PUBLIC SERVICE INDIANA                                       March 1, 1985 S. W. Shields Senior Vice President -
PUBLIC SERVICE INDIANA March 1, 1985 S. W. Shields Senior Vice President -
Nuclear Division Mr. Harold R. Denton, Director                     Docket Nos. SIN-546 Office of Nuclear Reactor Regulation                           STN-547 U.S. Nuclear Regulatory Ccmmission                 Construction Pennit Nos.:
Nuclear Division Mr. Harold R. Denton, Director Docket Nos. SIN-546 Office of Nuclear Reactor Regulation STN-547 U.S. Nuclear Regulatory Ccmmission Construction Pennit Nos.:
Washington, D.C.           20555                               CPPR-170 CPPR-171
Washington, D.C.
20555 CPPR-170 CPPR-171


==SUBJECT:==
==SUBJECT:==
Line 28: Line 29:


==Dear Mr. Denton:==
==Dear Mr. Denton:==
 
Public Service Ccmpany of Indiana, Inc. (PSI) hereby surrenders Construction Permit Nos. CPPR-170 and 171 for the Marble Hill Nuclear Generating Station, Units 1 and 2.
Public Service Ccmpany of Indiana, Inc. (PSI) hereby surrenders Construction Permit Nos. CPPR-170 and 171 for the Marble Hill Nuclear Generating Station, Units 1 and 2. All construction-related activities at the site have been halted. Site activities have been conducted in accordance with my letter to you of January 18, 1984. The attachment provides a stmmary of those activities PSI will conduct to stabilize the site.
All construction-related activities at the site have been halted. Site activities have been conducted in accordance with my letter to you of January 18, 1984. The attachment provides a stmmary of those activities PSI will conduct to stabilize the site.
                              'Ibe ccmmitments contained in the attached stabilization plan will govern future activities, If you have any questions, please call.
'Ibe ccmmitments contained in the attached stabilization plan will govern future activities, If you have any questions, please call.
Sincerely, mf
Sincerely,
                                                                    / f ft Attachment cc:     J. G. Keppler         w/att.
/ f ft mf Attachment cc:
J. E. Konklin         w/att.
J. G. Keppler w/att.
J. F. Schapkcr       w/att.
J. E. Konklin w/att.
P. W. O'Connor       w/att.
J. F. Schapkcr w/att.
8503050401 850301 PDR 4         ADOCK 05000546 PDR                                                 QOok P. O. Box 190, New Washington, Indiana 47162               812. 289 .1000       (
P. W. O'Connor w/att.
8503050401 850301 PDR 4
ADOCK 05000546 QOok PDR P. O. Box 190, New Washington, Indiana 47162 812. 289.1000
(
_}}
_}}

Latest revision as of 03:41, 13 December 2024

Surrenders CPs CPPR-170 & CPPR-171.All const-related Activities on Site Halted.Site Activities Conducted Per Author .Commitments Contained in Encl Site Stabilization Plan Will Govern Future Activities
ML20102C233
Person / Time
Site: Marble Hill
Issue date: 03/01/1985
From: Shields S
PSI ENERGY, INC. A/K/A PUBLIC SERVICE CO. OF INDIANA
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20102C234 List:
References
NUDOCS 8503050401
Download: ML20102C233 (1)


Text

....

c.

PUBLIC SERVICE INDIANA March 1, 1985 S. W. Shields Senior Vice President -

Nuclear Division Mr. Harold R. Denton, Director Docket Nos. SIN-546 Office of Nuclear Reactor Regulation STN-547 U.S. Nuclear Regulatory Ccmmission Construction Pennit Nos.:

Washington, D.C.

20555 CPPR-170 CPPR-171

SUBJECT:

Marble Hill Nuclear Generating Station, Units 1 and 2

Dear Mr. Denton:

Public Service Ccmpany of Indiana, Inc. (PSI) hereby surrenders Construction Permit Nos. CPPR-170 and 171 for the Marble Hill Nuclear Generating Station, Units 1 and 2.

All construction-related activities at the site have been halted. Site activities have been conducted in accordance with my letter to you of January 18, 1984. The attachment provides a stmmary of those activities PSI will conduct to stabilize the site.

'Ibe ccmmitments contained in the attached stabilization plan will govern future activities, If you have any questions, please call.

Sincerely,

/ f ft mf Attachment cc:

J. G. Keppler w/att.

J. E. Konklin w/att.

J. F. Schapkcr w/att.

P. W. O'Connor w/att.

8503050401 850301 PDR 4

ADOCK 05000546 QOok PDR P. O. Box 190, New Washington, Indiana 47162 812. 289.1000

(

_