment application. The NRC staff told the licensee that, though not required, the revised TS bases pages would be helpful in their review of the application. The staff also reminded the licensee that there are four categories of Surveillance Frequencies that cannot be relocated to the SFCP, as described in Section 2.0, "Proposed Change," of TSTF-425, Revision 3.

Members of the public were in attendance. Public Meeting Feedback forms were not received.

Please direct any inquiries to me at 301-415-2846, or Allison.Dietrich@nrc.gov.

Sincerely, Allison W. Dietrich, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-315 and 50-316

Enclosure:

List of Attendees cc w/encl: Distribution via Listserv

LIST OF ATTENDEES APRIL 14, 2015, PUBLIC MEETING WITH l&M, LLC DONALD C. COOK NUCLEAR PLANT, UNITS 1 AND 2 PLANNED LICENSE AMENDMENT REQUEST REGARDING TSTF-425 Name Organization Allison Dietrich NRC Ravinder Grover NRC Jonathan Evans NRC David Gennardo NRC Alice Erickson NRC Michael Scarpello* l&M Helen Etheridqe* l&M Danielle Burgoyne* l&M Steve Cherba* l&M Jim Heveck* l&M Eric Thornsberry* ERIN Engineering Brandon Ervin* ERIN Enqineerinq Todd Trvqier* Michigan State Dept of Environmental Quality

  • Participated by phone Enclosure

ML071360456), and RG 1.200, Revision 1 (ADAMS Accession No. ML070240001 ), as the technical bases for the request to adopt TSTF-425. The NRC staff explained that their review would be performed using RG 1.200, Revision 2. The licensee asked if the NRC staff expected revised TS bases pages to be submitted with the amendment application. The NRC staff told the licensee that, though not required, the revised TS bases pages would be helpful in their review of the application. The staff also reminded the licensee that there are four categories of Surveillance Frequencies that cannot be relocated to the SFCP, as described in Section 2.0, "Proposed Change," of TSTF-425, Revision 3.

Members of the public were in attendance. Public Meeting Feedback forms were not received.

Please direct any inquiries to me at 301-415-2846, or Allison.Dietrich@nrc.gov.

Sincerely, IRA/

Allison W. Dietrich, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-315 and 50-316

Enclosure:

List of Attendees cc w/encl: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrLAMHenderson Resource LPL3-1 Reading RidsRg n3mai1Center Resource RidsAcrsAcnw_MailCTR Resource RidsNrrPmDCCook Resource RidsNrrDorllpl3-1 Resource RidsNrrDorl Resource RidsOpaMail Resource DGennardo, NRR KMorganButler, EDO RGrover, NRR PMNS Resource PSnyder, NRR JEvans, NRR AErickson, NRR ADAMS Accession No.: ML15107A098 OFFICE DORL/LPL3-1 /PM DORL/LPL3-1 /LA DORL/LPL3-1 /BC DORL/LPL3-1/PM NAME ADietrich MHenderson DPelton ADietrich DATE 04/17/2015 04/23/2015 04/24/2015 04/24/2015