{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSLYVANIA 19406-2713 | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSLYVANIA 19406-2713 | ||
May 9, 2018 MEETING SUMMARY MN No. 18-005 | May 9, 2018 MEETING | ||
==SUMMARY== | |||
MN No. 18-005 | |||
LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC. | LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC. | ||
Line 25: | Line 29: | ||
==SUBJECT:== | ==SUBJECT:== | ||
SUMMARY OF PUBLIC MEETING | |||
==SUMMARY== | |||
OF PUBLIC MEETING | |||
On March 27, 2018, at 6:00 p.m., an annual assessment meeting for Pilgrim Nuclear Power Station (Pilgrim) was held at Hotel 1620 in Plymouth, MA, between the U.S. Nuclear Regulatory Commission (NRC) and Entergy Nuclear Operations, Inc. (Entergy). The meeting was conducted in two parts, a discussion between NRC and Entergy, followed by a question and answer period with members of the public. | On March 27, 2018, at 6:00 p.m., an annual assessment meeting for Pilgrim Nuclear Power Station (Pilgrim) was held at Hotel 1620 in Plymouth, MA, between the U.S. Nuclear Regulatory Commission (NRC) and Entergy Nuclear Operations, Inc. (Entergy). The meeting was conducted in two parts, a discussion between NRC and Entergy, followed by a question and answer period with members of the public. | ||
Line 39: | Line 45: | ||
https://www.nrc.gov/info-finder/reac tors/pilg/special-oversight.html | https://www.nrc.gov/info-finder/reac tors/pilg/special-oversight.html | ||
2 A transcript of this public meeting has been included as an enclosure to this meeting summary. Feedback forms submitted by members of the public following the meeting will be evaluated. The public meeting notice can be found in in ADAMS with Accession Number ML18073A140. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html | 2 A transcript of this public meeting has been included as an enclosure to this meeting summary. Feedback forms submitted by members of the public following the meeting will be evaluated. The public meeting notice can be found in in ADAMS with Accession Number ML18073A140. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. | ||
. | |||
_______/RA/___________________ Anthony Dimitriadis, Chief Reactor Projects Branch 5 | _______/RA/___________________ Anthony Dimitriadis, Chief Reactor Projects Branch 5 | ||
Line 54: | Line 59: | ||
==SUBJECT:== | ==SUBJECT:== | ||
SUMMARY OF PUBLIC MEETING dated May 9, 2018 | |||
==SUMMARY== | |||
OF PUBLIC MEETING dated May 9, 2018 | |||
DISTRIBUTION: (via email) | DISTRIBUTION: (via email) | ||
Line 71: | Line 78: | ||
DJanda, DNMS RidsNRRPMPilgrim Resource DOCUMENT NAME: G:\DRP\BRANCH5\Annual Assessment Meetings\2017 EOC\2018 PG AAM\Meeting Summary\PG 2018 Annual Assessment Meeting Summary.docx ADAMS Accession Number: ML18130A159 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME MHardgrove ADimitriadis DATE 5/9/18 5/7/18 OFFICIAL RECORD COPY UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSLYVANIA 19406-2713 | DJanda, DNMS RidsNRRPMPilgrim Resource DOCUMENT NAME: G:\DRP\BRANCH5\Annual Assessment Meetings\2017 EOC\2018 PG AAM\Meeting Summary\PG 2018 Annual Assessment Meeting Summary.docx ADAMS Accession Number: ML18130A159 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME MHardgrove ADimitriadis DATE 5/9/18 5/7/18 OFFICIAL RECORD COPY UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSLYVANIA 19406-2713 | ||
May 9, 2018 MEETING SUMMARY MN No. 18-005 | May 9, 2018 MEETING | ||
==SUMMARY== | |||
MN No. 18-005 | |||
LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC. | LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC. | ||
Line 78: | Line 89: | ||
==SUBJECT:== | ==SUBJECT:== | ||
SUMMARY OF PUBLIC MEETING | |||
==SUMMARY== | |||
OF PUBLIC MEETING | |||
On March 27, 2018, at 6:00 p.m., an annual assessment meeting for Pilgrim Nuclear Power Station (Pilgrim) was held at Hotel 1620 in Plymouth, MA, between the U.S. Nuclear Regulatory Commission (NRC) and Entergy Nuclear Operations, Inc. (Entergy). The meeting was conducted in two parts, a discussion between NRC and Entergy, followed by a question and answer period with members of the public. | On March 27, 2018, at 6:00 p.m., an annual assessment meeting for Pilgrim Nuclear Power Station (Pilgrim) was held at Hotel 1620 in Plymouth, MA, between the U.S. Nuclear Regulatory Commission (NRC) and Entergy Nuclear Operations, Inc. (Entergy). The meeting was conducted in two parts, a discussion between NRC and Entergy, followed by a question and answer period with members of the public. | ||
Line 92: | Line 105: | ||
https://www.nrc.gov/info-finder/reac tors/pilg/special-oversight.html | https://www.nrc.gov/info-finder/reac tors/pilg/special-oversight.html | ||
2 A transcript of this public meeting has been included as an enclosure to this meeting summary. Feedback forms submitted by members of the public following the meeting will be evaluated. The public meeting notice can be found in in ADAMS with Accession Number ML18073A140. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html | 2 A transcript of this public meeting has been included as an enclosure to this meeting summary. Feedback forms submitted by members of the public following the meeting will be evaluated. The public meeting notice can be found in in ADAMS with Accession Number ML18073A140. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. | ||
. | |||
_______/RA/___________________ Anthony Dimitriadis, Chief Reactor Projects Branch 5 | _______/RA/___________________ Anthony Dimitriadis, Chief Reactor Projects Branch 5 | ||
Line 107: | Line 119: | ||
==SUBJECT:== | ==SUBJECT:== | ||
SUMMARY OF PUBLIC MEETING dated May 9, 2018 | |||
==SUMMARY== | |||
OF PUBLIC MEETING dated May 9, 2018 | |||
DISTRIBUTION: (via email) | DISTRIBUTION: (via email) |
Revision as of 00:13, 6 July 2018
ML18130A159 | |
Person / Time | |
---|---|
Site: | Pilgrim |
Issue date: | 05/09/2018 |
From: | Anthony Dimitriadis NRC/RGN-I/DRP/PB5 |
To: | |
Dimitriadis A | |
References | |
MN 18-005 | |
Download: ML18130A159 (3) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSLYVANIA 19406-2713
May 9, 2018 MEETING
SUMMARY
MN No.18-005
LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC.
FACILITY: PILGRIM NUCLEAR POWER STATION
SUBJECT:
SUMMARY
OF PUBLIC MEETING
On March 27, 2018, at 6:00 p.m., an annual assessment meeting for Pilgrim Nuclear Power Station (Pilgrim) was held at Hotel 1620 in Plymouth, MA, between the U.S. Nuclear Regulatory Commission (NRC) and Entergy Nuclear Operations, Inc. (Entergy). The meeting was conducted in two parts, a discussion between NRC and Entergy, followed by a question and answer period with members of the public.
To start, NRC presented its assessment of the safety performance of Pilgrim for calendar year 2017, and discussed the status of follow-up inspections to review Entergy's fulfillment of commitments listed in the Confirmatory Action Letter (CAL) issued by the NRC in August 2017.
Entergy management then provided their perspectives on the organization's focus areas and plant performance. NRC staff also provided a brief update on the operational status of Pilgrim at the time of the meeting. Copies of the slides presented by both the NRC and Entergy are included as enclosures to this meeting summary. Members of the public, local and State officials, and staffers representing local area Congressional offices observed the discussions.
Following the meeting between the NRC and Entergy, attendees were offered the opportunity to ask questions of NRC officials or make statements. Several local and State representatives spoke, and several Congressional staff members read prepared statements (copies are included as enclosures). Questions raised by members of the public were addressed by the NRC staff.
Additional information on the NRC's Annual Assessment Process and safety performance of Pilgrim can be found on the NRC's website at: https://www.nrc.gov/reactors/operating/
oversight/actionmatrix-summary.html. Further information regarding the additional NRC oversight at Pilgrim due to their Column 4 performance can be found on the NRC's website at:
https://www.nrc.gov/info-finder/reac tors/pilg/special-oversight.html
2 A transcript of this public meeting has been included as an enclosure to this meeting summary. Feedback forms submitted by members of the public following the meeting will be evaluated. The public meeting notice can be found in in ADAMS with Accession Number ML18073A140. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.
_______/RA/___________________ Anthony Dimitriadis, Chief Reactor Projects Branch 5
Division of Reactor Projects
Enclosures:
- 1. NRC Slides (ML18127A027) 2. Entergy Slides (ML18127A028)
- 3. Meeting Transcript (ML18127A033)
- 4. Prepared statement from Congressman Keating (ML18127A030)
- 5. Prepared statement from Senator Warren (ML18127A032) 6. Prepared statement from Senator Markey (ML18127A031)
3
SUBJECT:
SUMMARY
OF PUBLIC MEETING dated May 9, 2018
DISTRIBUTION: (via email)
ADimitriadis, DRP
LCline, DRP MHardgrove, DRP ECarfang, DRP, SRI
PBoguszewski, DRP, RI
DScrenci, ORA NSheehan, ORA DTifft, ORA JGreives, ORA
JWeil, OCA JLamb, NRR/DORL DPelton, DRP BWatson, NMSS
BKlukan, ORA
DJanda, DNMS RidsNRRPMPilgrim Resource DOCUMENT NAME: G:\DRP\BRANCH5\Annual Assessment Meetings\2017 EOC\2018 PG AAM\Meeting Summary\PG 2018 Annual Assessment Meeting Summary.docx ADAMS Accession Number: ML18130A159 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME MHardgrove ADimitriadis DATE 5/9/18 5/7/18 OFFICIAL RECORD COPY UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSLYVANIA 19406-2713
May 9, 2018 MEETING
SUMMARY
MN No.18-005
LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC.
FACILITY: PILGRIM NUCLEAR POWER STATION
SUBJECT:
SUMMARY
OF PUBLIC MEETING
On March 27, 2018, at 6:00 p.m., an annual assessment meeting for Pilgrim Nuclear Power Station (Pilgrim) was held at Hotel 1620 in Plymouth, MA, between the U.S. Nuclear Regulatory Commission (NRC) and Entergy Nuclear Operations, Inc. (Entergy). The meeting was conducted in two parts, a discussion between NRC and Entergy, followed by a question and answer period with members of the public.
To start, NRC presented its assessment of the safety performance of Pilgrim for calendar year 2017, and discussed the status of follow-up inspections to review Entergy's fulfillment of commitments listed in the Confirmatory Action Letter (CAL) issued by the NRC in August 2017.
Entergy management then provided their perspectives on the organization's focus areas and plant performance. NRC staff also provided a brief update on the operational status of Pilgrim at the time of the meeting. Copies of the slides presented by both the NRC and Entergy are included as enclosures to this meeting summary. Members of the public, local and State officials, and staffers representing local area Congressional offices observed the discussions.
Following the meeting between the NRC and Entergy, attendees were offered the opportunity to ask questions of NRC officials or make statements. Several local and State representatives spoke, and several Congressional staff members read prepared statements (copies are included as enclosures). Questions raised by members of the public were addressed by the NRC staff.
Additional information on the NRC's Annual Assessment Process and safety performance of Pilgrim can be found on the NRC's website at: https://www.nrc.gov/reactors/operating/
oversight/actionmatrix-summary.html. Further information regarding the additional NRC oversight at Pilgrim due to their Column 4 performance can be found on the NRC's website at:
https://www.nrc.gov/info-finder/reac tors/pilg/special-oversight.html
2 A transcript of this public meeting has been included as an enclosure to this meeting summary. Feedback forms submitted by members of the public following the meeting will be evaluated. The public meeting notice can be found in in ADAMS with Accession Number ML18073A140. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.
_______/RA/___________________ Anthony Dimitriadis, Chief Reactor Projects Branch 5
Division of Reactor Projects
Enclosures:
- 1. NRC Slides (ML18127A027) 2. Entergy Slides (ML18127A028)
- 3. Meeting Transcript (ML18127A033)
- 4. Prepared statement from Congressman Keating (ML18127A030)
- 5. Prepared statement from Senator Warren (ML18127A032) 6. Prepared statement from Senator Markey (ML18127A031)
3
SUBJECT:
SUMMARY
OF PUBLIC MEETING dated May 9, 2018
DISTRIBUTION: (via email)
ADimitriadis, DRP
LCline, DRP MHardgrove, DRP ECarfang, DRP, SRI
PBoguszewski, DRP, RI
DScrenci, ORA NSheehan, ORA DTifft, ORA JGreives, ORA
JWeil, OCA JLamb, NRR/DORL DPelton, DRP BWatson, NMSS
BKlukan, ORA
DJanda, DNMS RidsNRRPMPilgrim Resource DOCUMENT NAME: G:\DRP\BRANCH5\Annual Assessment Meetings\2017 EOC\2018 PG AAM\Meeting Summary\PG 2018 Annual Assessment Meeting Summary.docx ADAMS Accession Number: ML18130A159 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME MHardgrove ADimitriadis DATE 5/9/18 5/7/18 OFFICIAL RECORD COPY