ML18066A898

From kanterella
Revision as of 10:11, 3 February 2020 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Monthly Operating Rept for Feb 1997 for Palisades Nuclear Plant.W/970304 Ltr
ML18066A898
Person / Time
Site: Palisades Entergy icon.png
Issue date: 02/28/1997
From: Hawn R, Kobiata K
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9703100274
Download: ML18066A898 (5)


Text

,.,_

' -c*l:onsun.ets ~

[l A CMS Energy Company Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, Ml 49043 March 4, 1997 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 LICENSEE REPORT OF MONTHLY OPERATING DATA DPR-20, DOCKET. NO 50-255 Enclosed is a copy of the Monthly Operating Data and Summary of Operating Experience for the Palisades Nuclear Plant for the month of February 1997.

If you have any questions or concerns, please to contact me at (616) 764-3179.

Sincerely, R. S. Hawn Reactor Engineering Supervisor CC: RAVincent, Palisades ALWilliams, Palisades Senior Resident Inspector, Palisades DRHahn, Div of Rad Health Services. Lansing, Ml BWJorgensen, Michigan Dept of Labor, Lansing, Ml JPadgett, Michigan Public Service Commission Records Center, INPO, Atlanta, GA CWMain, Palisades .

SMMclntyre, P26-204 Region Ill Administrator, USNRC

. Document Control, 950*22*35*1 O/L Cycle 13 Reports

( .

9703100274 970228

~DR ADOCK 05000255

- - -- - - ---- -- - ~DR -

~*.-~~~~

Illml llill llU I 7 llllll llill I

lml I

lnll Ililll Illlll 1IW 1111*

it

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO 50-255 UNIT Palisades DATE 03/04/97 COMPLETED BY KAKobiata MONTH February TELEPHONE (616)764-2572 AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe Net) (MWe Net)

1. 0 17. 31
2. 0 18. ,* . *o
3. 0 19. 17
4. 0 20. 503
5. 0 21. 768
6. 0 22. 774
7. 0 23. 775
8. 23 24. 774
9. 366 25. 774
10. 753 26. 774
11. 766 27. 775
12. 403 28. 775
13. 315 29.
14. 315 30.
15. 335 31.
16. 626 INSTRUCTIONS:

On this format, list the average daily unit power level in MWe-NET for each day in the reporting month.

Compute to the nearest whole megawatt.

SUMMARY

OF OPERATING EXPERIENCE FOR FEBRUARY 1997 The Unit began the month in a continued shutdown condition. The reactor went critical on February 7 at 1605.bours. and.online.febr.uacy. 8 aL1840 bours.-.On Febr.uacy.10 aLOS-45 the.Unit.was.aUOO.%.poweL.

On February 11 at 1916, the Unit began to reduce power in 10% increments to evaluate and reduce the vibration on the main generator bushings. Subsequently, the power was reduced until it was decreased to 49% power on February 12 to monitor the vibration. The Unit remained at 49% power until February 17, when the Unit was taken offline at 0202 due to a hydrogen leak in the generator. The reactor remained critical during the forced outage. The Unit went back online February 19 at 2003 hours0.0232 days <br />0.556 hours <br />0.00331 weeks <br />7.621415e-4 months <br />. The Unit achieved full power at 0300 on February 21.

REPORT MONTH FEBRUARY 1997 DOCKET NO 50-255 UNIT Palisades DATE 03/04/97 COMPLETED BY KAKobiata TELEPHONE 616-764-2572 UNIT SHUTDOWNS AND POWER REDUCTIONS No. Date Type1 Duration Reason2 . Method of Licensee System Component Cause & Corrective

,9 (Hours) Shutting Down Reactor Event Report#

Code* Code 5 Action to Prevent Recurrence

4. 2117 F 66 A Hydrogen leak on turbine generator.
1. 2. 3. 4. 5.

F: Forced Reason Method: Exhibit G - Instructions Exhibit I - Same Source S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction 4-0ther (Explain) (NUREG-0161)

E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain)

OPERATING DATA REPORT DOCKET NO 50-255 DATE 3-3-97 COMPLETED BY KAKobiata TELEPHONE (616)764-2572 OPERATING STATUS:

NOTES:

1. UNIT NAME Palisades
2. REPORTING PERIOD: 970201-970228
3. LICENSED THERMAL.POWER (MWt) 2530
4. NAMEPLATE RATING (GROSS MWe) 811. 7
5. DESIGN ELECTRICAL RATING (NET MWe) 805
6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe) **770
7. MAXIMUM DEPENDABLE CAPACITY (NET MWe) **730
8. IF CHANGES OCCUR IN CAPCITY RATINGS (ITEM NUMBERS 3 THROUGH 7AND 7) SINCE LAST REPORT, GIVE REASONS:
9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):
10. REASONS FOR* RESTRICTIONS, IF ANY:

This Month Yr-to-Date cumulative

11. HOURS IN REPORTING PERIOD 672. 0 1416. 0 220887.0
12. NUMBER OF HOURS REACTOR WAS CRITICAL 512.0 890.2 128987.4
13. REACTOR RESERVE SHUTDOWN HOURS
14. HOURS GENERATOR ON-LINE 441.4 772 .2 123997.7
15. UNIT RESERVE SHUTDOWN HOURS
16. GROSS THERMAL ENERGY GENERATED (MWH) 860456.4 1633018.8 273237017.3
17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 270153 517837 86584572
18. NET ELECTRICAL ENERGY GENERATED (MWH) 254494 489543 81757303 19.* UNIT SERVICE FACTOR 65.7\ 54.5\ 56 .1\
20. UNIT AVAILABILITY FACTOR 65.7\ 54.5\ 56 .1\
21. UNIT CAPACITY FACTOR (USING MDC NET) 51. 9\ 47.4\ 54.3\*
22. UNIT CAPACITY FACTOR (USING DER NET) 47.0\ 42. 9\ 46. O'ls
23. UNIT FORCED OUTAGE RATE 34.3\ 45.5\ 27.8\
24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH) : .
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
  • 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Based on condenser backpressure

    • Weighted Average (635 MWe used as MDC Net prior to October 1985)