IR 05000247/2016007

From kanterella
Revision as of 03:23, 16 September 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Indian Point Nuclear Generating Unit 2 - Triennial Fire Protection Inspection Report 05000247/2016007
ML17006A254
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 01/06/2017
From: Dentel G T
Engineering Region 1 Branch 2
To: Vitale A J
Entergy Nuclear Operations
Dentel G T
References
IR 2016007
Download: ML17006A254 (21)


Text

January 6, 2017

Mr. Anthony J. Vitale, Site Vice President Entergy Nuclear Operations, Inc.

Indian Point Energy Center

450 Broadway, GSB

P.O. Box 249

Buchanan, NY 10511-0249

SUBJECT: INDIAN POINT NUCLEAR GENERATING UNIT 2 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000247/2016007

Dear Mr. Vitale:

On December 16, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a triennial

fire protection inspection at your Indian Point Nuclear Generating Unit 2 and discussed the

results of this inspection with you and other members of your staff. The results of this

inspection are documented in the enclosed report.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations, and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed station personnel. The inspectors also reviewed mitigation strategies for addressing

large fires and explosions.

Based on the results of this inspection, no findings were identified. This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."

Sincerely,/RA/ Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety

Docket No. 50-247 License No. DPR-26

Enclosure:

Inspection Report 05000247/2016007

w/Attachment:

Supplementary Information

cc w/encl: Distribution via ListServ

SUMMARY

IR 05000247/2016007; 11/28/2016 - 12/16/2016; Indian Point Nuclear Generating Unit 2;

Triennial Fire Protection Inspection.

This report covered a two week on-site triennial fire protection team inspection by specialist inspectors. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 6, dated July 2016.

No findings were identified.

3

REPORT DETAILS

Background

This report presents the results of a triennial fire protection inspection conducted in accordance

with NRC Inspection Procedure (IP) 71111.05T, "Fire Protection." An objective of the inspection

was to assess whether Entergy Nuclear Operations, Inc. (Entergy) has implemented an

adequate fire protection program and that post-fire safe shutdown capabilities have been

established and are being properly maintained at the Indian Point Nuclear Generating Unit 2 (IP2). The following fire areas (FA) and associated fire zones (FZ) were selected for detailed

review based on prior inspection results and risk insights from the IP2 Individual Plant

Examination of External Events:

Fire Area / Fire Zone FZ 15 Main Control Room FZ 10 Diesel Generator Building FA F PAB Corridor 80' & 98' and Fan House 89' Inspection of these FAs/FZs fulfilled the IP requirement to inspect a minimum of three samples.

The inspectors evaluated Entergy's fire protection program (FPP) against applicable

requirements which included Unit 2 Operating License Conditions 2.K. and 2.N., Unit 3

Operating License Condition 2.AC., NRC Safety Evaluations, Title 10 of the Code of Federal Regulations (10 CFR) 50.48, and 10 CFR 50, Appendix R. The inspectors also reviewed related documents that included the Updated Final Safety Analysis Report (UFSAR), the Fire

Protection Program Plan, the Fire Hazards Analysis (FHA), and the Safe Shutdown Analysis

Report.

The team evaluated aspects of three mitigating strategies for responding to large fires and

explosions, which are required by Operating License Condition 2.N for Unit 2, Operating

License Condition 2.AC for Unit 3, and 10 CFR 50.54(hh)(2). The team also reviewed related

documents that included Nuclear Energy Institute 06-12, "B.5.b Phases 2 & 3 Submittal

Guidance," Revision 2 (ML070090060). Inspection of these strategies fulfills the IP requirement

to inspect a minimum of one sample.

Documents reviewed for each section of this report are listed in the Attachment.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity 1R05 Fire Protection (IP 71111.05T)

.01 Protection of Safe Shutdown Capabilities

a. Inspection Scope

The team reviewed the FHA, post-fire safe shutdown analyses, and supporting drawings

and documents to verify whether the safe shutdown capabilities were properly protected from fire damage. The team evaluated equipment and cable separation to determine whether the applicable separation requirements of Appendix R,Section III.G, and the

IP2 design and licensing bases were maintained for the credited safe shutdown

equipment and their supporting power, control, and instrumentation cables. The team's

review included an assessment of the adequacy of the selected systems for reactor

pressure control, reactivity control, reactor coolant makeup, decay heat removal, process monitoring, and associated support system functions.

b. Findings

No findings were identified.

.02 Passive Fire Protection

a. Inspection Scope

The team walked down accessible portions of the selected FAs to evaluate whether the

material conditions of the FA boundaries were adequate for the fire hazards in the area.

The team compared the FA boundaries, including walls, ceilings, floors, fire doors, fire

dampers, penetration seals, electrical raceway and conduit fire barriers, and redundant

equipment fire barriers to design and licensing basis requirements, industry standards, and the IP2 FPP, as approved by the NRC, to identify any potential degradation or non-

conformances.

The team reviewed selected engineering evaluations, installation and repair work

orders, and qualification records for a sample of penetration seals to determine whether

the fill material was properly installed and whether the as-left configuration satisfied

design requirements for the intended fire rating. The team also reviewed similar records

for selected fire protection wraps and an encapsulation system to verify whether the

material and configuration was appropriate for the required fire rating and conformed to

the engineering design.

The team also reviewed recent inspection records and functional test procedures for fire

dampers, and the inspection records for penetration seals and fire barriers, to verify

whether the inspection was adequately conducted, the acceptance criteria were met, and any potential performance degradation was identified.

b. Findings

No findings were identified.

.03 Active Fire Protection

a. Inspection Scope

The team evaluated manual and automatic fire suppression and detection systems in the selected FAs to determine whether they were installed, tested, maintained, and

operated in accordance with NRC requirements, National Fire Protection Association (NFPA) codes of record, and the IP2 FPP, as approved by the NRC. The team also

assessed whether the suppression systems capabilities were adequate to control and/or

extinguish fires associated with the hazards in the selected areas.

The team reviewed the as-built capability of the fire water supply system to verify the design and licensing basis and NFPA code of record requirements were satisfied, and to

assess whether those capabilities were adequate for the hazards involved. The team

reviewed the fire water system hydraulic analyses to assess the adequacy of a single

fire water pump to supply the largest single hydraulic load on the fire water system plus

concurrent fire hose usage. The team evaluated the fire pump performance tests to

assess the adequacy of the test acceptance criteria for pump minimum discharge

pressure at the required flow rate, to verify the criteria was adequate to ensure that the

design basis and hydraulic analysis requirements were satisfied. The team also

evaluated the underground fire loop flow tests to verify the tests adequately

demonstrated that the flow distribution circuits were able to meet design basis

requirements. In addition, the team reviewed recent pump and loop flow test results to

verify the testing was adequately conducted, the acceptance criteria were met, and any

potential performance degradation was identified.

The team walked down accessible portions of the detection and water suppression

systems in the selected areas and major portions of the fire water supply system, including motor and diesel driven fire pumps, interviewed system and program engineers, and reviewed condition reports to independently assess the material

condition of the systems and components. In addition, the team reviewed recent test

results for the fire detection and suppression systems for the selected FAs to verify the

testing was adequately conducted, the acceptance criteria were met, and any

performance degradation was identified.

The team assessed the fire brigade capabilities by reviewing training, qualification, and

drill critique records. The team also reviewed Entergy's fire-fighting strategies (i.e., pre-

fire plans) and smoke removal plans for the selected FAs to determine if appropriate

information was provided to fire brigade members and plant operators to identify safe

shutdown equipment and instrumentation, and to facilitate suppression of a fire that

could impact post-fire safe shutdown capability. The team independently inspected the

fire brigade equipment, including personnel protective gear (e.g., turnout gear) and

smoke removal equipment, to determine operational readiness for fire-fighting. In

addition, the team reviewed Entergy's fire brigade equipment inventory and recent

inspection and inventory results to verify adequate equipment was available, and any

potential material deficiencies were identified.

b. Findings

No findings were identified.

.04 Protection from Damage from Fire Suppression Activities

a. Inspection Scope

The team performed document reviews and plant walkdowns to verify that redundant

trains of systems required for hot shutdown, which are located in the same FA, are

not subject to damage from fire suppression activities or from the rupture or inadvertent

operation of fire suppression systems. Specifically, the team verified that:

A fire in one of the selected FAs would not indirectly, through production of smoke, heat or hot gases, cause activation of suppression systems that could

potentially damage all redundant safe shutdown trains; A fire in one of the selected FAs (or the inadvertent actuation or rupture of a fire suppression system) would not indirectly cause damage to all redundant trains (e.g. sprinkler caused flooding of other than the locally affected train); and, Adequate drainage is provided in areas pr otected by water suppression systems.

b. Findings

No findings were identified.

.05 Alternative Shutdown Capability

a. Inspection Scope

The team reviewed the safe shutdown analysis, operating procedures, piping and instrumentation drawings, electrical drawings, the UFSAR, and other supporting documents for the selected FAs to determine whether Entergy had properly identified the systems and components necessary to achieve and maintain post-fire safe shutdown conditions. The team evaluated selected systems and components credited by the safe shutdown analysis for reactor pressure control, reactivity control, reactor coolant

makeup, decay heat removal, process monitoring, and support system functions to assess the adequacy of Entergy's alternative shutdown methodology. The team also assessed whether alternative post-fire shutdown could be performed both with and without the availability of off-site power. The team walked down selected plant

configurations to verify whether they were consistent with the assumptions and descriptions in the safe shutdown and the FHA. In addition, the team evaluated whether the systems and components credited for use during post-fire safe shutdown would

remain free from fire damage.

The team reviewed the training program for licensed and non-licensed operators to verify whether it included alternative shutdown capability. The team also verified whether personnel, required for post-fire safe shutdown, using either the normal or alternative shutdown methods, were trained and available on-site at all times, exclusive

of those assigned as fire brigade members.

The team reviewed the adequacy of procedures utilized for post-fire shutdown and performed an independent walk through of procedure steps (i.e., a procedure tabletop)to assess the adequacy of implementation and human factors within the procedures.

The team also evaluated the time required to perform specific actions to verify whether operators could reasonably be expected to perform those actions within sufficient time to maintain plant parameters within specified limits.

Specific procedures reviewed for normal and alternative post-fire shutdown included:

2-AOP-SSD-1, Control Room Inaccessibility Safe Shutdown Control, Revision 23; 2-ONOP-FP-001, Plant Fires, Revision 17; and, 2-SOP-ESP-001, Local Equipment Operation and Contingency Actions, Revision 12.

The team reviewed selected operator manual actions to verify whether they had been

properly reviewed and approved and whether the actions could be implemented in accordance with plant procedures in the time necessary to support the safe shutdown method for each FA. The team also reviewed the periodic testing of the alternative shutdown transfer and isolation capability, and instrumentation and control functions, to evaluate whether the tests were adequate to ensure the functionality of the alternative shutdown capability.

b. Findings

No findings were identified.

.06 Circuit Analysis

a. Inspection Scope

The team reviewed Entergy's post-fire safe shutdown analysis for the selected FAs to determine whether the analysis identified both required and associated electrical circuits and cables for the systems and components necessary to achieve and maintain safe shutdown. The team reviewed electrical schematics and cable routing data for power, control, and instrumentation associated with selected components. Specifically, the team evaluated the selected circuits and cables to determine whether they were

(a) adequately protected from potential fire damage, or
(b) analyzed to show that fire-induced faults (e.g., hot shorts, open circuits, and shorts to ground) would not prevent safe shutdown, or
(c) analyzed to show that potential damage could be mitigated with approved operator manual actions, in order to determine whether fire-induced faults could adversely impact safe shutdown capabilities. The team's evaluations considered credible fire scenarios, cable insulation attributes, cable failure modes, cable routing, and common power supply or electrical bus configurations.

In addition, the team reviewed cable raceway drawings and cable routing databases for a sample of components required for post-fire safe shutdown to determine whether those cables were routed as described in the safe shutdown analysis. The team also reviewed equipment important to safe shutdown, but not part of the success path, to assess whether Entergy's safe shutdown methodologies were appropriate, conformed to design and licensing basis requirements, and appropriately considered the guidance in NRC Regulatory Guide 1.189, "Fire Protection for Nuclear Power Plants," Revision 2.

Cable failure modes were reviewed for the following components:

21CHP , 21 Charging Pump 21CCP, 21 Component Cooling Pump 250A and 4925, 21 Reactor Coolant Pump Seal Water Injection Line Isolation Valves LCV-112C, Volume Control Tank Outlet Isolation Valve LT-417D(427D), Steam Generator 21(22) Level Indicators The team reviewed a sample of circuit breaker and fuse over-current protection coordination studies to determine whether equipment needed for post-fire safe shutdown activities could be adversely affected due to a lack of coordination that could result in a common power supply or common electrical bus concern. The team also evaluated whether coordination studies appropriately considered multiple faults due to fire. In

addition, the team reviewed a sample of circuit breaker maintenance records, for components required for safe shutdown, to determine whether the breakers were properly maintained.

The team assessed the transfer of control from the main control room to the alternative shutdown location to determine whether it would be adversely affected by fire-induced circuit faults (e.g., by the provision of separate fuses and power supplies for alternative shutdown control circuits).

b. Findings

No findings were identified.

.07 Communications

a. Inspection Scope

The team reviewed safe shutdown procedures, the safe shutdown analysis, and

associated documents to verify an adequate method of communications would be

available to plant operators following a fire. During this review, the team considered the

effects of ambient noise levels, clarity of reception, reliability, and coverage patterns.

The team also inspected the designated emergency storage lockers to verify the

availability of portable radios for the fire brigade and for plant operators. The team also

verified that communications equipment such as repeaters and transmitters would not be

affected by a fire.

b. Findings

No findings were identified.

.08 Emergency Lighting

a. Inspection Scope

The team observed the placement and coverage area of eight-hour emergency lights

throughout the selected FAs to evaluate their adequacy for illuminating access and

egress pathways and any equipment requiring local operation or instrumentation monitoring for post-fire safe shutdown. The team also verified that the battery power

supplies were rated for at least an eight-hour capacity. Preventive maintenance

procedures, the vendor manual, completed surv eillance tests, and battery replacement practices were also reviewed to verify that the emergency lighting was being maintained

consistent with the manufacturer's recommendations and in a manner that would ensure

reliable operation.

b. Findings

No findings were identified.

.09 Cold Shutdown Repairs

a. Inspection Scope

The team reviewed Entergy's dedicated repair procedures for components which might be damaged by fire and were required to achieve post-fire cold shutdown. The team evaluated selected cold shutdown repairs to determine whether they could be achieved

within the time frames assumed in the design and licensing bases. In addition, the team verified whether the necessary repair equipment, tools, and materials (e.g., pre-cut cables with prepared attachment lugs) were available and accessible on site.

b. Findings

No findings were identified.

.10 Compensatory Measures

a. Inspection Scope

The team verified that compensatory measures were in place for out-of-service, degraded, or inoperable fire protection and post-fire safe shutdown equipment, systems, or features (e.g. detection and suppression systems and equipment; passive fire

barriers; or pumps, valves, or electrical dev ices providing safe shutdown functions or capabilities). The team also verified that the short term compensatory measures

compensated for the degraded function or feature until appropriate corrective action

could be taken and that Entergy was effective in returning the equipment to service in a

reasonable period of time.

b. Findings

No findings were identified.

.11 Review and Documentation of FPP Changes

a. Inspection Scope

The team reviewed recent changes to the approved FPP to verify that the changes did

not constitute an adverse effect on the ability to safely shutdown.

b. Findings

No findings were identified.

.12 Control of Transient Combustibles and Ignition Sources

a. Inspection Scope

The team reviewed Entergy's procedures and programs for the control of ignition

sources and transient combustibles to assess their effectiveness in preventing fires and

in controlling combustible loading within limits established in the FHA. A sample of hot

work and transient combustible control permits were also reviewed. The team

performed plant walkdowns to verify that transient combustibles and ignition sources

were being implemented in accordance with the administrative controls.

b. Findings

No findings were identified.

.13 Large Fires and Explosions Mitigation Strategies

a. Inspection Scope

The team conducted a review of selected mitigation strategies intended to maintain or

restore core decay heat removal and spent fuel pool cooling capabilities under the

circumstances associated with the loss of large areas of the plant due to explosions

and/or fires. The team assessed whether Entergy continued to meet the requirements

of the Indian Point Nuclear Power Station Units 2 and 3 Operating Licenses and 10 CFR

50.54(hh)(2).

The team reviewed the following mitigation strategies:

Unit 3 Makeup to the Spent Fuel Pool with Permanently Installed and Portable Equipment; Unit 3 External Spray; Unit 2 Manual Operation of Steam Generator Atmospheric Dump Valves; and, Unit 2 Makeup to the Steam Generators with the Portable Pump

The team's review included: a detailed assessment of the procedural guidance; a

tabletop discussion with licensed operators; and a walk down of four mitigation

strategies with operators to assess the feasibility of the strategies and operator

familiarity, maintenance and surveillance testing of selected strategy equipment, and an

inventory check of the B.5.b pump and equipment trailers to ensure the appropriateness

of equipment storage and availability.

b. Findings

No findings were identified.

OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems (IP 71152)

a. Inspection Scope

The team reviewed a sample of condition reports associated with the FPP, post-fire safe

shutdown issues, and mitigation strategy issues to determine whether Entergy was

appropriately identifying, characterizing, and correcting problems associated with these

areas and whether the planned or completed corrective actions were appropriate.

b. Findings

No findings were identified.

4OA6 Meetings, Including Exit

The team presented the inspection results to Mr. Anthony J. Vitale, Site Vice President, and other members of the site staff at an exit meeting on December 16, 2016. The team

verified that this report does not contain proprietary information.

ATTACHMENT:

SUPPLEMENTARY INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

J. Balletta Senior Reactor Operator

S. Bianco Fire Brigade Training

T. Chan Design Engineer

G. Dahl Licensing Engineer

K. Elliot Appendix R Engineer

D. Powell Senior Reactor Operator

C. Wilson Fire Protection Engineer

NRC

B. Haagensen Senior Resident Inspector, Indian Point
S. Rich Resident Inspector, Indian Point
C. Safouri Acting Resident Inspector, Indian

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

NONE

Opened and Closed

NONE

Closed

NONE

Discussed

NONE

LIST OF DOCUMENTS REVIEWED

Fire Protection Licensing Documents Indian Point Nuclear Generating Unit No. 2, Amended Facility Operating License, 9/28/73

IP2
EN-DC-330, Indian Point Nuclear Generating Unit No. 2, Fire Protection Program, Revision 4
IP2 UFSAR, Revision 26
IP2-RPT-03-00015, IP2 Fire Hazards Analysis, Revision 7
IP-RPT-04-00224, NFPA Code of Record Determination for Indian Point Unit 2 Fire Protection
Design Basis Documents and Specifications
IP2-DBD-221, IP2 Design Basis Document for Fire Protection System, Revision 3
Calculations/Engineering Evaluation Reports
247-09-0013.024, IP2 Nuclear Power Plant Fire Probabilistic Risk Assessment, Multiple Spurious Operations Report, Revision 0
CE-PS 100-79, Fireproofing of Diesel Generator Bldg., Revision 0
FEX-00246-00, Evaluation of PAB Fire Protection Line at EL. 80' Due to Potential Flooding of
RHR Pump Cells at
EL 15', Revision 0
IP2-RPT-03-00010, 3M INTERAM Fire-Resistant Enclosure at Electrical Penetration H20 &
Response to NRC Information Notice 95-52, Supplement 1, Revision 1
IP3-CALC-CVCS-393, Calculation of Allowable Time for Operating Charging Pumps Without Cooling Water, Revision 1
IP-CALC-04-01171, the Hydraulic Analysis of Indian Point Unit 1 and Unit 2 Fire Protection Water
Supply Systems and Several Unit 2 Suppression Systems, Revision 0
IP-CALC-08-00024, Sizing Calculation for RHR Pump Flooding Line, Revision 0
IP-RPT-04-00188, Evaluation of Hemyc Wrap Fire Protective Systems, Revision 1
IP-RPT-05-00071, IP2 10
CFR 50, Appendix R Safe-Shutdown Separation Analysis, Revision 2
IP-RPT-09-00012, Validation of Operator Manual Actions Credited for Appendix R, Section
III.G
Fire Areas: IP2 and IP3, Revision 0
IP-RPT-12-00022, Inaccessible Fire Barrier Penetration Seals, Revision 0
PGI-00355, NRC Information Notice 92-18 MOV Control Hot Short Issue, Revision 4
PGI-00581-00, Fire Protection 86-10 Evaluation for EDG Structural Steel Fire Resistant Coating, Revision 0
SGX-00048-01, 480V Switchgear Coordination Calculation for Switchgears 21 and 22, Revision 1
Engineering Change Requests (ECR)
EC-40404, Relocate 21 Charging Pump Control Switch from 480V switchgear to the CCR and Install Solenoid and its control in CCR to Resolve U2-OMA-20 and 21, 3/24/14
EC-41582, OMA Resolution:
OMA-6, 4/07/14
EC-42090, Resolve OMA 9 and 10, Support Safe Shutdown Instrument Indication in IP2 CCR,
3/24/14
EC-45124, Update EP & Operations Communication to Address Fukushima FLEX
Requirements in
NEI 12-01, Revision 0
EC-50149, FLEX Electrical EC for Phase 2, Revision 0
FPX-93-09146-F, Removal of Thermal Lag Fire Barrier from RHR Pump 22 Feeder, dated
5/9/94
Fire Barrier Tests
CTP 1001A, Three Hour Fire Qualification Test, 7/25/80
CTP 1076, Three Hour Fire Qualification Test, 3/28/85
CTP 1098A, Three Hour Fire Qualification Test, 8/11/86
CTP 2005/CTP 2008, Fire Endurance Test of 3M INTERAM Mat Fire Protective Envelopes, 11/12/98
Piping and Instrumentation Diagrams
21-F-2018, Flow Diagram Condensate & Boiler Feed Pump Suction, Revision 148
21-F-2019, Boiler Feedwater Flow Diagram, Revision 118
21-F-2036, Flow Diagram Instrument Air Control Bldg. Conventional Plant, Etc., Revision 101
21-F-2720, Auxiliary Coolant Syst em Flow Diagram, Revision 92
21-F-2722, Service Water System Flow Diagram, Revision 128
9321-F-2736, CVCS Flow Diagram, Revision 130
21-F-2738, Reactor Coolant System Flow Diagram, Revision 122

Drawings

and Wiring Diagrams

25151, Elementary Wiring Diagram of Component Cooling Pump 23, Revision 15
260430, Loop Diagram Reactor Coolant System, Pressurizer Level Control, Revision 3
260510, Loop Diagram Feedwater
SG 21 Wide Range Level, Revision 6
260511, Loop Diagram Feedwater
SG 22 Wide Range Level, Revision 6
400400-05, Fire Area/Zone Arrangement Site Plan, Revision 2
400402, Fire Area/Zone Arrangement at EL. 36', Revision 3
400403-05, Fire Area/Zone Arrangement at EL. 53', Revision 5
400404-04, Fire Area/ Zone arrangement at
EL 80', Revision 4
400405-02, Fire Area/Zone Arrangement at EL. 98', Revision 2
503797, Elementary Wiring Diagram for Charging Pump 21, Revision 0
503802, IP2 PAB, EL. 98' Valve
LCV-112C Fire Enclosure Plan & Sections, Civil, Revision 0
21-F-3008, Single Line Diagram DC Power Panels, Revision 92
21-F-4006-78, Yard Fire Protection Piping, Revision 78
A208088, One Line Diagram of 480Vac Switchgear 21 and 22, Revision 44
A208377, Main One Line Diagram, Revision 17
A208831, Schematic Diagram for Post-Accident
MOV 250A, Revision 4
A208832, Schematic Diagram for Post-Accident
MOV 4925, Revision 7
A227551-66, Sht. 1, Fire Protection System Diagram Details, Revision 66
A227552-47, Sht. 2, Fire Protection System Diagram Details, Revision 47
A227553-51, Sht. 3, Fire Protection System Diagram Detail, Revision 51
A227554-27, Sht. 4, Fire Protection System Diagram Detail, Revision 27
A231592, 6900Vac One Line Diagram, Revision 19
A240128, Boiler Feedwater Level and Flow Instrumentation SG's 21 thru 24, Revision 5
B192477-3, Flow Diagram Piping & Instrumentation Symbols, Revision 0
B225115, Sht. 9, Elementary Wiring Diagram Switch Development, Revision 3
B225133, Elementary Wiring Diagram on Component Cooling Pump 21, Revision 14
B228010-04, Fire Barrier Penetrations Diesel Generator Building, Wall 1032A-W, 12/17/03
B228016-05, Fire Barrier Penetrations Charging Pump Rooms, PAB Wells 7A/5-N, 7A/6-N,
7A/7-N, 12/17/03
B228050-06, Fire Barrier Penetration Schedule Walls 7A/5-N, 7A/6-N, 7A/7-N, 12/17/03
B228053-05, Fire Barrier Penetration Schedule Walls 14/ST3-S, 14/43A-W, 10/32A-W,
2/17/03
IP2-S-000255, Elementary Wiring Diagram VCT Drain MOV
LCV-112C, Revision 3

Procedures

0-PT-M002, Alternate Safe Shutdown Equipment Inventory and Inspection, Revision 16
0-PT-Q001, Alternate Safe Shutdown Equipment Inventory and Inspection, Revision 13
2-AOP-SSD-1, Control Room Inaccessibility Safe Shutdown Control, Revision 23
2BRK-021-CUB, Westinghouse 480V DB Series Breaker Cubicle Inspection and Cleaning, Revision 5
2-BRK-023-ELC, DB Breaker Amptector Overcurrent Test, Revision 6
2-BRK-024-ELC, DB Breaker Amptector Calibration Test, Revision 3
2-COL-3.1, Chemical and Volume Control System, Revision 43
2-ELC-004-FIR, IP2 Repairs for Safe Shutdown in the Event of an Appendix R Fire, Revision 2
2-IC-PC-I-L-417, 21 SG Wide Range Level Calibration, Revision 2
2-IC-PC-I-L-417, 21 SG Wide Range Level Calibration, Revision 3
2-IC-PC-I-L-427, 22 SG Wide Range Level Calibration, Revision 2
2-PC-R3-1, Pressurizer Level Transmitters, Revision 8
2-PC-R37, Alternate Safe Shutdown and Remote Shutdown Instruments, Revision 13
2-PT-2Y042, 21 CHP Central Control Room Station Switches, Revision 1
2-PT-Q017A, Alternate Safe Shutdown Supply Verification to 21 AFP, Revision 13
2-PT-Q017B, Alternate Safe Shutdown Supply Verification to 23 CHP, Revision 11
2-PT-Q017C, Alternate Safe Shutdown Supply Verification to 23 CCP, Revision 17
2-PT-Q017D, Alternate Safe Shutdown Supply Verification to 23 SWP, Revision 11
2-PT-Q017E, Alternate Safe Shutdown Supply Verification to 24 SWP, Revision 11
2-PT-Q017F, Alternate Safe Shutdown Supply Verification to 21 Safety Injection and Residual Heat Removal Pumps, Revision 9
EN-DC-127, Control of Hot Work and Ignition Sources, Revision 15
EN-DC-128, Fire Protection Impact Reviews, Revision 10
EN-DC-161, Control of Combustibles, Revision 13
EN-DC-186, Fuse Control, Revision 2
EN-DC-330, Fire Protection Program, Revision 4
SAO-703, Fire Protection Impairment Criteria and Surveillance, Revision 35
SEP-FPP-IP-001, IPEG Fire Protection Program, Revision 4
SEP-FPP-IP-002, IPEG Fire Watch Program, Revision 2
Operations Procedures
2-AOP-SSD-1, Control Room Inaccessibility Safe Shutdown Control, Revision 23
2-ONOP-FP-001, Plant Fires, Revision 17
2-SOP-ESP-001, Local Equipment Operation and Contingency Actions, Revision 12
Operator Safe Shutdown Training
IOLP-LOR-AOP010, 2/3-AOP-SSD-1, Control Room Inaccessibility Safe Shutdown Control, Revision 1
OPEX Reviews
OE-NOE-2015-30
CA-14,
IN 2015-02, Antifreeze Agents in Fire Water Sprinkler Systems
Quality Assurance Audits and Self Assessments
QA-9-2016-IP-1, Fire Protection, Revision 6
System Health Reports
480Vac Systems, 1

st and 3 rd Qtr. 2016

IPEG Fire Protection, 2

nd Quarter 2016

IPEG Fire Protection, 3

rd Quarter 2016

Completed Tests, Surveillances, and Preventive Maintenance
0-ELC-420-FIR, Appendix R Emergency Light Unit Inspection, Battery Replacement, and test, Completed on 2/15/16 and 11/3/16
0-PT-M001, Fire Brigade Equipment Inventory and Inspection, Completed11/6/16 and 12/3/16
2-PT-2Y017, Penetration Fire Barrier Seal Inspection, Completed 10/12/12 and 12/14/14
2-PT-2Y041, Fire Damper Functionality, Completed 6/12/12 and 4/6/15
2-PT-3Y015A, Underground Fire Loop Flow, Completed 10/24/11 and 7/12/15
2-PT-3Y015B, Turbine Building Fire Loop Flow, 5/17/11 and 7/27/14
2-PT-A023, Fire Main Booster Pump capacity Test, Completed 4/08/14 and 8/13/15
2-PT-A040, Diesel Driven Fire Pump Capacity, Completed on 2/15/15 and 2/14/16
2-PT-A048, Rollup Fire Doors, Completed 9/8/15 and 10/17/16
2-PT-A057, U1 Smoke Detector Test, Completed 9/30/14 and 9/28/15
2-PT-M034A, 11 Fire Main Booster Pump, Completed on 7/28/16 and 8/24/16
2-PT-M034B, 12 Fire Main Booster Pump, Completed on 7/28/16, 8/24/16, and 9/22/16
2-PT-M040, Diesel Fire Pump, Completed on 9/11/16 and 10/17/16
2-PT-M049B, Appendix R Emergency Lighting (Nuclear), Completed on 9/23/16 and 10/15/16
2-PT-SA012D, Ionization Type Smoke Detector (PAB-Specific), Completed 4/18/16 and 9/26/16
2-PT-SA012D, Ionization Type Smoke Detectors (PAB), Completed 11/19/15
2-PT-SA020, Swing Fire Doors, Completed 4/18/16 and 9/26/16
PT-EM9, Fire Dampers Operability, Completed 5/1/14 and 1/6/16
PT-SA11, Diesel Generator Building Fire Detection System, Completed 1/15/16 and 8/16/16
PT-SA12A, Ionization Type Smoke Detector (Conventional), Completed 2/9/16 and 7/19/16
PT-SA12B, Ionization Type Smoke Detector (PAB), Completed 2/11/16 and 9/22/16
PT-SA17, CCR Intake Smoke Detectors and Ventilation Control, Completed 1/15/16 and
8/26/16
Transient Combustible Evaluations
16-046, SFP Equipment Area, 10/3/16
16-044, AFW Pump Room, 10/8/16
16-045, AFW Building 2

nd Elevation, 10/9/16

16-047, U2 AFW Pump Room, 10/17/16
16-048, Fan House/PAB Annex, 10/19/16
Hot Work Permits
279749, U2, Turbine Bldg. 15' Col. 9 Line B-7, 9/15/16
297947, U2, Turbine Bldg. 33' Col. 3 Line B, 9/15/16
2864, U2, Telecom Room 15', 9/26/16
309854, U1,
FP-1 Elbow (Tool Room) EL. 15', 10/26/16
Fire Fighting Strategies (i.e., Pre-Fire Plans)
PFP-211, General Floor Plan - Primary Auxiliary Building 80'EL., Revision 14
PFP-212, General Floor Plan - Primary Auxiliary Building 98' EL., Revision 14
PFP-253, Control Room - Control Building, Revision 13
PFP-258, EDG #21-#22-#23-Diesel Generator Building/Electrical Tunnel Exhaust Fans, Revision 5
Fire Brigade Training
I0LP-OPS-FBT003, Fire Brigade Leadership (Initial/Retraining), 9/9/16
Initial Fire Brigade Training Manual, 2016
I0LP-OPS-FBT003, Fire Brigade Annual Retraining, 8/16
I0LP-OPS-FBT003, Fire Brigade Annual Retraining, 12/16
Fire Brigade Drills and Critiques
U1 TB Appendix R EDG, 9/17/16
U2 Dock Diesel Storage Tank, 9/14/16
U2 Dryden Diving Trailers, 9/14/16
U3 NLW Chem. App., 9/18/16
U3 MBFPL0 Purifier, 9/25/16
U3 Area 15' Water Factory, 11/1/16
Large Fires and Explosions Mitigation Strategies Documents
0-AOP-SEC-3, Event Contingency Actions, Revision 3
0-SOP-ESP-002, Emergency Contingency Plan, Revision 12
0-SOP-ESP-003, Emergency Contingency Plant Strategy Attachments, Revision 1
2-SOP-ESP-001, Local Equipment Operations and Contingency Actions, Revision 4
3-SOP-ESP-001, Local Equipment Operations and Contingency Actions, Revision 9
Corrective Action Program [Condition Reports (CR)]
CR-IP2-2004-00609
CR-IP2-2007-00719
CR-IP2-2010-03184
CR-IP2-2014-00128
CR-IP2-2014-00528
CR-IP2-2014-00904
CR-IP2-2014-01970
CR-IP2-2015-00483
CR-IP2-2015-01702
CR-IP2-2015-03333
CR-IP2-2015-04087
CR-IP2-2016-00458
CR-IP2-2016-00517
CR-IP2-2016-00699
CR-IP2-2016-01146
CR-IP2-2016-02710
CR-IP2-2016-03052
CR-IP2-2016-03209
CR-IP2-2016-03554
CR-IP2-2016-05139
CR-IP2-2016-05584
CR-IP2-2016-06527
CR-IP2-2016-06584
CR-IP2-2016-06637
CR-IP2-2016-06650
CR-IP2-2016-06674
CR-IP2-2016-06737
CR-IP2-2016-06828
CR-IP2-2016-06977
CR-IP2-2016-06593*
CR-IP2-2016-06844*
CR-IP2-2016-07028*
CR-IP2-2016-07048*
CR-IP2-2016-07049*
CR-IP2-2016-07050*
CR-IP2-2016-07074*
CR-IP2-2016-07077*
CR-IP2-2016-07078*
CR-IP2-2016-07082*
CR-IP2-2016-07092*
CR-IP2-2016-07094*
CR-IP2-2016-07105*
CR-IP2-2016-07233*
CR-IP2-2016-07310*
CR-IP2-2016-07316*
CR-IP2-2016-07317*
CR-IP2-2016-07320*
CR-IP2-2016-07322*
CR-IP2-2016-07323*
CR-IP2-2016-07340*
  • NRC identified during this inspection.

Work Orders

00224629
00339098
00340641
00340644
00340653
50065602
51498409
51503416
2309599
52309622
52310161
52429908
2448198
52458897
52474186
52477866
2501024
52527196
52537922
52541985
2556636
52560550
52582200
52587735
2624553
52638317
52638848
52639020
2640117
52643882
52644044
52649255
2654544
52663061
52672476
52672477
2677506
52677933
52677934
52690147
2695005
52696115
52697773
52699588
2704374
52706670
52706673
52713556
2721451
52727166

Miscellaneous Documents

10/32A-W001, IP2 Type 1, Fire Barrier Penetration Seal Index 9 PAB)
10/32A-W002, IP2 Type 1 Fire Barrier Penetration Seal Index (Diesel Generator Building)
CE-PS 100-79, Fireproofing of Diesel Generator Bldg., 6/21/79
Daily Plant status report, 11/29/16
Fire Protection System Impairment Summary Unit 2, Dated 11/01/16
Indian Point Unit 2 Fire Impairment Log, 11/1/16
IP2 Post-Fire Safe Shutdown OMA Timeline Validations on 12/18/12, 5/14/13, and 5/16/13
IPEG Radio System Summary Description, 2016
OAP, Operations Commitments and Policy Details, Revision 26

LIST OF ACRONYMS

CFR Title 10 of the

Code of Federal Regulations

DRS Division of Reactor Safety
FA Fire Area
FHA Fire Hazards Analysis
FPP Fire Protection Program
FZ Fire Zone
IP Inspection Procedure
NFPA National Fire Protection Association
NRC Nuclear Regulatory Commission,
U.S. [[]]
UFSAR Updated Final Safety Analysis Report