MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24221A2582024-09-0606 September 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Peach Bottom Atomic Power Station, Units 2 and 3 05000277/LER-2024-003, (Pbaps), Unit 2, Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum2024-09-0505 September 2024 (Pbaps), Unit 2, Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum IR 05000277/20240022024-09-0404 September 2024 Reissued Integrated Inspection Report 05000277/2024002 and 05000278/2024002 IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) IR 05000277/20240102024-08-23023 August 2024 Fire Protection Team Inspection Report 05000277/2024010 and 05000278/2024010 ML24235A0342024-08-23023 August 2024 U.S. Nuclear Regulatory Commission’S Analysis of Constellation Energy Generation’S Decommissioning Funding Status Report ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24227A5492024-08-14014 August 2024 Integrated Inspection Report 05000277/2024002 and 05000278/2024002 ML24225A1692024-08-12012 August 2024 10 CFR 50.46 Annual Report ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24214A3232024-08-0101 August 2024 Response to Request for Additional Information - Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) ML24191A0612024-07-0606 July 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24177A1512024-06-24024 June 2024 Post Accident Monitoring Instrumentation Report ML24166A1172024-06-20020 June 2024 Regulatory Audit Summary Regarding Proposed Alternative Schedule to Complete Decommissioning Beyond 60 Years RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000277/20243012024-06-13013 June 2024 Initial Operator Licensing Examination Report 05000277/2024301 and 05000278/2024301 RS-24-058, Regarding Subsequent License Renewal Environmental Review2024-06-0505 June 2024 Regarding Subsequent License Renewal Environmental Review ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24150A2722024-05-29029 May 2024 Annual Radiological Environmental Operating Report 81, January 1, 2023 Through December 31, 2023 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24134A1792024-05-13013 May 2024 Supplemental Information in Support of Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations IR 05000277/20240012024-05-13013 May 2024 Integrated Inspection Report 05000277/2024001 and 05000278/2024001 IR 05000277/20245012024-05-0808 May 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2024501 and 05000278/2024501 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24121A1832024-04-30030 April 2024 Pre-Submittal Meeting Presentation Material Peach Bottom ECCS Compensated Level System Replacement Project ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24120A2762024-04-23023 April 2024 Independent Spent Fuel Storage Installation (ISFSI) Facility - Annual Radioactive Effluent Release Report 66 January 1, 2023 Through December 31, 2023 CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24107A2462024-04-15015 April 2024 Submittal of Changes to Technical Specifications Bases ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24102A0472024-04-11011 April 2024 Operator Licensing Examination Approval ML24099A0012024-04-0808 April 2024 (PBAPS) Units 2 and 3, Uncoordinated DC Circuits Cause Unanalyzed Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. 05000277/LER-2024-001, Submittal of LER 2024-001-00 for Peach Bottom Atomic Power Station (PBAPS) Unit 2, Automatic Reactor Scram Due to an Invalid Generator Lockout2024-03-21021 March 2024 Submittal of LER 2024-001-00 for Peach Bottom Atomic Power Station (PBAPS) Unit 2, Automatic Reactor Scram Due to an Invalid Generator Lockout IR 05000277/20244022024-03-12012 March 2024 Cybersecurity Inspection Report 05000277/2024402 and 05000278/2024402 (Cover Letter Only) ML24061A2642024-03-0101 March 2024 Revision of Two Procedures That Implement the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) Commissioners ML24060A1192024-02-29029 February 2024 Notification of Conduct of a Fire Protection Team Inspection IR 05000277/20230062024-02-28028 February 2024 Annual Assessment Letter for Peach Bottom Atomic Power Station, Units 2 and 3 (Reports 05000277/2023006 and 05000278/2023006) IR 05000171/20230012024-02-20020 February 2024 Constellation Energy Generation, LLC - Peach Bottom Atomic Power Station, Unit 1 - NRC Inspection Report No. 05000171/2023001 ML24050A0012024-02-19019 February 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) 2024-09-06
[Table view] Category:License-Monthly Operating Report
MONTHYEARML0516804652005-06-0808 June 2005 May 2005 Monthly Operating Report for Peach Bottom Atomic Power Station Units 2 and 3 ML0513803492005-05-0303 May 2005 April 2005 Monthly Operating Report for Peach Bottom Atomic Power Station, Units 2 and 3 ML0512301702005-04-0404 April 2005 March 2005 Monthly Operating Report for Peach Bottom Atomic Power Station ML0507704492005-03-0404 March 2005 February 2005 Monthly Operating Report for Peach Bottom Atomic Power Station, Units 2 and 3 ML0505301982005-02-0404 February 2005 January 2005 Monthly Operating Report for Peach Bottom Atomic Power Station, Units 2 and 3 ML0502603182005-01-0404 January 2005 December 2004 Monthly Operating Report for Peach Bottom, Units 2 & 3 ML0500402422004-12-0202 December 2004 November 2004 Monthly Operating Report for Peach Bottom Atomic Power Station, Units 2 & 3 ML0432804132004-11-0202 November 2004 October 2004 Monthly Operating Report for Peach Bottom Atomic Power Station ML0432007662004-11-0202 November 2004 October 2004 Monthly Operating Report for Peach Bottom, Units 2 and 3 ML0429402652004-10-0101 October 2004 September 2004 Monthly Operating Report for Peach Bottom Units 1 and 2 ML0426601362004-09-0101 September 2004 August 2004 Monthly Operating Report for Peach Bottom Atomic Power Station, Units 2 and 3 ML0423004512004-08-0202 August 2004 July 2004 Monthly Operating Report for Peach Bottom, Units 2 and 3 ML0420302672004-07-0202 July 2004 June 2004 Monthly Operating Report for Peach Bottom Atomic Power Station, Units 2 and 3 ML0416901232004-06-0202 June 2004 May 2004 Monthly Operating Report for Peach Bottom Atomic Power Station, Units 2 and 3 ML0414100472004-05-0404 May 2004 April 2004 Monthly Operating Report for Peach Bottom Atomic Power Station, Units 2 and 3 ML0411108522004-04-0202 April 2004 March 2004 Monthly Operating Report for Peach Bottom, Units 2 & 3 ML0407805692004-03-0303 March 2004 February 2004 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0402302692004-01-0707 January 2004 December 2003 Monthly Operating Report for Peach Bottom, Units 2 and 3 ML0335003092003-12-0505 December 2003 November 2003 Monthly Operating Report for Peach Bottom, Units 2 and 3 ML0332400612003-11-0505 November 2003 October 2003 Monthly Operating Report for Peach Bottom, Units 2 & 3 ML0329406262003-10-0202 October 2003 September 2003 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0330304242003-10-0202 October 2003 September 2003 Monthly Operating Report for Peach Bottom, Units 2 and 3 ML0326710282003-09-0404 September 2003 August 2003 Monthly Operating Report for Peach Bottom, Units 2 and 3 ML0322600192003-08-0404 August 2003 July 2003 Monthly Operating Report for Peach Bottom, Units 2 & 3 ML0319804322003-07-0101 July 2003 June 2003 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0316903882003-06-0303 June 2003 May 2003 Monthly Operating Report for Peach Bottom Units 2 and 3 ML0314005612003-05-0202 May 2003 April 2003 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0310704512003-04-11011 April 2003 March 2003 Monthly Operating Report for Peach Bottom, Units 2 & 3 ML0307707552003-03-0404 March 2003 February 2003 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0305507422003-02-0404 February 2003 January 2003 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0302205092003-01-0303 January 2003 December 2002 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0235204902002-12-0606 December 2002 November 2002 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0232303522002-11-0404 November 2002 October 2002 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0229604272002-10-0303 October 2002 September 2002 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0226003522002-09-0404 September 2002 August 2002 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0223304212002-08-0202 August 2002 July 2002 Monthly Operating Report for Peach Bottom, Units 2 and 3 ML0219804392002-07-0202 July 2002 June 2002 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0217100532002-06-0404 June 2002 May 2002 Monthly Operating Report for Peach Bottom Units 2 & 3 ML0214203862002-05-0101 May 2002 April 2002 Monthly Operating Report for Peach Bottom, Units 2 & 3 ML0212303112002-04-0303 April 2002 March 2002 Monthly Operating Report for Peach Bottom, Units 2 and 3 ML0208405282002-03-0505 March 2002 February 2002 Monthly Operating Report for Peach Bottom, Units 2 & 3 ML0205903952002-02-0404 February 2002 January 2002 Monthly Operating Report for Peach Bottom, Units 2 & 3 ML0203505002002-01-0303 January 2002 December 2001 Monthly Operating Report for Peach Bottom, Units 2 & 3 2005-06-08
[Table view] |
Text
Exe l o n M Exelon Nuclear Telephone 717.456.7014 NuElear Peach Bottom Atomic Power Station www.exeloncorp.com 1848 Lay Road Delta, PA 17314-9032 April 11, 2003 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Docket Nos. 50-277 and 50-278 Gentlemen:
Enclosed is the monthly operating report for Peach Bottom Units 2 and 3 for the month of March 2003 forwarded pursuant to Technical Specification 5.6.4 under the guidance of Regulatory Guide 10.1, Revision 4.
Sincerely, Garey L. Stathes Director, Site Engineering Peach Bottom Atomic Power Station GLS/PRR/CSL:cmg q*. C-9L Enclosures cc:
H. J. Miller, Administrator, Region L USNRC A.C. McMurtray, USNRC, Senior Resident Inspector, PBAPS ccn 03-14033
Peach Bottom Atomic Power Station Unit 2 March 1 through March 31, 2003 Narrative Summary of Operating Experiences Unit 2 began the month of March at 100% power.
At 0644, on March 3r, Unit 2 decreased power to 99.7%, due to problems with the 3D Monicore and PMS computers. Following resets of these computers, the Unit returned to 100% power by 1818 on March 3d.
At 2300 on March 21',, Unit 2 reduced power to 92.7% for planned main turbine stop valve testing.
The Unit returned to 100% power by 0616 on March 22nd.
Unit 2 ended the month of March at 100% power.
Peach Bottom Atomic Power Station Unit 3 March 1 through March 31, 2003 Narrative Summary of Operating Experiences Unit 3 began the month of March at 100% power.
At 2350 on March 29 h,Unit 3 reduced power to 85%, for a planned rod pattern adjustment. The Unit returned to 100% power by 0250 on March 30th.
Unit 3 ended the month of March at 100% power.
Attachment to Monthly Operating Report for March 2003 Page 1 UNIT 2 REFUELING INFORMATION
- 1. Name of facility:
Peach Bottom Unit 2
- 2. Scheduled date for next refueling shutdown:
Reload 15 is scheduled for September 22, 2004.
- 3. Scheduled date for restart following refueling:
Restart following refueling forecast for October 7, 2004.
- 4. Will refueling or resumption of operation there after require a technical specification change or other license amendment?
Yes If answer is yes, what, in general, will these be?
- a. Potential Cycle 16 Safety Limit MCPR Change.
- 5. Scheduled date(s) for submitting proposed licensing action and supporting information:
Nothing to report for this period.
- 6. Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:
Nothing to report this period.
Docket No. 50-277 Attachment to Monthly Operating Report for March 2003 Page 2 UNIT 2 REFUELING INFORMATION (Continued)
- 7. The number of fuel assemblies (a) in the core, (b) in the spent fuel storage pool and (c) dry storage.
(a) Core - 764 Fuel Assemblies (b) Fuel Pool - 2908 Fuel Assemblies, 58 Fuel Rods (c) Interim Spent Fuel Storage Installation - 680 fuel assemblies
- 8. The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:
The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.
- 9. The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:
Based on projected dry cask storage schedules and reload batch sizes, a full core discharge will remain available throughout plant life.
Docket No. 50-278 Attachment to Monthly Operating Report for March 2003 Page 1 UNIT 3 REFUELING INFORMATION
- 1. Name of facility:
Peach Bottom Unit 3
- 2. Scheduled date for next refueling shutdown:
Reload 14 is scheduled for September 21, 2003.
- 3. Scheduled date for restart following refueling Restart following refueling forecast for October 9, 2003.
- 4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
Yes If answer is yes, what, in general, will these be?
a.) Potential Cycle 15 Safety Limit MCPR Change.
- 5. Scheduled date(s) for submitting proposed licensing action and supporting information.
a.) Submittal anticipated July 2003.
- 6. Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:
(a) The 3R14 reload will consist of approximately 288 GE-14 bundles. This will be the second reload of GE-14 fuel.
- 7. The number of fuel assemblies (a) in the core, (b) in the spent fuel storage pool and (c) dry storage.
(a) Core - 764 Fuel Assemblies (b) Fuel Pool - 2997 Fuel Assemblies, 6 Fuel Rods (c) Interim Spent Fuel Storage Installation - 340 fuel assemblies
- 8. The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:
The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.
Attachment to Monthly Operating Report for March 2003 Page 2 UNIT 3 REFUELING INFORMATION (Continued)
- 9. The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:
Based on projected dry cask storage schedules and reload batch sizes, a full core discharge will remain available throughout plant life.
OPERATING DATA REPORT DOCKET NO. 50 - 277 DATE APRIL 1, 2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 OPERATING STATUS
- 1. UNIT NAME: PEACH BOTTOM UNIT 2
- 2. REPORTING PERIOD: MARCH,2003
- 3. DESIGN ELECTRICAL RATING (NET MWE): 1143
- 4. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 1182
- 5. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 1116 THIS MONTH YR-TO-DATE CUMULATIVE
- 6. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 2,160.0 183,425.5
- 7. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 8. HOURS GENERATOR ON-LINE 744.0 2,160.0 179,039.9
- 9. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 10. NET ELECTRICAL ENERGY GENERATED (MWH) 854,160 2,417,523 176,303,289
OPERATING DATA REPORT (CONTINUED)
DOCKET NO. 50 - 277 DATE APRIL 1, 2003 THIS MONTH YR-TO-DATE CUMULATIVE
- 11. UNIT SERVICE FACTOR 100.0 % 100.0 % 71.1 %
- 12. UNIT AVAILABILITY FACTOR 100.0 % 100.0 % 71.1 %
- 13. UNIT CAPACITY FACTOR (USING MDC NET) 102.9 % 100.3 % 64.9 %
- 14. UNIT CAPACITY FACTOR (USING DER NET) 100.4 % 97.9 % 63.8 %
- 15. UNIT FORCED OUTAGE RATE .0% .0% 9.6 %
- 16. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):
(717) 456-4248
- 17. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: (717) 456-4248
- 18. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS): FORECAST ACHIEVED INITIAL CRITICALITY 09/16/73 INITIAL ELECTRICITY 02/18/74 COMMERCIAL OPERATION 07/05/74 PAGE 2 OF 2
UNIT SHUTDOWNS DOCKET NO. 50 - 277 UNIT NAME PEACH BOTTOM UNIT 2 DATE APRIL 1, 2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION REPORT MONTH MARCH, 2003 TELEPHONE (717) 458-3245 METHOD OF CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN ACTION TO NO. DATE (1) (HOURS) (2) REACTOR (3) PREVENT RECURRENCE TOTAL HOURS (1) (2) (3)
F-FORCED REASON METHOD S - SCHEDULED A - EQUIPMENT FAILURE (EXPLAIN) 1 - MANUAL B - MAINTENANCE OR TEST 2- MANUAL SCRAM C - REFUELING 3 - AUTOMATIC SCRAM D - REGULATORY RESTRICTION 4 - OTHER (EXPLAIN)
E - OPERATOR TRAINING + LICENSE EXAMINATION F - ADMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)
H - OTHER (EXPLAIN)
OPERATING DATA REPORT DOCKET NO. 50 - 278 DATE APRIL 1. 2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 OPERATING STATUS
- 1. UNIT NAME: PEACH BOTTOM UNIT 3
- 2. REPORTING PERIOD: MARCH, 2003
- 3. DESIGN ELECTRICAL RATING (NET MWE): 1119
- 4. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 1159
- 5. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 1093 THIS MONTH YR-TO-DATE CUMULATIVE
- 6. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 2,160.0 182,299.5
- 7. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 8. HOURS GENERATOR ON-LINE 744.0 2,160.0 178,393.8
- 9. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 10. NET ELECTRICAL ENERGY GENERATED (MWH) 831,865 2,414,084 174,530,050
OPERATING DATA REPORT (CONTINUED)
DOCKET NO. 50 - 278 DATE APRIL 1, 2003 THIS MONTH YR-TO-DATE CUMULATIVE
- 11. UNIT SERVICE FACTOR 100.0 % 100.0 % 72.0 %
- 12. UNIT AVAILABILITY FACTOR 100.0 % 100.0 % 72.0 %
- 13. UNIT CAPACITY FACTOR (USING MDC NET) 102.3 % 102.3 % 66.7%
- 14. UNIT CAPACITY FACTOR (USING DER NET) 99.9 % 99.9 % 64.9 %
- 15. UNIT FORCED OUTAGE RATE .0 % .0% 8.2%
- 16. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):
(717) 456-4248
- 17. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: (717)456 -4248
- 18. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS): FORECASTr ACHIEVED INITIAL CRITICALITY 08/07/74 INITIAL ELECTRICITY 09/01/74 COMMERCIAL OPERATION 12/23/74 PAGE 2 OF 2
UNIT SHUTDOWNS DOCKET NO. 50 - 278 UNIT NAME PEACH BOTTOM UNIT 3 DATE APRIL 1, 2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION REPORT MONTH MARCH, 2003 TELEPHONE (717) 458-3245 METHOD OF CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN ACTION TO NO. DATE (1) (HOURS) (2) REACTOR (3) PREVENT RECURRENCE TOTAL HOURS (1) (2) (3)
F-FORCED REASON METHOD S - SCHEDULED A - EQUIPMENT FAILURE (EXPLAIN) I - MANUAL B - MAINTENANCE OR TEST 2- MANUAL SCRAM C - REFUELING 3 - AUTOMATIC SCRAM D - REGULATORY RESTRICTION 4 - OTHER (EXPLAIN)
E - OPERATOR TRAINING + LICENSE EXAMINATION F - ADMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)
H - OTHER (EXPLAIN)