Monthly Operating Rept for Feb 1997 for Palisades Nuclear Plant
ML18066A901
Person / Time
Site: Palisades Entergy icon.png
Issue date: 02/28/1997
From: Hawn R, Kakobiata K
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9703120044
Download: ML18066A901 (5)


Text

A CMS Energy Company Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, Ml 49043 March 6, 1997 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 LICENSEE REPORT OF MONTHLY OPERATING DATA DPR-20, DOCKET NO 50-255 Enclosed is a revised copy of the Monthly Operating Data and Summary of Operating Experience for the

  • Palisades Nuclear Plant for the month of February 1997.

If you have any questions or concerns, please to contact me at (616) 764-3179.

Sincerely, R. S. Hawn Reactor Engineering Supervisor CC: RAVincent, Palisades ALWilliams, Palisades Senior Resident Inspector, Palisades DRHahn, Div of Rad Health Services, Lansing, Ml BWJorgensen, Michigan Dept of Labor, Lansing, Ml JPadgett, Michigan t:'ubiic Service Commission Records Center, INPO, Atlanta, GA CwMain, Palisades*

SMMclntyre, P26-204 Region Ill Administrator, USNRC Document Control, 950*22*35*1 O/L Cycle 13 Reports I llllll lru! 1111lllUI11m m1 llUI 11111 111111111 llU t

1 I

I I

t I

I

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO 50-255 UNIT Palisades DATE 03104197 COMPLETED BY KAKobiata MONTH February TELEPHONE (616)764-2572 AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL

.(MWe Net)

(MWe Net)

1.

0

17.

31

2.

0

18.

0

3.

0

19.

17

4.

0

20.

503

5.

0

21.

768

6.

0

22.

774

7.

0

23.

775

8.

23

24.

774

9.

366

25.

774

10.

753

26.

774

11.

766

27.

775

12.

403

28.

775

13.

315

29.
14.

315

30.
15.

335

31.
16.

626 INSTRUCTIONS:

On this format, list the average daily unit power level in MWe-NET for each day in the reporting month.

Compute to the nearest whole megawatt.

SUMMARY

OF OPERATING EXPERIENCE FOR FEBRUARY 1997 The Unit began the month in a continued shutdown condition. The reactor went critical on February 7 at 1605 hours0.0186 days <br />0.446 hours <br />0.00265 weeks <br />6.107025e-4 months <br /> and on line February 8 at 1840 hours0.0213 days <br />0.511 hours <br />0.00304 weeks <br />7.0012e-4 months <br />. On February 1 O at 0545 the Unit was at 100% power.

On February 11at1916, the Unit began to reduce power in 10% increments to evaluate and reduce the vibration on the main generator bushings. Subsequently, the power was reduced until it was decreased to 49% power on February 12 to monitor the vibration. The Unit remained at 49% power until February 17, when the Unit was taken offline at 0202 due to a hydrogen leak in the generator. The reactor remained critical during the forced outage. The Unit went back online February 19 at 2003 hours0.0232 days <br />0.556 hours <br />0.00331 weeks <br />7.621415e-4 months <br />. The Unit achieved full power at 0300 on February 21.

'-~.

REPORT MONTH FEBRUARY 1997 DOCKET NO 50-255 UNIT Palisades DA TE 03104/97 COMPLETED BY KAKobiata TELEPHONE 616-764-2572 UNIT SHUTDOWNS AND POWER REDUCTIONS REVISED No.

Date Type' Duration (Hours)

Reason2 Method of Shutting Licensee Event System Code4 Down Reactor Report #

3.

1/23 F

186.7 A

4.

2117 F

66 A

1.
2.

F: Forced Reason S: Scheduled A-Equipment Failure (Explain)

B-Maintenance or Test

3.

Method:

1-Manual 1

2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 4-0ther (Explain)

4.

Exhibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0161)

Component Code5

5.

Cause & Corrective Action to Prevent Recurrence Continuation of January shutdown, Duration from beginning of month.

Hydrogen leak on turbine generator.

Exhibit I - Same Source

-~l.

OPERATING STATUS:

1.

UNIT NAME

2.

REPORTING PERIOD:

3.

LICENSED THERMAL POWER (MWt)

4.

NAMEPLATE RATING (GROSS MWe)

5.

DESIGN ELECTRICAL RATING (NET MWe)

6.

MAXIMUM DEPENDABLE CAPACITY (GROSS MWe)

MAXIMUM DEPENDABLE CAPACITY (NET MWe)

OPERATING DATA REPORT Palisades 970201-970228 2530 811. 7 805

    • 770
    • 730
7.
8.

IF CHANGES OCCUR IN CAPCITY RATINGS (ITEM NUMBERS 3 THROUGH 7AND 7) SINCE LAST REPORT, GIVE REASONS:

9.

POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):

10. REASONS FOR RESTRICTIONS, IF ANY:
11. HOURS IN REPORTING PERIOD
12. NUMBER OF HOURS REACTOR WAS CRITICAL
13. REACTOR RESERVE SHUTDOWN HOURS
14. HOURS GENERATOR ON-LINE
15. UNIT RESERVE SHUTDOWN HOURS
16. GROSS THERMAL ENERGY GENERATED (MWH)
17. GROSS ELECTRICAL ENERGY GENERATED (MWH)
18. NET ELECTRICAL ENERGY GENERATED (MWH)
19. UNIT SERVICE FACTOR
20. UNIT AVAILABILITY FACTOR
21. UNIT CAPACITY FACTOR (USING MDC NET)
22. UNIT CAPACITY FACTOR (USING DER NET)
23. UNIT FORCED OUTAGE RATE This Month 672. 0 512.0 419.4 860456.4 270153 254494 62.4\\

62.4\\

51.9\\

47.0\\

37.6\\

24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

    • Based on condenser backpressure
  • Weighted Average (635 MWe used as MDC Net prior to October 1985)

Yr-to-Date 1416.0 890.2 750.2 1633018.8 517837 489543 53.0\\

53.0\\

47.4\\

42.9\\

47.0\\

Forecast DOCKET NO 50-255 DATE 3-3-97 COMPLETED BY KAKobiata TELEPHONE (616)764-2572 NOTES:

Cumulative 220887.0 128987.4 123975.7 273237017.3 86584572 81757303 56.1\\

56.H 54.3\\*

46.0\\

27.8\\

Achieved