November 3, 2020 LICENSEE:
Northern States Power Company FACILITY:
Prairie Island Nuclear Generating Plant, Units 1 and 2
SUBJECT:
SUMMARY
OF OCTOBER 19, 2020, MEETING WITH NORTHERN STATES POWER COMPANY, DOING BUSINESS AS XCEL ENERGY, RELATED TO THE LICENSE AMENDMENT TO ADOPT TSTF-505 PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES - RITSTF INTIATIVE 4b (EPID L-2019-LLA-0283)
On October 19, 2020, a Category 1 public teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Northern States Power Company, doing business as Xcel Energy (Xcel Energy, the licensee). The purpose of the meeting was for Xcel Energy to provide clarification of the supplemental information provided by letter dated September 1, 2020 (Agencywide Documents Access and Management System ML20245E401) related to the request to adopt Technical Specification Task Force (TSTF) Traveler TSTF-505 "Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b, for Prairie Island Nuclear Generating Plant, Units 1 and 2. The meeting notice and agenda, dated October 16, 2020, are available in ADAMS at Accession No. ML20280A609. A list of attendees is provided as Enclosure 1.
The NRC staff queried the licensee on the information provided in the September 1, 2020, letter.
Specifically, the staff requested clarification on the response to the NRC staffs request for additional information (RAI) 6.a. The response to RAI 6.a states that some containment penetrations will be able to use a risk informed completion time (RICT) and some will not, and summarized the criteria used to identify the two different populations of penetrations. The licensee noted that approval of the proposed amendment would add a note providing a RICT alternative to the current fixed completion time to technical specification (TS) ACTIONS 3.6.3.A and 3.6.3.C which apply to all containment penetrations. The licensee clarified that the population of containment penetrations that can use versus those that cannot use the RICT alternative will be part of the licensee controlled administrative process implementing the RICT program and not part of the TSs. The licensee stated that control of the identification of those penetrations that can use a RICT would be determined consistent with the administration of the program. The administrative process to ensure that the RICT is only used for those penetrations that can use the alternative will also be part of the administrative program. The NRC staff stated that it understood the licensee proposal.
Members of the public were in attendance. No public comments were received.
Please direct any inquiries to me at 301-415-3733, or Robert.Kuntz@nrc.gov.
/RA/
Robert F. Kuntz, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-282 and 50-306
Enclosure:
List of Attendees cc w/encls: Listserv
Enclosure LIST OF ATTENDEES OCTOBER 19, 2020, MEETING WITH NORTHERN STATES POWER COMPANY CLARIFICATION OF SUPPLEMENT RELATED TO THE LICENSE AMENDMENT REQUEST TO ADOPT TSTF-505 PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES - RITSTF INTIATIVE 4b PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1 AND 2 Nuclear Regulatory Commission Robert Kuntz Jeff Circle Robert Pascarelli Stephen Dinsmore Andrea Russell Northern States Power Company Sara Scott Mark Brossart Brian Slack Jayne Ritter Salma Mahzooni Steve Ingalls Jeff LeClair Ron Jacobson Public Jeff Quinn, Engineering Planning and Management (EPM), Inc.
Justin Hiller, Ameren Missouri
ML20296A261 (Package)
ML20280A609 (Meeting Notice)
ML20296A238 (Meeting Summary)
- via e-mail OFFICE NRR/DORL/LPL3/PM*
NRR/DORL/LPL3/LA*
NRR/DORL/LPL3/BC*
NRR/DORL/LPL3/PM*
NAME RKuntz SRohrer NSalgado (JWiebe for)
RKuntz DATE 10/22/2020 10/22/2020 11/03/2020 11/03/2020