Memo to File: May 7, 2018 Attached are NRC slides presented at the Annual Assessment Meeting for Pilgrim Nuclear Power Station on March 27, 2018.

1 Pilgrim Annual Assessment Meeting March 27, 2018 Agenda

  • Introduction
  • Discussion of NRC Oversight Results
  • Discussion of Confirmatory Action Letter Follow-Up Inspection Status
  • Entergy Response and Remarks
  • Break
  • Public Q&A
  • NRC Closing Remarks 2

ML18127A027

2 Annual Performance Assessment

  • Pilgrim operated safely in 2017
  • Pilgrims performance for 2017 warrants continued placement in Column 4
  • NRC noted some improvement in performance, but sustainability remains to be determined.

3 Background

  • 2015 - NRC placed Pilgrim in Column 4
  • 2016 - NRC enhanced oversight and inspections began
  • 2017 - NRC completed comprehensive team inspections (95003)

- NRC reviewed Pilgrim Recovery Plan

- Confirmatory Action Letter (CAL) issued 4

3 Enhanced Oversight Activities

  • Additional region-based resources to support enhanced baseline inspection o Increased problem identification and resolution samples on previously-identified performance issues o More in-depth inspections o Additional inspection resources
  • Increased NRC management oversight 5
  • 15,000+ inspection hours o 33 findings of very low safety significance o Performance Indicators - all Green
  • Significant Inspection and oversight in 2017:

o Supplemental Inspection (95003) o Refueling Outage Inspection, o Review of Entergys Recovery Plan o CAL development; 1st CAL inspection 2017 Inspection Findings and Performance Indicators 6

4 Confirmatory Action Letter Follow-up Inspections

  • CAL follow-up inspections scheduled to independently verify effectiveness of corrective actions
  • NRC inspectors will o review CAL items and focus areas to determine if corrective actions are completed and effective in accordance with the CAL commitments o evaluate whether Pilgrim has demonstrated sustained performance improvement 7

Confirmatory Action Letter Follow-up Inspections

  • Five quarterly team inspections o 1st inspection completed in 4th quarter of 2017 o 2nd inspection is ongoing o 3 additional inspections scheduled for 2018
  • Additional follow-up inspections will be scheduled, as warranted, until all CAL commitments are satisfied.

8

5 Summary

  • Pilgrim operated safely in 2017
  • NRC has seen some performance improvement, but the plant needs to demonstrate sustained improved performance to be removed from Column 4
  • Pilgrim will continue to receive heightened NRC inspection and oversight in 2018 9

Licensee Response and Remarks Brian Sullivan Site Vice President, Pilgrim Entergy Nuclear Operations, Inc.

10

Memo to File: May 7, 2018 Attached are NRC slides presented at the Annual Assessment Meeting for Pilgrim Nuclear Power Station on March 27, 2018.

1 Pilgrim Annual Assessment Meeting March 27, 2018 Agenda

  • Introduction
  • Discussion of NRC Oversight Results
  • Discussion of Confirmatory Action Letter Follow-Up Inspection Status
  • Entergy Response and Remarks
  • Break
  • Public Q&A
  • NRC Closing Remarks 2

ML18127A027

2 Annual Performance Assessment

  • Pilgrim operated safely in 2017
  • Pilgrims performance for 2017 warrants continued placement in Column 4
  • NRC noted some improvement in performance, but sustainability remains to be determined.

3 Background

  • 2015 - NRC placed Pilgrim in Column 4
  • 2016 - NRC enhanced oversight and inspections began
  • 2017 - NRC completed comprehensive team inspections (95003)

- NRC reviewed Pilgrim Recovery Plan

- Confirmatory Action Letter (CAL) issued 4

3 Enhanced Oversight Activities

  • Additional region-based resources to support enhanced baseline inspection o Increased problem identification and resolution samples on previously-identified performance issues o More in-depth inspections o Additional inspection resources
  • Increased NRC management oversight 5
  • 15,000+ inspection hours o 33 findings of very low safety significance o Performance Indicators - all Green
  • Significant Inspection and oversight in 2017:

o Supplemental Inspection (95003) o Refueling Outage Inspection, o Review of Entergys Recovery Plan o CAL development; 1st CAL inspection 2017 Inspection Findings and Performance Indicators 6

4 Confirmatory Action Letter Follow-up Inspections

  • CAL follow-up inspections scheduled to independently verify effectiveness of corrective actions
  • NRC inspectors will o review CAL items and focus areas to determine if corrective actions are completed and effective in accordance with the CAL commitments o evaluate whether Pilgrim has demonstrated sustained performance improvement 7

Confirmatory Action Letter Follow-up Inspections

  • Five quarterly team inspections o 1st inspection completed in 4th quarter of 2017 o 2nd inspection is ongoing o 3 additional inspections scheduled for 2018
  • Additional follow-up inspections will be scheduled, as warranted, until all CAL commitments are satisfied.

8

5 Summary

  • Pilgrim operated safely in 2017
  • NRC has seen some performance improvement, but the plant needs to demonstrate sustained improved performance to be removed from Column 4
  • Pilgrim will continue to receive heightened NRC inspection and oversight in 2018 9

Licensee Response and Remarks Brian Sullivan Site Vice President, Pilgrim Entergy Nuclear Operations, Inc.

10