Summary of August 11, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment Allow Bypass Testing of the Power Range Nuclear Instrumentation System Channels
ML21229A169
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 08/23/2021
From: Robert Kuntz
Plant Licensing Branch III
To: Domingos C
Northern States Power Co
Kuntz R
References
EPID L-2021-LRM-0061
Download: ML21229A169 (4)


Text

August 23, 2021 LICENSEE: Northern States Power Company FACILITY: Prairie Island Nuclear Generating Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF AUGUST 11, 2021, MEETING WITH NORTHERN STATES POWER COMPANY, DOING BUSINESS AS XCEL ENERGY, RELATED TO A PLANNED LICENSE AMENDMENT TO ALLOW BYPASS TESTING OF THE POWER RANGE NUCLEAR INSTRUMENTATION SYSTEM CHANNELS (EPID L-2021-LRM-0061)

On August 11, 2021, an observation public meeting was held between the U.S. Nuclear Regulatory Commission (NRC), and representatives of Northern States Power Company, doing business as Xcel Energy (Xcel Energy, the licensee). The purpose of the meeting was for Xcel Energy to provide information about a planned amendment for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Prairie Island). The planned amendment would modify the Prairie Island technical specifications (TSs) to allow testing the power range nuclear instrumentation system channels with the channel in bypass. The meeting notice and agenda, dated July 21, 2021, are available in Agencywide Documents Access and Management System (ADAMS) at Accession No. ML21202A008. The licensees presentation is available in ADAMS at Accession No. ML21221A020. A list of attendees is provided as Enclosure 1.

The licensee presented information regarding the planned license amendment that would allow a single channel to be bypassed during testing and maintenance activities for trips associated with power range instrumentation. The licensee stated that bypassing channels during testing and maintenance activities will reduce trip state vulnerability during power range nuclear instrumentation system testing. The NRC staff queried the licensee on the actuation logic that would be in place during testing and maintenance activities as a result of the amendment.

Specifically, the NRC staff questioned if the revised TSs would allow testing not currently permitted. The licensee clarified that the resulting TSs would permit testing without initiating an active channel trip. This would effectively alter the trip logic to a two-out-of-three configuration during testing and maintenance activities.

The NRC staff also inquired about the proposed elimination of actuation relays from the existing surveillance test program. The licensee stated that these relays would continue to be tested at a reduced frequency during plant refueling outages and that justification for this reduced testing would be provided as part of the license amendment request. The staff also confirmed that existing limiting conditions for operation under channel failure conditions would not be altered by the TS changes which would apply only to testing and maintenance activities.

No members of the public were in attendance. No regulatory decisions were made at this meeting.

Please direct any inquiries to me at 301-415-3733 or Robert.Kuntz@nrc.gov.

/RA/

Robert Kuntz, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES AUGUST 11, 2021, MEETING WITH NORTHERN STATES POWER COMPANY POTENTIAL AMENDMENT REQUEST TO ALLOW BYPASS TESTING OF THE POWER RANGE NUCLEAR INSTRUMENTATION SYSTEM CHANNELS Nuclear Regulatory Commission Robert Kuntz Richard Stattel Hang Vu Northern States Power Company Sara Scott Jeff Kivi Jack Harrison Kevin Holmstrom Sargent and Lundy (Northern States Power Company Contractor)

Chris Mundt Westinghouse (Northern States Power Company Contractor)

Jim Andrachek John Wiesemann Ed Jaszcar Enclosure

ML21229A169 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DORL/LPL3/BC NRR/DORL/LPL3/PM NAME RKuntz SRohrer NSalgado RKuntz DATE 08/16/2021 08/17/2021 08/23/2021 08/23/2021