| title = Crystal River, Inspection/Activity Plan, 03/01/2011 - 06/30/2012, Report 22
| title = Inspection/Activity Plan, 03/01/2011 - 06/30/2012, Report 22
| author name =  
| author name =  
| author affiliation = NRC/RGN-II
| author affiliation = NRC/RGN-II
Line 14: Line 14:
| page count = 2
| page count = 2
}}
}}
=Text=
{{#Wiki_filter:Page 1 of 2                                                                            Crystal River 03/04/2011    07:04:23                                                        Inspection / Activity Plan Report 22                                                                        03/01/2011 - 06/30/2012 Unit          Planned Dates                                                                                                    No. of Staff Number        Start      End      Inspection Activity                                                              Title          on Site SGRP          - SGRP ACTIVITIES                                                                        2 3      03/01/2011  04/01/2011  IP 50001                Steam Generator Replacement Inspection TFPI          - 805 TFPI                                                                              6 3      04/04/2011  04/08/2011  IP 7111105P            Fire Protection-NFPA 805 Transition Period [Triennial]
3      04/18/2011  04/22/2011  IP 7111105P            Fire Protection-NFPA 805 Transition Period [Triennial]
PSB1-RP      - RAD ENVIRONMENTAL MONITORING PROGRAM                                                  1 3      06/13/2011  06/17/2011  IP 71124.06            Radioactive Gaseous and Liquid Effluent Treatment EB3-HS        - HEAT SINK                                                                              1 3      06/20/2011  06/24/2011  IP 7111107T            Heat Sink Performance OL EXAM      - INIITIAL EXAM PREP                                                                    5 3      08/22/2011  08/26/2011      V23355              CRYSTAL RIVER/SEPTEMBER 2011 EXAM AT POWER FACILITIES OL EXAM      - INIITIAL EXAM - WEEK 1                                                                5 3      09/12/2011  09/16/2011      V23355              CRYSTAL RIVER/SEPTEMBER 2011 EXAM AT POWER FACILITIES PSB1EP        - EMERGENCY PREPAREDNESS INSPECTION                                                      1 3      09/12/2011  09/16/2011  IP 7111402              Alert and Notification System Testing 3      09/12/2011  09/16/2011  IP 7111403              Emergency Preparedness Organization Staffing and Augmentation System 3      09/12/2011  09/16/2011  IP 7111404              Emergency Action Level and Emergency Plan Changes 3      09/12/2011  09/16/2011  IP 7111405              Correction of Emergency Preparedness Weaknesses and Deficiencies 3      09/12/2011  09/16/2011  IP 71151                Performance Indicator Verification OL EXAM      - INITIAL EXAM - WEEK 2                                                                  4 3      09/19/2011  09/23/2011      V23355              CRYSTAL RIVER/SEPTEMBER 2011 EXAM AT POWER FACILITIES PSB1-RP      - RP OCCUPATIONAL WEEK 1                                                                4 3      10/31/2011  11/04/2011  IP 71124.01            Radiological Hazard Assessment and Exposure Controls 3      10/31/2011  11/04/2011  IP 71124.02            Occupational ALARA Planning and Controls 3      10/31/2011  11/04/2011  IP 71124.03            In-Plant Airborne Radioactivity Control and Mitigation 3      10/31/2011  11/04/2011  IP 71124.04            Occupational Dose Assessment 3      10/31/2011  11/04/2011  IP 71124.05            Radiation Monitoring Instrumentation 3      10/31/2011  11/04/2011  IP 71151                Performance Indicator Verification PSB1-RP      - RP OCCUPATIONAL WEEK 2                                                                4 3      11/14/2011  11/18/2011  IP 71124.01            Radiological Hazard Assessment and Exposure Controls 3      11/14/2011  11/18/2011  IP 71124.02            Occupational ALARA Planning and Controls 3      11/14/2011  11/18/2011  IP 71124.03            In-Plant Airborne Radioactivity Control and Mitigation 3      11/14/2011  11/18/2011  IP 71124.04            Occupational Dose Assessment 3      11/14/2011  11/18/2011  IP 71124.05            Radiation Monitoring Instrumentation 3      11/14/2011  11/18/2011  IP 71151                Performance Indicator Verification This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2                                                                            Crystal River 03/04/2011    07:04:23                                                        Inspection / Activity Plan Report 22 03/01/2011 - 06/30/2012 Unit          Planned Dates                                                                                                                No. of Staff Number        Start      End      Inspection Activity                                                          Title                        on Site PI&R          - PROBLEM IDENTIFICATION AND RESOLUTION                                                            5 3      01/17/2012  01/20/2012  IP 71152B              Identification and Resolution of Problems 3      01/30/2012  02/03/2012  IP 71152B              Identification and Resolution of Problems MOD          - MODIFICATION INSPECTION                                                                          3 3      04/16/2012  04/20/2012  IP 7111117T            Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 3      04/30/2012  05/04/2012  IP 7111117T            Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications ISFSI        - ISFSI PAD CONCRETE POUR                                                                          2 3      06/18/2012  06/22/2012  IP 60853                On-Site Fabrication Of Components And Construction On An ISFSI PSB1EP        - EMERGENCY PREPAREDNESS EXERCISE                                                                  3 3      06/25/2012  06/29/2012  IP 7111401              Exercise Evaluation 3      06/25/2012  06/29/2012  IP 7111404              Emergency Action Level and Emergency Plan Changes 3      06/25/2012  06/29/2012  IP 71151                Performance Indicator Verification This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.}}

Latest revision as of 03:26, 13 November 2019

Inspection/Activity Plan, 03/01/2011 - 06/30/2012, Report 22
ML110630249
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/04/2011
From:
NRC/RGN-II
To:
Shared Package
ML110630236 List:
References
Download: ML110630249 (2)


Text

Page 1 of 2 Crystal River 03/04/2011 07:04:23 Inspection / Activity Plan Report 22 03/01/2011 - 06/30/2012 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site SGRP - SGRP ACTIVITIES 2 3 03/01/2011 04/01/2011 IP 50001 Steam Generator Replacement Inspection TFPI - 805 TFPI 6 3 04/04/2011 04/08/2011 IP 7111105P Fire Protection-NFPA 805 Transition Period [Triennial]

3 04/18/2011 04/22/2011 IP 7111105P Fire Protection-NFPA 805 Transition Period [Triennial]

PSB1-RP - RAD ENVIRONMENTAL MONITORING PROGRAM 1 3 06/13/2011 06/17/2011 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment EB3-HS - HEAT SINK 1 3 06/20/2011 06/24/2011 IP 7111107T Heat Sink Performance OL EXAM - INIITIAL EXAM PREP 5 3 08/22/2011 08/26/2011 V23355 CRYSTAL RIVER/SEPTEMBER 2011 EXAM AT POWER FACILITIES OL EXAM - INIITIAL EXAM - WEEK 1 5 3 09/12/2011 09/16/2011 V23355 CRYSTAL RIVER/SEPTEMBER 2011 EXAM AT POWER FACILITIES PSB1EP - EMERGENCY PREPAREDNESS INSPECTION 1 3 09/12/2011 09/16/2011 IP 7111402 Alert and Notification System Testing 3 09/12/2011 09/16/2011 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 3 09/12/2011 09/16/2011 IP 7111404 Emergency Action Level and Emergency Plan Changes 3 09/12/2011 09/16/2011 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 3 09/12/2011 09/16/2011 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM - WEEK 2 4 3 09/19/2011 09/23/2011 V23355 CRYSTAL RIVER/SEPTEMBER 2011 EXAM AT POWER FACILITIES PSB1-RP - RP OCCUPATIONAL WEEK 1 4 3 10/31/2011 11/04/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 3 10/31/2011 11/04/2011 IP 71124.02 Occupational ALARA Planning and Controls 3 10/31/2011 11/04/2011 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 3 10/31/2011 11/04/2011 IP 71124.04 Occupational Dose Assessment 3 10/31/2011 11/04/2011 IP 71124.05 Radiation Monitoring Instrumentation 3 10/31/2011 11/04/2011 IP 71151 Performance Indicator Verification PSB1-RP - RP OCCUPATIONAL WEEK 2 4 3 11/14/2011 11/18/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 3 11/14/2011 11/18/2011 IP 71124.02 Occupational ALARA Planning and Controls 3 11/14/2011 11/18/2011 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 3 11/14/2011 11/18/2011 IP 71124.04 Occupational Dose Assessment 3 11/14/2011 11/18/2011 IP 71124.05 Radiation Monitoring Instrumentation 3 11/14/2011 11/18/2011 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 Crystal River 03/04/2011 07:04:23 Inspection / Activity Plan Report 22 03/01/2011 - 06/30/2012 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 5 3 01/17/2012 01/20/2012 IP 71152B Identification and Resolution of Problems 3 01/30/2012 02/03/2012 IP 71152B Identification and Resolution of Problems MOD - MODIFICATION INSPECTION 3 3 04/16/2012 04/20/2012 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 3 04/30/2012 05/04/2012 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications ISFSI - ISFSI PAD CONCRETE POUR 2 3 06/18/2012 06/22/2012 IP 60853 On-Site Fabrication Of Components And Construction On An ISFSI PSB1EP - EMERGENCY PREPAREDNESS EXERCISE 3 3 06/25/2012 06/29/2012 IP 7111401 Exercise Evaluation 3 06/25/2012 06/29/2012 IP 7111404 Emergency Action Level and Emergency Plan Changes 3 06/25/2012 06/29/2012 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.