Letter Sequence Other |
---|
|
|
MONTHYEARML21196A0042021-07-14014 July 2021 Slides - Cook - Pre-Application EP 7/20/2021 Meeting Slides Project stage: Meeting ML21202A1072021-07-23023 July 2021 Summary of July 20, 2021, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 Project stage: Other 2021-07-14
[Table View] |
Similar Documents at Cook |
---|
Category:Meeting Summary
MONTHYEARML24305A1002024-11-0101 November 2024 Summary of Meeting with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 ML24183A2292024-07-0101 July 2024 Summary of Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 ML24103A1872024-04-16016 April 2024 Summary of Meeting with Indiana Michigan Power Co., Regarding Surveillance Capsule Program for DC Cook Nuclear Plant, Unit 2 ML24031A5872024-02-0202 February 2024 Summary of Meeting with Indiana Michigan Power Company Regarding Neutron Flux Instrumentation for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML23215A1662023-08-17017 August 2023 Summary of July 31, 2023, Meeting with Indiana Michigan Power Company Regarding Operating Power Sources for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML23199A2402023-07-19019 July 2023 Summary of the July 13, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 ML22355A6022023-01-0303 January 2023 Summary of December 14, 2022, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML22318A1992022-11-21021 November 2022 Summary of November 7, 2022, Meeting with Indiana Michigan Power Company Regarding Neutron Flux Instrumentation for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML22154A5342022-06-0909 June 2022 Summary of the June 1, 2022, Public Outreach to Discuss the NRC 2021 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant ML22011A2732022-01-13013 January 2022 Summary of Meeting with Indiana Michigan Power Company to Discuss Planned Final Response to Generic Letter 2004-02 for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21349B3092022-01-0303 January 2022 Summary of Meeting with Indiana Michigan Power Company to Discuss Potential Changes to the Quality Assurance Program for Donald C. Cook Nuclear Plant, Units 1 and 2 ML21202A1072021-07-23023 July 2021 Summary of July 20, 2021, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21196A5182021-07-15015 July 2021 July 8, 2021, Summary of Public Webinar to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of the Donald C. Cook Nuclear Plant ML21082A0052021-03-24024 March 2021 Summary of March 19, 2021, with Indiana Michigan Power Company Regarding Containment Water Level Channels for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20349A0152020-12-17017 December 2020 Summary of November 30, 2020, Teleconference with Indiana Michigan Power Company Regarding a Planned License Amendment Request to Extend the Containment Integrated Leak Rate Testing Interval for Donald C. Cook Nuclear Plant, Unit No. 2 ML20282A2712020-10-14014 October 2020 Summary of October 2, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML20248H4752020-09-10010 September 2020 Summary of August 6, 2020, Teleconference with Indian Michigan Power Company Related to Steam Generator Eddy Current Testing License Amendment Request ML20209A6032020-07-27027 July 2020 Summary of the July 21, 2020, Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of the Donald C. Cook Nuclear Plant, Units 1 and 2 ML20133K1282020-05-21021 May 2020 Summary of May 4, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20121A0692020-05-0404 May 2020 Summary of Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20041C9492020-02-13013 February 2020 Summary of February 6, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19350A0552019-12-30030 December 2019 Summary of 12/12/2019 Meeting with Indiana Michigan Power Company, License Amendment Request for D.C. Cook Nuclear Plant, Units 1 and 2 to Delete Surveillance Requirement Related to Diesel Generator Load Test Resistor Banks ML19212A5652019-07-30030 July 2019 Summary of Public Open House to Discuss NRC Activities and the 2018 End-Of-Cycle Performance Assessment of Donald C. Cook Nuclear Generating Plant, Units 1 and 2 ML19141A0622019-06-0606 June 2019 Summary of November 19, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19099A3262019-04-16016 April 2019 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19067A0482019-03-12012 March 2019 Summary of Public Teleconference with Indiana Michigan Power Co. (I&M) Review of LAR for Approval of Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping (EPID-2019-LLA-0054) ML18334A0402018-12-13013 December 2018 Summary of Meeting with Indian Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML18109A0692018-04-26026 April 2018 Summary of April 10, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML18052B0542018-02-26026 February 2018 Summary of February 15, 2018, Meeting with Indian Michigan Power Company Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 (EPID L-2018-LRM-0008 ML18018B1382018-01-22022 January 2018 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML17265A4922017-10-0404 October 2017 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 2 ML17235B1232017-08-23023 August 2017 Summary of the July 27, 2017, Open House to Discuss the 2016 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant ML17082A0762017-03-27027 March 2017 Summary of March 20, 2017, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML16308A1132016-11-16016 November 2016 Summary of October 27, 2016, Public Meeting with Indiana Michigan Power Company Regarding the Donald C. Cook Nuclear Plant, Units 1 and 2 ML16244A7062016-08-30030 August 2016 Summary of the August 22, 2016, Donald C. Cook Public Meeting ML16193A5912016-07-15015 July 2016 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML15271A0462015-10-0505 October 2015 Summary of Public Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML15237A3362015-09-0202 September 2015 Summary of August 24, 2015, Telephone Call to Provide Verbal Authorization of Relief Request ISIR-4-06, Alternate Repair of Socket Weld ML15107A0982015-04-24024 April 2015 April 14, 2015, Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML14311A3182014-11-14014 November 2014 Summary of Conference Call with Donald C. Cook Nuclear Plant, Unit 1 Regarding the Fall 2014 Steam Generator Inspections ML14231A0752014-08-27027 August 2014 Summary of the August 8, 2014, Pre-Application Meeting with American Electric Power Company to Discuss a Future License Amendment Request for Alternative Source Term and TSTF-490 ML14209A9422014-07-30030 July 2014 July 9, 2014, Summary of Category 1, Public Meeting with Indiana Michigan Power Company to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2.1 ML14199A0802014-07-18018 July 2014 Summary of July 8, 2014 Donald C. Cook Public Annual Assessment Meeting ML14023A3872014-01-30030 January 2014 Summary of Joint Steering Committee Meeting to Discuss Activities Related to Lessons-Learned from the Fukushima Dai-Ichi Nuclear Power Plant Event ML13210A2272013-08-0202 August 2013 6/26/13, Summary of Pre-Application Meeting to Discuss Pending License Amendment Request to Modify the CNP Unit 1 Normal Operating Pressure and Temperature ML13189A2322013-07-15015 July 2013 Summary of Conference Telephone Call Regarding the 2013 Steam Generator Tube Inspections ML13154A4062013-06-0303 June 2013 5/30/2013 - Summary of the D.C. Cook Public Meeting ML12159A4022012-06-0707 June 2012 May 31, 2012 Summary of Public Meeting to Discuss the 2011 Annual Assessment Results for D.C. Cook ML1133307782011-11-29029 November 2011 Record of Discussion by Phone on 10/5/11 Regarding Steam Generator Inspection ML11129A2422011-06-0808 June 2011 Summary of Meeting with Indiana Michigan Power Company to Discuss Issues Related to a Future Submittal Using NFPA 805 2024-07-01
[Table view] |
Text
July 23, 2021 LICENSEE:
Indiana Michigan Power Company, LLC FACILITY:
Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2
SUBJECT:
SUMMARY
OF JULY 20, 2021, WITH INDIANA MICHIGAN POWER COMPANY TO DISCUSS POTENTIAL CHANGES TO THE EMERGENCY PLAN FOR DONALD C. COOK NUCLEAR PLANT, UNIT NOS. 1 AND 2 (EPID L-2021-LRM-0065)
On July 20, 2021, a public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Indiana Michigan Power Company (I&M, the licensee) via teleconference. The purpose of this meeting was for I&M to provide information on a planned license amendment request (LAR) for the Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 (CNP), related to related to revising the CNP Emergency Plan. The meeting notice and agenda dated July 6, 2021, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML21187A106, and I&Ms meeting handout is available at ADAMS Accession No. ML21196A004. A list of attendees is enclosed.
The licensee indicated that the potential license amendment revises the CNP EP to make, in part, the following changes to the Emergency Response Organization (ERO):
Align D.C. Cook on-shift and augmenting staff to the guidance provided in NUREG-0654 Revision 2, Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants, dated December 2019 (ADAMS Accession No. ML19347D139).
Reduction of the current on-shift staffing.
Extend full augmented ERO response times from 60 minutes to 90 minutes.
Revise Drive-in Drill frequency from annually to once per 8-yr cycle.
The licensee indicated that much of the potential LAR focused on aligning the CNP Emergency Plan with NUREG-0654/FEMA-REP-1, Revision 2. The NRC staff reminded I&M that Regulatory Issue Summary 2016-10, License Amendment Requests for Changes to Emergency Response Organization Staffing and Augmentation, dated August 5, 2016 (ADAMS Accession No. ML16124A002) provides clarification for developing an on-shift staffing analysis.
I&M currently plans to submit the LAR request later in 2021. The NRC staff appreciated that the licensee held the meeting early in the development process so that any staff comment could be considered in the application.
No members of the public had questions or comments during the meeting. No regulatory decisions were made at this meeting.
Please direct any inquiries to me at 301-415-2855, or Scott.Wall@nrc.gov.
Sincerely,
/RA/
Scott P. Wall, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-315 and 50-316
Enclosure:
List of Attendees cc: Listserv
Enclosure LIST OF ATTENDEES JULY 20, 2021, PUBLIC MEETING WITH I&M DONALD C. COOK NUCLEAR PLANT, UNIT NOS. 1 AND 2 PLANNED LICENSE AMENDMENT REQUEST RELATED TO EMERGENCY PLAN Name Organization Scott Wall Nuclear Regulatory Commission (NRC)
Nancy Salgado NRC Michael Norris NRC Jeannette Arce NRC Raymond Hoffman NRC Michael Scarpello Indiana Michigan Power Company (I&M)
Helen Levendosky I&M Brad Culwell I&M Danielle Burgoyne I&M Robert Becvar I&M Kevin Simpson I&M Peter Polfleit Nextera Energy
ML21202A107 OFFICE NRR/DORL/LPL3/PM*
NRR/DORL/LPL3/LA*
NRR/DORL/LPL3/BC*
NRR/DORL/LPL3/PM*
NAME SWall SRohrer NSalgado (JWiebe for)
SWall DATE 07/20/2021 07/21/2021 07/23/2021 07/23/2021