ML050770449
| ML050770449 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 03/04/2005 |
| From: | Grimes J Exelon Nuclear |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| Download: ML050770449 (7) | |
Text
Exeloni.
Exelon Nuclear Telephone 717.456.7014 Peach Bottom Atomic Power Station www.exeloncorp.com 1848 Lay Road Delta, PA 17314-9032 Nuclear March 4, 2005 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Docket Nos. 50-277 and 50-278
Subject:
Monthly Operating Report for February 2005 In accordance with Technical Specifications, Section 5.6.4, "Monthly Operating Reports,"
we are submitting this Monthly Operating Report for Peach Bottom Atomic Power Station, Units 2 and 3.
Should you have any questions concerning this letter, please contact Mr. Bradley Deihl at (717) 456-3623.
Respectfully, Joseph P. Grimes Plant Manager Peach Bottom Atomic Power Station JPG/PJD/NPA/BRD:cmg Enclosures cc:
S. Collins, Administrator, Region I, USNRC G. F. Wunder, Project Manager, USNRC U. S. NRC Senior Resident, PBAPS C C "
0 ! -I qbo35
I. INTRODUCTION Peach Bottom Atomic Power Station is composed of two Boiling Water Reactors and Steam Turbine/Generators located in Delta, Pennsylvania. Unit Two and Unit Three both have a Maximum Dependable Capacity of 1112 MWe Net. The Station is jointly owned by Exelon Nuclear and Public Service Electric and Gas. The Nuclear Steam Supply Systems are General Electric Company Boiling Water Reactors. The Architect/Engineer and Primary Construction Contractor was Bechtel Corporation. The Susquehanna River is the condenser cooling water source. The plant is subject to license numbers DPR-44 and DPR-56, issued October 25, 1973, and July 2, 1974, for Unit Two and Unit Three respectively, pursuant to Docket Numbers 50-277 and 50-278. The dates of initial Reactor criticality for Units Two and Three were September 16, 1973, and August 7, 1974, respectively. Commercial generation of power began on February 18, 1974, for Unit Two, and September 1, 1974, for Unit Three.
- i.
A II.
SUMMARY
OF OPERATING EXPERIENCE A. Unit TWO Unit 2 began the month of February at 100.0% of maximum allowable power (3514 MWth).
At 21:05 on February 1't, Unit 2 commenced power reduction for a planned normal plant shutdown to replace SRV 071D. The reactor was manually scrammed at 05:17 on February 2nd. The reactor was critical at 08:23 on February 4h and the main generator synchronized to the grid at 19:56 on February 4th. The Unit returned to full power at 21:30 on February 6th.
At 23:24 on February 7h, Unit 2 reduced power to 59.2% for planned rod pattern adjustment and turbine stop valve testing. Following completion of the tests, the Unit returned to full power by 10:17 on February 9 th.
At 20:33 on February 13'h, Unit 2 reduced power to 71% for planned final rod pattern adjustment. The Unit returned to full power by 17:00 on February 14%h.
Unit 2 ended the month of February at 100% of maximum allowable power (3514 MWth).
B. Unit THREE Unit 3 began the month of February at 100% of maximum allowable power (3514 MWth).
At 16:32 on February 10h, Unit 3 reduced load to repair the A Recirc Pump EOC RPT BKR. The minimum load during the load reduction was 32% on February I Ph Following completion of the EOC RPT BKR repair the Unit returned to full power by 07:24 on February 12th.
At 02:30 on February 13'h, Unit 3 reduced load to 69% for a rod pattern adjustment following the A Recirc Pump EOC RPT BKR replacement. Following completion of the rod pattern adjustment the Unit returned to full power by 08:23 on February 13th.
At 09:34 on February 17'h, Unit 3 reduced load to 98.7% due to loss of Core Thermal Power Calculation. Following restoration of the Core Thermal Power Calculation the Unit returned to full power by 14:42 on February 17'h.
Unit 3 ended the month of February at 100% of maximum allowable power (3514 MWth).
III. OPERATING DATA STATISTICS A. Peach Bottom Unit TWO Operating Data Report for February 2005 DOCKET NO.:
DATE:
COMPLETED BY:
TELEPHONE:
50-277 March 3, 2005 Brad Deihl (717) 456-3623 OPERATING STATUS REPORTING PERIOD:
GROSS HOURS IN REPORTING PERIOD:
CURRENTLY AUTHORIZED POWER LEVEL (MWth):
DESIGN ELECTRICAL RATING (MWe-Net):
MAX. DEPENDABLE CAPACITY (MWe-Net):
February 2005 672 3514 1138 1112 1.
2.
UNIT 2 OPERATING STATUS 3.
4.
5.
6.
PARAMETER NUMBER OF HOURS THE REACTOR WAS CRITICAL HOURS GENERATOR ON-LINE UNIT RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED THIS MONTH 620.9 609.0 0
663,497.6 YTD 1,364.9 1,353.0 0
1,501,450.8 CUMULATIVE 199,277.3 194,736.9 0
193,539,053.2
III. OPERATING DATA STATISTICS B. Peach Bottom Unit THREE Operating Data Report for February 2005 DOCKET NO.:
DATE:
COMPLETED BY:
TELEPHONE:
50-278 March 3, 2005 Brad Deihl (717) 456-3623 OPERATING STATUS REPORTING PERIOD:
GROSS HOURS IN REPORTING PERIOD:
CURRENTLY AUTHORIZED POWER LEVEL (MWth):
DESIGN ELECTRICAL RATING (MWe-Net):
MAX. DEPENDABLE CAPACITY (MWe-Net):
February 2005 672 3514 1138 1112 1.
2.
UNIT 3 OPERATING STATUS 3.
4.
5.
6.
PARAMETER NUMBER OF HOURS THE REACTOR WAS CRITICAL HOURS GENERATOR ON-LINE UNIT RESERVE SHUTDOWN HOURS NET ELECTRICAL ENERGY GENERATED THIS MONTH 672.0 672.0 0
740,796.6 YTD 1,416.0 1,416.0 0
1,583,233.8 CUMULATIVE 198,470.4 194,525.0 0
192,626,095.2
IV. OPERATING DATA STATISTICS A. Unit TWO Shutdowns for February 2005 No. for Year 1
Type Date (1!
2/2/2005 S
Duration (Hours) 63.0 Reason (2)
B Method of Shutting Down (3) 2 Corrective Actions/Comments Planned normal shutdown for maintenance to replace SRV 71D ("D" safety relief valve).
B. Unit THREE Shutdowns for February 2005 No. for Year Type Date (1)
Duration (Hours)
Reason (2!
Method of Shutting Down (3)
Corrective Actions/Comments No Unit THREE shutdowns for Febntary 2005 Legend (1) Type:
F - Forced S - Scheduled (2) Reason:
A. - Equipment Failure (Explain)
B. - Maintenance or Test C. - Refueling D. - Regulatory Restriction E. - Operator Training/License Examination F. - Administrative G. - Operational Error (Explain)
H. - Other (Explain)
(3) Method of Shutting Down:
- 1. - Manual
- 2. - Manual Trip/Scram
- 3. - Automatic Trip/Scram
- 4. - Continuation
- 5. - Other (Explain)