ML24222A409
Letter Sequence RAI | |
---|---|
EPID:L-2023-LLA-0118, May 9, 2024 Clinton Power Station Public Meeting Transcript (Approved, Closed) | |
Initiation Administration | |
MONTHYEARRS-23-081, Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2023-08-21021 August 2023
[Table View]Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation Project stage: Request ML23261A0032023-09-15015 September 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Amendment Request to Revise Timing of Reactor Water Cleanup Isolation Valves Project stage: Acceptance Review ML23361A1572024-01-24024 January 2024 Audit Plan in Support of Review of License Amendment Request Regarding Revision of Technical Specifications Related to Reactor Water Cleanup Isolation Project stage: Other ML24222A4092024-05-0303 May 2024 NRR E-mail Capture - Request for Additional Information Regarding Reactor Water Cleanup (RWCU) Pump Rooms - L-2023-LLA-0118 Project stage: RAI RS-24-050, Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2024-05-0909 May 2024 Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation Project stage: Request ML24157A3242024-07-11011 July 2024 Issuance of Amendment No. 254 Revision of Reactor Water Cleanup Isolation Valve Timing Project stage: Approval ML24222A3952024-08-23023 August 2024 Regulatory Audit Report to Support the Review of the Amendments to Revise Reactor Water Cleanup Valve Isolation Timing Project stage: Approval 2024-05-03 |
ML24222A409 | |
Person / Time | |
---|---|
Site: | Clinton |
Issue date: | 05/03/2024 |
From: | Joel Wiebe NRC/NRR/DORL/LPL3 |
To: | Nicely K Exelon Generation Co |
References | |
L-2023-LLA-0118 | |
Download: ML24222A409 (2) | |
Similar Documents at Clinton | |
---|---|
Category:E-Mail
MONTHYEARML24250A1062024-09-0606 September 2024
[Table view]NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24222A4092024-05-0303 May 2024 NRR E-mail Capture - Request for Additional Information Regarding Reactor Water Cleanup (RWCU) Pump Rooms - L-2023-LLA-0118 ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information ML23363A0302023-12-29029 December 2023 NRR E-mail Capture - Preliminary RAIs for Clinton Partial Site Release ML23338A0402023-12-0404 December 2023 NRR E-mail Capture - Ready for Clean TS Pages and Updated Review Hours for Clinton Power Station, Unit 1, Request for License Amendment to Revise Technical Specifications Section 3.8.3 ML23268A0022023-09-22022 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-264-A, Revision 0 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML23261A0032023-09-15015 September 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Amendment Request to Revise Timing of Reactor Water Cleanup Isolation Valves ML23230B1682023-08-18018 August 2023 NRR E-mail Capture - Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (Rais) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications ML23219A2142023-08-0404 August 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Request for Partial Site Release ML23194A1102023-07-13013 July 2023 NRR E-mail Capture - Non-acceptance of Clinton Request for Partial Site Release ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML23087A0122023-03-28028 March 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Revise Technical Specifications 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air (L-2023-LLA-0034) ML23033A0332023-02-0101 February 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Adopt TSTF-332 (L-2023-LLA-0007) ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22301A0902022-10-28028 October 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-301, Revision 2 ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22173A0382022-06-21021 June 2022 NRR E-mail Capture - Request for Additional Information (RAI) Regarding Clinton License Amendment Request for Secondary Containment Design Basis (L-2022-LLA-0055) ML22165A1902022-06-14014 June 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton Request to Adopt TSTF-230 (L-2022-LLA-0076) ML22165A1912022-06-14014 June 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton Request to Adopt TSTF-269 (L-2022-LLA-0077) ML23089A0182022-05-24024 May 2022 NRR E-mail Capture - Clinton Power Station Acceptance Review Results - Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan ML22116A0422022-04-26026 April 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Revise Secondary Containment Design Basis ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22157A3872022-01-28028 January 2022 Post Exam Submittal Letter Clinton 22 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21252A0482021-09-0707 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21252A0042021-08-26026 August 2021 NRR E-mail Capture - NRC Acceptance Review - Braidwood/Byron/Clinton - Adoption of TSTF-273, Safety Function Determination Program Clarifications ML21225A0392021-08-13013 August 2021 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Request to Revise Degraded Voltage Instrumentation Setpoints ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21203A3062021-07-21021 July 2021 NRR E-mail Capture - NRC Acceptance Review - Clinton - Third Inservice Inspection Interval Relief Request I3R-18 ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21182A0722021-06-29029 June 2021 SUNSI and Proprietary Review Determination Email Regarding: Tn CoC 1042 (Eos) Amendment 3 Rsi Responses ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21084A2532021-03-24024 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Transfer Application ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1012021-02-26026 February 2021 NRR E-mail Capture - Clarification of Second Round RAI - Clinton TSTF-505 License Amendment Request ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21057A1002021-02-17017 February 2021 NRR E-mail Capture - Second Round RAI - Clinton TSTF-505 License Amendment Request ML21041A5442021-02-10010 February 2021 NRR E-mail Capture - NRC Acceptance Review for Clinton Request for License Amendment to Revise Degraded Voltage Relay Allowable Values (L-2021-LLA-0005) ML21033A8552021-02-0202 February 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request to Expand the Use ASME Codes Cases N-878 and N-880 ML20350B5602020-12-15015 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-582 and TSTF-583-T (EPIDs L-2020-LLA-0253 and L-2020-LLA-0254) 2024-09-06 Category:Request for Additional Information (RAI) MONTHYEARML24283A1662024-10-23023 October 2024
[Table view]Enclosure 2 Clinton Audit Summary RCI and RAIs ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24222A4092024-05-0303 May 2024 NRR E-mail Capture - Request for Additional Information Regarding Reactor Water Cleanup (RWCU) Pump Rooms - L-2023-LLA-0118 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information ML23363A0302023-12-29029 December 2023 NRR E-mail Capture - Preliminary RAIs for Clinton Partial Site Release ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML23230B1682023-08-18018 August 2023 NRR E-mail Capture - Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (Rais) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications ML23202A0992023-07-24024 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2023004 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000461/20234012022-11-0808 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000461/2023401 ML22255A1402022-09-12012 September 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Clinton Power Station ML22173A0382022-06-21021 June 2022 NRR E-mail Capture - Request for Additional Information (RAI) Regarding Clinton License Amendment Request for Secondary Containment Design Basis (L-2022-LLA-0055) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21225A0392021-08-13013 August 2021 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Request to Revise Degraded Voltage Instrumentation Setpoints ML21204A0152021-07-23023 July 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2021004 ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21071A1882021-03-12012 March 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Clinton Power Station ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1012021-02-26026 February 2021 NRR E-mail Capture - Clarification of Second Round RAI - Clinton TSTF-505 License Amendment Request ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21057A1002021-02-17017 February 2021 NRR E-mail Capture - Second Round RAI - Clinton TSTF-505 License Amendment Request ML21026A0582021-01-25025 January 2021 Notification of NRC Supplemental Inspection (95001) and Request for Information ML20315A0642020-11-0909 November 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000461/2021010 ML20307A6592020-10-27027 October 2020 NRR E-mail Capture - Request for Additional Information Regarding TSTF-505 and 50.69 Applications ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20135H1972020-05-14014 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Extend Safety Relief Valve Test Interval ML20128J8642020-05-0707 May 2020 NRR E-mail Capture - Preliminary RAIs for Clinton Load Tap Changer License Amendment Request ML20105A1082020-04-14014 April 2020 NRR E-mail Capture - Request for Additional Information Regarding Clinton Relief Request I4R-01 ML20091F7892020-03-25025 March 2020 NRR E-mail Capture - Request for Additional Information Regarding Clinton Relief Request I4R-05 ML19330E1772019-11-25025 November 2019 RAI Dresden/Clinton Request for LAR to Modify TSs Following Adoption of TSTF-542 ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML18225A2882018-08-13013 August 2018 Ltr. 08/13/18 Clinton Power Station - Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the Environmental Qualification Program Inspection Report 05000461/2018011 (DRS-B.Jose) ML18214A4452018-08-0202 August 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Revised Alternate Source Term ML18193A9732018-07-12012 July 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Revised Alternate Source Term ML18088A5662018-03-28028 March 2018 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection 05000461/2018010 ML17285B1962017-10-27027 October 2017 Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools. ML17276B7632017-10-0303 October 2017 NRR E-mail Capture - Clinton Power Station - Request for Additional Information Regarding License Amendment Request Related to Reactor Pressure Vessel Water Inventory Control ML17159A6292017-06-0707 June 2017 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML17125A3212017-05-0202 May 2017 NRR E-mail Capture - Clinton Power Station, Unit 1 - Request for Additional Information Regarding the Permanent Extension of Leak Rate Testing ML16356A0422016-12-20020 December 2016 Notification of NRC Triennial Fire Protection Baseline Inspection and Request for Information 05000461/2017008 (Dxs) ML16130A6642016-05-11011 May 2016 Request for Additional Information Related to Incorporation of Revised Alternative Source Term (CAC No. MF7336)(RS-16-019) ML16071A2062016-03-15015 March 2016 RAI Regarding License Amendment Request to Revise the Reactor Steam Dome Pressure in Technical Specification 2.1.1, Reactor Core Sls(Cac Nos. MF6640 & MF6644) ML15106A9282015-04-24024 April 2015 Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.2, :Primary Coolant Sources Outside Containment ML15068A4212015-04-16016 April 2015 Request for Additional Information Regarding Relief Request 13R-11 2024-07-12 |
Text
From:
Joel Wiebe Sent:
Friday, May 3, 2024 11:27 AM To:
Nicely, Ken M.:(Exelon Nuclear)
Subject:
L-2023-LLA-0118 - Request for Additional Information REQUEST FOR ADDITIONAL INFORMATION EXELON GENERATION COMPANY, LLC CLINTON POWER STATION, UNIT NO. 1 DOCKET NO. 50-461 EPID: L-2023-LLA-0118 REGULATORY BASIS:
10 CFR 50 Appendix A Criterion 4Environmental and dynamic effects design bases NRC GUIDANCE of RELEVANCE:
NUREG-0800 Section 5.4.8 Reactor Water Cleanup System (BWR) Revision 3 NUREG-0800 Section 3.4.1, Internal Flood Protection for Onsite Equipment Failures. Revision 3 NUREG-0800 Section 3.6.1, Plant Design For Protection Against Postulated Piping Failures In Fluid Systems Outside Containment, Revision 3
RAI 1
Provide a summary of the calculation(s) that evaluate high energy line breaks in the reactor water cleanup (RWCU) pump rooms and credit the temperature isolation.
RAI 2
Do the RWCU rooms have watertight doors? Can a line break in the RWCU pump rooms leak into the auxiliary building hallway such that the water flows down the floor plugs into the emergency core cooling system cubicles?
Hearing Identifier:
NRR_DRMA Email Number:
2574 Mail Envelope Properties (MN2PR09MB497122FE5394EBF0B86563F08B1F2)
Subject:
L-2023-LLA-0118 - Request for Additional Information Sent Date:
5/3/2024 11:27:03 AM Received Date:
5/3/2024 11:27:00 AM From:
Joel Wiebe Created By:
Joel.Wiebe@nrc.gov Recipients:
"Nicely, Ken M.:(Exelon Nuclear)" <ken.nicely@constellation.com>
Tracking Status: None Post Office:
MN2PR09MB4971.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 1007 5/3/2024 11:27:00 AM Options Priority:
Normal Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date: