Advises NRC That as Licensee Recently Discussed by Telcon, Need Addl Time to Prepare Appropriate & Complete Responses
ML20217F860
Person / Time
Site: General Atomics
Issue date: 04/24/1998
From: Asmussen K
GENERAL ATOMICS (FORMERLY GA TECHNOLOGIES, INC./GENER
To: Alexander Adams
NRC (Affiliation Not Assigned), NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
38-67-2904, TAC-M98498, TAC-M98499, NUDOCS 9804280287
Download: ML20217F860 (1)


Text

h CENE:AL ATDRNCE April 24,1998 38/67-2904 Document Control Desk ATTN: Mr. Alexander Adams, Jr., Senior Project Manager Non-Power Reactors & Decommissioning Projects Directorate Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Subject:

Docket Nos. 50-89 and 50-163; Facility Licenses R-38 and R-67: TRIGA Reactors Facility Decommissioning Plan (TAC Nos. M98498 AND M98499)

Dear Mr. Adams:

General Atomics (GA) is in receipt of your request for additional information bted January 16,1998, regarding GA's TRIGA Mark I and Mark F research reactors decommisstq-ing plan. The purpose of this letter is simply to advise you, as we recently discussed t,y telephone, that GA will need additional time to prepare appropriate and complete responses.

At this time, we anticipate submitting our responses to you in about 90 days.

Should you desire edditional information concerning the above, please contact me at (619) 455-2823.

Very truly yours, Dr. Keith E. Asmussen, Director Licensing, Safety and Nuclear Compliance