Inspection/Activity Plan for 03/01/2005 - 09/30/2006
ML050610142
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/04/2005
From: Joel Munday
NRC/RGN-II/DRP/RPB3
To: Young D
Florida Power Corp
Shared Package
ML050610125 List:
References
IR-05-001 Report 22
Download: ML050610142 (2)


Text

Crystal River Inspection / Activity Plan 03/01/2005 - 09/30/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 02/28/2005 13:41:31 Report 22 1

EB1SSDPC - SSDPC PRE-INSPECTION VISIT Baseline Inspections 03/28/2005 03/30/2005 Safety System Design and Performance Capability IP 7111121 3

1 PS2-EP

- EP INSPECTION Baseline Inspections 04/25/2005 04/29/2005 Alert and Notification System Testing IP 7111402 3

Baseline Inspections 04/25/2005 04/29/2005 Emergency Response Organization Augmentation Testing IP 7111403 3

Baseline Inspections 04/25/2005 04/29/2005 Emergency Action Level and Emergency Plan Changes IP 7111404 3

Baseline Inspections 04/25/2005 04/29/2005 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 3

Baseline Inspections 04/25/2005 04/29/2005 Performance Indicator Verification IP 71151 3

4 EB1SSDPC - SAFETY SYSTEM DESIGN & PERF. CAPABILITY Baseline Inspections 04/25/2005 04/29/2005 Safety System Design and Performance Capability IP 7111121 3

Baseline Inspections 05/09/2005 05/13/2005 Safety System Design and Performance Capability IP 7111121 3

1 MTN-MR

- MR EFFECTIVENESS Baseline Inspections 08/15/2005 08/19/2005 Maintenance Effectiveness IP 7111112B 3

3 OL PREP

- INITIAL EXAM PREP Not Applicable 08/15/2005 08/19/2005 CRYSTAL RIVER/EXAMS AT POWER FACILITIES V23237 3

3 OL EXAM

- INITIAL EXAM Not Applicable 09/12/2005 09/16/2005 CRYSTAL RIVER/EXAMS AT POWER FACILITIES V23237 3

3 PS1-RP

- RP OCCUPATIONAL BASELINE - WEEK 1 Baseline Inspections 10/31/2005 11/04/2005 Access Control to Radiologically Significant Areas IP 7112101 3

Baseline Inspections 10/31/2005 11/04/2005 ALARA Planning and Controls IP 7112102 3

Baseline Inspections 10/31/2005 11/04/2005 Radioactive Material Processing and Transportation IP 7112202 3

Baseline Inspections 10/31/2005 11/04/2005 Performance Indicator Verification IP 71151 3

2 MTN-ISI

- INSERVICE INSPECTION Baseline Inspections 11/07/2005 11/11/2005 Inservice Inspection Activities - PWR IP 7111108P 3

1 MTNTI160

- 2515/160 U-3: PZR PENETRATION NOZZLES Safety Issues 11/07/2005 11/11/2005 Pzr Pene Nozzles & Stm Space Piping Connections in U.S. PWRs [NRC Bulletin 2004-01]

IP 2515/160 3

2 MTNSGISI

- STEAM GENERATOR ISI Baseline Inspections 11/14/2005 11/18/2005 Inservice Inspection Activities - PWR IP 7111108P 3

3 PS1-RP

- RP OCCUPATIONAL BASELINE - WEEK 2 Baseline Inspections 11/14/2005 11/18/2005 Access Control to Radiologically Significant Areas IP 7112101 3

Baseline Inspections 11/14/2005 11/18/2005 ALARA Planning and Controls IP 7112102 3

Baseline Inspections 11/14/2005 11/18/2005 Radioactive Material Processing and Transportation IP 7112202 3

Baseline Inspections 11/14/2005 11/18/2005 Performance Indicator Verification IP 71151 3

4 EB1-MODS

- MODIFICATIONS/10CFR50.59 Baseline Inspections 12/05/2005 12/09/2005 Evaluation of Changes, Tests, or Experiments IP 7111102 3

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Crystal River Inspection / Activity Plan 03/01/2005 - 09/30/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 02/28/2005 13:41:31 Report 22 4

EB1-MODS

- MODIFICATIONS/10CFR50.59 Baseline Inspections 12/05/2005 12/09/2005 Permanent Plant Modifications IP 7111117B 3

1 MTN-HS

- HEAT SINK Baseline Inspections 01/09/2006 01/13/2006 Heat Sink Performance IP 7111107B 3

2 OL RQ

- REQUAL INSPECTION Baseline Inspections 01/30/2006 02/03/2006 Licensed Operator Requalification Program IP 7111111B 3

3 PS2-EP

- EP EXERCISE Baseline Inspections 04/24/2006 04/28/2006 Exercise Evaluation IP 7111401 3

Baseline Inspections 04/24/2006 04/28/2006 Emergency Action Level and Emergency Plan Changes IP 7111404 3

Baseline Inspections 04/24/2006 04/28/2006 Performance Indicator Verification IP 71151 3

4 DRP

- PI&R Baseline Inspections 06/05/2006 06/23/2006 Identification and Resolution of Problems IP 71152B 3

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.