ML13120A181

From kanterella
Revision as of 20:07, 4 November 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
IR 05000454-13-002 and 05000455-13-002; Exelon Generation Company, LLC; 01/01/2013 - 03/31/2013; Byron Station, Units 1 & 2, Identification and Resolution of Problems Other Activities
ML13120A181
Person / Time
Site: Byron  Constellation icon.png
Issue date: 04/29/2013
From: Eric Duncan
Region 3 Branch 3
To: Pacilio M
Exelon Generation Co, Exelon Nuclear
References
IR-13-002
Download: ML13120A181 (37)


See also: IR 05000454/2013002

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210

LISLE, IL 60532-4352

April 29, 2013

Mr. Michael J. Pacilio

Senior Vice President, Exelon Generation Company, LLC

President and Chief Nuclear Officer (CNO), Exelon Nuclear

4300 Warrenville Road

Warrenville, IL 60555

SUBJECT: BYRON STATION, UNITS 1 AND 2, NRC INTEGRATED INSPECTION

REPORT 05000454/2013002; 05000455/2013002

Dear Mr. Pacilio:

On March 31, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an integrated

inspection at your Byron Station, Units 1 and 2. The enclosed inspection report documents the

inspection results which were discussed on April 4, 2013, with Mr. B. Youman and other

members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

Two NRC-identified findings of very low safety significance (Green) were identified during this

inspection. One of these findings was determined to involve a violation of NRC requirements.

However, because of its very low safety significance, and because the issue was entered into

your corrective action program, the NRC is treating this violation as a non-cited violation (NCV)

in accordance with Section 2.3.2 of the NRC Enforcement Policy.

If you contest this NCV, you should provide a response within 30 days of the date of this

inspection report, with the basis for your denial, to the Nuclear Regulatory Commission,

ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director,

Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-

0001; and the NRC Resident Inspector at the Byron Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the Regional Administrator, Region III, and the NRC Resident Inspector

at the Byron Station.

M. Pacilio -2-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Eric R. Duncan, Chief

Branch 3

Division of Reactor Projects

Docket Nos. 50-454, 50-455

License Nos. NPF-37, NPF-66

Enclosure: Inspection Report 05000454/2013002 and 05000455/2013002

w/Attachment: Supplemental Information

cc w/encl: Distribution via ListServ

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket Nos: 50-454; 50-455

License Nos: NPF-37; NPF-66

Report No: 05000454/2013002; 05000455/2013002

Licensee: Exelon Generation Company, LLC

Facility: Byron Station, Units 1 and 2

Location: Byron, IL

Dates: January 1 through March 31, 2013

Inspectors: B. Bartlett, Senior Resident Inspector

J. Robbins, Resident Inspector

J. Bozga, Reactor Inspector

V. Meyers, Health Physicist

V. Meghani, Reactor Inspector

T. Daun, Reactor Engineer

R. Ng, Project Engineer

C. Thompson, Resident Inspector, Illinois Emergency

Management Agency

Approved by: E. Duncan, Chief

Branch 3

Division of Reactor Projects

Enclosure

TABLE OF CONTENTS

SUMMARY OF FINDINGS ......................................................................................................... 1

REPORT DETAILS .................................................................................................................... 3

Summary of Plant Status ........................................................................................................ 3

1. REACTOR SAFETY .................................................................................................... 3

1R01 Adverse Weather Protection (71111.01)............................................................ 3

1R04 Equipment Alignment (71111.04) ...................................................................... 4

1R05 Fire Protection (71111.05) ................................................................................. 4

1R06 Flooding (71111.06) .......................................................................................... 5

1R11 Licensed Operator Requalification Program (71111.11) .................................... 6

1R12 Maintenance Effectiveness (71111.12).............................................................. 7

1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13) ......... 8

1R15 Operability Evaluations (71111.15) .................................................................... 8

1R18 Plant Modifications (71111.18) .......................................................................... 9

1R19 Post-Maintenance Testing (71111.19) ..............................................................10

1R20 Outage Activities (71111.20) ............................................................................11

1R22 Surveillance Testing (71111.22) .......................................................................12

1EP6 Drill Evaluation (71114.06) ...............................................................................13

2. RADIATION SAFETY .................................................................................................14

2RS4 Occupational Dose Assessment (71124.04) .....................................................14

4. OTHER ACTIVITIES ...................................................................................................14

4OA1 Performance Indicator Verification (71151).......................................................14

4OA2 Identification and Resolution of Problems (71152)............................................16

4OA5 Other Activities .................................................................................................20

4OA6 Management Meetings .....................................................................................23

SUPPLEMENTAL INFORMATION............................................................................................. 1

Key Points of Contact ............................................................................................................. 1

List of Items Opened, Closed, and Discussed ........................................................................ 2

List of Documents Reviewed .................................................................................................. 3

List of Acronymns Use ............................................................................................................ 7

Enclosure

SUMMARY OF FINDINGS

Inspection Report (IR) 05000454/2013002 and 05000455/2013002; 01/01/2013 - 03/31/2013;

Byron Station, Units 1 & 2; Identification and Resolution of Problems; Other Activities.

This report covers a 3-month period of inspection by resident inspectors and announced

baseline inspections by regional inspectors. Based on the results of this inspection, two NRC-

identified findings of very low safety significance (Green) were identified. One of these findings

had an associated Non-Cited Violation (NCV) of NRC regulations. The significance of

inspection findings is indicated by their color (Greater than Green, or Green, White, Yellow,

Red) and determined using Inspection Manual Chapter (IMC) 0609, Significance Determination

Process (SDP) dated June 2, 2011. Cross-cutting aspects are determined using IMC 0310,

Components Within the Cross-Cutting Areas, dated October 28, 2011. All violations of NRC

requirements are dispositioned in accordance with the NRCs Enforcement Policy dated

January 28, 2013. The NRCs program for overseeing the safe operation of commercial nuclear

power reactors is described in NUREG-1649, Reactor Oversight Process (ROP), Revision 4.

A. NRC-Identified and Self-Revealed Finding

Cornerstone: Mitigating Systems

  • Green. The inspectors identified a finding of very low safety significance (Green) and an

associated NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, when

licensee personnel failed to properly evaluate the structural steel embedment plate

which supported Safety Injection (SI) pipe supports 1SI06025V and 1SI06030S.

Specifically, the licensee failed to demonstrate compliance with the American Institute of

Steel Construction (AISC) and Seismic Category I linear elastic requirements. The

licensee entered this issue into their corrective action program (CAP) as Issue Report

(IR) 1478188. As part of their immediate corrective actions, the licensee performed an

operability evaluation and concluded the structural steel embedment plate was operable,

but nonconforming.

The inspectors determined that the performance deficiency was more than minor

because it was associated with the Design Control attribute of the Mitigating Systems

Cornerstone and adversely affected the cornerstone objective of ensuring the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences (i.e., core damage). Specifically, the licensee failed

to demonstrate compliance with AISC and Seismic Category I linear elastic requirements

to ensure the structural steel embedment plate would maintain structural integrity when

subjected to a design basis load. The inspectors determined that because the finding

did not result in a loss of operability or functionality, the finding was of very low safety

significance (Green). This finding did not have a cross-cutting aspect as it was not

indicative of current performance. (Section 4OA2.3)

  • Green. The inspectors identified a finding of very low safety significance (Green) when

licensee personnel failed to develop inspection lists that included all external flood

protection features credited in current licensing bases (CLB) documents as specified in

Nuclear Energy Institute (NEI) 12-07, Guidelines for Performing Walkdowns of Plant

Flood Protection Features. Specifically, concrete flood barriers in the fuel handling

building (FHB) that protected safety-related equipment in the auxiliary building and flood

barriers for the spent fuel pool cooling pumps were not included in the licensees

1 Enclosure

flooding inspection lists, although these passive components were a critical element of

the licensees flood mitigation strategy. The licensee entered this issue into their CAP

as IR 1466355. Corrective actions included plans to perform an inspection of the NRC-

identified features that were omitted from the inspection lists and an extent-of-condition

review.

The inspectors determined that the performance deficiency was more than minor

because it was associated with the Protection Against External Factors (Flood Hazard)

attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone

objective of ensuring the availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences (i.e., core damage). Because the

finding did not involve the loss or degradation of equipment or function specifically

designed to mitigate a seismic, flooding, or severe weather initiating event (e.g., seismic

snubbers, flooding barriers, tornado doors), the finding was of very low safety

significance (Green). This finding had a cross-cutting aspect in the Work Practices

component of the Human Performance cross-cutting area because licensee personnel

failed to properly apply human error prevention techniques such as peer checking and

proper documentation of activities H.4(a). (Section 4OA5.2)

B. Licensee-Identified Violations

None.

2 Enclosure

REPORT DETAILS

Summary of Plant Status

Unit 1 operated at or near full power throughout the inspection period.

Unit 2 operated at or near full power throughout most of the inspection period. On

March 20, 2013, at approximately 7:51 p.m., the Unit 2 reactor was manually tripped when the

only available generator stator cooling water pump failed. All equipment operated as expected

with a few minor exceptions. Unit 2 returned to full power operation on March 25, 2013, after

the pump was repaired and returned to service.

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity and

Emergency Preparedness

1R01 Adverse Weather Protection (71111.01)

.1 External Flooding

a. Inspection Scope

The inspectors evaluated the design, material condition, and procedures for coping with

the design bases probable maximum flood. The evaluation included a review to check

for deviations from the descriptions provided in the Updated Final Safety Analysis Report

(UFSAR) for features intended to mitigate the potential for flooding from external factors.

As part of this evaluation, the inspectors checked for obstructions that could prevent

draining, checked that the roofs did not contain obvious loose items that could clog

drains in the event of heavy precipitation, and determined whether barriers required to

mitigate flooding were in place and operable. Additionally, the inspectors performed a

walkdown of the protected area to identify any modification to the site which could inhibit

site drainage during a probable maximum precipitation event or allow water ingress past

a flood barrier. The inspectors also walked down underground bunkers/manholes

subject to flooding that contained multiple trains or multiple function risk-significant

cables. The inspectors also reviewed the abnormal operating procedure for mitigating

the design bases flood to ensure it could be implemented as written. Specific areas

inspected included the Unit 1 emergency diesel generators, main steam tunnels, and the

fuel handling building (FHB).

This inspection constituted one external flooding sample as defined in Inspection

Procedure (IP) 71111.01-05.

b. Findings

Findings identified during this inspection are documented in Section 4OA5, Other

Activities.

3 Enclosure

1R04 Equipment Alignment (71111.04)

.1 Quarterly Partial System Walkdowns

a. Inspection Scope

The inspectors performed partial system walkdowns of the following risk-significant

systems:

  • Unit Common Train A Control Room Chiller with Train B Control Room Chiller

Out of Service for Maintenance;

  • Unit 2 Instrument Inverter 212 with Instrument Inverter 214 Out of Service for

Maintenance; and

Service for Maintenance.

The inspectors selected these systems based on their risk significance relative to the

Reactor Safety Cornerstones at the time they were inspected. The inspectors attempted

to identify any discrepancies that could impact the function of the system and therefore

potentially increase risk. The inspectors reviewed applicable operating procedures,

system diagrams, the UFSAR, Technical Specification (TS) requirements, outstanding

work orders (WOs), issue reports (IRs), and the impact of ongoing work activities on

redundant trains of equipment in order to identify conditions that could have rendered

the systems incapable of performing their intended function(s). The inspectors also

walked down accessible portions of the systems to verify system components and

support equipment were aligned correctly and operable. The inspectors examined the

material condition of the components and observed operating parameters of equipment

to verify that there were no obvious deficiencies. The inspectors also verified that the

licensee had properly identified and resolved equipment alignment problems that could

cause initiating events or impact the capability of mitigating systems or barriers and

entered them into the corrective action program (CAP) with the appropriate significance

characterization. Documents reviewed are listed in the Attachment.

This inspection constituted three partial system walkdown samples as defined in

IP 71111.04-05.

b. Findings

No findings were identified.

1R05 Fire Protection (71111.05)

.1 Routine Resident Inspector Tours (71111.05Q)

a. Inspection Scope

The inspectors conducted fire protection walkdowns which were focused on the

availability, accessibility, and the condition of firefighting equipment in the following

risk-significant plant areas:

4 Enclosure

  • Division 11 Miscellaneous Electrical Equipment and Battery Room Fire

Area 5.6-1;

  • Division 21 Miscellaneous Electrical Equipment and Battery Room Fire

Area 5.6-2;

  • Division 12 Miscellaneous Electrical Equipment and Battery Room Fire

Area 5.4-1; and

  • Division 22 Miscellaneous Electrical Equipment and Battery Room Fire

Area 5.4-2.

The inspectors reviewed areas to assess if the licensee had implemented a fire

protection program that adequately controlled combustibles and ignition sources within

the plant; effectively maintained fire detection and suppression capability; maintained

passive fire protection features in good material condition; and implemented adequate

compensatory measures for out-of-service, degraded or inoperable fire protection

equipment, systems, or features in accordance with the licensees fire plan. The

inspectors selected fire areas based on their overall contribution to internal fire risk as

documented in the plants Individual Plant Examination of External Events with later

additional insights, their potential to impact equipment which could initiate or mitigate a

plant transient, or their impact on the plants ability to respond to a security event. Using

the documents listed in the Attachment, the inspectors verified that fire hoses and

extinguishers were in their designated locations and available for immediate use; that

fire detectors and sprinklers were unobstructed; that transient material loading was

within the analyzed limits; and fire doors, dampers, and penetration seals appeared to

be in satisfactory condition. The inspectors also verified that minor issues identified

during the inspection were entered into the licensees CAP.

This inspection constituted four quarterly fire protection inspection samples as defined in

IP 71111.05-05.

b. Findings

No findings were identified

1R06 Flooding (71111.06)

.1 Internal Flooding

a. Inspection Scope

The inspectors reviewed selected risk important plant design features and licensee

procedures intended to protect the plant and its safety-related equipment from internal

flooding events. The inspectors reviewed flood analyses and design documents,

including the UFSAR, engineering calculations, and abnormal operating procedures to

identify licensee commitments. In addition, the inspectors reviewed licensee drawings to

identify areas and equipment that may be affected by internal flooding caused by the

failure or misalignment of nearby sources of water, such as the fire suppression or the

circulating water systems. The inspectors also reviewed the licensees corrective action

documents with respect to past flood-related items identified in the CAP to verify the

adequacy of the corrective actions. The inspectors performed a walkdown of the

following plant areas to assess the adequacy of watertight doors and verify drains and

5 Enclosure

sumps were clear of debris and were operable, and that the licensee complied with

existing commitments:

  • Unit 1 and Unit 2 SX Pump Rooms

Documents reviewed are listed in the Attachment. This inspection constituted one

internal flooding sample as defined in IP 71111.06-05.

b. Findings

No findings were identified.

1R11 Licensed Operator Requalification Program (71111.11)

.1 Resident Inspector Quarterly Review (71111.11Q)

a. Inspection Scope

On January 31, 2013, the inspectors observed a crew of licensed operators in the plant

simulator during licensed operator requalification examinations to verify that operator

performance was adequate, evaluators were identifying and documenting crew

performance problems, and training was being conducted in accordance with licensee

procedures. The inspectors evaluated the following areas:

  • licensed operator performance;
  • crews clarity and formality of communications;
  • ability to take timely actions in the conservative direction;
  • prioritization, interpretation, and verification of annunciator alarms;
  • correct use and implementation of abnormal and emergency procedures;
  • control board manipulations;
  • oversight and direction from supervisors; and
  • ability to identify and implement appropriate TS actions and Emergency Plan

actions and notifications.

The crews performance in these areas was compared to pre-established operator action

expectations, procedural compliance, and successful critical task completion

requirements. Documents reviewed are listed in the Attachment.

In addition, the inspectors observed licensed operator performance in the actual plant

and the main control room during this calendar quarter.

This inspection constituted one quarterly licensed operator requalification program

sample as defined in IP 71111.11-05.

b. Findings

No findings were identified.

6 Enclosure

.2 Resident Inspector Quarterly Observation of Heightened Activity or Risk (71111.11Q)

On March 12, 2013, the inspectors observed control room operators during the

emergent failure of Unit 1 core exit thermocouple 50, and on March 22, 2013, the

inspectors observed plant startup following the Unit 2 forced outage. These were

activities that required heightened awareness and was related to increased risk.

The inspectors evaluated the following areas:

  • licensed operator performance;
  • crews clarity and formality of communications;
  • ability to take timely actions in the conservative direction;
  • prioritization, interpretation, and verification of annunciator alarms;
  • correct use and implementation of procedures;
  • control board manipulations;
  • oversight and direction from supervisors; and
  • ability to identify and implement appropriate TS actions and Emergency Plan

actions and notifications.

The crews performance in these areas was compared to pre-established operator action

expectations, procedural compliance, and successful critical task completion

requirements. Documents reviewed are listed in the Attachment.

This inspection constituted one quarterly licensed operator heightened activity/risk

sample as defined in IP 71111.11-05.

b. Findings

No findings were identified.

1R12 Maintenance Effectiveness (71111.12)

.1 Routine Quarterly Evaluations (71111.12Q)

a. Inspection Scope

The inspectors evaluated degraded performance issues involving the following

risk-significant systems:

  • Failure of Unit 1 Power Range Channel N43; and
  • Review of Maintenance Rule Assessment for the Period of January 2011 to

June 2012.

The inspectors assessed performance issues with respect to the reliability, availability,

and condition monitoring of the system. In addition, the inspectors verified maintenance

effectiveness issues were entered into the CAP with the appropriate significance

characterization. Documents reviewed are listed in the Attachment.

This inspection constituted two quarterly maintenance effectiveness samples as defined

in IP 71111.12-05.

7 Enclosure

b. Findings

No findings were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)

.1 Maintenance Risk Assessments and Emergent Work Control

a. Inspection Scope

The inspectors reviewed the licensee's evaluation and management of plant risk for the

maintenance and emergent work activities affecting risk-significant and safety-related

equipment listed below to verify that the appropriate risk assessments were performed

prior to removing equipment for work:

  • Unit 2 Train A Charging Pump Emergent Failure with the Unit 1 Train A SX

Pump Out of Service for Planned Maintenance;

  • Unit 1 Power Range Channel N43 Emergent Failure with Unit 2 Train B SX

Inoperable for Planned Maintenance; and

These activities were selected based on their potential risk significance relative to the

Reactor Safety Cornerstones. As applicable for each activity, the inspectors verified that

risk assessments were performed as required by 10 CFR 50.65(a)(4) and were accurate

and complete. When emergent work was performed, the inspectors verified that plant

risk was promptly reassessed and managed. The inspectors reviewed the scope of

maintenance work, discussed the results of the assessment with the licensee's

probabilistic risk analyst or shift technical advisor, and verified plant conditions were

consistent with the risk assessment. The inspectors also reviewed TS requirements and

walked down portions of redundant safety systems, when applicable, to verify risk

analysis assumptions were valid and applicable requirements were met.

This inspection constituted three maintenance risk assessments and emergent work

control samples as defined in IP 71111.13-05.

b. Findings

No findings were identified.

1R15 Operability Evaluations (71111.15)

.1 Operability Evaluations

a. Inspection Scope

The inspectors reviewed the following issues:

  • Unit 1 Division 111 Battery Racks Support Questions;

During Natural Circulation Cooldown;

8 Enclosure

  • Operation of SX Pump with Single Cubical Cooler; and

The inspectors selected these potential operability issues based on the risk significance

of the associated components and systems. The inspectors evaluated the technical

adequacy of the evaluations to ensure that TS operability was properly justified and the

subject component or system remained available such that no unrecognized increase in

risk occurred. The inspectors compared the operability and design criteria in the

appropriate sections of the TS and UFSAR to the licensees evaluations to determine

whether the components or systems were operable. Where compensatory measures

were required to maintain operability, the inspectors determined whether the measures

in place would function as intended and were properly controlled. The inspectors

determined, where appropriate, compliance with bounding limitations associated with the

evaluations. Additionally, the inspectors reviewed a sample of corrective action

documents to verify that the licensee was identifying and correcting any deficiencies

associated with operability evaluations. Documents reviewed are listed in the

Attachment.

This inspection constituted four operability inspection samples as defined in

IP 71111.15-05.

b. Findings

No findings were identified.

1R18 Plant Modifications (71111.18)

.1 Plant Modifications

a. Inspection Scope

The inspectors reviewed the following modification:

  • Reactor Containment Fan Cooler (RCFC) Check Dampers Closure Spring

Changes

The inspectors reviewed the configuration changes and associated 10 CFR 50.59 safety

evaluation screening against the design basis, the UFSAR, and the TS, as applicable, to

verify that the modification did not affect the operability or availability of the affected

system. The inspectors, as applicable, observed ongoing and completed work activities

to ensure that the modifications were installed as directed and consistent with the design

control documents; the modifications operated as expected; post-modification testing

adequately demonstrated continued system operability, availability, and reliability; and

that operation of the modifications did not impact the operability of any interfacing

systems. As applicable, the inspectors verified that relevant procedure, design, and

licensing documents were properly updated. Lastly, the inspectors discussed the plant

modification with operations, engineering, and training personnel to ensure that the

individuals were aware of how the operation with the plant modification in place could

impact overall plant performance. Documents reviewed are listed in the Attachment.

9 Enclosure

This inspection constituted one permanent plant modification sample as defined in

IP 71111.18-05.

b. Findings

No findings were identified.

1R19 Post-Maintenance Testing (71111.19)

.1 Post-Maintenance Testing

a. Inspection Scope

The inspectors reviewed the following post-maintenance testing activities to verify that

procedures and test activities were adequate to ensure system operability and functional

capability:

  • Unit 1 Bus 144 Breaker 1442 Following Lockout Relay Replacement;
  • Unit 1 Train A SX Cubical Coolers Following Repairs;
  • Unit 2 Instrument Inverter 214 Following Coil Replacement; and

Replacement.

These activities were selected based upon the structure, system, and components

(SSCs) ability to impact risk. The inspectors evaluated these activities for the following

(as applicable): the effect of testing on the plant had been adequately addressed;

testing was adequate for the maintenance performed; acceptance criteria were clear and

demonstrated operational readiness; test instrumentation was appropriate; tests were

performed as written in accordance with properly reviewed and approved procedures;

equipment was returned to its operational status following testing (temporary

modifications or jumpers required for test performance were properly removed after test

completion); and test documentation was properly evaluated. The inspectors evaluated

the activities against TSs, the UFSAR, 10 CFR Part 50 requirements, licensee

procedures, and various NRC generic communications to ensure that the test results

adequately ensured that the equipment met the licensing bases and design

requirements. In addition, the inspectors reviewed corrective action documents

associated with post-maintenance tests to determine whether the licensee was

identifying problems and entering them into the CAP at the appropriate threshold and

that the problems were being corrected commensurate with their importance to safety.

Documents reviewed are listed in the Attachment.

This inspection constituted four post-maintenance testing samples as defined in

IP 71111.19-05.

b. Findings

No findings were identified.

10 Enclosure

1R20 Outage Activities (71111.20)

.1 Unit 2 Forced Outage

a. Inspection Scope

On March 20, 2013, at 7:51 p.m., licensee personnel performed a manual trip of the

Unit 2 reactor. The reactor was manually tripped in accordance with site procedures

when the only operating and available electrical generator stator cooling water pump

tripped unexpectedly. The inspectors responded to the site and assessed the cause of

the trip, performed follow-up inspection of minor equipment failures, and immediately

communicated any observations to NRC management. The inspectors reviewed outage

equipment configuration and risk management, verified electrical lineups, monitored

decay heat removal, observed reactor startup activities, and reviewed the identification

and resolution of problems associated with the forced outage.

All safety-related equipment operated as designed. Some nonsafety-related equipment

experienced minor malfunctions. For example:

  • The B reactor trip breaker closed indication light extinguished as expected, however

the open indication light did not illuminate to indicate that the breaker was open. An

operator was dispatched and verified the breaker was open. Subsequently, a burned

out B reactor trip breaker open indication light bulb was replaced.

  • The control rod in position M-12 (control bank D) had a general warning light

flashing, although its associated rod bottom light was lit. Following troubleshooting,

a logic card was replaced in the control rod drive cabinet to address the issue.

  • Following the Unit 2 trip, light smoke was reported to be coming from the Unit 2 A

main feedwater pump motor. It was later determined that when the 2A main feedater

pump was shut down that its associated motor heater automatically energized. An

abnormally large amount of dust had built up on the heater and when it energized the

dust burned off.

The licensee addressed these issues and Unit 2 was restarted and synchronized to the

electrical grid on March 22, 2013.

Documents reviewed are listed in the Attachment. This inspection constituted one other

outage sample as defined in IP 71111.20-05.

b. Findings

No findings were identified.

.2 Unit 2 Refueling Outage

a. Inspection Scope

The inspectors reviewed the Outage Safety Plan and contingency plans for the Unit 2

refueling outage (RFO) that began on April 7, 2013, to confirm that the licensee had

appropriately considered risk, industry operating experience, and previous site specific

11 Enclosure

problems in developing and implementing a plan that assured maintenance of defense in

depth.

A complete list of accomplished inspection activities will be documented following

completion of the Unit 2 RFO.

This inspection constituted a partial RFO sample as defined in IP 71111.20-05.

b. Findings

No findings were identified.

1R22 Surveillance Testing (71111.22)

.1 Surveillance Testing

a. Inspection Scope

The inspectors reviewed the test results for the following activities to determine whether

risk-significant systems and equipment were capable of performing their intended safety

function and to verify testing was conducted in accordance with applicable procedural

and TS requirements:

  • Unit 1 Train A Diesel Generator Operability Surveillance;
  • Unit 1 Train A Solid State Protection System Surveillance;
  • Unit 2 K636 Engineered Safety Features (ESF) Relay Surveillance; and
  • Unit 2 K644 ESF Relay Surveillance.

The inspectors observed in-plant activities and reviewed procedures and associated

records to determine the following:

  • did preconditioning occur;
  • were the effects of the testing adequately addressed by control room personnel

or engineers prior to the commencement of the testing;

  • were acceptance criteria clearly stated, demonstrate operational readiness, and

consistent with the system design basis;

  • was plant equipment calibration correct, accurate, and properly documented;
  • were as left setpoints within required ranges; and was the calibration frequency

in accordance with TSs, the UFSAR, plant procedures, and applicable

commitments;

  • was measuring and test equipment calibration current;
  • was the test equipment used within the required range and accuracy and were

applicable prerequisites described in the test procedures satisfied;

  • did test frequencies meet TS requirements to demonstrate operability and

reliability;

  • were tests performed in accordance with the test procedures and other

applicable procedures;

  • were jumpers and lifted leads controlled and restored where used;
  • were test data and results accurate, complete, within limits, and valid;

12 Enclosure

  • was test equipment removed following testing;
  • where applicable for in-service testing activities, was testing performed in

accordance with the applicable version of Section XI of the American Society of

Mechanical Engineers (ASME) Code, and were reference values consistent with

the system design basis;

  • was the unavailability of the tested equipment appropriately considered in the

performance indicator data;

  • where applicable, were test results not meeting acceptance criteria addressed

with an adequate operability evaluation, or was the system or component

declared inoperable;

  • where applicable for safety-related instrument control surveillance tests, was the

reference setting data accurately incorporated into the test procedure;

  • was equipment returned to a position or status required to support the

performance of its safety function following testing;

  • were all problems identified during the testing appropriately documented and

dispositioned in the licensees CAP;

  • where applicable, were annunciators and other alarms demonstrated to be

functional and were annunicator and alarm setpoints consistent with design

documents; and

  • where applicable, were alarm response procedure entry points and actions

consistent with the plant design and licensing documents.

Documents reviewed are listed in the Attachment.

This inspection constituted five routine surveillance testing samples as defined in

IP 71111.22, Sections -02 and -05.

b. Findings

No findings were identified.

1EP6 Drill Evaluation (71114.06)

.1 Training Observation

a. Inspection Scope

The inspectors observed a simulator training evolution for licensed operators on

January 31, 2013, which required Emergency Plan implementation by a licensee

operations crew. This evolution was planned to be evaluated and included in

performance indicator data regarding drill and exercise performance. The inspectors

observed event classification and notification activities performed by the crew. The

inspectors also attended the post-evolution critique for the scenario. The focus of the

inspectors activities was to note any weaknesses and deficiencies in the crews

performance and ensure that the licensee evaluators noted the same issues and entered

them into the CAP. As part of the inspection, the inspectors reviewed the scenario

package and other documents listed in the Attachment.

This inspection constituted one training evolution with emergency preparedness drill

sample as defined in IP 71114.06-05.

13 Enclosure

b. Findings

No findings were identified.

2. RADIATION SAFETY

2RS4 Occupational Dose Assessment (71124.04)

This inspection constituted a partial sample as defined in IP 71124.04-05.

.1 External Dosimetry (02.02)

a. Inspection Scope

The inspectors evaluated whether the licensees dosimetry vendor is National Voluntary

Laboratory Accreditation Program (NVLAP) accredited and if the approved irradiation

test categories for each type of personnel dosimeter used were consistent with the types

and energies of the radiation present and the way the dosimeter was being used (e.g., to

measure deep dose equivalent, shallow dose equivalent, or lens dose equivalent).

b. Findings

No findings were identified.

4. OTHER ACTIVITIES

4OA1 Performance Indicator Verification (71151)

.1 Unplanned Scrams Per 7000 Critical Hours

a. Inspection Scope

The inspectors sampled licensee submittals for the Unplanned Scrams Per 7000 Critical

Hours Performance Indicator (PI) for both Unit 1 and Unit 2 for the period from the first

quarter 2012 through the fourth quarter 2012. To determine the accuracy of the PI data

reported during those periods, PI definitions and guidance contained in Nuclear Energy

Institute (NEI) 99-02, Regulatory Assessment Performance Indicator Guideline,

Revision 6, dated October 2009, were used. The inspectors reviewed the licensees

operator narrative logs, IRs, event reports and NRC Integrated Inspection Reports for

the period of January 2012 through December 2012 to validate the accuracy of the

submittals. The inspectors also reviewed the licensees IR database to determine if any

problems had been identified with the PI data collected or transmitted for this indicator.

Documents reviewed are listed in the Attachment.

This inspection constituted two unplanned scrams per 7000 critical hours samples as

defined in IP 71151-05.

b. Findings

No findings were identified.

14 Enclosure

.2 Unplanned Scrams with Complications

a. Inspection Scope

The inspectors sampled licensee submittals for the Unplanned Scrams with

Complications PI for Unit 1 and Unit 2 for the period from the first quarter 2012 through

the fourth quarter 2012. To determine the accuracy of the PI data reported during those

periods, PI definitions and guidance contained in NEI 99-02, Regulatory Assessment

Performance Indicator Guideline, Revision 6, dated October 2009, were used. The

inspectors reviewed the licensees operator narrative logs, IRs, event reports and NRC

Integrated Inspection Reports for the period of January 2012 through December 2012 to

validate the accuracy of the submittals. The inspectors also reviewed the licensees IR

database to determine if any problems had been identified with the PI data collected or

transmitted for this indicator. Documents reviewed are listed in the Attachment .

This inspection constituted two unplanned scrams with complications samples as

defined in IP 71151-05.

b. Findings

No findings were identified.

.3 Unplanned Power Changes Per 7000 Critical Hours

a. Inspection Scope

The inspectors sampled licensee submittals for the Unplanned Power Changes Per

7000 Critical Hours PI for Unit 1 and Unit 2 for the period from the first quarter 2012

through the fourth quarter 2012. To determine the accuracy of the PI data reported

during those periods, PI definitions and guidance contained in NEI 99-02, Regulatory

Assessment Performance Indicator Guideline, Revision 6, dated October 2009, were

used. The inspectors reviewed the licensees operator narrative logs, IRs, maintenance

rule records, event reports, and NRC Integrated Inspection Reports for the period of

January 2012 through December 2012 to validate the accuracy of the submittals. The

inspectors also reviewed the licensees IR database to determine if any problems had

been identified with the PI data collected or transmitted for this indicator. Documents

reviewed are listed in the Attachment.

This inspection constituted two unplanned power changes per 7000 critical hours

samples as defined in IP 71151-05.

b. Findings

No findings were identified.

15 Enclosure

4OA2 Identification and Resolution of Problems (71152)

.1 Routine Review of Items Entered into the Corrective Action Program

a. Inspection Scope

As part of the various baseline inspection procedures discussed in previous sections of

this report, the inspectors routinely reviewed issues during baseline inspection activities

and plant status reviews to verify that they were being entered into the licensees CAP at

an appropriate threshold, that adequate attention was being given to timely corrective

actions, and that adverse trends were identified and addressed. Attributes reviewed

included the complete and accurate identification of the problem; that timeliness was

commensurate with safety significance; that evaluation and disposition of performance

issues, generic implications, common causes, contributing factors, root causes, extent-

of-condition reviews, and previous occurrence reviews were proper and adequate; and

that the classification, prioritization, focus, and timeliness of corrective actions were

commensurate with safety and sufficient to prevent recurrence of the issue. Minor

issues entered into the licensees CAP as a result of the inspectors observations are

listed in the Attachment.

These routine reviews for the identification and resolution of problems did not constitute

any additional inspection samples. Instead, by procedure they were considered an

integral part of the inspections performed during the quarter and documented in

Section 1 of this report.

b. Findings

No findings were identified.

.2 Daily Corrective Action Program Reviews

a. Inspection Scope

To facilitate the identification of repetitive equipment failures and human performance

issues for follow-up, the inspectors performed a daily screening of items entered into the

licensees CAP. This review was accomplished through inspection of the stations daily

IR packages.

These daily reviews were performed by procedure as part of the inspectors daily plant

status monitoring activities and, as such, did not constitute any separate inspection

samples.

b. Findings

No findings were identified.

16 Enclosure

.3 Selected Issue Follow-Up Inspection: Actions to Address Engineering-Related Issues

Identified at Braidwood During NRC Inspections

a. Inspection Scope

The inspectors reviewed evaluations and calculations as well as related IRs to assess

the adequacy of the licensees extent-of-condition review of issues identified during the

Braidwood Station Unit 1 and Unit 2 Evaluation of Changes, Tests, or Experiments and

Permanent Plant Modifications inspections performed in 2011.

This review included an analysis that was performed by the licensee to determine the

effects of lead shielding on the Unit 1 Safety Injection (SI) system piping subsystem and

associated pipe supports.

This review constituted one in-depth problem identification and resolution sample as

defined in IP 71152-05.

b. Findings

Embedment Plate Design Deficiencies

Introduction: The inspectors identified a finding of very low safety significance (Green)

and an associated Non-Cited Violation (NCV) of 10 CFR Part 50, Appendix B,

Criterion III, Design Control, when licensee personnel failed to properly evaluate the

structural steel embedment plate which supported SI pipe supports 1SI06025V and

1SI06030S.

Description: The SI system is part of the emergency core cooling system (ECCS).

Section 6.3.1 of the Byron UFSAR stated, in part, that the primary function of the ECCS

is to remove the stored and fission product decay heat from the reactor during accident

conditions and provide shutdown capability for design basis accidents by means of

boron injection.

Piping Subsystem 1SI06 is part of the SI System and is a safety-related ASME Class II,

Seismic Category I subsystem located in the curved wall area of the auxiliary building. A

structural steel embedment plate that supports safety-related pipe supports 1SI06025V

and 1SI06030S is located in the auxiliary building, which is a Seismic Category I

structure. Section 3.8.4.5.2 of the UFSAR describes requirements for structural steel

design inside the auxiliary building and states, in part, The stresses and strains of

structural steel are limited to those specified in the AISC (American Institute of Steel

Construction) Also, this section required that stresses be held within the elastic range

and that no plastic deformation was allowed.

The inspectors reviewed Calculation No. 13.2.29BY, Mechanical Component Support

1SI06025V, Revision 2X that evaluated pipe supports 1SI06025V and 1SI06030S.

These supports were attached to a structural embedment plate in the auxiliary building.

The structural steel embedment plate evaluation was also included in this calculation.

During a review of Calculation No. 13.2.29BY, the inspectors identified a number of

concerns, including the following:

17 Enclosure

  • The calculated bending stress on the embedment plate was greater than the

allowable bending stress by about 67 percent and the licensee relied on engineering

judgment to demonstrate compliance with the design and licensing basis

requirements;

  • The calculation used the actual instead of minimum material yield stress of the

embedment plate to calculate the allowable bending stress;

  • The calculation used an acceptance criteria which permitted plastic or permanent

deformation through yielding of the structural steel embedment plate and

redistribution of stresses in the embedment plate due to applied loads;

  • The calculation did not include an evaluation for severe environmental load

combinations as described in UFSAR Table 3.8-9 and as described in UFSAR

Section 3.8.4.3, Loads and Loading Combinations; and

  • The calculation did not consider applied stresses due to self-weight and self-weight

seismic excitation of tube steel pipe support members.

The inspectors determined that the engineering judgment used to demonstrate

compliance with the design and licensing basis was not valid because the AISC required

that the allowable bending stress be determined using the minimum yield stress of the

material. In addition, UFSAR Section 3.8.4.5.2 specified no plastic or permanent

deformation due to applied stresses. The inspectors also identified that the structural

steel embedment plate was not qualified for the severe environmental load combination

as described in UFSAR Table 3.8-9 and as required by UFSAR Section 3.8.4.3.

The licensee entered this issue into their CAP as IR 1478188, NRC Identified Use of

CMTR in a 80's Calculation. As part of their immediate corrective actions, the licensee

performed an operability evaluation and concluded the structural steel embedment plate

was operable, but nonconforming.

Analysis: The inspectors determined that the failure to design the structural steel

embedment plate which supported pipe supports 1SI06025V and 1SI06030S in

accordance with AISC and Seismic Category I linear elastic requirements was a

performance deficiency.

The inspectors determined that the performance deficiency was more than minor

because it was associated with the Design Control attribute of the Mitigating Systems

Cornerstone and adversely affected the cornerstone objective of ensuring the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences (i.e., core damage). Specifically, the licensee did not

demonstrate that the structural steel embedment plate which supported pipe supports

1SI06025V and 1SI06030S would maintain structural linear elastic integrity when

subjected to design loads.

The inspectors reviewed Attachment 0609.04, Initial Characterization of Findings,

Table 3 - SDP Appendix Router. The inspectors answered No to all of the questions in

Sections A through E of Table 3 and therefore the finding was evaluated using the SDP

in accordance with IMC 0609, The Significance Determination Process (SDP) for

Findings At-Power, Appendix A, Exhibit 2, Mitigating Systems Screening

18 Enclosure

Questions. The inspectors answered Yes to Question 1 - If the finding is a deficiency

affecting the design or qualification of a mitigating SSC [Structure, System, or

Component], does the SSC maintain its operability or functionality? Specifically, the

design deficiency was confirmed not to result in a loss of operability of the structural

steel embedment plate. Therefore, the finding was determined to have very low safety

significance (Green). The inspectors performed an independent review of the operability

evaluation and had no further concerns.

The inspectors did not identify a cross-cutting aspect associated with this finding

because the calculation was from the 1980s and was therefore not representative of

current performance.

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires,

in part, that design control measures shall provide for verifying or checking the adequacy

of the design, such as by the performance of design reviews, by the use of alternate or

simplified calculational methods, or by the performance of a suitable testing program.

Piping Subsystem 1SI06 is part of the Safety Injection System and is a safety-related

ASME Class II, Seismic Category I subsystem located in the curved wall area of the

auxiliary building. A structural steel embedment plate that supports safety-related pipe

supports 1SI06025V and 1SI06030S is located in the auxiliary building, which is a

Seismic Category I structure. Section 3.8.4.5.2 of the UFSAR describes requirements

for structural steel design inside the auxiliary building and states, in part, The stresses

and strains of structural steel are limited to those specified in the AISC. Also,

Section 3.8.4.5.2 of the UFSAR required that stresses be within the elastic range and

that no plastic deformation was allowed.

Contrary to the above, from initial construction to February 21, 2013, the licensee failed

to demonstrate the design adequacy of the embedment plate which supported safety-

related Safety Injection pipe supports 1SI06025V and 1SI06030S. Specifically, the

design for the structural steel embedment plate which supported safety-related Safety

Injection pipe supports 1SI06025V and 1SI06030S was inadequate, in that Calculation

No. 13.2.29BY, Mechanical Component Support 1SI06025V, Revision 2X, which was a

quality calculation, did not demonstrate that the embedment plate would meet AISC and

Seismic Category I linear elastic requirements.

Because this violation was of very low safety significance and it was entered into the

licensees CAP as IR 1478188, this violation is being treated as a NCV, consistent with

Section 2.3.2 of the NRC Enforcement Policy. As part of their immediate corrective

actions, the licensee performed an operability evaluation and concluded the structural

steel embedment plate was operable. (NCV 05000454/2013002-01, Embedment

Plate Design Deficiencies)

.4 Selected Issue Follow-Up Inspection: Valves in LCO Due to Abandonment

a. Inspection Scope

During a review of items entered in the licensees CAP, the inspectors identified an

IR regarding equipment that had been abandoned in place. Specifically, IR 1306607,

Long Term LCO [Limiting Condition for Operation] Extent of Condition Review Per

IR 1298667, characterized a series of valves as abandoned. The valves were also

19 Enclosure

characterized as having a containment isolation function. The inspectors reviewed the

licensees procedures associated with containment leak rate testing and recent test data

to ensure that the performance of the abandoned valves remained acceptable.

This review constituted one in-depth problem identification and resolution sample as

defined in IP 71152-05.

b. Findings

No findings were identified.

4OA5 Other Activities

.1 (Closed) NRC Temporary Instruction (TI) 2515/187 - Inspection of Near-Term Task

Force Recommendation 2.3 Flooding Walkdowns

As discussed in NRC Integrated Inspection Report 05000454/2012005;

05000455/2012005, the inspectors previously verified that licensee walkdown packages

Unit 1 13-Line Wall, Unit 1 1A and 1D Main Steam Isolation Valve Room Probable

Maximum Precipitation (PMP) Curb, and River Screen House Penetration RH-15C,

contained the elements specified in Nuclear Energy Institute (NEI) 12-07, Guidelines for

Performing Walkdowns of Plant Flood Protection Features.

During the previous quarter, the inspectors accompanied the licensee on their walkdown

of the River Screen House, Penetration RH-15C; and Unit 1 A and D Main Steam

Isolation Valve Room PMP Curb and verified that the licensee confirmed the following

flood protection features:

  • Visual inspection of the flood protection feature was performed if the flood

protection feature was relevant. External visual inspection for indications of

degradation that would prevent its credited function from being performed was

performed.

  • Critical SSC dimensions were measured.
  • Available physical margin, where applicable, was determined.
  • Flood protection feature functionality was determined using either visual

observation or by review of other documents.

During this quarter, the inspectors conducted additional independent walkdowns to verify

licensee compliance with inspection guidance contained in TI 2515/187. The area

selected was the building that houses the spent fuel pool, the fuel handling building

(FHB). There were several reasons for selecting this area. For example, the spent fuel

pool filtering and heat removal systems are located in the FHB. In addition, the FHB has

access ways that lead to other portions of the auxiliary building, a safety-related

structure.

The Byron UFSAR identified that the FHB was not subject to flooding. The inspectors

questioned why the FHB would not be subject to flooding since portions of it are at

ground level, a roll-up door in this building leads to an adjacent structure which has a

20 Enclosure

roll-up door that leads outside, and railway channels in the FHB have been observed to

contain rain water.

The inspectors verified that noncompliances with current licensing requirements, and

issues identified in accordance with the 10 CFR 50.54(f) letter, Item 2.g of Enclosure 4,

were entered into the licensee's CAP. In addition, issues identified in response to Item

2.g that could challenge risk significant equipment and the licensees ability to mitigate

the consequences will be subject to additional NRC evaluation.

.2 Failure to Properly Scope All the Pertinent External Flood Protection Features into

Walkdown Lists in Accordance with Nuclear Energy Institute (NEI) 12-07

Introduction: The inspectors identified a finding of very low safety significance (Green)

when licensee personnel failed to develop inspection lists that included all external flood

protection features credited in current licensing bases (CLB) documents as specified in

NEI 12-07, Guidelines for Performing Walkdowns of Plant Flood Protection Features.

Specifically, the inspection lists did not include several passive components in the FHB

which were an essential element of the Byron flood mitigation strategy.

Description: The inspectors reviewed the licensees inspection and walkdown

documents associated with flooding reviews performed in accordance with NEI 12-07,

Guidelines for Performing Walkdowns of Plant Flood Protection Features, in response

to a letter from the NRC to licensees pursuant to 10 CFR 50.54(f). During the review,

the inspectors identified that the licensee had completed their scoping of components for

TI 2515/187, Inspection of Near-Term Task Force Recommendation 2.3 Flooding

Walkdowns, and failed to properly scope all flood protection features credited in the

CLB documents for flooding events. Specifically, while reviewing the Flooding Features

Walkdown List used to inspect and test design bases flood mitigating equipment in

accordance with the NRC-endorsed guidance of NEI 12-07, the inspectors identified that

the flood protection features in the FHB were not included. The flood protection features

in the FHB were designed to protect the auxiliary building, including residual heat

removal and containment spray pumps from site external flooding scenarios, and were

an essential part of the Byron design basis flood mitigation strategy. In particular, the

concrete steps inside the FHB were designed to prevent flood waters that enter the FHB

from reaching a door that would allow water to enter the auxiliary building.

Because the licensee did not adequately follow the guidance in NEI 12-07 and identify

components in the FHB that served as passive flooding barriers, these components

were not scheduled for visual inspections or walkdowns. As a result, the licensee failed

to recognize walkdowns of these passive flooding barriers were required to adequately

respond to the March 12, 2012 letter from the NRC to licensees that discussed these

reviews. The licensee acknowledged that they may not have identified these flood

barriers during subsequent reviews if the inspectors had not identified the issue.

The licensee entered this issue into their CAP as IR 1466355, Update UFSAR

Regarding External Flooding. Corrective actions included plans to perform an

inspection of the NRC-identified passive flooding features that were omitted from the

inspection lists and an extent-of-condition review.

Analysis: The inspectors determined that the failure to include concrete flood barriers in

the FHB in the flooding inspection lists developed to address NEI 12-07, although these

21 Enclosure

passive components were a critical element of the Byron flood mitigation strategy, was a

performance deficiency.

Using the guidance in IMC 0612, Power Reactor Inspection Reports, Appendix B,

Issue Screening, the inspectors determined this finding affected the Mitigating Systems

Cornerstone. The inspectors determined that the performance deficiency was more than

minor because it was associated with the Protection Against External Factors (Flood

Hazard) attribute of the Mitigating Systems Cornerstone and adversely affected the

cornerstone objective of ensuring the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences (i.e., core

damage). Specifically, the concrete flood barriers in the FHB protecting important

safety-related equipment in the auxiliary building as well as the flood barriers for the

spent fuel pool cooling pumps were not properly scoped into the licensees walkdown

lists.

The inspectors reviewed Attachment 0609.04, Initial Characterization of Findings,

Table 3 - SDP Appendix Router. The inspectors answered No to all of the questions in

Sections A through E of Table 3 and therefore the finding was evaluated using the SDP

in accordance with IMC 0609, The Significance Determination Process (SDP) for

Findings At-Power, Appendix A, Exhibit 2, Mitigating Systems Screening

Questions. The inspectors answered No to Question B for the External Event

Mitigation Systems - Does the finding involve the loss or degradation of equipment or

function specifically designed to mitigate a seismic, flooding, or severe weather initiating

event (e.g., seismic snubbers, flooding barriers, tornado doors)? Therefore, the finding

was determined to have very low safety significance (Green).

This finding had a cross-cutting aspect in the Work Practices component of the Human

Performance cross-cutting area because licensee personnel did not properly apply

human error prevention techniques such as peer checking and proper documentation of

activities H.4(a).

Enforcement: This finding did not involve enforcement action because no violation of a

regulatory requirement was identified. Because this finding does not involve a violation

and is of very low safety significance, it is identified as a finding (FIN). (FIN

05000454/2013002-02; 05000455/2013002-02, Failure to Properly Scope All

Pertinent External Flood Protection Features into Walkdown Lists in Accordance

with Industry Guidance NEI 12-07)

.3 (Closed) Unresolved Item 05000454/2011005-03; 05000455/2011005-03: Use of

Thermolumiscent Dosimeters May Not Be Consistent With the Methods Used By the

National Voluntary Laboratory Accreditation Program Accreditation Process

In the fourth quarter of 2011, the inspectors identified that the licensees use of

thermoluminescent dosimeters (TLDs) may not be consistent with the methods used by

the NVLAP accreditation process. Specifically, the licensee used a vendor to supply and

process dosimeters that measure radiation exposure for the monitored workers. This

vendor is NVLAP-accredited for beta, gamma, neutron, mixture of beta/gamma, and

mixture of neutron/gamma radiations. However, the licensee used the TLDs when

workers may be exposed to beta, gamma, and neutron radiations within the same

monitoring period. The inspectors determined that this mixture of three radiation types

may not be aligned with the accreditation process, and opened Unresolved Item (URI)

22 Enclosure

05000454/2011005-03; 05000455/2011005-03 to evaluate the issue. The inspectors

requested technical assistance from the Office of Nuclear Reactor Regulation (NRR)

through Task Interface Agreement (TIA) 2012-05 (ML 12268A330), the results of which

are discussed below.

Title 10 CFR 20.1501(c)(2) requires that the dosimeter processor be approved for the

type of radiation or radiations included in the NVLAP program that most closely

approximates the type of radiation or radiations for which the individual wearing the

dosimeter is monitored. As there is no NVLAP test category for dosimeters exposed to a

mixture of beta, gamma, and neutron radiations, the NRC has determined that licensees,

which monitor for beta, gamma, and neutron exposure with a single dosimeter, need to

use a processor that is NVLAP accredited in categories for beta-photon mixtures and

neutron-photon mixtures. The licensees dosimetry processor was NVLAP accredited

for both beta-photon and neutron-photon mixtures and therefore was in compliance with

10 CFR 20.1501(c)(2).

Notwithstanding the paragraph above, licensees are required to provide adequate

monitoring in accordance with 10 CFR 20.1502(a). For any type of in-field use

practice that can introduce error in the monitoring results (dependent upon the type of

dosimeter and processing method), it becomes a question of compliance with the

monitoring requirements of 10 CRR 20.1502(a) and not of NVLAP accreditation

requirements of 10 CFR 20.1501(c)(2). As described in TIA 2012-05, another licensee

had performed a study with the same dosimeters used by Byron (Harshaw 760). This

study demonstrated that exposing a single Harshaw 760 dosimeter to a mixture of beta,

gamma, and neutron radiation met industry standards for accuracy and precision.

Therefore, the licensee provided adequate monitoring and was in compliance with

10 CFR 20.1502(a).

The inspectors determined that no performance deficiency existed; therefore this URI is

closed.

4OA6 Management Meetings

.1 Exit Meeting Summary

On April 4, 2013, the inspectors presented the inspection results to Mr. B. Youman,

Byron Plant Manager, and other members of the licensees staff.

The licensee acknowledged the issues presented. The inspectors confirmed that none

of the potential report input discussed was considered proprietary.

.2 Interim Exit Meetings

  • The inspection results for the area of occupational dose assessment were

discussed with Mr. B. Burton, Radiation Protection Manager, on March 26, 2013.

  • The inspection results for the area of lead shielding and pipe supports were

discussed with Ms. A. Corrigan, Mechanical Design Manager, and

Mr. E. Blondin, Design Engineering Manager, on March 26, 2013.

The licensee acknowledged the issues presented. The inspectors confirmed that none

of the potential report input discussed was considered proprietary.

23 Enclosure

ATTACHMENT: SUPPLEMENTAL INFORMATION

24 Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

R. Kearney, Site Vice President

B. Youman, Plant Manager

B. Askren, Security Manager

B. Barton, Radiation Protection Manager

S. Briggs, Operations Director

A. Creamean, Chemistry Manager

S. Gackstetter, Training Manager

D. Gudger, Regulatory Assurance Manager

E. Hernandez, Engineering Director

D. Horstmann, Business Operations

B. Spahr, Maintenance Director

E. Topping, Nuclear Oversight Manager

Nuclear Regulatory Commission

E. Duncan, Chief, Branch 3, Division of Reactor Projects

B. Bartlett, Byron Senior Resident Inspector

J. Robbins, Byron Resident Inspector

Illinois Emergency Management Agency (IEMA)

R. Zuffa, IEMA

1 Attachment

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000454/2013002-01 NCV Embedment Plate Design Deficiencies (Section 4OA2.3)05000454/2013002-02; FIN Failure to Properly Scope All Pertinent External Flood

05000455/2013002-02 Protection Features into Walkdown Lists in Accordance with

Industry Guidance NEI 12-07 (Section 4OA5.2)

Closed

05000454/2013002-01 NCV Embedment Plate Design Deficiencies (Section 4OA2.3)05000454/2013002-02; FIN Failure to Properly Scope All Pertinent External Flood

05000455/2013002-02 Protection Features into Walkdown Lists in Accordance with

Industry Guidance NEI 12-07 (Section 4OA5.2)

TI 2515/187 TI Inspection of Near-Term Task Force Recommendation 2.3

Flooding Walkdown (Section 4OA5.1)05000454/2011005-03; URI Use of TLDs May Not Be Consistent With the Methods Used

05000455/2011005-03 by the NVLAP Accreditation Process (Section 4OA5.3)

2 Attachment

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply that the NRC inspectors reviewed the documents in their entirety, but rather, that

selected sections of portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

Section 1R04

- BOP WO-E4; Control Room Chilled Water Electrical Lineup, Revision 2

- BOP WO-M3; Control Room Chilled Water Valve Lineup, Revision 10

Section 1R06

- BAR 0PL02J-3-B2; ESW Sump 2 Level High High, Revision 52

- IR 1413893; Unit 1 SX Alpha Sump Pump Check Valve is Sticking Open, September 16, 2012

- M-48; Diagram of Miscellaneous Sumps and Pumps, Revision AE

Section 1R11

- IR 1486687; Unexpected Unit 1 PDMS Alarms Due to Failing CETC, March 12, 2012

Section 1R12

- IR 1487650; Potential Corporate Elevation for Byron Maintenance, March 12, 2013

- IR 1479105; Unit 1 Gain POT R303 for N-43 Not Functioning Properly, February 22, 2013

- Byron Station Maintenance Rule Expert Panel Meeting Notes, November 5, 2009

- Byron Station Maintenance Rule Expert Panel Meeting Notes, December 18, 2009

- Byron Station Maintenance Rule Expert Panel Meeting Notes, June 7, 2011

- Byron Station Maintenance Rule Expert Panel Meeting Notes, November 3, 2011

- IR 1214163; Common Cause Analysis for MCCB for MCC 134Y2-A4, June 2, 2011

- ER-AA-310-1005; (A)(1) Determination Template for IR 1207922, Revision 5

- ER-AA-310-1005; (A)(1) Determination Template for IR 1207931, Revision 5

- Byron Station Maintenance Rule Periodic Assessment #11, January 2011 - June 2012

Section 1R13

- IR 1474028; 2A CV Pump Gear Box Failed to Develop Oil Pressure on Start,

February 12, 2013

- IR 1474042; 2A CV Pump Gear Oil Pressure Guage Stuck at 0 Psig, February 12, 2013

Section 1R15

- IR 1413971; Byron OAD Investigated and Identified an Abnormal Indication of the Over

Current Relay, October 11, 2012

- NSWP-S-05; Concrete Expansion Anchors, Revision 7

- Calculation 7.16.10.2-BYR97-229; Structural Evaluation of Battery Racks and the Mounting

Details in 111 and 112 Battery Rooms of the Auxiliary Building, Revision 4

- Drawing 6E-0-3391AY; 125V DC Battery Rack Mounting Details

- Drawing M-11978; Bus 111 & 211 125V DC L Two Step EP3 Racks, Revision 2

3 Attachment

- Drawing 6E-0-3391AH; Byron Station Unit 1& 2, Electrical Equipment Mounting Details,

Revision S

- Drawing 64-05906; Floor Rack - Two Step EQ Protected for Plate Size 3 and 4 Batteries,

Revision 0

- CC-AA-112; Temporary Configuration Changes, Revision 19

- EC 378402; Single Use Evaluation for 1/2 of SX Cubical Coolers Not Available, January 6, 2010

- EC 392429; Operation of SX Pump with Single Cubical Cooler, February 12, 2013

- IR 1465872; Review of Braidwood IR 1459353 - PZR PORV Accumulator Pressure,

January 22

- CN-RRA-00-47; Calculational Table for Byron and Braidwood Natural Circulation Cooldown,

Revision 1

Section 1R18

- Performance Verification Testing; RCFC Check Dampers for Byron Units 1 and 2, July 1981

- Sargent & Lundy Fan Check Dampers for Byron Units 1 and 2, March 5, 1985

- Material and Equipment Receiving and Inspection Report CECo Engineering and

Construction, June 30, 1981

- Material and Equipment Receiving and Inspection Report CECo Engineering and

Construction, June 30, 1981

- Q.F.2910.24; Project No. 4391-05, Tornado/Isolation Dampers, May 11, 1981

- Q.F.2910.24; Project No. 4392-05, Tornado/Isolation Dampers, May 11, 1981

- IR 1419184; RCFC Damper Missing Springs; September 27, 2012

- IR 1419189; RCFC Damper Missing Springs; September 27, 2012

- IR 1419190; RCFC Damper Missing Springs; September 27, 2012

- IR 1419192; RCFC Damper Missing Springs; September 27, 2012

- IR 1474498; NRC Follow-Up - RCFC Discharge Check Damper; February 7, 2013

Section 1R19

- IR 1473967; No SX PP Cubicle Cooler Tubesheet Degradation Margin Exists,

February 11, 2013

- WO 1493809; 214 Instrument Inverter EOC Walkdown Due to 211 INV Failure, Revision 1

- WO 1591475; 1SX01PA Comprehensive IST Required for Essential Service Water Pump,

February 14, 2013

- BOP IP-1; Instrument Bus Inverter Startup, Revision 14

- IR 1472776; ACB 1442 Drives On-Line Risk Yellow for Both Units, February 8, 2013

- IR 1473015; Lockout Relay 486-1442 for Breaker 1442 is Degraded, February 8, 2013

- WO 1237471; Bus 144 Sat 142-2 Feed (ACB 1442) RES OC Relay Routine, February 8, 2013

- WO 1444425; Replace Lockout Relay on ACB 1442, February 9, 2013

- WO 1591475; 1SX01PA Comprehensive IST Requirement for Essential Service Water Pump,

February 14, 2013

- WO 1418630; Support Eddy Current Testing for 1A SX Pump Cubical Cooler,

February14, 2013

- WO 1366902; Operation Run Cooler and Check for Proper Operation, February 14, 2013

- WO 1314236; Preventative Maintenance on Breaker SAT Feed, February 14, 2013

Section 1R20

- OP-AA-101-113-1004; Equipment Prompt: 2A Generator Stator Cooling Water Pump (2A GC)

Tripped, Revision 24

4 Attachment

- IR 1490321; Smoke Noticed Coming from the 2A FW Pump Motor, March 20, 2013

- IR 1490323; DRPI POD M-12 Indicated General Warning Following Reactor Trip, March 20,

2013

- IR 1493026; Smoke was Reported Coming from U2 Voltage Regulator Cabinet,

March 20, 2013

- IR 1490315; U-2 Reactor Trip - Loss of GC, March 20, 2013

- IR 1490330; Oil Leaking From Exciter End of Main Generator, March 20, 2013

- IR 1490407; Need Cleanup of Generator Oil Leak in Various TB Elevations, March 21, 2013

- IR 1490453; U2 RCDT Elevated Inputs Investigation, March 21, 2013

- IR 1490635; Following U2 Reactor Trip, 2AR11J went Dark Blue and then White,

March 21, 2013

Section 1R22

- 1BOSR 3.1.5-1; Train A Solid State Protection System Surveillance, Revision 32

- WO 1469526 01; ESF Relay Train Reactor Trip - K636/2FW039S, February 25, 2013

- IR 631199; Revise Unit Two Schematic Diagram 6E-2 4030FW56, May 18, 2007

- IR 848809; 12/15 E-3 Schedule Review, November 23, 2008

- IR 1064332; Inadequate Technical Information Provided for New SSPS Cards, May 2, 2010

- IR 1293130; UV Driver Card Vulnerability in OE 34462 Applicable at Byron,

November 21, 2011

- IR 1323037; Unexpected FWI While Closing RX Trip Breakers, February 5, 2012

- IR 1328319; Unexpected Ground Reading During SSPS Surveillance, February 17, 2012

- IR 1329012; Unexpected FWI While Closing RX Trip Breakers, February 20, 2012

- IR 1329908; Low Contact Volts Found During SSPS - Not Unusual, February 21, 2012

- IR 1374658; Low Voltage Reading During 2BOSR 3.1.5-2, June 5, 2012

- WO 1588151; 1CS01PB Comprehensive IST Requirements for Containment Spray Pump,

January 29, 2013

- BOP CS-5; Containment Spray System Recirculation to the RWST, Revision 11

- WO 1609614; 1A Diesel Generator Operability Surveillance, February 6, 2013

- 1BOSR 8.1.2-1; Unit 1 Train A Diesel Generator Operability Surveillance, Revision 20

- WO 1596040; ESF Relay Train B CS-K644 ESFAS Instrumentation ESF Relay Surveillance,

February 28, 2013

- WO 1597146; 2CS01PB Comprehensive IST Requirements for Containment Spray Pump,

February 28, 2013

Section 2RS4

- Final Response to Task Interface Agreement 2012-05; ML12268A330; October 16, 2012

Section 4OA1

- Power History Curves for Unit 1 and Unit 2, January 2012 through December 2012

- Perfomance Indicator Data as Reported for the Period January 2012 through December 2012

- IR 1319908; B2F26 U2 Reactor Trip Due To Electrical Fault and Unusual Event,

January 30, 2012

- IR 1323547; B2F27 Manual Reactor Trip and Manual Auxiliary Feedwater Actuation,

February 6, 2012

5 Attachment

Section 4OA2

- IR 1474066; Issues With SX to CC MOD Installation, February 11, 2013

- IR 1477430; Insufficient Insertion of Anti-Vibration Bars in Alloy 600, February 19, 2013

- IR 1413971; EACE - 1B RH Pump Trip Due to CO-5 Overcurrent Relay Operation,

September 17, 2012

- IR1272187; Issues Applicable to Byron from Bwd Mod/50.59 Inspection; October 4, 2011

- IR 1296141; NER NC-11-045-Y Fleet Wide Actions; September 28, 2011

- Byron Document No. DS-MC-01-BY; Certification of Design Specification for Primary

Containment Piping Penetration Assemblies; Revision 3

- Byron/Braidwood Document No. 01-10-52; Bryon/Braidwood Piping Design Specification;

Revision 2

- Calculation No. 13.2.29BY; Mechanical Component Support 1SI06025V; Revision 2X

- ER-AA-380; Primary Containment Leakrate Testing Program, Revision 9

- BVP 800-39; Primary Containment Leakrate Testing Program, Revision 10

- 1BOSR 6.1.1-19; Unit 1 Primary Containment Type C Leakage Rate Tests and IST Tests of

the OffGas System, Revision 8

- 2BVSR 6.1.1-24; Unit 2 Summation of Primary Containment Type B & C Local Leakage Tests

for Acceptance Criteria, Revision 12

- 1BVSR 6.1.1-24; Unit 2 Summation of Primary Containment Type B & C Local Leakage Tests

for Acceptance Criteria, Revision 15

- IR 1298667; Long Term LCO for VQ Valves Needs Resolution, December 6, 2011

- IR 1306607; Long Term LCO Extent of Condition Review Per IR 1298667, December 26, 2011

- EC 390536; Determine Acceptability of Code Case N-597-2 use on FAC Components

1FW085B/D, Revision 0

- IR 1412470; B1R18 FAC Component 1FW085B Exam Failure, September 13, 2012

- IR 1415327; B1R18 FAC Component 1FW085D Exam Failure, September 13, 2012

Corrective Action Documents As a Result of NRC Inspection

- IR 1487707; NRC ID UFSAR Discrepancy-Appendix A, Page A.1.57-1; March 14, 2013

- IR 1478188; NRC Identified Use of CMTR in a 80's Calculation; February 21, 2013

- IR 1490153; NRC/IEMA 1A DG HELB Modification Walkdown; March 20, 2013

- IR 1493278; NRC IDed: PDP 50.59 Enhancement Required, March 27, 2013

Section 4OA5

- IR 1466355; FUK: Update UFSAR Regarding External Flooding, January 24, 2013

- IR 1472808; FUK: Effect of Local Intense Precipitation on FHB and SFP PP, February 8, 2013

- IR 1474686; FUK: Concrete Steps on 401 FHB to Areas 5 & 7, February 13, 2013

- IR 1475877; Blockwall Penetrations in SFP Pump Room, February 15, 2013

- IR 1484749; FUK: MCC 133X1 Fasteners Seismic Walkdown, March 7, 2013

- IR 1484755; FUK: MCC 133X1 Fasteners Seismic Walkdown, March 7, 2013

- IR 1484758; FUK: MCC 133X1 Fasteners Seismic Walkdown, March 7, 2013

- IR 1484765; FUK: MCC 132X3 Fasteners Seismic Walkdown, March 7, 2013

- IR 1484768; FUK: MCC 131X3 Fasteners Seismic Walkdown, March 7, 2013

Corrective Action Documents As a Result of NRC Inspection

-IR 1453636; FUK: Flooding and Seismic Walkdowns, December 18, 2012

6 Attachment

LIST OF ACRONYMNS USE

ADAMS Agencywide Document Access and Management System

AISC American Institute of Steel Construction

ASME American Society of Mechanical Engineers

CAP Corrective Action Program

CFR Code of Federal Regulations

CLB Current Licensing Basis

ECCS Emergency Core Cooling System

ESF Engineered Safety Feature

FHB Fuel Handling Building

FIN Finding

FSAR Final Safety Analysis Report

IMC Inspection Manual Chapter

IP Inspection Procedure

IR Inspection Report

IR Issue Report

LCO Limiting Condition for Operation

NCV Non-Cited Violation

NEI Nuclear Energy Institute

NRC U.S. Nuclear Regulatory Commission

NRR Office of Nuclear Reactor Regulation

NVLAP National Voluntary Laboratory Accreditation Program

PARS Publicly Available Records System

PI Performance Indicator

PMP Probable Maximum Precipitation

PORV Power-Operated Relief Valve

RCFC Reactor Containment Fan Cooler

ROP Reactor Oversight Process

RFO Refueling Outage

SDP Significance Determination Process

SI Safety Injection

SSC Structure, System, or Component

SX Essential Service Water

TI Temporary Instruction

TIA Task Interface Agreement

TLD Thermoluminescent Dosimeter

TS Technical Specification

UFSAR Updated Final Safety Analysis Report

URI Unresolved Item

WO Work Order

7 Attachment

M. Pacilio -2-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Eric R. Duncan, Chief

Branch 3

Division of Reactor Projects

Docket Nos. 50-454, 50-455

License Nos. NPF-37, NPF-66

Enclosure: Inspection Report No. 05000454/2013002 and 05000455/2013002

w/Attachment: Supplemental Information

cc w/encl: Distribution via ListServ

DOCUMENT NAME: G:\DRPIII\BYRO\Byron 2013 002.docx

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII

NAME TDaun:dtp EDuncan

DATE 04/26/13 04/29/13

OFFICIAL RECORD COPY

Letter to M. Pacilio from E. Duncan dated April 29, 2013.

SUBJECT: BYRON STATION, UNITS 1 AND 2, NRC INTEGRATED INSPECTION

REPORT 05000454/2013002; 05000455/2013002

DISTRIBUTION:

Doug Huyck

RidsNrrDorlLpl3-2 Resource

RidsNrrPMByron Resource

RidsNrrDirsIrib Resource

Chuck Casto

Cynthia Pederson

Steven Orth

Allan Barker

Christine Lipa

Carole Ariano

Linda Linn

DRPIII

DRSIII

Tammy Tomczak

Patricia Buckley

ROPreports.Resource@nrc.gov