Report 22 - 2010001, Inspection/Activity Plan
ML100621071
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/03/2010
From:
Division Reactor Projects II
To:
Progress Energy Florida
Shared Package
ML100621057 List:
References
IR-10-001
Download: ML100621071 (2)


Text

Inspection / Activity Plan Page 1 of 2 03/03/2010 07:27:45 Report 22 03/01/2010 - 06/30/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Crystal River EB3CR

- CONT DELAM DETENSION 1

3 IP Steam Generator Replacement Inspection 50001 03/04/2010 03/11/2010 EB3CR

- CONT DELAM CONCRETE REMOVAL 1

3 IP Steam Generator Replacement Inspection 50001 03/15/2010 03/19/2010 PI&R

- PROBLEM IDENTIFICATION AND RESOLUTION 5

3 IP Identification and Resolution of Problems 71152B 04/05/2010 04/09/2010 3

IP Identification and Resolution of Problems 71152B 04/19/2010 04/23/2010 EB3CR

- CONT DELAM CONCRETE FORM POUR 1

3 IP Steam Generator Replacement Inspection 50001 04/05/2010 04/30/2010 EB3CR

- CONT DELAM RETENSION 1

3 IP Steam Generator Replacement Inspection 50001 05/10/2010 05/14/2010 EB1-CDBI

- COMPONENT DESIGN BASES INSPECTION 7

3 IP Component Design Bases Inspection 7111121 05/10/2010 05/14/2010 3

IP Component Design Bases Inspection 7111121 05/24/2010 05/28/2010 3

IP Component Design Bases Inspection 7111121 06/07/2010 06/11/2010 3

IP Component Design Bases Inspection 7111121 06/21/2010 06/25/2010 EB3CR

- CONT DELAM RETENSION & DOC REVIEW 1

3 IP Steam Generator Replacement Inspection 50001 05/31/2010 06/04/2010 EB3CR

- CONT DELAM CONCRETE SCAN BORING 1

3 IP Steam Generator Replacement Inspection 50001 06/07/2010 06/09/2010 EB3LR

- EB3 LICENSE RENEWAL FOLLOWUP 2

3 IP License Renewal Inspection 71002 06/07/2010 06/11/2010 PSB1EP

- EMERGENCY PREPAREDNESS EXERCISE 3

3 IP Exercise Evaluation 7111401 10/04/2010 10/08/2010 3

IP Emergency Action Level and Emergency Plan Changes 7111404 10/04/2010 10/08/2010 3

IP Performance Indicator Verification 71151 10/04/2010 10/08/2010 TI-177

- GASEOUS INTRUSION 3

3 IP Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 2515/177 10/25/2010 10/29/2010 PSB1-RP

- RP PUBLIC RADIATION PROTECTION 4

3 IP Radiological Hazard Assessment and Exposure Controls 71124.01 12/06/2010 12/10/2010 3

IP Occupational Dose Assessment 71124.04 12/06/2010 12/10/2010 3

IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 12/06/2010 12/10/2010 3

IP Public Radiation Safety 71124.07 12/06/2010 12/10/2010 3

IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 12/06/2010 12/10/2010 3

IP Performance Indicator Verification 71151 12/06/2010 12/10/2010 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Inspection / Activity Plan Page 2 of 2 03/03/2010 07:27:45 Report 22 03/01/2010 - 06/30/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Crystal River TFPI

- 805 TFPI 1

3 IP Fire Protection [Triennial]

7111105T 04/04/2011 04/08/2011 3

IP Fire Protection [Triennial]

7111105T 04/18/2011 04/22/2011 EB3HS

- HEAT SINK 1

3 IP Heat Sink Performance 7111107T 06/20/2011 06/24/2011 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure