ML20216A645

From kanterella
Jump to navigation Jump to search
Summary of the July 16, 2020, Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of the Prairie Island Generating Plant
ML20216A645
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 08/03/2020
From: Hironori Peterson
Region 3 Branch 3
To:
References
Download: ML20216A645 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, ILLINOIS 60532-4352 August 3, 2020 LICENSEE: Northern States Power Company FACILITY: Prairie Island Nuclear Generating Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF THE JULY 16, 2020, PUBLIC WEBINAR TO DISCUSS THE NRC 2019 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF THE PRAIRIE ISLAND NUCLEAR GENERATING PLANT On July 16, 2020, from 4:00 p.m. to 5:00 p.m. (CST), a public webinar was held by representatives of the U.S. Nuclear Regulatory Commission (NRC) to provide the public with information on the 2019 End-of-Cycle plant performance assessment of the Prairie Island Nuclear Generating Plant, along with general information on the NRC. There were two members of the public in attendance, along with state and local government officials, and licensee personnel, listed in the attached enclosure.

The NRC discussed their assessment of the Prairie Island Nuclear Generating Plant, as documented in the March 3, 2020, End-of-Cycle Assessment Letter (ADAMS Accession Number ML20062E200) during the webinar. Representatives from the NRC made links to these letters, inspection reports, fact sheets and brochures, and other public documents available to those in attendance.

/RA/_____________________

Honoroni Peterson, Branch Chief Branch 3 Division of Reactor Projects Docket Nos. 50-282; 50-306 License Nos. DPR-42; DPR-60 cc: Distribution via LISTSERV

SUBJECT:

SUMMARY

OF THE JULY 16, 2020, PUBLIC WEBINAR TO DISCUSS THE NRC 2019 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF THE PRAIRIE ISLAND NUCLEAR GENERATING PLANT DISTRIBUTION:

Jessie Quichocho Elise Burket RidsNrrPMPrairieIsland Resource RidsNrrDorlLpl3 RidsNrrDroIrib Resource John Giessner Kenneth OBrien Jamnes Cameron Allan Barker DRPIII DRSIII ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML20216A645 OFFICE RIII RIII NAME NShah:wc via email HPeterson via email DATE 8/3/2020 8/3/2020 OFFICIAL RECORD COPY

PUBLIC MEETING ATTENDEES July 16, 2020 U.S. Nuclear Regulatory Commission H. Peterson, Chief, Division of Reactor Projects (DRP), Branch 3, Region III B. Dickson, Deputy Director, Acting, DRP, Region III L. Haeg, Senior Resident Inspector, Prairie Island Nuclear Generating Plant K. Pusateri, Resident Inspector, Prairie Island Nuclear Generating Plant N. Shah, Senior Project Engineer A. Barker, Government Liaison Officer P. Chandrathil, Public Affairs Officer H. Logaras, Regional Government Liaison Specialist R. Kuntz, Project Manager M. Luo, IT Specialist V. Mitlyng, Senior Public Affairs Officer P. Chandrathil, Senior Public Affairs Officer T. Magee, IT Specialist D. Bogedain, Administrative Assistant N. Koester, Administrative Assistant K. Martinic, Student Engineer Xcel Energy S. Sharp, Site Vice President, Prairie Island Nuclear Generating Plant G. Hernandez, Regulatory Affairs Manager, Monticello Nuclear Generating Plant L. Sueper, Regulatory Affairs Manager, Prairie Island Nuclear Generating Plant State of Minnesota / Goodhue County M. Hallock, City of Red Wing, Minnesota R. Wake, Wisconsin Department of Health R. Ward, Wright County, Minnesota P. McLaughlin, State of Minnesota Prairie Island Indian Community Shelley Buck, Tribal Council President M. Childs, Jr., Tribal Council Assistant Secretary/Treasurer J. Seim, General Counsel Members of the Public J. Sorensen M. Woolen J. McGough T. Beltz Enclosure