ML20054G354

From kanterella
Revision as of 11:59, 14 March 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Second Interim Deficiency Rept Re Cooper-Bessemer Emergency Diesel Generators Agastat Relay defect.Seventy-four Control Relays for Generator B Will Be Removed & Returned to Vendor for Repair/Replacement.Final Rept Expected by 820813
ML20054G354
Person / Time
Site: Waterford Entergy icon.png
Issue date: 06/14/1982
From: Mclendon G
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, W3K-82-0341, W3K-82-341, NUDOCS 8206210475
Download: ML20054G354 (2)


Text

.

O l.OUISIANA f ,42 ouAnoNoE S1nn1 POWER S LIGHT / P O DOX 6008

  • NEW OnLEANS. LOUISIANA 70174 * (504) 366 2345 U$\ISlN) June 14, 1982 G. D. McLENDON Senior Vice President W3K-82-0341 Q-3-A35.07.46 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012

SUBJECT:

Waterford SES Unit No. 3 Docket No. 50-382 Interim Report of Significant Conscruction Deficiency No. 46

" Cooper-Bessemer Emergency Diesel Generators Agastat Relay Defect" Second Interim Report Peference: 1) Interim Report W3K82-0144 from LP&L to NRC dated March 9, 1982

2) Telecon - R. Bennett (LP&L) to L. Martin (NRC) on 6/11/82

Dear Mr. Collins:

We have now receiyed the first seventy-four (74) control relays from Diesel Generator "A". Fifty-eight (58) each were verified acceptable and sixteen (16) each had to change the relay bases.

After reinstallation of the control relays for Generator "A" is complete, the remaining seventy-four (74) control relays for Diesel Generator "B" will be removed and returned to Amarace Corporation for repair / replacement. Turn around time has been reported to be four (4) weeks plus removal / reinstallation requirements.

A Final Report will be submitted to the USNRC by August 13, 1982.

Very truly yours, GDMcL/LLB/grf 8206210475 820614 PDRADOCK05000g

Mr. John T. Collins Page 2 cc: 1) Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555

2) Director Office of Management Information and Program Control i U. S. Nuclear Regulatory Commission Washington, D. C. 20555