April 9, 2020, Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request Related to Adopt TSTF-569 at Prairie Island Nuclear Generating Plant, Unit 1 and 2
ML20111A132
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 04/21/2020
From: Robert Kuntz
Plant Licensing Branch III
To:
Northern States Power Co
Kuntz R
References
EPID L-2020-LRM-0020
Download: ML20111A132 (4)


Text

April 21, 2020 LICENSEE: Northern States Power Company, a Minnesota Corporation FACILITY: Prairie Island Nuclear Generating Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF APRIL 9, 2020, MEETING WITH NORTHERN STATES POWER COMPANY, DOING BUSINESS AS XCEL ENERGY ON POTENTIAL LICENSE AMENDMENT REQUEST RELATED TO ADOPT TSTF-569 AT PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1 AND 2 (EPID L-2020-LRM-0020)

On April 9, 2020, a Category 1 public teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Northern States Power Company doing business as Xcel Energy (Xcel Energy). The purpose of the meeting was to discuss a potential license amendment to adopt Technical Specification Task Force (TSTF) Traveler TSTF-569 Revise Response Time Testing, for Prairie Island Nuclear Generating Plant (PINGP), Units 1 and 2. The meeting notice and agenda, dated March 26, 2020, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML20086N131. A list of attendees is provided as Enclosure 1.

The licensee presented information (ADAMS Accession No. ML20098F068) related to the potential license amendment request (LAR). The licensee presented an overview of the planned application.

The NRC staff queried the licensee on whether response time testing of transmitters is currently accomplished. The licensee responded that transmitters are not response time tested at PINGP, Units 1 and 2. Therefore, the proposed LAR would not affect the current test program for transmitters at PINGP, Units 1 and 2. The staff asked the licensee the basis for not performing response time testing and the licensee stated that it was part of the conversion to standard technical specifications.

The NRC staff then confirmed that the licensee currently performs response time testing on its protection system processing instrumentation. The licensee stated that implementation of TSTF-569 methodology could potentially eliminate this testing. The NRC staff stated that it would review the request when it is submitted and noted that no regulatory decisions will be made during the meeting.

Members of the public were not in attendance.

Please direct any inquiries to me at 301-415-3733, or Robert.Kuntz@nrc.gov.

/RA/

Robert F. Kuntz, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-282 and 50-306

Enclosure:

List of Attendees cc w/encls: Listserv

LIST OF ATTENDEES APRIL 9, 2020 MEETING WITH NORTHERN STATES POWER COMPANY POTENTIAL LICENSE AMENDMENT REQUEST RELATED TO TECHNICAL SPECIFICATION TASK FORCE (TSTF) TRAVELER TSTF-569 PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1 AND 2 Nuclear Regulatory Commission Robert Kuntz Kristy Bucholtz Richard Stattel Michael Waters Northern States Power Company Sara Scott Jeff Kivi Jack Harrison Kevin Holmstrom Enclosure

ML20086N131 (Meeting Notice)

ML20111A132 (Meeting Summary)

ML20098F068 (Handouts) *via e-mail OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DORL/LPL3/BC NRR/DORL/LPL3/PM NAME RKuntz SRohrer* NSalgado* RKuntz DATE 04/13/2020 04/20/2020 04/21/2020 04/21/2020