Category:E-Mail
MONTHYEARML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24222A4092024-05-0303 May 2024 NRR E-mail Capture - Request for Additional Information Regarding Reactor Water Cleanup (RWCU) Pump Rooms - L-2023-LLA-0118 ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information ML23363A0302023-12-29029 December 2023 NRR E-mail Capture - Preliminary RAIs for Clinton Partial Site Release ML23338A0402023-12-0404 December 2023 NRR E-mail Capture - Ready for Clean TS Pages and Updated Review Hours for Clinton Power Station, Unit 1, Request for License Amendment to Revise Technical Specifications Section 3.8.3 ML23268A0022023-09-22022 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-264-A, Revision 0 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML23261A0032023-09-15015 September 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Amendment Request to Revise Timing of Reactor Water Cleanup Isolation Valves ML23230B1682023-08-18018 August 2023 NRR E-mail Capture - Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (Rais) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications ML23219A2142023-08-0404 August 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Request for Partial Site Release ML23194A1102023-07-13013 July 2023 NRR E-mail Capture - Non-acceptance of Clinton Request for Partial Site Release ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML23087A0122023-03-28028 March 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Revise Technical Specifications 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air (L-2023-LLA-0034) ML23033A0332023-02-0101 February 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Adopt TSTF-332 (L-2023-LLA-0007) ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22301A0902022-10-28028 October 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-301, Revision 2 ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22173A0382022-06-21021 June 2022 NRR E-mail Capture - Request for Additional Information (RAI) Regarding Clinton License Amendment Request for Secondary Containment Design Basis (L-2022-LLA-0055) ML22165A1902022-06-14014 June 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton Request to Adopt TSTF-230 (L-2022-LLA-0076) ML22165A1912022-06-14014 June 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton Request to Adopt TSTF-269 (L-2022-LLA-0077) ML23089A0182022-05-24024 May 2022 NRR E-mail Capture - Clinton Power Station Acceptance Review Results - Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan ML22116A0422022-04-26026 April 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Revise Secondary Containment Design Basis ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22157A3872022-01-28028 January 2022 Post Exam Submittal Letter Clinton 22 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21252A0482021-09-0707 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21252A0042021-08-26026 August 2021 NRR E-mail Capture - NRC Acceptance Review - Braidwood/Byron/Clinton - Adoption of TSTF-273, Safety Function Determination Program Clarifications ML21225A0392021-08-13013 August 2021 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Request to Revise Degraded Voltage Instrumentation Setpoints ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21203A3062021-07-21021 July 2021 NRR E-mail Capture - NRC Acceptance Review - Clinton - Third Inservice Inspection Interval Relief Request I3R-18 ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21182A0722021-06-29029 June 2021 SUNSI and Proprietary Review Determination Email Regarding: Tn CoC 1042 (Eos) Amendment 3 Rsi Responses ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21084A2532021-03-24024 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Transfer Application ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1012021-02-26026 February 2021 NRR E-mail Capture - Clarification of Second Round RAI - Clinton TSTF-505 License Amendment Request ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21057A1002021-02-17017 February 2021 NRR E-mail Capture - Second Round RAI - Clinton TSTF-505 License Amendment Request ML21041A5442021-02-10010 February 2021 NRR E-mail Capture - NRC Acceptance Review for Clinton Request for License Amendment to Revise Degraded Voltage Relay Allowable Values (L-2021-LLA-0005) ML21033A8552021-02-0202 February 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request to Expand the Use ASME Codes Cases N-878 and N-880 ML20350B5602020-12-15015 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-582 and TSTF-583-T (EPIDs L-2020-LLA-0253 and L-2020-LLA-0254) 2024-09-06
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24283A1662024-10-23023 October 2024 Enclosure 2 Clinton Audit Summary RCI and RAIs ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24222A4092024-05-0303 May 2024 NRR E-mail Capture - Request for Additional Information Regarding Reactor Water Cleanup (RWCU) Pump Rooms - L-2023-LLA-0118 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information ML23363A0302023-12-29029 December 2023 NRR E-mail Capture - Preliminary RAIs for Clinton Partial Site Release ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML23230B1682023-08-18018 August 2023 NRR E-mail Capture - Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (Rais) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications ML23202A0992023-07-24024 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2023004 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000461/20234012022-11-0808 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000461/2023401 ML22255A1402022-09-12012 September 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Clinton Power Station ML22173A0382022-06-21021 June 2022 NRR E-mail Capture - Request for Additional Information (RAI) Regarding Clinton License Amendment Request for Secondary Containment Design Basis (L-2022-LLA-0055) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21225A0392021-08-13013 August 2021 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Request to Revise Degraded Voltage Instrumentation Setpoints ML21204A0152021-07-23023 July 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2021004 ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21071A1882021-03-12012 March 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Clinton Power Station ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1012021-02-26026 February 2021 NRR E-mail Capture - Clarification of Second Round RAI - Clinton TSTF-505 License Amendment Request ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21057A1002021-02-17017 February 2021 NRR E-mail Capture - Second Round RAI - Clinton TSTF-505 License Amendment Request ML21026A0582021-01-25025 January 2021 Notification of NRC Supplemental Inspection (95001) and Request for Information ML20315A0642020-11-0909 November 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000461/2021010 ML20307A6592020-10-27027 October 2020 NRR E-mail Capture - Request for Additional Information Regarding TSTF-505 and 50.69 Applications ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20135H1972020-05-14014 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Extend Safety Relief Valve Test Interval ML20128J8642020-05-0707 May 2020 NRR E-mail Capture - Preliminary RAIs for Clinton Load Tap Changer License Amendment Request ML20105A1082020-04-14014 April 2020 NRR E-mail Capture - Request for Additional Information Regarding Clinton Relief Request I4R-01 ML20091F7892020-03-25025 March 2020 NRR E-mail Capture - Request for Additional Information Regarding Clinton Relief Request I4R-05 ML19330E1772019-11-25025 November 2019 RAI Dresden/Clinton Request for LAR to Modify TSs Following Adoption of TSTF-542 ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML18225A2882018-08-13013 August 2018 Ltr. 08/13/18 Clinton Power Station - Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the Environmental Qualification Program Inspection Report 05000461/2018011 (DRS-B.Jose) ML18214A4452018-08-0202 August 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Revised Alternate Source Term ML18193A9732018-07-12012 July 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Clinton Revised Alternate Source Term ML18088A5662018-03-28028 March 2018 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection 05000461/2018010 ML17285B1962017-10-27027 October 2017 Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools. ML17276B7632017-10-0303 October 2017 NRR E-mail Capture - Clinton Power Station - Request for Additional Information Regarding License Amendment Request Related to Reactor Pressure Vessel Water Inventory Control ML17159A6292017-06-0707 June 2017 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML17125A3212017-05-0202 May 2017 NRR E-mail Capture - Clinton Power Station, Unit 1 - Request for Additional Information Regarding the Permanent Extension of Leak Rate Testing ML16356A0422016-12-20020 December 2016 Notification of NRC Triennial Fire Protection Baseline Inspection and Request for Information 05000461/2017008 (Dxs) ML16130A6642016-05-11011 May 2016 Request for Additional Information Related to Incorporation of Revised Alternative Source Term (CAC No. MF7336)(RS-16-019) ML16071A2062016-03-15015 March 2016 RAI Regarding License Amendment Request to Revise the Reactor Steam Dome Pressure in Technical Specification 2.1.1, Reactor Core Sls(Cac Nos. MF6640 & MF6644) ML15106A9282015-04-24024 April 2015 Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.2, :Primary Coolant Sources Outside Containment ML15068A4212015-04-16016 April 2015 Request for Additional Information Regarding Relief Request 13R-11 2024-07-12
[Table view] |
Text
From:
Joel Wiebe Sent:
Friday, August 18, 2023 1:03 PM To:
Nicely, Ken M.:(Exelon Nuclear)
Subject:
Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (RAIs) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications Hi Ken, We would like to have a clarification call regarding these RAIs within a week of this email. The purpose of providing preliminary RAIs is to ensure the NRC staff has clearly identified the information it needs to complete its review of the amendment request.
Joel REQUEST FOR ADDITIONAL INFORMATION RELATED TO DG AIR START SYSTEM AMENDMENT REQUEST CONSTELLATION ENERGY GENERATION CLINTON POWER STATION, UNIT 1 DOCKET NOS. 50-461 By application dated March 1, 2023 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML23060A258), Constellation Energy Generation (the licensee) submitted a license amendment request (LAR) for the Clinton Power Station, Unit 1 to modify Technical Specifications (TS) Section 3.8.3, "Diesel Fuel Oil, Lube Oil, and Starting Air," to delete Condition E that allows a required Diesel Generator (DG) to be considered operable with reduced starting air capability and to clarify that only one air start receiver with adequate pressure is required for the associated starting air system to be considered operable. In addition, Condition F is revised to reflect the deletion of Condition E.
General Design Criterion (GDC) 17, "Electric power systems," of Appendix A, "General Design Criteria for Nuclear Power Plants," to 10 CFR 50 requires, in part, that nuclear power plants have onsite and offsite electric power systems to permit the functioning of structures, systems, and components (SSCs) that are important to safety. The onsite system is required to have sufficient independence, redundancy, and testability to perform its safety function, assuming a single failure.
SRP 9.5.6 EMERGENCY DIESEL ENGINE STARTING SYSTEM acceptance criteria invoke GDC 17 as it relates to the capability of the diesel engine air starting system to meet independence and redundancy criteria.
RAI 1
The licensee requests changing Surveillance Requirement (SR) 3.8.3.4 from Verify each required DG air start receiver pressure is 200 psig to Verify each air start pressure is 200 psig. As indicated in the LAR, each DG has an air start system with adequate capacity for five successive start attempts of the DG without recharging the air start receiver(s).
The intent of air starting system SR 3.8.3.4 is contained in NUREG-1434 (Standard Technical Specifications (STS)) which reads in part, This Surveillance ensures that, without the aid of the refill compressor, sufficient air start capacity for each DG is available. The system design requirements provide for a minimum of five engine start cycles without recharging. The proposed change removes the pressurized requirement for the individual receiver and requires the overall system to remain above the pressure required for five starts (200 psig). With the SR revised as proposed, both receivers will not be required to meet the five-start requirement and could meet TS requirements with only one receiver operable.
Section 9.5.6.1.1 of Clintons Final Safety Analysis Report (FSAR) states, The diesel-generator starting systems for the Divisions I, II, and III diesel engines are independent and redundant for each division. Each diesel generator starting system consists of two full capacity air starting subsystems. Each
subsystem has a rated capacity capable of starting its respective engine set five times without recharging the associated air receiver. The rated air capacity of each subsystem is 93 ft.3 at 250 psig for the Division I and II DGs and 64 ft.3 at 240 psig for the Division III DG. All three DGs are capable of multiple successive starts without recharging the air receiver tank when the air receiver pressure is below the rated air pressure but above 200 psig.
The staff understands the terminology of diesel generator air starting system contained in FSAR Section 9.5.6.1.1 to represent the overall air start system (containing 2 receivers) suppling its respective DG (Div I, II, or III). Additionally, each diesel generator air starting system consists of two redundant air starting subsystems. The FSAR indicates each subsystem has a rated capacity for starting its respective engine set five times.
The staff requests that the licensee:
- 1. Provide a description of what components define the system and sub-system and their operability requirements with the proposed TS changes.
- 2. Describe how the system is normally aligned for the DG for the Divisions I, II, and III.
Also, define independence and redundancy within each division containing full capacity subsystems/systems and how the TS change impacts redundancy, as defined in FSAR 9.5.6.
RAI 2
The DG air start system safety function is to assure reliable starting of the emergency diesel engines in the event of a loss of offsite power. SRP 9.5.6 states the consequences of a single active failure in a starting air system will not lead to a loss of more than one diesel generator. Consistent with SRP criteria, FSAR Section 9.5.6.1.1.c indicates A failure of a single active or passive component for one division will not prevent another division from performing its intended function.
GDC 17 requires the onsite electric power supplies, including the batteries, and the onsite electric distribution system, shall have sufficient independence, redundancy, and testability to perform their safety functions assuming a single failure.
SRP 9.5.6 further indicates Piping interconnections between the dedicated air start systems are reviewed for whether a failure in the interconnecting piping could lead to the loss of starting for more than one diesel engine.
The staff requests that the licensee confirm that failure of single receiver will not result in multiple DGs being inoperable.
RAI 3
GDC 17 requires the onsite electric power supplies, including the batteries, and the onsite electric distribution system, shall have sufficient independence, redundancy, and testability to perform their safety functions assuming a single failure. Specific criteria and guidance necessary to meet GDC 17 requirements are indicated in Section 9.5.6 of NUREG-0800 (Standard Review Plan (SRP))
as follows: C. As a minimum, the air starting system should be capable of cranking a cold diesel engine five times without recharging the receiver(s). The air starting system capacity should be determined as follows: (i) each cranking cycle duration should be approximately three seconds, (ii) consist of two to three engine revolutions, or (iii) air start requirements per engine start provided by the engine manufacturer, whichever air start requirement is larger.
Current SR 3.8.3.4 requires that EDG starting air receiver pressure be maintained greater than or equal to 200 psig. This value is based on capacity as defined in FSAR Section 9.5.6.1.1 which specifies Each subsystem has a rated capacity capable of starting its respective engine set five times without recharging the associated air receiver.
Current TS 3.8.3 allows operating for 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> when pressure requirements are met for only one of the two starting air receivers. That is, up to 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> is allowed to restore the pressure of the DG receiver prior to declaring the DG inoperable. TS 3.8.3 further requires receiver pressure remain greater than 140 psig. NUREG-1434 defines lower specified pressure as allowance for
an extension of 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> prior to having to declare the EDG inoperable based on the assessment that the minimum pressure will be sufficient for a reliable start with one attempt.
The licensees basis for current TS criteria is defined in the Bases for TS 3.8.3 (Condition E) as, With the required starting air receiver pressure < 200 psig, sufficient capacity for multiple DG start attempts may not exist. However, as long as the receiver pressure is 140 psig, there is adequate capacity for at least one start attempt, and the DG can be considered OPERABLE while the air receiver pressure is restored to the required limit. A period of 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> is considered sufficient to complete restoration to the required pressure prior to declaring the DG inoperable. This period is acceptable based on the remaining air start capacity, the fact that most DG starts are accomplished on the first attempt, and the low probability of an event during this brief period.
The licensee proposed to delete Condition E that allows a required DG to be considered operable with reduced starting air capability. The LAR indicates This determination was made because the capability of one successful start attempt cannot be assured when starting air receiver pressure falls to the lower limit of 140 psig. With the proposed change, licensee removes the ability to consider the impacted DG operable with a minimum TS pressure requirement ensuring one start. As a result, overall air starting system pressure falling below the 200 psig SR requirement results in immediate entry into LCO 3.8.1 and declaring the impacted DG inoperable.
The NRC staff requests that the licensee confirm that the system meets the 5-start criteria (12 second fast start) with air receiver pressure at the proposed SR 200 psig and how the pressure is defined, calculated, tested, and monitored.
Hearing Identifier:
NRR_DRMA Email Number:
2207 Mail Envelope Properties (MN2PR09MB497194C97AEA6F0C668340988B1BA)
Subject:
Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (RAIs) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications Sent Date:
8/18/2023 1:03:28 PM Received Date:
8/18/2023 1:03:00 PM From:
Joel Wiebe Created By:
Joel.Wiebe@nrc.gov Recipients:
"Nicely, Ken M.:(Exelon Nuclear)" <ken.nicely@constellation.com>
Tracking Status: None Post Office:
MN2PR09MB4971.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 9238 8/18/2023 1:03:00 PM Options Priority:
Normal Return Notification:
No Reply Requested:
No Sensitivity: