|
|
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 25, 2010 | | {{#Wiki_filter:May 25, 2010 |
| | |
| Mr. Larry Meyer Site Vice-President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241 SUBJECT: POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT 05000266/2010403(DRS);
| |
|
| |
|
| | ==SUBJECT:== |
| | POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT 05000266/2010403(DRS); |
| 5000301/2010403(DRS) | | 5000301/2010403(DRS) |
|
| |
|
| ==Dear Mr. Meyer:== | | ==Dear Mr. Meyer:== |
| On April 30, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Point Beach Nuclear Plant. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on April 30, 2010, with you and other members of your staff. | | On April 30, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Point Beach Nuclear Plant. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on April 30, 2010, with you and other members of your staff. |
| | |
| | The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license. |
|
| |
|
| The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
| | The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. |
|
| |
|
| No findings of significance were identified. | | No findings of significance were identified. |
|
| |
|
| In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosures, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection. | | In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). |
| | |
| | However, because of the security-related concerns contained in the enclosures, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection. |
|
| |
|
| Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. - SECURITY-RELATED INFORM ATION Should you have any questions concerning this inspection, we will be pleased to discuss them with you. | | Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. Should you have any questions concerning this inspection, we will be pleased to discuss them with you. |
|
| |
|
| Sincerely, | | Sincerely, |
| /RA by D. Funk for/ | | /RA by D. Funk for/ |
| | | Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 Nonpublic Enclosure: Inspection Report 05000266/2010403(DRS); |
| Eric Duncan, Chief | | 05000301/2010403(DRS) |
| | | w/Attachment: Supplemental Information cc w/encl: S. Coker, NSIR/DSO/DDSO/ST C. Johnson, NSIR J. Trapp, Region I M. Ernstes, RII M. Shannon, RIV M. Nazar, Executive Vice President, Nuclear Division & Chief Nuclear Officer cc w/o encl: Distribution via ListServ |
| Plant Support Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 | |
| | |
| Nonpublic Enclosure: Inspection Report 05000266/2010403(DRS); 05000301/2010403(DRS) w/Attachment: Supplemental Information | |
| | |
| cc w/encl: S. Coker, NSIR/DSO/DDSO/ST C. Johnson, NSIR J. Trapp, Region I M. Ernstes, RII M. Shannon, RIV M. Nazar, Executive Vice President, Nuclear Division & Chief Nuclear Officer cc w/o encl: Distribution via ListServ | |
| }} | | }} |
|
---|
Category:Letter
MONTHYEARML24295A1142024-10-31031 October 2024 Suppl Env Audit Summary Letter W/Enclosure 1 ML24295A0862024-10-21021 October 2024 Notification of NRC Baseline Inspection and Request for Information Inspection Report 0500026/2025002 L-2024-160, Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41)2024-10-21021 October 2024 Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41) L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-120, LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization2024-10-0808 October 2024 LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000266/2024011 and 05000301/2024011 L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-145, Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency2024-09-0909 September 2024 Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency ML24207A0202024-08-28028 August 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Point Beach Nuclear Plant, Units 1 and 2 (Docket Numbers: 50-0266 and 50-0301) IR 05000266/20240052024-08-21021 August 2024 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2024005 and 05000301/2024005) IR 05000266/20240022024-08-13013 August 2024 Integrated Inspection Report 05000266/2024002 and 05000301/2024002 L-2024-131, Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-08-0909 August 2024 Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review ML24214A3092024-08-0202 August 2024 Confirmation of Initial License Examination L-2024-113, License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections2024-07-24024 July 2024 License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections ML24194A1802024-07-24024 July 2024 – Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20244012024-07-23023 July 2024 Public - Point Beach Nuclear Plant Cyber Security Inspection Report 05000266/2024401 and 05000301/2024401 ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-116, Preparation and Scheduling of Operator Licensing Examinations2024-07-11011 July 2024 Preparation and Scheduling of Operator Licensing Examinations L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal IR 05000266/20240102024-07-10010 July 2024 Age-Related Degradation Inspection Report 05000266/2024010 and 05000301/2024010 L-2024-105, License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-06-26026 June 2024 License Amendment Request 300, Modify Containment Average Air Temperature Requirements L-2024-107, Schedule for Subsequent License Renewal Environmental Review2024-06-25025 June 2024 Schedule for Subsequent License Renewal Environmental Review ML24176A2242024-06-24024 June 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-093, Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision2024-06-10010 June 2024 Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision IR 05000266/20244202024-06-0505 June 2024 Security Baseline Inspection Report 05000266/2024420 and 05000301/2024420 ML24149A1922024-05-28028 May 2024 Notification of NRC Baseline Inspection and Request for Information ML24141A1382024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection.Docx ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000266/2024301; 05000301/2024301 L-2024-067, Annual Monitoring Report2024-04-26026 April 2024 Annual Monitoring Report ML24116A0402024-04-23023 April 2024 Periodic Update of the Updated Final Safety Analysis Report ML24071A0912024-04-22022 April 2024 Issuance of Relief Request I6-RR-03 - Extension of the Unit 2 Steam Generator Primary Nozzle Dissimilar Metal Welds Sixth 10-Year Inservice Inspection Program Interval IR 05000266/20240012024-04-11011 April 2024 Integrated Inspection Report 05000266/2024001 and 05000301/2024001 L-2024-030, Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-03-27027 March 2024 Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-043, Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules2024-03-25025 March 2024 Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules L-2024-011, and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications IR 05000266/20230062024-02-28028 February 2024 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2023006 and 05000301/2023006) L-2024-020, Refueling Outage Owners Activity Report (OAR-1) Unit 1 for Inservice Inspections2024-02-22022 February 2024 Refueling Outage Owners Activity Report (OAR-1) Unit 1 for Inservice Inspections ML24053A3732024-02-22022 February 2024 Operator Licensing Examination Approval Point Beach, March 2024 ML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-2024-001, Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-01-26026 January 2024 Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24005A3242024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0040 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 2024-09-09
[Table view] Category:Inspection Report
MONTHYEARIR 05000266/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000266/2024011 and 05000301/2024011 IR 05000266/20240052024-08-21021 August 2024 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2024005 and 05000301/2024005) IR 05000266/20240022024-08-13013 August 2024 Integrated Inspection Report 05000266/2024002 and 05000301/2024002 IR 05000266/20244012024-07-23023 July 2024 Public - Point Beach Nuclear Plant Cyber Security Inspection Report 05000266/2024401 and 05000301/2024401 IR 05000266/20240102024-07-10010 July 2024 Age-Related Degradation Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20244202024-06-0505 June 2024 Security Baseline Inspection Report 05000266/2024420 and 05000301/2024420 IR 05000266/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000266/2024301; 05000301/2024301 IR 05000266/20240012024-04-11011 April 2024 Integrated Inspection Report 05000266/2024001 and 05000301/2024001 IR 05000266/20230062024-02-28028 February 2024 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2023006 and 05000301/2023006) IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 IR 05000266/20234022023-11-14014 November 2023 Security Baseline Inspection Report 05000266/2023402 and 05000301/2023402 IR 05000266/20230032023-10-16016 October 2023 Integrated Inspection Report 05000266/2023003 and 05000301/2023003 IR 05000266/20235012023-08-29029 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000266/2023501 and 05000301/2023501 IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) IR 05000266/20230022023-07-18018 July 2023 Integrated Inspection Report 05000266/2023002 and 05000301/2023002 IR 05000266/20234012023-07-13013 July 2023 Public-Point Beach Nuclear Plant-Security Baseline Inspection Report 05000266/2023401; 05000301/2023401; Independent Spent Fuel Storage Security Inspection Report 07200005/2023401 IR 05000266/20230012023-05-0101 May 2023 Integrated Inspection Report 05000266/2023001 and 05000301/2023001 IR 05000266/20233012023-03-28028 March 2023 NRC Initial Examination Report 05000266/2023301 and 05000301/2023301 IR 05000266/20220062023-03-0101 March 2023 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022006 and 05000301/2022006) IR 05000266/20230102023-02-23023 February 2023 Comprehensive Engineering Team Inspection Report 05000266/2023010 and 05000301/2023010 IR 05000266/20220042023-01-24024 January 2023 Integrated Inspection Report 05000266/2022004 and 05000301/2022004 ML23009B7002023-01-24024 January 2023 Review of the Spring 2022 Steam Generator Tub Inspections Report IR 05000266/20224012022-12-0808 December 2022 Security Baseline Inspection Report 05000266/2022401 and 05000301/2022401 IR 05000266/20224042022-12-0202 December 2022 Cyber Security Inspection Report 05000266/2022404 and 05000301/2022404 IR 05000266/20220032022-11-0707 November 2022 Integrated Inspection Report 05000266/2022003 and 05000301/2022003 ML22298A2972022-10-27027 October 2022 Review of the Fall 2021 Steam Generator Tube Inspections Report IR 05000266/20220122022-09-29029 September 2022 Biennial Problem Identification and Resolution Inspection Report 05000266/2022012 and 05000301/2022012 IR 05000266/20220052022-08-26026 August 2022 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022005 and 05000301/2022005) IR 05000266/20220112022-08-0303 August 2022 Triennial Fire Protection Inspection Report 05000266/2022011 and 05000301/2022011 IR 05000266/20220022022-07-27027 July 2022 Integrated Inspection Report 05000266/2022002 and 05000301/2022002 IR 05000266/20220012022-05-0404 May 2022 Integrated Inspection Report 05000266/2022001 and 05000301/2022001 IR 05000266/20210062022-03-0202 March 2022 Annual Assessment Letter for Point Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021006 and 05000301/2021006) IR 05000266/20220102022-02-0909 February 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000266/2022010 and 05000301/2022010 IR 05000266/20210042022-01-28028 January 2022 Integrated Inspection Report 05000266/2021004 and 05000301/2021004 and Exercise of Enforcement Discretion IR 05000266/20214022021-11-10010 November 2021 Security Baseline Inspection Report 05000266/2021402 and 05000301/2021402 IR 05000266/20210032021-10-20020 October 2021 Integrated Inspection Report 05000266/2021003 and 05000301/2021003 IR 05000266/20215012021-10-0505 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000266/2021501 and 05000301/2021501 IR 05000266/20213012021-09-14014 September 2021 NRC Initial License Examination Report 05000266/2021301; 05000301/2021301, and 07200005/2021301 IR 05000266/20210052021-09-0101 September 2021 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021005 and 05000301/2021005) IR 05000266/20214032021-08-0404 August 2021 Security Baseline Inspection Report 05000266/2021403 and 05000301/2021403 IR 05000266/20210022021-07-29029 July 2021 Integrated Inspection Report 05000266/2021002, 05000301/2021002, and 07200005/2021001 IR 05000266/20210102021-07-0101 July 2021 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000266/2021010 and 05000301/2021010 IR 05000266/20210012021-04-21021 April 2021 Integrated Inspection Report 05000266/2021001 and 05000301/2021001 IR 05000266/20214012021-03-16016 March 2021 Security Baseline Inspection Report 05000266/2021401; 05000301/2021401; Independent Spent Fuel Storage Security Inspection Report 07200005/2021401 IR 05000266/20200062021-03-0404 March 2021 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020006 and 05000301/2020006) IR 05000266/20200902021-02-0909 February 2021 Final Significance Determination of a Green Finding; NRC Inspection Report 05000266/2020090 and 05000301/2020090 IR 05000266/20200042021-02-0808 February 2021 Integrated Inspection Report 05000266/2020004 and 05000301/2020004 IR 05000266/20204022020-12-14014 December 2020 Security Baseline Inspection Report 05000266/2020402 and 05000301/2020402 IR 05000266/20200032020-11-0404 November 2020 Integrated Inspection Report 05000266/2020003 and 05000301/2020003 IR 05000266/20200102020-09-24024 September 2020 Biennial Problem Identification and Resolution Inspection Report 05000266/2020010 and 05000301/2020010 2024-09-18
[Table view] |
Text
May 25, 2010
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT 05000266/2010403(DRS);
5000301/2010403(DRS)
Dear Mr. Meyer:
On April 30, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Point Beach Nuclear Plant. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on April 30, 2010, with you and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
No findings of significance were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
However, because of the security-related concerns contained in the enclosures, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
/RA by D. Funk for/
Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 Nonpublic Enclosure: Inspection Report 05000266/2010403(DRS);
05000301/2010403(DRS)
w/Attachment: Supplemental Information cc w/encl: S. Coker, NSIR/DSO/DDSO/ST C. Johnson, NSIR J. Trapp, Region I M. Ernstes, RII M. Shannon, RIV M. Nazar, Executive Vice President, Nuclear Division & Chief Nuclear Officer cc w/o encl: Distribution via ListServ