MONTHYEARRS-23-117, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-114, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2023-11-0101 November 2023 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-23-100, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections RS-23-093, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel.2023-09-29029 September 2023 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel. RS-23-094, Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 752023-09-29029 September 2023 Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 75 RS-23-091, Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals2023-09-26026 September 2023 Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-075, Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process2023-06-0707 June 2023 Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process RS-23-056, Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 102023-04-20020 April 2023 Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 10 RS-23-055, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2023-04-10010 April 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-038, Response to Request for Additional Information for the Byron Proposal to Reinsert an Accident Tolerant Fuel Lead Test Assembly2023-02-27027 February 2023 Response to Request for Additional Information for the Byron Proposal to Reinsert an Accident Tolerant Fuel Lead Test Assembly RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-110, Supplemental Information - Proposed Alternatives Related to the Steam Generators and Request.2022-09-20020 September 2022 Supplemental Information - Proposed Alternatives Related to the Steam Generators and Request. RS-22-097, License Amendment Request to Reinsert an Accident Tolerant Fuel Lead Test Assembly2022-08-31031 August 2022 License Amendment Request to Reinsert an Accident Tolerant Fuel Lead Test Assembly RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-086, R. E. Ginna Nuclear Power Plant - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam.2022-08-10010 August 2022 R. E. Ginna Nuclear Power Plant - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam. RS-22-084, Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator .2022-06-17017 June 2022 Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator . RS-22-074, Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds .2022-05-20020 May 2022 Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds . RS-22-073, Supplemental Information Regarding License Amendment Request -Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube.2022-05-19019 May 2022 Supplemental Information Regarding License Amendment Request -Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube. RS-22-057, Constellation Radiological Emergency Plan Addendum Revision2022-04-21021 April 2022 Constellation Radiological Emergency Plan Addendum Revision RS-22-037, License Amendment Request - Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control2022-04-21021 April 2022 License Amendment Request - Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control RS-22-051, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-04-12012 April 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-050, Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2022-04-0808 April 2022 Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-22-047, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2022-04-0808 April 2022 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-22-049, Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for2022-04-0404 April 2022 Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for V RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations RS-22-014, Application to Adopt TSTF-246, RTS Instrumentation, 3.3.1 Condition F Completion Time2022-03-24024 March 2022 Application to Adopt TSTF-246, RTS Instrumentation, 3.3.1 Condition F Completion Time RS-22-041, Withdrawal of License Amendment Request to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) to Add References to NRC Approved Topical Report with Administrative Changes2022-03-22022 March 2022 Withdrawal of License Amendment Request to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) to Add References to NRC Approved Topical Report with Administrative Changes RS-22-036, Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2022-03-10010 March 2022 Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-22-023, Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement2022-02-23023 February 2022 Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement RS-22-027, Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated2022-02-23023 February 2022 Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated P RS-22-019, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-02-16016 February 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-015, Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Exelon Generation Company, LLC2022-02-0101 February 2022 Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Exelon Generation Company, LLC RS-22-008, Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report to Add References to NRC-Approved Topical Report with Admin2022-01-24024 January 2022 Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report to Add References to NRC-Approved Topical Report with Admin RS-22-004, Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2022-01-0404 January 2022 Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RS-21-121, Proposed Changes to Decommissioning Trust Agreements and Master Terms2021-12-15015 December 2021 Proposed Changes to Decommissioning Trust Agreements and Master Terms RS-21-112, Updated 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2021-10-22022 October 2021 Updated 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-21-103, Updated Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations for Byron Station and Dresden Nuclear Power Station2021-09-28028 September 2021 Updated Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations for Byron Station and Dresden Nuclear Power Station RS-21-096, Withdrawal of Certification of Permanent Cessation of Power Operations for Byron Station, Units 1 and 2, and Previously Submitted Licensing Actions in Support of Decommissioning2021-09-15015 September 2021 Withdrawal of Certification of Permanent Cessation of Power Operations for Byron Station, Units 1 and 2, and Previously Submitted Licensing Actions in Support of Decommissioning RS-21-091, Implementation of Insider Threat Program Requirements Associated with the Voluntary Security Clearance Program and Advisement of Leadership Changes2021-09-13013 September 2021 Implementation of Insider Threat Program Requirements Associated with the Voluntary Security Clearance Program and Advisement of Leadership Changes RS-21-093, R. E. Ginna, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2021-09-0101 September 2021 R. E. Ginna, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections 2023-09-29
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARRS-23-117, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information BYRON 2023-0029, Response to Request for Additional Information Regarding Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements2023-06-0101 June 2023 Response to Request for Additional Information Regarding Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements RS-23-056, Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 102023-04-20020 April 2023 Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 10 RS-23-038, Response to Request for Additional Information for the Byron Proposal to Reinsert an Accident Tolerant Fuel Lead Test Assembly2023-02-27027 February 2023 Response to Request for Additional Information for the Byron Proposal to Reinsert an Accident Tolerant Fuel Lead Test Assembly RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator RS-22-084, Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator .2022-06-17017 June 2022 Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator . RS-22-074, Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds .2022-05-20020 May 2022 Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds . RS-22-027, Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated2022-02-23023 February 2022 Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated P ML21320A2422021-11-16016 November 2021 Stations - Response to Request for Additional Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds JAFP-21-0087, Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments2021-09-16016 September 2021 Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments ML21225A0062021-08-13013 August 2021 Response to Request for Additional Information Regarding License Amendment Request to Address the Issues Identified in Westinghouse Documents NSAL-09-5, Rev.1 and NSAL-15-1, Rev. 0 NMP2L2773, Company - Response to Request for Additional Information2021-06-30030 June 2021 Company - Response to Request for Additional Information JAFP-21-0044, Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments2021-06-11011 June 2021 Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments JAFP-21-0032, Response to Request for Additional Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting2021-04-20020 April 2021 Response to Request for Additional Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting RS-21-024, Response to Request for Additional Information (RAI) Regarding Byron Station, Units 1 and 2, License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition2021-03-16016 March 2021 Response to Request for Additional Information (RAI) Regarding Byron Station, Units 1 and 2, License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition RS-21-029, Response to RAI Re License Amendment Request - Proposed Changes to Byron & Dresden Stations Emergency Plan for Post-Shutdown and Permanently Defueled Condition2021-03-15015 March 2021 Response to RAI Re License Amendment Request - Proposed Changes to Byron & Dresden Stations Emergency Plan for Post-Shutdown and Permanently Defueled Condition RS-21-015, Response to Request for Additional Information Related to Relief Request for Braidwood I4R-11 and Byron I4R-182021-02-10010 February 2021 Response to Request for Additional Information Related to Relief Request for Braidwood I4R-11 and Byron I4R-18 RS-20-017, Response to Request for Additional Information - Proposed Alternative to Utilize Code Case N-8852021-02-0101 February 2021 Response to Request for Additional Information - Proposed Alternative to Utilize Code Case N-885 RS-20-150, Response to Request for Additional Information Related to Subsequent Exemption from Part 26 Requirements2020-12-0101 December 2020 Response to Request for Additional Information Related to Subsequent Exemption from Part 26 Requirements RS-20-143, Response to Request for Additional Information Regarding Application to Revise Technical Specifications 3.8.1, AC Sources- Operating2020-11-20020 November 2020 Response to Request for Additional Information Regarding Application to Revise Technical Specifications 3.8.1, AC Sources- Operating RS-20-100, Response to Request for Additional Information Regarding Application for Revision to TS 5.5.9, Steam Generator (SG) Program, for a One-Time Deferral of Steam Generator Tube Inspections2020-08-19019 August 2020 Response to Request for Additional Information Regarding Application for Revision to TS 5.5.9, Steam Generator (SG) Program, for a One-Time Deferral of Steam Generator Tube Inspections NMP2L2711, Byron Station; Calvert Cliffs; Clinton Power Station; LaSalle County Station; Limerick Generating Station; and Nine Mile Point Nuclear Station - Proposed Alternative to Utilize Code Case N-8792019-10-16016 October 2019 Byron Station; Calvert Cliffs; Clinton Power Station; LaSalle County Station; Limerick Generating Station; and Nine Mile Point Nuclear Station - Proposed Alternative to Utilize Code Case N-879 RS-19-100, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended.2019-10-0707 October 2019 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended. RS-19-088, Response to Request for Additional Information Regarding Application to Revise Braidwood Station and Byron Station Technical Specifications to Adopt Risk Informed...2019-09-0505 September 2019 Response to Request for Additional Information Regarding Application to Revise Braidwood Station and Byron Station Technical Specifications to Adopt Risk Informed... JAFP-19-0057, Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-8802019-06-0404 June 2019 Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-880 NMP1L3279, Response to Request for Additional Information - Proposed Alternatives to Utilize Code Cases N-878 and N-880 for Plants2019-05-0101 May 2019 Response to Request for Additional Information - Proposed Alternatives to Utilize Code Cases N-878 and N-880 for Plants JAFP-19-0006, Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-8802019-01-0808 January 2019 Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-880 RS-18-143, Supplemental Information Supporting License Amendment Requests for Approval of Changes to Emergency Plan Staffing Requirements2018-11-29029 November 2018 Supplemental Information Supporting License Amendment Requests for Approval of Changes to Emergency Plan Staffing Requirements RS-18-097, Response to Request for Additional Information and Supplemental Information-License Amendment.2018-07-27027 July 2018 Response to Request for Additional Information and Supplemental Information-License Amendment. RS-18-072, Response to Request for Additional Information Regarding 50.69 Amendment2018-06-13013 June 2018 Response to Request for Additional Information Regarding 50.69 Amendment RS-18-061, Response to Request for Additional Information Regarding Decommissioning Funding Plans for Independent Spent Fuel Storage Installations (Isfsis)2018-05-0202 May 2018 Response to Request for Additional Information Regarding Decommissioning Funding Plans for Independent Spent Fuel Storage Installations (Isfsis) RS-17-138, Stations - Response to Request for Additional Information Related to License Amendment Request to Incorporate Changes Supported by TSTF-547, Clarification of Rod Position Requirements'2017-10-25025 October 2017 Stations - Response to Request for Additional Information Related to License Amendment Request to Incorporate Changes Supported by TSTF-547, Clarification of Rod Position Requirements' RS-17-084, Response to Request for Additional Information for Byron Station and Braidwood Station Post Peening Relief Requests2017-07-14014 July 2017 Response to Request for Additional Information for Byron Station and Braidwood Station Post Peening Relief Requests RS-17-085, Response to Request for Additional Information Regarding Amendments to Remove Obsolete License and Technical Specification Items2017-06-29029 June 2017 Response to Request for Additional Information Regarding Amendments to Remove Obsolete License and Technical Specification Items RS-17-032, Response to Request for Additional Information Regarding the License Amendment Request to Utilize the TORMIS Computer Code Methodology2017-03-20020 March 2017 Response to Request for Additional Information Regarding the License Amendment Request to Utilize the TORMIS Computer Code Methodology RS-17-044, Response to Request for Additional Information Regarding Proposed Alternative for the Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography2017-03-13013 March 2017 Response to Request for Additional Information Regarding Proposed Alternative for the Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography RS-17-036, Response to Request for Additional Information Regarding Relief Request I4R-102017-02-24024 February 2017 Response to Request for Additional Information Regarding Relief Request I4R-10 RS-16-259, Response to Request for Additional Information for Relief Request I4R-10: Proposed Alternative Requirements for the Repair and Examination of Reactor Vessel Head Penetrations for the Fourth Inservice Inspection Interval2016-12-29029 December 2016 Response to Request for Additional Information for Relief Request I4R-10: Proposed Alternative Requirements for the Repair and Examination of Reactor Vessel Head Penetrations for the Fourth Inservice Inspection Interval RS-16-175, High Frequency Supplement to Seismic Hazard Screening Report,Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 the Near Term-Task Force Review of Insights from the Fukushima Dai-ichi Accident2016-11-0202 November 2016 High Frequency Supplement to Seismic Hazard Screening Report,Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 the Near Term-Task Force Review of Insights from the Fukushima Dai-ichi Accident RS-16-195, Supplemental Information for the Fourth Inservice Inspection Interval Relief Request 14R-082016-09-29029 September 2016 Supplemental Information for the Fourth Inservice Inspection Interval Relief Request 14R-08 RS-16-122, Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident2016-08-31031 August 2016 Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident RA-16-049, Response to Request for Additional Information Regarding Requests to Withhold Emergency Preparedness Documents from Public Disclosure2016-05-26026 May 2016 Response to Request for Additional Information Regarding Requests to Withhold Emergency Preparedness Documents from Public Disclosure RS-16-079, Response to Request for Additional Information Regarding the Request for Exemption from 10 CFR 50.55a, Codes and Standards, Paragraph (h)(2), Protection Systems, Including Change to Request NRC Approval Under 10 CFR 50.55a..2016-04-11011 April 2016 Response to Request for Additional Information Regarding the Request for Exemption from 10 CFR 50.55a, Codes and Standards, Paragraph (h)(2), Protection Systems, Including Change to Request NRC Approval Under 10 CFR 50.55a.. RS-16-078, Clarification to Response to Requests for Additional Information for Relief for Alternate Requirements for Repair of Reactor Vessel Head Penetrations with Nozzles Having Pressure-Retaining Partial-Penetration J-Groove Welds2016-04-0404 April 2016 Clarification to Response to Requests for Additional Information for Relief for Alternate Requirements for Repair of Reactor Vessel Head Penetrations with Nozzles Having Pressure-Retaining Partial-Penetration J-Groove Welds RS-16-067, Supplement to Response to Requests for Additional Information for Relief for Alternate Requirements for Repair of Reactor Vessel Head Penetrations with Nozzles Having Pressure-Retaining Partial-Penetration J-Groove Welds2016-03-22022 March 2016 Supplement to Response to Requests for Additional Information for Relief for Alternate Requirements for Repair of Reactor Vessel Head Penetrations with Nozzles Having Pressure-Retaining Partial-Penetration J-Groove Welds RS-16-045, Response to Requests for Additional Information for Relief for Alternate Requirements for Repair of Reactor Vessel Head Penetrations with Nozzles Having Pressure-Retaining Partial-Penetration J-Groove Welds2016-02-11011 February 2016 Response to Requests for Additional Information for Relief for Alternate Requirements for Repair of Reactor Vessel Head Penetrations with Nozzles Having Pressure-Retaining Partial-Penetration J-Groove Welds RS-16-039, Response to Request for Additional Information Regarding the Request for Exemption from 10 CFR 50.55a, Codes and Standards, Paragraph (h)(2), Protection Systems.2016-01-29029 January 2016 Response to Request for Additional Information Regarding the Request for Exemption from 10 CFR 50.55a, Codes and Standards, Paragraph (h)(2), Protection Systems. RS-15-319, Responds to Request for Additional Information Regarding Relief Request RP-1 Associated with the Fourth Inservice Testing Interval2015-11-30030 November 2015 Responds to Request for Additional Information Regarding Relief Request RP-1 Associated with the Fourth Inservice Testing Interval RS-15-264, Response to Request for Additional Information Regarding the License Amendment Request to Install New Low Degraded Voltage Relays and Timers on the 4.16 Kv Engineered Safety Features (ESF) Buses2015-10-0909 October 2015 Response to Request for Additional Information Regarding the License Amendment Request to Install New Low Degraded Voltage Relays and Timers on the 4.16 Kv Engineered Safety Features (ESF) Buses RS-15-251, Response to Request for Additional Information Follow-Up Clarification Regarding License Amendment Request for Diesel Generator Load Rejection Surveillance Requirement2015-09-16016 September 2015 Response to Request for Additional Information Follow-Up Clarification Regarding License Amendment Request for Diesel Generator Load Rejection Surveillance Requirement 2023-06-01
[Table view] |
Text
200 Exelon Way Kennett Square, PA 19348 www.constellation.com 10 CFR 73.5 RS-23-117 November 10, 2023 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Byron Station, Units 1 and 2 Renewed Facility Operating Licensee Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and STN 50-455
Subject:
Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information
References:
- 1. Letter from D. Gudger (Constellation Energy Generation, LLC) to U.S.
Nuclear Regulatory Commission, "Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation," dated October 13, 2023 (ML23286A036)
- 2. Email from Scott Wall (NRC Senior Project Manager) to Ron Reynolds (Constellation Energy Generation, LLC), "Final RCI - Constellation Energy Generation, LLC - Byron 1 & 2 - Exemption from Security Rule," dated October 30, 2023 (ML23304A020)
By letter dated October 13, 2023 (Reference 1), Constellation Energy Generation, LLC (CEG) requested an exemption for Byron Station (Byron), Units 1 and 2, from the compliance date of January 8, 2024, for the new security Rule, "Enhanced Weapons, Firearms Background Checks, and Security Event Notifications." The requested exemption was based on the NRC's projected timeline for completion of revision to the applicable Regulatory Guides associated with the new rule, and the time necessary for Byron to process change management adequately to include the number of training weeks that will be required to implement the Rule. Byron requested a new compliance date of December 31, 2024, or 180 days after publication of final Regulatory Guides, whichever is later.
On October 24, 2023, the NRC issued, via email, a draft Request for Confirmatory Information (RCI). A clarification call with the NRC and CEG was held on October 25, 2023, resulting in a formal RCI request on October 30, 2023 (Reference 2).
The Attachment to this supplemental information letter provides responses to the RCI provided in Reference 2.
U.S. Nuclear Regulatory Commission Supplemental Information Letter Responses to Request for Confirmatory Information Docket Nos. STN 50-454 and STN 50-455 November 10, 2023 Page 2 There are no regulatory commitments contained in this supplement.
If you should have any questions concerning this submittal, please contact Richard Gropp at (267) 533-5642.
Respectfully, David P. Helker Sr. Manager, Licensing Constellation Energy Generation, LLC
Attachment:
Supplemental Information Letter cc: w/ Attachment NRC Regional Administrator, Region III NRC Project Manager - Byron NRC Senior Resident Inspector - Byron Scott Wall, NRC Fleet Project Manager Illinois Emergency Management Agency Division of Nuclear Safety
Supplemental Information Letter Attachment Responses to Request for Confirmatory Information Page 1 of 3 NRC Docket Nos. STN 50-454 and STN 50-455 SUPPLEMENTAL INFORMATION This Supplemental Information provides responses to the Request for Confirmatory Information (RCI) provided by the NRC in Reference 2. Each confirmatory request is provided below followed by CEG's response.
- 1. Regarding CEGs request for exemption from the January 8, 2024, compliance date, please confirm the following:
o CEG is requesting an exemption for Byron from specific requirements, as described below, associated with the final rule for Enhanced Weapons, Firearms Background Checks, and Security Event Notifications, as identified in your submission; that would defer compliance with those provisions until December 31, 2024, or 180 days after publication of final Regulatory Guides, whichever is later.
CEG Response:
Yes, CEG is requesting an exemption for Byron from specific requirements, as described below, associated with the final rule for Enhanced Weapons, Firearms Background Checks, and Security Event Notifications, as identified in Byron's submittal dated October 13, 2023 (ML23286A036), that would defer compliance with those provisions until December 31, 2024, or 180 days after publication of final Regulatory Guides, whichever is later.
o CEG is not requesting an extension to the compliance date for Byron for specific requirements in Title 10 of the Code of Federal Regulations (10 CFR) Part 73, Subpart B, "Enhanced Weapons, Preemption, and Firearms Background Checks," described in 10 CFR 73.15, "Authorization for Use of Enhanced Weapons and Preemption of Firearms Laws," and 10 CFR 73.17, "Firearms Background Checks for Armed Security Personnel."
CEG Response:
Correct, CEG is not requesting an extension to the compliance date for Byron for specific requirements in Title 10 of the Code of Federal Regulations (10 CFR) Part 73, Subpart B, "Enhanced Weapons, Preemption, and Firearms Background Checks," described in 10 CFR 73.15, "Authorization for Use of Enhanced Weapons and Preemption of Firearms Laws,"
and 10 CFR 73.17, "Firearms Background Checks for Armed Security Personnel."
o CEG is requesting an exemption for Byron from specific requirements in 10 CFR Part 73, Subpart T, "Security Notifications, Reports, and Recordkeeping," 10 CFR 73.1200(a) through 10 CFR 73.1200(t), "Notification of Physical Security Events," 10 CFR 73.1205(a)(1) through 10 CFR 73.1205(e), "Written Follow-up Reports of Physical Security Events," 10 CFR 73.1210(a)(1) through10 CFR 73.1210(h), "Recordkeeping of Physical Security Events," and "Suspicious Activity Reports," 10 CFR 73.1215(a) through 10 CFR 73.1215(f) until the later of December 31, 2024, or 180 days after publication of the final Regulatory Guides.
CEG Response:
Yes, CEG is requesting an exemption for Byron from specific requirements in 10 CFR Part 73, Subpart T, "Security Notifications, Reports, and Recordkeeping," 10 CFR 73.1200(a) through 10 CFR 73.1200(t), "Notification of Physical Security Events," 10 CFR 73.1205(a)(1) through 10 CFR 73.1205(e), "Written Follow-up Reports of Physical Security Events," 10
Supplemental Information Letter Attachment Responses to Request for Confirmatory Information Page 2 of 3 NRC Docket Nos. STN 50-454 and STN 50-455 CFR 73.1210(a)(1) through10 CFR 73.1210(h), "Recordkeeping of Physical Security Events," and 10 CFR 73.1215(a) through 10 CFR 73.1215(f), "Suspicious Activity Reports,"
until the later of December 31, 2024, or 180 days after publication of the final Regulatory Guides.
o CEG is requesting an exemption for Byron from using the definitions for the terms "Contraband," and "Time of Discovery" as recently revised in 10 CFR 73.2, "Definitions,"
until the later of December 31, 2024, or 180 days after publication of the final Regulatory Guides. The exemption would not apply to the definitions of those terms that were in effect prior to the issuance of the 2023 revisions.
CEG Response:
Yes, CEG is requesting an exemption for Byron from using the definitions for the terms "Contraband," and "Time of Discovery" as recently revised in 10 CFR 73.2, "Definitions,"
until the later of December 31, 2024, or 180 days after publication of the final Regulatory Guides. The exemption would not apply to the definitions of those terms that were in effect prior to the issuance of the 2023 revisions.
- 2. Confirm that the current Byron site security plan implements the requirements of 10 CFR 73.71, "Reporting of Safeguards Events" for reporting the suspension of security measures.
CEG Response:
CEG confirms that the current Byron site security plan implements the requirements of 10 CFR 73.71, "Reporting of Safeguards Events" for reporting the suspension of security measures.
o Confirm that Byron will continue to comply with security event reporting, as previously required in 10 CFR 73.71, "Reporting of Safeguards Events," and Appendix G to Part 73, "Reportable Safeguards Events."
CEG Response:
CEG confirms that Byron will continue to comply with security event reporting, as previously required in 10 CFR 73.71, "Reporting of Safeguards Events," and Appendix G to Part 73, "Reportable Safeguards Events."
o Confirm that Byron will use the definitions for the terms "Contraband" and "Discovery (time of)" in its site security plan consistent with how these terms are currently defined in Regulatory Guide 5.76, Revision 1, "Physical Protection Programs at Nuclear Power Reactors."
CEG Response:
CEG confirms that Byron will use the definitions for the terms "Contraband" and "Discovery (time of)" in its site security plan consistent with how these terms are currently defined in Regulatory Guide 5.76, Revision 1, "Physical Protection Programs at Nuclear Power Reactors."
Supplemental Information Letter Attachment Responses to Request for Confirmatory Information Page 3 of 3 NRC Docket Nos. STN 50-454 and STN 50-455
- 3. Confirm that when Byron states that it is implementing the new Access Authorization Rule it actually means that it is implementing the new 2022 10 CFR Part 26 Fitness for Duty Rule (87 FR 71422, November 22, 2022)?
CEG Response:
CEG confirms that the statement in its exemption request that "CEG is in the process of implementing the new Access Authorization Rule" was made in error. What the statement intended to say is that CEG is in the process of implementing the new 2022 10 CFR Part 26 Fitness for Duty Rule (87 FR 71422, November 22, 2022).