ML18040A227: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter:NIAG2GM MOHAWK PONER CORPORATION NUCLEAR ENGINEERING REPORT NINE MILE POINT 1 SHROUD CRACKING SAFETY ASSESSMENT FOR GENERIC LETTER 94-03 REPORT NO.NER-1M-014 Principal Contributors: | {{#Wiki_filter:NIAG2GM MOHAWK PONER CORPORATION NUCLEAR ENGINEERING REPORT NINE MILE POINT 1 SHROUD CRACKING SAFETY ASSESSMENT FOR GENERIC LETTER 94-03 REPORT NO. NER-1M-014 Principal Contributors: G.B. Inch R.F. Kirchner M.S. Leonard R. Corieri Reviewed by: D.L. Pike T.D. Lee A.G. Vierling Approved by: | ||
ae r ate Manager, Unit 1 Engineering 9409010263 940823 PDR ADOCK 05000220 1 P , PDR L | |||
~r Executive Summary The Nine Mile Point 1 safety assessment utilizes the BWR Vessel Internals Project (BWRVIP)generic assessment and reviews any diffezences in shroud cracking susceptibility including: | |||
available Nine Mile Point 1 shroud inspections, shroud fabrication, water chemistry, shroud material carbon content, neutron fluence and on-line years specific to Nine Mile Point 1.The generic BWRVIP assessment establishes that the likelihood of up to 360 degree cracking at some depth is fairly high for the H1 through H7 shroud welds.The structural margin assessment, assuming 360 degree cracking, determines that it is unlikely that any cracks exceed 90%depth at the H1 through H7 locations. | 0 I r | ||
The visual inspections available for H1, H2, H3,H4 and H7 support this conclusion. | |||
The overall structural margin assessment considers the uncertainties in the degree of cracking and recommends that the Oyster Creek shroud inspection results, scheduled to be completed October 1994, be used to assess the uncertainty in estimating the potential shzoud cracking depth for the Hl through H7 welds.The Nine Mile Point 1 specific safety assessment reviews in detail the shroud ring to inconel cone weld (H8)for Nine Mile Point 1 since failure of this weld had been postulated to potentially degrade the core spray system during the design basis recirculation line LOCA.This analysis demonstrates that intezgranular stress corrosion Cracking (IGSCC)cracking along the H8 weld is extremely unlikely.The ASME XI inspections of the H8 weld performed during the 1993 refuel outage, were conducted in the areas where this cracking is predicted to initiate.Surface cracking was not observed.Therefore, failure of the H8 weld prior to February 1995 (i.e., 360 degree through-wall cracks)is not considered credible.The ability of the plant safety features to perform their design basis functions, assuming 360 degree through-wall cracks, is reviewed with the conclusion that for the limiting main steam line break and recirculation line break, control rod insertion is not expected to be impacted and core spray would perform its design basis function.These conclusions aze based on preliminary analyses regarding the recirculation asymmetric loads and preliminary detailed main steam line break analyses for which BWRVIP assessment committee detailed analyses are in progress.In addition, a pzobabilistic safety assessment considering the probability of a design basis event coupled with shroud weld failure is performed. | Table of Contents Section Page Executive Summary 1.0 Introduction 2.0 Susceptibility Assessment 3.0 Structural Margin Assessment 12 4.0 Shroud Displacement Likelihood 13 5.0 Integrated Shroud Assessment 14 6.0 Conclusions 15 7.0 References 16 Figures 1-1 Shroud Welds 2 1-2 Detail Top Guide Flange 3 1-3 Detail Core Plate Flange 3 1-4 Detail Shroud to Shroud Support Joint 4 2-1 Reactor Water Conductivity Mean Values 11 Tables 2-1 Shroud Material Types 8 2-2 Nine Mile Point 1 Water Chemistry History 9 2-3 Nine Mile Point 1 Shroud Welds Estimated Fluence 9 2-4 Nine Mile Point 1 Shroud Visual Inspections 10 Appendices A) Analysis of the HS weld shroud ring to inconel support cone B) Probabilistic Safety Assessment of Potential IGSCC shroud weld failure | ||
This assessment determines that the overall inczemental coze damage and large/early release frequency is less than 8.3 E-8 per year or approximately 4 E-8 for a period between now and the scheduled February 1995 refueling outage.The Nine Mile Point 1 safety assessment supports continued operation until the scheduled February 1995 refuel outage based on the extremely low probability that the core shroud would fail to meet its design basis structuzal integrity margin during this time period.This, coupled with the extzemely low overall probabilistic risk estimate, supports continued operation until the scheduled February refuel outage. | |||
C 1.0 Introduction 1.1 Purpose The purpose of this safety assessment is to respond to Generic Letter (GL)94-03, which requested a safety analysis supporting continued operation of Nine Mile Point 1 until the scheduled February 1995 refuel outage.1.2 Scope This Nine Mile Point 1 specific shroud cracking safety assessment uses the BWR Shroud Cracking Generic Safety Assessment'ubmitted to the NRC through the BWR owners group.As, requested in GL 94-03, this safety assessment includes details of the conditions that influence the probability of occurrence of cracking and the rate of crack growth at Nine Mile Point 1.Based on this information, the likelihood of shroud cracking in excess of the required structural margins is assessed and the uncertainty in the extent of cracking is reviewed and if appropriate, corrective actions identified. | ~ r Executive Summary The Nine Mile Point 1 safety assessment utilizes the BWR Vessel Internals Project (BWRVIP) generic assessment and reviews any diffezences in shroud cracking susceptibility including: available Nine Mile Point 1 shroud inspections, shroud fabrication, water chemistry, shroud material carbon content, neutron fluence and on-line years specific to Nine Mile Point 1. The generic BWRVIP assessment establishes that the likelihood of up to 360 degree cracking at some depth is fairly high for the H1 through H7 shroud welds. The structural margin assessment, assuming 360 degree cracking, determines that it is unlikely that any cracks exceed 90% depth at the H1 through H7 locations. The visual inspections available for H1, H2, H3,H4 and H7 support this conclusion. The overall structural margin assessment considers the uncertainties in the degree of cracking and recommends that the Oyster Creek shroud inspection results, scheduled to be completed October 1994, be used to assess the uncertainty in estimating the potential shzoud cracking depth for the Hl through H7 welds. | ||
The safety assessment includes a pzobabilistic safety assessment to define the Nine Mile Point 1 overall risk assuming shroud weld failure.In addition, the shroud response to design basis loads assuming 360 degree through-wall cracking and the ability of the plant safety features to perform their design basis functions are reviewed.This safety assessment provides the basis for continued operation of Nine Mile Point 1 considering the uncertainty in the extent of cracking of the shroud welds identified in Figure 1-1.1.3 Shroud Function and Weld Designations The shroud is a stainless steel cylindrical assembly that provides a partition between the coze region and the downcomer annulus, to separate the upward flow of coolant thzough the core from the downward recirculation flow.The shroud also provides, in conjunction with other components, a eoolable core geometry.Nine Mile Point 1 relies on core spray cooling foz the recirculation line LOCA and does not require the shroud to maintain a floodable geometry following a postulated recirculation line break (i.e.bottom entry recirculation lines preclude a floodable region).The shroud is not a primary pressure boundary component. | The Nine Mile Point 1 specific safety assessment reviews in detail the shroud ring to inconel cone weld (H8) for Nine Mile Point 1 since failure of this weld had been postulated to potentially degrade the core spray system during the design basis recirculation line LOCA. | ||
The following are the Nine Mile Point 1 shroud weld designations, also shown in Figures 1-1, 1-2,1-3 and 1-4.H1, H2: | This analysis demonstrates that intezgranular stress corrosion Cracking (IGSCC) cracking along the H8 weld is extremely unlikely. The ASME XI inspections of the H8 weld performed during the 1993 refuel outage, were conducted in the areas where this cracking is predicted to initiate. Surface cracking was not observed. Therefore, failure of the H8 weld prior to February 1995 (i.e., 360 degree through-wall cracks) is not considered credible. | ||
Upper weld located below the bottom of the top guide support ring Mid-plane welds located above the core plate The welds located just above and below the coze plate Lower shroud to shroud support ring weld Inconel 182 weld between 304 SS shroud support ring to inconel shroud support cone Shroud Support Cone to Vessel Weld 1 | The ability of the plant safety features to perform their design basis functions, assuming 360 degree through-wall cracks, is reviewed with the conclusion that for the limiting main steam line break and recirculation line break, control rod insertion is not expected to be impacted and core spray would perform its design basis function. These conclusions aze based on preliminary analyses regarding the recirculation asymmetric loads and preliminary detailed main steam line break analyses for which BWRVIP assessment committee detailed analyses are in progress. In addition, a pzobabilistic safety assessment considering the probability of a design basis event coupled with shroud weld failure is performed. This assessment determines that the overall inczemental coze damage and large/early release frequency is less than 8.3 E-8 per year or approximately 4 E-8 for a period between now and the scheduled February 1995 refueling outage. | ||
UPPER RING UPPER CYLINOER CENTRAL RING CENTRAL UPPER C | The Nine Mile Point 1 safety assessment supports continued operation until the scheduled February 1995 refuel outage based on the extremely low probability that the core shroud would fail to meet its design basis structuzal integrity margin during this time period. This, coupled with the extzemely low overall probabilistic risk estimate, supports continued operation until the scheduled February refuel outage. | ||
C 1.0 Introduction 1.1 Purpose The purpose of this safety assessment is to respond to Generic Letter (GL) 94-03, which requested a safety analysis supporting continued operation of Nine Mile Point 1 until the scheduled February 1995 refuel outage. | |||
1.2 Scope This Nine Mile Point 1 specific shroud cracking safety assessment uses the BWR Shroud Cracking Generic Safety Assessment'ubmitted to the NRC through the BWR owners group. | |||
As, requested in GL 94-03, this safety assessment includes details of the conditions that influence the probability of occurrence of cracking and the rate of crack growth at Nine Mile Point 1. Based on this information, the likelihood of shroud cracking in excess of the required structural margins is assessed and the uncertainty in the extent of cracking is reviewed and if appropriate, corrective actions identified. The safety assessment includes a pzobabilistic safety assessment to define the Nine Mile Point 1 overall risk assuming shroud weld failure. In addition, the shroud response to design basis loads assuming 360 degree through-wall cracking and the ability of the plant safety features to perform their design basis functions are reviewed. This safety assessment provides the basis for continued operation of Nine Mile Point 1 considering the uncertainty in the extent of cracking of the shroud welds identified in Figure 1-1. | |||
1.3 Shroud Function and Weld Designations The shroud is a stainless steel cylindrical assembly that provides a partition between the coze region and the downcomer annulus, to separate the upward flow of coolant thzough the core from the downward recirculation flow. The shroud also provides, in conjunction with other components, a eoolable core geometry. Nine Mile Point 1 relies on core spray cooling foz the recirculation line LOCA and does not require the shroud to maintain a floodable geometry following a postulated recirculation line break (i.e. bottom entry recirculation lines preclude a floodable region). The shroud is not a primary pressure boundary component. | |||
The following are the Nine Mile Point 1 shroud weld designations, also shown in Figures 1-1, 1-2,1-3 and 1-4. | |||
H1, H2: Upper welds, with H1 above and H2 below the emergency core cooling system (ECCS) injection. | |||
H3: Upper weld located below the bottom of the top guide support ring H4,H5: Mid-plane welds located above the core plate H6A, H6B: The welds located just above and below the coze plate H7: Lower shroud to shroud support ring weld H8: Inconel 182 weld between 304 SS shroud support ring to inconel shroud support cone H9: Shroud Support Cone to Vessel Weld | |||
1 UPPER RING UPPER CYLINOER SEE FIGURE 1-2 CENTRAL RING H3 H4 CENTRAL UPPER C YLINOER CENTRAL HID CYLINOER CENTRAL LOWER CYLINOER H5 LOWER RING HSA LOWER CYLINOER SEE FIGURE 1-3 H7 HGB SEE FIGURE 1-4 SHROUO SUPPORT RING INCONEL SHROUD SUPPORT SKIRT FIGURE I-I NINE MILE POINT I SHROUD WELDS | |||
) | ) | ||
H2 CENTRAL RING (TOP GUIDE FLANGE) | H2 CENTRAL RING H3 (TOP GUIDE FLANGE) | ||
TO OBTAIN ALIGNMENT | FIGURE 1-2 DETAIL TOP GUIDE FLANGE LOWER RING (CORE PLATE FLANGE) | ||
OTHERWISE BLEND OF WELD INTO LEDGE WAS REOUIRED.2.FLOW BAFFLE FABRICATION BY P.F.AVERY. | HBB FIGURE 1-3 DETAIL CORE PLATE FLANGE | ||
SUPPORT RING/INCONEL CONE SKIRT FABRICATED BY COMBUSTION ENGINEERING 3.ALL FIELD WELD SHOWN HERE REQUIRED WELDING ELECTRODES PER ASTM A 298 E308 OR ASTM A 37IER308, EXCEPT FOR H8 SHOP WFLD.HB WELD IS INCONEL 182, | |||
J | |||
'I | |||
LOSER SHROUD CYLINDER 179'HROUD O.D. 213'ESSEL 1.0. | |||
SEE DETAIL G 17''NNULUS H7 WELD 5/16 MIN. | |||
SHIM (IF NECESSARY) | |||
TO OBTAIN ALIGNMENT R I/2 FIELD SEE DETAIL GB 8 GC WELD 3/16 FLOW BAFFLE FIELD WELD SFE NOTES I/4 BELOW 3/8 MAX GAP ALLOWEO H8 WELD CONE SKIRT SB 168 I'/2 REF. | |||
R I/2 SUPPORT RING FORGING (SA 336 F8) | |||
DETAIL GA RPV NOTES: | |||
SHELL I. J WELD INTO LEDGE JOINED WITH 3/16 FILLET WHERE LEDGE (SA 302 GR B) 37I/2'EF. | |||
SIZE PERMITTED. OTHERWISE BLEND OF WELD INTO LEDGE WAS MIN. | |||
REOUIRED. | |||
: 2. FLOW BAFFLE FABRICATION BY P.F.AVERY. SUPPORT RING/INCONEL CONE SKIRT FABRICATED BY COMBUSTION ENGINEERING | |||
: 3. ALL FIELD WELD SHOWN HERE REQUIRED WELDING ELECTRODES PER ASTM A 298 E308 OR ASTM A 37IER308, EXCEPT FOR H8 SHOP WFLD. HB WELD IS INCONEL 182, S(74.50 2X R.3I 1.50 S)74.00 BACKOROOVE TO SOUND METAL 5 WELD INSIDE 3 II/I6 | |||
~25 lo75 5 00 I SI80.62 I.oo-l | |||
~ 25 | |||
-II-09 S(69,00 2X, R.37 S(70.00 15'ETAIL G SI80.62 DETAIL GC DETAIL GB FlGURE I-4 DETAIL SHROUD TQ SHROUD SUPPORT JOINT | |||
2.0 Susceptibility Assessment 2.1 Overview The BWR Shroud Cracking Generic Safety Assessment'rovided a discussion of the factors which contribute to the susceptibility of a shzoud to stress corrosion cracking (IGSCC). The susceptibility criteria applied in refezence 1, SIL 0572, Rl'nd the BWR Owners Group (BWROG) BWR Coze Shroud Evaluation're water chemistry, material carbon content, fabrication history, neutron fluence and hot operating time The generic assessment recognized that factors such as degree of cold work and weld residual stress are significant factors affecting susceptibility; however, since quantitative information was not available these factors were not included. The Nine Mile Point 1 plant specific review of susceptibility discusses the above factors including residual stress, and available visual inspection information. | |||
2.2 Nine Mile Point 1 Shroud Inspections The generic assessment'iscussed the inspection recommendations of SIL 0572, Rl'nd the BWROG BWR Core Shroud Evaluation'nd provided both a qualitative summary of the inspection results and a quantitative summary of degree of cracking versus initial five cycle mean conductivity and cracking versus number of on-line years (hot operating time). This information, coupled with the susceptibility grouping factors, was used to establish the potential shroud welds for 360 degree cracking. Nine Mile Point 1 was classified in the generic assessment in the last grouping, 304 SS shrouds with welded plate rings and highest conductivity. The likelihood of 360 degree cracking for this grouping was considered fairly high, however, cracking greatez than 90% through-wall was considered unlikely in the short term. | |||
While Nine Mile Point 1 has not completed inspections in accordance with SIL 0572, Rl, visual inspections of welds H7 and HS have been performed as required by ASME Code Section XI visual inspection examination category B-N-1, Item B13.40, "Core Support Structure." | |||
These inspections satisfy the requirements of SIL 0572, Rl with the exception that no prior cleaning of the welds was performed. In addition, visuals of shroud welds H1, H2, H3 and H4 do exist as a result of access studies performed in 1989. The lighting provided was to the level needed foz verification of access and did not meet the requirements of SIL 0572 R1; however, the welds were clearly visible. | |||
The camera resolution level was as needed to gage accessibility. No prior cleaning was performed. The shroud visual inspections are summarized in Table 2-4. | |||
Niagara Mohawk is actively participating in the efforts of the BWRVIP inspection subcommittee to develop standardized visual inspection criteria. These standardized inspection criteria will include qualification of examination personnel through shroud specific experience and on-the-job training. In this regard, the inspection tapes summarized in Table 2-4 have been reviewed by an NMPC Level III qualified examinez concurrently with a GE level III qualified examiner, who participated in the examination activities at both Quad | |||
4 I | |||
Cities and Dresden and who is qualified to the enhanced level proposed by the new standards. Both examiners concluded that there was no evidence of cracking at the locations inspected. | |||
2.3 Basis For Ranking Nine Mile Point 1 Shroud fields A Nine Mile Point 1 specific review of the fabrication history, water chemistry, material carbon content, neutron fluence, and on line years has been completed and is provided below. | |||
2.3.1 Fabrication History The generic assessment'dentifies the shroud weld locations exhibiting the greatest extent of circumferential cracking as the ring to shell welds, i.e. H1, H2, H3, and H6A,H6B. The highest susceptibility was linked to the fabrication of rings cut from rolled plate and welded into a ring configuration, followed by machining to size. The Nine Mile Point 1 shroud rings, with the exception of the shroud support ring, aze welded plate rings (see Figures 1-1 and 1-2). Table 2-1 has the details of the shroud materials. The fabrication records indicate that the Nine Mile Point 1 shrouds and the Oyster Creek shrouds were fabricated by P.F. Avery during the same time period. A specific breakdown between the two shrouds of which specific items went into each shroud could not be found, so all the heat numbers related to each part number are identified in Table 2-1. All shop P.F. Avery welds were submerged arc welds using ASTM A-371 Type ER-308 filler metal with 5% minimum ferrite content and a maximum interpass tempezatuze of 350 degrees F. | |||
The shroud support ring is a forged 304 SS ring, however, for Nine Mile Point 1 the H7 and HS welds to the forged ring have a plant specific susceptibility because the shroud support ring forging was sensitized during the initial vessel heat treatment. The H7 weld is a field weld which was not stress relieved and therefore is considered to be suceptable to IGSCC czacking due to higher weld stresses and sensitized base material. The susceptibility to crack initiation and crack growth rate foz the H7 weld is considered similar to that used foz the welded plate zing evaluations (Hl through H6). The HS location susceptibility is discussed in detail in Appendix A. The Appendix A analysis concludes that IGSCC through the heat affected zone (HAZ) of the HS weld is extremely unlikely because the residual stresses were relieved for this weld during the initial vessel heat tzeatment, and because the HS weld is generally compressive during operation. In addition, the Appendix A analysis predicts that IGSCC cracking at HS would initiate at the OD surface due to the highest tensile stresses being located on the OD. The ASME XI inspection of the OD of HS revealed no indications. | |||
The inconel shroud support cone to vessel weld (H9) is not considered a shroud weld in this assessment. This is an inconel weld to inconel cone which is not creviced and was stress relieved during the vessel post weld heat treatment. This places the weld in a much more IGSCC resistant category which allows this weld to be eliminated from further discussion in this report. | |||
2.3.2 Water Chemistry The generic assessment'dentifies the mean conductivity for the first five cycles as a factor foz susceptibility grouping. Figure 2-1 and Table 2-2 provide the Nine Mile Point 1 specific cycle mean conductivities. This conductivity places Nine Mile Point 1 in the susceptible category for which IGSCC cracking in welded plate ring welds is likely to occur. | |||
2.3.3 Material Carbon Content The generic assessment'dentifies the carbon content as a factor in susceptibility grouping, with 304 shrouds being more susceptible than 304L. The Nine Mile Point 1 shroud matezial is 304, with the specific material carbon content identified in Table 2-1. | |||
2.3.4 Neutron Fluence The generic assessment'id not select fluence as a primary contributor to extensive cracking. However, a fluence effect on cracking susceptibility (IASCC at f>3-5 E 20 nvt) or a synergistic interaction of fluence .in already sensitized material (IGSCC at f>1E19 nvt) is expected and was verified at Brunswick-1 and KKM. The Nine Mile Point 1 specific fluence at each weld location is provided in Table 2-3. | |||
2.3.5 On-Line Years Consistent with the generic assessment', on-line years was used to estimate hot operating time. Nine Mile Point 1 on-line years is 14.4 years. The generic assessment did not use hot operating time to group the plants, however, the inspection data to date indicates that cracking in excess of 180 degrees was unlikely until a plant accumulated 10 on-line years. | |||
2.4 Estimated IGSCC Susceptibility for Nine Mile Point 1 Consistent with the generic assessment', the likelihood of 360 degree cracking at some depth is fairly high. The likelihood of 360 degree cracking to depths approaching analysis allowables is considered unlikely and is discussed in Section 3. | |||
0 TABLE 2-1 SHROUD MATERIAL TYPES MATERIAL PART NUMBER PART NAME QUANTITY CARBON COMMENTS ON TYPE HEAT NUMBER CONTENT - / MATERIAL / PROCESS 1 UPPER RING 2 PIECES A248 TYPE 384 65444-1 .864 PLATE 65235-IA .842 2 UPPER CYLINDER 2 PIECES A248 TYPE 384 65235-18 ~ 842 3 CENTRAL RING 2 PIECES A248 TYPE 384 65294-1 .856 CENTRAL UPPER 2 PIECES A248 TYPE 384 65235-1 .842 CYLINDER 65291-lA .852 CENTRAL MID 848784-2 .853 2 PIECES A248 TYPE 384 CYLINDER 65298-1 .847 65295-1 .862 65298-lA '847 CENTRAL LOWER 848784-28 .853 2 PIECES A248 TYPE 384 CYLINDER 848784-2A ~ 853 65291-1 ~ 852 7 LOWER RING 2 PIECES A248 TYPE 384 65444-1 .864 65291-1 ~ 852 B LOWER CYLINDER 2 PIECES A248 TYPE 384 848784-2A .853 848784-2B .853 65298-1A ,847 SHROUD 1 PIECE ASME SA-336 FS G-23/245352 NOT KNOWN FORGING SUPPORT RING NINE MILE POINT UNIT I SHROUD DATA NOTES: I. HEAT NUMBER DATA SHOWN MAY BE APPLICABLE FOR NINE MILE POINT I ANO/OR OYSTER CREEK. | |||
4 | |||
~ ~ | |||
Table 2-2 Nine Mile Point j. Water Chemistry History | |||
.,'::::.".:: Cycle.'::::'.'':,'.'.:,,'- ;::.:::::,-': Mea'ri";:".;,.Va'3 u~(j:,'::::.j ,'::,'Ch:1'o'r'i'de',( | |||
',;:-',;:.Co'n due't':i;:v'i.'t'y'.,':.';:.'k 0.432 30 0.525 46 0.591 58 0.445 44 0.291 33 0.225 27 0.181 26 0.133 25 0.087 18 10 0.082 0.084 Table 2-3 Shroud Weld Estimated Fluence Estimated Fluences (n/cm',E)lMev) | |||
H1 8.7E+09 4E+18 H2 4.6E+10 2E+19 H3 4.0E+11 2E+20 H4 7.8E+11 3.5E+20 H5 8.1E+11 3.6E+20 H6A 6.2E+07 3E+16 H6B 2.0E+07 9E+15 H7 <<1.0E+07 <<4E+15 Base on progecte EFPD at EOC Cyc e 11 (EOC Cycle 11 February 1995) | |||
P | |||
~ ~ | |||
Table 2-4 Shroud Visual Inspections i': """::::We'1d:..",,:.':,.;;: ~:'":-',.:::XD/QD~!::;;$N):;Neigh'tilrigj: ',ic3,"e'a'n'ed~':."! | |||
.,",:,:,:,::Numb.er;:.:,,,-'- :<:,''::.::.Exam!; d::;:,:,':;;-:; .'::;'':!:Etiam.,l'::,d:,',,:',,":iExa'mi neddy>> ~",'~:Exa'm':,',:.'d'~g,~ jP'i'o'vi;d'ed) .:Yes''j<N07p,~,i".. | |||
Hl 1989 63" 11% OD As No needed H2 1989 63 II 11% OD As No needed H3 1989 29" OD As No Needed H4 1989 85" 15% OD As No Needed H7 1986 568" 100% OD ASME XI No 1988 SIL 572 1993 H8 1986 568" 100% OD ASME XI No 1988 SIL 572 1993 10 | |||
I Figure 2-1 Reactor Water Conductivity Mean Values 10.00 ~ | |||
1.00 ~ | |||
IJ 0.10 ~ | |||
1 Max Weeldy Mean Va~ycW Q hyde Mean VUws wch S Id. Oaf. | |||
1I Aytl lace 0.01 I 8 | |||
Fuel Cycle 11 | |||
3.0 Structural Margin Assessment The generic assessment'iscussed the structural margins inherent in the shroud design and noted that 304 SS is a ductile material with high toughness properties even after accounting foz the effects of neutron fluence, and that only a minimal remaining ligament (5%-10% of wall) is required to maintain structural margins under post accident loads when 360 degree cracking is present. The generic assessment applies an assumption that cracking is initiated after one fuel cycle and that crack growth can be estimated analytically using the PLEDGE Model. Inspection of the Nine Mile Point 1 hot operating time and mean cycle conductivity demonstrates that Nine Mile Point 1 is bounded by the generic assessment conclusion that finding a 360 degree through-wall crack with an average depth in excess of 90% during the Fall 1994 inspections is unlikely. However, because of the uncertainties associated with residual stress profiles and oxide wedging phenomenon, the generic assessment could not rule out cracking in excess of 90%. | |||
The uncertainty associated with the residual stzesses is applicable to the Hl through H7 welds. The cracking uncertainty associated with HS weld is addressed separately in Appendix A. | |||
The next Nine Mile Point 1 refueling outage is currently scheduled for February 1995. A detailed inspection consistent with the BWRVIP inspection guidelines currently under development is scheduled and/or a pre-emptive repair would be implemented for all shroud horizontal welds. Considering the uncertainty in the extent of through-wall cracking prediction, the 1994 Fall outage inspection results of Oyster Creek (scheduled to commence at the end of September) will be used to determine the uncertainty associated with the potential for up to 360 degree cracking in excess of 90%. The Oyster Creek fall inspection is considered to be directly applicable to the structural margin assessment for Nine Mile Point 1 because the shroud fabrication is similar (see Section 2.3.1), and therefore, the uncertainty associated with residual stress profiles will be reduced. In addition, the Nine Mile Point 1 first 5 cycle mean conductivity is bounded by the Oyster Creek initial 5 cycle average, and the hot operating time is similar in magnitude. Therefore, the Oyster Creek inspection results are expected to allow Niagara Mohawk to assess the uncertainty associated with the structural margin integrity for the H1 through H7 welds. | |||
12 | |||
I 4.0 Shroud Displacement Likelihood As discussed in the generic assessment', several conditions must exist simultaneously in order for shroud displacement to occur. First, a 360 degree, ) 90% deep crack must exist in the shroud. Then, a design basis guillotine main steam line break inside the flow limiters or a DEGB recirculation line break, or a design basis seismic event must occur to generate the loads assumed on the shroud. Note that opezational transients, small and intermediate break LOCA, main steam line bzeaks outside the flow limiter and safe shutdown earthquake all have significantly reduced loads and minimal potential shroud displacement. In this section the Nine Mile Point 1 specific overall likelihood of the limiting design basis scenario is discussed using plant specific probabilities from the Individual Plant Examination (IPE). | |||
4.1 Cracking Likelihood Consistent with the genezic assessment', it is considered unlikely that Nine Mile Point 1 has 360 degree cracking in excess of 90% depth. This is supported by, the generic analysis and prior visual inspections. The uncertainty associated with this prediction is to be further clarified by review of the Fall Oyster Creek inspection (zesults expected in October 1994) . In addition, 360 degree cracking in excess of 90% depth is not credible at the H8 inconel 182 weld between the shroud support ring and inconnel shroud support cone (see appendix A). Note that H8 is a limiting location in the generic assessment regarding the consequences of failure during a DEGB recirculation line LOCA. | |||
4 ' LOCA Likelihood A Nine Mile Point 1 specific probabilistic safety assessment (PSA) based on the Nine Mile Point 1 IPE was performed to evaluate the safety significance of continued operation prior to determining the status of'elds related to the reactor shroud. The PSA evaluated the probability of accident scenarios resulting from potential failures of shroud welds. The events of primary concern are double ended guillotine breaks (DEGB) in main steam lines, DEGB in reactor recirculation lines, and earthquakes. Based on the probability of these events and the estimated conditional failure probability of the shroud welds, the estimated overall incremental core damage and large/early release frequency is less than 8.3E-8 per year. The detailed discussion of the PSA is included in Appendix B. | |||
4.3 Inspection Timing Consistent with the recommendations of the generic assessment', Nine Mile Point 1 plans to review the results of the Oyster Creek Fall inspection and other Fall inspections to assess the uncertainty associated with the evaluation that cracking is unlikely to be greater than 360 degrees and gzeatez than 90% deep. | |||
13 | |||
~ ~ | |||
5.0 Integrated 'Shroud Assessment The Nine Mile Point 1 susceptibility assessment has concluded that the likelihood of up to 360 degree cracking at some depth is fairly high at the H1 through H7 weld location. Cracking to any significant depth at the HS weld location is considered extremely unlikely. The structural margin assessment established that cracking at the H1 through H7 locations in excess of 90% depth is unlikely. The uncertainty in the cracking prediction will be re-assessed based upon the results of the Oyster Creek Fall (October 1994) inspection. | |||
The overall likelihood of the event scenario described, a LOCA or seismic event with a 360 degree, > 90% deep crack, is extremely unlikely. The assessment of the core damage frequency assuming shroud weld failure combined with the design basis seismic or recirculation line LOCA or MSLB LOCA is extremely low considering operation until February 1995, (4 E-8 per 6 months). This overall risk supports continued operation of Nine Mile Point 1 until the scheduled February 1995 refuel outage. | |||
The consequences of 360 degree through-wall cracks applicable to Nine Mile Point 1 were reviewed as part of the generic assessment'. This assessment reviewed the shroud response to the stzuctural loadings resulting from design basis events including, steam line break, recirculation line break and asymmetric loads associated with the recirculation line break. This assessment included a review of the ability of plant safety features to perform their functions considering the design basis accident loads with 360 degree through-wall cracking (e.g. control rod insertion, ECCS injection). Through the BNRVIP assessment subcommittee, analyses are under development which will provide more detailed shroud loads considezing both the main steam line break LOCA and recirculation line LOCA. These analyses are intended to better define the asymmetric loads associated with the recirculation suction line LOCA and the amount of shroud lift following the main steam line break LOCA. These analyses are estimated to be completed in the October 1994 time frame. In the interim, additional information is available to supplement the generic assessment discussion of the recirculation line break and steam line break. | |||
Main Steam Line Break Accident: | |||
GPU Nuclear has completed preliminary assessments4 using a RELAP 5 Oyster Creek model which confirms that the maximum potential lift is limited such that the top guide does not clear the fuel channels(e.g. less than 14 inches of lift) and control rod insertion is not expected to be impacted. Core spray lines are expected to be damaged by the possible displacement, however, the break is above TAF so ECCS injection inside the reactor vessel, at or above the core steaming rate, will assure short and long term cooling. | |||
Recirculation Line Break Accident: | |||
The generic assessment considered the shroud loads associated with the recirculation discharge line break as limiting and that 14 | |||
~ c no vertical displacement is expected at any but the vertically unsupported H8 weld. The consequence of this failure was vertical displacement (downward) which would damage the core spray lines and result in impaired core spray cooling. However, additional study of the H8 weld configuration (see Appendix A) has determined that failure of the H8 weld in such a manner which would allow vertical downward displacement is not a credible failure. With the H8 weld integrity assured, the core spray system would perform its design basis function and control rod insertion is assured. | |||
As discussed in the generic assessment, the lateral force on the shroud due to the blowdown asymmetric load is bounded by the restoring moment of the shroud weight and therefore, the recirculation line break analysis results are unchanged. As indicated above, additional analyses are in progress to address this issue generically through the BWRVIP assessment subcommittee. | |||
Nine Mile Point 1 has also reviewed the guidance provided in the generic assessment regarding through-wall crack indication during normal operation. This generic information has been provided to operations and has been incorporated into the normal operating procedure for the Nuclear Steam Supply System (N1-OP-1). The procedure has been revised to alert operators of the expected plant response should a through-wall shroud crack develop. This training was provided to all operations crews prior to their resumption of shift duties. | |||
6.0 Conclusions The Nine Mile Point 1 shroud cracking safety assessment indicates that 360 degree, greater than 90% through-wall cracking is unlikely to occur during operation up to the scheduled February 1995 refuel outage. The uncertainty in this determination will be assessed based upon the results of the scheduled Fall 1994 Oyster Creek shroud inspection. Based on this conservative approach, the probability that the Nine Mile Point 1 coze shroud does not satisfy the design basis structural integrity margins is considered extremely low. Even extreme condition of 360 degree, greater than 90% through-wall if the cracking coupled with a design basis accident is assumed, the safety assessment shows that control zod insertion is not expected to be impacted and the core spray system would provide adequate core cooling. This low probability, combined with the extremely low overall | |||
'zisk estimate, supports continued operation until the scheduled February 1995 refueling outage. | |||
15 | |||
S J | |||
' | |||
7.0 References GENE-523-A107P-0794, Revision 1 "BWR Shroud Cracking Generic Safety Assessment", August 1994 | |||
: 2) SIL 0572 R1, "Core Shroud Cracks" 4 | |||
: 3) GE-NE-523-148-1193, "BWR Core Shroud Evaluation", April 1994 | |||
: 4) GPUN Calc ¹C1302-222-5450-W06, Rev 0, "Oyster Creek Shroud Dispacement Calculation" | |||
: 5) NMPC Calc ¹ SO-VESSEL-M025, rev 0, "Residual stress and remaining ligament calcualtion for the shroud ring H8 weld", Contains MPR calculation 085-252-01 referenced in Appendix A. | |||
: 6) NMPC Technical Report SAS-94-005 "Probabilistic Risk Assessment of Potential Integranular Stress Corrosion Cracking of NMP1 Core Shroud", August 5, 1994 16 | |||
J APPENDIX A Analysis of Nine Mi3.e Point 1 Weld HS Shroud Support Ring to Inconel Shroud Support cone 17 | |||
I | |||
) | |||
%1MPR ASSOCIATES INC, E N VINE EBS August 16, 1994 ANALYSIS OF NINE MILE POINT UNIT 1 SHROUD SUPPORT RING TO INCONEL SUPPORT CONE WELD H-8 Weld H-8 attaches the Type 304 forged stainless steel shroud support ring to the Alloy 600 support cone as shown in Figure 1. The shroud support assembly, including the vessel shell, the cone and the ring, but not the shroud itself, was post weld heat treated (PWHT) at 1150'F during vessel fabrication, As a consequence, weld H-8 was stress relieved during PWHT, and peak tensile residual stresses were reduced by the heat treatment. In addition, the PWHT sensitized the stainless steel ring which increases concern for IGSCC on the ring side of weld H-8. While the weld metal and cone were also sensitized, these are Inconel materials which are more resistant to IGSCC than the stainless material, especially in the absence of crevices. Normal operating stresses in the support ring are expected to be compressive due to the difference in thermal expansion coefficients of the ring and the cone/vessel. | |||
A finite element stress analysis was performed on the shroud support assembly to quantify normal operating stress levels and to determine the stress state during PWHT (MPR Calculation 085-252-01). From the latter analysis, the stress relief effects for presumed weld residual stresses can be estimated. The residual stresses that remain, when combined with operating stresses, determine the overall stress state of weld H-8 during normal operation. | |||
The analysis confirmed that the hoop, radial and axial principal stress components are all generally compressive in the support ring during normal operation. The principal stress of concern is the radial one, since this stress component could lead to stress corrosion cracking whose orientation would cause weld H-8 to lose its vertical load-carrying capability. | |||
Stress contour plots for the radial stress component during the original stress relief and under normal operating conditions are shown in Figures 2 and 3. The principal load during stress relief is the thermal load, during which time the shroud is not attached. | |||
During normal operation, the loads include thermal, pressure, deadweight and hydraulic uplift forces. | |||
Inspection of Figure 3 reveals that the highest tensile radial stresses exist at the top of weld H-8 in the ring. This is considered to be the limiting location for possible crack initiation. It is presumed that local tensile weld residual stresses existed at this location after welding, and they were at the yield stress level. During stress relief (see Figure 2), | |||
18 | |||
L I | |||
induced tensile thermal stresses, combined with the reduced yield strength at the 1150'p temperature, reduced the weld residual stresses to a low value, about 7 ksi. During normal operation, these stresses add to the normal operating stresses for a total stress of about 13 ksi at the top of weld H-8 in the ring. | |||
While it is unlikely that cracking would initiate in a 13 ksi stress field, we note that the location of highest tensile stress is an area that'is inspectable. Further, cracking in the heat affected zone of the support ring adjacent to weld H-8 would grow very slowly, if at all, because: (1) it would have to grow into an area of applied compressive stresses, and (2) weld residual stresses are also expected to become compressive in the ring at the center of weld H-8. | |||
Finally, the limiting load for weld H-8 is the recirculation pipe break download of 2 million lbs. It is estimated that a ligament of only 1/4 inch is required in weld H-8 to support this load. Therefore, cracking in weld H-8 would have to be quite extensive, about ninety percent throughwall for 360 degrees, in order for the weld to fail under limiting accident conditions. | |||
We conclude that, because of reduced weld tensile residual stresses in weld H-8, and the fact that only about 1/4 inch of weld is required to support the limiting download transient, weld H-8 is extremely unlikely to be in a condition that could fail. | |||
19 | |||
C I | |||
Shroud Axial (Y) (Type 304 Stainless Steel) | |||
Radial (X) | |||
Weld H-8 (Inconel 182) | |||
Shroud Support Ring (Type 304 Stainless Steel) | |||
Support Cone (Inconel 600) | |||
Vessel Wall (Low Alloy Steel) | |||
FAIMpQ Figure 1. Shroud Support Components and Weld H-8 F C65 252-OI C6/16/94 (I Jl) 20 | |||
I ANSYS 5.0 A AUG 9 1994 11:18:24 PLOT NO. 1 NODAL SOLUTION STEP=1 SUB =1 TIME=1 SX (AVG) | |||
RSYS=O DMX =1.074 SMN =-12442 SMNB=-47643 SMX =10539 qir ~i I | |||
SMXB=49670 | |||
-12442 | |||
-9889 | |||
-7335 | |||
-4782 | |||
-2228 325.242 2879 5432 7986 10539 ~ | |||
NINE MILE POINT UNIT 1 CORE SHROUD THERMAL ANALYSIS Figure 2. Radial Stress During PWHT | |||
ANSYS 5.0 A AUG 9 1994 11:24:12 PLOT NO. 1 NODAL SOLUTION STEP=1 SUB =1 TIME=1 SX (AVG) | |||
RSYS=O DMX =0.440901 SMN =-12070 SMNB=-23687 SMX =6508 SMXB=26637 h | |||
-12070 | |||
~E | |||
-10006 | |||
~ | |||
t J | |||
-7941 | |||
-5877 | |||
-3813 | |||
-1749 315.396 2380 4444 6508 r | |||
JC r | |||
NINE MILE POINT UNIT 1 CORE SHROUD THERMAL ANALYSIS Figure 3. Radial Stress During Normal Operation | |||
APPENDIX B Analysis and Results from NMPC Technical Report SAS-94-005 "Probabilistic Risk Assessment of Potential Integranular Stress Corrosion Cracking of NMP1 Core Shroud", August 5, 1994 23 | |||
r The cracking of vessel shroud welds can lead to failure of vessel internals support. Should vessel support fail, core integrity may be compromised and, of chief importance, insertion of control rods may not be possible if fuel bundles are no longer parallel to control rod movement. In addition, for NMP1, shroud movement may result in failure of core spray spazgers during some events. Based on the engineering review and the information in References 1, 2, and 3, it is apparent that the principal scenarios of concern are main steam line breaks (MSLB), reactor recirculation line breaks (RRLB), and seismic events. Each of these events has the potential to induce loadings that could fail cracked welds and cause core movement. As such, this report calculates the probability of each of the events. | |||
These probability values should be useful in assessing the safety significance of the issue at NMP1. | |||
The NMP1 IPE is a detailed evaluation of the probability and consequences of plant risk. Because it was completed prior to the elevated concern regarding shroud IGSCC, it does not explicitly include recent insights associated with this issue. In that regard, the probability of shroud IGSCC events can be calculated, similar to the events developed in the IPE, and presented as an incremental risk above-and-beyond that calculated in the IPE. | |||
The best way to develop and describe the risk associated with the postulated IGSCC events is to treat each possible scenario separately and then sum the probability of each scenario to develop the total IGSCC event frequency. Therefore, the following section individually treats the MSLB, RRLB, and seismic events. | |||
Main Steam Line Break (MSLB) Shroud IGSCC Risk The MSLB event is defined by the rapid initiation of a crack which results in a double ended guillotine break 360'ircumferential (DEGB) of piping and an immediate loss of coolant (LOCA) event. As | |||
'such, makeup flow, from primarily the core spray system and feedwater, is required. This specific event was modeled in the NMP1 IPE as one of several contributors to the large LOCA (LLOCA) class of initiators. | |||
Other contributors to the large LOCA event frequency include: core spray system leakage/ruptures, multiple instrument penetration failures, SLC system piping leakage/rupture, and feedwater piping leakage/rupture. As discussed above, non-DEGB events pose little threat relative to the shroud issue and are not included in this risk assessment. Large LOCA events, including DEGB, were not a significant contributor to IPE calculated accident frequency. | |||
The postulated MSLB initiating event frequency represents a certain fraction of the IPE LLOCA initiating event frequency since MSLB is one of several events that aze considered to cause a LLOCA. However, the NMP1 IPE does not differentiate between specific LLOCA events because, foz the purposes of severe accident modeling, the plant response is similar between individual events that fit the IPE LLOCA definition. | |||
As the NMP1 IPE LLOCA frequency is quantified as 7E-4 per year, for this analysis, the MSLB frequency can be reasonably considered less 24 | |||
than 7E-4 per year. | |||
The BWROG'as performed research that is useful in characterizing the extent to which MSLB frequency is less than NMP1 LLOCA calculated frequency. The BWROG estimates that recirculation system piping, and it is inferred other large piping, has a rupture frequency of "several orders of magnitude lower than" 7.51E-6 per year. | |||
It should the be pointed out that there possibility of an instantaneous is considerable uncertainty DEGB of pipes in a nuclear as to application. A widely considered theory suggests that the pipe would leak foz some time before catastrophic rupture. As such, the leak would alert operators who would shut-down the plant before the DEGB occurred.,In any event, no credit is taken for the leak-before-break argument and the BWROG value is assumed representative of the MSLB frequency under the DEGB failure mode. | |||
Following a MSLB event, the integrity of the shroud welds will be challenged. IPEs have typically assumed that this passive failure mode is of low probability. However, due to the IGSCC issue, this assumption, at least temporarily, should be questioned. Per Pinelli', | |||
the possibility that weld failures will occur is "unlikely" even considering IGSCC. For this analysis, "unlikely" is reasonably translated to mean less than 1E-2 pez event. As such, the probability of a MSLB and resultant shroud failure is estimated as less than 7.51E-8 per year. | |||
According to the current IPE model, this event would be considered a core damage and large-early release event since any large LOCA with a failure to SCRAM was connected to core damage and large/early release endstates. When added to a core damage frequency (CDF) of 5.5E-6 per year and a large/Early release frequency (LERF) of 6.9E-7 per year, the MSLB-'Shroud event probability, 7.51E-8 per year, is a relatively minor contributor. | |||
In actuality, the impact is even less than the above calculation shows. The NMP1 IPE model does not link LLOCA events with a failure to SCRAM to the ATWS model but rather to a Class IV failure endstate. | |||
The IPE conservatively assumes that such scenarios result in core damage. This is done because the low probability of the sequences does not justify the level of effort required to incorporate the necessary modeling details. | |||
In reality, even if control rods are not inserted, the reactor could possibly be shut down using SLC injection. This is especially appropriate to consider since, at a minimum, some rods may be at least partially inserted even with the fuel rods in disarray. From the IPE, SLC failure probability, including the associated operator actions to initiate SLC and prevent dilution (Top events SL, EP, and CH), is 1.6E-3 per event. Multiplying this by the above 7.51E-8 per year yields an event probability of 1.2E-10 per year. As such, if could be credited then the risk impact would be far less. Note that SLC this does not include any consideration of SLC equipment or operator failures that could relate to a relocated shroud. In any event, the above shows the nature of safety provided by the SLC system during the postulated MSLB/shroud event. | |||
25 | |||
C I | |||
~ ~ | |||
In addition, even if covered and establish SLC failed, heat removal it is possible to keep the core equal to or greater than that generated by the reactor. This could be accomplished by some combination of containment spray or containment vent operation in concert with some combination of successful injection. These actions would be directed via the current symptom based emergency operating procedures (EOP). It is not suggested that the success probability would be large, but rather, in the above calculations. | |||
it is pointed out to show the conservatism Reactor Recirculation Line Break (RRLB) Shroud IGSCC Risk The RRLB event initiates when a 360'ircumferential crack develops in a reactor recirculation line and very quickly ruptures. As with the MSLB, this event results in an immediate loss of coolant (LOCA) event. | |||
The IPE treatment relative to large LOCA is the same as that discussed above. As such, all related discussion for MSLB is relevant here. | |||
From above, a good estimate, for the purposes of this study is the BWROG 7.51E-6 per year value. Should a RRLB event occur, makeup is immediately required. However, since the break could be below the core, core spray is required because spray cooling is necessary to protect the core until containment flooding is completed. For NMP1, the core spray spargers are attached to the shroud. As such, following a RRLB, should the HS shroud core support weld fail, the entire shroud could drop. This would result in failure of the core function; although core spray flow will still reach the vessel. 'pray Due to the nature of the HS shroud weld, engineering review has determined that it is very reliable; even considering the IGSCC issue This review has classified the H8 weld failure as an extremely unlikely event. As such, a value of 1E-3 per event failure frequency has been conservatively assigned as the failure probability of the HS shroud weld following a RRLB event. Multiplying 1E-3 per event by the above 7.51E-6 per year yields a RRLB/Shroud/Coze spray failure event of 7.51E-9 per year. | |||
In addition, the above is potentially conservative because although the coze spray function is failed, its inventory, as injection rather than spray, can reach the vessel. Combined with feedwater, CRD, and SLC, the total inventory might be enough to prevent fuel damage prior to completion of containment flooding. This success path is not credited in this, or most likely any other analysis, but mentioned here as a possible success path that could be developed it is further. | |||
Seismic Event Shroud IGSCC Risk Per NRC', the safe shutdown earthquake (SSE) is expected to produce minimal movement of equipment related to the above issue. As such, would require MSLB or RRLB events coincident with the SSE to cause it potential accidents. Due to the low likelihood of each individual event, the coincident occurrence of the SSE and a large break is 26 | |||
~ r | |||
~ | |||
~ g | |||
considered very small. Even if the SSE and large break could cause a problem (assume they occurred on the same day rather than in the same minute or hour), a CDF estimate of less than 1E-10 per year would result. | |||
Additionally, a beyond SSE earthquake could also occur such that the earthquake itself causes failure of a large line (MSLB or RRLB) and the shroud. Events of this magnitude are of very low probability (i.e. (1E-7 per year). Also, earthquakes of this magnitude would likely fail a significant portion of other plant equipment such that conditional failure probability of the plant as a whole would be large regardless of the status of the shroud welds. As such, the incremental risk caused by potentially cracked shroud welds is judged insignificant. | |||
Summing the above conservatively calculated scenario frequencies results in a total incremental CDF and LERF frequency of 8.27E-8 per year. Considering that only six months remain until the next refueling outage the incremental risk is half that above, or 4.14E-8 per 6 months. Also, it has been demonstrated that the above calculation is conservative. Conservative or not, the above incremental risk is very small. | |||
REFERENCES (1) Zimmerman, R. P. "Intergranular Stress" Corrosion Cracking of Core Shrouds in Boiling Water Reactors, Generic Letter 94-03, USNRC, July 25, 1994. | |||
(2) Stang, J.F..(USNRC) Letter to Farrar, D.L. (ComEd), "Resolution of Core Shroud Cracking at Dresden, Unit 3 and Quad Cities, Unit 1, " | |||
7/21/94. | |||
(3) Pinelli, R.A. Letter to BWR Owner's Group Executives, "BWROG Response to NRC Request for Shroud Information, " GE-NE-523-AI07P-0794, July 13, 1994. (GE Proprietary.) | |||
(4) Nine Mile Point Unit One Final Safety Analysis Report (Updated). | |||
(5) Kirchner, R. F., et. al., "Nine Mile Point Nuclear Station Unit 1 Individual Plant Examination (IPE)" Niagara Mohawk Power Corporation, SAS-TR-93-001, July 1993. | |||
(6) England, L.A.- Letter to USNRC (Serkiz, A.W.), "Response to NRC Request for Information on Pipe Break Frequencies, " BWR Owner's Group, BWROG-93149, December 8, 1993. | |||
27 | |||
I ~ ~ | |||
~ ~ | |||
$ II, | |||
~ eg ATTACHMENT 8 NINE MILE POINT UNIT 1 DOCKET NO. 50-220 LICENSE NO. DPR-63 GENERIC LETTER 94-03 HI T RY F RE HR I PE TI | |||
~ a~ i S>>, | |||
~ ' ~ | |||
Niagara Mohawk has not performed any shroud inspections which meet all of the General Electric (GE) SIL 572, Revision 1 recommendations for lighting level, camera resolution and weld pre-cleaning. However, visual (camera) inspections of vessel internal components, which directly or indirectly included film footage of the shroud plates and weldments, have previously been performed. These inspection tapes have been reviewed jointly by a Niagara Mohawk Level III qualified examiner and a General Electric Level III qualified examiner, who participated in the examination activities at both Quad Cities and Dresden and who is qualified to the enhanced level proposed by the new standards. The results of Niagara Mohawk's review of past invessel visual inspection tapes is provided below and summarized in the accompanying table. | |||
Core shroud welds Hl, H2, H3 and H4 were filmed during a 1989 access study conducted to verify clearances for the reactor pressure vessel beltline inspection tool. The lighting provided was to the level needed for verification of access, and though not specifically deployed to illuminate the welds, the welds are clearly visible. The camera resolution level was as needed to gauge accessibility. No prior cleaning of the welds was performed. The review of these tapes by the Level III qualified examiners concluded that there was no evidence of gross cracking at the locations inspected. | |||
Invessel inspections of the shroud supporting ring to the shroud support skirt (ISI component RV15I) were conducted in 1986, 1988 and 1993 in accordance with ASME Section XI. The areas inspected encompass core shroud welds H7 and H8. The lighting level and camera resolution required by ASME Section XI meet the requirements of GE SIL 572, Revision 1. | |||
No prior cleaning of the welds was performed. The inspections of ISI component RV15I in 1986, 1988 and 1993 did not reveal any reportable indications. | |||
NMP1 RE HR UD VI AL CAMERA EXAMINATION | |||
,':;.',:-''Numb'e'r',:::,:-:',::::!:.':;Exam! d'::,:::,:;:,:;:;;::;:,:::;::-':::Exnm':,d;'.!:.'",)',:;::ilExIuiiIiiedjji H1 1989 63 II 11% OD No H2 1989 63" 11% OD As needed No II H3 1989 29 5% OD As needed No H4 1989 85" 15% OD As needed No H7 1986 568" OD ASME XI/ No 1988 SIL 572 1993 H8 1986 568" 100% OD ASME XI/ No 1988 SIL 572 1993 | |||
C | |||
~ g> I | |||
ATTACHMENT C NINE MILE POINT UNIT 1 DOCKET NO. 50-220 LICENSE NO. DPR-63 GENERIC LETTER 94-03 DRA I F RE HR FI ATI | |||
a' Viiiag W% | |||
g~g KlCRR arne ANCE CXZRlCSma~ | |||
D 55~ ~%KM ggg ~ | |||
gggggggg~ M F/gi I 4i Q~ | |||
. FÃXWzr 0 | |||
/gal~~~ | |||
CZRRamCza | |||
~ | |||
/per Fizz///i~ | |||
F/YFY//zi | |||
'"NFYr, r r< | |||
8S ll I ll So mmll r< | |||
j .<<~ mx<32%R~g N | |||
~5~d>Il | |||
'C k | |||
~ I | |||
%WRY | |||
~1 J | |||
a'1 I | |||
P p | |||
~ ~ ~ b | |||
P | |||
~ ~ | |||
~ ~ | |||
%g) ~ ~ | |||
I ~ ~ ~ | |||
~ ~ | |||
~ ~ | |||
~~ | ~' | ||
~ | |||
I v | |||
4 l | |||
t | |||
%KNEE% | |||
NISI'~~~ | |||
RHKRKR% | |||
0 0 | |||
H~ ~ES~REHiR-RRRIRKRR 8 RSCSa~5 ggaggKIMIS~ | |||
RSRRCS RRRSFISRKQ | |||
~ 52RRil ECRIRRERSHW RRW W=== ' | |||
0 kg~ | |||
8 Fz~ b'ijÃ&ri rsPy. | |||
0 I i'ik . + | |||
C | |||
~ + f ~ | |||
1 1 i~/r//>. | |||
L el/~~ | |||
rvigil II | |||
. A g~r II r+/ mmmll | |||
'. | |||
BFIH~ SREKM6 mam 8 | |||
I L | |||
'I | |||
,4 ry o | |||
T r l}} | |||
I | |||
Revision as of 21:55, 21 October 2019
ML18040A227 | |
Person / Time | |
---|---|
Site: | Nine Mile Point |
Issue date: | 08/19/1994 |
From: | Inch G, Kirchner R, Yaeger W NIAGARA MOHAWK POWER CORP. |
To: | |
Shared Package | |
ML17059A420 | List: |
References | |
GL-94-03, GL-94-3, NER-1M-014, NER-1M-14, NUDOCS 9409010263 | |
Download: ML18040A227 (74) | |
Text
NIAG2GM MOHAWK PONER CORPORATION NUCLEAR ENGINEERING REPORT NINE MILE POINT 1 SHROUD CRACKING SAFETY ASSESSMENT FOR GENERIC LETTER 94-03 REPORT NO. NER-1M-014 Principal Contributors: G.B. Inch R.F. Kirchner M.S. Leonard R. Corieri Reviewed by: D.L. Pike T.D. Lee A.G. Vierling Approved by:
ae r ate Manager, Unit 1 Engineering 9409010263 940823 PDR ADOCK 05000220 1 P , PDR L
0 I r
Table of Contents Section Page Executive Summary 1.0 Introduction 2.0 Susceptibility Assessment 3.0 Structural Margin Assessment 12 4.0 Shroud Displacement Likelihood 13 5.0 Integrated Shroud Assessment 14 6.0 Conclusions 15 7.0 References 16 Figures 1-1 Shroud Welds 2 1-2 Detail Top Guide Flange 3 1-3 Detail Core Plate Flange 3 1-4 Detail Shroud to Shroud Support Joint 4 2-1 Reactor Water Conductivity Mean Values 11 Tables 2-1 Shroud Material Types 8 2-2 Nine Mile Point 1 Water Chemistry History 9 2-3 Nine Mile Point 1 Shroud Welds Estimated Fluence 9 2-4 Nine Mile Point 1 Shroud Visual Inspections 10 Appendices A) Analysis of the HS weld shroud ring to inconel support cone B) Probabilistic Safety Assessment of Potential IGSCC shroud weld failure
~ r Executive Summary The Nine Mile Point 1 safety assessment utilizes the BWR Vessel Internals Project (BWRVIP) generic assessment and reviews any diffezences in shroud cracking susceptibility including: available Nine Mile Point 1 shroud inspections, shroud fabrication, water chemistry, shroud material carbon content, neutron fluence and on-line years specific to Nine Mile Point 1. The generic BWRVIP assessment establishes that the likelihood of up to 360 degree cracking at some depth is fairly high for the H1 through H7 shroud welds. The structural margin assessment, assuming 360 degree cracking, determines that it is unlikely that any cracks exceed 90% depth at the H1 through H7 locations. The visual inspections available for H1, H2, H3,H4 and H7 support this conclusion. The overall structural margin assessment considers the uncertainties in the degree of cracking and recommends that the Oyster Creek shroud inspection results, scheduled to be completed October 1994, be used to assess the uncertainty in estimating the potential shzoud cracking depth for the Hl through H7 welds.
The Nine Mile Point 1 specific safety assessment reviews in detail the shroud ring to inconel cone weld (H8) for Nine Mile Point 1 since failure of this weld had been postulated to potentially degrade the core spray system during the design basis recirculation line LOCA.
This analysis demonstrates that intezgranular stress corrosion Cracking (IGSCC) cracking along the H8 weld is extremely unlikely. The ASME XI inspections of the H8 weld performed during the 1993 refuel outage, were conducted in the areas where this cracking is predicted to initiate. Surface cracking was not observed. Therefore, failure of the H8 weld prior to February 1995 (i.e., 360 degree through-wall cracks) is not considered credible.
The ability of the plant safety features to perform their design basis functions, assuming 360 degree through-wall cracks, is reviewed with the conclusion that for the limiting main steam line break and recirculation line break, control rod insertion is not expected to be impacted and core spray would perform its design basis function. These conclusions aze based on preliminary analyses regarding the recirculation asymmetric loads and preliminary detailed main steam line break analyses for which BWRVIP assessment committee detailed analyses are in progress. In addition, a pzobabilistic safety assessment considering the probability of a design basis event coupled with shroud weld failure is performed. This assessment determines that the overall inczemental coze damage and large/early release frequency is less than 8.3 E-8 per year or approximately 4 E-8 for a period between now and the scheduled February 1995 refueling outage.
The Nine Mile Point 1 safety assessment supports continued operation until the scheduled February 1995 refuel outage based on the extremely low probability that the core shroud would fail to meet its design basis structuzal integrity margin during this time period. This, coupled with the extzemely low overall probabilistic risk estimate, supports continued operation until the scheduled February refuel outage.
C 1.0 Introduction 1.1 Purpose The purpose of this safety assessment is to respond to Generic Letter (GL) 94-03, which requested a safety analysis supporting continued operation of Nine Mile Point 1 until the scheduled February 1995 refuel outage.
1.2 Scope This Nine Mile Point 1 specific shroud cracking safety assessment uses the BWR Shroud Cracking Generic Safety Assessment'ubmitted to the NRC through the BWR owners group.
As, requested in GL 94-03, this safety assessment includes details of the conditions that influence the probability of occurrence of cracking and the rate of crack growth at Nine Mile Point 1. Based on this information, the likelihood of shroud cracking in excess of the required structural margins is assessed and the uncertainty in the extent of cracking is reviewed and if appropriate, corrective actions identified. The safety assessment includes a pzobabilistic safety assessment to define the Nine Mile Point 1 overall risk assuming shroud weld failure. In addition, the shroud response to design basis loads assuming 360 degree through-wall cracking and the ability of the plant safety features to perform their design basis functions are reviewed. This safety assessment provides the basis for continued operation of Nine Mile Point 1 considering the uncertainty in the extent of cracking of the shroud welds identified in Figure 1-1.
1.3 Shroud Function and Weld Designations The shroud is a stainless steel cylindrical assembly that provides a partition between the coze region and the downcomer annulus, to separate the upward flow of coolant thzough the core from the downward recirculation flow. The shroud also provides, in conjunction with other components, a eoolable core geometry. Nine Mile Point 1 relies on core spray cooling foz the recirculation line LOCA and does not require the shroud to maintain a floodable geometry following a postulated recirculation line break (i.e. bottom entry recirculation lines preclude a floodable region). The shroud is not a primary pressure boundary component.
The following are the Nine Mile Point 1 shroud weld designations, also shown in Figures 1-1, 1-2,1-3 and 1-4.
H1, H2: Upper welds, with H1 above and H2 below the emergency core cooling system (ECCS) injection.
H3: Upper weld located below the bottom of the top guide support ring H4,H5: Mid-plane welds located above the core plate H6A, H6B: The welds located just above and below the coze plate H7: Lower shroud to shroud support ring weld H8: Inconel 182 weld between 304 SS shroud support ring to inconel shroud support cone H9: Shroud Support Cone to Vessel Weld
1 UPPER RING UPPER CYLINOER SEE FIGURE 1-2 CENTRAL RING H3 H4 CENTRAL UPPER C YLINOER CENTRAL HID CYLINOER CENTRAL LOWER CYLINOER H5 LOWER RING HSA LOWER CYLINOER SEE FIGURE 1-3 H7 HGB SEE FIGURE 1-4 SHROUO SUPPORT RING INCONEL SHROUD SUPPORT SKIRT FIGURE I-I NINE MILE POINT I SHROUD WELDS
)
H2 CENTRAL RING H3 (TOP GUIDE FLANGE)
FIGURE 1-2 DETAIL TOP GUIDE FLANGE LOWER RING (CORE PLATE FLANGE)
HBB FIGURE 1-3 DETAIL CORE PLATE FLANGE
J
'I
LOSER SHROUD CYLINDER 179'HROUD O.D. 213'ESSEL 1.0.
SEE DETAIL G 17NNULUS H7 WELD 5/16 MIN.
SHIM (IF NECESSARY)
TO OBTAIN ALIGNMENT R I/2 FIELD SEE DETAIL GB 8 GC WELD 3/16 FLOW BAFFLE FIELD WELD SFE NOTES I/4 BELOW 3/8 MAX GAP ALLOWEO H8 WELD CONE SKIRT SB 168 I'/2 REF.
R I/2 SUPPORT RING FORGING (SA 336 F8)
DETAIL GA RPV NOTES:
SHELL I. J WELD INTO LEDGE JOINED WITH 3/16 FILLET WHERE LEDGE (SA 302 GR B) 37I/2'EF.
SIZE PERMITTED. OTHERWISE BLEND OF WELD INTO LEDGE WAS MIN.
REOUIRED.
- 2. FLOW BAFFLE FABRICATION BY P.F.AVERY. SUPPORT RING/INCONEL CONE SKIRT FABRICATED BY COMBUSTION ENGINEERING
- 3. ALL FIELD WELD SHOWN HERE REQUIRED WELDING ELECTRODES PER ASTM A 298 E308 OR ASTM A 37IER308, EXCEPT FOR H8 SHOP WFLD. HB WELD IS INCONEL 182, S(74.50 2X R.3I 1.50 S)74.00 BACKOROOVE TO SOUND METAL 5 WELD INSIDE 3 II/I6
~25 lo75 5 00 I SI80.62 I.oo-l
~ 25
-II-09 S(69,00 2X, R.37 S(70.00 15'ETAIL G SI80.62 DETAIL GC DETAIL GB FlGURE I-4 DETAIL SHROUD TQ SHROUD SUPPORT JOINT
2.0 Susceptibility Assessment 2.1 Overview The BWR Shroud Cracking Generic Safety Assessment'rovided a discussion of the factors which contribute to the susceptibility of a shzoud to stress corrosion cracking (IGSCC). The susceptibility criteria applied in refezence 1, SIL 0572, Rl'nd the BWR Owners Group (BWROG) BWR Coze Shroud Evaluation're water chemistry, material carbon content, fabrication history, neutron fluence and hot operating time The generic assessment recognized that factors such as degree of cold work and weld residual stress are significant factors affecting susceptibility; however, since quantitative information was not available these factors were not included. The Nine Mile Point 1 plant specific review of susceptibility discusses the above factors including residual stress, and available visual inspection information.
2.2 Nine Mile Point 1 Shroud Inspections The generic assessment'iscussed the inspection recommendations of SIL 0572, Rl'nd the BWROG BWR Core Shroud Evaluation'nd provided both a qualitative summary of the inspection results and a quantitative summary of degree of cracking versus initial five cycle mean conductivity and cracking versus number of on-line years (hot operating time). This information, coupled with the susceptibility grouping factors, was used to establish the potential shroud welds for 360 degree cracking. Nine Mile Point 1 was classified in the generic assessment in the last grouping, 304 SS shrouds with welded plate rings and highest conductivity. The likelihood of 360 degree cracking for this grouping was considered fairly high, however, cracking greatez than 90% through-wall was considered unlikely in the short term.
While Nine Mile Point 1 has not completed inspections in accordance with SIL 0572, Rl, visual inspections of welds H7 and HS have been performed as required by ASME Code Section XI visual inspection examination category B-N-1, Item B13.40, "Core Support Structure."
These inspections satisfy the requirements of SIL 0572, Rl with the exception that no prior cleaning of the welds was performed. In addition, visuals of shroud welds H1, H2, H3 and H4 do exist as a result of access studies performed in 1989. The lighting provided was to the level needed foz verification of access and did not meet the requirements of SIL 0572 R1; however, the welds were clearly visible.
The camera resolution level was as needed to gage accessibility. No prior cleaning was performed. The shroud visual inspections are summarized in Table 2-4.
Niagara Mohawk is actively participating in the efforts of the BWRVIP inspection subcommittee to develop standardized visual inspection criteria. These standardized inspection criteria will include qualification of examination personnel through shroud specific experience and on-the-job training. In this regard, the inspection tapes summarized in Table 2-4 have been reviewed by an NMPC Level III qualified examinez concurrently with a GE level III qualified examiner, who participated in the examination activities at both Quad
4 I
Cities and Dresden and who is qualified to the enhanced level proposed by the new standards. Both examiners concluded that there was no evidence of cracking at the locations inspected.
2.3 Basis For Ranking Nine Mile Point 1 Shroud fields A Nine Mile Point 1 specific review of the fabrication history, water chemistry, material carbon content, neutron fluence, and on line years has been completed and is provided below.
2.3.1 Fabrication History The generic assessment'dentifies the shroud weld locations exhibiting the greatest extent of circumferential cracking as the ring to shell welds, i.e. H1, H2, H3, and H6A,H6B. The highest susceptibility was linked to the fabrication of rings cut from rolled plate and welded into a ring configuration, followed by machining to size. The Nine Mile Point 1 shroud rings, with the exception of the shroud support ring, aze welded plate rings (see Figures 1-1 and 1-2). Table 2-1 has the details of the shroud materials. The fabrication records indicate that the Nine Mile Point 1 shrouds and the Oyster Creek shrouds were fabricated by P.F. Avery during the same time period. A specific breakdown between the two shrouds of which specific items went into each shroud could not be found, so all the heat numbers related to each part number are identified in Table 2-1. All shop P.F. Avery welds were submerged arc welds using ASTM A-371 Type ER-308 filler metal with 5% minimum ferrite content and a maximum interpass tempezatuze of 350 degrees F.
The shroud support ring is a forged 304 SS ring, however, for Nine Mile Point 1 the H7 and HS welds to the forged ring have a plant specific susceptibility because the shroud support ring forging was sensitized during the initial vessel heat treatment. The H7 weld is a field weld which was not stress relieved and therefore is considered to be suceptable to IGSCC czacking due to higher weld stresses and sensitized base material. The susceptibility to crack initiation and crack growth rate foz the H7 weld is considered similar to that used foz the welded plate zing evaluations (Hl through H6). The HS location susceptibility is discussed in detail in Appendix A. The Appendix A analysis concludes that IGSCC through the heat affected zone (HAZ) of the HS weld is extremely unlikely because the residual stresses were relieved for this weld during the initial vessel heat tzeatment, and because the HS weld is generally compressive during operation. In addition, the Appendix A analysis predicts that IGSCC cracking at HS would initiate at the OD surface due to the highest tensile stresses being located on the OD. The ASME XI inspection of the OD of HS revealed no indications.
The inconel shroud support cone to vessel weld (H9) is not considered a shroud weld in this assessment. This is an inconel weld to inconel cone which is not creviced and was stress relieved during the vessel post weld heat treatment. This places the weld in a much more IGSCC resistant category which allows this weld to be eliminated from further discussion in this report.
2.3.2 Water Chemistry The generic assessment'dentifies the mean conductivity for the first five cycles as a factor foz susceptibility grouping. Figure 2-1 and Table 2-2 provide the Nine Mile Point 1 specific cycle mean conductivities. This conductivity places Nine Mile Point 1 in the susceptible category for which IGSCC cracking in welded plate ring welds is likely to occur.
2.3.3 Material Carbon Content The generic assessment'dentifies the carbon content as a factor in susceptibility grouping, with 304 shrouds being more susceptible than 304L. The Nine Mile Point 1 shroud matezial is 304, with the specific material carbon content identified in Table 2-1.
2.3.4 Neutron Fluence The generic assessment'id not select fluence as a primary contributor to extensive cracking. However, a fluence effect on cracking susceptibility (IASCC at f>3-5 E 20 nvt) or a synergistic interaction of fluence .in already sensitized material (IGSCC at f>1E19 nvt) is expected and was verified at Brunswick-1 and KKM. The Nine Mile Point 1 specific fluence at each weld location is provided in Table 2-3.
2.3.5 On-Line Years Consistent with the generic assessment', on-line years was used to estimate hot operating time. Nine Mile Point 1 on-line years is 14.4 years. The generic assessment did not use hot operating time to group the plants, however, the inspection data to date indicates that cracking in excess of 180 degrees was unlikely until a plant accumulated 10 on-line years.
2.4 Estimated IGSCC Susceptibility for Nine Mile Point 1 Consistent with the generic assessment', the likelihood of 360 degree cracking at some depth is fairly high. The likelihood of 360 degree cracking to depths approaching analysis allowables is considered unlikely and is discussed in Section 3.
0 TABLE 2-1 SHROUD MATERIAL TYPES MATERIAL PART NUMBER PART NAME QUANTITY CARBON COMMENTS ON TYPE HEAT NUMBER CONTENT - / MATERIAL / PROCESS 1 UPPER RING 2 PIECES A248 TYPE 384 65444-1 .864 PLATE 65235-IA .842 2 UPPER CYLINDER 2 PIECES A248 TYPE 384 65235-18 ~ 842 3 CENTRAL RING 2 PIECES A248 TYPE 384 65294-1 .856 CENTRAL UPPER 2 PIECES A248 TYPE 384 65235-1 .842 CYLINDER 65291-lA .852 CENTRAL MID 848784-2 .853 2 PIECES A248 TYPE 384 CYLINDER 65298-1 .847 65295-1 .862 65298-lA '847 CENTRAL LOWER 848784-28 .853 2 PIECES A248 TYPE 384 CYLINDER 848784-2A ~ 853 65291-1 ~ 852 7 LOWER RING 2 PIECES A248 TYPE 384 65444-1 .864 65291-1 ~ 852 B LOWER CYLINDER 2 PIECES A248 TYPE 384 848784-2A .853 848784-2B .853 65298-1A ,847 SHROUD 1 PIECE ASME SA-336 FS G-23/245352 NOT KNOWN FORGING SUPPORT RING NINE MILE POINT UNIT I SHROUD DATA NOTES: I. HEAT NUMBER DATA SHOWN MAY BE APPLICABLE FOR NINE MILE POINT I ANO/OR OYSTER CREEK.
4
~ ~
Table 2-2 Nine Mile Point j. Water Chemistry History
.,'::::.".:: Cycle.'::::'.:,'.'.:,,'- ;::.:::::,-': Mea'ri";:".;,.Va'3 u~(j:,'::::.j ,'::,'Ch:1'o'r'i'de',(
',;:-',;:.Co'n due't':i;:v'i.'t'y'.,':.';:.'k 0.432 30 0.525 46 0.591 58 0.445 44 0.291 33 0.225 27 0.181 26 0.133 25 0.087 18 10 0.082 0.084 Table 2-3 Shroud Weld Estimated Fluence Estimated Fluences (n/cm',E)lMev)
H1 8.7E+09 4E+18 H2 4.6E+10 2E+19 H3 4.0E+11 2E+20 H4 7.8E+11 3.5E+20 H5 8.1E+11 3.6E+20 H6A 6.2E+07 3E+16 H6B 2.0E+07 9E+15 H7 <<1.0E+07 <<4E+15 Base on progecte EFPD at EOC Cyc e 11 (EOC Cycle 11 February 1995)
P
~ ~
Table 2-4 Shroud Visual Inspections i': """::::We'1d:..",,:.':,.;;: ~:'":-',.:::XD/QD~!::;;$N):;Neigh'tilrigj: ',ic3,"e'a'n'ed~':."!
.,",:,:,:,::Numb.er;:.:,,,-'- :<:,::.::.Exam!; d::;:,:,':;;-:; .'::;:!:Etiam.,l'::,d:,',,:',,":iExa'mi neddy>> ~",'~:Exa'm':,',:.'d'~g,~ jP'i'o'vi;d'ed) .:Yesj<N07p,~,i"..
Hl 1989 63" 11% OD As No needed H2 1989 63 II 11% OD As No needed H3 1989 29" OD As No Needed H4 1989 85" 15% OD As No Needed H7 1986 568" 100% OD ASME XI No 1988 SIL 572 1993 H8 1986 568" 100% OD ASME XI No 1988 SIL 572 1993 10
I Figure 2-1 Reactor Water Conductivity Mean Values 10.00 ~
1.00 ~
IJ 0.10 ~
1 Max Weeldy Mean Va~ycW Q hyde Mean VUws wch S Id. Oaf.
1I Aytl lace 0.01 I 8
Fuel Cycle 11
3.0 Structural Margin Assessment The generic assessment'iscussed the structural margins inherent in the shroud design and noted that 304 SS is a ductile material with high toughness properties even after accounting foz the effects of neutron fluence, and that only a minimal remaining ligament (5%-10% of wall) is required to maintain structural margins under post accident loads when 360 degree cracking is present. The generic assessment applies an assumption that cracking is initiated after one fuel cycle and that crack growth can be estimated analytically using the PLEDGE Model. Inspection of the Nine Mile Point 1 hot operating time and mean cycle conductivity demonstrates that Nine Mile Point 1 is bounded by the generic assessment conclusion that finding a 360 degree through-wall crack with an average depth in excess of 90% during the Fall 1994 inspections is unlikely. However, because of the uncertainties associated with residual stress profiles and oxide wedging phenomenon, the generic assessment could not rule out cracking in excess of 90%.
The uncertainty associated with the residual stzesses is applicable to the Hl through H7 welds. The cracking uncertainty associated with HS weld is addressed separately in Appendix A.
The next Nine Mile Point 1 refueling outage is currently scheduled for February 1995. A detailed inspection consistent with the BWRVIP inspection guidelines currently under development is scheduled and/or a pre-emptive repair would be implemented for all shroud horizontal welds. Considering the uncertainty in the extent of through-wall cracking prediction, the 1994 Fall outage inspection results of Oyster Creek (scheduled to commence at the end of September) will be used to determine the uncertainty associated with the potential for up to 360 degree cracking in excess of 90%. The Oyster Creek fall inspection is considered to be directly applicable to the structural margin assessment for Nine Mile Point 1 because the shroud fabrication is similar (see Section 2.3.1), and therefore, the uncertainty associated with residual stress profiles will be reduced. In addition, the Nine Mile Point 1 first 5 cycle mean conductivity is bounded by the Oyster Creek initial 5 cycle average, and the hot operating time is similar in magnitude. Therefore, the Oyster Creek inspection results are expected to allow Niagara Mohawk to assess the uncertainty associated with the structural margin integrity for the H1 through H7 welds.
12
I 4.0 Shroud Displacement Likelihood As discussed in the generic assessment', several conditions must exist simultaneously in order for shroud displacement to occur. First, a 360 degree, ) 90% deep crack must exist in the shroud. Then, a design basis guillotine main steam line break inside the flow limiters or a DEGB recirculation line break, or a design basis seismic event must occur to generate the loads assumed on the shroud. Note that opezational transients, small and intermediate break LOCA, main steam line bzeaks outside the flow limiter and safe shutdown earthquake all have significantly reduced loads and minimal potential shroud displacement. In this section the Nine Mile Point 1 specific overall likelihood of the limiting design basis scenario is discussed using plant specific probabilities from the Individual Plant Examination (IPE).
4.1 Cracking Likelihood Consistent with the genezic assessment', it is considered unlikely that Nine Mile Point 1 has 360 degree cracking in excess of 90% depth. This is supported by, the generic analysis and prior visual inspections. The uncertainty associated with this prediction is to be further clarified by review of the Fall Oyster Creek inspection (zesults expected in October 1994) . In addition, 360 degree cracking in excess of 90% depth is not credible at the H8 inconel 182 weld between the shroud support ring and inconnel shroud support cone (see appendix A). Note that H8 is a limiting location in the generic assessment regarding the consequences of failure during a DEGB recirculation line LOCA.
4 ' LOCA Likelihood A Nine Mile Point 1 specific probabilistic safety assessment (PSA) based on the Nine Mile Point 1 IPE was performed to evaluate the safety significance of continued operation prior to determining the status of'elds related to the reactor shroud. The PSA evaluated the probability of accident scenarios resulting from potential failures of shroud welds. The events of primary concern are double ended guillotine breaks (DEGB) in main steam lines, DEGB in reactor recirculation lines, and earthquakes. Based on the probability of these events and the estimated conditional failure probability of the shroud welds, the estimated overall incremental core damage and large/early release frequency is less than 8.3E-8 per year. The detailed discussion of the PSA is included in Appendix B.
4.3 Inspection Timing Consistent with the recommendations of the generic assessment', Nine Mile Point 1 plans to review the results of the Oyster Creek Fall inspection and other Fall inspections to assess the uncertainty associated with the evaluation that cracking is unlikely to be greater than 360 degrees and gzeatez than 90% deep.
13
~ ~
5.0 Integrated 'Shroud Assessment The Nine Mile Point 1 susceptibility assessment has concluded that the likelihood of up to 360 degree cracking at some depth is fairly high at the H1 through H7 weld location. Cracking to any significant depth at the HS weld location is considered extremely unlikely. The structural margin assessment established that cracking at the H1 through H7 locations in excess of 90% depth is unlikely. The uncertainty in the cracking prediction will be re-assessed based upon the results of the Oyster Creek Fall (October 1994) inspection.
The overall likelihood of the event scenario described, a LOCA or seismic event with a 360 degree, > 90% deep crack, is extremely unlikely. The assessment of the core damage frequency assuming shroud weld failure combined with the design basis seismic or recirculation line LOCA or MSLB LOCA is extremely low considering operation until February 1995, (4 E-8 per 6 months). This overall risk supports continued operation of Nine Mile Point 1 until the scheduled February 1995 refuel outage.
The consequences of 360 degree through-wall cracks applicable to Nine Mile Point 1 were reviewed as part of the generic assessment'. This assessment reviewed the shroud response to the stzuctural loadings resulting from design basis events including, steam line break, recirculation line break and asymmetric loads associated with the recirculation line break. This assessment included a review of the ability of plant safety features to perform their functions considering the design basis accident loads with 360 degree through-wall cracking (e.g. control rod insertion, ECCS injection). Through the BNRVIP assessment subcommittee, analyses are under development which will provide more detailed shroud loads considezing both the main steam line break LOCA and recirculation line LOCA. These analyses are intended to better define the asymmetric loads associated with the recirculation suction line LOCA and the amount of shroud lift following the main steam line break LOCA. These analyses are estimated to be completed in the October 1994 time frame. In the interim, additional information is available to supplement the generic assessment discussion of the recirculation line break and steam line break.
Main Steam Line Break Accident:
GPU Nuclear has completed preliminary assessments4 using a RELAP 5 Oyster Creek model which confirms that the maximum potential lift is limited such that the top guide does not clear the fuel channels(e.g. less than 14 inches of lift) and control rod insertion is not expected to be impacted. Core spray lines are expected to be damaged by the possible displacement, however, the break is above TAF so ECCS injection inside the reactor vessel, at or above the core steaming rate, will assure short and long term cooling.
Recirculation Line Break Accident:
The generic assessment considered the shroud loads associated with the recirculation discharge line break as limiting and that 14
~ c no vertical displacement is expected at any but the vertically unsupported H8 weld. The consequence of this failure was vertical displacement (downward) which would damage the core spray lines and result in impaired core spray cooling. However, additional study of the H8 weld configuration (see Appendix A) has determined that failure of the H8 weld in such a manner which would allow vertical downward displacement is not a credible failure. With the H8 weld integrity assured, the core spray system would perform its design basis function and control rod insertion is assured.
As discussed in the generic assessment, the lateral force on the shroud due to the blowdown asymmetric load is bounded by the restoring moment of the shroud weight and therefore, the recirculation line break analysis results are unchanged. As indicated above, additional analyses are in progress to address this issue generically through the BWRVIP assessment subcommittee.
Nine Mile Point 1 has also reviewed the guidance provided in the generic assessment regarding through-wall crack indication during normal operation. This generic information has been provided to operations and has been incorporated into the normal operating procedure for the Nuclear Steam Supply System (N1-OP-1). The procedure has been revised to alert operators of the expected plant response should a through-wall shroud crack develop. This training was provided to all operations crews prior to their resumption of shift duties.
6.0 Conclusions The Nine Mile Point 1 shroud cracking safety assessment indicates that 360 degree, greater than 90% through-wall cracking is unlikely to occur during operation up to the scheduled February 1995 refuel outage. The uncertainty in this determination will be assessed based upon the results of the scheduled Fall 1994 Oyster Creek shroud inspection. Based on this conservative approach, the probability that the Nine Mile Point 1 coze shroud does not satisfy the design basis structural integrity margins is considered extremely low. Even extreme condition of 360 degree, greater than 90% through-wall if the cracking coupled with a design basis accident is assumed, the safety assessment shows that control zod insertion is not expected to be impacted and the core spray system would provide adequate core cooling. This low probability, combined with the extremely low overall
'zisk estimate, supports continued operation until the scheduled February 1995 refueling outage.
15
S J
'
7.0 References GENE-523-A107P-0794, Revision 1 "BWR Shroud Cracking Generic Safety Assessment", August 1994
- 2) SIL 0572 R1, "Core Shroud Cracks" 4
- 3) GE-NE-523-148-1193, "BWR Core Shroud Evaluation", April 1994
- 4) GPUN Calc ¹C1302-222-5450-W06, Rev 0, "Oyster Creek Shroud Dispacement Calculation"
- 5) NMPC Calc ¹ SO-VESSEL-M025, rev 0, "Residual stress and remaining ligament calcualtion for the shroud ring H8 weld", Contains MPR calculation 085-252-01 referenced in Appendix A.
- 6) NMPC Technical Report SAS-94-005 "Probabilistic Risk Assessment of Potential Integranular Stress Corrosion Cracking of NMP1 Core Shroud", August 5, 1994 16
J APPENDIX A Analysis of Nine Mi3.e Point 1 Weld HS Shroud Support Ring to Inconel Shroud Support cone 17
I
)
%1MPR ASSOCIATES INC, E N VINE EBS August 16, 1994 ANALYSIS OF NINE MILE POINT UNIT 1 SHROUD SUPPORT RING TO INCONEL SUPPORT CONE WELD H-8 Weld H-8 attaches the Type 304 forged stainless steel shroud support ring to the Alloy 600 support cone as shown in Figure 1. The shroud support assembly, including the vessel shell, the cone and the ring, but not the shroud itself, was post weld heat treated (PWHT) at 1150'F during vessel fabrication, As a consequence, weld H-8 was stress relieved during PWHT, and peak tensile residual stresses were reduced by the heat treatment. In addition, the PWHT sensitized the stainless steel ring which increases concern for IGSCC on the ring side of weld H-8. While the weld metal and cone were also sensitized, these are Inconel materials which are more resistant to IGSCC than the stainless material, especially in the absence of crevices. Normal operating stresses in the support ring are expected to be compressive due to the difference in thermal expansion coefficients of the ring and the cone/vessel.
A finite element stress analysis was performed on the shroud support assembly to quantify normal operating stress levels and to determine the stress state during PWHT (MPR Calculation 085-252-01). From the latter analysis, the stress relief effects for presumed weld residual stresses can be estimated. The residual stresses that remain, when combined with operating stresses, determine the overall stress state of weld H-8 during normal operation.
The analysis confirmed that the hoop, radial and axial principal stress components are all generally compressive in the support ring during normal operation. The principal stress of concern is the radial one, since this stress component could lead to stress corrosion cracking whose orientation would cause weld H-8 to lose its vertical load-carrying capability.
Stress contour plots for the radial stress component during the original stress relief and under normal operating conditions are shown in Figures 2 and 3. The principal load during stress relief is the thermal load, during which time the shroud is not attached.
During normal operation, the loads include thermal, pressure, deadweight and hydraulic uplift forces.
Inspection of Figure 3 reveals that the highest tensile radial stresses exist at the top of weld H-8 in the ring. This is considered to be the limiting location for possible crack initiation. It is presumed that local tensile weld residual stresses existed at this location after welding, and they were at the yield stress level. During stress relief (see Figure 2),
18
L I
induced tensile thermal stresses, combined with the reduced yield strength at the 1150'p temperature, reduced the weld residual stresses to a low value, about 7 ksi. During normal operation, these stresses add to the normal operating stresses for a total stress of about 13 ksi at the top of weld H-8 in the ring.
While it is unlikely that cracking would initiate in a 13 ksi stress field, we note that the location of highest tensile stress is an area that'is inspectable. Further, cracking in the heat affected zone of the support ring adjacent to weld H-8 would grow very slowly, if at all, because: (1) it would have to grow into an area of applied compressive stresses, and (2) weld residual stresses are also expected to become compressive in the ring at the center of weld H-8.
Finally, the limiting load for weld H-8 is the recirculation pipe break download of 2 million lbs. It is estimated that a ligament of only 1/4 inch is required in weld H-8 tosupport this load. Therefore, cracking in weld H-8 would have to be quite extensive, about ninety percent throughwall for 360 degrees, in order for the weld to fail under limiting accident conditions.
We conclude that, because of reduced weld tensile residual stresses in weld H-8, and the fact that only about 1/4 inch of weld is required to support the limiting download transient, weld H-8 is extremely unlikely to be in a condition that could fail.
19
C I
Shroud Axial (Y) (Type 304 Stainless Steel)
Radial (X)
Weld H-8 (Inconel 182)
Shroud Support Ring (Type 304 Stainless Steel)
Support Cone (Inconel 600)
Vessel Wall (Low Alloy Steel)
FAIMpQ Figure 1. Shroud Support Components and Weld H-8 F C65 252-OI C6/16/94 (I Jl) 20
I ANSYS 5.0 A AUG 9 1994 11:18:24 PLOT NO. 1 NODAL SOLUTION STEP=1 SUB =1 TIME=1 SX (AVG)
RSYS=O DMX =1.074 SMN =-12442 SMNB=-47643 SMX =10539 qir ~i I
SMXB=49670
-12442
-9889
-7335
-4782
-2228 325.242 2879 5432 7986 10539 ~
NINE MILE POINT UNIT 1 CORE SHROUD THERMAL ANALYSIS Figure 2. Radial Stress During PWHT
ANSYS 5.0 A AUG 9 1994 11:24:12 PLOT NO. 1 NODAL SOLUTION STEP=1 SUB =1 TIME=1 SX (AVG)
RSYS=O DMX =0.440901 SMN =-12070 SMNB=-23687 SMX =6508 SMXB=26637 h
-12070
~E
-10006
~
t J
-7941
-5877
-3813
-1749 315.396 2380 4444 6508 r
JC r
NINE MILE POINT UNIT 1 CORE SHROUD THERMAL ANALYSIS Figure 3. Radial Stress During Normal Operation
APPENDIX B Analysis and Results from NMPC Technical Report SAS-94-005 "Probabilistic Risk Assessment of Potential Integranular Stress Corrosion Cracking of NMP1 Core Shroud", August 5, 1994 23
r The cracking of vessel shroud welds can lead to failure of vessel internals support. Should vessel support fail, core integrity may be compromised and, of chief importance, insertion of control rods may not be possible if fuel bundles are no longer parallel to control rod movement. In addition, for NMP1, shroud movement may result in failure of core spray spazgers during some events. Based on the engineering review and the information in References 1, 2, and 3, it is apparent that the principal scenarios of concern are main steam line breaks (MSLB), reactor recirculation line breaks (RRLB), and seismic events. Each of these events has the potential to induce loadings that could fail cracked welds and cause core movement. As such, this report calculates the probability of each of the events.
These probability values should be useful in assessing the safety significance of the issue at NMP1.
The NMP1 IPE is a detailed evaluation of the probability and consequences of plant risk. Because it was completed prior to the elevated concern regarding shroud IGSCC, it does not explicitly include recent insights associated with this issue. In that regard, the probability of shroud IGSCC events can be calculated, similar to the events developed in the IPE, and presented as an incremental risk above-and-beyond that calculated in the IPE.
The best way to develop and describe the risk associated with the postulated IGSCC events is to treat each possible scenario separately and then sum the probability of each scenario to develop the total IGSCC event frequency. Therefore, the following section individually treats the MSLB, RRLB, and seismic events.
Main Steam Line Break (MSLB) Shroud IGSCC Risk The MSLB event is defined by the rapid initiation of a crack which results in a double ended guillotine break 360'ircumferential (DEGB) of piping and an immediate loss of coolant (LOCA) event. As
'such, makeup flow, from primarily the core spray system and feedwater, is required. This specific event was modeled in the NMP1 IPE as one of several contributors to the large LOCA (LLOCA) class of initiators.
Other contributors to the large LOCA event frequency include: core spray system leakage/ruptures, multiple instrument penetration failures, SLC system piping leakage/rupture, and feedwater piping leakage/rupture. As discussed above, non-DEGB events pose little threat relative to the shroud issue and are not included in this risk assessment. Large LOCA events, including DEGB, were not a significant contributor to IPE calculated accident frequency.
The postulated MSLB initiating event frequency represents a certain fraction of the IPE LLOCA initiating event frequency since MSLB is one of several events that aze considered to cause a LLOCA. However, the NMP1 IPE does not differentiate between specific LLOCA events because, foz the purposes of severe accident modeling, the plant response is similar between individual events that fit the IPE LLOCA definition.
As the NMP1 IPE LLOCA frequency is quantified as 7E-4 per year, for this analysis, the MSLB frequency can be reasonably considered less 24
than 7E-4 per year.
The BWROG'as performed research that is useful in characterizing the extent to which MSLB frequency is less than NMP1 LLOCA calculated frequency. The BWROG estimates that recirculation system piping, and it is inferred other large piping, has a rupture frequency of "several orders of magnitude lower than" 7.51E-6 per year.
It should the be pointed out that there possibility of an instantaneous is considerable uncertainty DEGB of pipes in a nuclear as to application. A widely considered theory suggests that the pipe would leak foz some time before catastrophic rupture. As such, the leak would alert operators who would shut-down the plant before the DEGB occurred.,In any event, no credit is taken for the leak-before-break argument and the BWROG value is assumed representative of the MSLB frequency under the DEGB failure mode.
Following a MSLB event, the integrity of the shroud welds will be challenged. IPEs have typically assumed that this passive failure mode is of low probability. However, due to the IGSCC issue, this assumption, at least temporarily, should be questioned. Per Pinelli',
the possibility that weld failures will occur is "unlikely" even considering IGSCC. For this analysis, "unlikely" is reasonably translated to mean less than 1E-2 pez event. As such, the probability of a MSLB and resultant shroud failure is estimated as less than 7.51E-8 per year.
According to the current IPE model, this event would be considered a core damage and large-early release event since any large LOCA with a failure to SCRAM was connected to core damage and large/early release endstates. When added to a core damage frequency (CDF) of 5.5E-6 per year and a large/Early release frequency (LERF) of 6.9E-7 per year, the MSLB-'Shroud event probability, 7.51E-8 per year, is a relatively minor contributor.
In actuality, the impact is even less than the above calculation shows. The NMP1 IPE model does not link LLOCA events with a failure to SCRAM to the ATWS model but rather to a Class IV failure endstate.
The IPE conservatively assumes that such scenarios result in core damage. This is done because the low probability of the sequences does not justify the level of effort required to incorporate the necessary modeling details.
In reality, even if control rods are not inserted, the reactor could possibly be shut down using SLC injection. This is especially appropriate to consider since, at a minimum, some rods may be at least partially inserted even with the fuel rods in disarray. From the IPE, SLC failure probability, including the associated operator actions to initiate SLC and prevent dilution (Top events SL, EP, and CH), is 1.6E-3 per event. Multiplying this by the above 7.51E-8 per year yields an event probability of 1.2E-10 per year. As such, if could be credited then the risk impact would be far less. Note that SLC this does not include any consideration of SLC equipment or operator failures that could relate to a relocated shroud. In any event, the above shows the nature of safety provided by the SLC system during the postulated MSLB/shroud event.
25
C I
~ ~
In addition, even if covered and establish SLC failed, heat removal it is possible to keep the core equal to or greater than that generated by the reactor. This could be accomplished by some combination of containment spray or containment vent operation in concert with some combination of successful injection. These actions would be directed via the current symptom based emergency operating procedures (EOP). It is not suggested that the success probability would be large, but rather, in the above calculations.
it is pointed out to show the conservatism Reactor Recirculation Line Break (RRLB) Shroud IGSCC Risk The RRLB event initiates when a 360'ircumferential crack develops in a reactor recirculation line and very quickly ruptures. As with the MSLB, this event results in an immediate loss of coolant (LOCA) event.
The IPE treatment relative to large LOCA is the same as that discussed above. As such, all related discussion for MSLB is relevant here.
From above, a good estimate, for the purposes of this study is the BWROG 7.51E-6 per year value. Should a RRLB event occur, makeup is immediately required. However, since the break could be below the core, core spray is required because spray cooling is necessary to protect the core until containment flooding is completed. For NMP1, the core spray spargers are attached to the shroud. As such, following a RRLB, should the HS shroud core support weld fail, the entire shroud could drop. This would result in failure of the core function; although core spray flow will still reach the vessel. 'pray Due to the nature of the HS shroud weld, engineering review has determined that it is very reliable; even considering the IGSCC issue This review has classified the H8 weld failure as an extremely unlikely event. As such, a value of 1E-3 per event failure frequency has been conservatively assigned as the failure probability of the HS shroud weld following a RRLB event. Multiplying 1E-3 per event by the above 7.51E-6 per year yields a RRLB/Shroud/Coze spray failure event of 7.51E-9 per year.
In addition, the above is potentially conservative because although the coze spray function is failed, its inventory, as injection rather than spray, can reach the vessel. Combined with feedwater, CRD, and SLC, the total inventory might be enough to prevent fuel damage prior to completion of containment flooding. This success path is not credited in this, or most likely any other analysis, but mentioned here as a possible success path that could be developed it is further.
Seismic Event Shroud IGSCC Risk Per NRC', the safe shutdown earthquake (SSE) is expected to produce minimal movement of equipment related to the above issue. As such, would require MSLB or RRLB events coincident with the SSE to cause it potential accidents. Due to the low likelihood of each individual event, the coincident occurrence of the SSE and a large break is 26
~ r
~
~ g
considered very small. Even if the SSE and large break could cause a problem (assume they occurred on the same day rather than in the same minute or hour), a CDF estimate of less than 1E-10 per year would result.
Additionally, a beyond SSE earthquake could also occur such that the earthquake itself causes failure of a large line (MSLB or RRLB) and the shroud. Events of this magnitude are of very low probability (i.e. (1E-7 per year). Also, earthquakes of this magnitude would likely fail a significant portion of other plant equipment such that conditional failure probability of the plant as a whole would be large regardless of the status of the shroud welds. As such, the incremental risk caused by potentially cracked shroud welds is judged insignificant.
Summing the above conservatively calculated scenario frequencies results in a total incremental CDF and LERF frequency of 8.27E-8 per year. Considering that only six months remain until the next refueling outage the incremental risk is half that above, or 4.14E-8 per 6 months. Also, it has been demonstrated that the above calculation is conservative. Conservative or not, the above incremental risk is very small.
REFERENCES (1) Zimmerman, R. P. "Intergranular Stress" Corrosion Cracking of Core Shrouds in Boiling Water Reactors, Generic Letter 94-03, USNRC, July 25, 1994.
(2) Stang, J.F..(USNRC) Letter to Farrar, D.L. (ComEd), "Resolution of Core Shroud Cracking at Dresden, Unit 3 and Quad Cities, Unit 1, "
7/21/94.
(3) Pinelli, R.A. Letter to BWR Owner's Group Executives, "BWROG Response to NRC Request for Shroud Information, " GE-NE-523-AI07P-0794, July 13, 1994. (GE Proprietary.)
(4) Nine Mile Point Unit One Final Safety Analysis Report (Updated).
(5) Kirchner, R. F., et. al., "Nine Mile Point Nuclear Station Unit 1 Individual Plant Examination (IPE)" Niagara Mohawk Power Corporation, SAS-TR-93-001, July 1993.
(6) England, L.A.- Letter to USNRC (Serkiz, A.W.), "Response to NRC Request for Information on Pipe Break Frequencies, " BWR Owner's Group, BWROG-93149, December 8, 1993.
27
I ~ ~
~ ~
$ II,
~ eg ATTACHMENT 8 NINE MILE POINT UNIT 1 DOCKET NO. 50-220 LICENSE NO. DPR-63 GENERIC LETTER 94-03 HI T RY F RE HR I PE TI
~ a~ i S>>,
~ ' ~
Niagara Mohawk has not performed any shroud inspections which meet all of the General Electric (GE) SIL 572, Revision 1 recommendations for lighting level, camera resolution and weld pre-cleaning. However, visual (camera) inspections of vessel internal components, which directly or indirectly included film footage of the shroud plates and weldments, have previously been performed. These inspection tapes have been reviewed jointly by a Niagara Mohawk Level III qualified examiner and a General Electric Level III qualified examiner, who participated in the examination activities at both Quad Cities and Dresden and who is qualified to the enhanced level proposed by the new standards. The results of Niagara Mohawk's review of past invessel visual inspection tapes is provided below and summarized in the accompanying table.
Core shroud welds Hl, H2, H3 and H4 were filmed during a 1989 access study conducted to verify clearances for the reactor pressure vessel beltline inspection tool. The lighting provided was to the level needed for verification of access, and though not specifically deployed to illuminate the welds, the welds are clearly visible. The camera resolution level was as needed to gauge accessibility. No prior cleaning of the welds was performed. The review of these tapes by the Level III qualified examiners concluded that there was no evidence of gross cracking at the locations inspected.
Invessel inspections of the shroud supporting ring to the shroud support skirt (ISI component RV15I) were conducted in 1986, 1988 and 1993 in accordance with ASME Section XI. The areas inspected encompass core shroud welds H7 and H8. The lighting level and camera resolution required by ASME Section XI meet the requirements of GE SIL 572, Revision 1.
No prior cleaning of the welds was performed. The inspections of ISI component RV15I in 1986, 1988 and 1993 did not reveal any reportable indications.
NMP1 RE HR UD VI AL CAMERA EXAMINATION
,':;.',:-Numb'e'r',:::,:-:',::::!:.':;Exam! d'::,:::,:;:,:;:;;::;:,:::;::-':::Exnm':,d;'.!:.'",)',:;::ilExIuiiIiiedjji H1 1989 63 II 11% OD No H2 1989 63" 11% OD As needed No II H3 1989 29 5% OD As needed No H4 1989 85" 15% OD As needed No H7 1986 568" OD ASME XI/ No 1988 SIL 572 1993 H8 1986 568" 100% OD ASME XI/ No 1988 SIL 572 1993
C
~ g> I
ATTACHMENT C NINE MILE POINT UNIT 1 DOCKET NO. 50-220 LICENSE NO. DPR-63 GENERIC LETTER 94-03 DRA I F RE HR FI ATI
a' Viiiag W%
g~g KlCRR arne ANCE CXZRlCSma~
D 55~ ~%KM ggg ~
gggggggg~ M F/gi I 4i Q~
. FÃXWzr 0
/gal~~~
CZRRamCza
~
/per Fizz///i~
F/YFY//zi
'"NFYr, r r<
8S ll I ll So mmll r<
j .<<~ mx<32%R~g N
~5~d>Il
'C k
~ I
%WRY
~1 J
a'1 I
P p
~ ~ ~ b
~ ~
~ ~
%g) ~ ~
I ~ ~ ~
~ ~
~ ~
~'
I v
4 l
t
%KNEE%
NISI'~~~
RHKRKR%
0 0
H~ ~ES~REHiR-RRRIRKRR 8 RSCSa~5 ggaggKIMIS~
RSRRCS RRRSFISRKQ
~ 52RRil ECRIRRERSHW RRW W=== '
0 kg~
8 Fz~ b'ijÃ&ri rsPy.
0 I i'ik . +
C
~ + f ~
1 1 i~/r//>.
L el/~~
rvigil II
. A g~r II r+/ mmmll
'.
BFIH~ SREKM6 mam 8
I L
'I
,4 ry o
T r l