Category:E-Mail
MONTHYEARML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24222A4092024-05-0303 May 2024 NRR E-mail Capture - Request for Additional Information Regarding Reactor Water Cleanup (RWCU) Pump Rooms - L-2023-LLA-0118 ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information ML23363A0302023-12-29029 December 2023 NRR E-mail Capture - Preliminary RAIs for Clinton Partial Site Release ML23338A0402023-12-0404 December 2023 NRR E-mail Capture - Ready for Clean TS Pages and Updated Review Hours for Clinton Power Station, Unit 1, Request for License Amendment to Revise Technical Specifications Section 3.8.3 ML23268A0022023-09-22022 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-264-A, Revision 0 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23261A0032023-09-15015 September 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Amendment Request to Revise Timing of Reactor Water Cleanup Isolation Valves ML23230B1682023-08-18018 August 2023 NRR E-mail Capture - Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (Rais) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications ML23219A2142023-08-0404 August 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Request for Partial Site Release ML23194A1102023-07-13013 July 2023 NRR E-mail Capture - Non-acceptance of Clinton Request for Partial Site Release ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML23087A0122023-03-28028 March 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Revise Technical Specifications 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air (L-2023-LLA-0034) ML23033A0332023-02-0101 February 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Adopt TSTF-332 (L-2023-LLA-0007) ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22301A0902022-10-28028 October 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-301, Revision 2 ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22173A0382022-06-21021 June 2022 NRR E-mail Capture - Request for Additional Information (RAI) Regarding Clinton License Amendment Request for Secondary Containment Design Basis (L-2022-LLA-0055) ML22165A1902022-06-14014 June 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton Request to Adopt TSTF-230 (L-2022-LLA-0076) ML22165A1912022-06-14014 June 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton Request to Adopt TSTF-269 (L-2022-LLA-0077) ML23089A0182022-05-24024 May 2022 NRR E-mail Capture - Clinton Power Station Acceptance Review Results - Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan ML22116A0422022-04-26026 April 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Revise Secondary Containment Design Basis ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22157A3872022-01-28028 January 2022 Post Exam Submittal Letter Clinton 22 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21252A0482021-09-0707 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21252A0042021-08-26026 August 2021 NRR E-mail Capture - NRC Acceptance Review - Braidwood/Byron/Clinton - Adoption of TSTF-273, Safety Function Determination Program Clarifications ML21225A0392021-08-13013 August 2021 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Request to Revise Degraded Voltage Instrumentation Setpoints ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21203A3062021-07-21021 July 2021 NRR E-mail Capture - NRC Acceptance Review - Clinton - Third Inservice Inspection Interval Relief Request I3R-18 ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21182A0722021-06-29029 June 2021 SUNSI and Proprietary Review Determination Email Regarding: Tn CoC 1042 (Eos) Amendment 3 Rsi Responses ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21084A2532021-03-24024 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Transfer Application ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1012021-02-26026 February 2021 NRR E-mail Capture - Clarification of Second Round RAI - Clinton TSTF-505 License Amendment Request ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21057A1002021-02-17017 February 2021 NRR E-mail Capture - Second Round RAI - Clinton TSTF-505 License Amendment Request ML21041A5442021-02-10010 February 2021 NRR E-mail Capture - NRC Acceptance Review for Clinton Request for License Amendment to Revise Degraded Voltage Relay Allowable Values (L-2021-LLA-0005) ML21033A8552021-02-0202 February 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request to Expand the Use ASME Codes Cases N-878 and N-880 ML20350B5602020-12-15015 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-582 and TSTF-583-T (EPIDs L-2020-LLA-0253 and L-2020-LLA-0254) 2024-09-06
[Table view] Category:Inspection Plan
MONTHYEARIR 05000461/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2024005) ML24220A2772024-08-0707 August 2024 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000461/2025010 ML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000461/20230062024-02-28028 February 2024 Annual Assessment Letter for Clinton Power Station (Report 05000461/2023006) ML24054A7112024-02-23023 February 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000461/2024011 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information IR 05000461/20220062023-03-0101 March 2023 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2022006) ML23005A0682023-01-0505 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000461/2023010 ML22312A5362022-11-0808 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000461/2023401 IR 05000461/20220052022-08-22022 August 2022 Updated Inspection Plan for Clinton Power Station (Report 05000461/2022005) IR 05000461/20210062022-03-0202 March 2022 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2021006) ML21333A0832021-11-29029 November 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Teams), Inspection Report Report 05000461/202201 IR 05000461/20210052021-09-0101 September 2021 Updated Inspection Plan for Clinton Power Station; Report 05000461/2021005 ML21215A5732021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21076A5112021-03-17017 March 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000461/2021013 ML21071A1882021-03-12012 March 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Clinton Power Station IR 05000461/20200062021-03-0404 March 2021 Annual Assessment Letter for Clinton Power Station Unit 1 (Report 05000461/2020006) ML20329A0662020-11-24024 November 2020 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection IR 05000461/20200052020-09-0101 September 2020 Updated Inspection Plan for Clinton Power Station, Unit 1 (Report 05000461/2020005) ML20183A1932020-06-30030 June 2020 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000461/2020010 IR 05000461/20190062020-03-0303 March 2020 Annual Assessment Letter for Clinton Power Station, (Report 05000461/2019006) IR 05000461/20190052019-08-28028 August 2019 Updated Inspection Plan for Clinton Power Station (Report 05000461/2019005 ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000461/20180062019-03-0404 March 2019 Annual Assessment Letter for Clinton Power Station (Report 05000461/2018006) ML19037A4772019-02-0606 February 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspect at Clinton Power Station ML19003A1912019-01-0303 January 2019 Request for Information for an NRC Triennial Baeline Design Bases Assurance Inspection; Inspection Report 05000461/2019011 IR 05000461/20180052018-08-28028 August 2018 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2018005) ML18088A5662018-03-28028 March 2018 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection 05000461/2018010 IR 05000461/20170062018-03-0202 March 2018 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2017006) ML17333A0782017-11-28028 November 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2018002 IR 05000461/20170052017-08-28028 August 2017 Updated Inspection Plan for Clinton Power Station, Unit 1 and Quarterly Assessment Letter (Report 05000461/2017005) ML17146B2492017-03-31031 March 2017 Inspection Plan for Clinton Power Station for Triennial Fire Protection Baseline Inspection Report 2017 008 ML17076A3382017-03-16016 March 2017 Notification of NRC Baseline Inspection and Request for Information 05000461/2017002 IR 05000461/20160062017-03-0101 March 2017 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2016006) IR 05000461/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2016005) ML16098A3242016-04-0707 April 2016 Information Request to Support Upcoming Temporary Instruction 191 Inspection at Clinton Power Station ML16076A2542016-03-15015 March 2016 Ltr. 03/15/16 Clinton Power Station, Unit 1 - Request for Information for an NRC Triennial Baseline Component Design Bases Inspection; Inspection Report 05000461/2016009 (Jen) ML16076A2462016-03-15015 March 2016 Ltr. 03/15/16 Clinton Power Station - Notification of NRC Inspection and Request for Information (Vlm) IR 05000461/20150062016-03-0202 March 2016 Annual Assessment Letter for Clinton Power Station Unit 1 (Inspection Report 05000461/2015006) IR 05000461/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2015005) IR 05000461/20140012015-03-0404 March 2015 Annual Assessment Letter for Clinton Power Station, Unit 1, (Report 05000461/2014001) ML14245A2362014-09-0202 September 2014 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 ML14177A3812014-06-25025 June 2014 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000451/20130012014-03-0404 March 2014 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000451/2013001) ML13308B1302013-11-0101 November 2013 Ltr 11/1/13 Clinton Fire Protection Request for Information ML13246A2152013-09-0303 September 2013 2013 Clinton Power Station Mid-Cycle Letter Combined IR 05000461/20130082013-07-25025 July 2013 IR 05000461-13-008, May 20 - 24, 2013, June 3 - 7, 2013, and June 17 - 21, 2013, Clinton Power Station, Component Design Bases Inspection (CDBI) IR 05000461/20120012013-03-0404 March 2013 Annual Assessment Letter for Clinton Power Station (Report 05000461/2012001) ML13038A3122013-02-0707 February 2013 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection Report 05000461-13-008 ML12249A4462012-09-0404 September 2012 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 2024-08-07
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24283A1662024-10-23023 October 2024 Enclosure 2 Clinton Audit Summary RCI and RAIs ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24222A4092024-05-0303 May 2024 NRR E-mail Capture - Request for Additional Information Regarding Reactor Water Cleanup (RWCU) Pump Rooms - L-2023-LLA-0118 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information ML23363A0302023-12-29029 December 2023 NRR E-mail Capture - Preliminary RAIs for Clinton Partial Site Release ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23230B1682023-08-18018 August 2023 NRR E-mail Capture - Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (Rais) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications ML23202A0992023-07-24024 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2023004 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22312A5362022-11-0808 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000461/2023401 ML22255A1402022-09-12012 September 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Clinton Power Station ML22173A0382022-06-21021 June 2022 NRR E-mail Capture - Request for Additional Information (RAI) Regarding Clinton License Amendment Request for Secondary Containment Design Basis (L-2022-LLA-0055) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21225A0392021-08-13013 August 2021 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Request to Revise Degraded Voltage Instrumentation Setpoints ML21204A0152021-07-23023 July 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2021004 ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21071A1882021-03-12012 March 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Clinton Power Station ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1012021-02-26026 February 2021 NRR E-mail Capture - Clarification of Second Round RAI - Clinton TSTF-505 License Amendment Request ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21057A1002021-02-17017 February 2021 NRR E-mail Capture - Second Round RAI - Clinton TSTF-505 License Amendment Request ML21026A0582021-01-25025 January 2021 Notification of NRC Supplemental Inspection (95001) and Request for Information ML20315A0642020-11-0909 November 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000461/2021010 ML20307A6592020-10-27027 October 2020 NRR E-mail Capture - Request for Additional Information Regarding TSTF-505 and 50.69 Applications ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20135H1972020-05-14014 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Extend Safety Relief Valve Test Interval ML20128J8642020-05-0707 May 2020 NRR E-mail Capture - Preliminary RAIs for Clinton Load Tap Changer License Amendment Request ML20105A1082020-04-14014 April 2020 NRR E-mail Capture - Request for Additional Information Regarding Clinton Relief Request I4R-01 ML20091F7892020-03-25025 March 2020 NRR E-mail Capture - Request for Additional Information Regarding Clinton Relief Request I4R-05 ML19330E1772019-11-25025 November 2019 RAI Dresden/Clinton Request for LAR to Modify TSs Following Adoption of TSTF-542 ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML18225A2882018-08-13013 August 2018 Ltr. 08/13/18 Clinton Power Station - Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the Environmental Qualification Program Inspection Report 05000461/2018011 (DRS-B.Jose) ML18214A4452018-08-0202 August 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Revised Alternate Source Term ML18193A9732018-07-12012 July 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Revised Alternate Source Term ML18088A5662018-03-28028 March 2018 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection 05000461/2018010 ML17285B1962017-10-27027 October 2017 Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools. ML17276B7632017-10-0303 October 2017 NRR E-mail Capture - Clinton Power Station - Request for Additional Information Regarding License Amendment Request Related to Reactor Pressure Vessel Water Inventory Control ML17159A6292017-06-0707 June 2017 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML17125A3212017-05-0202 May 2017 NRR E-mail Capture - Clinton Power Station, Unit 1 - Request for Additional Information Regarding the Permanent Extension of Leak Rate Testing ML16356A0422016-12-20020 December 2016 Notification of NRC Triennial Fire Protection Baseline Inspection and Request for Information 05000461/2017008 (Dxs) ML16130A6642016-05-11011 May 2016 Request for Additional Information Related to Incorporation of Revised Alternative Source Term (CAC No. MF7336)(RS-16-019) ML16071A2062016-03-15015 March 2016 RAI Regarding License Amendment Request to Revise the Reactor Steam Dome Pressure in Technical Specification 2.1.1, Reactor Core Sls(Cac Nos. MF6640 & MF6644) ML15106A9282015-04-24024 April 2015 Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.2, :Primary Coolant Sources Outside Containment ML15068A4212015-04-16016 April 2015 Request for Additional Information Regarding Relief Request 13R-11 2024-07-12
[Table view] |
Text
From: Nirodh Shah To: Miller, Chelsie A:(Constellation Nuclear); Evans, Natalie A:(Constellation Nuclear)
Cc: Jeffery Steward; Stephanie Liska; Robert Ruiz
Subject:
Request for Information for Clinton Biennial Problem Identification and Resolution Inspection (PIR)
Date: Monday, February 26, 2024 12:12:00 PM Attachments:
Hi Chelsie! As we had discussed earlier, the biennial PI&R inspection will occur between April 8-26, 2024. Besides I, the team members include Stephanie Liska and Jeremy Steward. I have attached the request for information to support the inspection.
Unless otherwise stated, the time frame for the requested materials should be for the period starting January 1, 2022, until February 29, 2024. For requested lists please provide the information, if possible, in a sortable Excel spreadsheet format. Unless otherwise stated, the information request should include all major plant departments (i.e.,
operations, engineering, maintenance, radiation protection, security, and emergency preparedness).
Please provide the information by March 15, 2024, to facilitate the selection of specific items that will be reviewed during the onsite inspection week. If you maintain a remote site (i.e., SharePoint, One Drive, etc.) please upload all documents to that location and provide all team members with access to that site. If you dont maintain a remote site, please mail the information to me in a CD or DVD format.
This e-mail contains voluntary (mandatory) information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB) approved these information collections (approval number 3150-0011). The burden to the public for these information collections is estimated to average 54 hours6.25e-4 days <br />0.015 hours <br />8.928571e-5 weeks <br />2.0547e-5 months <br /> per response. Send comments regarding this information collection to the FOIA, Library and Information Collection Branch, Office of the Chief Information Officer, Mail Stop: T6-A10M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by email to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0011) OMB, Washington, DC 20503.
If you have any questions, please contact me.
ThxN. Shah Senior Project Engineer Reactor Projects Branch 1 Division of Operating Reactor Safety, Region III INFORMATION REQUEST FOR THE CLINTON PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION
(a) PROGRAM DOCUMENTS
- 1. A current copy of administrative procedure(s) for the corrective action program (CAP),
quality assurance (QA) audit program, self-assessment program, corrective action effectiveness review program, trending program, industry operating experience review program, maintenance rule program and top-level documents for the work control programs, work scheduling programs, and aging management program(s).
- 2. A current copy of the Employee Concerns Program (ECP)/Ombudsman administrative procedure(s).
- 3. A copy of the QA manual.
- 4. Description of any substantive changes made to the corrective action program philosophy or operation since the last biennial PI&R Inspection. Please include with each listed substantive change the effective date of the change. Administrative and non-substantive changes do not need to be listed.
(b) CAP EFFECTIVENESSPROBLEM IDENTIFICATION
- 5. OPEN Condition Reports (CRs) - A list of all open CRs sorted by significance level.
Include CR number, the date initiated, a brief description/title, system affected if any, significance level, and anticipated completion date, if available. This list should be grouped by responsible department and listed in order of initiation date (oldest listed first).
- 6. CORPORATE CRs - A list of CRs generated by the corporate office that involve or affect plant operation, sorted by significance level. Include the date initiated, a brief description/title, site(s) affected, system affected, significance/priority level, assigned organization, and status (if closed include date closed; if open, include scheduled date to be closed).
- 7. CR GENERATION - A data table (or similar format) showing the total number of CRs generated per year, sorted by department (i.e., operations, engineering, security etc.)
since 2022.
- 8. EXTERNAL CR NUMBERS - A data table showing the number of issues identified externally (NRC, INPO, other, etc.) per year as compared to internally since 2022.
- 9. PLANT TRANSIENTS - A list of plant trips, unplanned down powers (greater than 20 percent), limiting condition for operation entries (not scheduled), and licensee event reports, including dates of these events.
- 10. CONTROL ROOM DEFICIENCIES - A list of current control room deficiencies and operator work-arounds, sorted by priority, with a brief description/title and corresponding CR and/or work order number.
(c) CAP EFFECTIVENESSPROBLEM PRIORITIZATION AND EVALUATION
- 11. ROOT CAUSES - A list of completed root cause evaluations with a brief description of the issue. Provide status of any actions developed as part of the evaluations. Include a reference, if not part of the root cause package, to the documents and/or CRs directing and tracking the actions.
5
- 12. APPARENT CAUSES - A list of completed apparent cause evaluations with a brief description of the issue. Provide status of any actions developed as part of the evaluations. Include a reference, if not part of the apparent cause package, to the documents and/or CRs directing and tracking the actions.
- 13. CLOSED CRs - A list of closed CRs sorted by significance level and then initiation date.
Include CR number, a brief description/title, the significance level, the date initiated and closed, assigned organization, and system affected.
- 14. OPERABILITY EVALUATIONS - A list of operability evaluations. Include a brief description/title of the issue, date initiated, date closed, or date anticipated to be closed.
Include any operability evaluations that are still open regardless of the date initiated.
- 15. MAINTENANCE RULE - A listing of all systems which were in Maintenance Rule a(1) status since 2022, even if no longer in that status. Include dates when system/components entered (a)(1) status and, if applicable, returned to (a)(2) status.
Provide copies of the applicable system health report sections and maintenance rule action plans for those systems.
- 16. IN SERVICE TESTING (IST) - A list of test failures (IST or Technical Specifications surveillances) with a brief description of component/system failed. Indicate if the failure was a maintenance preventable failure.
- 17. TEMPORARY MODIFICATIONS - A list of temporary modifications with a brief description of the modification, installation date, and date closed or anticipated closure date.
(d) CAP EFFECTIVENESSCORRECTIVE ACTIONS
- 18. OPEN ACTIONS - A list of open corrective actions, sorted by significance/priority level, with a brief description/title, initiating date and due date. The list should include the number of due date extension and be grouped by the responsible department.
- 19. EFFECTIVENESS REVIEWS - A list of completed effectiveness reviews with a brief description of the results. Include a cross -reference to the CRs for which the effectiveness review was conducted and, if applicable, CR numbers documenting any additional follow-up actions.
- 20. INADEQUATE ACTIONS - A list of CRs initiated for inadequate or ineffective corrective actions. Include the date initiated, a brief description/title, significance/priority level, system affected, assigned organization, and status (if closed, include date closed; if open, include scheduled date to be closed). Include a cross-reference to the CR or evaluation that generated the original corrective action.
- 21. REWORK - A list of rework items and repeat failures. Include cross-references to applicable Work Orders and CRs.
- 22. OPEN WORK ORDERS - A list of open work orders/equipment work requests with a brief description. Identify the work order as outage or non-outage, the date of initiation and scheduled or anticipated closure date, if available. If applicable, also provide the classification of the work orders with the recent industry classification scheme. Provide an explanation of the classification scheme and the procedure governing the classification. Work requests/work orders not associated with a degraded equipment condition (e.g., work orders for voluntary plant upgrades) and those associated with routine surveillance activities or preventative maintenance tasks do not have to be included in the list.
5 (e) CAP ASSESSMENT - PROBLEM IDENTIFICATION
- 23. QA AUDITS - A copy of QA audits of the corrective action program.
- 24. PI&R ASSESSMENT - A copy of self-assessments and associated condition reports generated in preparation for this PI&R inspection.
- 25. CAP SELF-ASSESSMENTS - A copy of completed CAP self-assessments and the plan/schedule for future CAP self-assessments.
- 26. CAP PERFORMANCE INDICATORS - A copy of any performance reports or indicators used to track CAP effectiveness for the past 24 months. The most recent data and end-of-quarter data will suffice; monthly reports are not required.
(f) CAP ASSESSMENT - CORRECTIVE ACTIONS
- 27. TREND REPORTS - Copies of any completed trend reports for CRs. Quarterly t rend reports are acceptable; copies of all monthly reports are not required.
- 28. TREND CRs - A list of CRs initiated for trends of conditions adverse to quality. Include the date initiated, a brief description/title, significance/ priority level, and status (if closed include date closed; if open, include scheduled date to be closed).
- 29. WORK ORDER TRENDS - A copy of any trend reports for work orders. The most recent trend reports and those that existed at the end-of-year and middle-of-year are acceptable; copies of monthly reports are not required. Include a copy of a recent (within 2 months of the data submittal) graph or document showing the status of work week planning of work activities.
(g) USE OF OPERATION EXPERIENCE (OP EX)
- 30. OP EX CRs: 1) A list of CRs initiated to evaluate NRC generic communications (e.g.,
bulletins, information notices, generic letters, etc.). 2) A list of CRs initiated to evaluate industry generic communications (industry operating experience, fleet operating experience, etc.). For both lists, include the date the CR was initiated, a brief description/title, and the status (if closed, include date closed; if open, include scheduled date to be closed).
(h) SELF-ASSESSMENT AND AUDITS
- 31. QA AUDITS - A list of all other QA audits completed with a brief description of areas where findings were identified.
- 32. QA AUDIT SCHEDULE - The schedule of future QA audits.
- 33. SELF-ASSESSMENTS - A chronological list of department and site self -assessments completed (include date completed).
- 34. A list of any audit or assessment performed by an outside agency/industry group (excepting the NRC or INPO). Please include the audit no., title and date performed.
- 35. SELF-ASSESSMENT CAPS - A list of CRs written for findings or concerns identified in self-assessments and audits. Include a short description/title of the finding, its status, and include a cross-reference to the audit or self-assessment number.
(i) SAFETY CONSCIOUS WORK ENVIRONMENT
5
- 36. SAFETY CONSCIOUS WORK ENVIRONMENT ASSESSMENTS - Copy of the results of safety culture and/or SCWE surveys or self-assessments. Include any organizational effectiveness surveys conducted by internal or external organizations. Include a listing of any action(s) resulting from the survey(s) and the status of the action(s).
- 37. ECP ISSUES - SCWE issues identified through alternate avenues, such as the employee concerns programs. If issue(s) are considered sensitive, in lieu of describing issue in the data package, provide a paper copy to the lead inspector at the start of the inspection.
(j) REGULATORY ISSUES - REVIEWED FOR ALL ASPECTS OF THE CAP PROGRAM
- 38. NRC FINDING CAPS - A list of CRs for issues (findings, violations, etc.) documented in NRC inspection reports. Include the CR number, brief description/title, date initiated and the status (if closed include date closed; if open, include scheduled date to be closed).
- 39. LICENSE IDENTIFIED VIOLATION CAPS - A list of CRs for licensee identified violations that have been documented in NRC inspection reports. Include the CR number, brief description/title, date initiated and the status (if closed, include date closed; if open, include scheduled date to be closed).
(k) NRC ISSUES CAPS - A list of CRs associated with NRC-identified issues. Include the CR number, brief description/title, date initiated and the status (if closed, include date closed; if open, include scheduled date to be closed).
(l) 5-YEAR REVIEW - Please provide a list of the following CAP items pertaining to the Essential Service Water system for all trains since January 1, 2019. Please sort the information by t rain.
- 40. CONDITION REPORTS - A list of CRs, include the CR number, brief description/title, significance level, level of evaluation (i.e., root cause, apparent cause, common cause, etc.), date initiated, and the status (if closed, include date closed; if open, include scheduled date to be closed).
- 41. OPERATING EXPERIENCE - A list of evaluations conducted on applicable internal and external industry operating experience.
- 42. ASSESSMENTS - a list of key issues being tracked either by the Plant Health Committee, System Health Report, or similar; a summary of maintenance rule scoping classification and performance monitoring criteria; any audits/evaluations performed whether internal or external and a copy of the most recent system health report or similar document.
- 43. List of open/closed operability evaluations (open or closed), ASME code evaluations/repairs; maintenance rule failure evaluations; or Adverse Condition Monitoring plans performed for any of the documented issues.
Please also arrange for the team to have access to the following documents while on site:
- a. Updated Final Safety Analysis Report.
- b. Technical Specifications.
- c. Procedures and procedure index.
- f. A list of the codes used in the CAP and Work Orders system(s).
5 Other:
On the first day of the inspection, or early on the second day, please provide the inspection team a briefing of your CAP including an overview of your actions, if any, associated with recent industry efforts to improve the efficiency of the CAP (e.g., cumulative effects initiative). Include your expectations for personnel using the program and how the work order system fits into the overall scheme for addressing identified issues. Also, please demonstrate how to use a computer to access CAP data.
The lead inspector will also request to talk to/interview plant personnel to seek information about the plants SCWE. The lead inspector will discuss with your staff the protocol and format of the interviews, whether impromptu or scheduled individuals or groups. For this the inspector will need access to organizations charts showing position titles and names.