Report 22, Inspection / Activity Plan 09/01/2008 - 12/31/2009
ML082460601
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 09/02/2008
From:
NRC/RGN-II/DRP/RPB3
To:
Shared Package
ML082460598 List:
References
Download: ML082460601 (2)


Text

Crystal River Inspection / Activity Plan 09/01/2008 - 12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 09/02/2008 12:08:50 Report 22 3

TI-171

- B.5.B PHASE 2&3 Generic Safety Inspectio Verification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies 10/06/2008 10/10/2008 3

2515/171 IP 1

PSB1-RP

- RADIATION PROTECTION PREINSPECTION VISIT Baseline Inspections Access Control to Radiologically Significant Areas 10/27/2008 10/29/2008 3

7112101 IP 4

PSB1-RP

- RADIATION PROTECTION PUBLIC BASELINE Baseline Inspections Access Control to Radiologically Significant Areas 12/01/2008 12/05/2008 3

7112101 IP Baseline Inspections Radiation Monitoring Instrumentation and Protective Equipment 12/01/2008 12/05/2008 3

7112103 IP Baseline Inspections Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 12/01/2008 12/05/2008 3

7112201 IP Baseline Inspections Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 12/01/2008 12/05/2008 3

7112203 IP Baseline Inspections Occupational Exposure Control Effectiveness 12/01/2008 12/05/2008 3

71151-OR01 IP Baseline Inspections RETS/ODCM Radiological Effluent 12/01/2008 12/05/2008 3

71151-PR01 IP 2

EB3TI172

- TI-172 Generic Safety Inspectio Reactor Coolant System Dissimiliar Metal Butt Welds 12/08/2008 12/12/2008 3

2515/172 IP 4

EB1-MODS

- MODIFICATIONS-10CFR50.59 Baseline Inspections Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 02/23/2009 02/27/2009 3

7111117 IP Baseline Inspections Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 03/09/2009 03/13/2009 3

7111117 IP 1

PSB1EP

- EMERGENCY PREPAREDNESS INSPECTION Baseline Inspections Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 05/04/2009 05/08/2009 3

2515/175 IP EP Baseline Inspection Alert and Notification System Testing 05/04/2009 05/08/2009 3

7111402 IP EP Baseline Inspection Emergency Response Organization Augmentation Testing 05/04/2009 05/08/2009 3

7111403 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 05/04/2009 05/08/2009 3

7111404 IP EP Baseline Inspection Correction of Emergency Preparedness Weaknesses and Deficiencies 05/04/2009 05/08/2009 3

7111405 IP Baseline Inspections Drill/Exercise Performance 05/04/2009 05/08/2009 3

71151-EP01 IP Baseline Inspections ERO Drill Participation 05/04/2009 05/08/2009 3

71151-EP02 IP Baseline Inspections Alert & Notification System 05/04/2009 05/08/2009 3

71151-EP03 IP 5

LI

- LICENSE RENEWAL INSPECTION License Renewal Inspec License Renewal Inspection 07/27/2009 07/31/2009 3

71002 IP 3

OL EXAM

- INITIAL EXAM - PREP Not Applicable CRYSTAL RIVER/SEPTEMBER 2009 EXAM AT POWER FACILITIES 08/03/2009 08/07/2009 3

V23305 5

LI

- LICENSE RENEWAL INSPECTION License Renewal Inspec License Renewal Inspection 08/10/2009 08/14/2009 3

71002 IP 3

OL EXAM

- INITIAL EXAM - WEEK 1 Not Applicable CRYSTAL RIVER/SEPTEMBER 2009 EXAM AT POWER FACILITIES 08/31/2009 09/04/2009 3

V23305 1

PSB1-RP

- RP PREINSPECTION VISIT (OCCUPATIONAL)

Baseline Inspections Access Control to Radiologically Significant Areas 09/07/2009 09/10/2009 3

7112101 IP This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Crystal River Inspection / Activity Plan 09/01/2008 - 12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 09/02/2008 12:08:50 Report 22 2

OL EXAM

- INITIAL EXAM - WEEK 2 Not Applicable CRYSTAL RIVER/SEPTEMBER 2009 EXAM AT POWER FACILITIES 09/14/2009 09/18/2009 3

V23305 4

EB3SGR

- STEAM GENERATOR REPLACEMENT Other Routine Steam Generator Replacement Inspection 09/26/2009 11/26/2009 3

50001 IP 3

PSB1-RP

- RP OCCUPATIONAL BASELINE WEEK 1 (OUTAGE)

Baseline Inspections Access Control to Radiologically Significant Areas 09/28/2009 10/02/2009 3

7112101 IP Baseline Inspections Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 09/28/2009 10/02/2009 3

7112201 IP Baseline Inspections Radioactive Material Processing and Transportation 09/28/2009 10/02/2009 3

7112202 IP Baseline Inspections Occupational Exposure Control Effectiveness 09/28/2009 10/02/2009 3

71151-OR01 IP Baseline Inspections RETS/ODCM Radiological Effluent 09/28/2009 10/02/2009 3

71151-PR01 IP 1

EB3ISI

- INSERVICE INSPECTION Baseline Inspections Inservice Inspection Activities - PWR 10/05/2009 10/09/2009 3

7111108P IP 1

EB3TI172

- TI-172 RCS DM BUTT WELDS Generic Safety Inspectio Reactor Coolant System Dissimiliar Metal Butt Welds 10/05/2009 10/09/2009 3

2515/172 IP This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.