IR 05000277-11-202 and IR 05000278-11-202, on 05/20/2011, Peach Bottom Atomic Power Station NRC Security Inspection Report
ML11187A140
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 07/07/2011
From: Rachel Johnson
NRC/NSIR/DSO/DDSO/SPEB
To: Dougherty T
Exelon Generation Co
References
IR-11-202
Download: ML11187A140 (3)


Text

July 7, 2011 Mr. Tom Dougherty, Vice President Exelon Generation Company, LLC Peach Bottom Atomic Power Station 1848 Lay Road Delta, PA 17314

SUBJECT: PEACH BOTTOM ATOMIC POWER STATION NRC SECURITY INSPECTION REPORT 05000277/2011202 AND 05000278/2011202

Dear Mr. Dougherty:

On May 20, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at the Peach Bottom Atomic Power Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed via telephone on June 2, 2011, with Mr. James Kovalchick, Site Security Manager, and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings of significance were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system, ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1).

The enclosure transmitted herewith contains Safeguards Information. When separated from the enclosure

, this transmittal document is decontrolled. Should you have any questions concerning this letter, please contact us. Your cooperation is appreciated.

Sincerely,

/RA/

Robert C. Johnson, Chief Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket Nos.: 50-277, 50-278 License Nos.: DPR-44, DPR-56

Enclosure: Inspection Report 05000277/2011202 and 05000278/2011202 w/Attachments: Supplemental Information cc w/encl: J. Kovalchick, Peach Bottom Atomic Power Station

cc w/o encl: J. Pacilio, Peach Bottom Atomic Power Station

ML11187A140 OFFICE NSIR/DSO/SPEB SRI RI NSIR/DSO/SPEB NAME A. Letourneau F. Bowers J. Trapp C. Johnson DATE 7/1/2011 6/30/2011 7/7/11 7/7/11