ML021710053
| ML021710053 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 06/04/2002 |
| From: | Davison P Exelon Nuclear |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| Download: ML021710053 (13) | |
Text
Exelkn.
Nuclear Exelon Nuclear Telephone 717.456.7014 Peach Bottom Atomic Power Station www.exeloncorp.com 1848 Lay Road Delta, PA 17314-9032 June 4, 2002 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Docket Nos. 50-277 and 50-278 Gentlemen:
Enclosed is the monthly operating report for Peach Bottom Units 2 and 3 for the month of May 2002 forwarded pursuant to Technical Specification 5.6.4 under the guidance of Regulatory Guide 10.1, Revision 4.
Sincerely, j6~ ý Th, A,
Paul J. Davison Director, Site Engineering Peach Bottom Atomic Power Station PJD/PRR/CSL:cmg Enclosures cc:
H. J. Miller, Administrator, Region I, USNRC A.C. McMurtray, USNRC, Senior Resident Inspector, PBAPS ccn 02-14047
ýYlý
Peach Bottom Atomic Power Station Unit 2 May 1 through May 31, 2002 Narrative Summary of Operating Experiences Unit 2 began the month of May at 100% power.
At 2205 on May 10 th, Unit 2 reduced power to 50% for a planned rod sequence exchange and scram time testing. The Unit returned to 100% power by 1628 on May 1 1 th.
At 2302 on May 12th Unit 2 reduced power to 85% for a planned follow-up rod pattern adjustment.
The Unit returned to 100% power by 0155 on May 13th.
At 2303 on May 3 1S, Unit 2 reduced power to 85% for a planned rod pattern adjustment. The load drop continued into June 1st, and the Unit returned to 100% power by 0440 on June 1S.
Unit 2 ended the month of May at 85% power.
Peach Bottom Atomic Power Station Unit 3 May 1 through May 31, 2002 Narrative Summary of Operating Experiences Unit 3 began the month of May at 100% power.
At 2203 on May 17 th, Unit 3 reduced power to 51% for a planned rod sequence exchange and scram time testing. The Unit returned to 100% power by 1700 on May 18th.
At 2300 on May 1 9 th, Unit 3 reduced power to 90% for a planned follow-up rod pattern adjustment.
The Unit returned to 100% power by 0039 on May 20th.
Unit 3 ended the month of May at 100% power.
Attachment to Monthly Operating Report for May 2002 Page 1 UNIT 2 REFUELING INFORMATION
- 1.
Name of facility:
Peach Bottom Unit 2
- 2.
Scheduled date for next refueling shutdown:
Reload 14 is scheduled for September 10, 2002.
- 3.
Scheduled date for restart following refueling:
Restart following refueling forecast for September 30, 2002.
- 4.
Will refueling or resumption of operation therefore require a technical specification change or other license amendment?
Yes If answer is yes, what, in general, will these be?
- a. Potential Cycle 15 Safety Limit MCPR Change.
- 5.
Scheduled date(s) for submitting proposed licensing action and supporting information:
- a. Submittal anticipated July, 2002.
- 6.
Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:
- a. The 2R14 reload will consist of approximately 284 GE-14 bundles. This will be the second reload of GE-14 fuel.
Docket No. 50-277 Attachment to Monthly Operating Report for May 2002 Page 2 UNIT 2 REFUELING INFORMATION (Continued)
- 7.
The number of fuel assemblies (a) in the core, (b) in the spent fuel storage pool and (c) dry storage.
(a) Core - 764 Fuel Assemblies (b) Fuel Pool - 2896 Fuel Assemblies, 58 Fuel Rods (c) Interim Spent Fuel Storage Installation - 408 fuel assemblies
- 8.
The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:
The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.
- 9.
The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:
Based on projected dry cask storage schedules and reload batch sizes, a full core discharge will remain available throughout plant life.
Docket No. 50-278 Attachment to Monthly Operating Report for May 2002 Page 1 UNIT 3 REFUELING INFORMATION I.
Name of facility:
Peach Bottom Unit 3
- 2.
Scheduled date for next refueling shutdown:
Reload 14 is scheduled for September 22, 2003.
- 3.
Scheduled date for restart following refueling Restart following refueling forecast for October 7, 2003.
- 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
Yes If answer is yes, what, in general, will these be?
a.) Potential Cycle 15 Safety Limit MCPR Change.
- 5.
Scheduled date(s) for submitting proposed licensing action and supporting information.
a.) Submittal anticipated July 2003.
- 6.
Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:
(a) The 3R14 reload will consist of approximately 284 GE-14 bundles. This will be the second reload of GE-14 fuel.
- 7.
The number of fuel assemblies (a) in the core, (b) in the spent fuel storage pool and (c) dry storage.
(a) Core - 764 Fuel Assemblies (b) Fuel Pool - 2997 Fuel Assemblies, 6 Fuel Rods (c) Interim Spent Fuel Storage Installation-340 fuel assemblies
- 8.
The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:
The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.
Attachment to Monthly Operating Report for May 2002 Page 2 UNIT 3 REFUELING INFORMATION (Continued)
- 9.
The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:
Based on projected dry cask storage schedules and reload batch sizes, a full core discharge will remain available throughout plant life.
OPERATING DATA REPORT DOCKET NO.
50-277 DATE JUNE 4, 2002 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 OPERATING STATUS
- 1. UNIT NAME:
- 2. REPORTING PERIOD:
- 3. DESIGN ELECTRICAL RATING (NET MWE):
- 4. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE):
- 5. MAXIMUM DEPENDABLE CAPACITY (NET MWE):
THIS MONTH
- 6. NUMBER OF HOURS REACTOR WAS CRITICAL
- 7. REACTOR RESERVE SHUTDOWN HOURS
- 8. HOURS GENERATOR ON-LINE
- 9. UNIT RESERVE SHUTDOWN HOURS
- 10. NET ELECTRICAL ENERGY GENERATED (MWH)
YR-TO-DATE 744.0 0.0 744.0 0.0 824,182 PEACH BOTTOM UNIT 2 MAY, 2002 1119 1159 1093 CUMULATIVE 3,623.0 0.0 3,623.0 0.0 4,043,563 176,706.6 0.0 172,353.8 0.0 169,090,396
OPERATING DATA REPORT (CONTINUED)
THIS MONTH UNIT SERVICE FACTOR 100.0%
UNIT AVAILABILITY FACTOR 100.0%
UNIT CAPACITY FACTOR (USING MDC NET) 101.4%
UNIT CAPACITY FACTOR (USING DER NET) 99.0%
UNIT FORCED OUTAGE RATE
.0 %
SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):
(717) 456-4248 IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
(717) 456-4248 UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS):
FORECAST INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION YR-TO-DATE 100.0%
100.0%
102.1 %
99.7 %
.0%
CUMULATIVE 70.5 %
70.5 %
64.8 %
63.7 %
9.9%
- 11.
- 12.
- 13.
- 14.
- 15.
- 16.
- 17.
18.
PAGE 2 OF 2 DOCKET NO.
DATE 50-277 JUNE 4, 2002 ACHIEVED 09/16/73 02/18/74 07/05/74
UNIT SHUTDOWNS REPORT MONTH DOCKET NO. 50-277 UNIT NAME PEACH BOTTOM UNIT 2 DATE JUNE 4, 2002 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 MAY, 2002 METHOD OF CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN ACTION TO NO.
DATE (1)
(HOURS)
(2)
REACTOR (3)
PREVENT RECURRENCE TOTAL HOURS (1)
F - FORCED S - SCHEDULED (2)
(3)
REASON A - EQUIPMENT FAILURE (EXPLAIN)
B - MAINTENANCE OR TEST C - REFUELING D - REGULATORY RESTRICTION E - OPERATOR TRAINING + LICENSE EXAMINATION F - ADMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)
H - OTHER (EXPLAIN)
METHOD 1-MANUAL 2-MANUAL SCRAM 3 -AUTOMATIC SCRAM 4 - OTHER (EXPLAIN)
OPERATING DATA REPORT DOCKET NO.
50-278 DATE JUNE 4, 2002 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 OPERATING STATUS
- 1. UNIT NAME:
- 2. REPORTING PERIOD:
- 3. DESIGN ELECTRICAL RATING (NET MWE):
- 4. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE):
- 5. MAXIMUM DEPENDABLE CAPACITY (NET MWE):
THIS MONTH
- 6. NUMBER OF HOURS REACTOR WAS CRITICAL
- 7. REACTOR RESERVE SHUTDOWN HOURS
- 8. HOURS GENERATOR ON-LINE
- 9. UNIT RESERVE SHUTDOWN HOURS
- 10. NET ELECTRICAL ENERGY GENERATED (MWH)
PEACH BOTTOM UNIT 3 MAY, 2002 1119 1159 1093 YR-TO-DATE 744.0 0.0 744.0 0.0 826,718 CUMULATIVE 3,623.0 0.0 3,603.4 175,002.5 0.0 171,096.8 0.0 166,429,221 0.0 3,960,639
OPERATING DATA REPORT (CONTINUED)
THIS MONTH
- 11. UNIT SERVICE FACTOR 100.0%
- 12. UNIT AVAILABILITY FACTOR 100.0%
- 13. UNIT CAPACITY FACTOR (USING MDC NET) 101.7%
- 14. UNIT CAPACITY FACTOR (USING DER NET) 99.3%
- 15. UNIT FORCED OUTAGE RATE
.0%
- 16. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):
(717) 456-4248
- 17. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
(717) 456-4248
- 18. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS):
FORECAST INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION YR-TO-DATE 99.5 %
99.5 %
100.0%
97.7 %
.5%
CUMULATIVE 71.1 %
71.1 %
65.6 %
63.9 %
8.6 %
ACHIEVED 08/07/74 09/01/74 12/23/74 PAGE 2 OF 2 DOCKET NO.
DATE 50 - 278 JUNE 4, 2002
UNIT SHUTDOWNS REPORT MONTH DOCKET NO. 50-278 UNIT NAME PEACH BOTTOM UNIT 3 DATE JUNE 4, 2002 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 MAY, 2002 METHOD OF CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN ACTION TO NO.
DATE (1)
(HOURS)
(2)
REACTOR (3)
PREVENT RECURRENCE TOTAL HOURS (1)
F-FORCED S - SCHEDULED (2)
(3)
REASON A - EQUIPMENT FAILURE (EXPLAIN)
B - MAINTENANCE OR TEST C - REFUELING D - REGULATORY RESTRICTION E - OPERATOR TRAINING + LICENSE EXAMINATION F - ADMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)
H - OTHER (EXPLAIN)
METHOD 1-MANUAL 2 - MANUAL SCRAM 3 - AUTOMATIC SCRAM 4 - OTHER (EXPLAIN)