Monthly Operating Rept for Nov 1998 for Palisades Nuclear Plant.With
ML18066A342
Person / Time
Site: Palisades 
Issue date: 11/30/1998
From: Handlovits S, Hawn R
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9812090082
Download: ML18066A342 (5)


Text

(

A CMS Energy Company December 2, 1998 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, Ml 49043 LICENSEE REPORT OF MONTHLY OPERATING DATA DPR-20, DOCKET NO 50-255 Enclosed is a copy of the Monthly Operating Data and Summary of Operating Experience for the Palisades Nuclear Plant for the month of November 1998.

If you have any questions or concerns, please contact me at (616) 764-3179.

Sincerely, R. S. Hawn Reactor Engineering Supervisor CC: AMDavis, Palisades GABaustian, Palisades Senior Resident Inspector, Palisades DRHahn, Div of Rad Health Services, Lansing, Ml BWJorgensen, Michigan Dept of Labor, Lansing, Ml RDWhale, Michigan Public Service Commission Records Center, INPO, Atlanta, GA*.

SMMclntyre, P26-204 Region Ill Administrator, USNRC Pal. Eng. Records Center, 950*22*35*1 O/L Cycle 14 Reports (SMH 98*13)

  • *.. l '

~. '

,. \\'.."' n !J q6

  • .) \\,) **.... )......

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO 50-255 UNIT Ealisades DATE 12/02/98 COMPLETED BY SMHandlovits MONTH November TELEPHONE (616)764-3262 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe Net)

(MWe Net)

1.

787

17.

790

2.

789

18.

789

3.

793

19.

789

4.

794

20.

792

5.

794

21.

793

6.

793

22.

790

7.

793

23.

785

8.

792

24.

790

9.

792

25.

789

10.

787

26.

791

11.

790

27.

790

12.

790

28.

787

13.

792

29.

780

14.

788

30.

783

15.

791

31.

N/A

16.

788 INSTRUCTIONS:

On this format, list the average daily unit power level in MWe-NET for each day in the reporting month.

Compute to the nearest whole megawatt.

SUMMARY

OF OPERATING EXPERIENCE FOR NOVEMBER 1998 The Plant began the month of November at 99.9% power and operated at nominal full power for the entire month.

REPORTMONTH~~~N~O~V~E~M~B~ER"'-"""19~9~8...._~

No.

Date NONE

1.

F: Forced S: Scheduled Type1 Duration Reason2 (Hours}

2.

Reason:

A-Equipment Failure (Explain}

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & License Examination F-Administrative G-Operational Error (Explain}

H-Other (Explain}

UNIT SHUTDOWNS AND POWER REDUCTIONS Method of Shutting Down Reactor

3.

Method:

1-Manual 2-Manual Scram 3-Automatic Scram Licensee Event Report#

4.

System Code4 Component Code5 Exhibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER} File

5.

Cause & Corrective Action to Prevent Recurrence Exhibit I - Same Source 4-0ther (Explain}

(NUREG-0161)

DOCKET NO 50-255 UNIT - Palisades DA TE 12102198 COMPLETED BY SMHandlovits TELEPHONE 616-764-3262

}*

.... ~

OPERATING STATUS:

1. UNIT NAME
2. REPORTING PERIOD:
3. LICENSED THERMAL POWER (MWt)

OPERATING DATA REPORT Palisades 981101-981130 2530

4. NAMEPLATE RATING (GROSS MWe) 811. 7
5. DESIGN ELECTRICAL RATING (NET MWe) 805
6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe) 770
7. MAXIMUM DEPENDABLE CAPACITY (NET MWe) 730
8. IF CHANGES OCCUR IN CAPCITY RATINGS (ITEM NUMBERS 3 THROUGH 7 AND 7) SINCE LAST REPORT, GIVE REASONS:
9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):

10 REASONS FOR RESTRICTIONS, IF ANY:

11 HOURS IN REPORTING PERIOD 12 NUMBER OF HOURS REACTOR WAS CRITICAL 13 REACTOR RESERVE SHUTDOWN HOURS 14 HOURS GENERATOR ON-LINE 15 UNIT RESERVE SHUTDOWN HOURS 16 GROSS THERMAL ENERGY GENERATED (MWH) 17 GROSS ELECTRICAL ENERGY GENERATED (MWH) 18 NET ELECTRICAL ENERGY GENERATED (MWH) 19 UNIT SERVICE FACTOR 20 UNIT AVAILABILITY FACTOR 21 UNIT CAPACITY FACTOR (USING MDC NET) 22 UNIT CAPACITY FACTOR (USING DER NET) 23 UNIT FORCED OUTAGE RATE This Month 720. 0 720.0 720. 0 1819725. 6 596634 568609 100.0%

100.0%

108.2%

98.1%

0.0%

24 SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):

25 IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

26 UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

Yr-to-Date 8016.0 7004.0 6834.5 16755114. 2 5415515 5147720 85.3%

85.3%

88.0%

79.8%

2.3%

Forecast INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Based on condenser backpressure

  • Weighted Average (635 MWe used as MDC Net prior to October 1985)

DOCKET NO 50-255 DATE 12-2-98 COMPLETED BY SMHandlovits TELEPHONE (616)764-3262 NOTES:

Cumulative 236247.0 142973.5 137775.7 307435918. 4 97586649 92218936 58.3%

58.3%

56. 8%
  • 48.5%

26.0%

Achieved