Category:Inspection Plan
MONTHYEARIR 05000461/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2024005) ML24220A2772024-08-0707 August 2024 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000461/2025010 ML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000461/20230062024-02-28028 February 2024 Annual Assessment Letter for Clinton Power Station (Report 05000461/2023006) ML24054A7112024-02-23023 February 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000461/2024011 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information IR 05000461/20220062023-03-0101 March 2023 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2022006) ML23005A0682023-01-0505 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000461/2023010 ML22312A5362022-11-0808 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000461/2023401 IR 05000461/20220052022-08-22022 August 2022 Updated Inspection Plan for Clinton Power Station (Report 05000461/2022005) IR 05000461/20210062022-03-0202 March 2022 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2021006) ML21333A0832021-11-29029 November 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Teams), Inspection Report Report 05000461/202201 IR 05000461/20210052021-09-0101 September 2021 Updated Inspection Plan for Clinton Power Station; Report 05000461/2021005 ML21215A5732021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21076A5112021-03-17017 March 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000461/2021013 ML21071A1882021-03-12012 March 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Clinton Power Station IR 05000461/20200062021-03-0404 March 2021 Annual Assessment Letter for Clinton Power Station Unit 1 (Report 05000461/2020006) ML20329A0662020-11-24024 November 2020 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection IR 05000461/20200052020-09-0101 September 2020 Updated Inspection Plan for Clinton Power Station, Unit 1 (Report 05000461/2020005) ML20183A1932020-06-30030 June 2020 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000461/2020010 IR 05000461/20190062020-03-0303 March 2020 Annual Assessment Letter for Clinton Power Station, (Report 05000461/2019006) IR 05000461/20190052019-08-28028 August 2019 Updated Inspection Plan for Clinton Power Station (Report 05000461/2019005 ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000461/20180062019-03-0404 March 2019 Annual Assessment Letter for Clinton Power Station (Report 05000461/2018006) ML19037A4772019-02-0606 February 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspect at Clinton Power Station ML19003A1912019-01-0303 January 2019 Request for Information for an NRC Triennial Baeline Design Bases Assurance Inspection; Inspection Report 05000461/2019011 IR 05000461/20180052018-08-28028 August 2018 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2018005) ML18088A5662018-03-28028 March 2018 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection 05000461/2018010 IR 05000461/20170062018-03-0202 March 2018 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2017006) ML17333A0782017-11-28028 November 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2018002 IR 05000461/20170052017-08-28028 August 2017 Updated Inspection Plan for Clinton Power Station, Unit 1 and Quarterly Assessment Letter (Report 05000461/2017005) ML17146B2492017-03-31031 March 2017 Inspection Plan for Clinton Power Station for Triennial Fire Protection Baseline Inspection Report 2017 008 ML17076A3382017-03-16016 March 2017 Notification of NRC Baseline Inspection and Request for Information 05000461/2017002 IR 05000461/20160062017-03-0101 March 2017 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2016006) IR 05000461/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2016005) ML16098A3242016-04-0707 April 2016 Information Request to Support Upcoming Temporary Instruction 191 Inspection at Clinton Power Station ML16076A2542016-03-15015 March 2016 Ltr. 03/15/16 Clinton Power Station, Unit 1 - Request for Information for an NRC Triennial Baseline Component Design Bases Inspection; Inspection Report 05000461/2016009 (Jen) ML16076A2462016-03-15015 March 2016 Ltr. 03/15/16 Clinton Power Station - Notification of NRC Inspection and Request for Information (Vlm) IR 05000461/20150062016-03-0202 March 2016 Annual Assessment Letter for Clinton Power Station Unit 1 (Inspection Report 05000461/2015006) IR 05000461/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2015005) IR 05000461/20140012015-03-0404 March 2015 Annual Assessment Letter for Clinton Power Station, Unit 1, (Report 05000461/2014001) ML14245A2362014-09-0202 September 2014 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 ML14177A3812014-06-25025 June 2014 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000451/20130012014-03-0404 March 2014 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000451/2013001) ML13308B1302013-11-0101 November 2013 Ltr 11/1/13 Clinton Fire Protection Request for Information ML13246A2152013-09-0303 September 2013 2013 Clinton Power Station Mid-Cycle Letter Combined IR 05000461/20130082013-07-25025 July 2013 IR 05000461-13-008, May 20 - 24, 2013, June 3 - 7, 2013, and June 17 - 21, 2013, Clinton Power Station, Component Design Bases Inspection (CDBI) IR 05000461/20120012013-03-0404 March 2013 Annual Assessment Letter for Clinton Power Station (Report 05000461/2012001) ML13038A3122013-02-0707 February 2013 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection Report 05000461-13-008 ML12249A4462012-09-0404 September 2012 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 2024-08-07
[Table view] Category:Letter
MONTHYEARML24285A1422024-10-24024 October 2024 Ltr. to Darwin Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Re CPS Section 106 Consultation ML24285A1442024-10-24024 October 2024 Ltr. to Estavio Elizondo, Sr., Chairman, Kickapoo Traditional Tribe of Texas Re CPS Section 106 Consultation ML24285A1482024-10-24024 October 2024 Ltr. to Joseph Rupnick, Chairman, Prairie Band Potawatomi Nation Re CPS Section 106 Consultation ML24285A1462024-10-24024 October 2024 Ltr. to Gena Kakkak, Chairwoman, Menominee Indian Tribe of Wisconsin Re CPS Section 106 Consultation ML24285A1472024-10-24024 October 2024 Ltr. to Geoffrey M. Standing Bear, Principal Chief, Osage Nation Re CPS Section 106 Consultation ML24285A1452024-10-24024 October 2024 Ltr. to Gail Cheatham, Kickapoo Tribe of Indians of the Kickapoo Reservation in Ks Re CPS Sect 106 Consult ML24285A1412024-10-21021 October 2024 Ltr. to Craig Harper, Chief, Peoria Tribe of Oklahoma Re CPS Section 106 Consultation ML24285A1432024-10-21021 October 2024 Ltr. to Douglas Lankford, Chief, Miami Tribe of Oklahoma Re CPS Section 106 Consultation RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing 05000461/LER-2023-002-01, Reactor Core Isolation Cooling Inoperable Prior to Mode Change2024-09-24024 September 2024 Reactor Core Isolation Cooling Inoperable Prior to Mode Change ML24211A2302024-09-11011 September 2024 – Request for Partial Site Release for Facility Operating License No. NPF-62 IR 05000461/20240112024-09-0909 September 2024 Commercial Grade Dedication Inspection Report 05000461/2024011 RS-24-087, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2024-09-0909 September 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station IR 05000461/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2024005) ML24222A3952024-08-23023 August 2024 Regulatory Audit Report to Support the Review of the Amendments to Revise Reactor Water Cleanup Valve Isolation Timing ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000461/20240022024-08-0909 August 2024 Integrated Inspection Report 05000461/2024002 ML24220A2772024-08-0707 August 2024 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000461/2025010 ML24212A2212024-08-0202 August 2024 License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-LNE-0000) (Docket Number: 50-461) ML24157A3242024-07-11011 July 2024 Issuance of Amendment No. 254 Revision of Reactor Water Cleanup Isolation Valve Timing ML24158A0772024-07-0303 July 2024 Notice of Consideration of Approval of Partial Site Release, Public Meeting, and Request for Comments (EPID L-2023-LLA-0088) - Letter ML24163A3252024-06-28028 June 2024 Aging Management Regulatory Audit Plan ML24163A3242024-06-28028 June 2024 LRA - Portal Letter ML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24176A0272024-06-25025 June 2024 Confirmation of Initial License Examination, July 2025 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes IR 05000461/20240122024-05-20020 May 2024 Biennial Problem Identification and Resolution Inspection Report Report 05000461/2024012 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-050, Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2024-05-0909 May 2024 Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation IR 05000461/20240012024-05-0707 May 2024 Integrated Inspection Report 05000461/2024001 ML24103A1032024-05-0101 May 2024 SHPO Consultation Letter for Clinton License Renewal RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24120A3432024-04-30030 April 2024 Ltr. to Darwin Kaskaske, Chairman, Kickapoo Tribe of Oklahoma; Re., CPS Section 106 Consultation ML24120A3452024-04-30030 April 2024 Ltr. to Lester Randell, Chairman, Kickapoo Tribe of Indians of the Kickapoo Reservation in Kansas; Re., CPS Section 106 Consultation ML24103A0992024-04-30030 April 2024 Achp Scoping Letter for Clinton License Renewal ML24120A3442024-04-30030 April 2024 Ltr. to Gena Kakkak, Chairman, Menominee Indian Tribe of Wisconsin; Re., CPS Section 106 Consultation ML24103A1152024-04-30030 April 2024 Ltr. to Geoffrey Standing Bear, Principal Chief, the Osage Nation; Re., CPS Section 106 Consultation ML24120A3462024-04-30030 April 2024 Ltr. to Douglas Lankford, Chief, Miami Tribe of Oklahoma; Re., CPS Section 106 Consultation ML24107B0312024-04-29029 April 2024 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24089A2222024-04-11011 April 2024 LRA - Acceptance and Opportunity for Hearing - Letter ML24092A3452024-04-0101 April 2024 Updated Safety Analysis Report (Usar), Revision 23 ML24092A3552024-04-0101 April 2024 Request for Information for NRC License Renewal Inspection: Inspection Report 05000461/2024010 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. ML24045A1422024-02-29029 February 2024 License Renewal Application Receipt and Availability - Letter IR 05000461/20230062024-02-28028 February 2024 Annual Assessment Letter for Clinton Power Station (Report 05000461/2023006) 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24222A4092024-05-0303 May 2024 NRR E-mail Capture - Request for Additional Information Regarding Reactor Water Cleanup (RWCU) Pump Rooms - L-2023-LLA-0118 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information ML23363A0302023-12-29029 December 2023 NRR E-mail Capture - Preliminary RAIs for Clinton Partial Site Release ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23230B1682023-08-18018 August 2023 NRR E-mail Capture - Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (Rais) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications ML23202A0992023-07-24024 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2023004 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22312A5362022-11-0808 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000461/2023401 ML22255A1402022-09-12012 September 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Clinton Power Station ML22173A0382022-06-21021 June 2022 NRR E-mail Capture - Request for Additional Information (RAI) Regarding Clinton License Amendment Request for Secondary Containment Design Basis (L-2022-LLA-0055) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21225A0392021-08-13013 August 2021 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Request to Revise Degraded Voltage Instrumentation Setpoints ML21204A0152021-07-23023 July 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2021004 ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21071A1882021-03-12012 March 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Clinton Power Station ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1012021-02-26026 February 2021 NRR E-mail Capture - Clarification of Second Round RAI - Clinton TSTF-505 License Amendment Request ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21057A1002021-02-17017 February 2021 NRR E-mail Capture - Second Round RAI - Clinton TSTF-505 License Amendment Request ML21026A0582021-01-25025 January 2021 Notification of NRC Supplemental Inspection (95001) and Request for Information ML20315A0642020-11-0909 November 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000461/2021010 ML20307A6592020-10-27027 October 2020 NRR E-mail Capture - Request for Additional Information Regarding TSTF-505 and 50.69 Applications ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20135H1972020-05-14014 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Extend Safety Relief Valve Test Interval ML20128J8642020-05-0707 May 2020 NRR E-mail Capture - Preliminary RAIs for Clinton Load Tap Changer License Amendment Request ML20105A1082020-04-14014 April 2020 NRR E-mail Capture - Request for Additional Information Regarding Clinton Relief Request I4R-01 ML20091F7892020-03-25025 March 2020 NRR E-mail Capture - Request for Additional Information Regarding Clinton Relief Request I4R-05 ML19330E1772019-11-25025 November 2019 RAI Dresden/Clinton Request for LAR to Modify TSs Following Adoption of TSTF-542 ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML18225A2882018-08-13013 August 2018 Ltr. 08/13/18 Clinton Power Station - Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the Environmental Qualification Program Inspection Report 05000461/2018011 (DRS-B.Jose) ML18214A4452018-08-0202 August 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Revised Alternate Source Term ML18193A9732018-07-12012 July 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Revised Alternate Source Term ML18088A5662018-03-28028 March 2018 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection 05000461/2018010 ML17285B1962017-10-27027 October 2017 Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools. ML17276B7632017-10-0303 October 2017 NRR E-mail Capture - Clinton Power Station - Request for Additional Information Regarding License Amendment Request Related to Reactor Pressure Vessel Water Inventory Control ML17159A6292017-06-0707 June 2017 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML17125A3212017-05-0202 May 2017 NRR E-mail Capture - Clinton Power Station, Unit 1 - Request for Additional Information Regarding the Permanent Extension of Leak Rate Testing ML16356A0422016-12-20020 December 2016 Notification of NRC Triennial Fire Protection Baseline Inspection and Request for Information 05000461/2017008 (Dxs) ML16130A6642016-05-11011 May 2016 Request for Additional Information Related to Incorporation of Revised Alternative Source Term (CAC No. MF7336)(RS-16-019) ML16071A2062016-03-15015 March 2016 RAI Regarding License Amendment Request to Revise the Reactor Steam Dome Pressure in Technical Specification 2.1.1, Reactor Core Sls(Cac Nos. MF6640 & MF6644) ML15106A9282015-04-24024 April 2015 Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.2, :Primary Coolant Sources Outside Containment ML15068A4212015-04-16016 April 2015 Request for Additional Information Regarding Relief Request 13R-11 ML15062A6482015-03-24024 March 2015 Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.2, Primary Coolant Sources Outside Containment 2024-07-12
[Table view] |
See also: IR 05000461/2018010
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, ILLINOIS 60532-4352
March 28, 2018
Mr. Bryan C. Hanson
Senior VP, Exelon Generation Company, LLC
President and CNO, Exelon Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: CLINTON POWER STATIONINFORMATION REQUEST FOR AN NRC
TRIENNIAL 10 CFR 50.59 (EVALUATION OF CHANGES, TESTS AND
EXPERIMENTS) BASELINE INSPECTION 05000461/2018010
Dear Mr. Hanson:
On July 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) will begin a Title 10 of the
Code of Federal Regulations, Part 50.59, (Evaluation of Changes, Tests and Experiments),
Baseline Inspection at the Clinton Power Station. This inspection will be performed in
accordance with the NRC Baseline Inspection Procedure 71111.17T. The onsite portions of the
inspection will take place on July 30-August 3, 2018.
Experience has shown that these baseline inspections are extremely resource intensive, both
for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on
the site and to ensure a productive inspection for both parties, we have enclosed a request for
documents needed for the inspection. These documents have been divided into three groups.
The first group of information is necessary to ensure that the inspection team is
adequately prepared for the inspection. This information should be made available via
compact disc and delivered to the regional office no later than June 1, 2018. The
inspection team will review this information and, by June 15, 2018, will request specific
items that should be provided for review in the regional office by July 13, 2018.
The second group of requested documents contains additional items that the team will
review, or need access to, during the inspection. Certain documents contained within
Group II (i.e., Item (1)), will be requested for review in the regional office prior to the
inspection by July 13, 2018, as identified above. The remaining documents should be
available by the first day of the onsite inspection, July 30, 2018.
The third group lists information necessary to aid the inspection team in tracking issues
identified as a result of the inspection. It is requested that this information be provided to
the lead inspector as the information is generated during the inspection. It is important
that all of these documents are up to date and complete in order to minimize the number
of additional documents requested during the preparation and/or the onsite portions of
the inspection.
The lead inspector for this inspection is Atif Shaikh. We understand that our regulatory contact
for this inspection is Nicholas Santos of your organization. If there are any questions about the
inspection or the material requested, please contact the lead inspector at 630-829-9824 or via
e-mail at Atif.Shaikh@nrc.gov.
B. Hanson -2-
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Atif Shaikh, Senior Inspector
Engineering Branch 3
Division of Reactor Safety
Docket No. 50-461
License No. NPF-62
Enclosure:
Document Request for 10 CFR 50.59
Inspection
cc: Distribution via LISTSERV
B. Hanson -3-
Letter to Bryan C. Hanson from Atif Shaikh dated March 28, 2018
SUBJECT: CLINTON POWER STATIONINFORMATION REQUEST FOR AN NRC
TRIENNIAL 10 CFR 50.59 (EVALUATION OF CHANGES, TESTS AND
EXPERIMENTS) BASELINE INSPECTION 05000461/2018010
DISTRIBUTION:
Jeremy Bowen
RidsNrrDorlLpl3
RidsNrrPMClinton Resource
RidsNrrDirsIrib Resource
Steven West
Darrell Roberts
Richard Skokowski
Allan Barker
DRSIII
DRPIII
ADAMS Accession Number ML: 18088A566
OFFICE RIII RIII RIII RIII
NAME AShaikh:cl
DATE 03/28/18
OFFICIAL RECORD COPY
DOCUMENT REQUEST FOR 10 CFR 50.59 INSPECTION
Inspection Report: 05000461/2018010
Inspection Dates: July 30-August 3, 2018
Inspection Procedure: IP 71111.17T, Evaluations of Changes, Tests and Experiments
Lead Inspector: Atif Shaikh
630-829-9824
Atif.Shaikh@nrc.gov
I. Information Requested for In-Office Preparation Week
The following information is requested by June 1, 2018, or sooner, to facilitate the
selection of specific items that will be reviewed during the onsite inspection week. The
inspection team will select specific items from the information requested below and
submit a list to your staff by June 15, 2018. We will request that certain items be made
available to the regional office prior to the inspection by July 13, 2018. We request that
the remaining items selected from the lists be available and ready for review on the first
day of inspection. All requested information should identify the associated system and
cover the time frame from the receipt of information for the last 50.59 inspection to the
present.
The required information identified below should be provided on compact disc (CD) or
uploaded to accessible links. Please provide three copies of each CD submitted (i.e.,
one for each inspector, if applicable). The preferred file format is a searchable pdf file.
The CDs should be indexed and hyper-linked to facilitate ease of use, if possible. If you
have any questions regarding this information, please call the inspection team leader as
soon as possible.
(1) List of all Title 10 of the Code of Federal Regulations (CFR), Part 50.59
completed evaluations involving (a) calculations, (b) procedure revisions,
(c) changes to the facility (modifications), (d) non-routine operating
configurations, or (e) departures in methods of analyses. This list should
include 50.59 evaluations for the following:
a. Changes that have been made under the provisions of 10 CFR 50.59 that
have been updated in accordance with 10 CFR 50.71(e)(4) since the last
MOD/50.59 inspection;
b. Modifications that are field work complete; and
c. Changes to calculations (or initiation of new calculations) that have been
issued. The list should contain the number and title of each document, a brief
description of the change, and the corresponding number and type of the
affected document (i.e., the modification or procedure to which the evaluation
applies). The list should NOT include any evaluations in which prior NRC
approval was sought and obtained.
DOCUMENT REQUEST FOR 10 CFR 50.59 INSPECTION
(2) A list of all 10 CFR 50.59 changes that have been screened out as not requiring
a full evaluation involving: (a) calculations; (b) procedure revisions; (c) changes
to the facility (modifications); (d) non-routine operating configurations; or
(e) departures in methods of analyses.
The list should contain the number and title of each document, a brief description
of the change, and the corresponding number and type of the affected document
(i.e., the modification or procedure to which the evaluation applies).
(3) A list of any modifications, procedure revisions, or Updated Final Safety Analysis
Report (UFSAR) changes where it was determined that 10 CFR 50.59 did not
apply.
(4) A list of calculation changes that have been issued for use.
(5) A list of corrective action documents (open and closed) that address
10 CFR 50.59 issues, concerns, or processes. These documents should also
include the associated corrective action documents and the 50.59 change
implementation.
The list should contain the number, title and revision (or date) of each document,
the affected system and corresponding documentation (if applicable), and should
be sorted in order of significance.
(6) Copies of procedures addressing the following: modifications, design changes,
set point changes, equivalency evaluations or suitability analyses, commercial
grade dedications, post-modification testing, 10 CFR 50.59 evaluations and
screenings, and UFSAR updates.
(7) UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide
copies of the complete submittal.(8) Copy of the UFSAR change log or a
synopsis of the changes. This should include all of the changes made to the
UFSAR that were incorporated in the last 10 CFR 50.71(e)(4) submittal.
(8) Electronic copy of the UFSAR and Bases, and technical specifications, if
available.
(9) Name(s) and phone numbers for the regulatory and technical contacts.
(10) Current management and engineering organizational chart.
II. Information requested to be available prior to inspection. Requests will be made
for specific item (1) documents by June 15, 2018, for availability of requested item
(1) documents in regional office by July 13, 2018, and items (2), (3) and (4)
documents on first day of inspection (July 30, 2018).
(1) Copies of all selected items from Section I. This includes copies of
associated documents such as calculations, post-modification test packages,
10 CFR 50.59 evaluations or screenings, and any corrective action documents.
(2) Copies of these documents do not need to be solely available to the inspection
team as long as the inspectors have easy and unrestrained access to them.
DOCUMENT REQUEST FOR 10 CFR 50.59 INSPECTION
a. Updated Final Safety Analysis Report , if not previously provided;
b. Original Final Safety Analysis Report Volumes;
c. Original Safety Evaluation Report and Supplements;
d. Final Safety Analysis Report Question and Answers;
e. Quality Assurance Plan;
f. Technical Specifications, if not previously provided;
g. Latest IPE/PRA Report;
h. Vendor Manuals; and
i. The latest 10 CFR 50.59 UFSAR Update Submittal.
(3) Please ensure that other supporting documents for the selected items have been
located and are readily retrievable as the inspection team will likely be requesting
these documents during the inspection. Examples of supporting documents are:
a. Drawings supporting the modifications;
b. Procedures affected by the modifications; and
c. UFSAR change papers generated due to a 10 CFR 50.59 evaluation.
(4) Assessment and Corrective Actions:
a. The most recent MOD/50.59 Quality Assurance audit and/or self-assessment;
and
b. Corrective action documents (e.g., condition reports, including status of
corrective actions) generate as a result of the most recent MOD/50.59 Quality
Assurance audit and/or self-assessment.
III. Information Requested to be provided throughout the inspection
(1) Copies of any corrective action documents generated as a result of the
inspection teams questions or queries during this inspection.
(2) Copies of the list of questions submitted by the inspection team members and
the status/resolution of the information requested (provide daily during the
inspection to each inspection team member).
If you have any questions regarding the information requested, please contact the inspection
team leader.