December 2002 Monthly Operating Report for Peach Bottom Units 2 & 3
ML030220509
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 01/03/2003
From: Eilola E
Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML030220509 (13)


Text

Exelon.

Exelon Nuclear Peach Bottom Atomic Power Station 1848 Lay Road Delta, PA 17314-9032 Telephone 717 456 7014 wwwexeloncorp corn Nuclear January 3, 2003 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Docket Nos. 50-277 and 50-278 Gentlemen:

Enclosed is the monthly operating report for Peach Bottom Units 2 and 3 for the month of December 2002 forwarded pursuant to Technical Specification 5.6.4 under the guidance of Regulatory Guide 10.1, Revision 4.

Sincerely, Edwin J. Eilola Jr.

Director, Site Engineering Peach Bottom Atomic Power Station EJE ICSL:cmg Enclosures cc:

H. J. Miller, Administrator, Region I, USNRC A.C. McMurtray, USNRC, Senior Resident Inspector, PBAPS ccn 03-14004

"ý-

-11

" Lý-

-ý ý

Peach Bottom Atomic Power Station Unit 2 December 1 through December 31, 2002 Narrative Summary of Operating Experiences Unit 2 began the month of December at 100% power.

At 1047, on December 17th, Unit 2 reduced power to 91%, for planned TIP run, to support LPRM gain calibration activities. The Unit returned to 100% power by 1243 on December 17th.

At 2303 on December 17 th, Unit 2 reduced power to 16% for planned activities to repair leaks in the Caldon LEFM flow measurement system. Following completion of the repairs, and a follow-up rod pattern adjustment, the Unit returned to 100% power by 1510 on December 21 st.

At 2035 on December 2 1 st, Unit 2 automatically scrammed due to a malfunctioning EHC control system card. Following troubleshooting and repairs, the Unit reached critical operation at 0030 on December 24 h, and was synchronized with the grid at 1531 on December 2 4th. The Unit reached th 100% power by 0604 on December 25 At 1152 on December 2 5 th, Unit 2 reduced power to 90% for a follow-up rod pattern adjustment.

th The Unit returned to 100% power by 1252 on December 25 At 2300 on December 2 9th, Unit 2 reduced power to 85% for a planned rod pattern adjustment. The Unit returned to 100% power by 0211 on December 3 0th.

At 1104 on December 30 th, Unit 2 reduced power to 99.6%, to end oscillations of the #3 turbine control valve. During this same period, investigations commenced concerning uncertainties in the Caldon LEFM flow measurement system. At 2128 on December 3 1st, the Caldon LEFM system was declared inoperable and was removed from service, pending further investigations. With the Caldon LEFM system out-of-service, the Unit was de-rated to 98.4% power, which was its previous rating of 3458 MWth.

Unit 2 ended the month of December at 98.4% power (3458 MWth).

Peach Bottom Atomic Power Station Unit 3 December 1 through December 31, 2002 Narrative Summary of Operating Experiences Unit 3 began the month of December at 100% power.

Unit 3 remained at 100% power for the entire month of December.

Unit 3 ended the month of December at 100% power.

Attachment to Monthly Operating Report for December 2002 Page 1 UNIT 2 REFUELING INFORMATION

1.

Name of facility:

Peach Bottom Unit 2

2.

Scheduled date for next refueling shutdown:

Reload 15 is scheduled for September 22, 2004.

3.

Scheduled date for restart following refueling:

Restart following refueling forecast for October 7, 2004.

4.

Will refueling or resumption of operation therefore require a technical specification change or other license amendment?

Yes If answer is yes, what, in general, will these be?

a. Cycle 16 Safety Limit MCPR Change, to be submitted in mid 2003.
5.

Scheduled date(s) for submitting proposed licensing action and supporting information:

Nothing to report for this period.

6.

Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:

Nothing to report this period.

Docket No. 50-277 Attachment to Monthly Operating Report for December 2002 Page 2 UNIT 2 REFUELING INFORMATION (Continued)

7.

The number of fuel assemblies (a) in the core, (b) in the spent fuel storage pool and (c) dry storage.

(a) Core - 764 Fuel Assemblies (b) Fuel Pool - 2908 Fuel Assemblies, 58 Fuel Rods (c) Interim Spent Fuel Storage Installation - 608 fuel assemblies

8.

The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:

The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.

9.

The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:

Based on projected dry cask storage schedules and reload batch sizes, a full core discharge will remain available throughout plant life.

Docket No. 50-278 Attachment to Monthly Operating Report for December 2002 Page 1 UNIT 3 REFUELING INFORMATION

1.

Name of facility:

Peach Bottom Unit 3

2.

Scheduled date for next refueling shutdown:

Reload 14 is scheduled for September 22, 2003.

3.

Scheduled date for restart following refueling Restart following refueling forecast for October 7, 2003.

4.

Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

Yes If answer is yes, what, in general, will these be?

a.) Potential Cycle 15 Safety Limit MCPR Change.

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

a.) Submittal anticipated July 2003.

6.

Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:

(a) The 3R14 reload will consist of approximately 288 GE-14 bundles. This will be the second reload of GE-14 fuel.

7.

The number of fuel assemblies (a) in the core, (b) in the spent fuel storage pool and (c) dry storage.

(a) Core - 764 Fuel Assemblies (b) Fuel Pool - 2997 Fuel Assemblies, 6 Fuel Rods (c) Interim Spent Fuel Storage Installation - 340 fuel assemblies

8.

The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:

The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.

Attachment to Monthly Operating Report for December 2002 Page 2 UNIT 3 REFUELING INFORMATION (Continued)

9.

The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:

Based on projected dry cask storage schedules and reload batch sizes, a full core discharge will remain available throughout plant life.

OPERATING DATA REPORT DOCKET NO.

50-277 DATE JANUARY 6,2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 OPERATING STATUS

1. UNIT NAME:

PEACH BOTTOM UNIT 2

2. REPORTING PERIOD:

DECEMBER. 2002

3. DESIGN ELECTRICAL RATING (NET MWE):

1119

4. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE):

1159

5. MAXIMUM DEPENDABLE CAPACITY (NET MWE):

1093 THIS MONTH YR-TO-DATE CUMULATIVE

6. NUMBER OF HOURS REACTOR WAS CRITICAL 692.1 8,181.9 181,265.5
7. REACTOR RESERVE SHUTDOWN HOURS 00 00 0.0
8. HOURS GENERATOR ON-LINE 677.1 8,149.1 176,879 9
9. UNIT RESERVE SHUTDOWN HOURS 00 0.0 0.0
10. NET ELECTRICAL ENERGY GENERATED (MWH) 704,846 8,838,933 173,885,766

OPERATING DATA REPORT (CONTINUED)

DOCKET NO.

DATE 50-277 JANUARY 6, 2003 THIS MONTH

11. UNIT SERVICE FACTOR 91.0%
12. UNIT AVAILABILITY FACTOR 91.0%

13 UNIT CAPACITY FACTOR (USING MDC NET) 86.7 %

14. UNIT CAPACITY FACTOR (USING DER NET) 84.7%
15. UNIT FORCED OUTAGE RATE 90%

16 SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):

(717) 4564248

17. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

(717) 456-4248

18. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS):

FORECAST INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION YR-TO-DATE 93.0%

93.0 %

92.3 %

90.2 %

.8%

CUMULATIVE 708%

70.8 %

65.2 %

64.1 %

97%

ACHIEVED 09/16/73 02/18f74 07/05/74 PAGE 2 OF 2

UNIT SHUTDOWNS REPORT MONTH DOCKET NO. 50-277 UNIT NAME PEACH BOTTOM UNIT 2 DATE JANUARY 6,2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 DECEMBER, 2002 METHOD OF CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN ACTION TO NO.

DATE (1)

(HOURS)

(2)

REACTOR (3)

PREVENT RECURRENCE 2

021221 F

66.9 REACTOR POWER WAS REDUCED TO 0% DUE TO FAILURE OF EHC SYSTEM CONTROL CARD. FAILURE CAUSED CONTROL VALVE TO OPEN AND UNIT SCRAMMED ON LOW STEAM PRESSURE.

TOTAL HOURS (1)

REASON A-EQUIPMENT FAILURE (EXPLAIN)

B - MAINTENANCE OR TEST C - REFUELING D - REGULATORY RESTRICTION E - OPERATOR TRAINING + LICENSE EXAMINATION F -ADMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)

H - OTHER (EXPLAIN)

METHOD 1-MANUAL 2-MANUAL SCRAM 3 - AUTOMATIC SCRAM 4 - OTHER (EXPLAIN) 66.9 F-FORCED S - SCHEDULED (2)

(3)

A 3

OPERATING DATA REPORT DOCKET NO.

50-278 DATE JANUARY 6,2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 OPERATING STATUS

1. UNIT NAME:

PEACH BOTTOM UNIT 3

2. REPORTING PERIOD:

DECEMBE.R,2002

3. DESIGN ELECTRICAL RATING (NET MWE):

1119

4. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE):

1159

5. MAXIMUM DEPENDABLE CAPACITY (NET MWE): ------------------------------------------------------------ 1093 THIS MONTH YR-TO-DATE CUMULATIVE
6. NUMBER OF HOURS REACTOR WAS CRITICAL 744 0 8,760.0 180,139.5
7. REACTOR RESERVE SHUTDOWN HOURS 00 0.0 0.0
8. HOURS GENERATOR ON-LINE 744.0 8,740.4 176,233.8
9. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 00
10. NET ELECTRICAL ENERGY GENERATED (MWH) 834,301 9,647,383 172,115,965

OPERATING DATA REPORT (CONTINUED)

DOCKET NO.

DATE 50-278 JANUARY 6,2003 THIS MONTH

11. UNIT SERVICE FACTOR 100 0%
12. UNIT AVAILABILITY FACTOR 100.0%
13. UNIT CAPACITY FACTOR (USING MDC NET) 1026 %
14. UNIT CAPACITY FACTOR (USING DER NET) 100.2%
15. UNIT FORCED OUTAGE RATE

.0 %

16. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):

(717) 456-4248

17. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

(717) 456-4248

18. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS):

FORECAST INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION YR-TO-DATE 99.8%

99.8 %

100.8%

98.4 %

.2%

CUMULATIVE 71.7%

71.7%

66.3 %

64.6 %

8.3 %

ACHIEVED 08/07/74 09/01[74 12/23/74 PAGE 2 OF 2

UNIT SHUTDOWNS REPORT MONTH DOCKET NO. 50 - 278 UNIT NAME PEACH BOTTOM UNIT 3 DATE JANUARY 6,2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 DECEMBER, 2002 METHOD OF CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN ACTION TO NO.

DATE (1)

(HOURS)

(2)

REACTOR (3)

PREVENT RECURRENCE TOTAL HOURS (1)

F-FORCED S - SCHEDULED (2)

(3)

REASON A - EQUIPMENT FAILURE (EXPLAIN)

B - MAINTENANCE OR TEST C - REFUELING D - REGULATORY RESTRICTION E - OPERATOR TRAINING + LICENSE EXAMINATION F - ADMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)

H - OTHER (EXPLAIN)

METHOD 1-MANUAL 2-MANUAL SCRAM 3 - AUTOMATIC SCRAM 4 - OTHER (EXPLAIN)