IR 05000454-13-002 and 05000455-13-002; Exelon Generation Company, LLC; 01/01/2013 - 03/31/2013; Byron Station, Units 1 & 2, Identification and Resolution of Problems Other Activities
ML13120A181
Person / Time
Site: Byron  Constellation icon.png
Issue date: 04/29/2013
From: Eric Duncan
Region 3 Branch 3
To: Pacilio M
Exelon Generation Co, Exelon Nuclear
References
IR-13-002
Download: ML13120A181 (37)


See also: IR 05000454/2013002

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210

LISLE, IL 60532

-4352 April 29, 2013

Mr. Michael J. Pacil

i o Senior Vice President, Exelon Generation Company, LLC

President and Chief Nuclear Office

r (CNO), Exelon Nuclear

4300 Warrenville Road

Warrenville, IL 60555

SUBJECT: BYRON STATION, UNITS

1 AND 2 , NRC INTEGRATED INSPECTION REPORT 05000454/201 3 00 2; 05000455/201 3 00 2 Dear Mr. Pacilio

On March 3 1, 201 3 , the U.S. Nuclear Regulatory Commission (NRC) completed an integrated inspection

at your Byron Station, Units 1 and 2. The

enclosed inspection report documents the inspection results which were discussed

on April 4 , 2013, with Mr. B. Youman and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

T wo NRC-identified finding

s of very low safety significance (Green

) were identified during this inspection. One of the s e finding s was determined to involve a violation

of NRC requirements. However, because of its

very low safety

significance, and because the

issue was entered into your corrective action program, the NRC is treating this violation

as a non-cited violation (NCV) in accordance with Section 2.3.2 of the NRC Enforcement Policy.

If you contest this NCV, you should provide a response

within 30 days of the date of this inspection report, with the basis for your denial, to

the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20

555-0001; with copies to the Regional Administrator, Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532

-4352; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555

-0001; and the

NRC Resident Inspector at the Byron Station. If you disagree with a cross

-cutting aspect assignment

in this report, you should provide a response within 30 days of

the date of this inspection report, with the basis for your

disagreement, to the Regional Administrator, Region III, and th

e NRC Resident Inspector

at the Byron Station.

M. Pacilio

-2- In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Sincerely, /RA/ Eric R. Duncan, Chief

Branch 3 Division of Reactor Projects

Docket Nos. 50-454, 50-455 License Nos. NPF

-37 , NPF-66 Enclosure:

Inspection Report 05000

454/201 3 00 2 and 05000455/201 3 00 2 w/Attachment: Supplemental Information

cc w/encl:

Distribution via ListServ

Enclosure U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket Nos:

50-454; 50-455 License Nos:

NPF-37; NPF-66 Report No:

05000454/201 3 00 2; 05000455/2013002 Licensee: Exelon Generation Company, LLC

Facility: Byron Station, Units 1 and 2

Location: Byron, IL Dates: January 1 through March 3 1, 201 3 Inspectors:

B. Bartlett, Senior Resident Inspector

J. Robbins, Resident Inspector

J. Bozga, Reactor Inspector V. Meyers, Health Physicist

V. Meghani, Reactor Inspector

T. Daun, Reactor Engineer

R. Ng, Project Engineer

C. Thompson, Resident Inspector, Illinois Emergency

Management Agency

Approved by:

E. Duncan, Chief Branch 3 Division of Reactor Project s

Enclosure TABLE OF CONTENTS

SUMMARY OF FINDINGS

................................

................................................................

......... 1 REPORT DETAILS

................................

................................................................

....................

3 Summary of Plant Status

................................

................................................................

........ 3 1. REACTOR SAFETY

................................

................................................................

.... 3 1R01 Adverse Weather Protection (71111.01)

................................

............................

3 1R04 Equipment Alignment (71111.04)

................................

...................................... 4 1R05 Fire Protection (71111.05)

................................

.................................................

4 1R06 Flooding (71111.06)

................................

..........................................................

5 1R11 Licensed Operator Requalification Program (71111.11)

................................

.... 6 1R12 Maintenance Effectiveness (71111.12)

................................

..............................

7 1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)

......... 8 1R15 Operability Evaluations (71111.15)

................................

.................................... 8 1R18 Plant Modifications (71111.18)

................................

..........................................

9 1R19 Post-Maintenance Testing (71111.19)

..............................................................

10 1R20 Outage Activities (71111.20)

............................................................................

11 1R22 Surveillance Testing (71111.22)

.......................................................................12 1EP6 Drill Evaluation (71114.06)

................................

...............................................

13 2. RADIATION SAFETY

................................

................................................................

.14 2RS4 Occupational Dose Assessment (71124.04)

................................

.....................

14 4. OTHER ACTIVITIES

................................................................................................

...14 4OA1 Performance Indicator Verification (71151)

................................

.......................

14 4OA2 Identification and Resolution of Problems (71152)............................................

16 4OA5 Other Activities

................................

................................................................

.20 4OA6 Management Meetings

................................

.....................................................

23 SUPPLEMENTAL INFORMATION

................................

.............................................................

1 Key Points of Contact

................................

................................................................

.............

1 List of Items Opened, Closed, and Discussed

................................

........................................ 2 List of Documents Reviewed

................................

................................................................

.. 3 List of Acronymns Use

................................

................................................................

............

7

1 Enclosure SUMMARY OF FINDINGS

Inspection Report (IR) 05000454/201

3 00 2 and 05000455/201 3 00 2; 0 1/01/201 3 - 03/3 1/201 3; Byron Station, Units 1 &

2; Identification and Resolution of Problems; Other Activities

. This report covers a

3-month period of inspection by resident inspectors and announced baseline inspections by regional inspectors. Based on the results of this inspection, two NRC-identified finding

s of very low safety significance (Green) were

identified. One of these findings had an associated Non-Cited Violation (NCV) of NRC regulations.

The significance of inspection findings is indicated by their color (Greater than Green, or Green, White, Yellow, Red) and determined using Inspection Manual Chapter (IMC) 0609, "Significance Determination Process" (SDP)

dated June 2, 2011. Cross-cutting aspects are determined using IMC 0310, "Components Within the Cross

-Cutting Areas," dated October

28, 2011. All violations of NRC requirements are dispositioned in accordance with the NRC's Enforcement Policy dated January 28, 2013. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG

-1649, "Reactor Oversight Process (ROP)," Revision 4.

A. N RC-Identified and Self

-Revealed Findin g Cornerstone: Mitigating Systems

Green. The inspectors identified a finding of very low safety significance (Green) and

an associated NCV

of 10 CFR Part 50, Appendix B, Criterion III, "Design Control," when licensee personnel failed to properly evaluate the structural steel embedment plate which supported

Safety Injection (SI) pipe supports 1SI06025V and 1SI06030S. Specifically, the licensee failed to demonstrate compliance with the

American Institute of Steel Construction (AISC) and Seismic Category I linear elastic requirements. The

licensee entered this issue into their corrective action program (CAP) as Issue Report

(IR) 1478188. As part of their immediate corrective actions, the licensee performed an operability evaluation and

concluded the structural steel embedment plate was operable

, but nonconforming.

The inspectors determined that the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems

Cornerstone and adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences

(i.e., core damage). Specifically, the licensee failed to demonstrate compliance with AISC and Seismic Category I linear elastic requirements to ensure the structural steel embedment plate would maintain structural integrity when subjected to a design basis load. The inspectors determined that because the finding did not result in

a loss of operability or functionality, the finding was of very low safety significance (Green). This finding did not have a cross

-cutting aspect as it was not indicative of current performance. (Section 4

OA2.3) Green. The inspectors identified a finding of very low safety significance (Green) when licensee personnel failed to develop

inspection list

s that included all external flood protection features credited in current licensing bas

e s (CLB) documents as specified in Nuclear Energy Institute (NEI) 12-07, "Guidelines for Performing Walkdowns of Plant Flood Protection Features." Specifically, concrete flood barriers in the

fu el handling building (FHB) that protected safety

-related equipment in the auxiliary building and flood barriers for the spent fuel pool cooling pumps were not included in the licensee's

2 Enclosure flooding inspection lists, although these passive components were a critical element

of the licensee's flood mitigation strategy. The licensee entered this issue into their CAP as IR 1466355. Corrective actions included

plans to perform an inspection of the NRC

-identified features that were omitted from the inspection list

s and an extent-of-condition review. The inspectors determined that

the performance deficiency was more than minor because it was associated with the Protection Against External Factors (Flood Hazard) attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences

(i.e., core damage). Because the finding did not involve the loss or degradation of equipment or function specifically

designed to mitigate a

seismic, flooding, or severe weather initiating event (e.g., seismic snubbers, flooding barriers, tornado doors), the finding was of very low safety

significance (Gree n). This finding had a cross-cutting aspect in the Work Practices component of the Human Performance cross

-cutting area because licensee personnel failed to properly apply human error prevention techniques such as peer checking and proper documentation of activities H.4(a). (Section 4O

A5.2) B. Licensee-Identified Violations

No ne.

3 Enclosure REPORT DETAILS Summary of Plant Status

Unit 1 operated at or near full power throughout the inspection period.

Unit 2 operated at or near full power throughout most of the inspection period. On March 20, 2013 , at approximately 7:51 p

.m., the Unit 2 reactor was manually tripped when the only available

generator stator cooling water pump failed. All equipment operated as expected with a few minor exceptions.

Unit 2 returned to full power operation on March 25, 2013

, after the pump was repaired and returned to service. 1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity and Emergency Preparedness

1R01 Adverse Weather Protection

(71111.01)

.1 External Flooding

a. Inspection Scope

The inspectors evaluated the design, material condition, and procedures for coping with the design bas

es probable maximum flood. The evaluation included a review to check for deviations from the descriptions provided in the Updated Final Safety Analysis Report

(UFSAR) for features intended to mitigate the potential for flooding from external factors. As part of this evaluation, the inspectors checked for obstructions that could prevent

draining, checked that the roofs did not contain obvious loose items that could clog drains in the event of heavy precipitation, and determined whether

barriers required to mitigate flooding were in place and operable. Additionally, the inspectors performed a walkdown of the protected area to identify any modification to the site which could inhibit site drainage during a probable maximum precipitation event or allow water ingress past

a flood barrier. The inspectors also walked down underground bunkers/manholes subject to flooding that contained multiple trains or multiple function risk

-significant cables. The inspectors also reviewed the abnormal operating procedure for mitigating the design bas

es flood to ensure it could be implemented as written. Specific area

s inspected included the Unit 1 emergency

diesel generators, main steam tunnels, and the fuel handling building (FHB). This inspection constituted

one external flooding sample as defined in

Inspection Procedure (IP) 71111.01-05. b. Findings Findings identified during this inspection are

documented in Section 4

OA5, "Other Activities.

"

4 Enclosure 1R04 Equipment Alignment

(71111.04)

.1 Quarterly Partial System Walkdowns

a. Inspection

Scope The inspectors performed partial system walkdowns of the following risk

-significant systems: Unit Common Train 'A

' Control Room Chiller with Train 'B' Control Room Chiller Out of Service for Maintenance;

Un it 2 Instrument Inverter 212 with Instrument Inverter 214 Out of Service for Maintenance; and

Unit 2 Train 'A' Essential Service Water (SX) with Unit 2 Train 'B' SX Out of Service for Maintenance.

The inspectors selected these systems based on their risk significance relative to the Reactor Safety Cornerstones at the time they were inspected. The inspectors attempted to identify any discrepancies that could impact the function of the system and therefore

potentially increase risk. The inspectors reviewed applicable operating procedures, system diagrams, the UFSAR, Technical Specification (TS) requirements, outstanding work orders (WOs), issue reports (IRs), and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have rendered the systems incapable of performing their intended function

(s). The inspectors also walked down accessible portions of the systems to verify system components and support equipment were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no obvious deficiencies. The inspectors also verified that the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program

(CAP) with the appropriate significance characterization. Documents reviewed are listed in the Attachment.

This inspection constituted three partial system walkdown samples as defined in

IP 71111.04-05. b. Findings No findings were identified.

1R05 Fire Protection

(71111.05)

.1 Routine Resident Inspector Tours

(71111.05Q)

a. Inspection Scope

The inspectors conducted fire protection walkdowns which were focused on the availability, accessibility, and the condition of firefighting equipment in the following risk-significant plant areas

5 Enclosure Division 11 Miscellaneous Electrical Equipment and Battery Room Fire Are a 5.6-1; Division 21 Miscellaneous Electrical Equipment and Battery Room Fire

Area 5.6-2; Division 12 Miscellaneous Electrical Equipment and Battery Room Fire

Area 5.4-1; and Division 22 Miscellaneous Electrical Equipment and Battery Room Fire Area 5.4-2. The inspectors reviewed areas to assess if the licensee had implemented a fire protection program that adequately controlled combustibles and ignition sources within the plant;

effectively maintained fire detection and suppression capability;

maintained passive fire protection features in good material condition;

and implemented adequate compensatory measures for out

-of-service, degraded or inoperable fire protection equipment, systems, or features in accordance with the licensee's fire plan. The

inspectors selected fire areas based on their overall contribution to internal fire risk as documented in the plant's Individual Plant Examination of External Events with later additional insights, their potential to impact equipment which could initiate or mitigate a plant transient, or their impact on the plant's ability to respond to a security event. Using the documents listed in the Attachment, the inspectors verified that fire hoses and extinguishers were in their designated locations and available for immediate use; that fire detectors and sprinklers were unobstructed;

that transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition. The inspectors also verified that minor issues identified during the inspection were entered into the licensee's CAP. This inspection constituted four quarterly fire protection inspection samples as defined in

IP 71111.05-05. b. Findings No findings were identified

1R06 Flooding (71111.06) .1 Internal Flooding

a. Inspection Scope

The inspectors reviewed selected risk important plant design features and licensee procedures intended to protect the plant and its safety

-related equipment from internal flooding events. The inspectors reviewed flood analyses and design documents,

including the UFSAR, engineering calculations, and abnormal operating procedures to identify licensee commitments. In addition, the inspectors reviewed licensee drawings to identify areas and equipment that may be affected by internal flooding caused by the failure or misalignment of nearby sources of water, such as the fire suppression or the

circulating water systems. The inspectors also reviewed the licensee's corrective action documents with respect to past flood

-related items identified in the CAP to verify the adequacy of the corrective actions. The inspectors performed a walkdown of the following plant area

s to assess the adequacy of watertight doors and verify drains and

6 Enclosure sumps were clear of debris and were operable, and that the licensee complied with existing commitments:

Unit 1 and

Unit 2 SX Pump Rooms

Documents reviewed are listed in the Attachment. This inspection constituted one internal flooding sample as defined in IP

71111.06-05. b. Findings No findings were identified.

1R11 Licensed Operator Requalification Program

(71111.11)

.1 Resident Inspector Quarterly Review

(71111.11Q)

a. Inspection Scope

On January 31, 201 3 , the inspectors observed a crew of licensed operators in the plant

simulator during licensed operator requalification examinations to verify that operator performance was adequate, evaluators were identifying and documenting crew performance

problems , and training was being conducted in accordance with licensee procedures. The inspectors evaluated the following areas:

licensed operator performance;

crew's clarity and formality of communications;

ability to take timely actions in the conservative direction;

prioritization, interpretation, and verification of annunciator alarms;

correct use and implementation of abnormal and emergency procedures;

control board manipulations;

oversight and direction from supervisors; and

ability to identify and implement appropriate TS actions and Emergency Plan

actions and notifications.

The crew's performance in these areas was compared to pre

-established operator action expectations, procedural compliance, and successful critical task completion requirements. Documents reviewed are listed in the Attachment.

In addition, the inspectors observed licensed operator performance in the actual plant and the main control room during this calendar quarter.

This inspection constituted

one quarterly licensed operator requalification program sample as defined in IP

71111.11-05. b. Findings No findings were identified.

7 Enclosure .2 Resident Inspector Quarterly Observation of Heightened Activity or Risk

(71111.11Q)

On March 12, 2013, the inspectors observed control room operators during the emergent failure of Unit 1 core exit thermocouple 50

, and on March 22, 2013

, the inspectors observed plant startup following the Unit 2

forced outage.

These were activities

that required heightened awareness and

was related to increased risk. The inspectors evaluated the following areas:

licensed operator performance;

crew's clarity and formality of communications;

ability to take timely actions in the conservative direction;

prioritization, interpretation, and verification of annunciator alarms;

correct use and implementation of procedures;

control board manipulations;

oversight and direction from supervisors; and

ability to identify and implement appropriate TS actions and Emergency Plan actions and notifications.

The crew's performance in these areas was compared to pre

-established operator action expectations, procedural compliance, and successful critical task completion requirements.

Documents reviewed are listed in the Attachment.

This inspection constituted

one quarterly licensed operator heightened activity/risk sample as defined in IP

71111.11-05. b. Findings No findings were identified.

1R12 Maintenance Effectiveness (71111.1 2) .1 Routine Quarterly Evaluations

(71111.12Q)

a. Inspection

Scope The inspectors evaluated degraded performance issues involving the following risk-significant systems:

Failure of Unit 1 Power Range Channel N43; and

Review of Maintenance Rule Assessment for the

Period of January 2011 to June 2012. The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the CAP with the appropriate significance characterization. Documents reviewed are listed in the

Attachment. This inspection constituted

two quarterly maintenance effectiveness samples as defined in IP 71111.12-05.

8 Enclosure b. Findings No findings were identified

. 1R13 Maintenance Risk Assessments and Emergent Work Control

(71111.13)

.1 Maintenance Risk Assessments and Emergent Work Control

a. Inspection

Scope The inspectors reviewed the licensee's evaluation and management of plant risk for the maintenance and emergent work activities affecting risk

-significant and safety

-related equipment listed below to verify that the appropriate risk assessments were performed

prior to removing equipment for work:

Unit 2 Train 'A' Charging Pump Emergent Failure with t

he Unit 1 Train 'A'

SX Pump Out of Service for Planned Maintenance;

Unit 1 Power Range Channel N43 Emergent Failure with Unit 2 Train 'B' SX

Inoperable for Planned Maintenance; and

Unit 1 Train 'B' Auxiliary Feedwater Pump Work Window.

These activities were selected based on their potential risk significance relative to the Reactor Safety Cornerstones. As applicable for each activity, the inspectors verified that risk assessments were performed as required by 10

CFR 50.65(a)(4) and were accurate and complete. When emergent work was performed, the inspectors verified that plant risk was promptly reassessed and managed. The inspectors reviewed the scope of maintenance work, discussed the results of the assessment with the licensee's probabilistic risk analyst or shift technical advisor, and verified plant conditions were consistent with the risk assessment. The inspectors also reviewed TS requirements and walked down portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid and applicable requirements were met

. This inspection constituted

three maintenance risk assessments and emergent work control samples as defined in IP

71111.13-05. b. Findings No findings were identified.

1R15 Operability Evaluations

(71111.15)

.1 Operability Evaluations

a. Inspection

Scope The inspectors reviewed the following issues:

Unit 1 Division 111 Battery Racks

Support Questions

Capacity of Pressurizer Power Operated Relief Valve (PORV) Air Accumulators

During Natural Circulation Cooldown;

9 Enclosure Operation of SX Pump with Single Cubical Cooler; and

Unit 1 Power Range Channel N43 TS 3.3.1.D Entry.

The inspectors selected these potential operability issues based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the evaluations to ensure that TS operability was properly justified and the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the TS and UFSAR to the licensee's evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. The inspectors determined, where appropriate, compliance with bounding limitations associated with the evaluations. Additionally, the inspectors reviewed a sample of corrective acti

on documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Documents reviewed are listed in the Attachment.

This inspection constituted four operability inspection samples as defined i

n IP 71111.15-05. b. Findings No findings were identified.

1R 18 Plant Modifications

(71111.18)

.1 Plant Modifications

a. Inspection Scope

T he inspectors reviewed the following modification

Reactor Containment Fan Cooler (RCFC) Check Dampers Closure Spring Changes The inspectors reviewed the configuration changes and associated

10 CFR 50.59 safety evaluation screening against the design basis, the UFSAR, and the TS, as applicable, to verify that the modification did not affect the operability or availability of the affected system. The inspectors, as applicable, observed ongoing and completed work activities to ensure that the modifications were installed as directed

and consistent with the design control documents; the modifications operated as expected; post-modification testing adequately demonstrated continued system operability, availability, and reliability; and that operation of the modifications did not impact the operability of any interfacing systems. As applicable, the inspectors verified that relevant procedure, design, and licensing documents were properly updated. Lastly, the inspectors discussed the plant

modification with operations, engineering, and training personnel to ensure that the individuals were aware of how the operation with the plant modification in place could impact overall plant performance.

Documents reviewed are listed in the Attachment

.

10 Enclosure This inspection constituted one

permanent plant modification sample as defined in

IP 71111.18-05. b. Findings No findings were identified.

1R19 Post-Maintenance Testing

(71111.19)

.1 Post-Maintenance Testing

a. Inspection

Scope The inspectors reviewed the following post

-maintenance testing activities to verify that procedures and test activities were adequate to ensure system operability and functional capability: Unit 1 Bus 144 Breaker 1442 Following Lockout Relay Replacement;

Unit 1 Train 'A'

SX Cubical Coolers Following Repairs;

Unit 2 Instrument Inverter 214 Following Coil Replacement; and

Unit 2 Train 'B' Generator Stator Water Cooling System Pump Following Motor Replacement.

These activities were selected based upon the structure, system, and component's

(SSC's) ability to impact risk. The inspectors evaluated these activities for the following (as applicable):

the effect of testing on the plant had been

adequately addressed; testing was adequate for the maintenance performed; acceptance criteria were clear and

demonstrated operational readiness; test instrumentation was appropriate; tests were performed as written in accordance with properly reviewed and

approved procedures; equipment was returned to its operational status following testing (temporary

modifications or jumpers required for test performance were properly removed after test completion); and test documentation was properly evaluated. The inspectors evaluated the activities against TSs, the UFSAR, 10

CFR Part 50 requirements, licensee procedures, and various NRC

generic communications to ensure that the test results adequately ensured that the equipment met the licensing bas

es and design requirements. In addition, the inspectors reviewed corrective action

documents associated with post

-maintenance tests to determine whether the licensee was identifying problems and entering them in

to the CAP at the appropriate threshold

and that the problems were being corrected commensurate with their importance to safety. Documents reviewed are listed in the Attachment.

This inspection constituted four post-maintenance testing samples

as defined in

IP 71111.19-05. b. Findings No findings were identified.

11 Enclosure 1R2 0 Outage Activities

(71111.20)

.1 Unit 2 Forced Outage

a. Inspection Scope

On March 20, 2013, at 7:51 p.m., licensee personnel performed a manual trip of the Unit 2 reactor. The reactor was manually tripped in accordance with site procedures when the only operating and available electrical generator stator cooling water pump

tripped unexpectedly

. The inspectors responded to the site and assessed the cause of the trip, performed follow

-up inspection of minor equipment failures, and immediately communicated any observations to NRC management.

The inspectors reviewed outage equipment configuration and risk management, verified electrical lineups, monitored decay heat removal, observed reactor startup activities, and reviewed the identification and resolution of problems associated with the forced outage. All safety

-related equipment operated as designed.

Some nonsafety

-related equipment experienced minor malfunctions.

For example:

The 'B' reactor trip breaker closed indication light extinguished as expected, however the open indication light did not illuminate to indicate that

the breaker was

open. A n operator was dispatched and verified the breaker was open.

Subsequently

, a burned out 'B' reactor trip breaker open indication light bulb was replaced.

The control

rod in position M

-12 (control bank D) had a general warning light flashing, although its associated rod bottom light was lit. Following troubleshooting, a logic card was replaced in the control rod drive cabinet

to address the issue

. Following the Unit 2

trip , light smoke was reported to be coming from the Unit 2 'A'

main feedwater pump motor.

It was later determined that when the 2A main feedater pump was shut down that its associated motor heater automatically energized.

An abnormally large amount of dust had built up on the heater and when it energized the dust "burned off."

The licensee addressed these issues

and Unit 2

was restarted and synchronized to the electrical grid on March 22, 2013. Documents reviewed are listed in the Attachment. This inspection constituted one other outage sample as defined in IP

71111.20-05. b. Findings No findings

were identified.

.2 Unit 2 Refueling Outage

a. Inspection Scope

The inspectors reviewed the Outage Safety Plan and contingency plans for the

Unit 2 refueling outage (RFO) that began on April 7, 2013, to confirm that the licensee had appropriately considered risk, industry operating experience, and previous site specific

12 Enclosure problems in developing and implementing a plan that assured maintenance of defense in depth. A complete list of accomplished inspection activ ities will be document

ed following completion of the Unit 2 RFO. This inspection constituted a partial RFO sample as defined in IP 71111.20

-05. b. Findings No findings were identified.

1R22 Surveillance Testing

(71111.22) .1 Surveillance Testing

a. Inspection

Scope The inspectors reviewed the test results for the following activities to determine whether

risk-significant systems and equipment were capable of performing their intended safety function and to verify testing was

conducted in accordance with applicable procedural and TS requirements:

Unit 1 Train 'B' Containment Spray Pump

Quarterly Surveillance

Unit 1 Train 'A' Diesel Generator Operability Surveillance;

Unit 1 Train 'A' Solid State Protection System Surveillance

Unit 2 K636 Engineered Safety Features (ESF) Relay Surveillance; and

Unit 2 K644 ESF Relay Surveillance.

The inspectors observed

in-plant activities and reviewed procedures and associated records to determine the following:

did preconditioning occur

were the effects of the testing adequately addressed by control room personnel or engineers prior to the commencement of the testing;

were acceptance criteria clearly stated, demonstrate

operational readiness, and consistent with the system design basis;

was plant equipment calibration correct, accurate, and properly documented;

were as left setpoints within required ranges; and was the calibration frequency in accordance with TSs, the U

FSAR, plant procedures, and applicable commitments;

was measuring and test equipment calibration current;

was the test equipment used within the required range and

accuracy and were applicable prerequisites described in the test procedures satisfied;

did test frequencies me

et TS requirements to demonstrate operability and reliability;

were tests performed in accordance with the test procedures and other applicable procedures;

were jumpers and lifted leads controlled and restored where used;

were test data and results accurate, complete, within limits, and valid;

13 Enclosure was test equipment removed following

testing; where applicable for

in-service testing activities, was testing performed in accordance with the applicable version of Section

XI of the American Society of Mechanical Engineers (ASME) Code, and were reference values consistent with the system design basis;

was the unavailability of the tested equipment appropriately considered in the performance indicator data;

where applicable, were test results not meeting acceptance criteria

addressed with an adequate operability evaluation , or was the system or component

declared inoperable;

where applicable for safety

-related instrument control surveillance tests, was the reference setting data accurately incorporated in

to the test procedure;

was equipment returned to a position or status required to support the

performance of its safety function

following testing

were all problems identified during the testing appropriately documented and dispositioned in the licensee's CAP; where applicable, were annunciators and other alarms demonstrated to be functional and were annunicator and alarm setpoints consistent with design documents; and

where applicable, were alarm response procedure entry points and actions consistent with the plant design and licensing documents.

Documents reviewed are

listed in the Attachment.

This inspection constituted five routine surveillance testing samples

as defined in

IP 71111.22, Sections

-02 and -05. b. Findings No findings were identified.

1EP6 Drill Evaluation

(71114.06)

.1 Training Observation

a. Inspection Scope

The inspector

s observed a simulator training evolution for licensed operators on

January 31, 2013 , which required Emergency Plan implementation by a licensee operations crew. This evolution was planned to be evaluated and included in performance indicator data regarding drill and exercise performance. The inspectors observed event classification and notification activities performed by the crew. The inspectors also attended the post

-evolution critique for the scenario. The focus of the inspectors' activities was to note any weaknesses and deficiencies in the crew's performance and ensure that the licensee evaluators noted the same issues and entered

them into the CAP. As part of the inspection, the inspectors reviewed the scenario package and other documents listed in the

Attachment.

This inspection constituted one training evolution with emergency preparedness drill sample as defined in IP

71114.06-05.

14 Enclosure b. Findings No findings were identified.

2. RADIATION SAFETY

2RS4 Occupational Dose Assessment

(71124.04) This inspection constituted a partial

sample as defined in IP 71124.04

-0 5. .1 External Dosimetry

(02.0 2) a. Inspection Scope

The inspectors evaluated whether the licensee's dosimetry vendor is National Voluntary Laboratory Accreditation Program (NVLAP) accredited and if the approved irradiation test categories for each type of personnel dosimeter used were consistent with the types and energies of the radiation present

and the way the dosimeter was being used (e.g., to measure deep dose equivalent, shallow dose equivalent, or lens dose equivalent).

b. Findings No findings were identified.

4. OTHER ACTIVITIES

4OA1 Performance Indicator Verification

(71151) .1 Unplanned Scrams Per 7000 Critical Hours

a. Inspection Scope

The inspectors sampled licensee submittals for the Unplanned Scrams Per 7000 Critical Hours Performance Indicator (PI) for both Unit 1 and Unit 2 for the period from the first quarter 201

2 through the

fourth quarter 2012. To determine the accuracy of the PI data reported during those periods, PI definitions and guidance contained in Nuclear Energy Institute (NEI)

99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, dated October 2009 , were used. The inspectors reviewed the licensee's operator narrative logs, IRs, event reports and

NRC Integrated

Inspection

Reports for the period of January 2012

through December 2012 to validate the accuracy of the submittals. The inspectors also reviewed the licensee's

IR database to determine if any problems had been identified with the PI data collected or transmitted for this indicator.

Documents reviewed are listed in the Attachment

. This inspection constitut

ed two unplanned scrams per 7000 critical hours sample

s as defined in IP

71151-05. b. Findings No findings were identified.

15 Enclosure .2 Unplanned Scrams

with Complications

a. Inspection Scope

The inspectors sampled licensee submittals for the Unplanned Scrams with Complications

PI for Unit 1 and Unit 2 for the period from the

first quarter 201

2 through the fourth quarter 201

2. To determine the accuracy of the PI data reported during those periods, PI definitions and guidance contained in

NE I 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, dated October 2009 , were used. The inspectors reviewed the licensee's operator narrative logs, IRs, event reports and NRC Integrated Inspection

Reports for the period of January 201

2 through December 201

2 to validate the accuracy of the submittals. The inspectors also reviewed the licensee's IR

database to determine if any problems had been identified with the PI data collected or

transmitted for this indicator. Documents reviewed are listed in the Attachment

. This inspection constituted two unplanned scrams with complications

sample s as defined in IP

71151-05. b. Findings No findings were identified. .3 Unplanned Power Changes

Per 7000 Critical Hours

a. Inspection Scope

The inspectors sampled licensee submittals for the Unplanned Power Changes

Per 7000 Critical Hours

PI for Unit 1 and Unit 2

for the period from the first quarter 201

2 through the fourth quarter 201 2. To determine the accuracy of the PI data reported during those periods, PI definitions and guidance contained in NEI 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, dated October 2009 , were used. The inspectors reviewed the licensee's operator narrative logs, IRs, maintenance rule records, event reports

, and NRC Integrated Inspection

Reports for the period of

January 201

2 through December 201

2 to validate the accuracy of the submittals. The inspectors also revi

ewed the licensee's IR

database to determine if any problems had been identified with the PI data collected or transmitted for this indicator. Documents reviewed are listed in the Attachment

. This inspection constituted two unplanned power changes

per 7000 critical hours samples as defined in IP

71151-05. b. Findings No findings were identified.

16 Enclosure 4OA2 Identification and Resolution of Problems

(71152) .1 Routine Review of Items Entered into the Corrective Action Program

a. Inspection Scope

As part of the various baseline inspection procedures discussed in previous sections of this report, the inspectors routinely reviewed issues during baseline inspection activities and plant status reviews to verify that they were being entered into the licensee's CAP at an appropriate

threshold, that adequate attention was being given to timely corrective actions, and that adverse trends were identified and addressed. Attributes reviewed

includ ed the complete and accurate identification of the problem; that timeliness was commensurate

with safety significance; that evaluation and disposition of performance issues, generic implications, common causes, contributing factors, root causes, extent

-of-condition reviews, and previous occurrence reviews were proper and adequate; and that the classification, prioritization, focus, and timeliness of corrective actions were commensurate with safety and sufficient to prevent recurrence of the issue. Minor issues entered into the licensee's CAP as a result of the inspectors' observations are listed in the Attachment

. These routine reviews for the identification and resolution of problems did not constitute any additional inspection samples. Instead, by procedure they were considered an integral part of the inspections performed during the quarter and documented in Section 1 of this report.

b. Findings No findings were identified.

.2 Daily Corrective Action Program Reviews

a. Inspection Scope

To facilitate the identification of repetitive equipment failures and human performance issues for follow

-up, the inspectors performed a daily screening of

items entered into the licensee's CAP. This review was accomplished through inspection of the station's daily IR packages. These daily reviews were performed by procedure as part of the inspectors' daily plant status monitoring activities and, as such, did not constitute any separate inspection samples. b. Findings No findings were identified.

17 Enclosure .3 Selected Issue Follow

-Up Inspection:

Actions to Address Engineering

-Related Issue s Identified at Braidwood During NRC Inspections

a. Inspection Scope

The inspectors reviewed evaluations and calculations as well as related IRs to assess the adequacy of the licensee

's extent-of-condition review of issues identified during the Braidwood Station Unit

1 and Unit 2 Evaluation of Changes, Tests, or Experiments and Permanent Plant Modifications inspection s performed in 2011. This review included an analysis that was performed by the licensee to determine the effects of lead shielding on the Unit 1 Safety Injection (SI) system

piping subsystem

and associated

pipe supports

. This review constituted one in

-depth problem identification and resolution sample as defined in IP 711

52-05. b. Findings Embedment Plate Design Deficiencies

Introduction: The inspectors identified a finding of very low safety significance (Green)

and an associated Non

-Cited Violation (NCV) of 10 CFR Part 50, Appendix B, Criterion III, "Design Control," when licensee personnel failed

to properly evaluate the structural steel embedment plate which supported

SI pipe supports 1SI06025V and 1SI06030S.

Description

The SI system is part of the emergency core cooling system (ECCS). Section 6.3.1

of the Byron UFSAR stated, in part, that

the primary function of the ECCS is to remove the stored and fission product decay heat from the reactor during accident conditions and provide shutdown capability for design basis accidents by means of boron injection.

Piping Subsystem 1SI06 is part of the SI System and is a safety

-related ASME Class II, Seismic Category I subsystem located

in the curved wall area of the auxiliary building. A

structural steel embedment plate that supports safety

-related pipe supports 1SI06025V and 1SI06030S is located in

the auxiliary building, which is a Seismic Category I structure. Section 3.8.4.5.2 of the UFSAR describes

requirements for structural steel design inside the auxiliary building and states, in part, "The stresses and strains of structural steel are limited to those specified

in the AISC

(American Institute of Steel Construction

)-" Also, this section required that stresses be

held within the elastic range

and that no plastic deformation

was allowed.

The inspectors reviewed Calculation No. 13.2.29BY, "Mechanical Component Support 1SI06025V,"

Revision 2X

that evaluate d pipe support

s 1SI06025V and 1SI06030S. These supports were attached to a structural embedment plate in

the auxiliary building. The structural steel embedment plate evaluation was also included in this calculation.

During a review of Calculation No. 13.2.29BY, the inspectors identified a number of concerns, including the following:

18 Enclosure The calculated bending stress on the embedment plate was greater than the allowable bending stress by about 67 percent and the licensee relied on

engineering judgment to demonstrate compliance with the

design and licensing basis requirements

The calculation used the actual instead of minimum material yield stress of the embedment plate to calculate the allowable bending stress;

The calculation used an acceptance criteria which permitted plastic or permanent deformation through yielding of the structural steel embedment plate and redistribution of stresses in the embedment plate due to applied loads;

The calculation did not include an evaluation for

severe environmental load combination

s as described in UFSAR Table 3.8-9 and as described in

UFSAR Section 3.8.4.3, "Loads and Loading Combinations;

" and The calcu la t ion did not consider applied stresses due to self

-weight and self

-weight seismic excitation of tube steel pipe support members.

The inspectors determined that the engineering judgment used to demonstrate compliance with the design and licensing basis was not valid because the AISC required that the allowable bending stress be

determined using the minimum yield stress of the material. In addition, UFSAR Section 3.8.4.5.2 specified no plastic or permanent deformation due to applied stresses. The inspectors also identified that the structural steel embedment plate was not qualified for the severe environmental load combination as described in UFSAR Table 3.8-9 and as required by UFSAR Section 3.8.4.3. The licensee entered this issue into their CAP as IR 1478188, "NRC Identified Use of CMTR in a 80's Calculation

." As part of their immediate corrective actions, the licensee performed an operability

evaluation and

concluded the structural steel embedment plate was operable

, but nonconforming.

Analysis: The inspectors determined that the failure to design

the structural steel embedment plate which supported pipe supports 1SI06025V and 1SI06030S in accordance with AISC and Seismic Category I linear elastic requirements

was a performance deficiency

. The inspectors determined that the performance deficiency was

more than minor because it was associated with the Design Control attribute of the Mitigating Systems C ornerstone and adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences

(i.e., core damage). Specifically, the licensee did not demonstrate that the structural steel embedment plate which supported pipe supports 1SI06025V and 1SI06030S would maintain structural linear elastic integrity when subjected to design loads.

The inspectors reviewed Attachment 0609.04, "Initial Characterization of Findings,"

Table 3 - SDP Appendix Router. The inspectors answered '

N o' to all of the questions in Sections A through

E of Table 3 and therefore the finding was evaluated using the SDP in accordance with IMC 0609, "The Significance Determina

tion Process (SDP) for Findings A

t-Power," Appendix A, Exhibit 2, "Mitigating Systems Screening

19 Enclosure Questions." The inspectors answered '

Yes' to Question 1

- If the finding is a deficiency affecting the design or qualification of a mitigating SSC

[Structure, System, or Component], does the SSC maintain its operability or functionality?

Specifically, the design deficiency was confirmed not to result in a loss of operability of the structural steel embedment plate. Therefore, the finding was determined to have

very low safety significance (Green).

The inspectors performed an independent review of the operability evaluation and had no further concerns.

The inspectors did not identify a cross

-cutting aspect associated with this finding because the calculation

was from the 1980

's and was therefore not representative of current performance.

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, "Design Control," requires, in part, that design control measures shall provide for verifying or checking the adequacy

of the design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program.

Piping Subsystem 1SI06 is part of the Saf

e ty Injection System and is a

safety-related ASME Class II, Seismic Category I subsystem located in the curved wall area of the auxiliary building. A structural steel embedment plate that supports safety

-related pipe supports 1SI06025V and 1SI06030S is located in the auxiliary building, which is a Seismic Category I structure. Section 3.8.4.5.2 of the UFSAR describes requirements for structural steel design inside the auxiliary building and states, in part, "The stresses and strains of structural steel are limited to those specified in the AISC-." Also, Section 3.8.4.5.2 of the UFSAR

required that stresses be within the elastic range and that no plastic deformation was allowed.

Contrary to the above, from initial construction to

February 21, 2013

, the licensee failed to demonstrate the design adequacy of the embedment plate

which supported safety

-related Safety Injection

pipe supports 1SI06025V and 1SI06030S. Specifically, the design for the structural steel embedment plate

which supported safet

y-related Safety Injection pipe supports 1SI06025V and 1SI06030S

w as inadequate, in that Calculation No. 13.2.29BY, "Mechanical Component Support 1SI06025V," Revision 2X, which was a quality calculation, did not demonstrate that the embedment plate would meet AISC and Seismic Category I linear elastic requirements.

Because this violation was of very low safety significance and it was entered into the

licensee's CAP as I R 1478188, this violation is being treated as a

NCV, consistent with Section 2.3.2 of the NRC Enforcement Policy. As part of their immediate corrective actions, the licensee performed an operability evaluation and

concluded the structural steel embedment plate was operable.

(NCV 05000454/2013002

-01 , "Embedment Plate Design Deficiencies

") .4 Selected Issue Follow

-Up Inspection: Valves in LCO Due to Abandonment

a. Inspection Scope During a review of items entered in the licensee's CAP, the inspectors identified an

IR regarding equipment that had been

abandoned in place. Specifically, IR 1306607, "Long Term LCO [Limiting Condition for Operation] Extent of Condition Review Per

IR 1298667," characterized a series of valves as abandoned. The valves were also

20 Enclosure characterized as

having a containment isolation function. The inspectors reviewed the licensees' procedures associated with containment leak rate testing and recent test data to ensure that the performance of the abandoned valves remained acceptable.

This review constituted

one in-depth problem identification and resolution sample

as defined in IP

71152-05. b. Findings No findings were identified. 4OA5 Other Activities

.1 (Closed) NRC Temporary Instruction (TI) 2515/187

- "Inspection of Near

-Term Task Force Recommendation 2.3 Flooding Walkdowns"

As discussed in NRC Integrated Inspection Report 05000454/2012005; 05000455/2012005 , the inspect or s previously verified that licensee

walkdown packages Unit 1 13-Line Wall, Unit

1 1A and 1D Main Steam Isolation Valve Room Probable Maximum Precipitation

(PMP) Curb, and River Screen House Penetration RH

-15C , contained the elements specified in Nuclear Energy Institute (NEI) 12-07 , "Guidelines for Performing Walkdowns of Plant Flood Protection Features

." During the previous quarter, the inspectors accompanied the licensee on their walkdown of the River Screen House, Penetration RH

-15C; and Unit 1 A and D

Main Steam Isolation Valve Room PMP Curb and verified that the licensee confirmed the following

flood protection features:

Visual inspection of the flood protection feature was performed if the flood protection feature was relevant.

External visual inspection for indications of degradation that would prevent its credited function from being performed was performed.

Critical SSC dimensions were measured

. Available physical margin, where applicable, was determined.

Flood protection feature functionality

was determined using either visual observation or by review of other documents.

During this quarter, the inspectors conducted additional independent walkdown

s to verify licensee compliance with inspection guidance contained in TI 2515/187.

The area selected was the building that houses the spent fuel pool, the

f uel handling building (FHB). There were several reasons for selecting this area.

For example, the spent fuel pool filtering and heat removal systems are located in the FHB

. In addition, the FHB has access ways that lead to other portions of the auxiliary building, a safety

-related structure.

The Byron UFSAR identified

that the FHB

was not subject to flooding.

The inspectors questioned why the FHB would not be subject to flooding since portions of it are at ground level, a roll

-up door in this building leads to an adjacent structure which has a

21 Enclosure roll-up door that leads outside, and railway channels in the FHB have been observed to contain rain water

. The inspectors verified that noncompliances with

current licensing requirements, and issues identified in accordance with the 10 CFR 50.54(f) letter, Item 2.g of Enclosure 4, were entered into the licensee's CAP. In addition, issues identified in response to Item 2.g that could challenge risk significant equipment and the licensee's ability to mitigate the consequences will be subject to additional NRC evaluation.

.2 Failure to Properly Scope All the Pertinent External Flood Protection Features into Walkdown List

s in Accordance with Nuclear Energy Institut

e (NEI) 12-07 Introduction

The inspectors identified a finding of very low safety significance (Green) when licensee personnel failed

to develop inspection lists that included all external flood protection features credited in current licensing bas

e s (CLB) documents as specified in NEI 12-07, "Guidelines for Performing Walkdowns of Plant Flood Protection Features."

Specifically, the inspection

list s did not include several passive components

in the FHB

which were an essential element

of the Byron flood mitigation strategy.

Description

The inspectors reviewed the licensee's inspection and walkdown documents associated with flooding reviews

performed in accordance with NEI

12-07 , "Guidelines for Performing Walkdowns of Plant Flood Protection Features

," in response to a letter from the NRC to licensees

pursuant to 10 CFR 50.54(f).

During the review, the inspectors identified that the licensee had completed their scoping of components for

TI 2515/187, "Inspection of Near

-Term Task Force Recommendation 2.3 Flooding Walkdowns,"

and failed to properly scope all flood protection features credited in the CLB documents for flooding events.

Specifically, while reviewing the Flooding Features Walkdown List

used to inspect and test design bas

es flood mitigating equipment in accordance with the NRC

-endorsed guidance of NEI 12

-07, the inspectors identified that the flood protection features in the FHB were not included.

The flood protection features

in the FHB were designed to protect the auxiliary building

, includin g residual heat removal and

containment spray pumps from site external flooding scenarios

, and were an essential part of the Byron design basis flood mitigation strategy.

In particular, the

concrete steps inside the FHB were designed to prevent flood wate

rs that enter

the FHB from reaching a door that would allow water to enter the auxiliary building.

Because the licensee

did not adequately follow the guidance in NEI 12-07 and identify components in the FHB that serve

d as passive flooding barriers, these components were not scheduled for visual inspection

s or walkdowns.

As a result, the licensee failed to recognize walkdowns of these passive flooding barriers were required to adequately respond to the March 12, 2012 letter from the NRC to licensees that discussed these reviews. The licensee acknowledged that they may

not have identified these flood barriers during subsequent reviews if the inspectors had not identified the issue

. The licensee entered this issue into their CAP as IR 1466355, "Update UFSAR

Regarding External Flooding

." Corrective actions included plans to perform an inspection of the NRC

-identified passive flooding features that were omitted from the inspection lists and an extent

-of-condition review.

Analysis: The inspectors determined that the failure to include concrete flood barriers in the FHB in the flooding inspection lists developed to address NEI 12

-07, although these

22 Enclosure passive components were a critical element of the Byron flood mitigation strategy, was a performance deficiency.

Using the guidance in IMC 0612, "Power Reactor Inspection Reports," Appendix B, "Issue Screening," the inspectors determined this finding affected the Mitigating Systems

Cornerstone.

The inspectors determined that the performance deficiency was more than

minor because it was associated with the Protection Against External Factors (Flood Hazard) attribute of the Mitigating Systems

Cornerstone and adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences

(i.e., core damage). Specifically, the concrete flood barriers in the FHB protecting important safety-related equipment in the auxiliary building as well as the flood barriers for the

spent fuel pool cooling pumps were not properly scoped into the licensee's walkdown lists. The inspectors reviewed Attachment 0609.04, "Initial Characterization of Findings,"

Table 3 - SDP Appendix Router. The inspectors answered 'No' to all of the questions in Sections A through

E of Table 3 and therefore the finding was evaluated using the SDP in accordance with IMC 0609, "The Significance Determination Process (SDP) for Findings A

t-Power," Appendix A, Exhibit 2, "Mitigating Systems Screening Questions." The inspectors answered 'No' to Question B for the External Event Mitigation Systems

- Does the finding involve the loss or degradation of equipment or function specifically designed to mitigate a seismic, flooding, or sever

e weather initiating event (e.g., seismic snubbers, flooding barriers, tornado doors)?

Therefore, the finding was determined to have

very low safety significance (Green).

This finding had a cross

-cutting aspect in the Work Practices component

of the Human Performance cross

-cutting area because licensee personnel did not properly apply human error prevention techniques such as peer checking and proper documentation of

activities H.4(a). Enforcement

This finding did not involve enforcement action because no violation of a regulatory requirement was

identified.

Because this finding d

oes not involve a violation and is of very low safety significance, it is identified as a finding (FIN). (FIN 05000454/2013002-0 2; 05000455/2013002

-02 , Failure to Properly Scope All Pertinent External Flood Protection Features into

Wa lkdown List s in Accordance with Industry Guidance NEI 12

-07) .3 (Closed) Unresolved Item 05000454/2011005

-03; 05000455/2011005

-03: Use of Thermolumiscent Dosimeters

May Not Be Consistent With the Methods Used

By the National Voluntary Laboratory

Accreditation

Program Accreditation Process

In the fourth quarter of 2011

, the inspectors identified that the licensee's use of thermoluminescent dosimeters (TLDs) may not be consistent with the methods used by the NVLAP accreditation process. Specifically, the licensee used a vendor to supply and process dosimeters that measure radiation exposure for the monitored workers. This vendor is NVLAP

-accredited for beta, gamma, neutron, mixture of beta/gamma, and mixture of neutron/gamma radiations. However, the licensee used the TLDs when

workers may be exposed to beta, gamma, and neutron radiations within the same monitoring period. The inspectors determined that this mixture of three radiation types may not be aligned with the accreditation process

, and opened Unresolved Item (URI)

23 Enclosure 05000454/2011005

-03; 05000455/2011005

-03 to evaluate the issue. The inspectors requested technical assistance from the Office of Nuclear Reactor Regulation (NRR) through Task Interface Agreement

(TIA) 2012-05 (ML 12268A330), the results of which are discussed below.

Title 10 CFR 20.1501(c)(2) requires that the dosimeter processor be approved for the type of radiation or radiations included in the NVLAP program that most closely approximates the type of radiation or radiations for which the individual wearing the dosimeter is monitored. As there is no NVLAP test category for dosimeters exposed to a mixture of beta, gamma, and neutron radiations, the NRC has determined that licensees, which monitor for beta, gamma, and neutron exposure with a single dosimeter

, need to use a processor that is NVLAP accredited in categories for beta

-photon mixtures and neutron-photon mixtures. The licensee's dosimetry processor was NVLAP accredited for both beta

-photon and neutron

-photon mixtures and therefore was in compliance with 10 CFR 20.1501(c)(2).

Notwithstanding the paragraph above, licensees are required to provide adequate

monitoring in accordance with 10 CFR 20.1502(a). For any type of in

-field use practice that can introduce error in the monitoring results (dependent upon the type of dosimeter and

processing method), it becomes a question of compliance with the monitoring requirements of 10 CRR 20.1502(a) and not of NVLAP accreditation requirements of 10

CFR 20.1501(c)(2). As described in TIA 2012-05, another licensee had performed a study with the same dosimeters used by Byron (Harshaw 760). This study demonstrated

that exposing a single Harshaw 760 dosimeter to a mixture of beta, gamma, and neutron radiation met industry standard

s for accuracy and precision. Therefore, the licensee provided adequate monitoring and was in compliance with

10 CFR 20.1502(a).

The inspectors determined that no performance deficiency existed; therefore this URI is closed. 4OA6 Management Meetings .1 Exit Meeting Summary O n April 4, 2013, the inspectors presented the inspection results to Mr. B. Youman, Byron Plant Manager , and other members of the licensee

's staff. The licensee acknowledged the issues presented. The inspectors confirmed that none of the potential report input discussed was considered proprietary.

.2 Interim Exit Meetings

The inspection results for the area of occupational dose assessment were

discussed with Mr. B. Burton, Radiation Protection Manager, on March 26, 2013.

The inspection results for the area of lead shielding and pipe supports were discussed with Ms. A. Corrigan, Mechanical Design Manager, and Mr. E. Blondin, Design Engineering Manager, on March 26, 2013.

The licensee acknowledged the issues presented. The inspectors confirmed that none of the potential report input discussed was considered proprietary.

24 Enclosure ATTACHMENT: SUPPLEMENTAL INFORMATION

1 Attachment

SUPPLEMENTAL INFORMATION KEY POINTS OF CONTAC

T Licensee R. Kearney, Site Vice President

B. Youman, Plant

Manager B. Askren, Security Manager

B. Barton, Radiation Protection Manager S. Briggs, Operations Director

A. Creamean, Chemistry Manager

S. Gackstetter, Training Manager

D. Gudger, Regulatory Assurance Manager

E. Hernandez, Engineering Director

D. Horstmann, Business Operations

B. Spahr, Maintenance Director

E. Topping, Nuclear Oversight

Manager Nuclear Regulatory Commission

E. Duncan , Chief, Branch 3, Division of Reactor Projects

B. Bartlett, Byron Senior Resident Inspector

J. Robbins, Byron Resident Inspector Illinois Emergency Management Agency (IEMA)

R. Zuffa, IEMA

2 Attachment

LIST OF ITEMS OPENED, CLOSED, AND DISCUS

SED Open ed 05000454/201 3 002-0 1 NCV E mbedment Plate Design Deficiencies (Section 4OA2.3

) 05000454/2013002

-02; 05000455/2013002

-0 2 FIN Failure to Properly Scope All Pertinent External Flood Protection Features into

Walkdown List

s in Accordance with Ind ustry Guidance NEI 12

-07 (Section 4OA5.

2) Closed 05000454/201

3 002-0 1 NCV E mbedment Plate Design Deficiencies (Section 4OA2

.3) 05000454/2013002

-02; 05000455/2013002

-0 2 FIN Failure to Properly Scope All Pertinent External Flood Protection Features into

Walkdown List

s in Accordance with Ind ustry Guidance NEI 12

-07 (Section 4OA5.2) TI 2515/187

TI Inspection of Near

-Term Task Force Recommendation 2.3

Flooding Walkdown (Section 4OA5.

1) 05000454/2011005

-03; 05000455/2011005

-03 URI Use of TLDs May Not Be Consistent With the Methods Used by the NVLAP Accreditation Process (Section 4OA5.3)

3 Attachment

LIST OF DOCUMENTS REVIEWED The following is a list of documents reviewed during the inspection. Inclusion on this list does not imply that the NRC inspectors reviewed the documents in their entirety, but rather, that selected sections of portions of the documents were evaluated as part of the overall inspection effort. Inclusion of a document on this list does not imply NRC acceptance of the document or any part of it, unless this is stated in the body of the inspection report.

Section 1R04

- BOP WO-E4; Control Room Chilled Water Electrical Lineup, Revision 2

- BOP WO-M3; Control Room Chilled Water Valve Lineup, Revision 10

Section 1R06

- BAR 0PL02J

-3-B2; ESW Sump 2 Level High High, Revision 52

- IR 1413893; Unit 1 SX Alpha Sump Pump Check Valve is Sticking Open, September

16, 2012 - M-48; Diagram of Miscellaneous Sumps and Pumps , Revision AE Section 1R11

- IR 1486687; Unexpected Unit 1 PDMS Alarms Due to Failing CETC, March 12, 2012

Section 1R12

- IR 1487650; Potential Corporate Elevation for Byron Maintenance, March 12, 2013

- IR 1479105; Unit 1 Gain POT R303 for N

-43 Not Functioning Properly, February

22, 2013 - Byron Station Maintenance Rule Expert Panel Meeting Notes, November 5, 2009

- Byron Station Maintenance Rule Expert Panel Meeting Notes, December 18, 2009

- Byron Station Maintenance Rule Expert Panel Meeting Notes, June 7, 2011

- Byron Station Maintenance Rule Expert Panel Meeting Notes, November 3, 2011

- IR 1214163; Common Cause Analysis for MCCB for MCC 134Y2

-A4, June 2, 2011

- ER-AA-310-1005; (A)(1) Determination Template for IR 1207922, Revision 5 - ER-AA-310-1005; (A)(1) Determination Template for IR 1207931, Revision 5 - Byron Station Maintenance Rule Periodic Assessment #11, January 2011

- June 2012 Section 1R13 - IR 1474028; 2A CV Pump Gear Box Failed to Develop Oil Pressure on Start,

February 12, 2013 - IR 1474042; 2A CV Pump Gear Oi

l Pressure Guage Stuck at 0 Psig, February 12, 2013

Section 1R15

- IR 1413971; Byron OAD Investigated and Identified an Abnormal Indication of the Over Current Relay, October 11, 2012

- NSWP-S-05; Concrete Expansion Anchors, Revision 7 - Calculation 7.16.10.2

-BYR 97-229; Structural

Evaluation of Battery Racks and the Mounting Details in 111 and 112 Battery Rooms of the Auxiliary Building, Revision 4 - Drawing 6E

-0-3391AY; 125V DC Battery Rack Mounting Details

- Drawing M-11978; Bus 111 & 211 125V DC "L" Two Step EP3 Racks, Revision 2

4 Attachment

- Drawing 6E

-0-3391AH; Byron Station Unit 1& 2, Electrical

Equipment Mounting Details, Revision S - Drawing 64

-05906; Floor Rack

- Two Step EQ Protected for Plate Size 3 and 4 Batteries, Revision 0 - CC-AA-112; Temporary Configuration Changes, Revision 19 - EC 378402; Single Use Evaluation for 1/2 of SX Cubical Coolers Not Available, January 6, 2010

- EC 392429; Operation of SX Pump with Single Cubical Cooler, February 12, 2013

- IR 1465872; Review of Braidwood IR 1459353

- PZR PORV Accumulator Pressure, January 22 - CN-RRA-00-47; Calculational Table for Byron and Braidwood Natural Circulation Cooldown, Revision 1 Section 1R18

- Performance Verification Testing; RCFC Check Dampers for Byron Units 1 and 2, July 1981 - Sargent & Lundy Fan Check Dampers for Byron Units 1 and 2, March 5, 1985

- Material and Equipment Receiving and Inspection Report CECo Engineering and Construction, June 30, 1981

- Material and Equipment Receiving and Inspection Report CECo Engineering and Construction, June 30, 1981

- Q.F.2910.24; Project

No. 4391-05, Tornado/Isolation Dampers, May 11, 1981

- Q.F.2910.24; Project No. 4392

-05, Tornado/Isolation Dampers, May

11, 1981 - IR 1419184; RCFC Damper Missing Springs; September 27, 2012

- IR 1419189; RCFC Damper Missing Springs; September 27, 2012

- IR 1419190; RCFC Damper Missing Springs; September 27, 2012

- IR 1419192; RCFC Damper Missing Springs; September 27, 2012

- IR 1474498; NRC Follow

-Up - RCFC Discharge Check Damper; February 7, 2013

Section 1R19

- IR 1473967; No SX PP Cubicle Cooler Tubesheet Degradation

Margin Exists, February 11, 2013 - WO 1493809; 214 Instrument Inverter EOC Walkdown Due to 211 INV Failure, Revision 1

- WO 1591475; 1SX01PA Comprehensive IST Required for Essential Service Water Pump , February 14, 2013

- BOP IP-1; Instrument Bus

Inverter Startup, Revision 14

- IR 1472776; ACB 1442 Drives On

-Line Risk Yellow for Both Units, February 8, 2013

- IR 1473015; Lockout Relay 486

-1442 for Breaker 1442 is Degraded, February 8, 2013

- WO 1237471; Bus 144 Sat 142

-2 Feed (ACB 1442) RES OC Relay Routine, February 8, 2013 - WO 1444425; Replace Lockout Relay on ACB 1442, February 9, 2013

- WO 1591475; 1SX01PA Comprehensive IST Requirement for Essential Service Water Pump,

February 14, 2013

- WO 1418630; Support Eddy Current Testing for 1A SX Pump Cubical Cooler, February14

, 2013 - WO 1366902; Operation Run Cooler and Check for Proper Operation, February 14, 2013

- WO 1314236; Preventative

Maintenance on Breaker SAT Feed, February 14, 2013

Section 1R20

- OP-AA-101-113-1004; Equipment Prompt: 2A Generator Stator Cooling Water Pump (2A GC) Tripped, Revision 24

5 Attachment

- IR 1490321; Smoke Noticed Coming from the 2A FW Pump Motor, March 20, 2013

- IR 1490323; DRPI POD M

-12 Indicated General Warning Following Reactor

Trip, March 20, 2013 - IR 1493026; Smoke was Reported Coming from U2 Voltage Regulator Cabinet, March 20, 2013 - IR 1490315; U

-2 Reactor Trip

- Loss of GC, March 20, 2013

- IR 1490330; Oil Leaking From Exciter End of Main Generator, March 20, 2013

- IR 1490407; Need Cleanup of Generator Oil Leak in Various TB Elevations, March 21, 2013

- IR 1490453; U2 RCDT Elevated Inputs Investigation, March 21, 2013

- IR 1490635; Following U2 Reactor

Trip, 2AR11J went Dark Blue and then White, March 21, 2013 Section 1R22

- 1BOSR 3.1.5

-1; Train A Solid State Protection System Surveillance, Revision 32

- WO 1469526 01;

ESF Relay Train Reactor

Trip - K636/2FW039S, February 25, 2013

- IR 631199; Revise Unit Two Schematic Diagram 6E

-2 4030FW56, May 18, 2007

- IR 848809; 12/15 E

-3 Schedule Review, November 23, 2008

- IR 1064332; Inadequate Technical Information Provided

for New SSPS Cards, May 2, 2010 - IR 1293130; UV Driver Card Vulnerability in OE 34462 Applicable at Byron, November 21, 2011 - IR 1323037; Unexpected FWI While Closing RX Trip Breakers, February 5, 2012 - IR 1328319; Unexpected Ground Reading During SSPS Surveillance, February 17, 2012

- IR 1329012; Unexpected FWI While Closing RX Trip Breakers, February 20, 2012

- IR 1329908; Low Contact Volts Found During SSPS

- Not Unusual, February 21, 2012

- IR 1374658; Low Voltage Reading During 2BOSR 3.1.5

-2, June 5, 2012 - WO 1588151; 1CS01PB Comprehensive IST Requirements for Containment Spray Pump, January 29, 2013

- BOP CS-5; Containment Spray System Recirculation to the RWST, Revision 11 - WO 1609614; 1A Diesel Generator Operability Surveillance, February 6, 2013

- 1BOSR 8.1.2

-1; Unit 1 Train A Diesel Generator Operability Surveillance, Revision 20 - WO 1596040;

ESF Relay Train B CS

-K644 ESFAS Instrumentation

ESF Relay Surveillance, February 28, 2013

- WO 1597146; 2CS01PB Comprehensive IST Requirements for Containment Spray Pump,

February 28, 20

13 Section 2RS4 - Final Response to Task Interface Agreement 2012

-05; ML12268A330;

October 16, 2012 Section 4OA1 - Power History Curves for Unit 1 and Unit 2, January 2012 through December 2012

- Perfomance Indicator Data as Reported for the Period January 2012 through December 2012

- IR 1319908; B2F26 U2 Reactor Trip Due To Elect

rical Fault and Unusual Event, January 30, 2012 - IR 1323547; B2F27 Manual Reactor Trip and Manual Auxiliary Feedwater Actuation, February 6, 2012

6 Attachment

Section 4OA2 - IR 1474066; Issues With SX to CC MOD Installation, February 11, 2013

- IR 1477430; Insufficient Insertion of Anti

-Vibration Bars in Alloy 600, February 19, 2013

- IR 1413971; EACE

- 1B RH Pump Trip Due to CO

-5 Overcurrent Relay Operation, September 17, 2012 - IR1272187; Issues Applicable to Byron from Bwd Mod/50.59 Inspection

October 4, 2011 - IR 1296141; NER NC-11-045-Y Fleet Wide Actions
September 28, 2011

- Byron Document No. DS

-MC-01-BY; Certification of Design Specification for Primary Containment Piping Penetration Assemblies; Revision

3 - Byron/Braidwood Document No. 01

-10-52; Bryon/Braidwood Piping Design Specification; Revision 2 - Calculation No. 13.2.29BY; Mechanical Component Support 1SI06025V; Revision 2X

- ER-AA-380; Primary Containment Leakrate Testing Program, Revision 9 - BVP 800-39; Primary Containment Leakrate Testing Program, Revision 10 - 1BOSR 6.1.1

-19; Unit 1 Primary Containment Type C Leakage Rate Tests and IST Tests of the OffGas System, Revision 8 - 2BVSR 6.1.1

-24; Unit 2 Summation of Primary Containment Type B & C Local Leakage Tests for Acceptance Criteria, Revision 12 - 1BVSR 6.1.1

-24; Unit 2 Summation of Primary Containment Type B & C Local Leakage Tests for Acceptance Criteria, Revision 15 - IR 1298667; Long Term LCO

for VQ Valves Needs Resolution, December 6, 2011

- IR 1306607; Long Term LCO

Extent of Condition Review Per IR 1298667, December

26, 2011 - EC 390536; Determine Acceptability of Code Case N

-597-2 use on FAC Components 1FW085B/D, Revision 0 - IR 1412470; B1R18 FAC Component 1FW085B Exam Failure, September 13, 2012

- IR 1415327; B1R18 FAC Component 1FW085D Exam Failure, September 13, 2012

Corrective Action Documents As a Result of NRC Inspection

- IR 1487707; NRC ID UFSAR Discrepancy

-Appendix A, Page

A.1.57-1; March 14, 2013

- IR 1478188; NRC Identified Use of CMTR in a 80's Calculation; February 21, 2013

- IR 1490153; NRC/IEMA 1A DG HELB Modification Walkdown; March 20, 2013

- IR 1493278; NRC ID'ed: PDP 50.59 Enhancement Required, March 27, 2013

Section 4 O A5 - IR 1466355; FUK: Update UFSAR Regarding External Flooding, January 24, 2013

- IR 1472808; FUK: Effect of Local Intense Precipitation on FHB and SFP PP, February

8, 2013 - IR 1474686; FUK: Concrete Steps on 401" FHB to Areas 5 & 7, February 13, 2013

- IR 1475877; Blockwall Penetrations in SFP Pump Room, February 15, 2013

- IR 1484749; FUK: MCC 133X1 Fasteners Seismic Walkdown, March 7, 2013 - IR 1484755; FUK: MCC 133X1 Fasteners Seismic Walkdown, March 7, 2013 - IR 1484758; FUK: MCC 133X1 Fasteners Seismic Walkdown, March 7, 2013 - IR 1484765; FUK: MCC 132X3 Fasteners Seismic Walkdown, March 7, 201 3 - IR 1484768; FUK: MCC 131X3 Fasteners Seismic Walkdown, March 7, 2013 Corrective Action Documents As a Result of NRC Inspection

-IR 1453636; FUK: Flooding and Seismic Walkdowns, December 18, 2012

7 Attachment

LIST OF ACRONYMNS US

E ADAMS Agencywide Document Access

and Management System

AISC American Institute of Steel Construction

ASME American Society of Mechanical Engineers

CAP Corrective Action Program

CFR Code of Federal Regulations

CLB Current Licensing Basis

ECCS Emergency Core Cooling System

ESF Engineered Safety Feature

FHB Fuel Handling Building

FIN Finding FSAR Final Safety Analysis Report

IMC Inspection Manual Chapter

IP Inspection Procedure

IR Inspection Report

IR Issue Report

LCO Limiting Condition for Operation

NCV Non-Cited Violation

NEI Nuclear Energy Institute NRC U.S. Nuclear Regulatory Commission

NRR Office of Nuclear Reactor Regulation

NVLAP National Voluntary Laboratory Accreditation Program

PARS Publicly Available Records

System PI Performance Indicator

PMP Probable Maximum Precipitation

PORV Powe r-Operated Relief Valve

RCFC Reactor Containment Fan Cooler

ROP Reactor Oversight Process

RFO Refueling Outage

SDP Significance Determination Process

SI Safety Injection

SSC Structure, System, or Component

SX Essential Service Water

TI Temporary Instructio

n TIA Task Interface Agreement

TLD Thermoluminescent Dosimeter

TS Technical Specification

UFSAR Updated Final Safety Analysis Report

URI Unresolved Item

WO Work Order

M. Pacilio

-2- In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management

System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Sincerely, /RA/ Eric R. Duncan, Chief

Branch 3 Division of Reactor Projects

Docket Nos. 50

-454, 50-455 License Nos. NPF

-37, NPF-66 Enclosure:

Inspection Report No. 05000454/

201 3 00 2 and 05000455/201 3 00 2 w/Attachment: Supplemental Information

cc w/encl:

Distribution via ListServ

DOCUMENT NAME:

G:\DRPIII\BYRO\Byron 201 3 00 2.docx Publicly Available

Non-Publicly Available

Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl

"E" = Copy with attach/encl "N" = No copy

OFFICE RIII NAME TDaun:dtp EDuncan DATE 04/26/13 0 4/29/13 OFFICIAL RECORD COPY

Letter to M. Pacilio from E. Duncan dated April 29, 2013.

SUBJECT: BYRON STATION, UNITS

1 AND 2, NRC INTEGRATED INSPECTION REPORT 05000454/201 3 00 2; 05000455/2013 00 2 DISTRIBUTION:

Doug Huyck

RidsNrrDorlLpl3

-2 Resource

RidsNrrPMByron Resource

RidsNrrDirsIrib Resource

Chuck Casto

Cynthia Pederson

Steven Orth

Allan Barker

Christine Lipa

Carole Ariano

Linda Linn

DRPIII DRSIII Tammy Tomczak Patricia Buckley

ROPreports.Resource@nrc.gov