First Interim Deficiency Rept 114 Re Possible Damage to safety-related Equipment Due to Water Hammers.Questionable or Damaged Seismic Restraints Reworked.Final Rept Will Be Submitted by 840831
ML20094N466
Person / Time
Site: Waterford Entergy icon.png
Issue date: 08/02/1984
From: Gerrets T
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
114, W3K84-1777, NUDOCS 8408160228
Download: ML20094N466 (5)


Text

__

t h.

a I LOUISIANA P OW E R & LiG H T /Waterford 3 SES/P. O. Box B/Killona, Louisiana 70066 N0YsErsN August 2, 1984 W3K84-1777 Q-3-A35.07.114

%3@BOUR %

Mr. John T. Collins Regional Administrator, Region IV M l Q lgg U. S. Nuclear Regulatory Commission ,j 611 Ryan Plaza Drive, Suite 1000 . S Arlington, Texas 76012

REFERENCE:

Telecon C. Hooper (LP&L) and J. Jourdan (NRC Region IV) on May 21, 1984 Telecon R. Gimelli (LP&L) and L. Martin (NRC Region IV) on July 11, 1984

Dear Mr. Collins:

SUBJECT:

Waterford SES Unit No. 3 Docket No. 50-382 Significant Construction Deficiency No. 114 "Possible Damage to Safety Related Equipment Due to Water Hammers" First Interim Report In accordance with the requirements of 10CFR50.55(e), we are hereby providing two copies of the Interim Report of Significant Construction Deficiency No.

114, "Possible Damage to Safety Related Equipment Due to Water Hammers". This item was previously reported as PRD No. 170.

If you have any questions, please advise.

Very truly yours, T.

~ A^at$

Gerrets Corporate Quality Assurance Manager TFG:CNH:SSTG Enclosure cc: Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D.C. 20555 (15 copies) 8408160228 840802 f 1 PDR ADOCK 05000392 S PDR e

l l i

I

4

'Mr. John T. Collins August 2, 1984

.W3K84-1777 Page 2 cc: Director Office of. Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D.C. '20555 Mr. E. L. Blake Shaw, Pittman, Potts & Tr vbridge 1800 M Street, N.W.

Washington, D.C. 20036 Mr. W. M. Stevenson Monroe & Lemann 1424 Whitney Building New Orleans, Louisiana 70130 Records Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, Georgia 30339 Mr. W. A. Cross 7910 Woodmont Avenue Suite 1200 Bethesda, Maryland 20814 4

4 l

f , 1

~% .

INTERIM REPORT OF .

,u. ISIGNIFICANT CONSTRUCTION DEFICIENCY- NO.114

" DAMAGED SAFETY RELATED SYSTEMS DUE TO WATER HAMMERS" l l

l

'INTe0 DUCTION-

~

This report is submitted pursuant to-10CFR50.55(e). It' describes the water hammer events which' occurred' on 5/10/84 ~ and 5/17/84. It-also describes the systems / components affected, subsequent corrective actions, and actions taken

. to minimize the potential for. recurrence.-

This deficiency has not been reported to the USNRC pursuant to 10CFR21.

-DESCRIPTION On May 9,1984 'at. approximately 14:45, with Safety Injection System (SIS) train "A" aligned in the shutdown cooling (SDC) mode, the annunciator for

" Loop 2 Shutdown Cooling System; Hydraulic Isolation Valve Troubis" began to alarm intermittently. In accordance.with annunciator response procedure OP-500-011, the motor breaker to the hydraulic actuator was opened for SIS Isol. Valve SI405A. On May 10, 1984 at about 06:48, a loss of shutdown cooling flow was observed and SI405A was indicated closed with LPSI "A" pump still running. LPSI "A" pump was immediately secured. The operators were not aware that a negative pressure existed in the Emergency Core Cooling' System (ECCS). The water hammer occurred when the Refueling Water Storage Pool (RWSP) quick opening butterfly outlet valve SIl06A was opened. ,

on May 17, 1984 at 00:50, while conducting an operability check of Containment Spray Pump (CSP) "A", personnel observed a drop in suction and discharge pressure and saw recirculation flow drop to zero. The pump was secured and valve SIl06A was found closed. Due to misinterpretation of communications.

SIl06A was opened resulting in the second water hammer event.

Subsequent walkdowns were performed to evaluate potential damage that may have been sustained in both events. Scope of inspections were as follows:

1) Ninety-six (96) supports associated with train A of the ECCS were evaluated. Twenty (20) restraints required further evaluation, rework, or replacement.
2) Ultra-sonic (UT) and dye penetrant testing (PT), consistent with the LP&L Inservice Inspection (ISI) program, were performed on affected piping. Six pts and five UTs were performed in areas where piping was postulated to have received the highest stresses.
3) All affected pumps (High Pressure Safety Injection (HPSI) "A", HPSI "A/B", Low Pressure Safety Injection (LPSI) "A", and Containment Spray (CS) "A") were tested in accordance with ISI surveillance procedures. X-Y vibration plots were performed on all the above pumps and' maintenance was performed where necessary to assure minimum vibration.

b ,s

~

=;

t , 3

. ).;

- SCD No. Il4' Page 2

- DESCRIPTION'(Continued) 14)7 A defe'ctive check valve within the hydraulic' operator for SI405A caused _the valve _to close thereby interrupting SDC flow.

' SAFETY IMPLICATION Supports associated with Train "A" of,the safety injection and containment

' spray! systems were damaged by the water hammer events. If left uncorrected, the event could have potentially caused inoperaoility of a single train of systems designed to remove residual heat and mitigate'the consequences of an accident in the event of a design basis earthquake.

CORRECTIVE ACTION The following corrective actions were taken to assure hardware integrity:-

1) The 20 questionable or damaged seismic restraints were reworked cne replaced to original specifications in accordance with approved procedures.

-2)- Vibration data for all-pumps were analyzed and passed the ISI surveillance requirements .

3) The defective check valve within the hydraulic operator for SI405A was repaired and satisfactorily tested.
4) No anomalies were observed on those portions of piping systems which had undergone Nondestructive Examination (NDE). Therefore, no further NDE was performed.

The following actions have been taken by the Operations Department to prevent system water hammer events:

1)- Operating Procedures OP-500-11 and 12 have been revised to assure that respective trains are declared inoperable when power cannot be

~

restored to the hydraulic pump motor.

2) The Operations Supervisors have been cautioned and instructed to f caution their personnel concerning the water hammer events to'date.
Additionally, the Potential Reportable Events-(PRE) reports concerning water hammer events to date have been added to the required reading list for operators.

i I i l l c - . . -- ---.--.-. . . _ . _ , . . - -. -

y- .

. To ,

, l

": J SCD No. 114 Page-3' CORRECTIVE ACTION (Continued)

3) Daily instructions were prepared which cautioned Operations personnel concerning. proper valve alignments and venting.of systems prior to operation to prevent water hammer events.
4) Departmental instructions (01-01-000)- addressing sound operating practices and guidelines are being developed which address such things as water hammer. Implementing these practices should' reduce the probability for future operational events.

This interim report is submitted as the initial response to SCD 114. A final report will be submitted by August 31, 1984 af ter corrective action verification.

.