{{#Wiki_filter:STATUS REPORT ON THE LICENSING ACTIVITIES AND REGULATORY DUTIES OF THE U.S. NUCLEAR REGULATORY COMMISSION For the Reporting Period through January 2018 Enclosure
{{#Wiki_filter:Enclosure STATUS REPORT ON THE LICENSING ACTIVITIES AND REGULATORY DUTIES OF THE U.S. NUCLEAR REGULATORY COMMISSION For the Reporting Period through January 2018


Table of Contents RESOURCES
i Table of Contents RESOURCES
: 1. Status of Project Aim and additional activities                                   1
: 1. Status of Project Aim and additional activities 1
: 2. Incorporation of five-year workload planning into policies and procedures         2
: 2. Incorporation of five-year workload planning into policies and procedures 2
: 3. Staffing                                                                           3
: 3. Staffing 3
: 4. Actions taken or planned to reduce corporate support costs, including efforts to reduce office space                                                               16
: 4. Actions taken or planned to reduce corporate support costs, including efforts to reduce office space 16
: 5. Status of efforts to provide greater transparency, timeliness, and itemization in invoices to applicants and licensees, including any progress toward electronic invoicing and payment                                                             18
: 5. Status of efforts to provide greater transparency, timeliness, and itemization in invoices to applicants and licensees, including any progress toward electronic invoicing and payment 18
: 6. Research activities initiated during the reporting period                         19 URANIUM RECOVERY
: 6. Research activities initiated during the reporting period 19 URANIUM RECOVERY
: 7. Information regarding major uranium recovery licensing application reviews       20
: 7. Information regarding major uranium recovery licensing application reviews 20
: 8. Status of major uranium recovery licensing actions                               21
: 8. Status of major uranium recovery licensing actions 21
: 9. Status of minor uranium recovery licensing actions                               24
: 9. Status of minor uranium recovery licensing actions 24
: 10. Status of Wyoming Agreement State application                                   25
: 10. Status of Wyoming Agreement State application 25
: 11. Specific actions planned to improve the efficiency of reviews conducted for compliance with the National Historic Preservation Act                     26
: 11. Specific actions planned to improve the efficiency of reviews conducted for compliance with the National Historic Preservation Act 26
: 12. Progress of the pilot project on flat fees for uranium recovery licensees       27 LICENSING
: 12. Progress of the pilot project on flat fees for uranium recovery licensees 27 LICENSING
: 13. Information regarding license amendment reviews for operating reactors, new reactors, and uranium recovery licensees                                   29
: 13. Information regarding license amendment reviews for operating reactors, new reactors, and uranium recovery licensees 29
: 14. Information regarding decommissioning transition reviews                         38
: 14. Information regarding decommissioning transition reviews 38
: 15. List of Technical Specifications Task Force travelers under review               38
: 15. List of Technical Specifications Task Force travelers under review 38
: 16. Actions planned and/or taken to ensure that the Technical Specifications Task Force traveler process achieves the regulatory efficiencies that were initially projected                                                             39
: 16. Actions planned and/or taken to ensure that the Technical Specifications Task Force traveler process achieves the regulatory efficiencies that were initially projected 39
: 17. Information regarding license renewal review applications                       39
: 17. Information regarding license renewal review applications 39
: 18. Status of ongoing license renewal reviews                                       44 i
: 18. Status of ongoing license renewal reviews 44  
: 19. Status of NRCs readiness to review applications for subsequent license renewal                                                                        46
: 20. Status of subsequent license renewal reviews                                  47
: 21. Information regarding power uprate application reviews                        47
: 22. Status of power uprate application reviews                                    47
: 23. Information regarding requests for additional information (RAIs) issued by various offices/programs                                                  47
: 24. Status of specific actions taken or planned to ensure greater discipline, management oversight, and transparency in the RAI process                    54
: 25. Actions taken to enhance the integration of risk information across the agencys activities to improve the technical basis for regulatory activities, to increase efficiency, and to improve effectiveness                          57
: 26. Status of power reactor transition from analog to digital instrumentation    61
: 27. Actions taken and planned to prepare to review industry requests to use accident tolerant fuel in existing reactors                                  63
: 28. Actions taken and planned to improve the quality of cost benefit analyses conducted in association with new requirements, backfit analyses, or rulemaking                                                                    64
: 29. Status of the revised guidance to clarify the use of qualitative factors      65
: 30. List of all final generic regulatory actions issued in the last three years  67
: 31. List and brief description of all facility-specific backfits issued during the reporting period                                                          75
: 32. Twelve-month and three-year rolling averages for CRGR formal and informal reviews                                                              76
: 33. Status of the application of the backfit rule in licensing and inspection programs across the agency                                                    76
: 34. Actions taken and planned to address recommendations made by the CRGR in its report U.S. Nuclear Regulatory Commissions Implementation of Backfitting and Issue Finality Requirements                              78 REACTOR INSPECTION
: 35. Reactor Oversight Process findings for year-to-date and three-year rolling metrics                                                              80 ii
: 36. Percentage of Final Significance Determinations made within 90 days for all potentially greater-than-green findings, monthly for one-year rolling metrics and annually for the past 10 years                                              81
: 37. Instances where Inspection Manual Chapter 609, Appendix M, Significance Determination Process Using Qualitative Criteria, has been applied in the Reactor Oversight Process Significance Determination Process                    81
: 38. Status of potential changes to the Reactor Oversight Process and identification of any changes that may require Commission approval prior to implementation    82
: 39. Progress toward utilizing an industry consensus document as a means of accomplishing predictability and consistency in operability determinations      82
: 40. Information regarding Design Basis Assurance Inspections completed in the last three years                                                                82
: 41. Status of the holistic review of engineering inspection procedures and any actions taken and/or planned because of the review                              86 NEW REACTORS
: 42. Funds budgeted, resources spent, and total Part 170 fees billed each year for the past ten years for the Office of New Reactors                            87
: 43. Information regarding each design certification, combined license, and early site permit application reviewed since 2007                                    87
: 44. Summary of the status of ongoing design certification, combined license, and early site permit application reviews                                        94
: 45. Information on ITAAC reviews for reactors under construction                    97
: 46. License amendments for reactors under construction                              100
: 47. Budgeted resources and actual expenditures each month for the past 24 months for reactors under construction                                      100
: 48. Summary of the status of licensing and inspection for Vogtle Units 3 and 4      101
: 49. Actions taken in the past three years or planned to improve the efficiency of new plant reviews                                                            102
: 50. Unresolved policy issues regarding the licensing of small modular light-water reactors                                                            103
: 51. Unresolved policy issues regarding the licensing of advanced non-light water reactors                                                                108
: 52. Status of preparations to review non-light water reactor applications          108 iii


RESOURCES
ii
: 19. Status of NRCs readiness to review applications for subsequent license renewal 46
: 20. Status of subsequent license renewal reviews 47
: 21. Information regarding power uprate application reviews 47
: 22. Status of power uprate application reviews 47
: 23. Information regarding requests for additional information (RAIs) issued by various offices/programs 47
: 24. Status of specific actions taken or planned to ensure greater discipline, management oversight, and transparency in the RAI process 54
: 25. Actions taken to enhance the integration of risk information across the agencys activities to improve the technical basis for regulatory activities, to increase efficiency, and to improve effectiveness 57
: 26. Status of power reactor transition from analog to digital instrumentation 61
: 27. Actions taken and planned to prepare to review industry requests to use accident tolerant fuel in existing reactors 63
: 28. Actions taken and planned to improve the quality of cost benefit analyses conducted in association with new requirements, backfit analyses, or rulemaking 64
: 29. Status of the revised guidance to clarify the use of qualitative factors 65
: 30. List of all final generic regulatory actions issued in the last three years 67
: 31. List and brief description of all facility-specific backfits issued during the reporting period 75
: 32. Twelve-month and three-year rolling averages for CRGR formal and informal reviews 76
: 33. Status of the application of the backfit rule in licensing and inspection programs across the agency 76
: 34. Actions taken and planned to address recommendations made by the CRGR in its report U.S. Nuclear Regulatory Commissions Implementation of Backfitting and Issue Finality Requirements 78 REACTOR INSPECTION
: 35. Reactor Oversight Process findings for year-to-date and three-year rolling metrics 80
 
iii
: 36. Percentage of Final Significance Determinations made within 90 days for all potentially greater-than-green findings, monthly for one-year rolling metrics and annually for the past 10 years 81
: 37. Instances where Inspection Manual Chapter 609, Appendix M, Significance Determination Process Using Qualitative Criteria, has been applied in the Reactor Oversight Process Significance Determination Process 81
: 38. Status of potential changes to the Reactor Oversight Process and identification of any changes that may require Commission approval prior to implementation 82
: 39. Progress toward utilizing an industry consensus document as a means of accomplishing predictability and consistency in operability determinations 82
: 40. Information regarding Design Basis Assurance Inspections completed in the last three years 82
: 41. Status of the holistic review of engineering inspection procedures and any actions taken and/or planned because of the review 86 NEW REACTORS
: 42. Funds budgeted, resources spent, and total Part 170 fees billed each year for the past ten years for the Office of New Reactors 87
: 43. Information regarding each design certification, combined license, and early site permit application reviewed since 2007 87
: 44. Summary of the status of ongoing design certification, combined license, and early site permit application reviews 94
: 45. Information on ITAAC reviews for reactors under construction 97
: 46. License amendments for reactors under construction 100
: 47. Budgeted resources and actual expenditures each month for the past 24 months for reactors under construction 100
: 48. Summary of the status of licensing and inspection for Vogtle Units 3 and 4 101
: 49. Actions taken in the past three years or planned to improve the efficiency of new plant reviews 102
: 50. Unresolved policy issues regarding the licensing of small modular light-water reactors 103
: 51. Unresolved policy issues regarding the licensing of advanced non-light water reactors 108
: 52. Status of preparations to review non-light water reactor applications 108
 
1 RESOURCES
: 1. Will Project Aim 2020 conclude in early 2018, or will it continue pursuing additional improvements? If Project Aim will continue, please describe any new or additional actions taken or planned, including milestones for completion of such actions.
: 1. Will Project Aim 2020 conclude in early 2018, or will it continue pursuing additional improvements? If Project Aim will continue, please describe any new or additional actions taken or planned, including milestones for completion of such actions.
In June 2015, the Commission approved 19 discrete Project Aim tasks intended to improve NRCs efficiency and agility, as well as right size the agencys workforce to its workload, while retaining employees with the skills necessary to accomplish its safety and security mission and streamline processes. In 2017, the NRC completed the major deliverables for each of the 19 Project Aim tasks. The deliverables for some of the tasks entailed full implementation of the task, while others included detailed proposals and implementation plans for activities to be implemented in the future. The NRC staff is completing follow-on actions to implement recommendations, which will continue to affect and shape NRCs line organizations going forward. The NRC staff continues to provide a quarterly Project Aim status report to the Commission. A copy will be transmitted with this report each quarter.
In June 2015, the Commission approved 19 discrete Project Aim tasks intended to improve NRCs efficiency and agility, as well as right size the agencys workforce to its workload, while retaining employees with the skills necessary to accomplish its safety and security mission and streamline processes. In 2017, the NRC completed the major deliverables for each of the 19 Project Aim tasks. The deliverables for some of the tasks entailed full implementation of the task, while others included detailed proposals and implementation plans for activities to be implemented in the future. The NRC staff is completing follow-on actions to implement recommendations, which will continue to affect and shape NRCs line organizations going forward. The NRC staff continues to provide a quarterly Project Aim status report to the Commission. A copy will be transmitted with this report each quarter.
The NRC Chairmans June 29, 2017, and October 25, 2017, letters to Senators Cochran and Leahy, on the progress of certain licensing actions and right-sizing commitments indicated that one of the 19 completed tasks implemented a re-baselining effort, which identified 150 activities to be shed, deferred, or performed with fewer resources.
The NRC Chairmans June 29, 2017, and {{letter dated|date=October 25, 2017|text=October 25, 2017, letter}}s to Senators Cochran and Leahy, on the progress of certain licensing actions and right-sizing commitments indicated that one of the 19 completed tasks implemented a re-baselining effort, which identified 150 activities to be shed, deferred, or performed with fewer resources.
The NRC continues to institutionalize the actions related to Project Aim and pursue additional activities. The table below describes two such activities that continue the objectives of Project Aim and demonstrate the NRCs continued commitment to effectiveness and efficiency. These and other Project Aim initiatives are now integrated with the NRC agency reform plan, developed in response to OMB requirements.
The NRC continues to institutionalize the actions related to Project Aim and pursue additional activities. The table below describes two such activities that continue the objectives of Project Aim and demonstrate the NRCs continued commitment to effectiveness and efficiency. These and other Project Aim initiatives are now integrated with the NRC agency reform plan, developed in response to OMB requirements.
Initiative                         Milestones                         Notes Develop an agency-level         Project initiation: April 20, 2017 Idea Greenhouse program and Innovation Forum to          January 26, 2018: Develop Draft     Completed capture and refine staff        Communication Strategy recommendations to improve NRC operations                  February 2, 2018: Launch             Completed SharePoint site for idea submittals for evaluation and tracking the status of the ideas February 23, 2018: Implement Communications Strategy on Agency-wide Implementation of Innovation Programs March 30, 2018: Operation of Office/Region-Level Innovation Program 1
Initiative Milestones Notes Develop an agency-level Idea Greenhouse program and Innovation Forum to capture and refine staff recommendations to improve NRC operations Project initiation: April 20, 2017 January 26, 2018: Develop Draft Communication Strategy February 2, 2018: Launch SharePoint site for idea submittals for evaluation and tracking the status of the ideas February 23, 2018: Implement Communications Strategy on Agency-wide Implementation of Innovation Programs March 30, 2018: Operation of Office/Region-Level Innovation Program Completed Completed


Initiative                         Milestones                         Notes March 30, 2018: Finalize Processes for Agency Innovation Forum to evaluate ideas and present recommendations to Senior Leadership Implement an enhanced           Project initiation 07/29/2017          Piloting the process with strategic workforce planning                                           three offices to test a (SWP) process that will                                               variety of guidance, improve workforce                                                     templates, and tools, and management by focusing on                                             to refine the process strategic human capital                                               before launching management and longer-                                                 agencywide.
2 Initiative Milestones Notes March 30, 2018: Finalize Processes for Agency Innovation Forum to evaluate ideas and present recommendations to Senior Leadership Implement an enhanced strategic workforce planning (SWP) process that will improve workforce management by focusing on strategic human capital management and longer-term planning Project initiation 07/29/2017 Train supervisors in SWP concepts and process 10/11/17 Pilot offices deliver workload forecast (execution year+1 and execution year+5) 12/12/17 Deliverable: Workforce Demand Analysis 01/31/18 Deliverable: Workforce Supply Analysis 03/09/18 Deliverable: Prioritized list of gaps and surpluses 05/07/18 Deliverable: Strategies to address gaps and surpluses 06/22/18 Pilot Report to the Executive Director for Operations (EDO) 07/13/18 Piloting the process with three offices to test a variety of guidance, templates, and tools, and to refine the process before launching agencywide.
term planning                   Train supervisors in SWP concepts and process 10/11/17         Completed Pilot offices deliver workload forecast (execution year+1 and execution year+5) 12/12/17             Completed Deliverable: Workforce Demand         Completed Analysis 01/31/18 Deliverable: Workforce Supply Analysis 03/09/18 Deliverable: Prioritized list of gaps and surpluses 05/07/18 Deliverable: Strategies to address gaps and surpluses 06/22/18 Pilot Report to the Executive         Final report will include a Director for Operations (EDO)         determination of 07/13/18                               strengths, challenges, and scalability of the process.
Completed Completed Completed Final report will include a determination of strengths, challenges, and scalability of the process.
: 2. Consistent with the workload forecast done under Project Aim 2020, to what extent has the NRC incorporated five-year workload planning into its policies and procedures, e.g.,
: 2. Consistent with the workload forecast done under Project Aim 2020, to what extent has the NRC incorporated five-year workload planning into its policies and procedures, e.g.,
strategic planning and budget formulation? Please describe the actions taken or planned.
strategic planning and budget formulation? Please describe the actions taken or planned.
On July 5, 2017, the NRCs EDO initiated a three-office pilot of an enhanced SWP process that better integrates workload projection, skills identification, human capital management, individual development, and workforce management activities (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17178A284). The pilot implements the process described in an April 19, 2017, memo, Proposed Enhancements to NRCS Strategic Workforce Planning (ADAMS Accession No. ML17109A319). As currently envisioned, the enhanced SWP has an annual cycle that ensures the insights from both one-year and five-year workload forecasts are considered in NRC strategic planning, human capital management, and 2
On July 5, 2017, the NRCs EDO initiated a three-office pilot of an enhanced SWP process that better integrates workload projection, skills identification, human capital management, individual development, and workforce management activities (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17178A284). The pilot implements the process described in an April 19, 2017, memo, Proposed Enhancements to NRCS Strategic Workforce Planning (ADAMS Accession No. ML17109A319). As currently envisioned, the enhanced SWP has an annual cycle that ensures the insights from both one-year and five-year workload forecasts are considered in NRC strategic planning, human capital management, and  


budget formulation activities. The actions taken and planned for the SWP pilot are outlined in the table in the response to Question 1, above. Depending on the results of the pilot, the agency expects to adopt the enhanced strategic workforce planning process agencywide in 2018, which will fully incorporate five-year workload planning into other established processes.
3 budget formulation activities. The actions taken and planned for the SWP pilot are outlined in the table in the response to Question 1, above. Depending on the results of the pilot, the agency expects to adopt the enhanced strategic workforce planning process agencywide in 2018, which will fully incorporate five-year workload planning into other established processes.
: 3. Please provide the total number of staff and corporate support staff (FTE), budgeted vs actual, for the agency and in each of the following offices: Nuclear Reactor Regulation, New Reactors, Nuclear Material Safety and Safeguards, Nuclear Security and Incident Response, Nuclear Regulatory Research, Uranium Recovery, Decommissioning, and each regional office. Please provide this information for the current month, each of the previous eleven months, and projections for each of the twelve months going forward. Please do not divide by twelve.
: 3. Please provide the total number of staff and corporate support staff (FTE), budgeted vs actual, for the agency and in each of the following offices: Nuclear Reactor Regulation, New Reactors, Nuclear Material Safety and Safeguards, Nuclear Security and Incident Response, Nuclear Regulatory Research, Uranium Recovery, Decommissioning, and each regional office. Please provide this information for the current month, each of the previous eleven months, and projections for each of the twelve months going forward. Please do not divide by twelve.
U.S. Nuclear Regulatory Commission Agency Level FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
U.S. Nuclear Regulatory Commission Agency Level FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Fiscal Projected                       Annual Period                               Year to Date FTE for the                      Budget FTE Period 01/22/2017 - 02/18/2017                 251.5         1270.8 02/19/2017 - 03/18/2017                 251.0         1521.8 03/19/2017 - 04/15/2017                 250.3         1772.1 04/16/2017 - 05/13/2017                 247.9         2020.0 05/14/2017 - 06/10/2017                 245.6         2265.6 06/11/2017 - 07/08/2017                 245.1         2510.7 07/09/2017 - 08/05/2017                 244.2         2754.9 08/06/2017 - 09/02/2017                 243.2         2998.1 09/03/2017 - 09/30/2017                 242.8         3240.9           3405     FY 2017 10/01/2017 - 10/28/2017                 241.3           241.3 10/29/2017 - 11/25/2017                 240.8           482.1 11/26/2017 - 12/23/2017                 240.4           722.5 12/24/2017 - 01/20/2018                 238.2           960.7 01/21/2018 - 02/17/2018                 237.2         1197.9 02/18/2018 - 03/17/2018                 236.8         1434.7 03/18/2018 - 04/14/2018                 236.8         1671.5 04/15/2018 - 05/12/2018                 236.5         1908.0 05/13/2018 - 06/09/2018                 236.4         2144.4 06/10/2018 - 07/07/2018                 236.5         2380.9 07/08/2018 - 08/04/2018                 236.4         2617.3 08/05/2018 - 09/01/2018                 236.4         2853.7 09/02/2018 - 09/29/2018                 236.5         3090.2           3293     FY 2018 09/30/2018 - 10/27/2018                 236.7           236.7 3
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 251.5 1270.8 02/19/2017 - 03/18/2017 251.0 1521.8 03/19/2017 - 04/15/2017 250.3 1772.1 04/16/2017 - 05/13/2017 247.9 2020.0 05/14/2017 - 06/10/2017 245.6 2265.6 06/11/2017 - 07/08/2017 245.1 2510.7 07/09/2017 - 08/05/2017 244.2 2754.9 08/06/2017 - 09/02/2017 243.2 2998.1 09/03/2017 - 09/30/2017 242.8 3240.9 3405 FY 2017 10/01/2017 - 10/28/2017 241.3 241.3 10/29/2017 - 11/25/2017 240.8 482.1 11/26/2017 - 12/23/2017 240.4 722.5 12/24/2017 - 01/20/2018 238.2 960.7 01/21/2018 - 02/17/2018 237.2 1197.9 02/18/2018 - 03/17/2018 236.8 1434.7 03/18/2018 - 04/14/2018 236.8 1671.5 04/15/2018 - 05/12/2018 236.5 1908.0 05/13/2018 - 06/09/2018 236.4 2144.4 06/10/2018 - 07/07/2018 236.5 2380.9 07/08/2018 - 08/04/2018 236.4 2617.3 08/05/2018 - 09/01/2018 236.4 2853.7 09/02/2018 - 09/29/2018 236.5 3090.2 3293 FY 2018 09/30/2018 - 10/27/2018 236.7 236.7  


10/28/2018 - 11/24/2018                           236.7             473.4 11/25/2018 - 12/22/2018                           236.8             710.2 12/23/2018 - 01/19/2019                           236.8             947.0               3255   FY 2019 Notes: 1 Data are reported in two-pay-period groups because of the biweekly payroll cycle.
4 10/28/2018 - 11/24/2018 236.7 473.4 11/25/2018 - 12/22/2018 236.8 710.2 12/23/2018 - 01/19/2019 236.8 947.0 3255 FY 2019 Notes:
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
1 2
3   Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
4 Includes staff in the Office of the Inspector General.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
6 FY 2018 and FY 2019 FTE include FTE associated with the High-Level Waste Program (HLW) activities.
4 Includes staff in the Office of the Inspector General.
5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
6 FY 2018 and FY 2019 FTE include FTE associated with the High-Level Waste Program (HLW) activities.
The Office Level tables do not include the annual budgeted FTE for the HLW program; FTE will be allocated at the Office Level in future reports, if funds are enacted.
The Office Level tables do not include the annual budgeted FTE for the HLW program; FTE will be allocated at the Office Level in future reports, if funds are enacted.
U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Fiscal Projected                           Annual Period                                     Year to Date FTE for                            Budget FTE the Period 01/22/2017 - 02/18/2017                       37.8           191.0 02/19/2017 - 03/18/2017                       37.6           228.6 03/19/2017 - 04/15/2017                       37.5           266.1 04/16/2017 - 05/13/2017                       37.2           303.3 05/14/2017 - 06/10/2017                       36.6           339.9 06/11/2017 - 07/08/2017                       36.5           376.4 07/09/2017 - 08/05/2017                       36.4           412.8 08/06/2017 - 09/02/2017                       36.4           449.2 09/03/2017 - 09/30/2017                       36.1           485.3               488     FY 2017 10/01/2017 - 10/28/2017                       35.9             35.9 10/29/2017 - 11/25/2017                       34.7             70.6 11/26/2017 - 12/23/2017                       34.5           105.1 12/24/2017 - 01/20/2018                       34.5           139.6 01/21/2018 - 02/17/2018                       34.5           174.1 02/18/2018 - 03/17/2018                       34.6           208.7 03/18/2018 - 04/14/2018                       34.6           243.3 04/15/2018 - 05/12/2018                       34.5           277.8 05/13/2018 - 06/09/2018                       34.6           312.4 06/10/2018 - 07/07/2018                       34.6           347.0 07/08/2018 - 08/04/2018                       34.6           381.6 08/05/2018 - 09/01/2018                       34.6           416.2 09/02/2018 - 09/29/2018                       34.6           450.8               461     FY 2018 09/30/2018 - 10/27/2018                       34.6             34.6 4
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 37.8 191.0 02/19/2017 - 03/18/2017 37.6 228.6 03/19/2017 - 04/15/2017 37.5 266.1 04/16/2017 - 05/13/2017 37.2 303.3 05/14/2017 - 06/10/2017 36.6 339.9 06/11/2017 - 07/08/2017 36.5 376.4 07/09/2017 - 08/05/2017 36.4 412.8 08/06/2017 - 09/02/2017 36.4 449.2 09/03/2017 - 09/30/2017 36.1 485.3 488 FY 2017 10/01/2017 - 10/28/2017 35.9 35.9 10/29/2017 - 11/25/2017 34.7 70.6 11/26/2017 - 12/23/2017 34.5 105.1 12/24/2017 - 01/20/2018 34.5 139.6 01/21/2018 - 02/17/2018 34.5 174.1 02/18/2018 - 03/17/2018 34.6 208.7 03/18/2018 - 04/14/2018 34.6 243.3 04/15/2018 - 05/12/2018 34.5 277.8 05/13/2018 - 06/09/2018 34.6 312.4 06/10/2018 - 07/07/2018 34.6 347.0 07/08/2018 - 08/04/2018 34.6 381.6 08/05/2018 - 09/01/2018 34.6 416.2 09/02/2018 - 09/29/2018 34.6 450.8 461 FY 2018 09/30/2018 - 10/27/2018 34.6 34.6  


10/28/2018 - 11/24/2018                 34.6               69.2 11/25/2018 - 12/22/2018                 34.6             103.8 12/23/2018 - 01/19/2019                 34.6             138.4               451       FY 2019 Notes:     1 Data are reported in two-pay-period groups because of the biweekly payroll cycle.
5 10/28/2018 - 11/24/2018 34.6 69.2 11/25/2018 - 12/22/2018 34.6 103.8 12/23/2018 - 01/19/2019 34.6 138.4 451 FY 2019 Notes:
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
1 2
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
4 Includes all staff in NRR.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
U.S. Nuclear Regulatory Commission Office of New Reactors FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
4 Includes all staff in NRR.
Fiscal Projected                             Annual Period                                       Year to Date FTE for the                            Budget FTE Period 01/22/2017 - 02/18/2017                     22.7             116.9 02/19/2017 - 03/18/2017                     22.5             139.4 03/19/2017 - 04/15/2017                     22.7             162.1 04/16/2017 - 05/13/2017                     22.4             184.5 05/14/2017 - 06/10/2017                     22.3             206.8 06/11/2017 - 07/08/2017                     22.4             229.2 07/09/2017 - 08/05/2017                     22.2             251.4 08/06/2017 - 09/02/2017                     22.1             273.5 09/03/2017 - 09/30/2017                     22.0             295.5                 313           FY 2017 10/01/2017 - 10/28/2017                     22.0               22.0 10/29/2017 - 11/25/2017                     21.9               43.9 11/26/2017 - 12/23/2017                     21.6               65.5 12/24/2017 - 01/20/2018                     20.8               86.3 01/21/2018 - 02/17/2018                     20.8             107.1 02/18/2018 - 03/17/2018                     20.6             127.7 03/18/2018 - 04/14/2018                     20.6             148.3 04/15/2018 - 05/12/2018                     20.5             168.8 05/13/2018 - 06/09/2018                     20.5             189.3 06/10/2018 - 07/07/2018                     20.5             209.8 07/08/2018 - 08/04/2018                     20.5             230.3 08/05/2018 - 09/01/2018                     20.5             250.8 09/02/2018 - 09/29/2018                     20.5             271.3                 303           FY 2018 09/30/2018 - 10/27/2018                     20.6               20.6 10/28/2018 - 11/24/2018                     20.6               41.2 11/25/2018 - 12/22/2018                     20.6               61.8 12/23/2018 - 01/19/2019                     20.6               82.4                 263           FY 2019 5
5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
U.S. Nuclear Regulatory Commission Office of New Reactors FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 22.7 116.9 02/19/2017 - 03/18/2017 22.5 139.4 03/19/2017 - 04/15/2017 22.7 162.1 04/16/2017 - 05/13/2017 22.4 184.5 05/14/2017 - 06/10/2017 22.3 206.8 06/11/2017 - 07/08/2017 22.4 229.2 07/09/2017 - 08/05/2017 22.2 251.4 08/06/2017 - 09/02/2017 22.1 273.5 09/03/2017 - 09/30/2017 22.0 295.5 313 FY 2017 10/01/2017 - 10/28/2017 22.0 22.0 10/29/2017 - 11/25/2017 21.9 43.9 11/26/2017 - 12/23/2017 21.6 65.5 12/24/2017 - 01/20/2018 20.8 86.3 01/21/2018 - 02/17/2018 20.8 107.1 02/18/2018 - 03/17/2018 20.6 127.7 03/18/2018 - 04/14/2018 20.6 148.3 04/15/2018 - 05/12/2018 20.5 168.8 05/13/2018 - 06/09/2018 20.5 189.3 06/10/2018 - 07/07/2018 20.5 209.8 07/08/2018 - 08/04/2018 20.5 230.3 08/05/2018 - 09/01/2018 20.5 250.8 09/02/2018 - 09/29/2018 20.5 271.3 303 FY 2018 09/30/2018 - 10/27/2018 20.6 20.6 10/28/2018 - 11/24/2018 20.6 41.2 11/25/2018 - 12/22/2018 20.6 61.8 12/23/2018 - 01/19/2019 20.6 82.4 263 FY 2019


Notes:   1 Data are reported in two-pay-period groups because of the biweekly payroll cycle.
6 Notes:
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
1 2
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
4 Includes all staff in NRO.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
U.S. Nuclear Regulatory Commission Office of Nuclear Materials Safety and Safeguards FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
4 Includes all staff in NRO.
Fiscal Projected                               Annual Period                                       Year to Date FTE for the                              Budget FTE Period 01/22/2017 - 02/18/2017                       22.2             112.5 02/19/2017 - 03/18/2017                       22.2             134.7 03/19/2017 - 04/15/2017                       22.1             156.8 04/16/2017 - 05/13/2017                       21.9             178.7 05/14/2017 - 06/10/2017                       21.7             200.4 06/11/2017 - 07/08/2017                       22.0             222.4 07/09/2017 - 08/05/2017                       21.9             244.3 08/06/2017 - 09/02/2017                       21.9             266.2 09/03/2017 - 09/30/2017                       21.9             288.1                   297     FY 2017 10/01/2017 - 10/28/2017                       21.5               21.5 10/29/2017 - 11/25/2017                       23.1               44.6 11/26/2017 - 12/23/2017                       23.2               67.8 12/24/2017 - 01/20/2018                       23.3               91.1 01/21/2018 - 02/17/2018                       23.4             114.5 02/18/2018 - 03/17/2018                       23.4             137.9 03/18/2018 - 04/14/2018                       23.4             161.3 04/15/2018 - 05/12/2018                       23.4             184.7 05/13/2018 - 06/09/2018                       23.4             208.1 06/10/2018 - 07/07/2018                       23.4             231.5 07/08/2018 - 08/04/2018                       23.4             254.9 08/05/2018 - 09/01/2018                       23.4             278.3 09/02/2018 - 09/29/2018                       23.4             301.7                   295     FY 2018 09/30/2018 - 10/27/2018                       23.4               23.4 10/28/2018 - 11/24/2018                       23.4               46.8 11/25/2018 - 12/22/2018                       23.4               70.2 12/23/2018 - 01/19/2019                       23.4               93.6                 292     FY 2019 Notes:   1 Data are reported in two-pay-period groups because of the biweekly payroll cycle.
5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
U.S. Nuclear Regulatory Commission Office of Nuclear Materials Safety and Safeguards FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
6
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 22.2 112.5 02/19/2017 - 03/18/2017 22.2 134.7 03/19/2017 - 04/15/2017 22.1 156.8 04/16/2017 - 05/13/2017 21.9 178.7 05/14/2017 - 06/10/2017 21.7 200.4 06/11/2017 - 07/08/2017 22.0 222.4 07/09/2017 - 08/05/2017 21.9 244.3 08/06/2017 - 09/02/2017 21.9 266.2 09/03/2017 - 09/30/2017 21.9 288.1 297 FY 2017 10/01/2017 - 10/28/2017 21.5 21.5 10/29/2017 - 11/25/2017 23.1 44.6 11/26/2017 - 12/23/2017 23.2 67.8 12/24/2017 - 01/20/2018 23.3 91.1 01/21/2018 - 02/17/2018 23.4 114.5 02/18/2018 - 03/17/2018 23.4 137.9 03/18/2018 - 04/14/2018 23.4 161.3 04/15/2018 - 05/12/2018 23.4 184.7 05/13/2018 - 06/09/2018 23.4 208.1 06/10/2018 - 07/07/2018 23.4 231.5 07/08/2018 - 08/04/2018 23.4 254.9 08/05/2018 - 09/01/2018 23.4 278.3 09/02/2018 - 09/29/2018 23.4 301.7 295 FY 2018 09/30/2018 - 10/27/2018 23.4 23.4 10/28/2018 - 11/24/2018 23.4 46.8 11/25/2018 - 12/22/2018 23.4 70.2 12/23/2018 - 01/19/2019 23.4 93.6 292 FY 2019 Notes:
1 2
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).  


3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
7 3
4 Provides all staff in NMSS, including FTE for Uranium Recovery and Reactor Decommissioning.
Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
4 5
U.S. Nuclear Regulatory Commission Office of Nuclear Regulatory Research FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
Provides all staff in NMSS, including FTE for Uranium Recovery and Reactor Decommissioning.
Fiscal Projected                               Annual Period                                       Year to Date FTE for the                              Budget FTE Period 01/22/2017 - 02/18/2017                       15.9               80.6 02/19/2017 - 03/18/2017                       15.8               96.4 03/19/2017 - 04/15/2017                       15.6             112.0 04/16/2017 - 05/13/2017                       15.4             127.4 05/14/2017 - 06/10/2017                       15.3             142.7 06/11/2017 - 07/08/2017                       15.3             158.0 07/09/2017 - 08/05/2017                       15.3             173.3 08/06/2017 - 09/02/2017                       15.3             188.6 09/03/2017 - 09/30/2017                       15.1             203.7                   197     FY 2017 10/01/2017 - 10/28/2017                       15.0               15.0 10/29/2017 - 11/25/2017                       14.9               29.9 11/26/2017 - 12/23/2017                       15.1               45.0 12/24/2017 - 01/20/2018                       15.3               60.3 01/21/2018 - 02/17/2018                       15.2               75.5 02/18/2018 - 03/17/2018                       15.2               90.7 03/18/2018 - 04/14/2018                       15.3             106.0 04/15/2018 - 05/12/2018                       15.4             121.4 05/13/2018 - 06/09/2018                       15.4             136.8 06/10/2018 - 07/07/2018                       15.4             152.2 07/08/2018 - 08/04/2018                       15.4             167.6 08/05/2018 - 09/01/2018                       15.4             183.0 09/02/2018 - 09/29/2018                       15.4             198.4                   197     FY 2018 09/30/2018 - 10/27/2018                       15.4               15.4 10/28/2018 - 11/24/2018                       15.4               30.8 11/25/2018 - 12/22/2018                       15.4               46.2 12/23/2018 - 01/19/2019                       15.4               61.6                 208     FY 2019 Notes:   1 Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
U.S. Nuclear Regulatory Commission Office of Nuclear Regulatory Research FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 15.9 80.6 02/19/2017 - 03/18/2017 15.8 96.4 03/19/2017 - 04/15/2017 15.6 112.0 04/16/2017 - 05/13/2017 15.4 127.4 05/14/2017 - 06/10/2017 15.3 142.7 06/11/2017 - 07/08/2017 15.3 158.0 07/09/2017 - 08/05/2017 15.3 173.3 08/06/2017 - 09/02/2017 15.3 188.6 09/03/2017 - 09/30/2017 15.1 203.7 197 FY 2017 10/01/2017 - 10/28/2017 15.0 15.0 10/29/2017 - 11/25/2017 14.9 29.9 11/26/2017 - 12/23/2017 15.1 45.0 12/24/2017 - 01/20/2018 15.3 60.3 01/21/2018 - 02/17/2018 15.2 75.5 02/18/2018 - 03/17/2018 15.2 90.7 03/18/2018 - 04/14/2018 15.3 106.0 04/15/2018 - 05/12/2018 15.4 121.4 05/13/2018 - 06/09/2018 15.4 136.8 06/10/2018 - 07/07/2018 15.4 152.2 07/08/2018 - 08/04/2018 15.4 167.6 08/05/2018 - 09/01/2018 15.4 183.0 09/02/2018 - 09/29/2018 15.4 198.4 197 FY 2018 09/30/2018 - 10/27/2018 15.4 15.4 10/28/2018 - 11/24/2018 15.4 30.8 11/25/2018 - 12/22/2018 15.4 46.2 12/23/2018 - 01/19/2019 15.4 61.6 208 FY 2019 Notes:
4 Includes all staff in RES.
1 2
7
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
4 Includes all staff in RES.  


5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
8 5
U.S. Nuclear Regulatory Commission Office of Nuclear Security and Incident Response FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
Fiscal Projected                               Annual Period                                       Year to Date FTE for the                              Budget FTE Period 01/22/2017 - 02/18/2017                       13.5               68.5 02/19/2017 - 03/18/2017                       13.5               82.0 03/19/2017 - 04/15/2017                       13.6               95.6 04/16/2017 - 05/13/2017                       13.4             109.0 05/14/2017 - 06/10/2017                       13.3             122.3 06/11/2017 - 07/08/2017                       13.0             135.3 07/09/2017 - 08/05/2017                       12.9             148.2 08/06/2017 - 09/02/2017                       12.9             161.1 09/03/2017 - 09/30/2017                       12.9             174.0                   182     FY 2017 10/01/2017 - 10/28/2017                       13.0               13.0 10/29/2017 - 11/25/2017                       13.1               26.1 11/26/2017 - 12/23/2017                       13.2               39.3 12/24/2017 - 01/20/2018                       13.1               52.4 01/21/2018 - 02/17/2018                       13.0               65.4 02/18/2018 - 03/17/2018                       13.0               78.4 03/18/2018 - 04/14/2018                       13.1               91.5 04/15/2018 - 05/12/2018                       13.1             104.6 05/13/2018 - 06/09/2018                       13.1             117.7 06/10/2018 - 07/07/2018                       13.2             130.9 07/08/2018 - 08/04/2018                       13.2             144.1 08/05/2018 - 09/01/2018                       13.2             157.3 09/02/2018 - 09/29/2018                       13.2             170.5                   176     FY 2018 09/30/2018 - 10/27/2018                       13.2               13.2 10/28/2018 - 11/24/2018                       13.2               26.4 11/25/2018 - 12/22/2018                       13.2               39.6 12/23/2018 - 01/19/2019                       13.2               52.8                 168     FY 2019 Notes:   1 Data are reported in two-pay-period groups because of the biweekly payroll cycle.
U.S. Nuclear Regulatory Commission Office of Nuclear Security and Incident Response FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 13.5 68.5 02/19/2017 - 03/18/2017 13.5 82.0 03/19/2017 - 04/15/2017 13.6 95.6 04/16/2017 - 05/13/2017 13.4 109.0 05/14/2017 - 06/10/2017 13.3 122.3 06/11/2017 - 07/08/2017 13.0 135.3 07/09/2017 - 08/05/2017 12.9 148.2 08/06/2017 - 09/02/2017 12.9 161.1 09/03/2017 - 09/30/2017 12.9 174.0 182 FY 2017 10/01/2017 - 10/28/2017 13.0 13.0 10/29/2017 - 11/25/2017 13.1 26.1 11/26/2017 - 12/23/2017 13.2 39.3 12/24/2017 - 01/20/2018 13.1 52.4 01/21/2018 - 02/17/2018 13.0 65.4 02/18/2018 - 03/17/2018 13.0 78.4 03/18/2018 - 04/14/2018 13.1 91.5 04/15/2018 - 05/12/2018 13.1 104.6 05/13/2018 - 06/09/2018 13.1 117.7 06/10/2018 - 07/07/2018 13.2 130.9 07/08/2018 - 08/04/2018 13.2 144.1 08/05/2018 - 09/01/2018 13.2 157.3 09/02/2018 - 09/29/2018 13.2 170.5 176 FY 2018 09/30/2018 - 10/27/2018 13.2 13.2 10/28/2018 - 11/24/2018 13.2 26.4 11/25/2018 - 12/22/2018 13.2 39.6 12/23/2018 - 01/19/2019 13.2 52.8 168 FY 2019 Notes:
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
1 2
4 Includes all staff in NSIR.
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
8
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
4 5
Includes all staff in NSIR.
Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.  


U.S. Nuclear Regulatory Commission Uranium Recovery FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
9 U.S. Nuclear Regulatory Commission Uranium Recovery FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Fiscal Projected                               Annual Period                                       Year to Date FTE for the                              Budget FTE Period 01/22/2017 - 02/18/2017                         1.7               8.5 02/19/2017 - 03/18/2017                         1.7             10.2 03/19/2017 - 04/15/2017                         1.7             11.9 04/16/2017 - 05/13/2017                         1.7             13.6 05/14/2017 - 06/10/2017                         1.7             15.3 06/11/2017 - 07/08/2017                         1.7             17.0 07/09/2017 - 08/05/2017                         1.7             18.7 08/06/2017 - 09/02/2017                         1.7             20.4 09/03/2017 - 09/30/2017                         1.6             22.0                   31   FY 2017 10/01/2017 - 10/28/2017                         1.6               1.6 10/29/2017 - 11/25/2017                         1.6               3.2 11/26/2017 - 12/23/2017                         1.6               4.8 12/24/2017 - 01/20/2018                         1.5               6.3 01/21/2018 - 02/17/2018                         1.5               7.8 02/18/2018 - 03/17/2018                         1.5               9.3 03/18/2018 - 04/14/2018                         1.5             10.8 04/15/2018 - 05/12/2018                         1.5             12.3 05/13/2018 - 06/09/2018                         1.5             13.8 06/10/2018 - 07/07/2018                         1.5             15.3 07/08/2018 - 08/04/2018                         1.5             16.8 08/05/2018 - 09/01/2018                         1.5             18.3 09/02/2018 - 09/29/2018                         1.5             19.8                   30   FY 2018 09/30/2018 - 10/27/2018                         1.5               1.5 10/28/2018 - 11/24/2018                         1.5               3.0 11/25/2018 - 12/22/2018                         1.5               4.5 12/23/2018 - 01/19/2019                         1.5               6.0                   15   FY 2019 Notes: 1   Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 1.7 8.5 02/19/2017 - 03/18/2017 1.7 10.2 03/19/2017 - 04/15/2017 1.7 11.9 04/16/2017 - 05/13/2017 1.7 13.6 05/14/2017 - 06/10/2017 1.7 15.3 06/11/2017 - 07/08/2017 1.7 17.0 07/09/2017 - 08/05/2017 1.7 18.7 08/06/2017 - 09/02/2017 1.7 20.4 09/03/2017 - 09/30/2017 1.6 22.0 31 FY 2017 10/01/2017 - 10/28/2017 1.6 1.6 10/29/2017 - 11/25/2017 1.6 3.2 11/26/2017 - 12/23/2017 1.6 4.8 12/24/2017 - 01/20/2018 1.5 6.3 01/21/2018 - 02/17/2018 1.5 7.8 02/18/2018 - 03/17/2018 1.5 9.3 03/18/2018 - 04/14/2018 1.5 10.8 04/15/2018 - 05/12/2018 1.5 12.3 05/13/2018 - 06/09/2018 1.5 13.8 06/10/2018 - 07/07/2018 1.5 15.3 07/08/2018 - 08/04/2018 1.5 16.8 08/05/2018 - 09/01/2018 1.5 18.3 09/02/2018 - 09/29/2018 1.5 19.8 30 FY 2018 09/30/2018 - 10/27/2018 1.5 1.5 10/28/2018 - 11/24/2018 1.5 3.0 11/25/2018 - 12/22/2018 1.5 4.5 12/23/2018 - 01/19/2019 1.5 6.0 15 FY 2019 Notes:
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
1 2
3   Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
4   Includes all staff in the Uranium Recovery Branch of the Office of Nuclear Material Safety and Safeguards (NMSS), and relevant staff in the following:
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
Environmental Review Branch, NMSS; Division of Materials Safety, State, Tribal, and Rulemaking Programs, NMSS; Fuel Cycle and Decommissioning Branch, Region IV; Office of General Counsel (OGC); and Atomic Safety Licensing Board Panel (ASLB).
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
9
4 Includes all staff in the Uranium Recovery Branch of the Office of Nuclear Material Safety and Safeguards (NMSS), and relevant staff in the following:
Environmental Review Branch, NMSS; Division of Materials Safety, State, Tribal, and Rulemaking Programs, NMSS; Fuel Cycle and Decommissioning Branch, Region IV; Office of General Counsel (OGC); and Atomic Safety Licensing Board Panel (ASLB).  


U.S. Nuclear Regulatory Commission Decommissioning FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
10 U.S. Nuclear Regulatory Commission Decommissioning FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Fiscal Projected                                 Annual Period                                         Year to Date FTE for the                                Budget FTE Period 01/22/2017 - 02/18/2017                         3.3               16.6 02/19/2017 - 03/18/2017                         3.3               19.9 03/19/2017 - 04/15/2017                         3.3               23.2 04/16/2017 - 05/13/2017                         3.3               26.5 05/14/2017 - 06/10/2017                         3.4               29.9 06/11/2017 - 07/08/2017                         3.4               33.3 07/09/2017 - 08/05/2017                         3.5               36.8 08/06/2017 - 09/02/2017                         3.5               40.3 09/03/2017 - 09/30/2017                         3.5               43.8                   37   FY 2017 10/01/2017 - 10/28/2017                         3.5                 3.5 10/29/2017 - 11/25/2017                         3.5                 7.0 11/26/2017 - 12/23/2017                         3.5               10.5 12/24/2017 - 01/20/2018                         3.5               14.0 01/21/2018 - 02/17/2018                         3.5               17.5 02/18/2018 - 03/17/2018                         3.4               20.9 03/18/2018 - 04/14/2018                         3.4               24.3 04/15/2018 - 05/12/2018                         3.4               27.7 05/13/2018 - 06/09/2018                         3.4               31.1 06/10/2018 - 07/07/2018                         3.4               34.5 07/08/2018 - 08/04/2018                         3.4               37.9 08/05/2018 - 09/01/2018                         3.4               41.3 09/02/2018 - 09/29/2018                         3.4               44.7                   37   FY 2018 09/30/2018 - 10/27/2018                         3.4                 3.4 10/28/2018 - 11/24/2018                         3.4                 6.8 11/25/2018 - 12/22/2018                         3.4               10.2 12/23/2018 - 01/19/2019                         3.4               13.6                   35   FY 2019 Notes:   1   Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 3.3 16.6 02/19/2017 - 03/18/2017 3.3 19.9 03/19/2017 - 04/15/2017 3.3 23.2 04/16/2017 - 05/13/2017 3.3 26.5 05/14/2017 - 06/10/2017 3.4 29.9 06/11/2017 - 07/08/2017 3.4 33.3 07/09/2017 - 08/05/2017 3.5 36.8 08/06/2017 - 09/02/2017 3.5 40.3 09/03/2017 - 09/30/2017 3.5 43.8 37 FY 2017 10/01/2017 - 10/28/2017 3.5 3.5 10/29/2017 - 11/25/2017 3.5 7.0 11/26/2017 - 12/23/2017 3.5 10.5 12/24/2017 - 01/20/2018 3.5 14.0 01/21/2018 - 02/17/2018 3.5 17.5 02/18/2018 - 03/17/2018 3.4 20.9 03/18/2018 - 04/14/2018 3.4 24.3 04/15/2018 - 05/12/2018 3.4 27.7 05/13/2018 - 06/09/2018 3.4 31.1 06/10/2018 - 07/07/2018 3.4 34.5 07/08/2018 - 08/04/2018 3.4 37.9 08/05/2018 - 09/01/2018 3.4 41.3 09/02/2018 - 09/29/2018 3.4 44.7 37 FY 2018 09/30/2018 - 10/27/2018 3.4 3.4 10/28/2018 - 11/24/2018 3.4 6.8 11/25/2018 - 12/22/2018 3.4 10.2 12/23/2018 - 01/19/2019 3.4 13.6 35 FY 2019 Notes:
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
1 2
3   Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
4   Includes all staff in the Reactor and Materials Decommissioning Branches of NMSS, plus relevant contributions from staff in OGC, R-I, and R-III. No mission support staff, second level and above supervisory staff, or staff support from other offices is included.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
10
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
4 Includes all staff in the Reactor and Materials Decommissioning Branches of NMSS, plus relevant contributions from staff in OGC, R-I, and R-III. No mission support staff, second level and above supervisory staff, or staff support from other offices is included.  


U.S. Nuclear Regulatory Commission Region I FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
11 U.S. Nuclear Regulatory Commission Region I FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Fiscal Projected                               Annual Period                                       Year to Date FTE for the                              Budget FTE Period 01/22/2017 - 02/18/2017                       15.6               79.1 02/19/2017 - 03/18/2017                       15.4               94.5 03/19/2017 - 04/15/2017                       15.4             109.9 04/16/2017 - 05/13/2017                       15.2             125.1 05/14/2017 - 06/10/2017                       15.3             140.4 06/11/2017 - 07/08/2017                       15.5             155.9 07/09/2017 - 08/05/2017                       15.7             171.6 08/06/2017 - 09/02/2017                       15.6             187.2 09/03/2017 - 09/30/2017                       15.5             202.7                   209     FY 2017 10/01/2017 - 10/28/2017                       15.4               15.4 10/29/2017 - 11/25/2017                       15.5               30.9 11/26/2017 - 12/23/2017                       15.4               46.3 12/24/2017 - 01/20/2018                       15.1               61.4 01/21/2018 - 02/17/2018                       14.9               76.3 02/18/2018 - 03/17/2018                       14.7               91.0 03/18/2018 - 04/14/2018                       14.7             105.7 04/15/2018 - 05/12/2018                       14.8             120.5 05/13/2018 - 06/09/2018                       14.8             135.3 06/10/2018 - 07/07/2018                       14.7             150.0 07/08/2018 - 08/04/2018                       14.6             164.6 08/05/2018 - 09/01/2018                       14.6             179.2 09/02/2018 - 09/29/2018                       14.6             193.8                   198     FY 2018 09/30/2018 - 10/27/2018                       14.6               14.6 10/28/2018 - 11/24/2018                       14.6               29.2 11/25/2018 - 12/22/2018                       14.6               43.8 12/23/2018 - 01/19/2019                       14.6               58.4                 195     FY 2019 Notes:   1 Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 15.6 79.1 02/19/2017 - 03/18/2017 15.4 94.5 03/19/2017 - 04/15/2017 15.4 109.9 04/16/2017 - 05/13/2017 15.2 125.1 05/14/2017 - 06/10/2017 15.3 140.4 06/11/2017 - 07/08/2017 15.5 155.9 07/09/2017 - 08/05/2017 15.7 171.6 08/06/2017 - 09/02/2017 15.6 187.2 09/03/2017 - 09/30/2017 15.5 202.7 209 FY 2017 10/01/2017 - 10/28/2017 15.4 15.4 10/29/2017 - 11/25/2017 15.5 30.9 11/26/2017 - 12/23/2017 15.4 46.3 12/24/2017 - 01/20/2018 15.1 61.4 01/21/2018 - 02/17/2018 14.9 76.3 02/18/2018 - 03/17/2018 14.7 91.0 03/18/2018 - 04/14/2018 14.7 105.7 04/15/2018 - 05/12/2018 14.8 120.5 05/13/2018 - 06/09/2018 14.8 135.3 06/10/2018 - 07/07/2018 14.7 150.0 07/08/2018 - 08/04/2018 14.6 164.6 08/05/2018 - 09/01/2018 14.6 179.2 09/02/2018 - 09/29/2018 14.6 193.8 198 FY 2018 09/30/2018 - 10/27/2018 14.6 14.6 10/28/2018 - 11/24/2018 14.6 29.2 11/25/2018 - 12/22/2018 14.6 43.8 12/23/2018 - 01/19/2019 14.6 58.4 195 FY 2019 Notes:
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
1 2
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
4 Includes all staff in R-I.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
11
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
4 Includes all staff in R-I.  


U.S. Nuclear Regulatory Commission Region II FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
12 U.S. Nuclear Regulatory Commission Region II FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Fiscal Projected                               Annual Period                                       Year to Date FTE for the                              Budget FTE Period 01/22/2017 - 02/18/2017                       20.2             100.8 02/19/2017 - 03/18/2017                       20.3             121.1 03/19/2017 - 04/15/2017                       20.3             141.4 04/16/2017 - 05/13/2017                       20.2             161.6 05/14/2017 - 06/10/2017                       20.3             181.9 06/11/2017 - 07/08/2017                       20.0             201.9 07/09/2017 - 08/05/2017                       19.9             221.8 08/06/2017 - 09/02/2017                       19.8             241.6 09/03/2017 - 09/30/2017                       19.8             261.4                   274     FY 2017 10/01/2017 - 10/28/2017                       19.7               19.7 10/29/2017 - 11/25/2017                       19.6               39.3 11/26/2017 - 12/23/2017                       19.6               58.9 12/24/2017 - 01/20/2018                       19.4               78.3 01/21/2018 - 02/17/2018                       19.5               97.8 02/18/2018 - 03/17/2018                       19.5             117.3 03/18/2018 - 04/14/2018                       19.5             136.8 04/15/2018 - 05/12/2018                       19.5             156.3 05/13/2018 - 06/09/2018                       19.3             175.6 06/10/2018 - 07/07/2018                       19.3             194.9 07/08/2018 - 08/04/2018                       19.3             214.2 08/05/2018 - 09/01/2018                       19.3             233.5 09/02/2018 - 09/29/2018                       19.3             252.8                   272     FY 2018 09/30/2018 - 10/27/2018                       19.3               19.3 10/28/2018 - 11/24/2018                       19.3               38.6 11/25/2018 - 12/22/2018                       19.3               57.9 12/23/2018 - 01/19/2019                       19.3               77.2                 249     FY 2019 Notes:   1 Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 20.2 100.8 02/19/2017 - 03/18/2017 20.3 121.1 03/19/2017 - 04/15/2017 20.3 141.4 04/16/2017 - 05/13/2017 20.2 161.6 05/14/2017 - 06/10/2017 20.3 181.9 06/11/2017 - 07/08/2017 20.0 201.9 07/09/2017 - 08/05/2017 19.9 221.8 08/06/2017 - 09/02/2017 19.8 241.6 09/03/2017 - 09/30/2017 19.8 261.4 274 FY 2017 10/01/2017 - 10/28/2017 19.7 19.7 10/29/2017 - 11/25/2017 19.6 39.3 11/26/2017 - 12/23/2017 19.6 58.9 12/24/2017 - 01/20/2018 19.4 78.3 01/21/2018 - 02/17/2018 19.5 97.8 02/18/2018 - 03/17/2018 19.5 117.3 03/18/2018 - 04/14/2018 19.5 136.8 04/15/2018 - 05/12/2018 19.5 156.3 05/13/2018 - 06/09/2018 19.3 175.6 06/10/2018 - 07/07/2018 19.3 194.9 07/08/2018 - 08/04/2018 19.3 214.2 08/05/2018 - 09/01/2018 19.3 233.5 09/02/2018 - 09/29/2018 19.3 252.8 272 FY 2018 09/30/2018 - 10/27/2018 19.3 19.3 10/28/2018 - 11/24/2018 19.3 38.6 11/25/2018 - 12/22/2018 19.3 57.9 12/23/2018 - 01/19/2019 19.3 77.2 249 FY 2019 Notes:
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
1 2
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
4 Includes all staff in R-II.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
12
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
4 Includes all staff in R-II.  


U.S. Nuclear Regulatory Commission Region III FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
13 U.S. Nuclear Regulatory Commission Region III FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Fiscal Projected                               Annual Period                                       Year to Date FTE for the                              Budget FTE Period 01/22/2017 - 02/18/2017                       14.3               71.1 02/19/2017 - 03/18/2017                       14.3               85.4 03/19/2017 - 04/15/2017                       14.3               99.7 04/16/2017 - 05/13/2017                       14.3             114.0 05/14/2017 - 06/10/2017                       14.3             128.3 06/11/2017 - 07/08/2017                       14.5             142.8 07/09/2017 - 08/05/2017                       14.4             157.2 08/06/2017 - 09/02/2017                       14.2             171.4 09/03/2017 - 09/30/2017                       14.2             185.6                   197     FY 2017 10/01/2017 - 10/28/2017                       14.3               14.3 10/29/2017 - 11/25/2017                       14.3               28.6 11/26/2017 - 12/23/2017                       14.3               42.9 12/24/2017 - 01/20/2018                       14.1               57.0 01/21/2018 - 02/17/2018                       14.0               71.0 02/18/2018 - 03/17/2018                       14.0               85.0 03/18/2018 - 04/14/2018                       14.0               99.0 04/15/2018 - 05/12/2018                       13.8             112.8 05/13/2018 - 06/09/2018                       13.8             126.6 06/10/2018 - 07/07/2018                       13.8             140.4 07/08/2018 - 08/04/2018                       13.8             154.2 08/05/2018 - 09/01/2018                       13.8             168.0 09/02/2018 - 09/29/2018                       13.8             181.8                   184     FY 2018 09/30/2018 - 10/27/2018                       13.8               13.8 10/28/2018 - 11/24/2018                       13.8               27.6 11/25/2018 - 12/22/2018                       13.8               41.4 12/23/2018 - 01/19/2019                       13.8               55.2                 182     FY 2019 Notes:   1 Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 14.3 71.1 02/19/2017 - 03/18/2017 14.3 85.4 03/19/2017 - 04/15/2017 14.3 99.7 04/16/2017 - 05/13/2017 14.3 114.0 05/14/2017 - 06/10/2017 14.3 128.3 06/11/2017 - 07/08/2017 14.5 142.8 07/09/2017 - 08/05/2017 14.4 157.2 08/06/2017 - 09/02/2017 14.2 171.4 09/03/2017 - 09/30/2017 14.2 185.6 197 FY 2017 10/01/2017 - 10/28/2017 14.3 14.3 10/29/2017 - 11/25/2017 14.3 28.6 11/26/2017 - 12/23/2017 14.3 42.9 12/24/2017 - 01/20/2018 14.1 57.0 01/21/2018 - 02/17/2018 14.0 71.0 02/18/2018 - 03/17/2018 14.0 85.0 03/18/2018 - 04/14/2018 14.0 99.0 04/15/2018 - 05/12/2018 13.8 112.8 05/13/2018 - 06/09/2018 13.8 126.6 06/10/2018 - 07/07/2018 13.8 140.4 07/08/2018 - 08/04/2018 13.8 154.2 08/05/2018 - 09/01/2018 13.8 168.0 09/02/2018 - 09/29/2018 13.8 181.8 184 FY 2018 09/30/2018 - 10/27/2018 13.8 13.8 10/28/2018 - 11/24/2018 13.8 27.6 11/25/2018 - 12/22/2018 13.8 41.4 12/23/2018 - 01/19/2019 13.8 55.2 182 FY 2019 Notes:
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
1 2
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
4 Includes all staff in R-III.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
13
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
4 Includes all staff in R-III.  
 
14 U.S. Nuclear Regulatory Commission Region IV FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 13.6 69.7 02/19/2017 - 03/18/2017 13.5 83.2 03/19/2017 - 04/15/2017 13.4 96.6 04/16/2017 - 05/13/2017 13.2 109.8 05/14/2017 - 06/10/2017 13.0 122.8 06/11/2017 - 07/08/2017 13.0 135.8 07/09/2017 - 08/05/2017 13.0 148.8 08/06/2017 - 09/02/2017 13.0 161.8 09/03/2017 - 09/30/2017 12.8 174.6 187 FY 2017 10/01/2017 - 10/28/2017 12.6 12.6 10/29/2017 - 11/25/2017 12.6 25.2 11/26/2017 - 12/23/2017 12.7 37.9 12/24/2017 - 01/20/2018 12.8 50.7 01/21/2018 - 02/17/2018 13.0 63.7 02/18/2018 - 03/17/2018 13.0 76.7 03/18/2018 - 04/14/2018 13.0 89.7 04/15/2018 - 05/12/2018 13.0 102.7 05/13/2018 - 06/09/2018 13.0 115.7 06/10/2018 - 07/07/2018 13.0 128.7 07/08/2018 - 08/04/2018 13.0 141.7 08/05/2018 - 09/01/2018 13.0 154.7 09/02/2018 - 09/29/2018 13.0 167.7 175 FY 2018 09/30/2018 - 10/27/2018 13.0 13.0 10/28/2018 - 11/24/2018 13.0 26.0 11/25/2018 - 12/22/2018 13.0 39.0 12/23/2018 - 01/19/2019 13.0 52.0 169 FY 2019 Notes:
1 2
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
4 Includes all staff in R-IV.


U.S. Nuclear Regulatory Commission Region IV FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
15 U.S. Nuclear Regulatory Commission Corporate Support Functions FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/
Fiscal Projected                               Annual Period                                       Year to Date FTE for the                              Budget FTE Period 01/22/2017 - 02/18/2017                       13.6              69.7 02/19/2017 - 03/18/2017                       13.5              83.2 03/19/2017 - 04/15/2017                       13.4              96.6 04/16/2017 - 05/13/2017                       13.2            109.8 05/14/2017 - 06/10/2017                       13.0             122.8 06/11/2017 - 07/08/2017                       13.0            135.8 07/09/2017 - 08/05/2017                       13.0            148.8 08/06/2017 - 09/02/2017                       13.0            161.8 09/03/2017 - 09/30/2017                       12.8             174.6                  187      FY 2017 10/01/2017 - 10/28/2017                       12.6              12.6 10/29/2017 - 11/25/2017                       12.6              25.2 11/26/2017 - 12/23/2017                       12.7               37.9 12/24/2017 - 01/20/2018                       12.8              50.7 01/21/2018 - 02/17/2018                       13.0              63.7 02/18/2018 - 03/17/2018                       13.0              76.7 03/18/2018 - 04/14/2018                       13.0              89.7 04/15/2018 - 05/12/2018                       13.0            102.7 05/13/2018 - 06/09/2018                       13.0             115.7 06/10/2018 - 07/07/2018                       13.0            128.7 07/08/2018 - 08/04/2018                       13.0            141.7 08/05/2018 - 09/01/2018                       13.0            154.7 09/02/2018 - 09/29/2018                       13.0            167.7                  175      FY 2018 09/30/2018 - 10/27/2018                       13.0              13.0 10/28/2018 - 11/24/2018                       13.0              26.0 11/25/2018 - 12/22/2018                       13.0              39.0 12/23/2018 - 01/19/2019                       13.0              52.0                  169      FY 2019 Notes:   1 Data are reported in two-pay-period groups because of the biweekly payroll cycle.
Projected FTE for the Period Fiscal Year to Date FTE 01/22/2017 - 02/18/2017 40.5 204.8 02/19/2017 - 03/18/2017 40.4 245.2 03/19/2017 - 04/15/2017 40.1 285.3 04/16/2017 - 05/13/2017 39.3 324.6 05/14/2017 - 06/10/2017 38.4 363.0 06/11/2017 - 07/08/2017 38.2 401.2 07/09/2017 - 08/05/2017 37.9 439.1 08/06/2017 - 09/02/2017 37.4 476.5 09/03/2017 - 09/30/2017 37.3 513.8 594 FY 2017 10/01/2017 - 10/28/2017 36.9 36.9 10/29/2017 - 11/25/2017 36.0 72.9 11/26/2017 - 12/23/2017 35.8 108.7 12/24/2017 - 01/20/2018 35.3 144.0 01/21/2018 - 02/17/2018 35.2 179.2 02/18/2018 - 03/17/2018 35.2 214.4 03/18/2018 - 04/14/2018 35.2 249.6 04/15/2018 - 05/12/2018 35.2 284.8 05/13/2018 - 06/09/2018 35.2 320.0 06/10/2018 - 07/07/2018 35.3 355.3 07/08/2018 - 08/04/2018 35.3 390.6 08/05/2018 - 09/01/2018 35.3 425.9 09/02/2018 - 09/29/2018 35.3 461.2 510 FY 2018 09/30/2018 - 10/27/2018 35.3 35.3 10/28/2018 - 11/24/2018 35.3 70.6 11/25/2018 - 12/22/2018 35.3 105.9 12/23/2018 - 01/19/2019 35.3 141.2 506 FY 2019 Notes:
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
1 2
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
Data are reported in two-pay-period groups because of the biweekly payroll cycle.
4 Includes all staff in R-IV.
Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
14
3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
4 Includes all staff in the following corporate support offices: Office of the Chief Financial Officer, Office of the Chief Information Officer, Office of Administration, Office of Small Business and Civil Rights, and Office of the Chief Human Capital Officer.
5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.  


U.S. Nuclear Regulatory Commission Corporate Support Functions FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Actual/
16
Fiscal Projected Period                                        Year to Date FTE for the FTE Period 01/22/2017 - 02/18/2017                      40.5            204.8 02/19/2017 - 03/18/2017                      40.4            245.2 03/19/2017 - 04/15/2017                      40.1            285.3 04/16/2017 - 05/13/2017                      39.3            324.6 05/14/2017 - 06/10/2017                      38.4            363.0 06/11/2017 - 07/08/2017                      38.2            401.2 07/09/2017 - 08/05/2017                      37.9            439.1 08/06/2017 - 09/02/2017                      37.4            476.5 09/03/2017 - 09/30/2017                      37.3            513.8                  594          FY 2017 10/01/2017 - 10/28/2017                      36.9              36.9 10/29/2017 - 11/25/2017                      36.0              72.9 11/26/2017 - 12/23/2017                      35.8            108.7 12/24/2017 - 01/20/2018                      35.3            144.0 01/21/2018 - 02/17/2018                      35.2            179.2 02/18/2018 - 03/17/2018                      35.2            214.4 03/18/2018 - 04/14/2018                      35.2            249.6 04/15/2018 - 05/12/2018                      35.2            284.8 05/13/2018 - 06/09/2018                      35.2            320.0 06/10/2018 - 07/07/2018                      35.3            355.3 07/08/2018 - 08/04/2018                      35.3            390.6 08/05/2018 - 09/01/2018                      35.3            425.9 09/02/2018 - 09/29/2018                      35.3            461.2                  510          FY 2018 09/30/2018 - 10/27/2018                      35.3              35.3 10/28/2018 - 11/24/2018                      35.3              70.6 11/25/2018 - 12/22/2018                      35.3            105.9 12/23/2018 - 01/19/2019                      35.3            141.2                  506          FY 2019 Notes:  1  Data are reported in two-pay-period groups because of the biweekly payroll cycle.
2  Actual/projected FTE for the period reflects FTE utilization (or projected utilization).
3  Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.
4  Includes all staff in the following corporate support offices: Office of the Chief Financial Officer, Office of the Chief Information Officer, Office of Administration, Office of Small Business and Civil Rights, and Office of the Chief Human Capital Officer.
5  Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.
15
: 4. Please describe the status of actions taken or planned to reduce corporate support costs, including efforts to reduce office space in the Three While Flint North building and in the regional offices. Please include goals for space reductions and cost savings, as well as the estimated date to achieve those goals.
: 4. Please describe the status of actions taken or planned to reduce corporate support costs, including efforts to reduce office space in the Three While Flint North building and in the regional offices. Please include goals for space reductions and cost savings, as well as the estimated date to achieve those goals.
The NRC remains committed to identifying and achieving efficiencies in the corporate support area. The agencys FY 2017 enacted budget for corporate support activities was $300.1 million.
The NRC remains committed to identifying and achieving efficiencies in the corporate support area. The agencys FY 2017 enacted budget for corporate support activities was $300.1 million.
Line 196: Line 222:
In addition to the above re-baselining reductions, in SECY-16-0035, Additional Re-baselining Items, the NRC staff identified other actions that could provide additional efficiencies in the long-term. For example, efforts to reduce office space in NRC headquarters and the regional offices will continue. A detailed discussion of these activities follows the summary table below.
In addition to the above re-baselining reductions, in SECY-16-0035, Additional Re-baselining Items, the NRC staff identified other actions that could provide additional efficiencies in the long-term. For example, efforts to reduce office space in NRC headquarters and the regional offices will continue. A detailed discussion of these activities follows the summary table below.
The NRC remains committed to identifying and achieving efficiencies in the corporate support area that will lead to reduced costs, such as the following:
The NRC remains committed to identifying and achieving efficiencies in the corporate support area that will lead to reduced costs, such as the following:
Product Line                                                           Total $                     Fiscal Description                                FTE  Status (M)*                         Year Additional Re-baselining Items (SECY-16-0035)
Product Line Description Total $
Administrative         Reduce Office Space in Three White Flint North       -4.0       0 In process FY 2018 -
(M)*
Services                                                                                              FY 2021 Administrative         Reduce Office Space in the Regions                   -1.2       0 In process FY 2018 -
FTE Status Fiscal Year Additional Re-baselining Items (SECY-16-0035)
Services                                                                                              FY 2021 Financial             Standardize Budget Formulation and Execution         TBD       TBD In process FY 2019 Management             across Business Lines Financial              Use a Federal Shared Service Provider for           TBD       TBD In process FY 2019 Management            Accounts Payable Administrative         Workstation Efficiencies                             TBD       TBD In process FY 2019 Services and Information Technology Subtotal - Additional Re-baselining Reductions       -$5.2     TBD Other Corporate Support Reductions Information           IT Infrastructure Support - the agency expects to   -3.6       0 In process FY 2018 Technology            realize a 10 to 15 percent drop in contract 16
Administrative Services Reduce Office Space in Three White Flint North  
-4.0 0
In process FY 2018 -
FY 2021 Administrative Services Reduce Office Space in the Regions  
-1.2 0
In process FY 2018 -
FY 2021 Financial Management Standardize Budget Formulation and Execution across Business Lines TBD TBD In process FY 2019 Financial Management Use a Federal Shared Service Provider for Accounts Payable TBD TBD In process FY 2019 Administrative Services and Information Technology Workstation Efficiencies TBD TBD In process FY 2019 Subtotal - Additional Re-baselining Reductions
-$5.2 TBD Other Corporate Support Reductions Information Technology IT Infrastructure Support - the agency expects to realize a 10 to 15 percent drop in contract
-3.6 0
In process FY 2018  


Product Line                                                         Total $                       Fiscal Description                              FTE  Status (M)*                         Year expenses resulting from a new acquisition strategy.
17 Product Line Description Total $
Subtotal - Other Corporate Support     -$3.6     0 Total                                                             -$8.8     0
(M)*
*Total includes any FTE cost.
FTE Status Fiscal Year expenses resulting from a new acquisition strategy.
Subtotal - Other Corporate Support
-$3.6 0
Total  
-$8.8 0  
*Total includes any FTE cost.
Reduction of Office Space.
Reduction of Office Space.
NRC office space is currently comprised of a Headquarters Campus in Rockville, MD (One White Flint North (OWFN), Two White Flint North (TWFN), and partial space in Three White Flint North (3WFN)), a warehouse, four regional office buildings, and a technical training center.
NRC office space is currently comprised of a Headquarters Campus in Rockville, MD (One White Flint North (OWFN), Two White Flint North (TWFN), and partial space in Three White Flint North (3WFN)), a warehouse, four regional office buildings, and a technical training center.
From FY 2013 through FY 2015, NRC relinquished a net total of 364,997 useable square feet (USF) at its headquarters by shedding a total of eight floors in the 3WFN building and four temporary satellite locations. As a result, the agencys headquarters now consists of OWFN, TWFN, and five floors and the B1 level of 3WFN. NRC plans to relinquish an additional 139,244 USF of office space at its headquarters location and four regional office locations, from FY 2018 through FY 2021. This space consists of four floors in 3WFN totaling 93,244 USF, and approximately 46,000 USF at the regional locations, by consolidating at headquarters and within each regional office location. NRCs proposed agency-wide total space reduction goals by fiscal year are shown in the table below.
From FY 2013 through FY 2015, NRC relinquished a net total of 364,997 useable square feet (USF) at its headquarters by shedding a total of eight floors in the 3WFN building and four temporary satellite locations. As a result, the agencys headquarters now consists of OWFN, TWFN, and five floors and the B1 level of 3WFN. NRC plans to relinquish an additional 139,244 USF of office space at its headquarters location and four regional office locations, from FY 2018 through FY 2021. This space consists of four floors in 3WFN totaling 93,244 USF, and approximately 46,000 USF at the regional locations, by consolidating at headquarters and within each regional office location. NRCs proposed agency-wide total space reduction goals by fiscal year are shown in the table below.
NRC Square Foot Reduction Goals FY 2018 - FY 2021 FY 2018         FY 2019       FY 2020     FY 2021 Office Target (Net SF Reduction)           33,561         42,561         29,561       33,561 Significantly reducing costs by releasing the space will be a challenge due to the non-cancelable terms of many of the occupancy agreements and leases, including the terms of 3WFN. However, NRC is working with the General Services Administration (GSA) to identify potential tenants for both 3WFN and the regional office locations. The Food and Drug Administration (FDA) has expressed an interest in acquiring an additional floor in 3WFN in FY 2018 and the National Institutes of Health (NIH) has expressed an interest in acquiring the remaining three floors as NRC continues to consolidate at headquarters and the space becomes available in the FY 2019 through FY 2021 timeframe. Regional office space reductions can be achieved by reconfiguring the existing space to use fewer square feet, thereby allowing for unused blocks of space to be released. However, with the exception of NRCs Region III office in Lisle, IL, rent savings will not be achieved until GSA identifies and places a new tenant into the released space, or until such time as the terms of the NRCs current leases allow. The timing and scope of the regional reductions are as follows: Region III, Lisle, IL, 11,000 USF in FY 2018; Region II, Atlanta, GA,17,000 USF in FY 2019; Region I, King of Prussia, PA, 7,000 USF in FY 2020; and Region IV, Arlington, TX, 11,000 USF in FY 2021.
NRC Square Foot Reduction Goals FY 2018 - FY 2021 FY 2018 FY 2019 FY 2020 FY 2021 Office Target (Net SF Reduction) 33,561 42,561 29,561 33,561 Significantly reducing costs by releasing the space will be a challenge due to the non-cancelable terms of many of the occupancy agreements and leases, including the terms of 3WFN. However, NRC is working with the General Services Administration (GSA) to identify potential tenants for both 3WFN and the regional office locations. The Food and Drug Administration (FDA) has expressed an interest in acquiring an additional floor in 3WFN in FY 2018 and the National Institutes of Health (NIH) has expressed an interest in acquiring the remaining three floors as NRC continues to consolidate at headquarters and the space becomes available in the FY 2019 through FY 2021 timeframe. Regional office space reductions can be achieved by reconfiguring the existing space to use fewer square feet, thereby allowing for unused blocks of space to be released. However, with the exception of NRCs Region III office in Lisle, IL, rent savings will not be achieved until GSA identifies and places a new tenant into the released space, or until such time as the terms of the NRCs current leases allow. The timing and scope of the regional reductions are as follows: Region III, Lisle, IL, 11,000 USF in FY 2018; Region II, Atlanta, GA,17,000 USF in FY 2019; Region I, King of Prussia, PA, 7,000 USF in FY 2020; and Region IV, Arlington, TX, 11,000 USF in FY 2021.
At headquarters, the amount and timing of rent reductions for 3WFN are contingent upon GSAs ability to identify and place a new tenant into the relinquished floors; however, NRC anticipates an annual reduction of $1 million per floor for each floor relinquished upon a new tenant taking the space. The agency anticipates rent costs to begin decreasing in July 2018 when FDA has 17
At headquarters, the amount and timing of rent reductions for 3WFN are contingent upon GSAs ability to identify and place a new tenant into the relinquished floors; however, NRC anticipates an annual reduction of $1 million per floor for each floor relinquished upon a new tenant taking the space. The agency anticipates rent costs to begin decreasing in July 2018 when FDA has  


agreed to occupy the 2nd floor of 3WFN, and again by early FY 2020 as NIH begins to occupy the remaining three floors. Once the release of NRCs space is complete in FY 2021, the agency will realize a total reduction of $4 million in office space costs going forward. Cost reductions for the regional locations are likewise dependent upon successful and timely leasing of the space to new tenants. The annual reduction in costs for the regional office space is anticipated to average approximately $300,000 per regional office. As a result of the planned space reductions, NRC anticipates an annual total rent reduction of $5.2 million from FY 2022 forward, as compared to FY 2018.
18 agreed to occupy the 2nd floor of 3WFN, and again by early FY 2020 as NIH begins to occupy the remaining three floors. Once the release of NRCs space is complete in FY 2021, the agency will realize a total reduction of $4 million in office space costs going forward. Cost reductions for the regional locations are likewise dependent upon successful and timely leasing of the space to new tenants. The annual reduction in costs for the regional office space is anticipated to average approximately $300,000 per regional office. As a result of the planned space reductions, NRC anticipates an annual total rent reduction of $5.2 million from FY 2022 forward, as compared to FY 2018.
: 5. Please describe the status of efforts to provide greater transparency, timeliness, and itemization in invoices to applicants and licensees, including any progress toward electronic invoicing and payment. Please include near-term (within 6 months), medium-term (6 to 12 months), and long-term (greater than 12 months) milestones.
: 5. Please describe the status of efforts to provide greater transparency, timeliness, and itemization in invoices to applicants and licensees, including any progress toward electronic invoicing and payment. Please include near-term (within 6 months), medium-term (6 to 12 months), and long-term (greater than 12 months) milestones.
Improvements to invoices showing itemized charges by standard codes for greater transparency and timeliness.
Improvements to invoices showing itemized charges by standard codes for greater transparency and timeliness.
Complete:
Complete:
In January 2018 the NRC issued the first redesigned quarterly invoices that improve transparency of the costs. Enhancements include:
In January 2018 the NRC issued the first redesigned quarterly invoices that improve transparency of the costs. Enhancements include:
* Invoice charges are grouped by project (Enterprise Project Identifier (EPID)), which is a new data element on the invoice, and for each EPID further itemized by activity (Cost Activity Code (CAC)).
Invoice charges are grouped by project (Enterprise Project Identifier (EPID)), which is a new data element on the invoice, and for each EPID further itemized by activity (Cost Activity Code (CAC)).
* Invoices include standard CAC titles to provide consistent descriptions for the same type of work performed for all projects.
Invoices include standard CAC titles to provide consistent descriptions for the same type of work performed for all projects.
* The names of NRC staff and contractor companies appear on the invoice for each itemized CAC.
The names of NRC staff and contractor companies appear on the invoice for each itemized CAC.
The invoices were sent with a document, Content Updates to your NRC Invoice, which describes the improvements to the invoice. The document can be found here:
The invoices were sent with a document, Content Updates to your NRC Invoice, which describes the improvements to the invoice. The document can be found here:
https://www.nrc.gov/about-nrc/regulatory/licensing/sample-invoice.pdf Near-Term:
https://www.nrc.gov/about-nrc/regulatory/licensing/sample-invoice.pdf Near-Term:
* The NRC will have a booth at the Regulatory Information Conference (RIC) on March 13 and 14, 2018 to further communicate changes to the invoices as well as solicit stakeholder feedback on the changes.
The NRC will have a booth at the Regulatory Information Conference (RIC) on March 13 and 14, 2018 to further communicate changes to the invoices as well as solicit stakeholder feedback on the changes.
* The NRC will be holding a public meeting on March 15, 2018, to further communicate changes to the invoices as well as solicit stakeholder feedback.
The NRC will be holding a public meeting on March 15, 2018, to further communicate changes to the invoices as well as solicit stakeholder feedback.
* The NRC will continue to evaluate feedback on the changes to the invoices.
The NRC will continue to evaluate feedback on the changes to the invoices.
Medium-Term:
Medium-Term:
* The Office of the Chief Financial Officer (OCFO) is working with an intra-agency working group during FY 2018 to implement a standardized 10 CFR Part 170 (fees for service) fee billing validation process, and establish standardized roles and responsibilities. The working group will develop, pilot, and finalize the process. OCFO will provide training to all staff involved in the billing process. OCFO is on target for a completion date of October 1, 2018.
The Office of the Chief Financial Officer (OCFO) is working with an intra-agency working group during FY 2018 to implement a standardized 10 CFR Part 170 (fees for service) fee billing validation process, and establish standardized roles and responsibilities. The working group will develop, pilot, and finalize the process. OCFO will provide training to all staff involved in the billing process. OCFO is on target for a completion date of October 1, 2018.  
18


Progress towards electronic invoicing and payment.
19 Progress towards electronic invoicing and payment.
The NRC is currently in the planning phase of the electronic invoicing (eBilling) project, which includes the following tasks:
The NRC is currently in the planning phase of the electronic invoicing (eBilling) project, which includes the following tasks:
Near-Term:
Near-Term:
* Document the initial "as-is" fee billing processes and fee billing information technology systems (complete).
Document the initial "as-is" fee billing processes and fee billing information technology systems (complete).
* Update the current as-is fee billing processes and fee billing information technology systems for OCFO acceptance (in progress).
Update the current as-is fee billing processes and fee billing information technology systems for OCFO acceptance (in progress).
* Continue to perform requirements analysis on items that may impact the fee billing process and systems (in progress).
Continue to perform requirements analysis on items that may impact the fee billing process and systems (in progress).
* Interview other Federal agencies that recently implemented electronic invoicing for lessons-learned opportunities (in progress).
Interview other Federal agencies that recently implemented electronic invoicing for lessons-learned opportunities (in progress).
* Conduct market research for eBilling tool selection (in progress).
Conduct market research for eBilling tool selection (in progress).
* Select an eBilling tool.
Select an eBilling tool.
Medium-Term:
Medium-Term:
* Establish the initial eBilling solution based on the eBilling tool selected, outreach activities, lesson learned opportunities, and a requirements analysis.
Establish the initial eBilling solution based on the eBilling tool selected, outreach activities, lesson learned opportunities, and a requirements analysis.
* Reach out to stakeholders for input on the initial eBilling proposed solution and to identify licensees to participate in phased-approach implementation pilot.
Reach out to stakeholders for input on the initial eBilling proposed solution and to identify licensees to participate in phased-approach implementation pilot.
* Develop a phased-approach and corresponding project plan to implement the eBilling solution based on stakeholder feedback.
Develop a phased-approach and corresponding project plan to implement the eBilling solution based on stakeholder feedback.
Long-Term:
Long-Term:
* Execute the eBilling solution. The initial phased approach deployment is planned to occur on or about October 2019.
Execute the eBilling solution. The initial phased approach deployment is planned to occur on or about October 2019.
* Continue to perform outreach activities with stakeholders.
Continue to perform outreach activities with stakeholders.
: 6. Please provide a list of alI new research initiated during the reporting period. For each new project, please provide the estimated timeframe and resources necessary for completion, and a description of the safety significance of the research.
: 6. Please provide a list of alI new research initiated during the reporting period. For each new project, please provide the estimated timeframe and resources necessary for completion, and a description of the safety significance of the research.
During the month of January 2018, the Office of Nuclear Regulatory Research (RES) initiated research on or substantially revised the following research:
During the month of January 2018, the Office of Nuclear Regulatory Research (RES) initiated research on or substantially revised the following research:
Estimated      Estimated          Safety Significance of Name of New or Revised Project             Completion     Resources             Research Activity No New or Revised Research Activities to Report for January 2018 Comments:
Comments:
19
Name of New or Revised Project Estimated Completion Estimated Resources Safety Significance of Research Activity No New or Revised Research Activities to Report for January 2018  


The table above provides projects that were reviewed and approved during the monthly reporting period for projects that exceed 300 staff hours or $500K of program support.
20 The table above provides projects that were reviewed and approved during the monthly reporting period for projects that exceed 300 staff hours or $500K of program support.
URANIUM RECOVERY
URANIUM RECOVERY
: 7. For major uranium recovery licensing actions, please provide a table including the date the application was filed, the duration of the application review, the originally forecasted completion date, the currently forecasted completion date, and the total current amount of fees billed to the licensee/applicant for the review.
: 7. For major uranium recovery licensing actions, please provide a table including the date the application was filed, the duration of the application review, the originally forecasted completion date, the currently forecasted completion date, and the total current amount of fees billed to the licensee/applicant for the review.
Major Uranium Recovery Licensing Actions (1)
Major Uranium Recovery Licensing Actions (1)
Originally        Currently        Total Current Fees Licensing                        Duration of Site/Facility                     Date of                           Forecasted        Forecasted        Billed (through Licensee                      Action                          Review (2)
Licensee Site/Facility Name Licensing Action Type Date of Submittal Duration of Review (2)
Name                              Submittal                          Completion        Completion        December 23, Type                            (months)
(months)
Date               Date             2017)
Originally Forecasted Completion Date Currently Forecasted Completion Date Total Current Fees Billed (through December 23, 2017)
Uranium Ludeman           Expansion       12/06/2011       69.0             08/14/2013         08/31/2018       $2,210,317.74 One (3)
Uranium One (3)
Kennecott   Sweetwater         Renewal         09/08/2014       38.5             12/31/2016         08/31/2018       $1,780,312.25 Crow Butte Marsland           Expansion       06/20/2012       64.0             02/14/2015         05/25/2018       $3,896,953.70 Resources (4)
Ludeman Expansion 12/06/2011 69.0 08/14/2013 08/31/2018  
Cameco Resources  Smith Ranch       Renewal         02/01/2012       67.0             07/05/2015         09/27/2018       $2,510,994.99 (5)
$2,210,317.74 Kennecott Sweetwater Renewal 09/08/2014 38.5 12/31/2016 08/31/2018  
Lost        KM Creek,      Horizon/LC         Expansion       02/27/2017       9.0               08/07/2018         08/07/2018       $1,409,796.95 ISR (6)    East Notes:
$1,780,312.25 Crow Butte Resources (4)
: 1. NRC staff completed a self-assessment of the uranium recovery licensing process in 2017. The review compared the uranium recovery licensing process to other licensing groups within the NRC to identify best practices. The review identified several recommendations for improvements to the uranium recovery licensing process. A number of these recommendations, such as the use of schedule letters to communicate changes in review schedules and developing tools to better track project status have already been implemented. In addition, in 2016, the uranium recovery program established an agency metric that tracks the percentage of major milestones completed on schedule. The uranium recovery staff anticipates that implementing these changes will result in future efficiencies in the uranium recovery licensing process.
Marsland Expansion 06/20/2012 64.0 02/14/2015 05/25/2018  
: 2. The duration of review is the total amount of time the application has been under consideration, starting when the application was accepted for review by the NRC staff. The NRCs goal is to complete major reviews within 36 months from acceptance of the application. The duration of review includes periods of delay that could be attributed to the NRC staff, the licensee, or both.
$3,896,953.70 Cameco Resources (5)
20
Smith Ranch Renewal 02/01/2012 67.0 07/05/2015 09/27/2018  
: 3. The duration of review has been primarily impacted by the applicants change in the design of the facility during the review process. The duration of review has also been impacted by a prior limited availability of health physics reviewers.
$2,510,994.99 Lost
: 4. The duration review has been impacted by the applicants timeliness in responding to NRC staffs RAI.
: Creek, ISR (6)
: 5. The duration review has been primarily impacted by delays in applicant providing adequate responses to NRC staffs RAI.
KM Horizon/LC East Expansion 02/27/2017 9.0 08/07/2018 08/07/2018  
: 6. Currently forecasted completion date represents completion of NRC safety evaluation report. The NRC staff continues to coordinate with the U.S. Bureau of Land Management (BLM) in its preparation of the environmental impact statement (EIS) in accordance with the BLM/NRC Memorandum of Understanding (MOU) and the letter of December 4, 2014, designating BLM as the lead agency and the NRC as a cooperating agency. The BLM is scheduled to publish the final EIS in December 2018.
$1,409,796.95 Notes:
: 1.
NRC staff completed a self-assessment of the uranium recovery licensing process in 2017. The review compared the uranium recovery licensing process to other licensing groups within the NRC to identify best practices. The review identified several recommendations for improvements to the uranium recovery licensing process. A number of these recommendations, such as the use of schedule letters to communicate changes in review schedules and developing tools to better track project status have already been implemented. In addition, in 2016, the uranium recovery program established an agency metric that tracks the percentage of major milestones completed on schedule. The uranium recovery staff anticipates that implementing these changes will result in future efficiencies in the uranium recovery licensing process.
: 2.
The duration of review is the total amount of time the application has been under consideration, starting when the application was accepted for review by the NRC staff. The NRCs goal is to complete major reviews within 36 months from acceptance of the application. The duration of review includes periods of delay that could be attributed to the NRC staff, the licensee, or both.  
 
21
: 3.
The duration of review has been primarily impacted by the applicants change in the design of the facility during the review process. The duration of review has also been impacted by a prior limited availability of health physics reviewers.
: 4.
The duration review has been impacted by the applicants timeliness in responding to NRC staffs RAI.
: 5.
The duration review has been primarily impacted by delays in applicant providing adequate responses to NRC staffs RAI.
: 6.
Currently forecasted completion date represents completion of NRC safety evaluation report. The NRC staff continues to coordinate with the U.S. Bureau of Land Management (BLM) in its preparation of the environmental impact statement (EIS) in accordance with the BLM/NRC Memorandum of Understanding (MOU) and the letter of December 4, 2014, designating BLM as the lead agency and the NRC as a cooperating agency. The BLM is scheduled to publish the final EIS in December 2018.
: 8. For major uranium recovery licensing actions, please provide a brief description of the status of each review, including* projected budget and timeline for both the environmental impact statement and the safety evaluation report.
: 8. For major uranium recovery licensing actions, please provide a brief description of the status of each review, including* projected budget and timeline for both the environmental impact statement and the safety evaluation report.
The table below provides the status of major uranium recovery licensing actions currently under review, the timeline for completing the associated EISs and SERs, and the total projected budget per project.
The table below provides the status of major uranium recovery licensing actions currently under review, the timeline for completing the associated EISs and SERs, and the total projected budget per project.
The NRC does not formulate its budget at the project level. The budget for the Uranium Recovery Program is formulated at a higher level using budget models for the number, type, and complexity of reviews anticipated. The projected budget information reported below includes the program staff and contract support resource estimates to perform the safety and environmental reviews from submittal to licensing decision, excluding resources for OGCs reviews, hearings, mission support, supervisory support, travel, and allocated agency corporate support resources. The estimates are based on budget models for different types (such as expansions, renewals, and new licenses) and complexities of major licensing action reviews.
The NRC does not formulate its budget at the project level. The budget for the Uranium Recovery Program is formulated at a higher level using budget models for the number, type, and complexity of reviews anticipated. The projected budget information reported below includes the program staff and contract support resource estimates to perform the safety and environmental reviews from submittal to licensing decision, excluding resources for OGCs reviews, hearings, mission support, supervisory support, travel, and allocated agency corporate support resources. The estimates are based on budget models for different types (such as expansions, renewals, and new licenses) and complexities of major licensing action reviews.
The NRC staffs goal is to complete the review of major licensing actions within 3 years; however, the staff estimates that smaller, less complex applications may be reviewed in 2 years, while larger, more complex, applications may require up to 4 years to review.
The NRC staffs goal is to complete the review of major licensing actions within 3 years; however, the staff estimates that smaller, less complex applications may be reviewed in 2 years, while larger, more complex, applications may require up to 4 years to review.
Uranium             Application       Review Status and Projected Budget Recovery            Accepted Applicant          for Review Cameco North       08/28/07         The licensee requested the NRC staff to stop its review of Trend                                the North Trend application and to instead focus its efforts Expansion                            on the review of the Marsland expansion. The SER for the North Trend expansion was completed in July 2013.
Uranium Recovery Applicant Application Accepted for Review Review Status and Projected Budget Cameco North Trend Expansion 08/28/07 The licensee requested the NRC staff to stop its review of the North Trend application and to instead focus its efforts on the review of the Marsland expansion. The SER for the North Trend expansion was completed in July 2013.
The NRC staff has suspended its work related to the development of the draft Environmental Assessment (EA) and conduct of Section 106 consultations pursuant to the National Historic Preservation Act. In addition, the hearing to address contentions related to groundwater is on hold, pending completion of the NRC staffs environmental review. The current schedule for remaining milestones will be determined after the NRC staff has completed its review for the Marsland expansion.
The NRC staff has suspended its work related to the development of the draft Environmental Assessment (EA) and conduct of Section 106 consultations pursuant to the National Historic Preservation Act. In addition, the hearing to address contentions related to groundwater is on hold, pending completion of the NRC staffs environmental review. The current schedule for remaining milestones will be determined after the NRC staff has completed its review for the Marsland expansion.
The projected total budget to conduct the review is 3.0 FTE and $600K.
The projected total budget to conduct the review is 3.0 FTE and $600K.  
21


Uranium     Application Review Status and Projected Budget Recovery    Accepted Applicant  for Review Uranium One 05/16/12   NRC environmental and safety reviews are in progress for Ludeman                this expansion of the existing Willow Creek project. The Expansion              licensee is resolving safety and environmental issues.
22 Uranium Recovery Applicant Application Accepted for Review Review Status and Projected Budget Uranium One Ludeman Expansion 05/16/12 NRC environmental and safety reviews are in progress for this expansion of the existing Willow Creek project. The licensee is resolving safety and environmental issues.
NRC met with the licensee on February 22, 2017, to discuss these issues and the licensees plan to submit an amended application that addresses a major change of design. On March 28, 2017, the NRC staff issued a letter to the licensee requesting an updated schedule of when it would submit the required information necessary for the staff to complete its review. In April 2017, the licensee provided all information except for the amended application. The staff received the amended technical report in June 2017, and the amended environmental report in August 2017. The NRC staff is on schedule to complete the SER by March 2018. Based on the amended environmental report, the cultural resources review can now be completed. The NRC staff is on schedule to issue the final EA by August 3, 2018, and reach a decision on the license amendment on August 31, 2018.
NRC met with the licensee on February 22, 2017, to discuss these issues and the licensees plan to submit an amended application that addresses a major change of design. On March 28, 2017, the NRC staff issued a letter to the licensee requesting an updated schedule of when it would submit the required information necessary for the staff to complete its review. In April 2017, the licensee provided all information except for the amended application. The staff received the amended technical report in June 2017, and the amended environmental report in August 2017. The NRC staff is on schedule to complete the SER by March 2018. Based on the amended environmental report, the cultural resources review can now be completed. The NRC staff is on schedule to issue the final EA by August 3, 2018, and reach a decision on the license amendment on August 31, 2018.
The projected total budget to conduct the review is 3.0 FTE and $600K.
The projected total budget to conduct the review is 3.0 FTE and $600K.
Cameco     07/05/12   Environmental and safety reviews are in progress. Open Smith Ranch            issues are currently being addressed. On May 2, 2013, License                the NRC staff issued an RAI on safety and environmental Renewal                aspects of the renewal request. On April 21, 2015, the licensee submitted its responses to the RAI. The NRC staff is working with the licensee to close remaining open issues. On May 2, 2016, the staff communicated to the licensee that its responses to the RAIs were incomplete. In December 2016 the staff requested the licensee to provide a schedule for completing its response to the remaining aspects of the RAI. On January 10, 2017, the licensee provided an update on when it expects to respond to part, but not all, of the NRC staffs RAI. The NRC staff responded to Camecos letter on April 14, 2017.
Cameco Smith Ranch License Renewal 07/05/12 Environmental and safety reviews are in progress. Open issues are currently being addressed. On May 2, 2013, the NRC staff issued an RAI on safety and environmental aspects of the renewal request. On April 21, 2015, the licensee submitted its responses to the RAI. The NRC staff is working with the licensee to close remaining open issues. On May 2, 2016, the staff communicated to the licensee that its responses to the RAIs were incomplete. In December 2016 the staff requested the licensee to provide a schedule for completing its response to the remaining aspects of the RAI. On January 10, 2017, the licensee provided an update on when it expects to respond to part, but not all, of the NRC staffs RAI. The NRC staff responded to Camecos letter on April 14, 2017.
The NRC staff and Cameco also had several public meetings to address Camecos development of sufficient RAI responses. The NRC staffs SER and EA completion dates in September 2018 were based on receipt of Camecos RAI responses by January 19, 2018. The NRC staff will reassess the schedule for completion of the SER and EA, when the responses are received.
The NRC staff and Cameco also had several public meetings to address Camecos development of sufficient RAI responses. The NRC staffs SER and EA completion dates in September 2018 were based on receipt of Camecos RAI responses by January 19, 2018. The NRC staff will reassess the schedule for completion of the SER and EA, when the responses are received.
The projected total budget to conduct the review is 3.5 FTE.
The projected total budget to conduct the review is 3.5 FTE.  
22


Uranium   Application Review Status and Projected Budget Recovery  Accepted Applicant  for Review Crow Butte 10/05/12   The NRC staff issued RAIs in July 2013. The licensee Marsland              responded in November 2015. After reviewing the Expansion              responses, the NRC determined that additional information was required to resolve the RAIs. Cameco submitted responses to the open issues in June and August 2017. The NRC staff completed its safety review for the final SER on January 29, 2018. The staff plans to complete the final EA in April 2018, and make a final licensing decision in May 2018. The Marsland expansion review has an admitted contention that will go to hearing after completion of the NRC staffs review.
23 Uranium Recovery Applicant Application Accepted for Review Review Status and Projected Budget Crow Butte Marsland Expansion 10/05/12 The NRC staff issued RAIs in July 2013. The licensee responded in November 2015. After reviewing the responses, the NRC determined that additional information was required to resolve the RAIs. Cameco submitted responses to the open issues in June and August 2017. The NRC staff completed its safety review for the final SER on January 29, 2018. The staff plans to complete the final EA in April 2018, and make a final licensing decision in May 2018. The Marsland expansion review has an admitted contention that will go to hearing after completion of the NRC staffs review.
The projected total budget to conduct the review is 3.0 FTE and $600K.
The projected total budget to conduct the review is 3.0 FTE and $600K.
Hydro     06/24/13   The sites, located very close to Navajo Nation lands, were Resources,            licensed in 1998. Construction has not yet commenced.
Hydro Resources, Inc. (HRI)
Inc. (HRI)            The license renewal review was placed in abeyance on License                November 13, 2014, while HRI continues its work with the Renewal                Navajo Nation Council. In March 2016 the NRC approved the transfer of control of the license from the HRI parent company, Uranium Resources, Inc., to Laramide Resources. The parties finalized the transaction in January 2017. The schedule for remaining milestones associated with the licensing review is to be determined.
License Renewal 06/24/13 The sites, located very close to Navajo Nation lands, were licensed in 1998. Construction has not yet commenced.
The license renewal review was placed in abeyance on November 13, 2014, while HRI continues its work with the Navajo Nation Council. In March 2016 the NRC approved the transfer of control of the license from the HRI parent company, Uranium Resources, Inc., to Laramide Resources. The parties finalized the transaction in January 2017. The schedule for remaining milestones associated with the licensing review is to be determined.
The projected total budget to conduct the review is 2.6 FTE.
The projected total budget to conduct the review is 2.6 FTE.
Kennecott 11/25/14   The licensee has maintained the facility in stand-by since Sweetwater            1983, waiting on better market conditions to resume License                operations. Environmental and safety reviews are in Renewal                progress. On October 18, 2016, the licensee submitted supplemental information related to groundwater detection monitoring. On November 14, 2016, the licensee submitted revised environmental information. The NRC staff issued RAIs to Kennecott on June 29, 2017, and received the licensees response on October 2, 2017.
Kennecott Sweetwater License Renewal 11/25/14 The licensee has maintained the facility in stand-by since 1983, waiting on better market conditions to resume operations. Environmental and safety reviews are in progress. On October 18, 2016, the licensee submitted supplemental information related to groundwater detection monitoring. On November 14, 2016, the licensee submitted revised environmental information. The NRC staff issued RAIs to Kennecott on June 29, 2017, and received the licensees response on October 2, 2017.
The staff plans to complete its SER in February 2018 and final EA in July 2018, and is on schedule to reach a licensing decision in August 2018.
The staff plans to complete its SER in February 2018 and final EA in July 2018, and is on schedule to reach a licensing decision in August 2018.
The projected total budget to conduct the review is 0.5 FTE.
The projected total budget to conduct the review is 0.5 FTE.  
23


Uranium         Application   Review Status and Projected Budget Recovery        Accepted Applicant        for Review Strata           01/14/16       On May 27, 2016, and September 14, 2016, the NRC staff Kendrick                        issued RAIs for the environmental review and for the Expansion                      safety review, respectively. On December 15, 2016, the licensee requested that the NRC cease all activities related to this review. As a result of the licensees request, the NRC staff is no longer reviewing this licensing action. The staffs safety and environmental reviews, including development of the Supplemental EIS, are on hold.
24 Uranium Recovery Applicant Application Accepted for Review Review Status and Projected Budget Strata Kendrick Expansion 01/14/16 On May 27, 2016, and September 14, 2016, the NRC staff issued RAIs for the environmental review and for the safety review, respectively. On December 15, 2016, the licensee requested that the NRC cease all activities related to this review. As a result of the licensees request, the NRC staff is no longer reviewing this licensing action. The staffs safety and environmental reviews, including development of the Supplemental EIS, are on hold.
The projected total budget to conduct the review is 3.5 FTE and $1500K, which includes completing the EIS.
The projected total budget to conduct the review is 3.5 FTE and $1500K, which includes completing the EIS.
Lost Creek       05/02/17       By letter dated February 27, 2017, the licensee KM                              resubmitted a revised application. The NRC staff has Horizon/East                    accepted the application for review on May 2, 2017. The Expansion                      NRC staff continues to coordinate with the BLM in its preparation of the EIS in accordance with the BLM/NRC MOU and the letter of December 4, 2014, designating BLM as the lead agency and NRC as a cooperating agency. BLM is scheduled to publish the final EIS in December 2018. The NRC staff is submitting its RAIs in batches in order to support BLMs schedule for issuing the EIS. The NRC staff issued its initial set of RAIs on July 27, 2017, its second set of RAIs on August 28, 2017, and its third set of RAIs on October 30, 2017. The final safety evaluation report is scheduled to be completed in August 2018.
Lost Creek KM Horizon/East Expansion 05/02/17 By {{letter dated|date=February 27, 2017|text=letter dated February 27, 2017}}, the licensee resubmitted a revised application. The NRC staff has accepted the application for review on May 2, 2017. The NRC staff continues to coordinate with the BLM in its preparation of the EIS in accordance with the BLM/NRC MOU and the letter of December 4, 2014, designating BLM as the lead agency and NRC as a cooperating agency. BLM is scheduled to publish the final EIS in December 2018. The NRC staff is submitting its RAIs in batches in order to support BLMs schedule for issuing the EIS. The NRC staff issued its initial set of RAIs on July 27, 2017, its second set of RAIs on August 28, 2017, and its third set of RAIs on October 30, 2017. The final safety evaluation report is scheduled to be completed in August 2018.
The projected total budget to conduct the review is 3.0 FTE.
The projected total budget to conduct the review is 3.0 FTE.
Cameco                         Three Crow is an expansion of the operating Crow Butte Three Crow                      facility located in Crawford, NE. The NRC staff started its Expansion                      acceptance review on March 3, 2011, and was waiting for the licensee to complete changes in its design prior to acceptance. However, in November 2014, the licensee requested that the NRC staff place the review on hold and instead focus efforts on the review of the Marsland expansion. The acceptance review remains on hold.
Cameco Three Crow Expansion Three Crow is an expansion of the operating Crow Butte facility located in Crawford, NE. The NRC staff started its acceptance review on March 3, 2011, and was waiting for the licensee to complete changes in its design prior to acceptance. However, in November 2014, the licensee requested that the NRC staff place the review on hold and instead focus efforts on the review of the Marsland expansion. The acceptance review remains on hold.
: 9. For minor uranium recovery licensing actions, please provide the following information each reporting period, including any months previously reported, in this format:
: 9. For minor uranium recovery licensing actions, please provide the following information each reporting period, including any months previously reported, in this format:
: a. Size of inventory;
: a. Size of inventory;
: b. Number of acceptance reviews completed on time;
: b. Number of acceptance reviews completed on time;
: c. The number of items completed in the period being reported; and
: c. The number of items completed in the period being reported; and
: d. Of the items completed in the reporting period, the number completed within the forecasted schedule.
: d. Of the items completed in the reporting period, the number completed within the forecasted schedule.  
24
 
25
: e. Please identify any unusually complex items omitted from the inventory and provide the age of the item, a brief description of the item, the justification for omitting it from the inventory size, and an explanation for any review exceeding its original schedule by 125 percent.
: e. Please identify any unusually complex items omitted from the inventory and provide the age of the item, a brief description of the item, the justification for omitting it from the inventory size, and an explanation for any review exceeding its original schedule by 125 percent.
Number of       Unusually Number of       Number of        Items          Complex Acceptance         Items        Completed          Items Reviews       Completed          Within          Omitted Size of    Completed         During      Forecasted          from Month/Year Inventory          on Time(1)         Month       Schedule(2)       Inventory Nov-2017         21           NA               2               1                 0 Dec-2017         21             1               0               0                 0 Jan-2018         22             1               1               1                 0 Notes:
Month/Year Size of Inventory Number of Acceptance Reviews Completed on Time(1)
Number of Items Completed During Month Number of Items Completed Within Forecasted Schedule(2)
Unusually Complex Items Omitted from Inventory Nov-2017 21 NA 2
1 0
Dec-2017 21 1
0 0
0 Jan-2018 22 1
1 1
0 Notes:
: 1. NA means no acceptance reviews were due.
: 1. NA means no acceptance reviews were due.
: 2. This column represents the total number of minor licensing actions completed within the staffs forecasted schedule in a particular month. At times, the uranium recovery staff has to divert resources from minor licensing actions to address oversight of operating sites, emergent issues, and major licensing actions. When this occurs, the NRC staff tries to accommodate the licensees priorities for completion of minor licensing actions.
: 2. This column represents the total number of minor licensing actions completed within the staffs forecasted schedule in a particular month. At times, the uranium recovery staff has to divert resources from minor licensing actions to address oversight of operating sites, emergent issues, and major licensing actions. When this occurs, the NRC staff tries to accommodate the licensees priorities for completion of minor licensing actions.
Line 313: Line 373:
The NRC and the Wyoming Department of Environmental Quality (DEQ) have worked closely to facilitate the timely completion of the Agreement through biweekly conference calls, in-person meetings, emails, and letters. As an interim step, the NRC staff, on July 5, 2016, requested Commission approval of the State of Wyomings proposed approach to submit a draft application for a limited agreement. Under this approach six Uranium Mill Tailings Radiation Control Act (UMTRCA) sites would have been transferred to Wyoming under the Agreement.
The NRC and the Wyoming Department of Environmental Quality (DEQ) have worked closely to facilitate the timely completion of the Agreement through biweekly conference calls, in-person meetings, emails, and letters. As an interim step, the NRC staff, on July 5, 2016, requested Commission approval of the State of Wyomings proposed approach to submit a draft application for a limited agreement. Under this approach six Uranium Mill Tailings Radiation Control Act (UMTRCA) sites would have been transferred to Wyoming under the Agreement.
On August 3, 2016, the Commission approved this approach in SRM-SECY-16-0084.
On August 3, 2016, the Commission approved this approach in SRM-SECY-16-0084.
On October 28, 2016, the State of Wyoming submitted a draft application for a limited agreement. The draft application proposed that the NRC retain jurisdiction over the six 25
On October 28, 2016, the State of Wyoming submitted a draft application for a limited agreement. The draft application proposed that the NRC retain jurisdiction over the six  


UMTRCA sites. In response to the draft application, the NRC staff had lengthy discussions with the State of Wyoming, after which the State of Wyoming proposed to include five UMTRCA sites in its final application. On August 16, 2017, the NRC staff recommended that the Commission approve the retention of NRCs regulatory authority over one of the six UMTRCA sites excluded in the State of Wyomings draft application (i.e., the American Nuclear Corporation (ANC) site in Gas Hills, Wyoming). On October 4, 2017, the Commission approved the staffs proposal in SRM-SECY-17-0081.
26 UMTRCA sites. In response to the draft application, the NRC staff had lengthy discussions with the State of Wyoming, after which the State of Wyoming proposed to include five UMTRCA sites in its final application. On August 16, 2017, the NRC staff recommended that the Commission approve the retention of NRCs regulatory authority over one of the six UMTRCA sites excluded in the State of Wyomings draft application (i.e., the American Nuclear Corporation (ANC) site in Gas Hills, Wyoming). On October 4, 2017, the Commission approved the staffs proposal in SRM-SECY-17-0081.
In parallel with resolving the jurisdiction of the six UMTRCA sites, the NRC staff provided comments to Wyoming DEQ on the draft application in an April 20, 2017, letter. On June 22, July 17, and August 16, 2017, Wyoming DEQ provided written responses to address NRCs comments.
In parallel with resolving the jurisdiction of the six UMTRCA sites, the NRC staff provided comments to Wyoming DEQ on the draft application in an {{letter dated|date=April 20, 2017|text=April 20, 2017, letter}}. On June 22, July 17, and August 16, 2017, Wyoming DEQ provided written responses to address NRCs comments.
On November 14, 2017, the State of Wyoming submitted its formal request for an Agreement.
On November 14, 2017, the State of Wyoming submitted its formal request for an Agreement.
The NRC staff continues to work with Wyoming DEQ to resolve the remaining issues related to the overall compatibility of the proposed program. The NRC staff is completing the assessment of the Wyoming Agreement State application and plans to request Commission approval to publish the draft agreement and staffs assessment for public comment in early spring 2018.
The NRC staff continues to work with Wyoming DEQ to resolve the remaining issues related to the overall compatibility of the proposed program. The NRC staff is completing the assessment of the Wyoming Agreement State application and plans to request Commission approval to publish the draft agreement and staffs assessment for public comment in early spring 2018.
Line 325: Line 385:
In fiscal year 2013, the NRC entered into an interagency agreement with the ACHP, under which the ACHP established a dedicated liaison to provide the NRC with technical assistance with Section 106 reviews of specific licensing actions, as well as relevant training and guidance.
In fiscal year 2013, the NRC entered into an interagency agreement with the ACHP, under which the ACHP established a dedicated liaison to provide the NRC with technical assistance with Section 106 reviews of specific licensing actions, as well as relevant training and guidance.
In June 2014, the NRC published its draft Interim Staff Guidance (ISG) for conducting the Section 106 process specific to uranium recovery licensing actions, Guidance for Conducting the Section 106 Process of the National Historic Preservation Act for Uranium Recovery Licensing Actions (FSME-ISG-02). Due to workload, resources, and other priorities, the NRC has had to delay completion of the ISG until calendar year 2018.
In June 2014, the NRC published its draft Interim Staff Guidance (ISG) for conducting the Section 106 process specific to uranium recovery licensing actions, Guidance for Conducting the Section 106 Process of the National Historic Preservation Act for Uranium Recovery Licensing Actions (FSME-ISG-02). Due to workload, resources, and other priorities, the NRC has had to delay completion of the ISG until calendar year 2018.
The NRC staff continues to attend and participate in the National Mining Associations (NMAs) annual uranium recovery workshops. The NRC staffs participation includes presentations or 26
The NRC staff continues to attend and participate in the National Mining Associations (NMAs) annual uranium recovery workshops. The NRC staffs participation includes presentations or  


panel discussions of the NRCs activities to carry out its NHPA Section 106 obligations, including challenges and potential solutions related to the NHPA Section 106 reviews.
27 panel discussions of the NRCs activities to carry out its NHPA Section 106 obligations, including challenges and potential solutions related to the NHPA Section 106 reviews.
To further improve the agencys NHPA and NEPA processes for licensing activities, the NRC has updated several documents regarding tribal consultation. The NRC published the final Tribal Policy Statement in the Federal Register on January 9, 2017 (82 FR 2402), and revised its Tribal Protocol Manual. The Tribal Protocol Manual is intended to facilitate effective consultations and interactions between the NRC and Tribes.
To further improve the agencys NHPA and NEPA processes for licensing activities, the NRC has updated several documents regarding tribal consultation. The NRC published the final Tribal Policy Statement in the Federal Register on January 9, 2017 (82 FR 2402), and revised its Tribal Protocol Manual. The Tribal Protocol Manual is intended to facilitate effective consultations and interactions between the NRC and Tribes.
Consistent with NRCs MOU with BLM, in FY 2017, the NRC staff continued its coordination of NEPA and NHPA Section 106 reviews related to such facilities that require an NRC license to possess and use source and byproduct materials, and are located on public lands under BLMs regulatory authority. The goal of the MOU is to limit, to the extent possible, duplication of consultation, review, and evaluation efforts on a project.
Consistent with NRCs MOU with BLM, in FY 2017, the NRC staff continued its coordination of NEPA and NHPA Section 106 reviews related to such facilities that require an NRC license to possess and use source and byproduct materials, and are located on public lands under BLMs regulatory authority. The goal of the MOU is to limit, to the extent possible, duplication of consultation, review, and evaluation efforts on a project.
Line 337: Line 397:
Concurrently, the staff began outreach to Agreement States with uranium recovery licensees to understand their fee schedule development process. The new data structure was deployed on October 1, 2017.
Concurrently, the staff began outreach to Agreement States with uranium recovery licensees to understand their fee schedule development process. The new data structure was deployed on October 1, 2017.
Near-Term:
Near-Term:
* The NRC staff will record time and attendance, which indicates the hours spent on specific work products, using the new data structure.
The NRC staff will record time and attendance, which indicates the hours spent on specific work products, using the new data structure.
* The NRC staff will continue to follow-up with the Agreement States in order to gain additional facts to inform the staffs analysis regarding a flat fee structure.
The NRC staff will continue to follow-up with the Agreement States in order to gain additional facts to inform the staffs analysis regarding a flat fee structure.  
27


Medium-Term:
28 Medium-Term:
* After a year of recording data using the new data structure, by November 1, 2018, the staff will begin analysis of the data to develop recommendations.
After a year of recording data using the new data structure, by November 1, 2018, the staff will begin analysis of the data to develop recommendations.
Long-Term:
Long-Term:
* Beginning in January 2019, the staff will engage with stakeholders to solicit for comments and concerns. The analysis and draft recommendations will be completed by the end of April 2019. The recommendations will be included in the FY 2020 fee rule SECY paper due to the Commission on August 15, 2019. These recommendations will continue to address requirements under the Omnibus Budget Reconciliation Act of 1990 to collect approximately 90 percent of the NRCs annual budget through fees, and under the Independent Offices Appropriation Act, 1952 to assess user fees that are fair and based on the costs to the government and certain other factors. The Commission is expected to report its decision to Congress by the end of December 2019. The FY 2020 proposed fee rule is expected to be published in January 2020. The FY 2020 final fee rule is expected to be published by May 2020 and would be effective 60 days thereafter.
Beginning in January 2019, the staff will engage with stakeholders to solicit for comments and concerns. The analysis and draft recommendations will be completed by the end of April 2019. The recommendations will be included in the FY 2020 fee rule SECY paper due to the Commission on August 15, 2019. These recommendations will continue to address requirements under the Omnibus Budget Reconciliation Act of 1990 to collect approximately 90 percent of the NRCs annual budget through fees, and under the Independent Offices Appropriation Act, 1952 to assess user fees that are fair and based on the costs to the government and certain other factors. The Commission is expected to report its decision to Congress by the end of December 2019. The FY 2020 proposed fee rule is expected to be published in January 2020. The FY 2020 final fee rule is expected to be published by May 2020 and would be effective 60 days thereafter.  
28


LICENSING
29 LICENSING
: 13. For operating reactors, new reactors, and uranium recovery licensees, please provide the following information regarding license amendment reviews:
: 13. For operating reactors, new reactors, and uranium recovery licensees, please provide the following information regarding license amendment reviews:
13.a     Please provide the following information for the current reporting period, including any information previously reported in the last six months:
13.a Please provide the following information for the current reporting period, including any information previously reported in the last six months:
: i. Size of inventory; ii. The number of items completed in the period being reported; iii. Percentage of acceptance reviews completed on time; iv. The percentage of these items completed within the forecasted schedule;
: i.
Size of inventory; ii. The number of items completed in the period being reported; iii. Percentage of acceptance reviews completed on time; iv. The percentage of these items completed within the forecasted schedule;
: v. The percentage of these items completed within 125 percent of the forecasted schedule; vi. The percentage of items completed within ten months; vii. The average age for items completed during the month being reported; viii. The ages of the quickest three items completed; and ix. The ages of the slowest three items completed.
: v. The percentage of these items completed within 125 percent of the forecasted schedule; vi. The percentage of items completed within ten months; vii. The average age for items completed during the month being reported; viii. The ages of the quickest three items completed; and ix. The ages of the slowest three items completed.
Operating Reactors Month/Year         Size of     No. of     Percentage     Percentage     Percentage    Percentage      Average    Ages of the   Ages of the Inventory      Items           of           of Items      of Items      of Items      Age for    Quickest        Slowest (Note 1)   Completed     Acceptance      Completed      Completed    Completed        Items    Three Items  Three Items in the      Reviews        within the    within 125%    within 10   Completed    Completed      Completed Report     Completed      Forecasted          of        Months        During      (months)       (months)
Operating Reactors Month/Year Size of Inventory (Note 1)
Period        on Time        Schedule      Forecasted                    Report (Note 2)      Schedule                      Period (Note 3)                  (months)
No. of Items Completed in the Report Period Percentage of Acceptance Reviews Completed on Time Percentage of Items Completed within the Forecasted Schedule (Note 2)
Nov-2017             588           46         100%             94%           94%           85%           6.9     <1 <1   <1   21   21 21 Dec-2017             579           93         100%             94%           94%           91%           9.2     <1 <1   1   12   12 12 Jan-2018             495         105         100%           100%           100%           84%           5.7     <1 <1   1   12   12 11 Note 1:       Similar to the licensing actions reported in the yearly CBJ, the inventory does not include unusually complex or Fukushima related licensing actions.
Percentage of Items Completed within 125%
Note 2:       Internal processes track licensing action completions within forecasted scheduled (+ 1 month) [this percentage does not include unusually complex or Fukushima related licensing actions].
of Forecasted Schedule (Note 3)
29
Percentage of Items Completed within 10 Months Average Age for Items Completed During Report Period (months)
Ages of the Quickest Three Items Completed (months)
Ages of the Slowest Three Items Completed (months)
Nov-2017 588 46 100%
94%
94%
85%
6.9  
<1
<1
<1 21 21 21 Dec-2017 579 93 100%
94%
94%
91%
9.2  
<1
<1 1
12 12 12 Jan-2018 495 105 100%
100%
100%
84%
5.7  
<1
<1 1
12 12 11 Note 1:
Similar to the licensing actions reported in the yearly CBJ, the inventory does not include unusually complex or Fukushima related licensing actions.
Note 2:
Internal processes track licensing action completions within forecasted scheduled (+ 1 month) [this percentage does not include unusually complex or Fukushima related licensing actions].  


Note 3:     Internal processes track licensing action completions within 125 percent of the forecasted schedule [this percentage does not include unusually complex or Fukushima related licensing actions].
30 Note 3:
New Reactors Average Percentage No. of     Percentage    Percentage                                       Age for of Items      Percentage                         Ages of the        Ages of the Items            of        of Items                                        Items Completed         of Items                           Quickest      Slowest Three Size of    Completed    Acceptance      Completed                                    Completed Month/Year                                                            within 125%     Completed                         Three Items            Items Inventory      in the      Reviews      within the                                      During of        within 10                         Completed          Completed Report     Completed      Forecasted                                      Report Forecasted        Months                            (months)           (months)
Internal processes track licensing action completions within 125 percent of the forecasted schedule [this percentage does not include unusually complex or Fukushima related licensing actions].
Period        on Time      Schedule                                        Period Schedule (months)
New Reactors Month/Year Size of Inventory No. of Items Completed in the Report Period Percentage of Acceptance Reviews Completed on Time Percentage of Items Completed within the Forecasted Schedule Percentage of Items Completed within 125%
Nov-2017         38             7           100%           86%           100%           100%             6.4         5   5     5     6       7     8 Dec-2017         35             4           75%           50%           100%           100%             4.5         2   4     5     4       5     7 Jan-2018         30             2           50%           50%           100%             50%             8.5         5   12   N/A   12       5   N/A Uranium Recovery Percent      Average Percentage Number of   Percentage     Percentage                 age of        Age for of Items Items            of        of Items                   Items        Items            Ages of the          Ages of the Completed Size of    Completed  Acceptance      Completed                  Comple      Completed         Quickest Three        Slowest Three Month/Year                                                          within 125%
of Forecasted Schedule Percentage of Items Completed within 10 Months Average Age for Items Completed During Report Period (months)
Inventory      in the      Reviews        within                     ted        during        Items Completed       Items Completed of Report     Completed      Forecasted                  within        Report              (months)             (months)
Ages of the Quickest Three Items Completed (months)
Forecasted Period      on Time      Schedule                      10        Period Schedule Months      (months)(1)
Ages of the Slowest Three Items Completed (months)
Nov-2017         24           2           N/A           50%         50%         50%           24.5         48(2)     1     N/A   48(2)     1     N/A Dec-2017         24           0             0           0%           0%           0%           N/A         N/A     N/A     N/A   N/A     N/A     N/A Jan-2018         25           1           100%         100%         100%         100%           10           10     N/A     N/A   10     N/A     N/A Note 1: The uranium recovery staffs goal is to complete major licensing actions within 36 months of acceptance and minor licensing actions within 12 months of acceptance. At times, the uranium recovery staff has to divert resources from minor 30
Nov-2017 38 7
100%
86%
100%
100%
6.4 5
5 5
6 7
8 Dec-2017 35 4
75%
50%
100%
100%
4.5 2
4 5
4 5
7 Jan-2018 30 2
50%
50%
100%
50%
8.5 5
12 N/A 12 5
N/A Uranium Recovery Month/Year Size of Inventory Number of Items Completed in the Report Period Percentage of Acceptance Reviews Completed on Time Percentage of Items Completed within Forecasted Schedule Percentage of Items Completed within 125%
of Forecasted Schedule Percent age of Items Comple ted within 10 Months Average Age for Items Completed during Report Period (months)(1)
Ages of the Quickest Three Items Completed (months)
Ages of the Slowest Three Items Completed (months)
Nov-2017 24 2
N/A 50%
50%
50%
24.5 48(2) 1 N/A 48(2) 1 N/A Dec-2017 24 0
0 0%
0%
0%
N/A N/A N/A N/A N/A N/A N/A Jan-2018 25 1
100%
100%
100%
100%
10 10 N/A N/A 10 N/A N/A Note 1: The uranium recovery staffs goal is to complete major licensing actions within 36 months of acceptance and minor licensing actions within 12 months of acceptance. At times, the uranium recovery staff has to divert resources from minor  


licensing actions to address oversight of operating sites, emergent issues, and major licensing actions. When this occurs, the NRC staff tries to accommodate the licensees priorities when determining which minor licensing actions to complete first.
31 licensing actions to address oversight of operating sites, emergent issues, and major licensing actions. When this occurs, the NRC staff tries to accommodate the licensees priorities when determining which minor licensing actions to complete first.
Note 2: One review of a minor licensing action completed in November 2017 required 48 months to complete. This review was low priority for the licensee; therefore, the uranium recovery staff focused on higher priority work until sufficient resources were available to complete the review.
Note 2: One review of a minor licensing action completed in November 2017 required 48 months to complete. This review was low priority for the licensee; therefore, the uranium recovery staff focused on higher priority work until sufficient resources were available to complete the review.
13.b   For the reporting period, please also provide the following for license amendment requests:
13.b For the reporting period, please also provide the following for license amendment requests:
: i. The number not accepted for review; and ii. A list of the requests that were withdrawn or denied after being accepted for review including the age of the request at the time it was withdrawn or denied.
: i.
Operating Reactors No. of License                                                 Age of the List the Requests that were Amendment                                                  Request at the Month/Year                                    Withdrawn or Denied after Requests Not                                                    Time it was Being Accepted for Review Accepted for Review                                              Withdrawn or Denied (months)
The number not accepted for review; and ii. A list of the requests that were withdrawn or denied after being accepted for review including the age of the request at the time it was withdrawn or denied.
Jan-2018                     8                             None                       N/A New Reactors No. of License List the Requests that were       Age of the Request at the Amendment Requests Month/Year                                        Withdrawn or Denied after        Time it was Withdrawn or Not Accepted for Being Accepted for Review                  Denied Review (months)
Operating Reactors Month/Year No. of License Amendment Requests Not Accepted for Review List the Requests that were Withdrawn or Denied after Being Accepted for Review Age of the Request at the Time it was Withdrawn or Denied (months)
Jan-2018                         0             Withdrawn: Vogtle Electric                         16 Generating Plant Units 3 and 4:
Jan-2018 8
Addition of Interim Amendment Process to license condition 2.D.(1) (LAR 16-015) 31
None N/A New Reactors Month/Year No. of License Amendment Requests Not Accepted for Review List the Requests that were Withdrawn or Denied after Being Accepted for Review Age of the Request at the Time it was Withdrawn or Denied (months)
Jan-2018 0
Withdrawn: Vogtle Electric Generating Plant Units 3 and 4:
Addition of Interim Amendment Process to license condition 2.D.(1) (LAR 16-015) 16


Uranium Recovery Number of Amendment         List of the Requests that were     Age of the Request at the Month/Year        Requests Not Accepted        Withdrawn or Denied after          Time it was Withdrawn or for Review                  being Accepted for Review          Denied (months)
32 Uranium Recovery Month/Year Number of Amendment Requests Not Accepted for Review List of the Requests that were Withdrawn or Denied after being Accepted for Review Age of the Request at the Time it was Withdrawn or Denied (months)
Jan-2018                       0                           None                               N/A 13.c Please identify items considered unusually complex items (e.g. criticality reviews, NFPA 805 reviews) and omitted from the
Jan-2018 0
None N/A 13.c Please identify items considered unusually complex items (e.g. criticality reviews, NFPA 805 reviews) and omitted from the
[licensing amendment] inventory including: the age of the item, a brief description of the item, the justification for omitting it from the inventory size and an explanation for any review exceeding its original schedule by 125 percent.
[licensing amendment] inventory including: the age of the item, a brief description of the item, the justification for omitting it from the inventory size and an explanation for any review exceeding its original schedule by 125 percent.
Operating Reactors Note:       Unusually complex license amendments are not included in the internal performance measures and their nature does not allow for realistic forecasted schedule development. Rather, they are given escalated management attention to ensure progress is being made towards resolving outstanding issues and completing the reviews in a timely manner.
Operating Reactors Note:
* Technical Specification Task Force (TSTF)-505 Reviews o
Unusually complex license amendments are not included in the internal performance measures and their nature does not allow for realistic forecasted schedule development. Rather, they are given escalated management attention to ensure progress is being made towards resolving outstanding issues and completing the reviews in a timely manner.
Technical Specification Task Force (TSTF)-505 Reviews o


== Description:==
== Description:==
These submittals request changes to Technical Specifications (TSs) for the adoption of Risk-Informed Technical Specification Task Force (RITSTF) Initiative 4b, specifically "TSTF-505 Revision 1, Provide Risk-Informed Extended Completion Times." This effort is associated with NEI 06-09, "Risk-Informed Technical Specifications Initiative 4b, Risk-Managed Technical Specifications Guidelines,"
These submittals request changes to Technical Specifications (TSs) for the adoption of Risk-Informed Technical Specification Task Force (RITSTF) Initiative 4b, specifically "TSTF-505 Revision 1, Provide Risk-Informed Extended Completion Times." This effort is associated with NEI 06-09, "Risk-Informed Technical Specifications Initiative 4b, Risk-Managed Technical Specifications Guidelines,"
o Justification: During review of the Vogtle pilot license amendment requests (LAR) for a risk-informed TS Completion time (RICT) program, a number of issues were raised by NRC staff. These issues resulted in the suspension of TSTF-505 to allow necessary revisions to the process. The NRC has been working with the TSTF group and other stakeholders to resolve the issues and lift the suspension. The five LARs currently under review are being reviewed on a plant-specific basis in parallel with revision of TSTF-505. Four of the five LARs have been supplemented to address the issues raised with TSTF-505. The supplements represent significant additional information and modifications to the licensee implementation of a RICT program. Although not a complete reset of the review, the additional information and changes to the LARs have added time to the review schedule and may result in the need for additional clarification requests. One licensee (Diablo Canyon) has yet to supplement its submittals to address the issues.
o Justification: During review of the Vogtle pilot license amendment requests (LAR) for a risk-informed TS Completion time (RICT) program, a number of issues were raised by NRC staff. These issues resulted in the suspension of TSTF-505 to allow necessary revisions to the process. The NRC has been working with the TSTF group and other stakeholders to resolve the issues and lift the suspension. The five LARs currently under review are being reviewed on a plant-specific basis in parallel with revision of TSTF-505. Four of the five LARs have been supplemented to address the issues raised with TSTF-505. The supplements represent significant additional information and modifications to the licensee implementation of a RICT program. Although not a complete reset of the review, the additional information and changes to the LARs have added time to the review schedule and may result in the need for additional clarification requests. One licensee (Diablo Canyon) has yet to supplement its submittals to address the issues.  
32


Current Reviews               Age (Months)
33 Current Reviews Age (Months)
Turkey Point Units 3 & 4               38 Saint Lucie Units 1 & 2               38 Calvert Cliffs Unit 1 & 2             24 Palo Verde Units 1, 2, & 3             31 Diablo Canyon Units 1 & 2               51
Turkey Point Units 3 & 4 38 Saint Lucie Units 1 & 2 38 Calvert Cliffs Unit 1 & 2 24 Palo Verde Units 1, 2, & 3 31 Diablo Canyon Units 1 & 2 51 National Fire Protection Association (NFPA) 805 Reviews o
* National Fire Protection Association (NFPA) 805 Reviews o


== Description:==
== Description:==
Line 394: Line 523:
Each submittal requesting implementation of NFPA 805 is over 1000 pages, requires five different technical disciplines to review, and has reviews staggered in an overlapping fashion. At any one time, 30 technical reviewers were active in the NFPA 805 LAR review process. Each NFPA 805 LAR requires at least one regulatory on-site audit; some required return regulatory audits to review on-site documentation and walk-down plant fire areas.
Each submittal requesting implementation of NFPA 805 is over 1000 pages, requires five different technical disciplines to review, and has reviews staggered in an overlapping fashion. At any one time, 30 technical reviewers were active in the NFPA 805 LAR review process. Each NFPA 805 LAR requires at least one regulatory on-site audit; some required return regulatory audits to review on-site documentation and walk-down plant fire areas.
o Justification: The NFPA 805 reviews are voluminous and technically challenging, have unique site-specific issues, have utilized unreviewed analysis methods (UAMs), and required additional response time for RAIs. Some licensees used UAMs that deviated from the acceptable NUREG/CR-6850 methods, and had to be reviewed in-depth by the staff for the first time. To resolve these UAMs, the licensees either perform a sensitivity analysis or redo their fire probabilistic risk assessment (PRA). Due to the complexity of these methods, a great deal of time is required for the staff to prepare initial RAIs, significant time may be required for licensees to provide responses, and several rounds of RAIs may be needed to resolve issues. In some cases, licensees required up to 180 days to respond to the more complex RAIs. This complexity adds greatly to the length of the review.
o Justification: The NFPA 805 reviews are voluminous and technically challenging, have unique site-specific issues, have utilized unreviewed analysis methods (UAMs), and required additional response time for RAIs. Some licensees used UAMs that deviated from the acceptable NUREG/CR-6850 methods, and had to be reviewed in-depth by the staff for the first time. To resolve these UAMs, the licensees either perform a sensitivity analysis or redo their fire probabilistic risk assessment (PRA). Due to the complexity of these methods, a great deal of time is required for the staff to prepare initial RAIs, significant time may be required for licensees to provide responses, and several rounds of RAIs may be needed to resolve issues. In some cases, licensees required up to 180 days to respond to the more complex RAIs. This complexity adds greatly to the length of the review.
Current Reviews             Age (Months)
Current Reviews Age (Months)
Davis-Besse Unit 1                 26
Davis-Besse Unit 1 26 Sequoyah Units 1 & 2 - Updated Final Safety Analysis Reports (UFSARs) Regarding Changes to Hydrologic Analysis o
* Sequoyah Units 1 & 2 - Updated Final Safety Analysis Reports (UFSARs) Regarding Changes to Hydrologic Analysis o


== Description:==
== Description:==
Tennessee Valley Authority (TVA or the licensee) submitted LARs on July 19, 2012, for Watts Bar, Unit 1, and August 10, 2012, for Sequoyah, Units 1 and 2, that proposed to revise the respective UFSAR, Section 2.4, Hydrologic Engineering, to reflect new probable maximum flood (PMF) levels and the associated changes.
Tennessee Valley Authority (TVA or the licensee) submitted LARs on July 19, 2012, for Watts Bar, Unit 1, and August 10, 2012, for Sequoyah, Units 1 and 2, that proposed to revise the respective UFSAR, Section 2.4, Hydrologic Engineering, to reflect new probable maximum flood (PMF) levels and the associated changes.
o Justification: The schedule has been challenged by issues with analysis and calculations, or reference to industry standards (e.g., Federal Energy Regulatory Commission, United States Army Corps of Engineers, and TVA River 33
o Justification: The schedule has been challenged by issues with analysis and calculations, or reference to industry standards (e.g., Federal Energy Regulatory Commission, United States Army Corps of Engineers, and TVA River  


Operations), that support the UFSAR changes using a factor of safety greater than 1.0 for sliding. The licensee has not resolved dam stability issues associated with these LARs. The LAR cannot be withdrawn since it is tied to a plant confirmatory action.
34 Operations), that support the UFSAR changes using a factor of safety greater than 1.0 for sliding. The licensee has not resolved dam stability issues associated with these LARs. The LAR cannot be withdrawn since it is tied to a plant confirmatory action.
o Current Age: 65 months
o Current Age: 65 months Saint Lucie Units 1 & 2 and McGuire Units 1 & 2 - Reactor Vessel Internals (RVI) Aging Management Plan License Renewal Commitment o
* Saint Lucie Units 1 & 2 and McGuire Units 1 & 2 - Reactor Vessel Internals (RVI) Aging Management Plan License Renewal Commitment o


== Description:==
== Description:==
Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guidelines, MRP-227-A, provides a generic program for aging management of pressurized water reactor (PWR) RVI. Many applicants made commitments during the license renewal process to implement the industry program (which became MRP-227-A) when it was completed. During calendar year 2012, the owners of seven PWRs, as part of their license renewal commitments, submitted Aging Management Programs (AMP) consistent with the MRP-227-A guidelines for RVI components and/or inspection plans.
Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guidelines, MRP-227-A, provides a generic program for aging management of pressurized water reactor (PWR) RVI. Many applicants made commitments during the license renewal process to implement the industry program (which became MRP-227-A) when it was completed. During calendar year 2012, the owners of seven PWRs, as part of their license renewal commitments, submitted Aging Management Programs (AMP) consistent with the MRP-227-A guidelines for RVI components and/or inspection plans.
o Justification: Since 2013, considerable progress has been made towards resolving technical issues related to the NRC review of the plant-specific MRP-227-A inspection plans. However, responding to the RAIs related to such items as cold-worked components and core design/fuel management requires review of the fabrication records, which are usually held by the original equipment manufacturer (OEM). There is a backlog of licensee requests for the OEM to provide this information, resulting in delays of several months to a year.
o Justification: Since 2013, considerable progress has been made towards resolving technical issues related to the NRC review of the plant-specific MRP-227-A inspection plans. However, responding to the RAIs related to such items as cold-worked components and core design/fuel management requires review of the fabrication records, which are usually held by the original equipment manufacturer (OEM). There is a backlog of licensee requests for the OEM to provide this information, resulting in delays of several months to a year.
Current Reviews               Age (Months)
Current Reviews Age (Months)
Saint Lucie Units 1 & 2               29 McGuire Units 1 & 2                   2
Saint Lucie Units 1 & 2 29 McGuire Units 1 & 2 2
* Palo Verde Units 1, 2 & 3 - Implementation of Next Generation Fuel (NGF) License Amendment Review and Exemption o
Palo Verde Units 1, 2 & 3 - Implementation of Next Generation Fuel (NGF) License Amendment Review and Exemption o


== Description:==
== Description:==
The licensee is requesting exemption from certain requirements of 10 CFR 50.46, Acceptance Criteria for Emergency Core Cooling Systems [ECCS] for Light-Water Nuclear Power Reactors, and 10 CFR Part 50, Appendix K, ECCS Evaluation Models, for the use of Optimized ZIRLOTM cladding.
The licensee is requesting exemption from certain requirements of 10 CFR 50.46, Acceptance Criteria for Emergency Core Cooling Systems [ECCS] for Light-Water Nuclear Power Reactors, and 10 CFR Part 50, Appendix K, ECCS Evaluation Models, for the use of Optimized ZIRLOTM cladding.
o Justification: The review is an extensive first-of-a-kind review of the application of several analysis methodologies that have not been previously approved by NRC staff. The verification of the analyses for full cores of NGF, and transition cores of NGF and existing fuel is a significantly time-consuming complex review.
o Justification: The review is an extensive first-of-a-kind review of the application of several analysis methodologies that have not been previously approved by NRC staff. The verification of the analyses for full cores of NGF, and transition cores of NGF and existing fuel is a significantly time-consuming complex review.
o Current Age: 19 months
o Current Age: 19 months Columbia Generating Station - Reclassification of Portions of Reactor Water Cleanup System  
* Columbia Generating Station - Reclassification of Portions of Reactor Water Cleanup System 34


o  
35 o


== Description:==
== Description:==
The licensee is requesting approval to revise the Quality Group designation for the piping, valves, pumps, and mechanical modules located in low temperature portions of the reactor water cleanup (RWCU) system, which is located in the radwaste building, from Quality Group C to Quality Group D.
The licensee is requesting approval to revise the Quality Group designation for the piping, valves, pumps, and mechanical modules located in low temperature portions of the reactor water cleanup (RWCU) system, which is located in the radwaste building, from Quality Group C to Quality Group D.
o Justification: No previous boiling-water reactor license amendment precedent exists for this reclassification; therefore, regulatory documentation and a basis from which to review and consider this amendment are not readily available.
o Justification: No previous boiling-water reactor license amendment precedent exists for this reclassification; therefore, regulatory documentation and a basis from which to review and consider this amendment are not readily available.
Collecting this documentation will take significant effort.
Collecting this documentation will take significant effort.
o Current Age: 18 months
o Current Age: 18 months Seabrook - Alkali-Silica Reaction (ASR) Licensing Basis Amendment o
* Seabrook - Alkali-Silica Reaction (ASR) Licensing Basis Amendment o


== Description:==
== Description:==
The licensee is requesting revising the current licensing basis to adopt a methodology for the analysis of seismic Category I structures with concrete affected by ASR.
The licensee is requesting revising the current licensing basis to adopt a methodology for the analysis of seismic Category I structures with concrete affected by ASR.
o Justification: Seabrook is the first US nuclear facility to exhibit ASR in concrete structures. As such, this LAR is a first-of-a-kind amendment to a plants licensing basis to include the effects of ASR. In addition, the LAR references licensee conducted research to justify an analysis methodology that has never been used before.
o Justification: Seabrook is the first US nuclear facility to exhibit ASR in concrete structures. As such, this LAR is a first-of-a-kind amendment to a plants licensing basis to include the effects of ASR. In addition, the LAR references licensee conducted research to justify an analysis methodology that has never been used before.
o Current Age: 18 months
o Current Age: 18 months Brunswick Units 1 & 2 - Maximum Extended Load Line Limit Analysis Plus (MELLLA)+ Core Flow Operating Range Expansion o
* Brunswick Units 1 & 2 - Maximum Extended Load Line Limit Analysis Plus (MELLLA)+ Core Flow Operating Range Expansion o


== Description:==
== Description:==
Line 438: Line 562:
o Justification: Due to the complexity of the subject, the review involves eight technical branches, and conducting Advisory Committee on Reactor Safeguards (ACRS) subcommittee and full committee meetings. The current proposed schedule for completing the review is approximately 18 to 20 months. The Monticello Nuclear Generating Plant was the first commercial plant to submit an LAR to adopt the MELLLA+ operating domain and required more than 4 years to complete.
o Justification: Due to the complexity of the subject, the review involves eight technical branches, and conducting Advisory Committee on Reactor Safeguards (ACRS) subcommittee and full committee meetings. The current proposed schedule for completing the review is approximately 18 to 20 months. The Monticello Nuclear Generating Plant was the first commercial plant to submit an LAR to adopt the MELLLA+ operating domain and required more than 4 years to complete.
Based on the considerations above, the Brunswick MELLLA+ LAR is especially voluminous.
Based on the considerations above, the Brunswick MELLLA+ LAR is especially voluminous.
o Current Age: 17 months
o Current Age: 17 months Shearon Harris Unit 1 - Spent Fuel Pool Criticality Analysis o
* Shearon Harris Unit 1 - Spent Fuel Pool Criticality Analysis o


== Description:==
== Description:==
The licensee is requesting to revise the TSs for fuel storage criticality to account for the use of Metamic neutron absorbing spent fuel pool rack inserts and soluble boron for the purpose of criticality control in the Boiling Water Reactor (BWR) storage racks that currently credit Boraflex. This license amendment request is required to resolve a current operable but degraded condition.
The licensee is requesting to revise the TSs for fuel storage criticality to account for the use of Metamic neutron absorbing spent fuel pool rack inserts and soluble boron for the purpose of criticality control in the Boiling Water Reactor (BWR) storage racks that currently credit Boraflex. This license amendment request is required to resolve a current operable but degraded condition.
o Justification: Precedents have shown that a review related to spent fuel pool criticality analyses is complex. Further, this review is considered a first-of-a-kind due to the unique configuration of the Shearon Harris spent fuel pool (SFP).
o Justification: Precedents have shown that a review related to spent fuel pool criticality analyses is complex. Further, this review is considered a first-of-a-kind due to the unique configuration of the Shearon Harris spent fuel pool (SFP).  
35


Specifically, the SFP configuration is the only one in the United States that contains both pressurized water reactor fuel racks and boiling water reactor fuel racks.
36 Specifically, the SFP configuration is the only one in the United States that contains both pressurized water reactor fuel racks and boiling water reactor fuel racks.
o   Current Age: 4 months
o Current Age: 4 months Point Beach Units 1 & 2 - Risk-Informed Approach to Resolve Construction Truss Design Code Non-conformances o
* Point Beach Units 1 & 2 - Risk-Informed Approach to Resolve Construction Truss Design Code Non-conformances o


== Description:==
== Description:==
The licensee is requesting approval of a risk-informed strategy to resolve low risk, legacy design code non-conformances associated with construction trusses in the containment building.
The licensee is requesting approval of a risk-informed strategy to resolve low risk, legacy design code non-conformances associated with construction trusses in the containment building.
o Justification: Established risk-informed applications follow endorsed guidance for the technical content that needs to be submitted. Such endorsed technical guidance is not available for this first-of-a-kind application and extra review effort is needed to determine the acceptability of the proposed technical approach.
o Justification: Established risk-informed applications follow endorsed guidance for the technical content that needs to be submitted. Such endorsed technical guidance is not available for this first-of-a-kind application and extra review effort is needed to determine the acceptability of the proposed technical approach.
o Current Age: 9 months New Reactors
o Current Age: 9 months New Reactors None.
* None.
Uranium Recovery None.
Uranium Recovery
* None.
13.d Please describe any steps taken to provide transparency into the progress of license amendment reviews, such as publicly available, real-time tracking of the completion of review schedule milestones.
13.d Please describe any steps taken to provide transparency into the progress of license amendment reviews, such as publicly available, real-time tracking of the completion of review schedule milestones.
Operating Reactors The routine interactions between licensees/applicants and the NRC project manager provide the same information, and possibly more insights, to a licensee regarding the status of an individual licensing review than would a tracking system. Therefore, the NRC does not consider such a tracking system necessary to facilitate these communications with licensees.
Operating Reactors The routine interactions between licensees/applicants and the NRC project manager provide the same information, and possibly more insights, to a licensee regarding the status of an individual licensing review than would a tracking system. Therefore, the NRC does not consider such a tracking system necessary to facilitate these communications with licensees.
Project managers and licensees have routine communications regarding the status and schedules of licensing actions. During these conversations, the schedules for each licensing action are discussed, including schedule expectations, when to expect requests for additional information, and when to expect the safety evaluation, if approved. In addition, the project managers and their direct supervisors are accessible to the licensees by phone or e-mail if any other issues arise.
Project managers and licensees have routine communications regarding the status and schedules of licensing actions. During these conversations, the schedules for each licensing action are discussed, including schedule expectations, when to expect requests for additional information, and when to expect the safety evaluation, if approved. In addition, the project managers and their direct supervisors are accessible to the licensees by phone or e-mail if any other issues arise.
The NRC staff will begin publishing monthly performance metrics on the NRC public website in the first quarter of 2018. While metrics do not provide insight into specific licensing amendment reviews, the metrics will provide information on the age of the existing inventory as a whole along with the number of reviews completed. Information will also be provided on average adherence to initial schedules and resource estimates.
The NRC staff will begin publishing monthly performance metrics on the NRC public website in the first quarter of 2018. While metrics do not provide insight into specific licensing amendment reviews, the metrics will provide information on the age of the existing inventory as a whole along with the number of reviews completed. Information will also be provided on average adherence to initial schedules and resource estimates.  
36


The NRC continues to refine its licensing process for operating reactors. Through the use of controls and metrics, the staff is currently meeting the Congressionally-reported metrics for the quantity of licensing actions reviewed annually, and the percentage of actions completed within one year. The NRC considers the current performance metrics appropriate to balance efficiency with safety. These measures recognize that schedule performance can be affected by applicant, licensee, or NRC performance, and may need fluidity to account for emerging safety or security issues, or changes in licensee plans.
37 The NRC continues to refine its licensing process for operating reactors. Through the use of controls and metrics, the staff is currently meeting the Congressionally-reported metrics for the quantity of licensing actions reviewed annually, and the percentage of actions completed within one year. The NRC considers the current performance metrics appropriate to balance efficiency with safety. These measures recognize that schedule performance can be affected by applicant, licensee, or NRC performance, and may need fluidity to account for emerging safety or security issues, or changes in licensee plans.
The NRC has launched several initiatives to focus on leveraging existing licensing processes to enhance efficiency, effectiveness, and predictability as a regulator, while maintaining a continued strong safety focus. For example, an initiative analyzed the issues that caused the backlog in processing amendment requests for reactor licensees, including issues related to the request for information (RAI) process, and provided recommendations to Office of Nuclear Reactor Regulation management regarding enhancements to the licensing review process. Such efforts resulted in reducing the inventory of licensing actions greater than one year old by more than 95 percent over the past years and enabled the staff to maintain this inventory at historically low levels. The staffs continual efforts in this area have significantly improved the NRCs ability to monitor safety reviews and improve predictability.
The NRC has launched several initiatives to focus on leveraging existing licensing processes to enhance efficiency, effectiveness, and predictability as a regulator, while maintaining a continued strong safety focus. For example, an initiative analyzed the issues that caused the backlog in processing amendment requests for reactor licensees, including issues related to the request for information (RAI) process, and provided recommendations to Office of Nuclear Reactor Regulation management regarding enhancements to the licensing review process. Such efforts resulted in reducing the inventory of licensing actions greater than one year old by more than 95 percent over the past years and enabled the staff to maintain this inventory at historically low levels. The staffs continual efforts in this area have significantly improved the NRCs ability to monitor safety reviews and improve predictability.
New Reactors For NRO license amendment reviews, only the final safety evaluation report (FSER) completion date is tracked as a milestone. In the amendment request, the licensee provides a date by which the amendment would need to be issued in order to facilitate the desired construction schedule. Occasionally, the staff works with the licensee to identify an alternate agreed-upon date, which is provided in a supplement or revision to the amendment request. These letters containing the requested or alternate agreed-upon date for the license amendment issuance are publicly available.
New Reactors For NRO license amendment reviews, only the final safety evaluation report (FSER) completion date is tracked as a milestone. In the amendment request, the licensee provides a date by which the amendment would need to be issued in order to facilitate the desired construction schedule. Occasionally, the staff works with the licensee to identify an alternate agreed-upon date, which is provided in a supplement or revision to the amendment request. These letters containing the requested or alternate agreed-upon date for the license amendment issuance are publicly available.
Uranium Recovery To ensure transparency in the process of licensing reviews, the NRCs uranium recovery staff provides the status of major licensing actions on the agencys public web page. For minor licensing actions, staff discusses these schedules during phone calls with licensees. In addition, for major licensing action reviews, the uranium recovery staff issues schedule letters at the beginning of each review and subsequent letters are issued, if the schedule changes.
Uranium Recovery To ensure transparency in the process of licensing reviews, the NRCs uranium recovery staff provides the status of major licensing actions on the agencys public web page. For minor licensing actions, staff discusses these schedules during phone calls with licensees. In addition, for major licensing action reviews, the uranium recovery staff issues schedule letters at the beginning of each review and subsequent letters are issued, if the schedule changes.  
37
 
38
: 14. For decommissioning transition reviews, please provide the following information for the reporting period, including any months previously reported:
: 14. For decommissioning transition reviews, please provide the following information for the reporting period, including any months previously reported:
: a. Size of inventory;
: a. Size of inventory;
Line 475: Line 594:
: e. Please identify any unusually complex items omitted from the inventory including:
: e. Please identify any unusually complex items omitted from the inventory including:
the age of the item, a brief description of the item, the justification for omitting it from the inventory size and an explanation for any review exceeding its original schedule by 125 percent.
the age of the item, a brief description of the item, the justification for omitting it from the inventory size and an explanation for any review exceeding its original schedule by 125 percent.
Decommissioning Transition Open Inventory and Closed Reviews Month                     Open Inventory Total              Closed Reviews Total (Note 1)
Decommissioning Transition Open Inventory and Closed Reviews Month Open Inventory Total (Note 1)
November 2017                           19                                   1 December 2017                           15                                   4 January 2018                           14                                   1 Note 1: The inventory includes licensing actions and other licensing tasks specifically related to an operating reactor plant transitioning into a decommissioning plant.
Closed Reviews Total November 2017 19 1
December 2017 15 4
January 2018 14 1
Note 1: The inventory includes licensing actions and other licensing tasks specifically related to an operating reactor plant transitioning into a decommissioning plant.
Information responsive to #14c-e is included in the response to #13 above.
Information responsive to #14c-e is included in the response to #13 above.
: 15. Please provide a list of Technical Specifications Task Force (TSTF) "travelers" under review, including the date filed, the milestone schedule for completing the review, and the estimated date for final agency action. Please provide an explanation for any review exceeding the original schedule by 125 percent.
: 15. Please provide a list of Technical Specifications Task Force (TSTF) "travelers" under review, including the date filed, the milestone schedule for completing the review, and the estimated date for final agency action. Please provide an explanation for any review exceeding the original schedule by 125 percent.
Traveler Under Review                                 Date Filed         Milestone         Estimated Schedule         Completion (Draft SE)         (Final SE)
Traveler Under Review Date Filed Milestone Schedule (Draft SE)
TSTF-567, Add Containment Sump TS to               03/30/2017         02/02/2018         04/04/2018 Address GSI-191 Issues TSTF-541. Add Exceptions to Surveillance           09/10/2013*       01/31/2019         07/31/2019 Requirements When the Safety Function is Being Performed TSTF-563, Revise Instrument Testing                 05/10/2017         03/03/2018         05/17/2018 Definitions to Incorporate the Surveillance Frequency Control Program TSTF-565, Clarify the Term Operational             05/10/2017         04/23/2018         07/31/2018 Convenience in the LCO 3.0.2 Bases TSTF-564, Safety Limit MCPR                       08/28/2017         05/30/2018         07/31/2018 TSTF-568, "Clarify Applicability of BWR/4           12/19/2017**            TBD                TBD TS 3.6.2.5 and TS 3.6.3.2" TSTF-557, Revision 1, "Spent Fuel Storage           12/19/2017**           TBD               TBD Rack Neutron Absorber Monitoring Program"
Estimated Completion (Final SE)
*Industry is currently drafting a revision for NRC review following a recent public meeting.
TSTF-567, Add Containment Sump TS to Address GSI-191 Issues 03/30/2017 02/02/2018 04/04/2018 TSTF-541. Add Exceptions to Surveillance Requirements When the Safety Function is Being Performed 09/10/2013*
01/31/2019 07/31/2019 TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program 05/10/2017 03/03/2018 05/17/2018 TSTF-565, Clarify the Term Operational Convenience in the LCO 3.0.2 Bases 05/10/2017 04/23/2018 07/31/2018 TSTF-564, Safety Limit MCPR 08/28/2017 05/30/2018 07/31/2018 TSTF-568, "Clarify Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2" 12/19/2017**
TBD TBD TSTF-557, Revision 1, "Spent Fuel Storage Rack Neutron Absorber Monitoring Program" 12/19/2017**
TBD TBD  
*Industry is currently drafting a revision for NRC review following a recent public meeting.  
**NRC staff is performing the acceptance review and developing the review schedule.
**NRC staff is performing the acceptance review and developing the review schedule.
None of the reviews exceeded the original schedule by 125 percent.
None of the reviews exceeded the original schedule by 125 percent.  
38
 
: 16.       Please describe the actions planned and/or taken to ensure that the TSTF traveler process achieves the regulatory efficiencies that were initially projected. Please include progress reports with regard to any TSTF travelers adopted by the industry.
39
: 16. Please describe the actions planned and/or taken to ensure that the TSTF traveler process achieves the regulatory efficiencies that were initially projected. Please include progress reports with regard to any TSTF travelers adopted by the industry.
Industry, through the TSTF, proposes changes to the Standard Technical Specifications (STS) via a traveler submitted for NRC review and approval. The traveler process was collaboratively developed between NRC and the nuclear industry 20 years ago as a means to revise the STS to gain regulatory efficiencies and enhance safety. Since then, the NRC has approved over 340 travelers, and has a mature process for review and approval of plant-specific license amendment requests to adopt approved STS changes.
Industry, through the TSTF, proposes changes to the Standard Technical Specifications (STS) via a traveler submitted for NRC review and approval. The traveler process was collaboratively developed between NRC and the nuclear industry 20 years ago as a means to revise the STS to gain regulatory efficiencies and enhance safety. Since then, the NRC has approved over 340 travelers, and has a mature process for review and approval of plant-specific license amendment requests to adopt approved STS changes.
Over the last several years NRC introduced two enhancements to the traveler review process:
Over the last several years NRC introduced two enhancements to the traveler review process:
Line 492: Line 619:
In 2017, two travelers were approved by the NRC. Currently seven travelers are under review by the NRC staff. The latest status report of travelers currently under review is available (ADAMS Accession No. ML17317A424).
In 2017, two travelers were approved by the NRC. Currently seven travelers are under review by the NRC staff. The latest status report of travelers currently under review is available (ADAMS Accession No. ML17317A424).
: 17. For each ongoing license renewal review, please provide the date each application was filed, the duration of the review, the original milestone schedule based on 22 months for uncontested applications and 30 months for contested applications, the actual completion dates for milestones, and the scheduled date for completion of the review. Please provide an explanation for any review exceeding the original schedule by 125 percent.
: 17. For each ongoing license renewal review, please provide the date each application was filed, the duration of the review, the original milestone schedule based on 22 months for uncontested applications and 30 months for contested applications, the actual completion dates for milestones, and the scheduled date for completion of the review. Please provide an explanation for any review exceeding the original schedule by 125 percent.
Indian Point 2&3 Application Review Time from Acceptance Review Date (Months)                                   125 Original       Current   Completion Milestone Schedule        Schedule        Date License Renewal Application Receipt                         04/30/2007                   04/30/2007 Publish FRN-Acceptance/rejection and opportunity 08/01/2007                   08/01/2007 for hearing Public Meeting - Environmental Scoping                       09/19/2007                   09/19/2007 Issue draft Supplemental Environmental Impact 07/25/2008                   12/22/2008 Statement (SEIS)
Indian Point 2&3 Application Review Time from Acceptance Review Date (Months) 125 Milestone Original Schedule Current Schedule Completion Date License Renewal Application Receipt 04/30/2007 04/30/2007 Publish FRN-Acceptance/rejection and opportunity for hearing 08/01/2007 08/01/2007 Public Meeting - Environmental Scoping 09/19/2007 09/19/2007 Issue draft Supplemental Environmental Impact Statement (SEIS) 07/25/2008 12/22/2008 Issue SER with open items 09/05/2008 01/15/2009 1st ACRS Subcommittee meeting 10/2008 03/18/2009  
Issue SER with open items                                   09/05/2008                   01/15/2009 1 ACRS Subcommittee meeting st                                                          10/2008                     03/18/2009 39


Indian Point 2&3 Application Review Time from Acceptance Review Date (Months)                             125 Original     Current     Completion Milestone Schedule      Schedule        Date Issue final SER                                           03/27/2009                 08/11/2009 ACRS Full Committee meeting                                 05/2009                   09/10/2009 Issue final SEIS                                         04/03/2009                 12/03/2010 1st Supplement to SER                                         N/A*                   08/30/2011 Issue Draft 1 Supplement to final SEIS st                                              N/A*                   06/26/2012 Issue Final 1st Supplement to final SEIS                     N/A*                   06/13/2013 FRN - Notice of Intent to Prepare Supplemental N/A*                   09/04/2014 Environmental Impact Statement 2nd ACRS Subcommittee meeting                                 N/A*                   04/23/2015 Issue 2nd Supplement to SER                                   N/A*                   07/07/2015 Issue Draft 2nd Supplement to final SEIS                     N/A*       01/2016     12/22/2015 End of Comment Period for Draft 2nd Supplement to final supplemental environmental impact                   N/A*       03/2016     03/04/2016 statement (FSEIS)
40 Indian Point 2&3 Application Review Time from Acceptance Review Date (Months) 125 Milestone Original Schedule Current Schedule Completion Date Issue final SER 03/27/2009 08/11/2009 ACRS Full Committee meeting 05/2009 09/10/2009 Issue final SEIS 04/03/2009 12/03/2010 1st Supplement to SER N/A*
Issue Final 2nd Supplement to FSEIS                           N/A*       03/2018 Issue 3rd Supplement to SER                                   N/A*       04/2018 Decision-Director, NRR (no hearing)                         07/2009       09/2018 Commission decision (if hearing is granted)                   TBD           N/A
08/30/2011 Issue Draft 1st Supplement to final SEIS N/A*
06/26/2012 Issue Final 1st Supplement to final SEIS N/A*
06/13/2013 FRN - Notice of Intent to Prepare Supplemental Environmental Impact Statement N/A*
09/04/2014 2nd ACRS Subcommittee meeting N/A*
04/23/2015 Issue 2nd Supplement to SER N/A*
07/07/2015 Issue Draft 2nd Supplement to final SEIS N/A*
01/2016 12/22/2015 End of Comment Period for Draft 2nd Supplement to final supplemental environmental impact statement (FSEIS)
N/A*
03/2016 03/04/2016 Issue Final 2nd Supplement to FSEIS N/A*
03/2018 Issue 3rd Supplement to SER N/A*
04/2018 Decision-Director, NRR (no hearing) 07/2009 09/2018 Commission decision (if hearing is granted)
TBD N/A  
*The NRC did not issue an official schedule for the first supplement to the final SEIS.
*The NRC did not issue an official schedule for the first supplement to the final SEIS.
The Indian Point License Renewal Application schedule letters are publicly available in ADAMS at Accession Nos. ML071900365, ML080230115, ML081000441, ML082400214, ML100110063, ML101260536, ML102300092, ML14254A207, ML15147A199 and ML16153A351.
The Indian Point License Renewal Application schedule letters are publicly available in ADAMS at Accession Nos. ML071900365, ML080230115, ML081000441, ML082400214, ML100110063, ML101260536, ML102300092, ML14254A207, ML15147A199 and ML16153A351.
The delays in the review of the Indian Point application were associated with complex adjudicatory issues, audits, reviews of substantial new information submitted by the licensee, review of the severe accident mitigation alternatives (SAMA) analyses and review of extensive public comments on NRC staff environmental review documents. In 2012, the issuance of renewed licenses was suspended pending completion of the continued storage rulemaking; the licensing reviews continued to move forward. On August 26, 2014, the Continued Storage rule was approved and the Commission lifted the suspension on issuing renewed licenses. The parties to the legal proceedings reached an agreement that resulted in the withdrawal of all contentions on the license renewal application. Thus on March 13, 2017, all pending adjudicatory actions were voluntarily dismissed. A decision regarding the renewal of the operating licenses for both units is expected to be issued in the 4th quarter of FY 2018.
The delays in the review of the Indian Point application were associated with complex adjudicatory issues, audits, reviews of substantial new information submitted by the licensee, review of the severe accident mitigation alternatives (SAMA) analyses and review of extensive public comments on NRC staff environmental review documents. In 2012, the issuance of renewed licenses was suspended pending completion of the continued storage rulemaking; the licensing reviews continued to move forward. On August 26, 2014, the Continued Storage rule was approved and the Commission lifted the suspension on issuing renewed licenses. The parties to the legal proceedings reached an agreement that resulted in the withdrawal of all contentions on the license renewal application. Thus on March 13, 2017, all pending adjudicatory actions were voluntarily dismissed. A decision regarding the renewal of the operating licenses for both units is expected to be issued in the 4th quarter of FY 2018.
Diablo Canyon 1 & 2 Application Review Time from Acceptance Review Date (Months)                                     77 Original     Completion Milestone Schedule          Date License Renewal Application Receipt                                     11/23/2009     11/23/2009 Publish FRN-Acceptance/rejection and opportunity for hearing           01/21/2010     01/21/2010 Public Meeting- Environmental Scoping meeting                           03/03/2010     03/03/2010 Deadline for filing hearing requests and petitions for intervention     03/22/2010     03/22/2010 Issue draft SEIS                                                       10/15/2010 Issue SER with Open Items                                               12/10/2010     01/10/2011 40
Diablo Canyon 1 & 2 Application Review Time from Acceptance Review Date (Months) 77 Milestone Original Schedule Completion Date License Renewal Application Receipt 11/23/2009 11/23/2009 Publish FRN-Acceptance/rejection and opportunity for hearing 01/21/2010 01/21/2010 Public Meeting-Environmental Scoping meeting 03/03/2010 03/03/2010 Deadline for filing hearing requests and petitions for intervention 03/22/2010 03/22/2010 Issue draft SEIS 10/15/2010 Issue SER with Open Items 12/10/2010 01/10/2011  


Diablo Canyon 1 & 2 Application Review Time from Acceptance Review Date (Months)                                     77 Original     Completion Milestone Schedule          Date ACRS Subcommittee meeting                                                 02/2011       02/09/2011 Request by applicant for delay in final processing of the license 04/10/2011 renewal review Issue final SER                                                       05/23/2011       06/02/2011 ACRS Full Committee meeting                                               07/2011 Issue final SEIS                                                       08/12/2011 NRR Director Decision (no hearing)                                     09/26/2011 Commission Decision (if hearing is granted)                           05/25/2012 NRC Letter to Pacific Gas and Electric (PG&E) regarding information to be submitted if the license renewal review process                       05/02/2014 where to restart PG&E letter to NRC to inform that PG&E will provide some information in December 2014 and will coordinate with NRC later to                     06/04/2014 discuss a schedule for providing additional information.
41 Diablo Canyon 1 & 2 Application Review Time from Acceptance Review Date (Months) 77 Milestone Original Schedule Completion Date ACRS Subcommittee meeting 02/2011 02/09/2011 Request by applicant for delay in final processing of the license renewal review 04/10/2011 Issue final SER 05/23/2011 06/02/2011 ACRS Full Committee meeting 07/2011 Issue final SEIS 08/12/2011 NRR Director Decision (no hearing) 09/26/2011 Commission Decision (if hearing is granted) 05/25/2012 NRC Letter to Pacific Gas and Electric (PG&E) regarding information to be submitted if the license renewal review process where to restart 05/02/2014 PG&E letter to NRC to inform that PG&E will provide some information in December 2014 and will coordinate with NRC later to discuss a schedule for providing additional information.
PG&E submitted an annual update for the license renewal 12/22/2014 application PG&E submits a revised Environmental Report                                             02/25/2015 Publish FRN-of Notice of Intent to reinitiate the Scoping Process         07/2015       07/2015 and Prepare an Environmental Impact Statement Public Meeting-Environmental Scoping meeting                             08/2015       08/05/2015 PG&E letter to NRC request to suspend NRC review                                       06/21/2016 NRC letter to PG&E, response to request to suspend license                             07/18/2016 renewal application review Following the California Public Utility Commission decision on the PG&E Diablo Canyon closure proposal (issued 1/11/18), PG&E will         Early 2018 notify the NRC The Diablo Canyon license renewal application schedule letters are publicly available in ADAMS at Accession Nos. ML093631560, ML102700490, ML110140904, ML11138A315, ML15104A509, and ML16193A599.
06/04/2014 PG&E submitted an annual update for the license renewal application 12/22/2014 PG&E submits a revised Environmental Report 02/25/2015 Publish FRN-of Notice of Intent to reinitiate the Scoping Process and Prepare an Environmental Impact Statement 07/2015 07/2015 Public Meeting-Environmental Scoping meeting 08/2015 08/05/2015 PG&E letter to NRC request to suspend NRC review 06/21/2016 NRC letter to PG&E, response to request to suspend license renewal application review 07/18/2016 Following the California Public Utility Commission decision on the PG&E Diablo Canyon closure proposal (issued 1/11/18), PG&E will notify the NRC Early 2018 The Diablo Canyon license renewal application schedule letters are publicly available in ADAMS at Accession Nos. ML093631560, ML102700490, ML110140904, ML11138A315, ML15104A509, and ML16193A599.
In October 2010, the schedule was updated to allow the staff additional time to complete a thorough review of the SAMA analyses and of the effects to marine ecology. In April 2011, PG&E requested the deferral of a final decision on the license renewal application until seismic studies were completed. In 2012, the issuance of renewed licenses was suspended pending completion of the continued storage rulemaking. On August 26, 2014, the Continued Storage rule was approved and the Commission lifted the suspension on issuing renewed licenses. The NRC staff resumed the review after PG&E submitted the annual update for the application in December 2014. Subsequently in June 2016, PG&E requested the NRC suspend the review and also requested approval from the California Public Utilities Commission (CPUC) not to proceed with license renewal. In July 2016, the NRC suspended the license renewal review.
In October 2010, the schedule was updated to allow the staff additional time to complete a thorough review of the SAMA analyses and of the effects to marine ecology. In April 2011, PG&E requested the deferral of a final decision on the license renewal application until seismic studies were completed. In 2012, the issuance of renewed licenses was suspended pending completion of the continued storage rulemaking. On August 26, 2014, the Continued Storage rule was approved and the Commission lifted the suspension on issuing renewed licenses. The NRC staff resumed the review after PG&E submitted the annual update for the application in December 2014. Subsequently in June 2016, PG&E requested the NRC suspend the review and also requested approval from the California Public Utilities Commission (CPUC) not to proceed with license renewal. In July 2016, the NRC suspended the license renewal review.
The CPUC held a public meeting on January 11, 2018, where the CPUC approved PG&Es proposal to close Diablo Canyon in 2025. PG&E is expected to provide an update on its plans regarding withdrawal of the license renewal application; however, PG&E has not yet informed NRC of the projected submittal date.
The CPUC held a public meeting on January 11, 2018, where the CPUC approved PG&Es proposal to close Diablo Canyon in 2025. PG&E is expected to provide an update on its plans regarding withdrawal of the license renewal application; however, PG&E has not yet informed NRC of the projected submittal date.  
41


Seabrook 1 Application Review Time from Acceptance Review Date (Months)                           90 Original           Current     Completion Milestone Schedule          Schedule        Date License Renewal Application Receipt               06/01/2010                       06/01/2010 Publish FRN-Acceptance/rejection and 07/23/2010                       07/21/2010 opportunity for hearing Public Meeting- Environmental Scoping 08/19/2010                       08/19/2010 meeting Deadline for filing hearing requests and 09/21/2010                       10/20/2010 petitions for intervention Issue draft SEIS                                   05/13/11                       08/01/2011 Issue SER with open items                           07/2011                       06/08/2012 1st ACRS Subcommittee meeting                       09/2011                       07/10/2012 Issue 2nd draft SEIS                                 12/2012                       04/22/2013 Issue final SEIS                                   01/07/2012                       07/29/2015 2nd ACRS Subcommittee meeting                         N/A Issue final SER                                     01/2012 ACRS full committee meeting                         02/2012 NRR Director Decision (no hearing)                 04/02/2012         04/2019 Commission Decision (if hearing is granted)       12/03/2012           NA The Seabrook LRA schedule letters are publicly available in ADAMS at Accession Nos.
42 Seabrook 1 Application Review Time from Acceptance Review Date (Months) 90 Milestone Original Schedule Current Schedule Completion Date License Renewal Application Receipt 06/01/2010 06/01/2010 Publish FRN-Acceptance/rejection and opportunity for hearing 07/23/2010 07/21/2010 Public Meeting-Environmental Scoping meeting 08/19/2010 08/19/2010 Deadline for filing hearing requests and petitions for intervention 09/21/2010 10/20/2010 Issue draft SEIS 05/13/11 08/01/2011 Issue SER with open items 07/2011 06/08/2012 1st ACRS Subcommittee meeting 09/2011 07/10/2012 Issue 2nd draft SEIS 12/2012 04/22/2013 Issue final SEIS 01/07/2012 07/29/2015 2nd ACRS Subcommittee meeting N/A Issue final SER 01/2012 ACRS full committee meeting 02/2012 NRR Director Decision (no hearing) 04/02/2012 04/2019 Commission Decision (if hearing is granted) 12/03/2012 NA The Seabrook LRA schedule letters are publicly available in ADAMS at Accession Nos.
ML101690417, ML110890319, ML11178A365, ML12074A096, ML12109A427, ML12352A075, ML13298A091, ML14148A218, ML14223B144, ML15041A449, ML15107A300, ML15293A157 and ML16074A246.
ML101690417, ML110890319, ML11178A365, ML12074A096, ML12109A427, ML12352A075, ML13298A091, ML14148A218, ML14223B144, ML15041A449, ML15107A300, ML15293A157 and ML16074A246.
In 2011, the Seabrook schedule was updated to ensure that the applicant properly addressed SAMA analysis and technical issues related to the alkali silica reaction (ASR) of concrete. In 2012, subsequent to the NRC staff issuing the draft SEIS, the applicant made significant changes to the SAMA. Additional, in 2012, the issuance of new licenses was suspended pending completion of the Continued Storage rulemaking; the licensing reviews continued to move forward. The second draft SEIS was issued in April 2013 and in August 2013 an agreement regarding a contention associated with the SEIS was reached. On August 26, 2014, the Continued Storage rule was approved and the Commission lifted the suspension on issuing renewed licenses. The NRC staff issued the final SEIS in 2015.
In 2011, the Seabrook schedule was updated to ensure that the applicant properly addressed SAMA analysis and technical issues related to the alkali silica reaction (ASR) of concrete. In 2012, subsequent to the NRC staff issuing the draft SEIS, the applicant made significant changes to the SAMA. Additional, in 2012, the issuance of new licenses was suspended pending completion of the Continued Storage rulemaking; the licensing reviews continued to move forward. The second draft SEIS was issued in April 2013 and in August 2013 an agreement regarding a contention associated with the SEIS was reached. On August 26, 2014, the Continued Storage rule was approved and the Commission lifted the suspension on issuing renewed licenses. The NRC staff issued the final SEIS in 2015.
In August 2016, NextEra submitted a LAR to the current license to adopt a methodology for the analysis of seismic Category I structures with concrete affected by ASR. This methodology is the basis for the aging management program being evaluated for the license renewal application review. On October 6, 2017, the ASLB admitted a contention on the ASR LAR.
In August 2016, NextEra submitted a LAR to the current license to adopt a methodology for the analysis of seismic Category I structures with concrete affected by ASR. This methodology is the basis for the aging management program being evaluated for the license renewal application review. On October 6, 2017, the ASLB admitted a contention on the ASR LAR.
After the NRC staff completes safety evaluation of the ASR LAR, the ASLB hearing will be held and the ACRS will also perform its review. The review of this amendment has a direct impact on the schedule for the license renewal review and a decision on the license renewal is currently projected to be made by April 2019.
After the NRC staff completes safety evaluation of the ASR LAR, the ASLB hearing will be held and the ACRS will also perform its review. The review of this amendment has a direct impact on the schedule for the license renewal review and a decision on the license renewal is currently projected to be made by April 2019.
Waterford 3 Application Review Time from Acceptance Review Date (Months)                           19 Original         Current     Completion Milestone Schedule        Schedule          Date License Renewal Application Receipt               03/23/2016                     03/23/2016 42
Waterford 3 Application Review Time from Acceptance Review Date (Months) 19 Milestone Original Schedule Current Schedule Completion Date License Renewal Application Receipt 03/23/2016 03/23/2016  


Waterford 3 Application Review Time from Acceptance Review Date (Months)                         19 Original       Current   Completion Milestone Schedule      Schedule        Date Publish FRN-Acceptance/rejection and 05/20/2016                   05/20/2016 opportunity for hearing Public Meeting- Environmental Scoping 06/08/2016                   06/08/2016 meeting Deadline for filing hearing requests and 08/01/2016                   08/01/2016 petitions for intervention Issue draft SEIS                                       05/2017       02/2018 Issue SER with open-items                             06/2017       09/2018 ACRS Subcommittee meeting                             07/2017       10/2018 Issue final SEIS                                       03/2018       05/2018 Issue final SER                                       01/2018       03/2019 ACRS full committee meeting                           03/2018       04/2019 NRR Director Decision (no hearing)                     04/2018       06/2019 Commission Decision (if hearing is granted)             TBD             N/A The Waterford License Renewal Application schedule letters are publicly available in ADAMS at Accession Nos. ML16130A023 and ML17131A194.
43 Waterford 3 Application Review Time from Acceptance Review Date (Months) 19 Milestone Original Schedule Current Schedule Completion Date Publish FRN-Acceptance/rejection and opportunity for hearing 05/20/2016 05/20/2016 Public Meeting-Environmental Scoping meeting 06/08/2016 06/08/2016 Deadline for filing hearing requests and petitions for intervention 08/01/2016 08/01/2016 Issue draft SEIS 05/2017 02/2018 Issue SER with open-items 06/2017 09/2018 ACRS Subcommittee meeting 07/2017 10/2018 Issue final SEIS 03/2018 05/2018 Issue final SER 01/2018 03/2019 ACRS full committee meeting 03/2018 04/2019 NRR Director Decision (no hearing) 04/2018 06/2019 Commission Decision (if hearing is granted)
TBD N/A The Waterford License Renewal Application schedule letters are publicly available in ADAMS at Accession Nos. ML16130A023 and ML17131A194.
The NRC staff continues work on the Waterford safety and environmental reviews. The applicant submitted an LAR in November 2017 that requests approval of their plant-specific neutron fluence methodology that is applied to the reactor vessel neutron fluence embrittlement analysis referred to in the license renewal application. The LAR acceptance review has been completed and the NRC staff safety review is currently underway. The review of the LAR is estimated to take approximately 1 year. The license renewal application fluence methodology review is dependent on the approval of the LAR. Therefore, the decision regarding the renewal of the operating license is expected to be issued in 3rd quarter of FY 2019.
The NRC staff continues work on the Waterford safety and environmental reviews. The applicant submitted an LAR in November 2017 that requests approval of their plant-specific neutron fluence methodology that is applied to the reactor vessel neutron fluence embrittlement analysis referred to in the license renewal application. The LAR acceptance review has been completed and the NRC staff safety review is currently underway. The review of the LAR is estimated to take approximately 1 year. The license renewal application fluence methodology review is dependent on the approval of the LAR. Therefore, the decision regarding the renewal of the operating license is expected to be issued in 3rd quarter of FY 2019.
River Bend Application Review Time from Acceptance Review Date (Months)                               5 Original       Completion Milestone Schedule            Date License Renewal Application Receipt                           05/31/2017       05/31/2017 Publish FRN-Acceptance/rejection and opportunity for 08/2017         08/17/2017 hearing Public Meeting- Environmental Scoping meeting                   09/2017         09/19/2017 Deadline for filing hearing requests and petitions for 10/2017         10/13/2017 intervention Issue draft SEIS                                                 04/2018 Issue final SER                                                 07/2018 ACRS Subcommittee meeting                                       10/2018 Issue final SEIS                                                 11/2018 ACRS full committee meeting                                     12/2018 NRR Director Decision (no hearing)                               02/2019 Commission Decision (if hearing is granted)                       TBD 43
River Bend Application Review Time from Acceptance Review Date (Months) 5 Milestone Original Schedule Completion Date License Renewal Application Receipt 05/31/2017 05/31/2017 Publish FRN-Acceptance/rejection and opportunity for hearing 08/2017 08/17/2017 Public Meeting-Environmental Scoping meeting 09/2017 09/19/2017 Deadline for filing hearing requests and petitions for intervention 10/2017 10/13/2017 Issue draft SEIS 04/2018 Issue final SER 07/2018 ACRS Subcommittee meeting 10/2018 Issue final SEIS 11/2018 ACRS full committee meeting 12/2018 NRR Director Decision (no hearing) 02/2019 Commission Decision (if hearing is granted)
TBD  


The River Bend license renewal application review schedule is available in ADAMS at Accession No. ML17187A035.
44 The River Bend license renewal application review schedule is available in ADAMS at Accession No. ML17187A035.
: 18. Please provide the status of ongoing license renewal reviews.
: 18. Please provide the status of ongoing license renewal reviews.
Application Accepted Applicant                            Review Status for Long-Term Application Reviews for Review Indian Point   08/01/2007     The NRC staff has addressed the public comments received on its 2&3                      draft second supplement to the FSEIS, which was issued for comment in December 2015. The staffs response to the public comments will be documented in the FSEIS supplement, which is currently under final review. The initial SER was issued in November 2009, with supplements issued in August 2011 and July 2015. A third SER supplement will be issued in the second quarter of FY 2018 to address new information received by the staff concerning safety issues. In January 2017, the parties to the legal proceedings reached an agreement that resulted in the withdrawal of all contentions on the license renewal application. Under the agreement, Units 2 & 3 will cease operations in April 2020 and 2021, respectively, with possible extensions to operate until April 2024 and 2025, respectively. On February 8, 2017, the State of New York Department of Environmental Conservation (NYDEC) and Riverkeeper filed an unopposed motion to the ASLB to withdraw their contentions and terminate the adjudicatory proceeding. The Licensing Board granted that motion and terminated the adjudicatory proceeding on March 13, 2017. Recently the National Marine Fisheries Service (NMFS) designated critical habitat in the Hudson River for Atlantic Sturgeon. Ongoing interactions between the NRC staff, NMFS, NYDEC, and Entergy regarding this new designation and Entergys monitoring plan for sturgeon are expected to be completed in the second quarter of FY 2018. Resolution of this issue will be documented in the Record of Decision issued in conjunction with the renewed operating licenses for the units. A decision on the renewed operating licenses for both units is expected to be issued in the 4th quarter of FY 2018.
Applicant Application Accepted for Review Review Status for Long-Term Application Reviews Indian Point 2&3 08/01/2007 The NRC staff has addressed the public comments received on its draft second supplement to the FSEIS, which was issued for comment in December 2015. The staffs response to the public comments will be documented in the FSEIS supplement, which is currently under final review. The initial SER was issued in November 2009, with supplements issued in August 2011 and July 2015. A third SER supplement will be issued in the second quarter of FY 2018 to address new information received by the staff concerning safety issues. In January 2017, the parties to the legal proceedings reached an agreement that resulted in the withdrawal of all contentions on the license renewal application. Under the agreement, Units 2 & 3 will cease operations in April 2020 and 2021, respectively, with possible extensions to operate until April 2024 and 2025, respectively. On February 8, 2017, the State of New York Department of Environmental Conservation (NYDEC) and Riverkeeper filed an unopposed motion to the ASLB to withdraw their contentions and terminate the adjudicatory proceeding. The Licensing Board granted that motion and terminated the adjudicatory proceeding on March 13, 2017. Recently the National Marine Fisheries Service (NMFS) designated critical habitat in the Hudson River for Atlantic Sturgeon. Ongoing interactions between the NRC staff, NMFS, NYDEC, and Entergy regarding this new designation and Entergys monitoring plan for sturgeon are expected to be completed in the second quarter of FY 2018. Resolution of this issue will be documented in the Record of Decision issued in conjunction with the renewed operating licenses for the units. A decision on the renewed operating licenses for both units is expected to be issued in the 4th quarter of FY 2018.
Diablo     01/21/2010     In June 2016, Pacific Gas and Electric requested a suspension of Canyon 1&2                    the license renewal review to allow it to seek approval from the CPUC of an agreement in principle not to proceed with license renewal for Diablo Canyon. In July 2016, the NRC suspended the license renewal review. The CPUC held a public meeting on January 11, 2018, during which it approved PG&Es proposal to close Diablo Canyon in 2025. PG&E is expected to provide an update on its plans regarding withdrawal of the license renewal application; however, PG&E has not yet provided a projected submittal date.
Diablo Canyon 1&2 01/21/2010 In June 2016, Pacific Gas and Electric requested a suspension of the license renewal review to allow it to seek approval from the CPUC of an agreement in principle not to proceed with license renewal for Diablo Canyon. In July 2016, the NRC suspended the license renewal review. The CPUC held a public meeting on January 11, 2018, during which it approved PG&Es proposal to close Diablo Canyon in 2025. PG&E is expected to provide an update on its plans regarding withdrawal of the license renewal application; however, PG&E has not yet provided a projected submittal date.  
44


Application Accepted Applicant                        Review Status for Long-Term Application Reviews for Review Seabrook 1   07/21/2010 The NRC staff continues discussions with NextEra to ensure that technical issues related to the ASR open item in the SER are properly addressed. In August 2016, NextEra submitted a LAR to the current license to adopt a methodology for the analysis of seismic Category I structures with concrete affected by ASR. This methodology is the basis for the aging management program being evaluated under the license renewal application review. On October 6, 2017, the ASLB admitted a contention on the ASR LAR.
45 Applicant Application Accepted for Review Review Status for Long-Term Application Reviews Seabrook 1 07/21/2010 The NRC staff continues discussions with NextEra to ensure that technical issues related to the ASR open item in the SER are properly addressed. In August 2016, NextEra submitted a LAR to the current license to adopt a methodology for the analysis of seismic Category I structures with concrete affected by ASR. This methodology is the basis for the aging management program being evaluated under the license renewal application review. On October 6, 2017, the ASLB admitted a contention on the ASR LAR.
The review of this amendment has a direct impact on the schedule for the license renewal review. A decision on the license renewal, is currently projected to be made by April 2019.
The review of this amendment has a direct impact on the schedule for the license renewal review. A decision on the license renewal, is currently projected to be made by April 2019.
Waterford   05/31/2016 The NRC staff continues their safety and environmental reviews, including the resolution of specific questions regarding the Waterford neutron fluence time-limited aging analysis. The applicant submitted a LAR in November 2017 that will request approval of their plant-specific neutron fluence methodology which is applied to the reactor vessel neutron fluence embrittlement analysis referred to in the license renewal application. The acceptance review of this LAR has been completed and NRC staff safety review is currently underway.
Waterford 05/31/2016 The NRC staff continues their safety and environmental reviews, including the resolution of specific questions regarding the Waterford neutron fluence time-limited aging analysis. The applicant submitted a LAR in November 2017 that will request approval of their plant-specific neutron fluence methodology which is applied to the reactor vessel neutron fluence embrittlement analysis referred to in the license renewal application. The acceptance review of this LAR has been completed and NRC staff safety review is currently underway.
The review of the LAR is estimated to take approximately 1 year.
The review of the LAR is estimated to take approximately 1 year.
The license renewal application fluence methodology review is dependent on the approval of the LAR. Therefore, the decision on the renewed operating license is expected to be issued in the 3rd quarter of FY 2019.
The license renewal application fluence methodology review is dependent on the approval of the LAR. Therefore, the decision on the renewed operating license is expected to be issued in the 3rd quarter of FY 2019.
River Bend 08/07/2017 The staff continues the safety and environmental reviews, which are expected to take approximately 18 months. The staff has completed its Operating Experience, Scoping and Screening, and Aging Management Program audits. The staff is in the process of issuing requests for additional information and drafting the SER.
River Bend 08/07/2017 The staff continues the safety and environmental reviews, which are expected to take approximately 18 months. The staff has completed its Operating Experience, Scoping and Screening, and Aging Management Program audits. The staff is in the process of issuing requests for additional information and drafting the SER.
A petition to intervene and request for hearing was filed in connection with this proceeding. The ASLB ruled the petitioners contentions inadmissible and denied the petition in January 2018; the Board's decision is subject to appeal before the Commission.
A petition to intervene and request for hearing was filed in connection with this proceeding. The ASLB ruled the petitioners contentions inadmissible and denied the petition in January 2018; the Board's decision is subject to appeal before the Commission.
Turkey Point 1/30/2018   On January 30, 2018, Florida Power & Light Company submitted the 3&4                  first subsequent license renewal application for the Turkey Point Nuclear Generating Units 3 and 4. The NRC staff is currently performing a proprietary determination in accordance with 10 CFR 2.390. Once the proprietary determination is completed, the NRC staff will perform an acceptance review for docketing in accordance with the requirements of 10 CFR 2.101. Should the NRC staff determine that the application is acceptable for docketing, the NRC staff will issue the application review schedule.
Turkey Point 3&4 1/30/2018 On January 30, 2018, Florida Power & Light Company submitted the first subsequent license renewal application for the Turkey Point Nuclear Generating Units 3 and 4. The NRC staff is currently performing a proprietary determination in accordance with 10 CFR 2.390. Once the proprietary determination is completed, the NRC staff will perform an acceptance review for docketing in accordance with the requirements of 10 CFR 2.101. Should the NRC staff determine that the application is acceptable for docketing, the NRC staff will issue the application review schedule.  
45
 
46
: 19. Please provide the status of the NRCs readiness to review applications for Subsequent License Renewal (SLR).
: 19. Please provide the status of the NRCs readiness to review applications for Subsequent License Renewal (SLR).
In August 2014, the Commission affirmed that no revisions to either the safety or environmental regulations are needed to support the assessment of a SLR application. However, the Commission directed the staff to update license renewal guidance, as needed, to provide additional clarity on the implementation of the license renewal regulatory framework. The main guidance documents for initial license renewal are:
In August 2014, the Commission affirmed that no revisions to either the safety or environmental regulations are needed to support the assessment of a SLR application. However, the Commission directed the staff to update license renewal guidance, as needed, to provide additional clarity on the implementation of the license renewal regulatory framework. The main guidance documents for initial license renewal are:
* Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants (SRP-LR), Revision 2;
Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants (SRP-LR), Revision 2; Generic Aging Lessons Learned (GALL) Report, Revision 2; and Standard Review Plan for Environmental Reviews for Nuclear Power Plants, Supplement 1:
* Generic Aging Lessons Learned (GALL) Report, Revision 2; and
* Standard Review Plan for Environmental Reviews for Nuclear Power Plants, Supplement 1:
Operating License Renewal (Revision 1).
Operating License Renewal (Revision 1).
The guidance in these documents is based on plant operation up to 60 years. The staff evaluated this guidance to determine what, if any, revisions were necessary to address issues for plant operations up to 80 years under SLR. The staff determined that no revisions were needed to the NRC guidance document entitled, Standard Review Plans for Environmental Reviews for Nuclear Power Plants, to support environmental reviews from 60 to 80 years.
The guidance in these documents is based on plant operation up to 60 years. The staff evaluated this guidance to determine what, if any, revisions were necessary to address issues for plant operations up to 80 years under SLR. The staff determined that no revisions were needed to the NRC guidance document entitled, Standard Review Plans for Environmental Reviews for Nuclear Power Plants, to support environmental reviews from 60 to 80 years.
Line 545: Line 681:
(NUREG-2192). On December 29, 2017, the NRC staff published NUREG-2221, Technical Bases for Changes in the Subsequent License Renewal Guidance Documents NUREG-2191 and NUREG-2192, and NUREG-2222, Disposition of Public Comments on the Draft Subsequent License Renewal Guidance Documents NUREG-2191 and NUREG-2192.
(NUREG-2192). On December 29, 2017, the NRC staff published NUREG-2221, Technical Bases for Changes in the Subsequent License Renewal Guidance Documents NUREG-2191 and NUREG-2192, and NUREG-2222, Disposition of Public Comments on the Draft Subsequent License Renewal Guidance Documents NUREG-2191 and NUREG-2192.
On November 6, 2015, Dominion Virginia Power notified the NRC of its intent to submit an SLR application in the first quarter of 2019 for Surry Power Station. On June 7, 2016, Exelon Generation Company, LLC notified the NRC of its intent to submit an application for Peach Bottom Atomic Power Station in the third quarter of 2018. On November 9, 2017, Dominion Energy Virginia notified the NRC of its intent to pursue subsequent license renewal for North Anna Power Station Units 1 and 2 in the 4th quarter of 2020.
On November 6, 2015, Dominion Virginia Power notified the NRC of its intent to submit an SLR application in the first quarter of 2019 for Surry Power Station. On June 7, 2016, Exelon Generation Company, LLC notified the NRC of its intent to submit an application for Peach Bottom Atomic Power Station in the third quarter of 2018. On November 9, 2017, Dominion Energy Virginia notified the NRC of its intent to pursue subsequent license renewal for North Anna Power Station Units 1 and 2 in the 4th quarter of 2020.
On December 20, 2017, the staff issued a letter to NEI providing interim approval for use of guidance documents NEI 17-01, Industry Guideline for Implementing the Requirements of 10 CFR Part 54 for Subsequent License Renewal [SLR], and NEI 17-04, Model SLR New and Significant Assessment Approach for SAMA, Revision 0. These documents will provide interim guidance to licensees that have notified the NRC of their intent to submit SLR applications while formal NRC endorsement of the NEI guidance document is considered. The NRC expects that issuance of formal revisions to Regulatory Guides 1.188, Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses, and 4.2, Preparation of Environmental Reports for Nuclear Power Plant License Renewal Applications, by December 31, 2019, will supersede the interim guidance.
On December 20, 2017, the staff issued a letter to NEI providing interim approval for use of guidance documents NEI 17-01, Industry Guideline for Implementing the Requirements of 10 CFR Part 54 for Subsequent License Renewal [SLR], and NEI 17-04, Model SLR New and Significant Assessment Approach for SAMA, Revision 0. These documents will provide interim guidance to licensees that have notified the NRC of their intent to submit SLR applications while formal NRC endorsement of the NEI guidance document is considered. The NRC expects that issuance of formal revisions to Regulatory Guides 1.188, Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses, and 4.2, Preparation of Environmental Reports for Nuclear Power Plant License Renewal Applications, by December 31, 2019, will supersede the interim guidance.  
46
 
47
: 20. Once Subsequent License Renewal reviews begin, please report progress similarly to current license renewal reviews, including: the date each application was filed, the duration of the review, the original milestone schedule based on an 18-month review, the actual completion dates for milestones, and the scheduled date for completion of the review.
: 20. Once Subsequent License Renewal reviews begin, please report progress similarly to current license renewal reviews, including: the date each application was filed, the duration of the review, the original milestone schedule based on an 18-month review, the actual completion dates for milestones, and the scheduled date for completion of the review.
By letter dated January 30, 2018, Florida Power & Light Company submitted an application for subsequent renewal for the operating license for Turkey Point Nuclear Generating Units 3 and 4 to the NRC. The NRC staff is currently performing a proprietary determination in accordance with the regulations (10 CFR 2.390). Once the proprietary determination is completed, the NRC staff will perform an acceptance review for docketing in accordance with the requirements of 10 CFR 2.101. Should the NRC staff determine that the application is acceptable for docketing, the NRC staff will issue the application review schedule.
By {{letter dated|date=January 30, 2018|text=letter dated January 30, 2018}}, Florida Power & Light Company submitted an application for subsequent renewal for the operating license for Turkey Point Nuclear Generating Units 3 and 4 to the NRC. The NRC staff is currently performing a proprietary determination in accordance with the regulations (10 CFR 2.390). Once the proprietary determination is completed, the NRC staff will perform an acceptance review for docketing in accordance with the requirements of 10 CFR 2.101. Should the NRC staff determine that the application is acceptable for docketing, the NRC staff will issue the application review schedule.
: 21. For each ongoing power uprate review, please provide:
: 21. For each ongoing power uprate review, please provide:
: a. The date the application was filed;
: a. The date the application was filed;
Line 555: Line 692:
: d. The actual completion dates for the milestones; and
: d. The actual completion dates for the milestones; and
: e. The scheduled date for completion of the review based on the metrics in SECY-13-0070.
: e. The scheduled date for completion of the review based on the metrics in SECY-13-0070.
Plant Name           Uprate       Date    Planned      Actual        Planned      Actual    Notes Type       Filed      Issue      Issue        Review      Review (Note 1)                 Date       Date       Duration     Duration (Months)    (Months)
Plant Name Uprate Type (Note 1)
Date Filed Planned Issue Date Actual Issue Date Planned Review Duration (Months)
(Note 2)
(Note 2)
Hope Creek             MUR       07/12/17   04/30/18                     9 Generating Station Note 1: MUR = measurement uncertainty recapture power uprate EPU = extended power uprate Note 2: For licensing actions, with an application date of October 1, 2016, or later, the duration of the review of the licensing action will be measured starting when the acceptance review is complete.
Actual Review Duration (Months)
Notes Hope Creek Generating Station MUR 07/12/17 04/30/18 9
Note 1: MUR = measurement uncertainty recapture power uprate EPU = extended power uprate Note 2: For licensing actions, with an application date of October 1, 2016, or later, the duration of the review of the licensing action will be measured starting when the acceptance review is complete.
: 22. Please provide a brief status of power uprate application reviews.
: 22. Please provide a brief status of power uprate application reviews.
The NRC staff is reviewing one power uprate application. The Hope Creek Generating Station measurement uncertainty recapture uprate application was accepted for review on August 9, 2017. The staff is currently performing a safety evaluation of the application.
The NRC staff is reviewing one power uprate application. The Hope Creek Generating Station measurement uncertainty recapture uprate application was accepted for review on August 9, 2017. The staff is currently performing a safety evaluation of the application.
Line 563: Line 703:
: a. Number of RAIs issued;
: a. Number of RAIs issued;
: b. The number of RAIs issued prior to preparation of a draft safety evaluation with open items;
: b. The number of RAIs issued prior to preparation of a draft safety evaluation with open items;
: c. The number of RAIs issued in an additional round, subsequent to previous RAIs, in specific technical area or by a technical branch; 47
: c. The number of RAIs issued in an additional round, subsequent to previous RAIs, in specific technical area or by a technical branch;  
 
48
: d. The percentage of RAI responses provided by licensees within 30 days of the date mutually agreed upon;
: d. The percentage of RAI responses provided by licensees within 30 days of the date mutually agreed upon;
: e. The number of RAIs prepared or responses reviewed by contractors; and
: e. The number of RAIs prepared or responses reviewed by contractors; and
: f. The number of RAIs prepared or responses reviewed by NRC staff.
: f.
The number of RAIs prepared or responses reviewed by NRC staff.
: g. Once sufficient date becomes available please provide 12-month rolling average number of RAIs issued by each office.
: g. Once sufficient date becomes available please provide 12-month rolling average number of RAIs issued by each office.
NOTE: Information for the Office of Nuclear Security and Incident Response is included within each of the other entities or programs reporting below.
NOTE: Information for the Office of Nuclear Security and Incident Response is included within each of the other entities or programs reporting below.  
48


Office of Nuclear Reactor Regulation Number of The RAIs Percentage Number of     Issued in of RAI RAIs           an                                                    12 Month Responses                      The Issued       Additional                      The                        Rolling Provided                  Number of Prior to the     Round,                      Number                      Average, Number                                          by                        RAI Preparation Subsequent                        of RAIs                      Number Month/Year      of RAIs                                     Licensees                  Responses of a Draft    to Previous                   prepared                      of RAIs Issued                                      within 30                  Reviewed Safety        RAI's in                     by NRC                    Issued by Days or                     by NRC Evaluation      Specific                      staff                       Each the Date                      Staff with Open      Technical                                                  Office Mutually Items      Area or by Agreed a Technical Upon Branch 205 Jan 2018         205         Note 1           1           83%         Note 2         168         Note 3 Note 1: The database systems do not have readily available information that distinguishes between item 23a and 23b. Accurately compiling the number of RAI questions issued prior to preparation of a draft safety evaluation with open items would require extensive manual document searches and analysis to cover the significant volume of project reviews. The count of RAIs is presented collectively under Item 23a.
49 Office of Nuclear Reactor Regulation Month/Year Number of RAIs Issued Number of RAIs Issued Prior to the Preparation of a Draft Safety Evaluation with Open Items Number of RAIs Issued in an Additional
Note 2: The NRC employs contractors to supplement the staff in selected critical skill areas; however, all RAIs identified by contractors are evaluated by NRC staff to verify that they are necessary to support a regulatory finding. If the RAIs are necessary, they are formally prepared and issued by NRC staff. The NRC does not track the number of draft RAIs prepared by contractors. In addition, the NRC staff is responsible for making the final determination on the acceptability of all RAI responses.
: Round, Subsequent to Previous RAI's in Specific Technical Area or by a Technical Branch The Percentage of RAI Responses Provided by Licensees within 30 Days or the Date Mutually Agreed Upon The Number of RAIs prepared by NRC staff The Number of RAI Responses Reviewed by NRC Staff 12 Month Rolling
Note 3: A 12-month rolling average will not be available until November 2018.
: Average, Number of RAIs Issued by Each Office Jan 2018 205 Note 1 1
49
83%
205 Note 2 168 Note 3 Note 1:
The database systems do not have readily available information that distinguishes between item 23a and 23b. Accurately compiling the number of RAI questions issued prior to preparation of a draft safety evaluation with open items would require extensive manual document searches and analysis to cover the significant volume of project reviews. The count of RAIs is presented collectively under Item 23a.
Note 2:
The NRC employs contractors to supplement the staff in selected critical skill areas; however, all RAIs identified by contractors are evaluated by NRC staff to verify that they are necessary to support a regulatory finding. If the RAIs are necessary, they are formally prepared and issued by NRC staff. The NRC does not track the number of draft RAIs prepared by contractors. In addition, the NRC staff is responsible for making the final determination on the acceptability of all RAI responses.
Note 3:
A 12-month rolling average will not be available until November 2018.  


Office of New Reactors Number of   Number of RAIs                                   Number of Percentage of RAIs  Number of RAIs Issued    Issued in an                                       RAIs Responses          RAIs Prior to  Additional Round,                                 Prepared or Number of                                 Provided by the   Prepared or Preparation  Subsequent to                                    Responses RAIs                                  Applicant/Licensee Responses              12-Month of a Draft Previous RAIs, in                                  Reviewed Project Name    Issued in                                within 30 Days or Reviewed by              Rolling SER with  Specific Technical                                  by NRC January                                  the Date Mutually Contractors            Average Open Items      Area or by                                        Staff in 2018                                    Agreed Upon in         in                  (Note 3) in    Technical Branch                                    January January 2018   January 2018 January    in January 2018                                      2018 (Note 2) 2018         (Note 1)                                       (Note 2)
50 Office of New Reactors Project Name Number of RAIs Issued in January 2018 Number of RAIs Issued Prior to Preparation of a Draft SER with Open Items in January 2018 Number of RAIs Issued in an Additional Round, Subsequent to Previous RAIs, in Specific Technical Area or by Technical Branch in January 2018 (Note 1)
APR1400             0           0           N/A                 0%               0           0       N/A Design Certification (DC)
Percentage of RAIs Responses Provided by the Applicant/Licensee within 30 Days or the Date Mutually Agreed Upon in January 2018 Number of RAIs Prepared or Responses Reviewed by Contractors in January 2018 (Note 2)
U.S. Advanced       1          0            N/A                N/A              0          1        N/A Pressurized Water Reactor (US-APWR) DC Advanced            0          0           N/A                 N/A               0           0        N/A Boiling Water Reactor (ABWR) DC Renewal (General Electric Hitachi (GEH))
Number of RAIs Prepared or Responses Reviewed by NRC Staff in January 2018 (Note 2) 12-Month Rolling Average (Note 3)
Clinch River        0           0           N/A                 N/A               0           0       N/A Early Site Permit (ESP)
APR1400 Design Certification (DC) 0 0
NuScale Small       76         76           N/A                 39%               0         76       N/A Modular Reactor (SMR)
N/A 0%
DC NuScale             2           2           N/A                 46%               0           2       N/A Topical Reports 50
0 0
N/A U.S. Advanced Pressurized Water Reactor (US-APWR) DC 1
0 N/A N/A 0
1 N/A Advanced Boiling Water Reactor (ABWR) DC Renewal (General Electric Hitachi (GEH))
0 0
N/A N/A 0
0 N/A Clinch River Early Site Permit (ESP) 0 0
N/A N/A 0
0 N/A NuScale Small Modular Reactor (SMR)
DC 76 76 N/A 39%
0 76 N/A NuScale Topical Reports 2
2 N/A 46%
0 2
N/A  


Number of       Number of RAIs                                                   Number of Percentage of RAIs      Number of RAIs Issued        Issued in an                                                     RAIs Responses                RAIs Prior to    Additional Round,                                               Prepared or Number of                                               Provided by the       Prepared or Preparation      Subsequent to                                                  Responses RAIs                                              Applicant/Licensee       Responses                        12-Month of a Draft    Previous RAIs, in                                                Reviewed Project Name      Issued in                                            within 30 Days or     Reviewed by                        Rolling SER with      Specific Technical                                                by NRC January                                              the Date Mutually       Contractors                      Average Open Items            Area or by                                                    Staff in 2018                                                Agreed Upon in             in                            (Note 3) in      Technical Branch                                                  January January 2018         January 2018 January      in January 2018                                                      2018 (Note 2) 2018               (Note 1)                                                   (Note 2)
51 Project Name Number of RAIs Issued in January 2018 Number of RAIs Issued Prior to Preparation of a Draft SER with Open Items in January 2018 Number of RAIs Issued in an Additional Round, Subsequent to Previous RAIs, in Specific Technical Area or by Technical Branch in January 2018 (Note 1)
Vogtle LARs           11             11                 N/A                   100%                   0               11             N/A Note 1: NRO does not currently have an electronic system to track how many RAIs are issued in an additional round as a subsequent RAI to a previous RAI issued. To develop this capability within the current electronic system used to track RAIs would be labor and resource intensive.
Percentage of RAIs Responses Provided by the Applicant/Licensee within 30 Days or the Date Mutually Agreed Upon in January 2018 Number of RAIs Prepared or Responses Reviewed by Contractors in January 2018 (Note 2)
Number of RAIs Prepared or Responses Reviewed by NRC Staff in January 2018 (Note 2) 12-Month Rolling Average (Note 3)
Vogtle LARs 11 11 N/A 100%
0 11 N/A Note 1: NRO does not currently have an electronic system to track how many RAIs are issued in an additional round as a subsequent RAI to a previous RAI issued. To develop this capability within the current electronic system used to track RAIs would be labor and resource intensive.
Note 2: The NRC employs contractors to supplement the staff in selected critical skill areas; however, all RAIs identified by contractors are evaluated by NRC staff to verify that they are necessary to support a regulatory finding. If the RAIs are necessary, they are formally prepared and issued by NRC staff. The NRC does not track the number of draft RAIs prepared by contractors. In addition, the NRC staff is responsible for making the final determination on the acceptability of all RAI responses.
Note 2: The NRC employs contractors to supplement the staff in selected critical skill areas; however, all RAIs identified by contractors are evaluated by NRC staff to verify that they are necessary to support a regulatory finding. If the RAIs are necessary, they are formally prepared and issued by NRC staff. The NRC does not track the number of draft RAIs prepared by contractors. In addition, the NRC staff is responsible for making the final determination on the acceptability of all RAI responses.
Note 3: A 12-month rolling average will not be available until November 2018.
Note 3: A 12-month rolling average will not be available until November 2018.  
51


Office of Nuclear Material Safety and Safeguards Uranium Recovery Number of The RAIs Percentage Number of     Issued in of RAI RAIs           an                                                            12 Month Responses                  The                  The Issued       Additional                The                    The              Rolling Provided              Number of            Number of Prior to the     Round,                Number of             Number              Average, Number                                    by                   RAI                 RAI Preparation Subsequent                    RAIs                of RAIs           Number Month/Year    of RAIs                              Licensees              Responses            Responses of a Draft  to Previous              prepared             prepared            of RAIs Issued                                within 30              Reviewed            Reviewed Safety        RAIs in                    by                  by NRC           Issued by Days or                    by                by NRC Evaluation      Specific              Contractors              staff              Each the Date              Contractors            Staff with Open      Technical                                                            Office Mutually Items      Area or by Agreed a Technical Upon Branch Jan 2018         1             1             0         N/A           0         0         1       0         N/A 52
52 Office of Nuclear Material Safety and Safeguards Uranium Recovery Month/Year Number of RAIs Issued Number of RAIs Issued Prior to the Preparation of a Draft Safety Evaluation with Open Items Number of RAIs Issued in an Additional
: Round, Subsequent to Previous RAIs in Specific Technical Area or by a Technical Branch The Percentage of RAI Responses Provided by Licensees within 30 Days or the Date Mutually Agreed Upon The Number of RAIs prepared by Contractors The Number of RAI Responses Reviewed by Contractors The Number of RAIs prepared by NRC staff The Number of RAI Responses Reviewed by NRC Staff 12 Month Rolling
: Average, Number of RAIs Issued by Each Office Jan 2018 1
1 0
N/A 0
0 1
0 N/A  


Reactor Decommissioning Number of The RAIs Percentage Number of     Issued in of RAI RAIs         an                                                             12 Month Responses                  The                  The Issued      Additional                 The                     The              Rolling Provided               Number of            Number of Prior to the   Round,                Number of               Number              Average, Number of                               by                   RAI                  RAI Preparation Subsequent                  RAIs                  of RAIs           Number of Month/Year  RAIs                              Licensees              Responses            Responses of a Draft  to Previous              prepared              prepared              RAIs Issued                            within 30                Reviewed            Reviewed Safety      RAIs in                    by                  by NRC           Issued by Days or                    by                by NRC Evaluation    Specific              Contractors              staff              Each the Date              Contractors            Staff with Open    Technical                                                            Office Mutually Items      Area or by Agreed a Technical Upon Branch Jan 2018     8           0           8           0           0           0         8       9         N/A 53
53 Reactor Decommissioning Month/Year Number of RAIs Issued Number of RAIs Issued Prior to the Preparation of a Draft Safety Evaluation with Open Items Number of RAIs Issued in an Additional
: Round, Subsequent to Previous RAIs in Specific Technical Area or by a Technical Branch The Percentage of RAI Responses Provided by Licensees within 30 Days or the Date Mutually Agreed Upon The Number of RAIs prepared by Contractors The Number of RAI Responses Reviewed by Contractors The Number of RAIs prepared by NRC staff The Number of RAI Responses Reviewed by NRC Staff 12 Month Rolling
: Average, Number of RAIs Issued by Each Office Jan 2018 8
0 8
0 0
0 8
9 N/A  
 
54
: 24. Please provide the status of specific actions taken or planned to ensure greater discipline, management oversight, and transparency in the use of the RAI process and to limit RAIs to those necessary for making regulatory decisions. The description should include:
: 24. Please provide the status of specific actions taken or planned to ensure greater discipline, management oversight, and transparency in the use of the RAI process and to limit RAIs to those necessary for making regulatory decisions. The description should include:
management oversight and accountability, the training necessary to provide consistency and sustainable improvement across the applicable program business lines, efforts to establish consistent procedures in relevant offices, and any gaps or trends identified by management or through internal reviews including periodic internal RAI audits.
management oversight and accountability, the training necessary to provide consistency and sustainable improvement across the applicable program business lines, efforts to establish consistent procedures in relevant offices, and any gaps or trends identified by management or through internal reviews including periodic internal RAI audits.
Line 598: Line 775:
NRR launched several initiatives and to focus on leveraging or revising existing licensing processes to enhance agency efficiency, effectiveness, and predictability, while maintaining a continued strong safety focus. These initiatives have analyzed the issues that caused the previous licensing action backlog, including the RAI process, and recommended enhancements to the licensing review process. NRR management issued interim guidance to the staff in January 2015, and updated interim guidance in April 2016, providing expectations to help enhance consistency of the licensing review process, sound decision-making, and discipline of schedule. In January 2017, this interim guidance was incorporated into NRR procedures.
NRR launched several initiatives and to focus on leveraging or revising existing licensing processes to enhance agency efficiency, effectiveness, and predictability, while maintaining a continued strong safety focus. These initiatives have analyzed the issues that caused the previous licensing action backlog, including the RAI process, and recommended enhancements to the licensing review process. NRR management issued interim guidance to the staff in January 2015, and updated interim guidance in April 2016, providing expectations to help enhance consistency of the licensing review process, sound decision-making, and discipline of schedule. In January 2017, this interim guidance was incorporated into NRR procedures.
Some of the key items that have added discipline and management oversight to the RAI process include the following:
Some of the key items that have added discipline and management oversight to the RAI process include the following:
* NRR staff review of an application will be limited to the scope of the licensing action and RAIs should only request information that is required to make a safety determination.
NRR staff review of an application will be limited to the scope of the licensing action and RAIs should only request information that is required to make a safety determination.
* At the point when RAIs are transmitted from the technical staff to the NRR project manager, the technical staff is expected to have developed a draft safety evaluation (SE). In addition to ensuring that the RAIs contain a sound technical and regulatory basis, the technical staff should be able to correlate each RAI to a hole in the draft SE that the licensee response is expected to fill.
At the point when RAIs are transmitted from the technical staff to the NRR project manager, the technical staff is expected to have developed a draft safety evaluation (SE). In addition to ensuring that the RAIs contain a sound technical and regulatory basis, the technical staff should be able to correlate each RAI to a hole in the draft SE that the licensee response is expected to fill.
* Prior to sending a second (and any subsequent) round of RAIs in a specific technical area, NRR division-level management will apply additional oversight to discuss the need for the RAIs and whether alternative methods, such as a public meeting or audit, may be more effective and efficient for obtaining the necessary information.
Prior to sending a second (and any subsequent) round of RAIs in a specific technical area, NRR division-level management will apply additional oversight to discuss the need for the RAIs and whether alternative methods, such as a public meeting or audit, may be more effective and efficient for obtaining the necessary information.
* NRR project managers track licensee timeliness and adherence to RAI response schedules. Any significant delays in licensee responses will be brought to NRR management attention.
NRR project managers track licensee timeliness and adherence to RAI response schedules. Any significant delays in licensee responses will be brought to NRR management attention.
Training sessions were held with the technical and project management staff on RAI quality and the RAI process. Following the issuance of the finalized NRR guidance in this area in January 2017, online training was developed and provided to the NRR staff. This training covered expectations regarding added discipline and management oversight of the RAI process.
Training sessions were held with the technical and project management staff on RAI quality and the RAI process. Following the issuance of the finalized NRR guidance in this area in January 2017, online training was developed and provided to the NRR staff. This training covered expectations regarding added discipline and management oversight of the RAI process.  
54


Other actions that provide a stable and sustainable improvement in the RAI process and add accountability to the process include the following:
55 Other actions that provide a stable and sustainable improvement in the RAI process and add accountability to the process include the following:
* In November 2014, NRR management began holding periodic meetings to discuss open licensing actions, develop alignment on the best approaches for completing those actions, and monitor licensing performance.
In November 2014, NRR management began holding periodic meetings to discuss open licensing actions, develop alignment on the best approaches for completing those actions, and monitor licensing performance.
* In October 2016, NRR replaced the existing software used to manage and monitor licensing reviews with a newly developed software package called the Reactor Program System - Licensing/Workload Management software. This system has the capability to better track RAI issuance and status.
In October 2016, NRR replaced the existing software used to manage and monitor licensing reviews with a newly developed software package called the Reactor Program System - Licensing/Workload Management software. This system has the capability to better track RAI issuance and status.
* NRR performed an internal audit of a sample of RAIs issued between April and December 2016 and found that the overall adherence to quality, timeliness, and process expectations was satisfactory. The audit team identified areas for continued improvement and recommended increased staff training on the RAI guidance, development of staff job aids, and consideration of modifications to staff guidance to better reflect the reactor license renewal and non-power utilization facilities licensing processes.
NRR performed an internal audit of a sample of RAIs issued between April and December 2016 and found that the overall adherence to quality, timeliness, and process expectations was satisfactory. The audit team identified areas for continued improvement and recommended increased staff training on the RAI guidance, development of staff job aids, and consideration of modifications to staff guidance to better reflect the reactor license renewal and non-power utilization facilities licensing processes.
* On January 2, 2018, in response to the recommendations from the internal audit, NRR management issued a tasking memorandum to the staff with four specific actions to address the audit findings: (1) provide mandatory RAI refresher training for applicable NRR, NSIR, and NRO staff and branch chiefs, (2) evaluate existing RAI job aid for applications to other divisions, (3) formalize use of NRR guidance, as applicable, for reactor license renewal and non-power utilization facilities, and (4) conduct subsequent RAI quality reviews. By the end of January 2018, three refresher training sessions were held for branch chiefs.
On January 2, 2018, in response to the recommendations from the internal audit, NRR management issued a tasking memorandum to the staff with four specific actions to address the audit findings: (1) provide mandatory RAI refresher training for applicable NRR, NSIR, and NRO staff and branch chiefs, (2) evaluate existing RAI job aid for applications to other divisions, (3) formalize use of NRR guidance, as applicable, for reactor license renewal and non-power utilization facilities, and (4) conduct subsequent RAI quality reviews. By the end of January 2018, three refresher training sessions were held for branch chiefs.
NRO Activities NRO has taken several steps to ensure that its RAIs are consistently of high quality and are necessary to make a safety finding. In 2016, senior managers in NRO undertook initiatives to examine licensing activities with a goal of promoting a continued strong safety focus, consistency, efficiency, and clarity in our reviews of new reactor licensing applications. These initiatives included revising the RAI process to promote the consistent generation of high quality RAIs.
NRO Activities NRO has taken several steps to ensure that its RAIs are consistently of high quality and are necessary to make a safety finding. In 2016, senior managers in NRO undertook initiatives to examine licensing activities with a goal of promoting a continued strong safety focus, consistency, efficiency, and clarity in our reviews of new reactor licensing applications. These initiatives included revising the RAI process to promote the consistent generation of high quality RAIs.
In October 2016, the NRO RAI process was revised (ADAMS Accession No. ML16280A389) to include a new quality check audit process where, in addition to the technical branchs supervisor, the division management of both the technical and project management organizations review an RAI before it is issued to the applicant or licensee. In addition, the NRO Office Director reviews a sample of RAIs to keep abreast of high-priority issues identified in reviews and to support NROs emphasis on effectiveness and efficiency as it focuses on safety, security, and environmentally significant matters.
In October 2016, the NRO RAI process was revised (ADAMS Accession No. ML16280A389) to include a new quality check audit process where, in addition to the technical branchs supervisor, the division management of both the technical and project management organizations review an RAI before it is issued to the applicant or licensee. In addition, the NRO Office Director reviews a sample of RAIs to keep abreast of high-priority issues identified in reviews and to support NROs emphasis on effectiveness and efficiency as it focuses on safety, security, and environmentally significant matters.
On October 7, 2016, the NRO Office Director issued a memorandum titled Effective Use of Request for Additional Information, Audit, and Confirmatory Analysis in New Reactor Licensing Review, to all NRO staff, which emphasized the goals of the RAI process, described the revised process, and included a job aid that contains best practices for preparing RAIs.
On October 7, 2016, the NRO Office Director issued a memorandum titled Effective Use of Request for Additional Information, Audit, and Confirmatory Analysis in New Reactor Licensing Review, to all NRO staff, which emphasized the goals of the RAI process, described the revised process, and included a job aid that contains best practices for preparing RAIs.
The staff has incorporated many lessons-learned into its review of the active DC and ESP applications. The 2016 initiative to improve the focus of RAIs has improved the quality and safety focus of these requests. The staff is also using the regulatory audit tool earlier in the process to better inform the staff about the bases supporting the applications and therefore, 55
The staff has incorporated many lessons-learned into its review of the active DC and ESP applications. The 2016 initiative to improve the focus of RAIs has improved the quality and safety focus of these requests. The staff is also using the regulatory audit tool earlier in the process to better inform the staff about the bases supporting the applications and therefore,  


better focus the staffs RAIs on information that directly relates to the staff reaching safety findings.
56 better focus the staffs RAIs on information that directly relates to the staff reaching safety findings.
The staff is currently conducting an audit to assess the effectiveness of the revised NRO RAI process. The audit is expected to evaluate whether the revised RAI process has yielded tangible improvements to NROs licensing process; and if the revised RAI process should be maintained, modified or eliminated.
The staff is currently conducting an audit to assess the effectiveness of the revised NRO RAI process. The audit is expected to evaluate whether the revised RAI process has yielded tangible improvements to NROs licensing process; and if the revised RAI process should be maintained, modified or eliminated.
NMSS Activities In NMSS, internal guidance for uranium recovery and waste program reviews includes the expectation that RAIs will be developed in conjunction with the draft SER to ensure that each RAI is necessary to reach a safety finding. In addition, the guidance contains the expectation to include a reference in the RAI to the specific relevant requirement and encourages staff to conduct telephone conferences with licensees and applicants to efficiently resolve technical issues on RAIs. The NRC staff recently finalized an internal self-assessment that identifies possible efficiency improvements within the Uranium Recovery Program. The self-assessment includes recommendations for improving the efficiency of the RAI process, such as issuing RAIs as they are written rather than as a group, and reemphasizing the expectation that staff develop the draft safety evaluation and RAIs in concert.
NMSS Activities In NMSS, internal guidance for uranium recovery and waste program reviews includes the expectation that RAIs will be developed in conjunction with the draft SER to ensure that each RAI is necessary to reach a safety finding. In addition, the guidance contains the expectation to include a reference in the RAI to the specific relevant requirement and encourages staff to conduct telephone conferences with licensees and applicants to efficiently resolve technical issues on RAIs. The NRC staff recently finalized an internal self-assessment that identifies possible efficiency improvements within the Uranium Recovery Program. The self-assessment includes recommendations for improving the efficiency of the RAI process, such as issuing RAIs as they are written rather than as a group, and reemphasizing the expectation that staff develop the draft safety evaluation and RAIs in concert.
Line 622: Line 798:
In addition, NMSS is revising NUREG-1556, Volume 20, Guidance about Administrative Licensing Procedures. Information in this NUREG regarding requests for additional information for materials licensing actions is being updated to improve consistency and management oversight between NRC headquarters and regional materials licensing staff.
In addition, NMSS is revising NUREG-1556, Volume 20, Guidance about Administrative Licensing Procedures. Information in this NUREG regarding requests for additional information for materials licensing actions is being updated to improve consistency and management oversight between NRC headquarters and regional materials licensing staff.
In August 2016, NMSSs Division of Spent Fuel Management (DSFM) issued Division Instruction (DI) 26, DSFM-26, Rev., 0, which provided management expectations and guidance to employees with regard to meeting division and business line goals of being an independent, transparent, and effective regulator. In DSFM-26, management has specifically indicated that DSFMs goal is one round of RAIs for a typical review and a maximum of two rounds of RAIs. RAIs and the applicants responses need to converge on the information needed for making a regulatory finding. As part of the management oversight process, the staff has been seeking concurrence by the division-level management, in-addition to branch-level, when a second round of RAIs is being considered during the review of an application. In addition, the staff has developed further guidance on preparing RAIs that are clear, complete, and specific with respect to the requested information, the justification for the request, and the associated regulatory basis. This guidance has been discussed with all the reviewers as part of continuous training, supplemented by a desk guide and a quick reference card. The division also is of preparing for a self-assessment on RAIs during FY 2018 - FY 2019 time frame.
In August 2016, NMSSs Division of Spent Fuel Management (DSFM) issued Division Instruction (DI) 26, DSFM-26, Rev., 0, which provided management expectations and guidance to employees with regard to meeting division and business line goals of being an independent, transparent, and effective regulator. In DSFM-26, management has specifically indicated that DSFMs goal is one round of RAIs for a typical review and a maximum of two rounds of RAIs. RAIs and the applicants responses need to converge on the information needed for making a regulatory finding. As part of the management oversight process, the staff has been seeking concurrence by the division-level management, in-addition to branch-level, when a second round of RAIs is being considered during the review of an application. In addition, the staff has developed further guidance on preparing RAIs that are clear, complete, and specific with respect to the requested information, the justification for the request, and the associated regulatory basis. This guidance has been discussed with all the reviewers as part of continuous training, supplemented by a desk guide and a quick reference card. The division also is of preparing for a self-assessment on RAIs during FY 2018 - FY 2019 time frame.
The Division of Fuel Cycle Safety, Safeguards, and Environmental Review (FCSE) conducted a review of the FCSE RAI process during the second quarter of FY 2017. Staff reviewed audit reports from the NRCs Office of the Inspector General (OIG) and the U.S. Government Accountability Office (GAO) Statement of Facts (GAO Job Code 100910). The NRC staff assessment report is at ADAMS Accession Number ML17102A783. The NRC staff also reviewed the internal policies and interviewed subject matter experts in the Office of Nuclear 56
The Division of Fuel Cycle Safety, Safeguards, and Environmental Review (FCSE) conducted a review of the FCSE RAI process during the second quarter of FY 2017. Staff reviewed audit reports from the NRCs Office of the Inspector General (OIG) and the U.S. Government Accountability Office (GAO) Statement of Facts (GAO Job Code 100910). The NRC staff assessment report is at ADAMS Accession Number ML17102A783. The NRC staff also reviewed the internal policies and interviewed subject matter experts in the Office of Nuclear  


Reactor Regulation, the Office of New Reactors, and the Office of Nuclear Material Safety and Safeguards. The results of this assessment, including staffs recommendations and proposed actions for implementing recommended improvements, were documented in a report to FCSE management on May 25, 2017. The report proposed revisions to the FCSE Licensing Review Handbook, including:
57 Reactor Regulation, the Office of New Reactors, and the Office of Nuclear Material Safety and Safeguards. The results of this assessment, including staffs recommendations and proposed actions for implementing recommended improvements, were documented in a report to FCSE management on May 25, 2017. The report proposed revisions to the FCSE Licensing Review Handbook, including:
* Periodically reinforcing expectations of key aspects in the RAI process during licensing seminars or division meetings;
Periodically reinforcing expectations of key aspects in the RAI process during licensing seminars or division meetings; Promoting a more consistent and uniform use and application of the guidance, particularly following the instructions on interactions with the licensee, drafting the safety evaluation report as a tool to identify any RAIs, having a sound regulatory basis for the RAIs, and maintaining licensing reviews aligned with its scope; The addition of clear instructions specifying that RAIs should not request information available elsewhere; and Continuing with current management oversight practice for RAIs process, such as elevating any challenges encountered during the RAI process to Division management for their awareness and involvement.
* Promoting a more consistent and uniform use and application of the guidance, particularly following the instructions on interactions with the licensee, drafting the safety evaluation report as a tool to identify any RAIs, having a sound regulatory basis for the RAIs, and maintaining licensing reviews aligned with its scope;
* The addition of clear instructions specifying that RAIs should not request information available elsewhere; and
* Continuing with current management oversight practice for RAIs process, such as elevating any challenges encountered during the RAI process to Division management for their awareness and involvement.
Based on recommendations, FCSE has conducted 2 licensing seminars on RAIs for Project Managers and Technical Reviewers, as well as a team meeting for those involved in the license renewal application review for Honeywell International. Tasks for updates to the guidance are scheduled for completion by the end of September 2018.
Based on recommendations, FCSE has conducted 2 licensing seminars on RAIs for Project Managers and Technical Reviewers, as well as a team meeting for those involved in the license renewal application review for Honeywell International. Tasks for updates to the guidance are scheduled for completion by the end of September 2018.
No adverse findings were identified in the Final GAO Report GAO-17-344, U.S. Nuclear Regulatory Commission: Efforts Intended to Improve Procedures for Requesting Additional Information for Licensing Action are Underway, dated May 25, 2017.
No adverse findings were identified in the Final GAO Report GAO-17-344, U.S. Nuclear Regulatory Commission: Efforts Intended to Improve Procedures for Requesting Additional Information for Licensing Action are Underway, dated May 25, 2017.
Line 634: Line 807:
: 25. In keeping with the Commissions policy statement on the use of probabilistic risk assessment (PRA), please describe the agencys actions to enhance the integration of risk information across the agencys activities to improve the technical basis for regulatory activities, to increase efficiency, and to improve effectiveness. Please include actions taken or planned (including milestones, where appropriate) for improving the realism of PRA information used in regulatory decision-making, for training staff to more effectively apply risk information, for updating agency processes and procedures accordingly, and for improving consistency among NRC offices and regions.
: 25. In keeping with the Commissions policy statement on the use of probabilistic risk assessment (PRA), please describe the agencys actions to enhance the integration of risk information across the agencys activities to improve the technical basis for regulatory activities, to increase efficiency, and to improve effectiveness. Please include actions taken or planned (including milestones, where appropriate) for improving the realism of PRA information used in regulatory decision-making, for training staff to more effectively apply risk information, for updating agency processes and procedures accordingly, and for improving consistency among NRC offices and regions.
As directed by the Commission in SRM-M170511, the staff recently issued SECY-17-0112, which summarizes its plans to increase staff capabilities to use risk information in decision-making activities. The paper describes five overarching strategies and summarizes associated staff actions and plans. Strategy I evaluates and updates risk-informed decision-making (RIDM) guidance to foster a collaborative review process and a broadened understanding of risk and risk insights. Strategy II develops a graded approach for using risk information in licensing reviews. Strategy III enhances training requirements related to RIDM for managers and staff.
As directed by the Commission in SRM-M170511, the staff recently issued SECY-17-0112, which summarizes its plans to increase staff capabilities to use risk information in decision-making activities. The paper describes five overarching strategies and summarizes associated staff actions and plans. Strategy I evaluates and updates risk-informed decision-making (RIDM) guidance to foster a collaborative review process and a broadened understanding of risk and risk insights. Strategy II develops a graded approach for using risk information in licensing reviews. Strategy III enhances training requirements related to RIDM for managers and staff.
Strategy IV advances NRC and industry risk-informed initiatives, and Strategy V enhances communication on risk-informed activities. To implement overarching strategies at a tactical level, the staff is also developing a detailed action plan for the reactor program. As directed by SRM-M170511, the staff will provide periodic updates to the Commission on its progress.
Strategy IV advances NRC and industry risk-informed initiatives, and Strategy V enhances communication on risk-informed activities. To implement overarching strategies at a tactical level, the staff is also developing a detailed action plan for the reactor program. As directed by SRM-M170511, the staff will provide periodic updates to the Commission on its progress.  
57


Each strategy with examples of specific actions taken or planned (including milestones, where appropriate) is summarized in the table below. Additional details are available in SECY-17-0112 and in an action plan that leverages best practices in RIDM from the operating and new reactor programs (initial issuance at ADAMS Accession No. ML17219A375). Though strategies and actions mainly focus on the reactor program, Strategies III and V will be coordinated across all agency offices and the regions, as appropriate. In addition, risk-informed approaches as applied in the materials safety and waste management arenas are described, along with reactor safety and cross cutting activities, on the Risk-Informed Activities page on the NRC public Web site (https://www.nrc.gov/about-nrc/regulatory/risk-informed/rpp.html).
58 Each strategy with examples of specific actions taken or planned (including milestones, where appropriate) is summarized in the table below. Additional details are available in SECY-17-0112 and in an action plan that leverages best practices in RIDM from the operating and new reactor programs (initial issuance at ADAMS Accession No. ML17219A375). Though strategies and actions mainly focus on the reactor program, Strategies III and V will be coordinated across all agency offices and the regions, as appropriate. In addition, risk-informed approaches as applied in the materials safety and waste management arenas are described, along with reactor safety and cross cutting activities, on the Risk-Informed Activities page on the NRC public Web site (https://www.nrc.gov/about-nrc/regulatory/risk-informed/rpp.html).
Strategy                                   Actions/Milestones Description/Background I. Evaluate and Update
Strategy Description/Background Actions/Milestones I. Evaluate and Update Guidance Updated or new guidance will be developed to more fully equip staff with the tools necessary to use quantitative or qualitative risk information in both traditionally deterministic and formal risk-informed reactor licensing reviews.
* A new revision to NUREG-1855, Treatment of Uncertainties Guidance                      Associated with PRAs in Risk-Informed Decision Making was published in March 2017 (ADAMS Accession Updated or new guidance            No. ML17062A466).
Importantly, all other strategies also involve guidance development activities.
will be developed to more
A new revision to NUREG-1855, Treatment of Uncertainties Associated with PRAs in Risk-Informed Decision Making was published in March 2017 (ADAMS Accession No. ML17062A466).
* A new revision to Regulatory Guide 1.174 An Approach for fully equip staff with the        Using Probabilistic Risk Assessment in Risk-Informed tools necessary to use            Decisions on Plant-Specific Changes to The Licensing Basis quantitative or qualitative        is nearing completion. Milestone: RG 1.174 is scheduled for risk information in both          March 2018 publication.
A new revision to Regulatory Guide 1.174 An Approach for Using Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes to The Licensing Basis is nearing completion. Milestone: RG 1.174 is scheduled for March 2018 publication.
traditionally deterministic
New and revised inspection procedures and field guides are being developed for risk-informed initiatives.
* New and revised inspection procedures and field guides are and formal risk-informed          being developed for risk-informed initiatives.
Action plan task 2 seeks to broaden the definition of risk [the understanding of risk and risk insights] beyond just a quantitative value.
reactor licensing reviews.
Action plan task 4 includes a review of branch technical position (BTP) 8-8, Onsite (Emergency Diesel Generators) and Offsite Power Sources Allowed Outage Time Extensions, to determine if clarification is needed for use of a 14-day backstop for deterministic evaluations; applicability of the guidance to one-time and permanent extensions; and defense-in-depth considerations, particularly with respect to mitigating the consequences of a loss of offsite power coincident with a loss-of-coolant accident with a single failure.
* Action plan task 2 seeks to broaden the definition of risk [the understanding of risk and risk insights] beyond just a Importantly, all other            quantitative value.
strategies also involve
* Action plan task 4 includes a review of branch technical guidance development              position (BTP) 8-8, Onsite (Emergency Diesel Generators) activities.                        and Offsite Power Sources Allowed Outage Time Extensions, to determine if clarification is needed for use of a 14-day backstop for deterministic evaluations; applicability of the guidance to one-time and permanent extensions; and defense-in-depth considerations, particularly with respect to mitigating the consequences of a loss of offsite power coincident with a loss-of-coolant accident with a single failure.
Milestone: The staff will provide findings and recommended changes to office management by June 2018.
Milestone: The staff will provide findings and recommended changes to office management by June 2018.
II. Develop a Graded
II. Develop a Graded Approach for Using Risk Information in Licensing Reviews A graded approach seeks to leverage risk insights across the spectrum of licensing review types (i.e.,
* The staff created a tool to guide technical reviewers to Approach for Using Risk        consider plant design features when formulating the scope Information in Licensing      and depth of new reactor review activities. This tool was Reviews                        successfully applied to the NuScale design certification review and is a critical element of the ongoing enhanced safety-A graded approach seeks            focused review of this design.
deterministic and formal risk-informed submittals). A framework that supports a graded risk-informed review approach is already described in NUREG-0800 The staff created a tool to guide technical reviewers to consider plant design features when formulating the scope and depth of new reactor review activities. This tool was successfully applied to the NuScale design certification review and is a critical element of the ongoing enhanced safety-focused review of this design.
to leverage risk insights
Action plan task 3 involves developing a graded approach for using risk information more broadly in operating reactor licensing reviews. As part of this task, the staff is developing, assessing, and piloting a risk-screening tool to help determine the appropriate level of its review using risk insights with other relevant factors. Action plan task 1 seeks to expand the use of license review teams with enhanced collaboration between the engineering staff and the PRA practitioners.  
* Action plan task 3 involves developing a graded approach for across the spectrum of            using risk information more broadly in operating reactor licensing review types (i.e.,      licensing reviews. As part of this task, the staff is developing, deterministic and formal          assessing, and piloting a risk-screening tool to help determine risk-informed submittals). A      the appropriate level of its review using risk insights with other framework that supports a          relevant factors. Action plan task 1 seeks to expand the use graded risk-informed review        of license review teams with enhanced collaboration between approach is already                the engineering staff and the PRA practitioners.
described in NUREG-0800 58


Strategy                               Actions/Milestones Description/Background (ADAMS Accession Nos.
59 Strategy Description/Background Actions/Milestones (ADAMS Accession Nos.
ML070630046 and ML13207A315).
ML070630046 and ML13207A315).
III. Enhance Training
III. Enhance Training Requirements Related to Risk-Informed Decision-Making (RIDM) for Managers and Staff The NRC provides over 30 formal staff training courses on technical and regulatory aspects associated with RIDM. Courses are available to all staff members; however, currently, only some NRC employees are required to take these courses.
* A new course for NRC managers (Perspectives on Requirements Related to    Risk-Informed Decision-Making for NRC Managers) is being Risk-Informed Decision-    developed that will focus on practical applications of PRA and Making (RIDM) for          describe how risk insights can inform decision-making. If Managers and Staff        successfully piloted, the course will be made mandatory for all supervisors and senior managers in the reactor program.
Furthermore, many courses focus on the technical aspects of PRA as opposed to describing how risk information can be used to inform regulatory decisions.
The NRC provides over 30        Milestone: Conduct pilot course by spring 2018.
A new course for NRC managers (Perspectives on Risk-Informed Decision-Making for NRC Managers) is being developed that will focus on practical applications of PRA and describe how risk insights can inform decision-making. If successfully piloted, the course will be made mandatory for all supervisors and senior managers in the reactor program.
formal staff training courses
Milestone: Conduct pilot course by spring 2018.
* The staff continues to offer the newly developed Risk-on technical and regulatory    Informed Thinking Workshop that provides participants with aspects associated with        hands-on experience in applying RIDM using scenarios of RIDM. Courses are              practical agency work.
The staff continues to offer the newly developed Risk-Informed Thinking Workshop that provides participants with hands-on experience in applying RIDM using scenarios of practical agency work.
available to all staff
The staff plans to update position-specific qualification requirements to include the newly developed Risk-Informed Thinking Workshop for reactor program staff.
* The staff plans to update position-specific qualification members; however,              requirements to include the newly developed Risk-Informed currently, only some NRC        Thinking Workshop for reactor program staff.
The staff is evaluating whether aspects of the Risk-Informed Thinking Workshop could be integrated with appropriate modules of the Fundamentals of Reactor Licensing Workshop for Technical Reviewers. Milestone: Complete evaluation by June 30, 2018.
employees are required to
IV. Advance Risk-Informed Initiatives The NRC primarily uses the Risk Informed Steering Committee (RISC) to advance risk-informed initiatives. RISC is a senior management committee with members from each of the program offices. The industry also has a RISC composed of senior managers. Since inception in 2014, the NRC and industry RISCs meet quarterly. The NRC RISCs objectives include the following: engage industry and listen to concerns relative to the use of PRA to support regulatory decision-making; communicate NRC actions in the area of risk-informed decision-making; Fire PRA realism: The staff is discussing with industry concerns related to fire PRA realism and potential updates to the fire PRA methods, where appropriate. In recent public meetings, industry representatives indicated that, if approved and implemented, some new methods will potentially reduce the calculated risk level at nuclear plant sites. Existing processes allow licensees to propose method improvements through the frequently asked question (FAQ) process, by submitting a license amendment request, or by a topical report. Following a recent workshop and meeting with industry stakeholders to discuss additional FAQs and research activities with the potential to affect Fire PRA realism (additional details at ADAMS Accession No. ML17312B370),
* The staff is evaluating whether aspects of the Risk-Informed take these courses.            Thinking Workshop could be integrated with appropriate Furthermore, many courses      modules of the Fundamentals of Reactor Licensing Workshop focus on the technical          for Technical Reviewers. Milestone: Complete evaluation by aspects of PRA as opposed      June 30, 2018.
the staff proposed additional FAQs and research activities.
to describing how risk information can be used to inform regulatory decisions.
Realism in the Reactor Oversight Process (ROP): The NRC continuously maintains and improves guidance documents and NRC risk tools used to support ROP activities. One such tool is the Risk Assessment Standardization Project Handbook (RASP Handbook). In March 2017, the staff transmitted plans to discuss industry concerns associated with the RASP Handbook. As a result of public meetings, industry proposed pursuing the issue on common cause failure as the highest priority and discussed alternatives.
IV. Advance Risk-Informed
Industry provided a document regarding common cause failure (CCF) modeling for staff review on December 8, 2017.  
* Fire PRA realism: The staff is discussing with industry Initiatives                concerns related to fire PRA realism and potential updates to the fire PRA methods, where appropriate. In recent public The NRC primarily uses the      meetings, industry representatives indicated that, if approved Risk Informed Steering          and implemented, some new methods will potentially reduce Committee (RISC) to            the calculated risk level at nuclear plant sites. Existing advance risk-informed          processes allow licensees to propose method improvements initiatives. RISC is a senior  through the frequently asked question (FAQ) process, by management committee            submitting a license amendment request, or by a topical with members from each of      report. Following a recent workshop and meeting with the program offices. The        industry stakeholders to discuss additional FAQs and industry also has a RISC        research activities with the potential to affect Fire PRA realism composed of senior              (additional details at ADAMS Accession No. ML17312B370),
 
managers. Since inception      the staff proposed additional FAQs and research activities.
60 Strategy Description/Background Actions/Milestones discuss what initiative can be taken by the NRC to incentivize industry to continue to develop PRAs to help both reduce uncertainty and provide a framework to make decisions in light of uncertainty; and discuss industry actions necessary to achieve the vision for future use of PRA to support regulatory decisions.
in 2014, the NRC and
A brief summary of RISC actions to improve the realism of PRA information used in regulatory decision-making are provided here. SECY 17-0112 provides additional information on all active RISC initiatives including TS Initiative 4b, The Peer Review Facts and Observations Closure Process, 10 CFR 50.69, PRA Methods Vetting Process, and Risk Aggregation.
* Realism in the Reactor Oversight Process (ROP): The NRC industry RISCs meet            continuously maintains and improves guidance documents quarterly. The NRC RISCs      and NRC risk tools used to support ROP activities. One such objectives include the          tool is the Risk Assessment Standardization Project following: engage industry      Handbook (RASP Handbook). In March 2017, the staff and listen to concerns          transmitted plans to discuss industry concerns associated relative to the use of PRA to  with the RASP Handbook. As a result of public meetings, support regulatory decision-    industry proposed pursuing the issue on common cause making; communicate NRC        failure as the highest priority and discussed alternatives.
Activities supplemental to the RISC that also advance risk-informed initiatives are also briefly described here.
actions in the area of risk-    Industry provided a document regarding common cause informed decision-making;      failure (CCF) modeling for staff review on December 8, 2017.
Following this review, the staff plans to develop additional guidance for addressing CCF for the Significance Determination Process.
59
Credit for Diverse and Flexible Coping Strategies (FLEX) in RIDM: FLEX is currently being credited in multiple risk-informed applications. The NRC staff has developed several guidance documents to promote consistency and efficiency in applications in these areas. The staff is continuing to monitor the licensees use of FLEX and is evaluating the need for additional guidance changes.
Additional activities that advance risk-informed initiatives outside the RISC include:
Cooperative Research Activities with the Electric Power Research Institute (EPRI). To conserve resources and to avoid unnecessary duplication of effort, both the NRC and EPRI have agreed to cooperate in selected research efforts and to share information and/or costs whenever such cooperation and cost sharing is appropriate and mutually beneficial. A Memorandum of Understanding with EPRI (ADAMS ML16223A497) currently covers a number of risk-related topics, including fire, seismic, PRA methods, and flooding.
* Update to RG 1.200, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities. RG 1.200 is the agencys vehicle for endorsing the industry consensus PRA standards and related PRA peer review guidance. RG 1.200 will be revised to reflect the NRCs endorsement of pertinent industry documents.
Consensus Standards Development: The NRC actively participates in the development and maintenance of consensus standards for all levels of PRA, reactor operating modes, and hazards. This effort ensures NRC staff considers a range of industry views when developing regulatory guidance and industry stakeholders are kept informed of regulatory perspectives.
V. Enhance Communication on Risk-Informed Activities The NRC is enhancing communication to ensure that its stakeholders are aware of new and enhanced risk training courses and guidance, ongoing RIDM initiatives, and plans and experience using risk information.
Staff with risk/PRA expertise are sharing knowledge and experience through presentations at branch and division meetings across the offices on topics such as risk-informed screening tools for operating and new reactor reviews.
Seminars on RIDM for NRC inspectors and enhanced inclusion of RIDM topics at regional and senior reactor analyst counterpart meetings are planned.


Strategy                                    Actions/Milestones Description/Background discuss what initiative can      Following this review, the staff plans to develop additional be taken by the NRC to            guidance for addressing CCF for the Significance incentivize industry to          Determination Process.
61
continue to develop PRAs
* Credit for Diverse and Flexible Coping Strategies (FLEX) in to help both reduce              RIDM: FLEX is currently being credited in multiple risk-uncertainty and provide a        informed applications. The NRC staff has developed several framework to make                guidance documents to promote consistency and efficiency in decisions in light of            applications in these areas. The staff is continuing to monitor uncertainty; and discuss          the licensees use of FLEX and is evaluating the need for industry actions necessary        additional guidance changes.
to achieve the vision for future use of PRA to          Additional activities that advance risk-informed initiatives outside support regulatory            the RISC include:
decisions.
* Cooperative Research Activities with the Electric Power Research Institute (EPRI). To conserve resources and to A brief summary of RISC          avoid unnecessary duplication of effort, both the NRC and actions to improve the            EPRI have agreed to cooperate in selected research efforts realism of PRA information        and to share information and/or costs whenever such used in regulatory decision-      cooperation and cost sharing is appropriate and mutually making are provided              beneficial. A Memorandum of Understanding with EPRI here. SECY 17-0112                (ADAMS ML16223A497) currently covers a number of risk-  provides              related topics, including fire, seismic, PRA methods, and additional information on all    flooding.
active RISC initiatives
* Update to RG 1.200, An Approach for Determining the including TS Initiative 4b,      Technical Adequacy of Probabilistic Risk Assessment Results The Peer Review Facts and        for Risk-Informed Activities. RG 1.200 is the agencys Observations Closure              vehicle for endorsing the industry consensus PRA standards Process, 10 CFR 50.69,            and related PRA peer review guidance. RG 1.200 will be PRA Methods Vetting              revised to reflect the NRCs endorsement of pertinent industry Process, and Risk                documents.
Aggregation.
* Consensus Standards Development: The NRC actively participates in the development and maintenance of Activities supplemental to        consensus standards for all levels of PRA, reactor operating the RISC that also advance        modes, and hazards. This effort ensures NRC staff considers risk-informed initiatives are    a range of industry views when developing regulatory also briefly described here.      guidance and industry stakeholders are kept informed of regulatory perspectives.
V. Enhance Communication
* Staff with risk/PRA expertise are sharing knowledge and on Risk-Informed              experience through presentations at branch and division Activities                    meetings across the offices on topics such as risk-informed screening tools for operating and new reactor reviews.
The NRC is enhancing              Seminars on RIDM for NRC inspectors and enhanced communication to ensure          inclusion of RIDM topics at regional and senior reactor analyst that its stakeholders are        counterpart meetings are planned.
aware of new and enhanced risk training courses and guidance, ongoing RIDM initiatives, and plans and experience using risk information.
60
: 26. The NRC has a long-standing effort to establish an efficient, reliable, and predictable licensing process for power reactors to transition from analog to digital instrumentation and control systems for safety-related applications. Please provide the date this effort began, a milestone schedule for implementation of the licensing process including the actual milestone completion dates, and the scheduled date for completion.
: 26. The NRC has a long-standing effort to establish an efficient, reliable, and predictable licensing process for power reactors to transition from analog to digital instrumentation and control systems for safety-related applications. Please provide the date this effort began, a milestone schedule for implementation of the licensing process including the actual milestone completion dates, and the scheduled date for completion.
The NRC is implementing an integrated strategy plan to modernize the NRC regulatory infrastructure for digital instrumentation and controls (I&C), through strategic and tactical modernization plans (MPs). The plans focus on topics identified by industry that will provide confidence in transitioning from analog to digital control systems (Integrated Action Plan - ADAMS Accession No. ML17102B307)
The NRC is implementing an integrated strategy plan to modernize the NRC regulatory infrastructure for digital instrumentation and controls (I&C), through strategic and tactical modernization plans (MPs). The plans focus on topics identified by industry that will provide confidence in transitioning from analog to digital control systems (Integrated Action Plan - ADAMS Accession No. ML17102B307)
MP #1A: Develop guidance for near term implementation of digital upgrades without prior NRC approval under 10 CFR 50.59 (limited scope of systems)(endorsement clarification of NEI 01-01 via RIS supplement)
MP #1A: Develop guidance for near term implementation of digital upgrades without prior NRC approval under 10 CFR 50.59 (limited scope of systems)(endorsement clarification of NEI 01-01 via RIS supplement)
Activity                                                         Actual or Projected Completion Date NRC begins effort:                                               March 2017 Prepare preliminary drafts of RIS 2002-22, Supplement 1, clarifying the staffs previous endorsement of NEI 01-01 Issue Draft RIS for Public Comment                               July 2017 Anticipate issuing the final RIS                                 To be determined upon receipt and evaluation of industry stakeholder comments expected February 2018 MP #1B: NRC review and endorsement, as appropriate, of industry technical guidance for addressing common cause failure in digital I&C (NEI 16-16)
Activity Actual or Projected Completion Date NRC begins effort:
Activity                                                         Completion Date NRC begins effort:                                               December 2016 Begin staff evaluation of the partial draft of NEI 16-16 received December 22, 2016, and develop staff comments and gap analysis NEI submits complete NEI 16-16 to the NRC for review             Review suspended per NEIs request to evaluate the pending changes to EPRI technical guidance that underpins NEI 16-16 NRC decision on technical adequacy and whether to issue         To be determined a potential interim endorsement letter NRC formally enters NEI 16-16 into the Regulatory Guide         To be determined development process (if decision is made to endorse) 61
Prepare preliminary drafts of RIS 2002-22, Supplement 1, clarifying the staffs previous endorsement of NEI 01-01 March 2017 Issue Draft RIS for Public Comment July 2017 Anticipate issuing the final RIS To be determined upon receipt and evaluation of industry stakeholder comments expected February 2018 MP #1B: NRC review and endorsement, as appropriate, of industry technical guidance for addressing common cause failure in digital I&C (NEI 16-16)
Activity Completion Date NRC begins effort:
Begin staff evaluation of the partial draft of NEI 16-16 received December 22, 2016, and develop staff comments and gap analysis December 2016 NEI submits complete NEI 16-16 to the NRC for review Review suspended per NEIs request to evaluate the pending changes to EPRI technical guidance that underpins NEI 16-16 NRC decision on technical adequacy and whether to issue a potential interim endorsement letter To be determined NRC formally enters NEI 16-16 into the Regulatory Guide development process (if decision is made to endorse)
To be determined


MP #1C: Modernize NRCs current position on defense against potential common cause failure in I&C systems and components Activity                                                       Completion Date NRC efforts begin:                                             July 2017 Begin staff review to identify if there are policy issues that need to be taken to the Commission Present SECY to Commission for consideration                   June 2018 Begin implementing resolutions as directed by the             September 2018 Commission MP #2: Issue durable guidance for implementation of digital upgrades without NRC approval under 10 CFR 50.59 (full scope of systems)
62 MP #1C: Modernize NRCs current position on defense against potential common cause failure in I&C systems and components Activity Completion Date NRC efforts begin:
- Endorsement review of NEI 96-07, Appendix D Activity                                                           Completion Date NRC efforts begin:                                             April 2016 Initiate review and stakeholder interactions of NEI guidance document, NEI 96-07, Appendix D, Guidelines for 10 CFR 50.59 Evaluations NRC decision on technical adequacy and s whether to           June 2018 issue a potential interim endorsement letter NRC formally enters NEI 96-07 Appendix D into the             December 2018 Regulatory Guide development process (if decision is made to endorse)
Begin staff review to identify if there are policy issues that need to be taken to the Commission July 2017 Present SECY to Commission for consideration June 2018 Begin implementing resolutions as directed by the Commission September 2018 MP #2: Issue durable guidance for implementation of digital upgrades without NRC approval under 10 CFR 50.59 (full scope of systems)  
MP #3: Review Industrys process for using commercially available digital equipment Activity                                                       Completion Date NRC efforts begin:                                             April 2016 Public Meeting to discuss resolution of RIS 2016-05 public comments EPRI publishes research results                               October 2018 NEI Submits NEI 17-06 for NRC Review                           January 2019 NRC makes decision on technical adequacy                       April 2019 NRC staff completes audits of Safety Integrity Level           June 2020 certification organizations and accrediting entities NRC formally enters NEI 17-06 into the Regulatory Guide       July 2020 development process (if decision is made to endorse) 62
- Endorsement review of NEI 96-07, Appendix D Activity Completion Date NRC efforts begin:
Initiate review and stakeholder interactions of NEI guidance document, NEI 96-07, Appendix D, Guidelines for 10 CFR 50.59 Evaluations April 2016 NRC decision on technical adequacy and s whether to issue a potential interim endorsement letter June 2018 NRC formally enters NEI 96-07 Appendix D into the Regulatory Guide development process (if decision is made to endorse)
December 2018 MP #3: Review Industrys process for using commercially available digital equipment Activity Completion Date NRC efforts begin:
Public Meeting to discuss resolution of RIS 2016-05 public comments April 2016 EPRI publishes research results October 2018 NEI Submits NEI 17-06 for NRC Review January 2019 NRC makes decision on technical adequacy April 2019 NRC staff completes audits of Safety Integrity Level certification organizations and accrediting entities June 2020 NRC formally enters NEI 17-06 into the Regulatory Guide development process (if decision is made to endorse)
July 2020


MP #4A: Streamline the licensing process guidance - update to Interim Staff Guidance ISG-06 Activity                                                          Completion Date NRC begins effort:                                                February 2017 Conduct a series of public stakeholder meetings (e.g.,
63
public workshops) for additional feedback Issue final Draft revision of ISG-06 for public comment          July 2018 Issue final revision of ISG-06                                    December 2018 MP #4B: Develop strategic activities for long-term improvements to the regulatory infrastructure NRC begins effort to develop strategic plan to modernize          October 2017 overall regulatory infrastructure Consider evaluation of lessons learned from MP 1-4A              April 2018 progress Coordinate with stakeholders to identify potential regulatory June 2018 gaps and potential options for improving the regulatory infrastructure Develop additional detailed modernization plan for                August 2018 implementing tactical and strategic improvements to the regulatory infrastructure
: 27. Please describe actions taken and/or planned to prepare to review industry requests to use Accident Tolerant Fuel in existing reactors, including but not limited to actions taken and/or planned for lead test assemblies and fuel loads. Please include a milestone schedule and brief project plan for both evolutionary and revolutionary designs.
: 27. Please describe actions taken and/or planned to prepare to review industry requests to use Accident Tolerant Fuel in existing reactors, including but not limited to actions taken and/or planned for lead test assemblies and fuel loads. Please include a milestone schedule and brief project plan for both evolutionary and revolutionary designs.
The staff has finalized a draft project plan that outlines the strategy to efficiently and effectively license evolutionary and revolutionary accident tolerant fuel (ATF) designs. The draft plan covers all aspects of ATF, including fabrication, transportation, storage, and the regulatory framework for in-reactor performance (i.e., 10 CFR Parts 50, 70, 71, 72, and 100). The draft plan contains tasks covering regulatory and infrastructure needs (regulations and guidance),
The staff has finalized a draft project plan that outlines the strategy to efficiently and effectively license evolutionary and revolutionary accident tolerant fuel (ATF) designs. The draft plan covers all aspects of ATF, including fabrication, transportation, storage, and the regulatory framework for in-reactor performance (i.e., 10 CFR Parts 50, 70, 71, 72, and 100). The draft plan contains tasks covering regulatory and infrastructure needs (regulations and guidance),
Line 707: Line 873:
The NRC has recently communicated its position on the use of ATF lead test assemblies (LTAs) at Hatch Unit 1 (the first plant to insert ATF LTAs) planned for the spring of 2018 (ML17150A443). The NRC found that no exemption from the NRC regulations would be necessary for the plant; the NRCs interpretation of the plants technical specifications would allow the use of LTAs and that the licensees intent to conduct a full evaluation of the activity in accordance with 10 CFR 50.59 would be appropriate.
The NRC has recently communicated its position on the use of ATF lead test assemblies (LTAs) at Hatch Unit 1 (the first plant to insert ATF LTAs) planned for the spring of 2018 (ML17150A443). The NRC found that no exemption from the NRC regulations would be necessary for the plant; the NRCs interpretation of the plants technical specifications would allow the use of LTAs and that the licensees intent to conduct a full evaluation of the activity in accordance with 10 CFR 50.59 would be appropriate.
The staff has chartered a steering committee and working group to explore the development of generic guidance regarding the use of LTAs in commercial operating nuclear reactors and plans to have a position by early 2018.
The staff has chartered a steering committee and working group to explore the development of generic guidance regarding the use of LTAs in commercial operating nuclear reactors and plans to have a position by early 2018.
63
MP #4A: Streamline the licensing process guidance - update to Interim Staff Guidance ISG-06 Activity Completion Date NRC begins effort:
Conduct a series of public stakeholder meetings (e.g.,
public workshops) for additional feedback February 2017 Issue final Draft revision of ISG-06 for public comment July 2018 Issue final revision of ISG-06 December 2018 MP #4B: Develop strategic activities for long-term improvements to the regulatory infrastructure NRC begins effort to develop strategic plan to modernize overall regulatory infrastructure October 2017 Consider evaluation of lessons learned from MP 1-4A progress April 2018 Coordinate with stakeholders to identify potential regulatory gaps and potential options for improving the regulatory infrastructure June 2018 Develop additional detailed modernization plan for implementing tactical and strategic improvements to the regulatory infrastructure August 2018
 
64
: 28. Please describe actions taken and/or planned to improve the quality of cost benefit analyses conducted in association with new requirements, backfit analyses, or rulemaking, including the development of metrics for assessing the quality of cost-benefit analyses. Please include milestones for completing these actions and the guidance that is currently under revision.
: 28. Please describe actions taken and/or planned to improve the quality of cost benefit analyses conducted in association with new requirements, backfit analyses, or rulemaking, including the development of metrics for assessing the quality of cost-benefit analyses. Please include milestones for completing these actions and the guidance that is currently under revision.
The NRC has taken specific actions to improve the quality of cost-benefit analyses conducted in association with new requirements, backfit analyses, or rulemaking. The key milestones for these actions are described below.
The NRC has taken specific actions to improve the quality of cost-benefit analyses conducted in association with new requirements, backfit analyses, or rulemaking. The key milestones for these actions are described below.
Line 716: Line 886:
The staff informed the Commission of its planned two-phase approach for revising the content and structure of cost-benefit guidance documents. Phase 1 aligns regulatory guidance across NRCs business lines by restructuring and incorporating non-policy revisions to NRC cost-benefit guidance. This phase is underway, as described below. In Phase 2, staff will identify and analyze potential policy issues that could affect the NRCs cost-benefit guidance and present these issues to the Commission for consideration and approval. The staff then will incorporate final updates to guidance for conducting cost-benefit analyses that support backfitting decisions.
The staff informed the Commission of its planned two-phase approach for revising the content and structure of cost-benefit guidance documents. Phase 1 aligns regulatory guidance across NRCs business lines by restructuring and incorporating non-policy revisions to NRC cost-benefit guidance. This phase is underway, as described below. In Phase 2, staff will identify and analyze potential policy issues that could affect the NRCs cost-benefit guidance and present these issues to the Commission for consideration and approval. The staff then will incorporate final updates to guidance for conducting cost-benefit analyses that support backfitting decisions.
On August 14, 2014, in response to SRM-SECY-12-0157, the staff submitted SECY-14-0087, Qualitative Consideration of Factors in the Development of Regulatory Analyses and Backfit Analyses. In SECY-14-0087, the staff proposed updating the cost-benefit guidance to include a set of methods that could be used for the consideration of qualitative factors within a cost-benefit analysis for regulatory and backfit analyses.
On August 14, 2014, in response to SRM-SECY-12-0157, the staff submitted SECY-14-0087, Qualitative Consideration of Factors in the Development of Regulatory Analyses and Backfit Analyses. In SECY-14-0087, the staff proposed updating the cost-benefit guidance to include a set of methods that could be used for the consideration of qualitative factors within a cost-benefit analysis for regulatory and backfit analyses.
On December 16, 2014, in response to Commission direction to provide a regulatory gap analysis before developing new cost-benefit guidance, the staff submitted SECY-14-0143, Regulatory Gap Analysis of the Nuclear Regulatory Commissions Cost Benefit Regulations, Guidance and Practices. In SECY-14-0143, the staff described the review of current NRC guidance, methodologies, and tools used for cost-benefit determinations. The staff also described the results of its review of the NRC regulatory analyses that had been completed and identified differences across NRC business lines (e.g., material users, fuel cycle facilities, new and operating reactors) and procedures (i.e., regulatory analyses, backfit analyses). Finally, SECY-14-0143 included staffs gap analysis, and identified where additional guidance is needed to ensure consistency across the agency.
On December 16, 2014, in response to Commission direction to provide a regulatory gap analysis before developing new cost-benefit guidance, the staff submitted SECY-14-0143, Regulatory Gap Analysis of the Nuclear Regulatory Commissions Cost Benefit Regulations, Guidance and Practices. In SECY-14-0143, the staff described the review of current NRC guidance, methodologies, and tools used for cost-benefit determinations. The staff also described the results of its review of the NRC regulatory analyses that had been completed and identified differences across NRC business lines (e.g., material users, fuel cycle facilities, new and operating reactors) and procedures (i.e., regulatory analyses, backfit analyses). Finally, SECY-14-0143 included staffs gap analysis, and identified where additional guidance is needed to ensure consistency across the agency.  
64


On March 4, 2015, the Commission issued SRM-SECY-14-0087. The Commission approved the staffs plans for updating guidance regarding the use of qualitative factors, including the treatment of uncertainties, and directed the staff to focus the update on capturing best practices for the consideration of qualitative factors. The Commission also directed the staff to provide a toolkit for analysts regarding the consideration of qualitative factors.
65 On March 4, 2015, the Commission issued SRM-SECY-14-0087. The Commission approved the staffs plans for updating guidance regarding the use of qualitative factors, including the treatment of uncertainties, and directed the staff to focus the update on capturing best practices for the consideration of qualitative factors. The Commission also directed the staff to provide a toolkit for analysts regarding the consideration of qualitative factors.
In July 2015 and May 2017, the staff held two public meetings on the proposed cost-benefit guidance updates. The staff also held a public workshop in March 2016 to discuss proposed changes to the cost-benefit guidance. Meeting participants included industry representatives, government and nongovernment organizations, and other interested parties.
In July 2015 and May 2017, the staff held two public meetings on the proposed cost-benefit guidance updates. The staff also held a public workshop in March 2016 to discuss proposed changes to the cost-benefit guidance. Meeting participants included industry representatives, government and nongovernment organizations, and other interested parties.
The Phase 1 update identified in SECY-14-0002 and described above is underway. In April 2017, the NRC issued draft NUREG/BR-0058, Revision 5, Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission, and published a notice requesting public comment in the Federal Register (82 FR 18163; April 17, 2017). The staff received three comment submissions with a total of 58 individual comments from industry and members of the public.
The Phase 1 update identified in SECY-14-0002 and described above is underway. In April 2017, the NRC issued draft NUREG/BR-0058, Revision 5, Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission, and published a notice requesting public comment in the Federal Register (82 FR 18163; April 17, 2017). The staff received three comment submissions with a total of 58 individual comments from industry and members of the public.
The NRC staff considered this input when revising the NUREG, which is under review by agency management.
The NRC staff considered this input when revising the NUREG, which is under review by agency management.
The staff will submit NUREG/BR-0058, Revision 5, and five appendices to the Commission via a notation vote paper in early 2018 after completing management review. The following appendices will be included in this update:
The staff will submit NUREG/BR-0058, Revision 5, and five appendices to the Commission via a notation vote paper in early 2018 after completing management review. The following appendices will be included in this update:
* Appendix A, Qualitative Factors Assessment Tools
Appendix A, Qualitative Factors Assessment Tools Appendix B, Cost Estimating and Best Practices Appendix C, Treatment of Uncertainty Appendix D, Guidance on Regulatory Analysis Related to ASME Rules Appendix E, Special Circumstances and Relationship to Other Procedural Requirements Metrics for assessing the quality of cost-benefit analyses are contained in NUREG/BR-0058, Appendix B. Enclosure B-4 to Appendix B discusses the expectations for quality cost estimates and details the steps to ensure high-quality cost-benefit analyses are developed and presented to agency management. Additionally, the enclosure describes the steps to verify the quality of a cost-benefit analysis through various techniques for checking accuracy.
* Appendix B, Cost Estimating and Best Practices
* Appendix C, Treatment of Uncertainty
* Appendix D, Guidance on Regulatory Analysis Related to ASME Rules
* Appendix E, Special Circumstances and Relationship to Other Procedural Requirements Metrics for assessing the quality of cost-benefit analyses are contained in NUREG/BR-0058, Appendix B. Enclosure B-4 to Appendix B discusses the expectations for quality cost estimates and details the steps to ensure high-quality cost-benefit analyses are developed and presented to agency management. Additionally, the enclosure describes the steps to verify the quality of a cost-benefit analysis through various techniques for checking accuracy.
Following Commission review and approval of Revision 5 of NUREG/BR-0058, the staff will publish this updated final guidance. The staff will also conduct Phase 2 of the activity, as described in SECY-14-0002.
Following Commission review and approval of Revision 5 of NUREG/BR-0058, the staff will publish this updated final guidance. The staff will also conduct Phase 2 of the activity, as described in SECY-14-0002.
: 29. Please provide the status of the revised guidance currently under development to clarify the use of qualitative factors, including milestones and the projected date for completion. In addition to this revised guidance, please list and briefly describe any actions taken and/or planned to improve the use of quantitative factors in regulatory analyses required for rulemaking, in the regulatory analyses required under the Backfit Rule, and in the Reactor Oversight Process Significance Determination Process.
: 29. Please provide the status of the revised guidance currently under development to clarify the use of qualitative factors, including milestones and the projected date for completion. In addition to this revised guidance, please list and briefly describe any actions taken and/or planned to improve the use of quantitative factors in regulatory analyses required for rulemaking, in the regulatory analyses required under the Backfit Rule, and in the Reactor Oversight Process Significance Determination Process.
NUREG/BR-0058, Revision 5, and five supporting appendices are under final review by agency management. The staff is scheduled to submit these documents to the Commission via a notation vote paper in early 2018.
NUREG/BR-0058, Revision 5, and five supporting appendices are under final review by agency management. The staff is scheduled to submit these documents to the Commission via a notation vote paper in early 2018.  
65


Following Commission review and approval of Revision 5 of NUREG/BR-0058, the staff will publish this updated final guidance. A draft of the NUREG was issued for public comment and is available for interim staff use. In conducting its regulatory analyses, the staff is implementing the best practices and lessons learned that are contained within this draft revision of NUREG/BR-0058.
66 Following Commission review and approval of Revision 5 of NUREG/BR-0058, the staff will publish this updated final guidance. A draft of the NUREG was issued for public comment and is available for interim staff use. In conducting its regulatory analyses, the staff is implementing the best practices and lessons learned that are contained within this draft revision of NUREG/BR-0058.
In revising this cost-benefit guidance, the staff focused on improving methods for quantitative analyses, including the treatment of uncertainty and the development of realistic estimates of the cost of implementing proposed requirements. Specifically, the staff developed two appendices to NUREG/BR-0058, Revision 5 to guide the staff in these areas.
In revising this cost-benefit guidance, the staff focused on improving methods for quantitative analyses, including the treatment of uncertainty and the development of realistic estimates of the cost of implementing proposed requirements. Specifically, the staff developed two appendices to NUREG/BR-0058, Revision 5 to guide the staff in these areas.
* Appendix B, Cost Estimating and Best Practices, provides expanded guidance on incorporating cost-estimating best practices, including estimating life-cycle costs.
Appendix B, Cost Estimating and Best Practices, provides expanded guidance on incorporating cost-estimating best practices, including estimating life-cycle costs.
* Appendix C, The Treatment of Uncertainty, expands on the existing guidance for performing uncertainty and sensitivity analyses for cost-benefit analyses.
Appendix C, The Treatment of Uncertainty, expands on the existing guidance for performing uncertainty and sensitivity analyses for cost-benefit analyses.
In addition to the improved methods for quantitative analyses, the revised cost-benefit guidance directs the staff to quantify the estimates of costs and benefits to the extent possible. However, the staff acknowledges that some attributes in regulatory analyses are difficult to quantify, and require additional resources to develop a strictly quantitative analysis. To address this gap, staff developed a toolkit to enable analysts to clearly present analyses of qualitative results in a transparent way that decision makers, and stakeholders can understand.
In addition to the improved methods for quantitative analyses, the revised cost-benefit guidance directs the staff to quantify the estimates of costs and benefits to the extent possible. However, the staff acknowledges that some attributes in regulatory analyses are difficult to quantify, and require additional resources to develop a strictly quantitative analysis. To address this gap, staff developed a toolkit to enable analysts to clearly present analyses of qualitative results in a transparent way that decision makers, and stakeholders can understand.
* Appendix A, Qualitative Factors Assessment Tools, identifies best practices for the consideration of qualitative factors and describes a number of methods that can be used to support the NRCs evidence-based, quantitative, and analytical approach to decision-making. The guidance clearly states that these methods (1) should only be used when quantification may not be practical, (2) are not a substitute for collecting accurate information to develop realistic cost estimates, and (3) do not constitute an expansion of the consideration of qualitative factors in regulatory, backfit, or environmental analyses.
Appendix A, Qualitative Factors Assessment Tools, identifies best practices for the consideration of qualitative factors and describes a number of methods that can be used to support the NRCs evidence-based, quantitative, and analytical approach to decision-making. The guidance clearly states that these methods (1) should only be used when quantification may not be practical, (2) are not a substitute for collecting accurate information to develop realistic cost estimates, and (3) do not constitute an expansion of the consideration of qualitative factors in regulatory, backfit, or environmental analyses.
Revision 5 of NUREG/BR-0058 is intended to meet the following objectives:
Revision 5 of NUREG/BR-0058 is intended to meet the following objectives:
* Refocus and expand guidance on cost-benefit analysis across the agency
Refocus and expand guidance on cost-benefit analysis across the agency Emphasize quantification and provides methods for creating realistic estimates Provide methods for assessing factors that are difficult to quantify Incorporate cost estimating best practices identified in U.S. Government Accountability Office (GAO) guidance and in recommendations from GAO in GAO-15-98, Nuclear Regulatory Commission: NRC Needs to Improve Its Cost Estimates by Incorporating More Best Practices, dated December 12, 2014 Expand guidance on the treatment of uncertainties Enhance transparency of analysis for the decision-maker With regard to the use of qualitative factors in the Reactor Oversight Process Significance Determination Process (SDP), the SRM for SECY-13-0137 directed the staff, in part, to evaluate the need to provide additional clarity on the use of qualitative factors for operating reactors to provide more transparency and predictability to the process. The staff expects to respond to this direction by mid-2018.  
* Emphasize quantification and provides methods for creating realistic estimates
 
* Provide methods for assessing factors that are difficult to quantify
67
* Incorporate cost estimating best practices identified in U.S. Government Accountability Office (GAO) guidance and in recommendations from GAO in GAO-15-98, Nuclear Regulatory Commission: NRC Needs to Improve Its Cost Estimates by Incorporating More Best Practices, dated December 12, 2014
* Expand guidance on the treatment of uncertainties
* Enhance transparency of analysis for the decision-maker With regard to the use of qualitative factors in the Reactor Oversight Process Significance Determination Process (SDP), the SRM for SECY-13-0137 directed the staff, in part, to evaluate the need to provide additional clarity on the use of qualitative factors for operating reactors to provide more transparency and predictability to the process. The staff expects to respond to this direction by mid-2018.
66
: 30. Please provide a list of all final generic regulatory actions issued in the last 3 years. Please include:
: 30. Please provide a list of all final generic regulatory actions issued in the last 3 years. Please include:
: a. Whether the item was reviewed by Committee for the Review of Generic Requirements (CRGR);
: a. Whether the item was reviewed by Committee for the Review of Generic Requirements (CRGR);
Line 757: Line 917:
Items for CRGR review are forwarded by the agencys program offices or are directed for review by the EDO. The table below illustrates that only a few final generic agency actions are reviewed by the CRGR to assess if generic backfitting concerns exist. Most backfitting issues are resolved during management review and legal review, or identified during interactions with external stakeholders.
Items for CRGR review are forwarded by the agencys program offices or are directed for review by the EDO. The table below illustrates that only a few final generic agency actions are reviewed by the CRGR to assess if generic backfitting concerns exist. Most backfitting issues are resolved during management review and legal review, or identified during interactions with external stakeholders.
Rules, orders, bulletins, GLs, and RISs are final generic regulatory actions that are reviewed and evaluated to screen for potential backfitting concerns and new staff positions. CRGR reviews these items when certain criteria are met, including:
Rules, orders, bulletins, GLs, and RISs are final generic regulatory actions that are reviewed and evaluated to screen for potential backfitting concerns and new staff positions. CRGR reviews these items when certain criteria are met, including:
* Stakeholders or NRC staff identify concerns regarding backfitting or regulatory analysis
Stakeholders or NRC staff identify concerns regarding backfitting or regulatory analysis The EDO directs the review or an office director requests review Use of the compliance exception or the adequate protection exceptions to justify backfitting For rulemaking, if there are finality concerns or possible backfitting qualitative factors were used to justify a rulemaking with significant costs, or substantial statistical uncertainty exists in the qualitative benefit determination in the backfit analysis.
* The EDO directs the review or an office director requests review
* Use of the compliance exception or the adequate protection exceptions to justify backfitting
* For rulemaking, if there are finality concerns or possible backfitting qualitative factors were used to justify a rulemaking with significant costs, or substantial statistical uncertainty exists in the qualitative benefit determination in the backfit analysis.
For rulemaking, over the last 3 years CRGR reviews were not conducted because the criteria for requiring CRGR review were not met for any of the rulemakings listed in the table. However, under the revised criteria, the CRGR is now more actively reviewing rulemaking activities. For example, in June 2017, the CRGR reviewed a draft proposed rule on cybersecurity at fuel cycle facilities. This marked the first CRGR review using the new criteria and guidance. The draft proposed rule is currently with the Commission for its consideration. Also, on October 25, 2017, the CRGR reviewed the draft final rule on enhanced weapons, firearms background checks, and security event notifications. In reviewing both of these packages, the CRGR requested additional information to ensure that the staff was not unnecessarily imposing backfits on the licensees.
For rulemaking, over the last 3 years CRGR reviews were not conducted because the criteria for requiring CRGR review were not met for any of the rulemakings listed in the table. However, under the revised criteria, the CRGR is now more actively reviewing rulemaking activities. For example, in June 2017, the CRGR reviewed a draft proposed rule on cybersecurity at fuel cycle facilities. This marked the first CRGR review using the new criteria and guidance. The draft proposed rule is currently with the Commission for its consideration. Also, on October 25, 2017, the CRGR reviewed the draft final rule on enhanced weapons, firearms background checks, and security event notifications. In reviewing both of these packages, the CRGR requested additional information to ensure that the staff was not unnecessarily imposing backfits on the licensees.
Regulatory guides, standard review plans, and interim staff guidance, are only reviewed by CRGR when concerns are raised during staff review regarding potential generic backfitting.
Regulatory guides, standard review plans, and interim staff guidance, are only reviewed by CRGR when concerns are raised during staff review regarding potential generic backfitting.
These documents are intended to provide acceptable approaches for licensees or applicants to meet NRC requirements, or for the NRC staff to confirm the adequacy of proposed approaches.
These documents are intended to provide acceptable approaches for licensees or applicants to meet NRC requirements, or for the NRC staff to confirm the adequacy of proposed approaches.
Additionally, adopting new regulatory guides is intended to be voluntary for licensees and 67
Additionally, adopting new regulatory guides is intended to be voluntary for licensees and  


applicants. For limited instances where regulatory guides may result in potential backfits or new staff positions, the CRGR conducts a review.
68 applicants. For limited instances where regulatory guides may result in potential backfits or new staff positions, the CRGR conducts a review.
The table below provides NRC final generic regulatory actions issued within the last 3 years.
The table below provides NRC final generic regulatory actions issued within the last 3 years.
For the response, the staff has included final rules, orders, bulletins, RISs, and GLs.
For the response, the staff has included final rules, orders, bulletins, RISs, and GLs.
Summary of Final Generic Regulatory Actions over the Last 3 Years Item #         Title                       Issuance         CRGR1         CRGR           NRC Date            Review        Recommen        Backfitting dation          Review RIS-18-01     Common Violations Cited 01/22/18              None          NA              No Backfitting During First 2 Years of 10 CFR Part 37, "Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material,"
Summary of Final Generic Regulatory Actions over the Last 3 Years Item #
Implementation and Guidance Documents Available to Support Rule Implementation 10 CFR        Approval of American        01/17/18         None           NA             No Backfitting Part 50       Society of Mechanical Engineers' Code Cases       83 FR 2331 10 CFR 2      Adjustment of Civil          01/12/18         None           NA             No Backfitting and 13         Penalties for Inflation for Fiscal Year 2018             83 FR 1515 RIS-17-08     Process for Scheduling       12/21/17        None          NA              No Backfitting and Allocating Resources for Fiscal Years 2020 Through 2022 for the Review of New Licensing Applications for Light-Water Reactors and Non-Light-Water Reactors 10 CFR        Miscellaneous                11/15/17;        None           NA             No Backfitting Parts 2, 9,   Corrections                  82 FR 40, 50,                                     52823 61, 71, 73, and 110 1
Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review RIS-18-01 Common Violations Cited During First 2 Years of 10 CFR Part 37, "Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material,"
None - indicates that the item was administrative in nature or did not meet thresholds for CRGR backfitting review, informal reviews - were conducted by the members without a meeting. Formal Reviews - are these items that a meeting was conducted to assess potential backfitting concerns.
Implementation and Guidance Documents Available to Support Rule Implementation 01/22/18 None NA No Backfitting 10 CFR Part 50 Approval of American Society of Mechanical Engineers' Code Cases 01/17/18 83 FR 2331 None NA No Backfitting 10 CFR 2 and 13 Adjustment of Civil Penalties for Inflation for Fiscal Year 2018 01/12/18 83 FR 1515 None NA No Backfitting RIS-17-08 Process for Scheduling and Allocating Resources for Fiscal Years 2020 Through 2022 for the Review of New Licensing Applications for Light-Water Reactors and Non-Light-Water Reactors 12/21/17 None NA No Backfitting 10 CFR Parts 2, 9, 40, 50, 61, 71, 73, and 110 Miscellaneous Corrections 11/15/17; 82 FR 52823 None NA No Backfitting 1 None - indicates that the item was administrative in nature or did not meet thresholds for CRGR backfitting review, informal reviews - were conducted by the members without a meeting. Formal Reviews - are these items that a meeting was conducted to assess potential backfitting concerns.  
68


Summary of Final Generic Regulatory Actions over the Last 3 Years Item #   Title                       Issuance CRGR1       CRGR     NRC Date      Review      Recommen Backfitting dation  Review RIS-17-06 NRC Policy on Use of         09/19/17 None       NA       No Backfitting Combination Dosimetry Devices During Industrial Radiographic Operations RIS-17-05 Administration of 10 CFR     09/13/17 None       NA       No Backfitting Part 72 Certificate of Compliance Corrections and Revisions RIS-17-04 Clarification on the         08/30/17  Informal    NA      No Backfitting Implementation of                     Review Compensatory Measures for Protective Strategy Deficiencies or Degraded or Inoperable Security Systems, Equipment, or Components 10 CFR   American Society of         07/18/17; None       NA       Two changes Part 50  Mechanical Engineers        82 FR                          resulted in an Codes and Code Cases        329034                        adequate protection backfit exception (Code Case N-729-4 and Code Case N-770-2) 10 CFR   Fee Recovery for Fiscal     06/30/17; None       NA       No Backfitting Parts 170 Year 2017                    82 FR and 171                                30682 RIS-17-03 Preparation and             04/05/17 None       NA       No Backfitting Scheduling of Operator Licensing Examinations RIS-17-02 Applicability of Title 10 of 02/08/17  None        NA      No Backfitting the Code of Federal Regulations Part 37 to Non-Manufacturing and Distribution Service Provider Licensees RIS-17-01 Human Reliability and       02/02/17 None       NA       No Backfitting Human Performance Database 69
69 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #
Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review RIS-17-06 NRC Policy on Use of Combination Dosimetry Devices During Industrial Radiographic Operations 09/19/17 None NA No Backfitting RIS-17-05 Administration of 10 CFR Part 72 Certificate of Compliance Corrections and Revisions 09/13/17 None NA No Backfitting RIS-17-04 Clarification on the Implementation of Compensatory Measures for Protective Strategy Deficiencies or Degraded or Inoperable Security Systems, Equipment, or Components 08/30/17 Informal Review NA No Backfitting 10 CFR Part 50 American Society of Mechanical Engineers Codes and Code Cases 07/18/17; 82 FR 329034 None NA Two changes resulted in an adequate protection backfit exception (Code Case N-729-4 and Code Case N-770-2) 10 CFR Parts 170 and 171 Fee Recovery for Fiscal Year 2017 06/30/17; 82 FR 30682 None NA No Backfitting RIS-17-03 Preparation and Scheduling of Operator Licensing Examinations 04/05/17 None NA No Backfitting RIS-17-02 Applicability of Title 10 of the Code of Federal Regulations Part 37 to Non-Manufacturing and Distribution Service Provider Licensees 02/08/17 None NA No Backfitting RIS-17-01 Human Reliability and Human Performance Database 02/02/17 None NA No Backfitting  


Summary of Final Generic Regulatory Actions over the Last 3 Years Item #   Title                     Issuance   CRGR1       CRGR     NRC Date        Review      Recommen Backfitting dation  Review 10 CFR   Adjustment of Civil       01/24/17;   None         NA       No Backfitting Parts 2  Penalties for Inflation  82 FR 8133 and 13 10 CFR   List of Approved Spent   Published 6 None        NA      No Backfitting Part 72  Fuel Storage Casks       Certificate of Compliance (COC) rules in 2017 10 CFR   Increase in the Maximum   12/30/16;  None        NA      No Backfitting Part 140  Amount of Primary         81 FR Nuclear Liability         96347 Insurance 10 CFR    Update to Incorporate    12/30/16;   None         NA       No Backfitting Parts 2   Freedom of Information   81 FR and 9    Act Improvement Act of   96344 2016 Requirements RIS-16-12 NRC Employee Access       11/22/16   None         NA       No Backfitting to Switchyards at Licensee Facilities RIS-16-11 Requests to Dispose of   11/13/16    Informal    Endorsed No Backfitting Very Low-Level                       Review Radioactive Waste Pursuant to 10 CFR 20.2002 RIS  Decommissioning          09/27/16   None        NA      No Backfitting 19, Rev 1 Timeliness Rule Implementation and Associated Regulatory Relief RIS-16-10 License Amendment         08/05/16    Informal    Endorsed No Backfitting Requests for Changes to               Review Emergency Response Organization Staffing and Augmentation 10 CFR   Update to Transcript     07/20/16;   None         NA       No Backfitting Part 2    Correction Procedures    81 FR 47005 70
70 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #
Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review 10 CFR Parts 2 and 13 Adjustment of Civil Penalties for Inflation 01/24/17; 82 FR 8133 None NA No Backfitting 10 CFR Part 72 List of Approved Spent Fuel Storage Casks Published 6 Certificate of Compliance (COC) rules in 2017 None NA No Backfitting 10 CFR Part 140 Increase in the Maximum Amount of Primary Nuclear Liability Insurance 12/30/16; 81 FR 96347 None NA No Backfitting 10 CFR Parts 2 and 9 Update to Incorporate Freedom of Information Act Improvement Act of 2016 Requirements 12/30/16; 81 FR 96344 None NA No Backfitting RIS-16-12 NRC Employee Access to Switchyards at Licensee Facilities 11/22/16 None NA No Backfitting RIS-16-11 Requests to Dispose of Very Low-Level Radioactive Waste Pursuant to 10 CFR 20.2002 11/13/16 Informal Review Endorsed No Backfitting RIS 19, Rev 1 Decommissioning Timeliness Rule Implementation and Associated Regulatory Relief 09/27/16 None NA No Backfitting RIS-16-10 License Amendment Requests for Changes to Emergency Response Organization Staffing and Augmentation 08/05/16 Informal Review Endorsed No Backfitting 10 CFR Part 2 Update to Transcript Correction Procedures 07/20/16; 81 FR 47005 None NA No Backfitting  


Summary of Final Generic Regulatory Actions over the Last 3 Years Item #   Title                   Issuance     CRGR1       CRGR     NRC Date        Review      Recommen Backfitting dation  Review 10 CFR   Adjustment of Civil     07/01/16;   None         NA       No Backfitting Parts 2  Penalties for Inflation  81 FR and 13                            43019 10 CFR    Fee Recovery for Fiscal 06/24/16;   None         NA       No Backfitting Parts 9,  Year 2016                81 FR 170, and                          41171 171 RIS-16-09 Preparation and         06/16/16     None         NA       No Backfitting Scheduling of Operator Licensing Examinations RIS-16-08 Process for Scheduling   06/07/16    None        NA      No Backfitting and Allocating Resources in Fiscal Year 2019 for the Review of New Licensing Applications for Light-Water Reactors and Non-Light-Water Reactors 10 CFR   Variable Annual Fee     05/24/16;   None         NA       No Backfitting Parts 170 Structure for Small      81 FR and 171  Modular Reactors        32617 RIS-16-07 Containment Shell or     05/09/16     Informal     Endorsed No Backfitting Liner Moisture Barrier                Review Inspection RIS-16-06 NRC Regulation of       05/09/16    None        NA      No Backfitting Radium-226 Under Military Control and for Coordination on the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA)
71 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #
Response Actions at Department of Defense Sites with Radioactive Materials 71
Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review 10 CFR Parts 2 and 13 Adjustment of Civil Penalties for Inflation 07/01/16; 81 FR 43019 None NA No Backfitting 10 CFR Parts 9, 170, and 171 Fee Recovery for Fiscal Year 2016 06/24/16; 81 FR 41171 None NA No Backfitting RIS-16-09 Preparation and Scheduling of Operator Licensing Examinations 06/16/16 None NA No Backfitting RIS-16-08 Process for Scheduling and Allocating Resources in Fiscal Year 2019 for the Review of New Licensing Applications for Light-Water Reactors and Non-Light-Water Reactors 06/07/16 None NA No Backfitting 10 CFR Parts 170 and 171 Variable Annual Fee Structure for Small Modular Reactors 05/24/16; 81 FR 32617 None NA No Backfitting RIS-16-07 Containment Shell or Liner Moisture Barrier Inspection 05/09/16 Informal Review Endorsed No Backfitting RIS-16-06 NRC Regulation of Radium-226 Under Military Control and for Coordination on the Comprehensive Environmental
: Response, Compensation, and Liability Act (CERCLA)
Response Actions at Department of Defense Sites with Radioactive Materials 05/09/16 None NA No Backfitting


Summary of Final Generic Regulatory Actions over the Last 3 Years Item #   Title                     Issuance   CRGR1       CRGR     NRC Date        Review      Recommen Backfitting dation  Review RIS-16-05 Embedded Digital         04/29/16   Informal     Endorsed No Backfitting Devices in Safety-                    Review Related Systems RIS-16-04 Clarification of 10 CFR   04/19/16    Informal    Endorsed No Backfitting 50.46 Reporting                       Review Requirements and Recent Issues with Related Guidance Not Approved for Use RIS-16-03 10 CFR 50.59 Issues       04/13/16    None        NA      No Backfitting Identified in NRC's San Onofre Steam Generator Tube Degradation Lessons Learned Report GL-16-01 Monitoring of Neutron-   04/07/16   Formal       Endorsed No Backfitting Absorbing Materials in Spent Fuels Pools RIS-16-02 Design Basis Issues       03/23/16    None        NA      No Backfitting Related to Tube-to-Tubesheet Joints in Pressurized-Water Reactor Steam Generators RIS-16-01 Nuclear Energy Institute 03/16/16    Informal    Endorsed No Backfitting Guidance for the Use of               Review Accreditation in Lieu of Commercial Grade Surveys for Procurement of Laboratory Calibration and Test Services RIS  Planned Licensing Action  01/15/16   None        NA      No Backfitting 16, Rev 1 Submittals for All Power Reactor Licensees 10 CFR   List of Approved Spent   Published 5 None        NA      No Backfitting Part 72  Fuel Storage Casks       COC rules in 2016 RIS-15-17 Review and Submission     12/23/15   None         NA       No Backfitting of Updates to Final Safety Analysis Reports, Emergency 72
72 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #
Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review RIS-16-05 Embedded Digital Devices in Safety-Related Systems 04/29/16 Informal Review Endorsed No Backfitting RIS-16-04 Clarification of 10 CFR 50.46 Reporting Requirements and Recent Issues with Related Guidance Not Approved for Use 04/19/16 Informal Review Endorsed No Backfitting RIS-16-03 10 CFR 50.59 Issues Identified in NRC's San Onofre Steam Generator Tube Degradation Lessons Learned Report 04/13/16 None NA No Backfitting GL-16-01 Monitoring of Neutron-Absorbing Materials in Spent Fuels Pools 04/07/16 Formal Endorsed No Backfitting RIS-16-02 Design Basis Issues Related to Tube-to-Tubesheet Joints in Pressurized-Water Reactor Steam Generators 03/23/16 None NA No Backfitting RIS-16-01 Nuclear Energy Institute Guidance for the Use of Accreditation in Lieu of Commercial Grade Surveys for Procurement of Laboratory Calibration and Test Services 03/16/16 Informal Review Endorsed No Backfitting RIS 16, Rev 1 Planned Licensing Action Submittals for All Power Reactor Licensees 01/15/16 None NA No Backfitting 10 CFR Part 72 List of Approved Spent Fuel Storage Casks Published 5 COC rules in 2016 None NA No Backfitting RIS-15-17 Review and Submission of Updates to Final Safety Analysis Reports, Emergency 12/23/15 None NA No Backfitting  


Summary of Final Generic Regulatory Actions over the Last 3 Years Item #   Title                     Issuance   CRGR1       CRGR     NRC Date      Review      Recommen Backfitting dation  Review Preparedness Documents, and Fire Protection Documents RIS   Decommissioning            12/21/15  None        NA      No Backfitting 19, Rev 0 Timeliness Rule Implementation and Associated Regulatory Relief RIS-15-18 Sodium Iodide-131 (I-     12/14/15   None         NA       No Backfitting 131) Patient Release Information Collection RIS-15-15 Information Regarding a   12/04/15  Informal    Endorsed No Backfitting Specific Exemption in the             Review Requirements for the Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material RIS  Planned Licensing Action  11/25/15   None        NA      No Backfitting 16, Rev 0 Submittals for All Power Reactor Licensees RIS-15-13 Seismic Stability Analysis 11/12/15   None         NA       No Backfitting Methodologies for Spent Fuel Dry Cask RIS-15-11 Protective Action         11/05/15  Informal    Endorsed No Backfitting Recommendations for                   Review Members of the Public on Bodies of Water 10 CFR   Cyber Security Event       11/02/15; None         NA       No Backfitting Part 73  Notifications              80 FR 67264 RIS-15-14 Issuance of Enforcement   10/30/15  None        NA      No Backfitting Guidance Memorandum
73 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #
          - Emergency Plan and Emergency Plan Implementing Procedure Updates 73
Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review Preparedness Documents, and Fire Protection Documents RIS 19, Rev 0 Decommissioning Timeliness Rule Implementation and Associated Regulatory Relief 12/21/15 None NA No Backfitting RIS-15-18 Sodium Iodide-131 (I-131) Patient Release Information Collection 12/14/15 None NA No Backfitting RIS-15-15 Information Regarding a Specific Exemption in the Requirements for the Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material 12/04/15 Informal Review Endorsed No Backfitting RIS 16, Rev 0 Planned Licensing Action Submittals for All Power Reactor Licensees 11/25/15 None NA No Backfitting RIS-15-13 Seismic Stability Analysis Methodologies for Spent Fuel Dry Cask 11/12/15 None NA No Backfitting RIS-15-11 Protective Action Recommendations for Members of the Public on Bodies of Water 11/05/15 Informal Review Endorsed No Backfitting 10 CFR Part 73 Cyber Security Event Notifications 11/02/15; 80 FR 67264 None NA No Backfitting RIS-15-14 Issuance of Enforcement Guidance Memorandum  
- Emergency Plan and Emergency Plan Implementing Procedure Updates 10/30/15 None NA No Backfitting


Summary of Final Generic Regulatory Actions over the Last 3 Years Item #   Title                     Issuance   CRGR1       CRGR     NRC Date        Review      Recommen Backfitting dation  Review 10 CFR   Hearings on Challenges   10/20/15;   None         NA       No Backfitting Parts 2  to the Immediate          80 FR and 150  Effectiveness of Orders  63409 10 CFR   Revisions to the Petition 10/07/15;   None         NA       No Backfitting Part 2    for Rulemaking Process    80 FR 60513 10 CFR   List of Approved Spent   08/18/15;  None        NA      No Backfitting Part 72  Fuel Storage Casks:       80 FR Holtec international HI- 49887 STORM 100 Cask System, Certificate of Compliance No. 1014, Amendment No. 8, Revision 1 RIS-15-10 Applicability of ASME     07/16/15    Formal      Endorsed No Backfitting Code Case N-770-1 As Conditioned in 10 CFR 50.55a, "Code and Standards," to Branch Connection Butt Welds RIS-15-09 Implementation of         07/09/15   None         NA       No Backfitting Fingerprinting Requirements for Non-Power Reactors 10 CFR   Fee Recovery for Fiscal   06/30/15;   None         NA       No Backfitting Parts 170 Year 2015                80 FR and 171                            37431 RIS-15-08 Oversight of Counterfeit, 06/24/15   None         NA       No Backfitting Fraudulent and Suspect Items in the Nuclear Industry GL-15-01 Treatment of Natural     06/22/15   Formal       Endorsed No Backfitting Phenomena Hazards in Fuel Cycle Facilities 10 CFR   Transportation Safety     06/12/15;   None         NA       No Backfitting Part 71  Requirements and          80 FR Harmonization with        33987 International Atomic Energy Agency 74
74 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #
Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review 10 CFR Parts 2 and 150 Hearings on Challenges to the Immediate Effectiveness of Orders 10/20/15; 80 FR 63409 None NA No Backfitting 10 CFR Part 2 Revisions to the Petition for Rulemaking Process 10/07/15; 80 FR 60513 None NA No Backfitting 10 CFR Part 72 List of Approved Spent Fuel Storage Casks:
Holtec international HI-STORM 100 Cask System, Certificate of Compliance No. 1014, Amendment No. 8, Revision 1 08/18/15; 80 FR 49887 None NA No Backfitting RIS-15-10 Applicability of ASME Code Case N-770-1 As Conditioned in 10 CFR 50.55a, "Code and Standards," to Branch Connection Butt Welds 07/16/15 Formal Endorsed No Backfitting RIS-15-09 Implementation of Fingerprinting Requirements for Non-Power Reactors 07/09/15 None NA No Backfitting 10 CFR Parts 170 and 171 Fee Recovery for Fiscal Year 2015 06/30/15; 80 FR 37431 None NA No Backfitting RIS-15-08 Oversight of Counterfeit, Fraudulent and Suspect Items in the Nuclear Industry 06/24/15 None NA No Backfitting GL-15-01 Treatment of Natural Phenomena Hazards in Fuel Cycle Facilities 06/22/15 Formal Endorsed No Backfitting 10 CFR Part 71 Transportation Safety Requirements and Harmonization with International Atomic Energy Agency 06/12/15; 80 FR 33987 None NA No Backfitting  


Summary of Final Generic Regulatory Actions over the Last 3 Years Item #       Title                       Issuance         CRGR1         CRGR             NRC Date              Review        Recommen        Backfitting dation          Review Transportation Requirements; Revisions RIS-15-06     Tornado Missile             06/10/15         Formal       Endorsed         No Backfitting Protection RIS-15-07     Process for Scheduling       05/11/15          None          NA              No Backfitting and Allocating Resources in FY 2017 for the Review of New Licensing Applications for Large Light-Water Reactors and Small Modular Reactors RIS-15-05     Preparation and             04/20/15         None         NA               No Backfitting Scheduling of Operator Licensing Examinations RIS-15-04     Withdrawal of               04/14/15         None         NA               No Backfitting Administrative Letter 93-01 10 CFR       List of Approved Spent       03/06/15;        None          NA              No Backfitting Part 72      Fuel Storage Casks:         80 FR Holtec international HI-     12073 STORM Underground Maximum Capacity Canister Storage System, Certificate of Compliance No. 1040 RIS-15-03     Identifying and Reporting   02/24/15         None         NA               No Backfitting Security Incidents Under 10CFR Part 37 RIS-15-02     Reporting of H-3, C-14,     02/18/15          None          NA              No Backfitting Tc-99, and I-129 on the Uniform Waste Manifest
75 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #
Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review Transportation Requirements; Revisions RIS-15-06 Tornado Missile Protection 06/10/15 Formal Endorsed No Backfitting RIS-15-07 Process for Scheduling and Allocating Resources in FY 2017 for the Review of New Licensing Applications for Large Light-Water Reactors and Small Modular Reactors 05/11/15 None NA No Backfitting RIS-15-05 Preparation and Scheduling of Operator Licensing Examinations 04/20/15 None NA No Backfitting RIS-15-04 Withdrawal of Administrative Letter 93-01 04/14/15 None NA No Backfitting 10 CFR Part 72 List of Approved Spent Fuel Storage Casks:
Holtec international HI-STORM Underground Maximum Capacity Canister Storage System, Certificate of Compliance No. 1040 03/06/15; 80 FR 12073 None NA No Backfitting RIS-15-03 Identifying and Reporting Security Incidents Under 10CFR Part 37 02/24/15 None NA No Backfitting RIS-15-02 Reporting of H-3, C-14, Tc-99, and I-129 on the Uniform Waste Manifest 02/18/15 None NA No Backfitting
: 31. Please provide a list and brief description of all facility specific backfits issued in the reporting period.
: 31. Please provide a list and brief description of all facility specific backfits issued in the reporting period.
None.
None.  
75
 
76
: 32. For matters reviewed by the CRGR, please provide 12-month and 3-year rolling averages for the following metrics:
: 32. For matters reviewed by the CRGR, please provide 12-month and 3-year rolling averages for the following metrics:
: a. For the number of issues reviewed formally: the percentage accepted for imposition on industry and the percentage rejected based on cost-benefit or Backfit concerns; and
: a. For the number of issues reviewed formally: the percentage accepted for imposition on industry and the percentage rejected based on cost-benefit or Backfit concerns; and
: b. For the number of issues reviewed informally: the percentage accepted for imposition on industry and the percentage rejected based on cost-benefit or Backfit concerns.
: b. For the number of issues reviewed informally: the percentage accepted for imposition on industry and the percentage rejected based on cost-benefit or Backfit concerns.
12-Month Summary of CRGR Review Decisions of Potential Backfit Issues Percentage Accepted or         Percentage Rejected         Percentage Review Type &            Endorsed with          Based on Backfit       Endorsed without Outcome                Backfitting              Concerns                Backfitting Informal Reviews               0.0%                     0.0%                 100.0%
12-Month Summary of CRGR Review Decisions of Potential Backfit Issues Review Type &
Formal Reviews               20.0%                   20.0%                   60.0%
Outcome Percentage Accepted or Endorsed with Backfitting Percentage Rejected Based on Backfit Concerns Percentage Endorsed without Backfitting Informal Reviews 0.0%
3-Year Summary of CRGR Review Decisions of Potential Backfit Issues Percentage Accepted or         Percentage Rejected         Percentage Review Type &            Endorsed with          Based on Backfit       Endorsed without Outcome                Backfitting              Concerns                Backfitting Informal Reviews               0.0%                     0.0%                 100.0%
0.0%
Formal Reviews               18.2%                     9.1%                   72.7%
100.0%
Formal Reviews 20.0%
20.0%
60.0%
3-Year Summary of CRGR Review Decisions of Potential Backfit Issues Review Type &
Outcome Percentage Accepted or Endorsed with Backfitting Percentage Rejected Based on Backfit Concerns Percentage Endorsed without Backfitting Informal Reviews 0.0%
0.0%
100.0%
Formal Reviews 18.2%
9.1%
72.7%
Comments:
Comments:
: 1. As of January 31, 2018, for the rolling 3-year period, the CRGR has completed 28 reviews for potential backfits. Completed reviews include 17 informal reviews and 11 formal reviews.
: 1. As of January 31, 2018, for the rolling 3-year period, the CRGR has completed 28 reviews for potential backfits. Completed reviews include 17 informal reviews and 11 formal reviews.
Line 808: Line 985:
: c. A review of proposed regulatory changes that are currently in process to ensure that regulatory actions are appropriately informed by the requirements of 10 CFR 50.109.
: c. A review of proposed regulatory changes that are currently in process to ensure that regulatory actions are appropriately informed by the requirements of 10 CFR 50.109.
Examples of such actions could include but are not limited to the following:
Examples of such actions could include but are not limited to the following:
: i. The Draft Regulatory Issue Summary on Service Life addressing the treatment of vendor recommendations within the regulatory framework; 76
: i.
The Draft Regulatory Issue Summary on Service Life addressing the treatment of vendor recommendations within the regulatory framework;  


ii. 10 CFR 50.46(c) rulemaking for which the justification utilizes the adequate protection provisions of the backfit rule to obviate the need to compare the benefits of public health and safety with the cost of compliance for the three major portions of the rule; iii. Use of the compliance exception backfit as proposed by the NRC staff to address the "open phase condition (OPC)" issue; and iv. Possible alteration of the risk reduction credit given for Incipient Fire Protection after the modifications have been installed and received approval from the NRC crediting the technology.
77 ii. 10 CFR 50.46(c) rulemaking for which the justification utilizes the adequate protection provisions of the backfit rule to obviate the need to compare the benefits of public health and safety with the cost of compliance for the three major portions of the rule; iii. Use of the compliance exception backfit as proposed by the NRC staff to address the "open phase condition (OPC)" issue; and iv. Possible alteration of the risk reduction credit given for Incipient Fire Protection after the modifications have been installed and received approval from the NRC crediting the technology.
: d. Please describe the progress made during each reporting period.
: d. Please describe the progress made during each reporting period.
a, b, & d. Consistent with the EDO approved milestones in Response 34, the agency developed and implemented refresher training for management, inspection staff, engineers, and project managers. The agency is currently developing enhanced backfit training that will be deployed in 2018 and 2019. As of January 31, 2018, the agency completed refresher training for NRC senior managers, NRC regional inspection staff, and applicable NRC headquarters offices.
a, b, & d. Consistent with the EDO approved milestones in Response 34, the agency developed and implemented refresher training for management, inspection staff, engineers, and project managers. The agency is currently developing enhanced backfit training that will be deployed in 2018 and 2019. As of January 31, 2018, the agency completed refresher training for NRC senior managers, NRC regional inspection staff, and applicable NRC headquarters offices.
Line 816: Line 994:
: c. The agency has incorporated the recent lessons learned from the Exelon backfit appeal decision and the Commissions direction in SRM-COMSECY-16-0020 into its reviews of proposed regulatory changes and decision making.
: c. The agency has incorporated the recent lessons learned from the Exelon backfit appeal decision and the Commissions direction in SRM-COMSECY-16-0020 into its reviews of proposed regulatory changes and decision making.
The table below provides a summary of the status of regulatory changes and issues as of January 31, 2018.
The table below provides a summary of the status of regulatory changes and issues as of January 31, 2018.
Status of Select Regulatory Activities Title                   Status of Regulatory Change                         Backfitting Considerations RIS on Service Life -     RIS (ADAMS Accession No. ML17177A060)             While the CRGR found Disposition of            was issued for public comment and the public       that the draft RIS did not Information Related        comments have been dispositioned.                  contain any specific to the Time Period                                                            backfits or new staff That Safety-Related                                                          positions, it did not Structures, Systems,                                                          endorse the RIS in its or Components are          RIS was reviewed by CRGR on September              current form. The CRGR Installed                12 and 14, 2017. CRGR Meeting Nos. #446,          indicated that a RIS may
Status of Select Regulatory Activities Title Status of Regulatory Change Backfitting Considerations RIS on Service Life -
                            #447(ADAMS Accession No.                          not be appropriate for ML17276B156).                                      addressing these issues.
Disposition of Information Related to the Time Period That Safety-Related Structures, Systems, or Components are Installed RIS (ADAMS Accession No. ML17177A060) was issued for public comment and the public comments have been dispositioned.
RIS was reviewed by CRGR on September 12 and 14, 2017. CRGR Meeting Nos. #446,
#447(ADAMS Accession No. ML17276B156).
While the CRGR found that the draft RIS did not contain any specific backfits or new staff positions, it did not endorse the RIS in its current form. The CRGR indicated that a RIS may not be appropriate for addressing these issues.
Currently, the staff is discussing its next steps forward.
Currently, the staff is discussing its next steps forward.
10 CFR 50.46(c)           The NRC staff prepared a regulatory analysis       Based on established Rulemaking                for the 10 CFR 50.46c draft final rule             criteria at the time, the (ADAMS Accession No. ML15323A122) to               CRGR was not required identify the benefits and costs of the             to review the rulemaking particular regulatory approach for addressing     to assess potential emergency core cooling system                     backfits. The rulemaking performance. The regulatory analysis               is currently with the focuses on the marginal difference in benefits 77
10 CFR 50.46(c)
Rulemaking The NRC staff prepared a regulatory analysis for the 10 CFR 50.46c draft final rule (ADAMS Accession No. ML15323A122) to identify the benefits and costs of the particular regulatory approach for addressing emergency core cooling system performance. The regulatory analysis focuses on the marginal difference in benefits Based on established criteria at the time, the CRGR was not required to review the rulemaking to assess potential backfits. The rulemaking is currently with the


Status of Select Regulatory Activities Title                   Status of Regulatory Change                     Backfitting Considerations and costs for each alternative relative to the Commission for its no action baseline alternative for the three consideration.
78 Status of Select Regulatory Activities Title Status of Regulatory Change Backfitting Considerations and costs for each alternative relative to the no action baseline alternative for the three major portions of the rule, which is consistent with the requirements of the backfit rule (10 CFR 50.109), Commission direction, and the ongoing revisions to the agencys cost-benefit guidance (e.g., NUREG/BR-0058, Revision 5).
major portions of the rule, which is consistent with the requirements of the backfit rule (10 CFR 50.109), Commission direction, and the ongoing revisions to the agencys cost-benefit guidance (e.g., NUREG/BR-0058, Revision 5).
Commission for its consideration.
RIS on AP1000           The purpose of this RIS is to provide           This item has been Certified Design          guidance, to present and future applicants for closed. Staff no longer Information Errors        a Combined License (COL) or COL renewal         plans to issue the subject Discovered During        referencing the AP1000 DC, regarding           RIS.
RIS on AP1000 Certified Design Information Errors Discovered During Design Finalization and Construction Activities The purpose of this RIS is to provide guidance, to present and future applicants for a Combined License (COL) or COL renewal referencing the AP1000 DC, regarding previous applicant-identified errors contained in the AP1000 DC (DCD Revision 19) and how these errors may be addressed by current and future applicants.
Design Finalization      previous applicant-identified errors contained and Construction          in the AP1000 DC (DCD Revision 19) and Activities              how these errors may be addressed by current and future applicants.
This item has been closed. Staff no longer plans to issue the subject RIS.
Proposed Rule, 10         The proposed rule (ADAMS Accession No.         CRGR completed its CFR 73.53,                ML17145A342), if approved, would require       review in two meetings, Requirements for        certain Fuel Cycle Facility licensees to       June 27 and July 12, Cyber Security at        establish, implement, and maintain a cyber     2017. This rule contained Nuclear Fuel Cycle        security program that can detect, protect       backfitting and was Facilities and          against, and respond to a cyber-attack         endorsed by the CRGR.
Proposed Rule, 10 CFR 73.53, Requirements for Cyber Security at Nuclear Fuel Cycle Facilities and associated draft regulatory guidance, DG-5062 Cyber Security Programs for Nuclear Fuel Cycle Facilities The proposed rule (ADAMS Accession No. ML17145A342), if approved, would require certain Fuel Cycle Facility licensees to establish, implement, and maintain a cyber security program that can detect, protect against, and respond to a cyber-attack capable of causing one or more of the consequences of concern as defined in the proposed rule.
associated draft          capable of causing one or more of the           This rulemaking is regulatory guidance,      consequences of concern as defined in the       currently with the DG-5062 Cyber            proposed rule.                                  Commission for its Security Programs                                                        consideration.
CRGR completed its review in two meetings, June 27 and July 12, 2017. This rule contained backfitting and was endorsed by the CRGR.
for Nuclear Fuel Cycle Facilities Regulatory Guide         This regulatory guide describes an approach    This item has been 5.77, Revision 1,         that the NRC staff considers acceptable for     closed. The staff did not Insider Mitigation      an insider mitigation program for nuclear       identify a backfitting Program                  power reactors that contain protected or vital concern. This RG is areas.                                          currently being reviewed by the Commission.
This rulemaking is currently with the Commission for its consideration.
Regulatory Guide 5.77, Revision 1, Insider Mitigation Program This regulatory guide describes an approach that the NRC staff considers acceptable for an insider mitigation program for nuclear power reactors that contain protected or vital areas.
This item has been closed. The staff did not identify a backfitting concern. This RG is currently being reviewed by the Commission.
: 34. Please provide a description of actions taken and/or planned to address recommendations made by the CRGR in their report "U.S. Nuclear Regulatory Commission's Implementation of Backfitting and Issue Finality Requirements," dated June 27, 2017. Please include a milestone schedule for completing action on each recommendation.
: 34. Please provide a description of actions taken and/or planned to address recommendations made by the CRGR in their report "U.S. Nuclear Regulatory Commission's Implementation of Backfitting and Issue Finality Requirements," dated June 27, 2017. Please include a milestone schedule for completing action on each recommendation.
The actions identified in the CRGR Review Report and approved by the EDO in a memo dated July 19, 2017, have been organized into the following activities:
The actions identified in the CRGR Review Report and approved by the EDO in a memo dated July 19, 2017, have been organized into the following activities:  
78


Backfitting Enhancement Tasks from the June 27, 2017, CRGR Review Report Item                           Task                             Lead     Due Date   Status 1 Update agency-level guidance on backfitting and             NRR    05/02/2018  On track issue finality to reflect Commission direction on the use of the compliance exception to the backfit rule and submit for Commission approval.
79 Backfitting Enhancement Tasks from the June 27, 2017, CRGR Review Report Item Task Lead Due Date Status 1
2 Update office-level implementing guidance on           NRR, NMSS, 02/21/2019    On track backfitting and issue finality, and the Enforcement     NRO, NSIR, Manual to reflect Commission-approved                     RES, all agencywide guidance.                                    Regions, OE 3 Develop and conduct "reset" training for managers           CRGR    02/28/2018 Completed and staff on backfitting and issue finality.
Update agency-level guidance on backfitting and issue finality to reflect Commission direction on the use of the compliance exception to the backfit rule and submit for Commission approval.
4 Update initial training on backfitting and issue           CRGR    06/31/2018  On track finality for use in office and regional qualification programs.
NRR 05/02/2018 On track 2
5 Develop or update refresher training and               CRGR, NRR, 09/31/2018    On track developmental activities on backfitting and issue       NMSS, NRO, finality, and revise office qualification procedures to NSIR, RES, require such training and developmental activities.     all Regions 6 Make available "just-in-time" training and                 CRGR     10/31/2018 On track references on backfitting and issue finality.
Update office-level implementing guidance on backfitting and issue finality, and the Enforcement Manual to reflect Commission-approved agencywide guidance.
Add backfitting information to agency knowledge             CRGR     09/18/2017 Completed management Web site.
NRR, NMSS, NRO, NSIR, RES, all Regions, OE 02/21/2019 On track 3
Prepare a NUREG/Knowledge Management report                 CRGR    08/31/2019  On track on the history and activities of the Committee to Review Generic Requirements.
Develop and conduct "reset" training for managers and staff on backfitting and issue finality.
9 Create a backfitting Community of Practice with             CRGR     08/31/2017 Completed office points of contact.
CRGR 02/28/2018 Completed 4
10 Conduct an effectiveness review of actions taken             CRGR    07/27/2020  On track in response to the June 27, 2017, CRGR report.
Update initial training on backfitting and issue finality for use in office and regional qualification programs.
11 Propose a revision to the charter for the CRGR to           CRGR    03/19/2018  On track reflect rulemaking criteria, incorporate recent Commission direction, and enhance rigor of CRGR assessments.
CRGR 06/31/2018 On track 5
12 Report on the availability of key docketed                   OCIO    02/28/2018  On track information categories and the resources needed to make information more readily retrievable.
Develop or update refresher training and developmental activities on backfitting and issue finality, and revise office qualification procedures to require such training and developmental activities.
13 Report on the resources needed to implement the             CRGR    10/02/2017 Completed actions in the July 19, 2017, EDO tasking on backfitting.
CRGR, NRR, NMSS, NRO, NSIR, RES, all Regions 09/31/2018 On track 6
79
Make available "just-in-time" training and references on backfitting and issue finality.
CRGR 10/31/2018 On track 7
Add backfitting information to agency knowledge management Web site.
CRGR 09/18/2017 Completed 8
Prepare a NUREG/Knowledge Management report on the history and activities of the Committee to Review Generic Requirements.
CRGR 08/31/2019 On track 9
Create a backfitting Community of Practice with office points of contact.
CRGR 08/31/2017 Completed 10 Conduct an effectiveness review of actions taken in response to the June 27, 2017, CRGR report.
CRGR 07/27/2020 On track 11 Propose a revision to the charter for the CRGR to reflect rulemaking criteria, incorporate recent Commission direction, and enhance rigor of CRGR assessments.
CRGR 03/19/2018 On track 12 Report on the availability of key docketed information categories and the resources needed to make information more readily retrievable.
OCIO 02/28/2018 On track 13 Report on the resources needed to implement the actions in the July 19, 2017, EDO tasking on backfitting.
CRGR 10/02/2017 Completed


REACTOR INSPECTION
80 REACTOR INSPECTION
: 35. Please provide the Reactor Oversight Process findings for year-to-date and 3-year rolling metrics, including the total number and for each region for green, white, yellow, and red findings.
: 35. Please provide the Reactor Oversight Process findings for year-to-date and 3-year rolling metrics, including the total number and for each region for green, white, yellow, and red findings.
Location       # of Findings               2014         2015         2016       2017(Note 1)
Location  
Nationally           Total                   824         821           704           505 NSIR (all regions)                       18           26           19           N/A (Note 2)
# of Findings 2014 2015 2016 2017(Note
Green                     167         169           155           119 White                     3           4             2             2 Yellow                     0           1             0             0 RI              Red                       0           0             0             0 GTG Security                   1           1             0             0 Total                   171         175           157           121
: 1)
                    # OP Units                   26           25           25           25 Green                     148         159           151           104 White                     4           1             0             3 Yellow                     0           0             0             0 R2              Red                       0           0             0             0 GTG Security                   0           0             1             2 Total                   152         160           152           109
Nationally Total 824 821 704 505 NSIR (all regions) 18 26 19 N/A (Note 2)
                    # OP Units                   32           32           33           33 Green                     221         202           177           113 White                     4           5             1             4 Yellow                     0           0             0             0 R3              Red                       0           0             0             0 GTG Security                   1           1             1             0 Total                   226         208           179           117
RI Green 167 169 155 119 White 3
                    # OP Units                   23           23           23           23 Green                     249         248           196           154 White                     5           2             1             2 Yellow                     2           1             0             0 R4              Red                       0           0             0             0 GTG Security                   1           1             0             2 Total                   257         252           197           158
4 2
                    # OP Units                   19           19           19           19 NSIR: Office of Nuclear Security and Incident Response*
2 Yellow 0
GTG Security: Greater-than-green security;
1 0
0 Red 0
0 0
0 GTG Security 1
1 0
0 Total 171 175 157 121  
# OP Units 26 25 25 25 R2 Green 148 159 151 104 White 4
1 0
3 Yellow 0
0 0
0 Red 0
0 0
0 GTG Security 0
0 1
2 Total 152 160 152 109  
# OP Units 32 32 33 33 R3 Green 221 202 177 113 White 4
5 1
4 Yellow 0
0 0
0 Red 0
0 0
0 GTG Security 1
1 1
0 Total 226 208 179 117  
# OP Units 23 23 23 23 R4 Green 249 248 196 154 White 5
2 1
2 Yellow 2
1 0
0 Red 0
0 0
0 GTG Security 1
1 0
2 Total 257 252 197 158  
# OP Units 19 19 19 19 NSIR: Office of Nuclear Security and Incident Response*
GTG Security: Greater-than-green security;  
#OP Units: Number of operating units; Notes:
#OP Units: Number of operating units; Notes:
: 1. Data are presented by calendar year. Some fourth quarter data are still being processed for CY 2017.
: 1. Data are presented by calendar year. Some fourth quarter data are still being processed for CY 2017.
: 2. Starting in CY 2017, these finding are included in the findings for each region.
: 2. Starting in CY 2017, these finding are included in the findings for each region.  
80
 
81
: 36. Please provide the percentage of Final Significance Determinations made within 90 Days for all potentially Greater-Than-Green findings, monthly for one-year rolling metrics and annually for the past 10 years.
: 36. Please provide the percentage of Final Significance Determinations made within 90 Days for all potentially Greater-Than-Green findings, monthly for one-year rolling metrics and annually for the past 10 years.
1-Year Rolling Metric Month                                       Percent Met February 2017                                         100 March 2017                                         N/A April 2017                                         100 May 2017                                           100 June 2017                                         N/A July 2017                                         100 August 2017                                         100 September 2017                                         N/A October 2017                                         100 November 2017                                           0 December 2017                                         100 January 2018                                         N/A 10-Year Annual Determinations Within 90 Days Year                                       Percent Met 2008                                           100 2009                                           100 2010                                             93 2011                                           100 2012                                           100 2013                                           100 2014                                             86 2015                                             88 2016                                           100 2017                                             93 Comments:
1-Year Rolling Metric Month Percent Met February 2017 100 March 2017 N/A April 2017 100 May 2017 100 June 2017 N/A July 2017 100 August 2017 100 September 2017 N/A October 2017 100 November 2017 0
December 2017 100 January 2018 N/A 10-Year Annual Determinations Within 90 Days Year Percent Met 2008 100 2009 100 2010 93 2011 100 2012 100 2013 100 2014 86 2015 88 2016 100 2017 93 Comments:
This metric, reported in the NRCs CBJ, measures the time from the issuance date of the first official correspondence that describes the inspection finding, until the final significance determination letter is sent to the licensee, which is expected to be 90 days or less.
This metric, reported in the NRCs CBJ, measures the time from the issuance date of the first official correspondence that describes the inspection finding, until the final significance determination letter is sent to the licensee, which is expected to be 90 days or less.
: 37. For each reporting period, please describe each instance where Inspection Manual Chapter 609 Appendix M, "Significance Determination Process Using Qualitative Criteria," has been applied in the Reactor Oversight Process Significance Determination Process, including the justification for doing so.
: 37. For each reporting period, please describe each instance where Inspection Manual Chapter 609 Appendix M, "Significance Determination Process Using Qualitative Criteria," has been applied in the Reactor Oversight Process Significance Determination Process, including the justification for doing so.
Appendix M was used to disposition three green inspection findings during this reporting period.
Appendix M was used to disposition three green inspection findings during this reporting period.
Two of these findings were associated with spent fuel pool water inventory and one was associated with post-Fukushima safety enhancements. In all three cases, the use of Appendix M was directed by another SDP appendix.
Two of these findings were associated with spent fuel pool water inventory and one was associated with post-Fukushima safety enhancements. In all three cases, the use of Appendix M was directed by another SDP appendix.  
81
 
82
: 38. Please provide the status of potential changes to the Reactor Oversight Process, and identify any changes that may require Commission approval prior to implementation.
: 38. Please provide the status of potential changes to the Reactor Oversight Process, and identify any changes that may require Commission approval prior to implementation.
Significant potential changes to the ROP include the following:
Significant potential changes to the ROP include the following:
* IMC 0609, Significance Determination Process, Appendix M, Significance Determination Process Using Qualitative Criteria. Having received stakeholder feedback on its initially proposed changes to Appendix M, the NRC staff is preparing a revised approach, and will re-engage with stakeholders in the coming months to review the changes and next steps. Based on the changes contemplated, at the present time, the staff does not expect that Commission approval will be required.
IMC 0609, Significance Determination Process, Appendix M, Significance Determination Process Using Qualitative Criteria. Having received stakeholder feedback on its initially proposed changes to Appendix M, the NRC staff is preparing a revised approach, and will re-engage with stakeholders in the coming months to review the changes and next steps. Based on the changes contemplated, at the present time, the staff does not expect that Commission approval will be required.
: 39. Please describe the progress toward utilizing an industry consensus document as a means of accomplishing predictability and consistency in operability determinations.
: 39. Please describe the progress toward utilizing an industry consensus document as a means of accomplishing predictability and consistency in operability determinations.
The NRC is engaged with nuclear industry stakeholders on its effort to develop a consensus document for operability determinations. The agency held a public meeting on June 1, 2017, to discuss the fundamental concepts used to make operability determinations. The staff also participated in an operability panel at the NEI Licensing Forum on August 23, 2017. NRC expects to receive industrys draft guidance in early 2018. The NRC anticipates that this effort will inform a future revision of IMC 0326, Operability Determinations & Functionality Assessments for Conditions Adverse to Quality or Safety.
The NRC is engaged with nuclear industry stakeholders on its effort to develop a consensus document for operability determinations. The agency held a public meeting on June 1, 2017, to discuss the fundamental concepts used to make operability determinations. The staff also participated in an operability panel at the NEI Licensing Forum on August 23, 2017. NRC expects to receive industrys draft guidance in early 2018. The NRC anticipates that this effort will inform a future revision of IMC 0326, Operability Determinations & Functionality Assessments for Conditions Adverse to Quality or Safety.
: 40. For each Design Bases Assurance Inspection (formerly known as the Component Design Basis Inspection) completed in the last three years, please list the duration, amount of fees billed, and percentage of fees used to reimburse contractors.
: 40. For each Design Bases Assurance Inspection (formerly known as the Component Design Basis Inspection) completed in the last three years, please list the duration, amount of fees billed, and percentage of fees used to reimburse contractors.
The fees are grouped per Design Bases Assurance (DBA) inspection in order to allow easier review by the reader and facilitate comparison between the costs of DBA inspections performed at each site. Monthly comparison of DBA inspection fees will not provide an accurate representation of each licensees charges due to the fact that the DBA inspections span 2 months.
The fees are grouped per Design Bases Assurance (DBA) inspection in order to allow easier review by the reader and facilitate comparison between the costs of DBA inspections performed at each site. Monthly comparison of DBA inspection fees will not provide an accurate representation of each licensees charges due to the fact that the DBA inspections span 2 months.  
82
 
83
 
84
 
85


83 84 85
86
: 41. Please provide the status of the holistic review of engineering inspection procedures and any actions taken and/or planned because of the review.
: 41. Please provide the status of the holistic review of engineering inspection procedures and any actions taken and/or planned because of the review.
During January and February 2018, NRC management and staff are conducting internal briefings for NRC senior management to obtain their endorsement of the recommended changes to the suite of ROP engineering inspections proposed by the staffs engineering inspection working group. The potentially impacted ROP inspections include:
During January and February 2018, NRC management and staff are conducting internal briefings for NRC senior management to obtain their endorsement of the recommended changes to the suite of ROP engineering inspections proposed by the staffs engineering inspection working group. The potentially impacted ROP inspections include:
Line 881: Line 1,117:
IP 71111.07, Heat Sink Performance IP 71111.08, Inservice Inspection Activities IP 71111.12, Maintenance Effectiveness IP 71111.17T, Evaluations of Changes, Tests, and Experiments IP 71111.18, Plant Modifications IP 71111.21M, Design Bases Assurance Inspection (Team)
IP 71111.07, Heat Sink Performance IP 71111.08, Inservice Inspection Activities IP 71111.12, Maintenance Effectiveness IP 71111.17T, Evaluations of Changes, Tests, and Experiments IP 71111.18, Plant Modifications IP 71111.21M, Design Bases Assurance Inspection (Team)
IP 71111.21N, Design Bases Assurance Inspection (Program)
IP 71111.21N, Design Bases Assurance Inspection (Program)
The purpose of this review effort is to improve the effectiveness and efficiency of these ROP engineering inspections. The NRC held a public meeting on February 22, 2018, to inform industry stakeholders of the recommended changes. NRC staff plans to seek Commission approval for these changes in the summer of 2018 and, if approved by the Commission, the NRC plans to implement these changes starting in calendar year 2020.
The purpose of this review effort is to improve the effectiveness and efficiency of these ROP engineering inspections. The NRC held a public meeting on February 22, 2018, to inform industry stakeholders of the recommended changes. NRC staff plans to seek Commission approval for these changes in the summer of 2018 and, if approved by the Commission, the NRC plans to implement these changes starting in calendar year 2020.  
86


NEW REACTORS
87 NEW REACTORS
: 42. Please provide a table showing the funds budgeted, the resources spent, and the total Part 170 fees billed each year for the last ten years for the Office of New Reactors.
: 42. Please provide a table showing the funds budgeted, the resources spent, and the total Part 170 fees billed each year for the last ten years for the Office of New Reactors.
FY 08     FY 09     FY 10       FY 11       FY 12     FY 13       FY 14     FY 15       FY 16 FY17     FY 18PB Enacted ($M)           137.08     110.46   109.81     110.71     102.53   100.87     112.61     96.08       91.63 72.03     76.49 Expended ($M)         82.57     81.16     90.55       89.75       76.06     89.16       67.03     61.46       62.63 54.84     17.61 Part 170 Billed ($M)                                   75.73       74.65     60.28       60.18     59.62       60.12 55.65     11.40 Enacted: Beginning in FY 2018, the NRC eliminated the allocation of mission indirect resources in the agency's budget request to increase transparency (see NRC FY 2018 Congressional Budget Justification page 161 for detailed explanation). To allow for comparison of historical budget data, FY 2008 - FY 2017 are presented in a consistent manner. FY 2018 expenditure and Part 170 billing is as of January 31, 2018.
FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 FY 14 FY 15 FY 16 FY17 FY 18PB Enacted ($M) 137.08 110.46 109.81 110.71 102.53 100.87 112.61 96.08 91.63 72.03 76.49 Expended ($M) 82.57 81.16 90.55 89.75 76.06 89.16 67.03 61.46 62.63 54.84 17.61 Part 170 Billed ($M) 75.73 74.65 60.28 60.18 59.62 60.12 55.65 11.40 Enacted: Beginning in FY 2018, the NRC eliminated the allocation of mission indirect resources in the agency's budget request to increase transparency (see NRC FY 2018 Congressional Budget Justification page 161 for detailed explanation). To allow for comparison of historical budget data, FY 2008 - FY 2017 are presented in a consistent manner. FY 2018 expenditure and Part 170 billing is as of January 31, 2018.
Part 170 Billed: For FY 2008 - FY 2010, the data in the legacy billing system is not available at the office level.
Part 170 Billed: For FY 2008 - FY 2010, the data in the legacy billing system is not available at the office level.
: 43. For each design certification, Construction and Operating License (COL), and Early Site Permit (ESP) application reviewed since 2007, please provide:
: 43. For each design certification, Construction and Operating License (COL), and Early Site Permit (ESP) application reviewed since 2007, please provide:
Line 894: Line 1,129:
: d. The originally scheduled dates for completion of the safety evaluation report and environmental impact statement;
: d. The originally scheduled dates for completion of the safety evaluation report and environmental impact statement;
: e. The actual dates for completion of the safety evaluation report and environmental impact statement;
: e. The actual dates for completion of the safety evaluation report and environmental impact statement;
: f. For ongoing reviews, the projected date for final agency action;
: f.
For ongoing reviews, the projected date for final agency action;
: g. For terminated or suspended reviews, the dates of the termination or suspension; and
: g. For terminated or suspended reviews, the dates of the termination or suspension; and
: h. The total fees billed for each review.
: h. The total fees billed for each review.  
87
 
88 Project Name Date of First Pre-Application Meeting Date the Application was Filed Acceptanc e Review Completed in 60 Days (Note 1)
Original Review Schedule Dates for FSER and FEIS (or EA)
Completion Actual FSER and FEIS (or EA)
Completion Dates Projected Date for Final NRC Action Date of Withdrawal or Suspension Request (for terminated projects only)
Total Fees Billed for Each Review (Note 4)
U.S. Advanced Pressurized Water Reactor (APWR) DC 05/12/2006 12/31/2007 Yes FSER: 06/2012 FEIS: N/A Application is currently under review Not Scheduled (Note 2)
N/A
$77,885,573 APR1400 DC 11/05/2009 12/23/2014 Yes FSER: 09/2018 FEIS: N/A Application is currently under review 09/2019 N/A
$54,236,631 ABWR DC Renewal (GEH) 02/23/2010 12/07/2010 Yes FSER: 03/2018 FEIS: N/A Application is currently under review Schedule currently under review N/A
$5,071,312 Turkey Point COL 02/10/2009 06/30/2009 Yes FSER: 12/2012 FEIS: 10/2012 FSER:
12/2016 FEIS: 10/2016 04/2018 N/A
$35,115,339 Clinch River ESP 12/14/2010 05/12/2016 No (Note 3)
FSER: 08/2019 FEIS: 06/2019 Application is currently under review 02/2020 N/A
$5,647,335 NuScale SMR DC 07/09/2008 01/06/2017 Yes FSER: 09/2020 FEIS: N/A Application is currently under review 01/2021 N/A
$16,643,723 North Anna ESP Information not known 09/25/2003 Yes FSER: 6/2005 FEIS: 6/2005 FSER:
08/2006 FEIS: 12/2006 ESP issued on 11/27/2007 N/A
$8,579,177 Vogtle ESP Information not known 08/15/2006 Yes FSER: 05/2008 FEIS: 05/2008 FSER:
02/2009 FEIS: 08/2008 ESP issued on 08/26/2009 N/A
$11,680,269 South Texas Project COL Information not known 09/20/2007 Yes FSER: 09/2011 FEIS: 03/2011 FSER:
09/2015 FEIS: 02/2011 COL issued on 02/12/2016
$58,463,244


Original Date of Acceptanc      Review    Actual FSER Date of                                                                   Withdrawal or    Total Fees Date the    e Review    Schedule    and FEIS (or    Projected First Pre-                                                                   Suspension    Billed for Each Project Name              Application Completed    Dates for        EA)        Date for Application                                                                   Request (for      Review was Filed   in 60 Days   FSER and      Completion    Final NRC Meeting                                                                      terminated      (Note 4)
89 Project Name Date of First Pre-Application Meeting Date the Application was Filed Acceptanc e Review Completed in 60 Days (Note 1)
(Note 1) FEIS (or EA)     Dates         Action projects only)
Original Review Schedule Dates for FSER and FEIS (or EA)
Completion U.S. Advanced 05/12/2006  12/31/2007 Yes         FSER: 06/2012 Application is  Not        N/A Pressurized                                        FEIS: N/A    currently under Scheduled                $77,885,573 Water Reactor                                                    review          (Note 2)
Completion Actual FSER and FEIS (or EA)
(APWR) DC APR1400 DC    11/05/2009  12/23/2014  Yes         FSER: 09/2018 Application is  09/2019    N/A FEIS: N/A    currently under                          $54,236,631 review ABWR DC      02/23/2010   12/07/2010  Yes        FSER: 03/2018 Application is  Schedule  N/A Renewal (GEH)                                      FEIS: N/A    currently under currently                $5,071,312 review          under review Turkey Point  02/10/2009  06/30/2009  Yes         FSER: 12/2012 FSER:           04/2018    N/A COL                                                FEIS: 10/2012 12/2016                                   $35,115,339 FEIS: 10/2016 Clinch River  12/14/2010  05/12/2016  No          FSER: 08/2019 Application is 02/2020    N/A ESP                                    (Note 3)   FEIS: 06/2019 currently under                          $5,647,335 review NuScale SMR  07/09/2008   01/06/2017  Yes         FSER: 09/2020 Application is 01/2021    N/A DC                                                FEIS: N/A    currently under                          $16,643,723 review North Anna    Information 09/25/2003  Yes         FSER: 6/2005  FSER:           ESP        N/A            $8,579,177 ESP          not known                            FEIS: 6/2005  08/2006        issued on FEIS: 12/2006  11/27/2007 Vogtle ESP    Information  08/15/2006  Yes        FSER: 05/2008 FSER:          ESP        N/A           $11,680,269 not known                           FEIS: 05/2008 02/2009        issued on FEIS: 08/2008  08/26/2009 South Texas  Information  09/20/2007  Yes        FSER: 09/2011 FSER:          COL                      $58,463,244 Project COL   not known                           FEIS: 03/2011 09/2015        issued on FEIS: 02/2011  02/12/2016 88
Completion Dates Projected Date for Final NRC Action Date of Withdrawal or Suspension Request (for terminated projects only)
Total Fees Billed for Each Review (Note 4)
Bellefonte COL Information not known 10/30/2007 Yes FSER: 02/2011 FEIS: 01/2010 Application withdrawn by the applicant N/A 03/28/2016
$21,916,556 North Anna COL Information not known 11/26/2007 Yes FSER: 08/2010 FEIS: 12/2009 FSER:
01/2017 FSEIS:
02/2010 COL issued on 06/02/2017 N/A  
$33,032,175 Lee COL Information not known 12/12/2007 Yes FSER: 02/2011 FEIS: 03/2010 FSER:
08/2016 FEIS: 12/2013 COL issued on 12/19/2016 N/A
$22,762,364 U.S. EPR DC 2/8/05 12/11/2007 Yes FSER: 05/2011 FEIS: N/A Application review is suspended at the applicants request N/A 02/25/2015 (suspension request)  
$82,585,674 Shearon Harris COL Information not known 02/18/2008 Yes FSER: 04/2011 FEIS: 05/2010 Application review is suspended at the applicants request N/A 05/02/2013 (suspension request)
$10,106,258 Vogtle COL Information not known 03/28/2008 Yes FSER: 12/2010 FEIS: 01/2010 FSER:
08/2011 FEIS: 04/2011 COL issued on 02/10/2012 N/A  
$29,770,625 V.C. Summer COL Information not known 03/27/2008 Yes FSER: 02/2011 FEIS: 02/2011 FSER:
08/2011 FEIS: 04/2011 COL issued on 03/30/2012 N/A
$28,057,913 Levy COL Information not known 07/30/2008 Yes FSER: 05/2011 FEIS: 09/2010 FSER:
05/2016 FEIS: 04/2012 COL issued on 10/26/2016 N/A
$27,398,694


Original Date of Acceptanc      Review    Actual FSER Date of                                                                  Withdrawal or    Total Fees Date the    e Review    Schedule    and FEIS (or    Projected First Pre-                                                                 Suspension    Billed for Each Project Name              Application Completed    Dates for        EA)        Date for Application                                                                 Request (for      Review was Filed in 60 Days   FSER and      Completion    Final NRC Meeting                                                                    terminated      (Note 4)
90 Project Name Date of First Pre-Application Meeting Date the Application was Filed Acceptanc e Review Completed in 60 Days (Note 1)
(Note 1) FEIS (or EA)     Dates         Action projects only)
Original Review Schedule Dates for FSER and FEIS (or EA)
Completion Bellefonte COL Information 10/30/2007  Yes       FSER: 02/2011 Application    N/A        03/28/2016    $21,916,556 not known                          FEIS: 01/2010 withdrawn by the applicant North Anna    Information  11/26/2007  Yes        FSER: 08/2010 FSER:           COL        N/A            $33,032,175 COL            not known                          FEIS: 12/2009 01/2017        issued on FSEIS:          06/02/2017 02/2010 Lee COL        Information  12/12/2007  Yes        FSER: 02/2011 FSER:          COL        N/A           $22,762,364 not known                           FEIS: 03/2010 08/2016        issued on FEIS: 12/2013  12/19/2016 U.S. EPR DC    2/8/05      12/11/2007  Yes        FSER: 05/2011 Application    N/A       02/25/2015    $82,585,674 FEIS: N/A    review is                 (suspension suspended at               request) the applicants request Shearon Harris Information  02/18/2008  Yes        FSER: 04/2011 Application    N/A       05/02/2013     $10,106,258 COL           not known                           FEIS: 05/2010 review is                  (suspension suspended at              request) the applicants request Vogtle COL    Information  03/28/2008 Yes       FSER: 12/2010 FSER:          COL        N/A           $29,770,625 not known                          FEIS: 01/2010 08/2011        issued on FEIS: 04/2011  02/10/2012 V.C. Summer    Information  03/27/2008  Yes        FSER: 02/2011 FSER:          COL        N/A            $28,057,913 COL           not known                           FEIS: 02/2011 08/2011        issued on FEIS: 04/2011  03/30/2012 Levy COL      Information  07/30/2008 Yes        FSER: 05/2011 FSER:          COL        N/A           $27,398,694 not known                          FEIS: 09/2010 05/2016        issued on FEIS: 04/2012  10/26/2016 89
Completion Actual FSER and FEIS (or EA)
Completion Dates Projected Date for Final NRC Action Date of Withdrawal or Suspension Request (for terminated projects only)
Total Fees Billed for Each Review (Note 4)
Fermi COL Information not known 09/18/2008 Yes FSER: 03/2012 FEIS: 08/2011 FSER:
11/2014 FEIS: 01/2013 COL issued on 05/01/2015 N/A  
$26,413,206 Comanche Peak COL Information not known 09/18/2008 Yes FSER: 12/11 FEIS: 01/2011 FSER: N/A FEIS: 05/2011 Application review is suspended at the applicants request N/A 11/07/2013 (suspension request)
$23,278,377 River Bend COL Information not known 09/25/2008 Yes A review schedule was not developed for this application Application withdrawn by the applicant N/A 01/09/2009 (suspension request) 12/04/2015 (withdrawal request)
$1,350,316 Callaway COL Information not known 07/24/2008 No A review schedule was not developed for this application Application withdrawn by the applicant N/A 06/23/2009 (suspension request) 08/12/2015 (withdrawal request)
$4,066,138


Original Date of Acceptanc      Review    Actual FSER Date of                                                                   Withdrawal or    Total Fees Date the    e Review      Schedule    and FEIS (or    Projected First Pre-                                                                   Suspension    Billed for Each Project Name              Application Completed      Dates for        EA)        Date for Application                                                                   Request (for      Review was Filed in 60 Days   FSER and      Completion    Final NRC Meeting                                                                      terminated      (Note 4)
91 Project Name Date of First Pre-Application Meeting Date the Application was Filed Acceptanc e Review Completed in 60 Days (Note 1)
(Note 1)   FEIS (or EA)     Dates         Action projects only)
Original Review Schedule Dates for FSER and FEIS (or EA)
Completion Fermi COL     Information 09/18/2008 Yes       FSER: 03/2012 FSER:           COL        N/A           $26,413,206 not known                          FEIS: 08/2011  11/2014        issued on FEIS: 01/2013  05/01/2015 Comanche      Information 09/18/2008  Yes       FSER: 12/11    FSER: N/A      N/A       11/07/2013    $23,278,377 Peak COL      not known                          FEIS: 01/2011  FEIS: 05/2011              (suspension Application                request) review is suspended at the applicants request River Bend    Information 09/25/2008  Yes       A review       Application     N/A       01/09/2009    $1,350,316 COL          not known                           schedule was  withdrawn by               (suspension not developed  the applicant             request) for this application                              12/04/2015 (withdrawal request)
Completion Actual FSER and FEIS (or EA)
Callaway COL Information 07/24/2008 No         A review      Application     N/A       06/23/2009    $4,066,138 not known                           schedule was   withdrawn by               (suspension not developed  the applicant             request) for this application                              08/12/2015 (withdrawal request) 90
Completion Dates Projected Date for Final NRC Action Date of Withdrawal or Suspension Request (for terminated projects only)
Total Fees Billed for Each Review (Note 4)
Bell Bend COL Information not known 10/10/2008 Yes FSER: 03/2012 FEIS: 03/2011 FSER: N/A FEIS: 04/2016 Application withdrawn by the applicant N/A 02/25/2015 (suspension request) 08/30/2016 (withdrawal request)
$20,026,574 PSEG ESP Information not known 05/25/2010 Yes FSER: 07/2013 FEIS: 03/2013 FSER:
09/2015 FEIS: 11/2015 ESP issued on 05/05/2016 N/A  
$17,917,093 ABWR DC Renewal (Toshiba)
Information not known 10/27/2010 Yes A review schedule was not developed for this application Application withdrawn by the applicant N/A 06/09/2016 (withdrawal request)
$686,911 Victoria County ESP Information not known 03/25/2010 Yes FSER: 04/2013 FEIS: 08/2013 Application withdrawn by the applicant N/A 08/28/2012 (withdrawal request)  
$6,146,248 Calvert Cliffs COL Information not known 07/13/2007 (Part 1 of application) 03/14/2008 (Part 2 of application)
No Yes FSER: 07/2012 FEIS: 03/2010 FSER: N/A FEIS: 05/2011 Application withdrawn by the applicant N/A 02/27/2015 (suspension request) 06/08/2015 (withdrawal request)
$31,400,772 Nine Mile Point COL Information not known 09/30/2008 Yes A review schedule was not developed for this Application withdrawn by the applicant N/A 12/01/2009 (suspension request) 11/26/2013
$2,687,822


Original Date of Acceptanc      Review    Actual FSER Date of                                                                   Withdrawal or    Total Fees Date the    e Review      Schedule    and FEIS (or  Projected First Pre-                                                                 Suspension    Billed for Each Project Name                Application Completed      Dates for        EA)      Date for Application                                                                 Request (for      Review was Filed   in 60 Days   FSER and      Completion  Final NRC Meeting                                                                    terminated      (Note 4)
92 Project Name Date of First Pre-Application Meeting Date the Application was Filed Acceptanc e Review Completed in 60 Days (Note 1)
(Note 1)   FEIS (or EA)     Dates       Action projects only)
Original Review Schedule Dates for FSER and FEIS (or EA)
Completion Bell Bend COL   Information 10/10/2008   Yes       FSER: 03/2012  FSER: N/A    N/A        02/25/2015    $20,026,574 not known                            FEIS: 03/2011 FEIS: 04/2016            (suspension Application             request) withdrawn by the applicant           08/30/2016 (withdrawal request)
Completion Actual FSER and FEIS (or EA)
PSEG ESP       Information 05/25/2010  Yes       FSER: 07/2013  FSER:         ESP       N/A           $17,917,093 not known                           FEIS: 03/2013  09/2015      issued on FEIS: 11/2015 05/05/2016 ABWR DC        Information  10/27/2010  Yes        A review      Application  N/A       06/09/2016    $686,911 Renewal        not known                           schedule was  withdrawn by            (withdrawal (Toshiba)                                            not developed  the applicant            request) for this application Victoria County Information  03/25/2010  Yes       FSER: 04/2013  Application  N/A       08/28/2012    $6,146,248 ESP            not known                            FEIS: 08/2013  withdrawn by            (withdrawal the applicant            request)
Completion Dates Projected Date for Final NRC Action Date of Withdrawal or Suspension Request (for terminated projects only)
Calvert Cliffs  Information  07/13/2007  No         FSER: 07/2012  FSER: N/A     N/A       02/27/2015    $31,400,772 COL            not known   (Part 1 of              FEIS: 03/2010 FEIS: 05/2011            (suspension application)                          Application              request) withdrawn by 03/14/2008  Yes                      the applicant            06/08/2015 (Part 2 of                                                      (withdrawal application)                                                    request)
Total Fees Billed for Each Review (Note 4) application (withdrawal request)
Nine Mile Point Information 09/30/2008   Yes       A review       Application   N/A       12/01/2009    $2,687,822 COL            not known                            schedule was  withdrawn by            (suspension not developed  the applicant            request) for this                                11/26/2013 91
Grand Gulf COL Information not known 02/27/2008 Yes FSER: 03/2011 FEIS: 05/2010 Application withdrawn by the applicant N/A 2/9/2015 (withdrawal request)  
$4,719,505 Grand Gulf ESP Information not known 10/21/2003 Yes FSER: 10/2005 FEIS: 10/2005 FSER:
10/2005 FEIS: 04/2006 ESP issued on 04/05/2007 N/A  
$5,352,875 Clinton ESP Information not known 09/25/2003 Yes FSER: 08/2005 FEIS: 08/2005 FSER:
02/2006 FEIS: 07/2006 ESP issued on 3/15/2007 N/A  
$5,186,587 AP1000 DC Amendment Information not known 05/26/2007 Yes FSER: 08/2010 FEIS: N/A FSER:
08/2011 FEIS: N/A Final Rule published on 12/30/2011 N/A
$33,036,394 Economic Simplified Boiling Water Reactor (ESBWR) DC 6/20-21/2002 08/24/2005 No FSER: 06/2009 FEIS: N/A FSER:
03/2011 Supplement FSER: 9/2014 FEIS: N/A Final Rule published on 10/15/2014 N/A
$68,153,802 ABWR DC Amendment Information not known 06/30/2009 Yes FSER: 04/2010 FEIS: N/A FSER:
10/2010 FEIS: N/A Final Rule published on 12/16/2011 N/A
$1,145,852 Victoria County COL Information not known 09/03/2008 Yes A review schedule was not developed for this application Application withdrawn by the applicant N/A 06/11/2010 (withdrawal request)
$1,493,183


Original Date of Acceptanc      Review    Actual FSER Date of                                                                  Withdrawal or    Total Fees Date the   e Review      Schedule    and FEIS (or  Projected First Pre-                                                                Suspension    Billed for Each Project Name                Application Completed      Dates for        EA)      Date for Application                                                                Request (for      Review was Filed  in 60 Days    FSER and     Completion  Final NRC Meeting                                                                    terminated      (Note 4)
93 Note 1:
(Note 1)  FEIS (or EA)      Dates      Action projects only)
NROs acceptance review metric is to complete the acceptance review within 60 days and to issue a letter to the applicant documenting the staffs findings on acceptability within 75 days.
Completion application                            (withdrawal request)
Note 2:
Grand Gulf      Information  02/27/2008  Yes        FSER: 03/2011  Application  N/A        2/9/2015      $4,719,505 COL            not known                          FEIS: 05/2010  withdrawn by             (withdrawal the applicant           request)
The NRC is performing the review of the US APWR at a very reduced pace at the request of the applicant and will continue at this pace until notified by the applicant of a change in its plans. Therefore, no completion date has been established.
Grand Gulf ESP  Information  10/21/2003  Yes        FSER: 10/2005  FSER:        ESP       N/A            $5,352,875 not known                          FEIS: 10/2005  10/2005      issued on FEIS: 04/2006 04/05/2007 Clinton ESP    Information  09/25/2003  Yes        FSER: 08/2005  FSER:        ESP        N/A            $5,186,587 not known                          FEIS: 08/2005  02/2006      issued on FEIS: 07/2006 3/15/2007 AP1000 DC      Information  05/26/2007  Yes        FSER: 08/2010  FSER:        Final Rule N/A            $33,036,394 Amendment      not known                          FEIS: N/A      08/2011      published FEIS: N/A    on 12/30/2011 Economic        6/20-21/2002 08/24/2005  No        FSER: 06/2009  FSER:        Final Rule N/A            $68,153,802 Simplified                                          FEIS: N/A      03/2011      published Boiling Water                                                      Supplement    on Reactor                                                            FSER: 9/2014  10/15/2014 (ESBWR) DC                                                        FEIS: N/A ABWR DC        Information  06/30/2009  Yes        FSER: 04/2010  FSER:        Final Rule N/A            $1,145,852 Amendment      not known                          FEIS: N/A      10/2010      published FEIS: N/A    on 12/16/2011 Victoria County Information  09/03/2008  Yes        A review      Application  N/A        06/11/2010    $1,493,183 COL            not known                          schedule was  withdrawn by            (withdrawal not developed  the applicant            request) for this application 92
Note 3: The acceptance review for the Clinch River ESP application was extended at the request of the applicant, TVA, by {{letter dated|date=August 19, 2016|text=letter dated August 19, 2016}}.
Note 4:
The NRCs 10 CFR Part 170 charges are billed on a quarterly basis. Therefore, updates will be provided in this report to Question 43.h during the reporting periods for January, April, July, and October.


Note 1: NROs acceptance review metric is to complete the acceptance review within 60 days and to issue a letter to the applicant documenting the staffs findings on acceptability within 75 days.
94
Note 2: The NRC is performing the review of the US APWR at a very reduced pace at the request of the applicant and will continue at this pace until notified by the applicant of a change in its plans. Therefore, no completion date has been established.
: 44.
Note 3: The acceptance review for the Clinch River ESP application was extended at the request of the applicant, TVA, by letter dated August 19, 2016.
Please provide a concise summary of the status of ongoing design certification, COL, and ESP application reviews. Please include a discussion of the issuance of RAls and receipt of responses.
Note 4: The NRCs 10 CFR Part 170 charges are billed on a quarterly basis. Therefore, updates will be provided in this report to Question 43.h during the reporting periods for January, April, July, and October.
93
: 44.      Please provide a concise summary of the status of ongoing design certification, COL, and ESP application reviews. Please include a discussion of the issuance of RAls and receipt of responses.
In addition to the updates provided here, each of the DC, COL, and ESP milestone schedules that are under review are publicly available on the NRC website.
In addition to the updates provided here, each of the DC, COL, and ESP milestone schedules that are under review are publicly available on the NRC website.
DC Applications The NRC employs a 6 Phase schedule to monitor progress towards completion of the safety review. These phases are:
DC Applications The NRC employs a 6 Phase schedule to monitor progress towards completion of the safety review. These phases are:
* Phase 1 - Preliminary SER with RAIs issued to applicant
Phase 1 - Preliminary SER with RAIs issued to applicant Phase 2 - SER with Open Items issued Phase 3 - Response to ACRS regarding SER with Open Items issued Phase 4 - Advanced SER with no Open Items issued Phase 5 - Response to ACRS regarding SER with no Open Items issued Phase 6 - Final SER issued US-APWR Mitsubishi Heavy Industries (MHI) submitted its US-APWR DC application on December 31, 2007. The staff is currently in Phase 2 of the review. By {{letter dated|date=November 5, 2013|text=letter dated November 5, 2013}}, MHI initiated a coordinated slowdown of NRC licensing activities in order to focus its resources towards supporting the restart of the Mitsubishi-designed reactors in Japan following the Fukushima event. The NRC staff has been performing the review of the US-APWR DC application at a very reduced pace and will continue at this reduced pace until further notice from the applicant. As of January 31, 2018, the staff has issued 5,681 RAIs and the applicant has responded to 5,532 of them.
* Phase 2 - SER with Open Items issued
* Phase 3 - Response to ACRS regarding SER with Open Items issued
* Phase 4 - Advanced SER with no Open Items issued
* Phase 5 - Response to ACRS regarding SER with no Open Items issued
* Phase 6 - Final SER issued US-APWR Mitsubishi Heavy Industries (MHI) submitted its US-APWR DC application on December 31, 2007. The staff is currently in Phase 2 of the review. By letter dated November 5, 2013, MHI initiated a coordinated slowdown of NRC licensing activities in order to focus its resources towards supporting the restart of the Mitsubishi-designed reactors in Japan following the Fukushima event. The NRC staff has been performing the review of the US-APWR DC application at a very reduced pace and will continue at this reduced pace until further notice from the applicant. As of January 31, 2018, the staff has issued 5,681 RAIs and the applicant has responded to 5,532 of them.
APR1400 On December 23, 2014, Korea Electric Power Corp. and Korea Hydro & Nuclear Power Co.,
APR1400 On December 23, 2014, Korea Electric Power Corp. and Korea Hydro & Nuclear Power Co.,
Ltd. (KHNP), submitted to the NRC its application for the certification of the APR1400 standard plant design for use in the U.S. domestic energy market. The NRC completed the Phase 2 review for all chapters of the application in May 2017 and completed the Phase 3 review in June 2017. The staff is currently in Phases 4 and 5 of its review. As of January 31, 2018, the staff had issued 2,224 RAI questions and the applicant has responded to 2,223 of them. Of the RAI questions issued, 99.5% are closed or are considered confirmatory actions that the staff will verify, upon receipt of the updated final safety analysis report, that the applicant has incorporated all changes in accordance with the response approved by the staff.
Ltd. (KHNP), submitted to the NRC its application for the certification of the APR1400 standard plant design for use in the U.S. domestic energy market. The NRC completed the Phase 2 review for all chapters of the application in May 2017 and completed the Phase 3 review in June 2017. The staff is currently in Phases 4 and 5 of its review. As of January 31, 2018, the staff had issued 2,224 RAI questions and the applicant has responded to 2,223 of them. Of the RAI questions issued, 99.5% are closed or are considered confirmatory actions that the staff will verify, upon receipt of the updated final safety analysis report, that the applicant has incorporated all changes in accordance with the response approved by the staff.
On October 31, 2017, the staff issued an updated schedule letter to KHNP explaining that, although the NRC staff has made substantial progress toward completing both the remaining Phase 4 and Phase 5 reviews, issues related to the technical quality, completeness, or timeliness of the applicants submittals have resulted in delays that affected the milestone dates for completion of Phase 4 and Phase 5. Therefore, the staff revised the Phase 4 public milestone date from December 2017 to March 2018. While no change was made to the Phase 5 or Phase 6 milestone dates, the Phase 4 delay may also impact the completion of the review schedule within the 42 month schedule.
On October 31, 2017, the staff issued an updated schedule letter to KHNP explaining that, although the NRC staff has made substantial progress toward completing both the remaining Phase 4 and Phase 5 reviews, issues related to the technical quality, completeness, or timeliness of the applicants submittals have resulted in delays that affected the milestone dates for completion of Phase 4 and Phase 5. Therefore, the staff revised the Phase 4 public milestone date from December 2017 to March 2018. While no change was made to the Phase 5 or Phase 6 milestone dates, the Phase 4 delay may also impact the completion of the review schedule within the 42 month schedule.  
94


NuScale On January 6, 2017, NuScale submitted the first SMR DC application for review by the NRC.
95 NuScale On January 6, 2017, NuScale submitted the first SMR DC application for review by the NRC.
On March 15, 2017, the NRC completed its acceptance review and docketed the application.
On March 15, 2017, the NRC completed its acceptance review and docketed the application.
The staff issued the acceptance review letter to NuScale on March 23, 2017, and developed a full review schedule with public milestones that was transmitted to NuScale on May 22, 2017.
The staff issued the acceptance review letter to NuScale on March 23, 2017, and developed a full review schedule with public milestones that was transmitted to NuScale on May 22, 2017.
The staffs review is currently in Phase 1 and Phase 2. To date the NRC has identified 23 critical issues requiring resolution and that have the potential to adversely affect the review schedule. As of January 31, 2018, the staff has issued 357 RAIs, which included 994 RAI questions and the applicant has responded to 779 of the RAI questions. Of the 357 RAIs issued, 68 RAIs (19%) are now closed. This months report corrects the total number of RAIs that have been closed for the NuScale project.
The staffs review is currently in Phase 1 and Phase 2. To date the NRC has identified 23 critical issues requiring resolution and that have the potential to adversely affect the review schedule. As of January 31, 2018, the staff has issued 357 RAIs, which included 994 RAI questions and the applicant has responded to 779 of the RAI questions. Of the 357 RAIs issued, 68 RAIs (19%) are now closed. This months report corrects the total number of RAIs that have been closed for the NuScale project.
DC Renewal Applications ABWR Renewal (General Electric-Hitachi (GEH))
DC Renewal Applications ABWR Renewal (General Electric-Hitachi (GEH))
On December 7, 2010, GEH submitted an application for renewal of the ABWR DC. The review is currently in Phase 2, safety evaluation with open items. The NRC staff issued a letter to GEH on July 20, 2012, describing 28 design changes that GEH should have included in the application. By letter dated September 17, 2012, GEH stated it planned to address the 28 items in its Revision 6 of the ABWR DCD. By letter dated February 19, 2016, GEH submitted its revised application incorporating the changes to the ABWR DCD. On August 30, 2016, the staff issued a schedule letter to GEH based on resolving all open items by January 2017. However, some open items associated with the review of the application remain unresolved. On August 3, 2017, the staff issued a letter to GEH stating that the NRC will not be able to meet the original schedule outlined in the August 30, 2016, letter due to unresolved issues with the application. The letter also stated that the NRC will issue a revised schedule letter to GEH after additional interactions with the applicant are held to resolve these issues and the staff receives complete responses to the NRCs RAIs. As of January 31, 2018, the staff has issued 37 RAIs and the applicant has responded to all of them.
On December 7, 2010, GEH submitted an application for renewal of the ABWR DC. The review is currently in Phase 2, safety evaluation with open items. The NRC staff issued a letter to GEH on July 20, 2012, describing 28 design changes that GEH should have included in the application. By {{letter dated|date=September 17, 2012|text=letter dated September 17, 2012}}, GEH stated it planned to address the 28 items in its Revision 6 of the ABWR DCD. By {{letter dated|date=February 19, 2016|text=letter dated February 19, 2016}}, GEH submitted its revised application incorporating the changes to the ABWR DCD. On August 30, 2016, the staff issued a schedule letter to GEH based on resolving all open items by January 2017. However, some open items associated with the review of the application remain unresolved. On August 3, 2017, the staff issued a letter to GEH stating that the NRC will not be able to meet the original schedule outlined in the {{letter dated|date=August 30, 2016|text=August 30, 2016, letter}} due to unresolved issues with the application. The letter also stated that the NRC will issue a revised schedule letter to GEH after additional interactions with the applicant are held to resolve these issues and the staff receives complete responses to the NRCs RAIs. As of January 31, 2018, the staff has issued 37 RAIs and the applicant has responded to all of them.
COL Applications Turkey Point Units 6 and 7 On June 30, 2009, Florida Power & Light Company (FPL) submitted a COL application for two AP1000 units at the existing Turkey Point Nuclear Generating Station site in Miami-Dade County, FL. On September 4, 2009, the NRC staff issued a letter to FPL indicating the Turkey Point COL application was acceptable for docketing.
COL Applications Turkey Point Units 6 and 7 On June 30, 2009, Florida Power & Light Company (FPL) submitted a COL application for two AP1000 units at the existing Turkey Point Nuclear Generating Station site in Miami-Dade County, FL. On September 4, 2009, the NRC staff issued a letter to FPL indicating the Turkey Point COL application was acceptable for docketing.
The NRC staff completed its safety review and presented the final SER to ACRS on August 19, 2016. The final SER for Turkey Point was issued on November 10, 2016. The NRC issued the final EIS on October 28, 2016. The Commission held the mandatory hearing on December 12, 2017.
The NRC staff completed its safety review and presented the final SER to ACRS on August 19, 2016. The final SER for Turkey Point was issued on November 10, 2016. The NRC issued the final EIS on October 28, 2016. The Commission held the mandatory hearing on December 12, 2017.
On May 2-3, 2017, the ASLB conducted an evidentiary hearing in Homestead, FL, for the contested proceeding involving the Southern Alliance for Clean Energy, National Parks Conservation Association, and other joint intervenors. On July 10, 2017, the ASLB ruled in favor of the NRC staff and terminated the contested proceeding. No appeal was filed within the appeal deadline. On April 18, 2017, the City of Miami, City of South Miami, and Village of Pinecrest (petitioners) filed a new petition seeking a hearing. On July 31, 2017, the ASLB 95
On May 2-3, 2017, the ASLB conducted an evidentiary hearing in Homestead, FL, for the contested proceeding involving the Southern Alliance for Clean Energy, National Parks Conservation Association, and other joint intervenors. On July 10, 2017, the ASLB ruled in favor of the NRC staff and terminated the contested proceeding. No appeal was filed within the appeal deadline. On April 18, 2017, the City of Miami, City of South Miami, and Village of Pinecrest (petitioners) filed a new petition seeking a hearing. On July 31, 2017, the ASLB  


rejected the pending contention and terminated the contested proceeding involving those petitioners. The Commission denied the petitioners appeal from that decision on December 11, 2017 (CLI-17-12).
96 rejected the pending contention and terminated the contested proceeding involving those petitioners. The Commission denied the petitioners appeal from that decision on December 11, 2017 (CLI-17-12).
ESP Applications The NRC employs a 4 Phase schedule to monitor the progress towards completion of the safety review. These phases are:
ESP Applications The NRC employs a 4 Phase schedule to monitor the progress towards completion of the safety review. These phases are:
* Phase A - Preliminary SER and RAIs issued to the applicant
Phase A - Preliminary SER and RAIs issued to the applicant Phase B - Advanced SER with No Open Items Developed Phase C - ACRS meeting on Advanced SER Phase D - Final SER issued The NRC also employs a 4 Phase schedule to monitor completion of the environmental impact statement. These phases are:
* Phase B - Advanced SER with No Open Items Developed
Phase 1 - Scoping Summary Report issued Phase 2 - Draft EIS issued to the U.S. Environmental Protection Agency (EPA)
* Phase C - ACRS meeting on Advanced SER
Phase 3 - Responses to DEIS comments completed Phase 4 - Final EIS issued to EPA Clinch River On May 12, 2016, TVA submitted an ESP application for the Clinch River Nuclear Site located in Oak Ridge, Tennessee. By {{letter dated|date=August 11, 2016|text=letter dated August 11, 2016}}, TVA identified certain aspects of the application for which it intended to provide supplemental information. The NRC responded to TVA in a {{letter dated|date=August 19, 2016|text=letter dated August 19, 2016}}, and informed TVA that its application would remain in a tendered but not docketed status until all of the supplemental information was provided to NRC. By December 15, 2016, TVA had provided the supplemental information in support of its application, and by {{letter dated|date=January 5, 2017|text=letter dated January 5, 2017}}, the NRC staff informed TVA that its application, as supplemented, was acceptable for docketing and detailed technical review.
* Phase D - Final SER issued The NRC also employs a 4 Phase schedule to monitor completion of the environmental impact statement. These phases are:
* Phase 1 - Scoping Summary Report issued
* Phase 2 - Draft EIS issued to the U.S. Environmental Protection Agency (EPA)
* Phase 3 - Responses to DEIS comments completed
* Phase 4 - Final EIS issued to EPA Clinch River On May 12, 2016, TVA submitted an ESP application for the Clinch River Nuclear Site located in Oak Ridge, Tennessee. By letter dated August 11, 2016, TVA identified certain aspects of the application for which it intended to provide supplemental information. The NRC responded to TVA in a letter dated August 19, 2016, and informed TVA that its application would remain in a tendered but not docketed status until all of the supplemental information was provided to NRC. By December 15, 2016, TVA had provided the supplemental information in support of its application, and by letter dated January 5, 2017, the NRC staff informed TVA that its application, as supplemented, was acceptable for docketing and detailed technical review.
NRC staff began its detailed technical review of the ESP application in January 2017 and developed a full review schedule with public milestones that was transmitted to TVA on March 17, 2017. The Phase A review for all chapters of the application was completed by the staff on August 4, 2017 (consistent with the established schedule). The staff is currently in Phase B of its review, which is scheduled to conclude on October 29, 2018. As of January 31, 2018, the staff has issued 42 RAI questions and the applicant has responded to 34 RAI questions. Of the RAI questions issued, 81% are closed or are considered confirmatory items.
NRC staff began its detailed technical review of the ESP application in January 2017 and developed a full review schedule with public milestones that was transmitted to TVA on March 17, 2017. The Phase A review for all chapters of the application was completed by the staff on August 4, 2017 (consistent with the established schedule). The staff is currently in Phase B of its review, which is scheduled to conclude on October 29, 2018. As of January 31, 2018, the staff has issued 42 RAI questions and the applicant has responded to 34 RAI questions. Of the RAI questions issued, 81% are closed or are considered confirmatory items.
The final SER is projected to be issued in August 2019.
The final SER is projected to be issued in August 2019.
On June 12, 2017, the Southern Alliance for Clean Energy (SACE), Tennessee Environmental Coalition (TEC), and Blue Ridge Environmental Defense League filed petitions seeking a hearing. On September 12, 2017, the ASLB conducted oral argument on these petitions. On October 10, 2017, the Licensing Board issued a decision that denied the Blue Ridge Environmental Defense Leagues petition to intervene and granted the SACE and the TECs joint petition to intervene and admitted two contentions. SACE/TEC filed a motion for reconsideration of the Boards dismissal of the third contention and the motion was dismissed.
On June 12, 2017, the Southern Alliance for Clean Energy (SACE), Tennessee Environmental Coalition (TEC), and Blue Ridge Environmental Defense League filed petitions seeking a hearing. On September 12, 2017, the ASLB conducted oral argument on these petitions. On October 10, 2017, the Licensing Board issued a decision that denied the Blue Ridge Environmental Defense Leagues petition to intervene and granted the SACE and the TECs joint petition to intervene and admitted two contentions. SACE/TEC filed a motion for reconsideration of the Boards dismissal of the third contention and the motion was dismissed.
Separately, TVA appealed the admission of the two contentions to the Commission and that appeal is currently pending before the Commission. The Board is working to schedule the contested hearing for the two admitted contentions.
Separately, TVA appealed the admission of the two contentions to the Commission and that appeal is currently pending before the Commission. The Board is working to schedule the contested hearing for the two admitted contentions.  
96
 
97
: 45. For reactors under construction, please provide:
: 45. For reactors under construction, please provide:
Project Name               Project Type           Licensing Status Vogtle Unit 3             COL Holder       COL issued on 02/10/2012 Vogtle Unit 4             COL Holder       COL issued on 02/10/2012
Project Name Project Type Licensing Status Vogtle Unit 3 COL Holder COL issued on 02/10/2012 Vogtle Unit 4 COL Holder COL issued on 02/10/2012
: a. The number of NRC inspections and ITAAC reviews forecast to be completed per month versus the number completed each month; NRC Inspections Test Analyses and Acceptance Criteria (ITAAC) Inspections:
: a. The number of NRC inspections and ITAAC reviews forecast to be completed per month versus the number completed each month; NRC Inspections Test Analyses and Acceptance Criteria (ITAAC) Inspections:
ITAAC Inspections Completion Status 14 13 ITAAC Inspections Completed 12 ITAAC Inspections Not Complete for ICNs Submitted 10 Total Number 8
Comments:
8 6
4 3
2 2                                                                1 0
0 Nov-17                      Dec-17                Jan-18 Comments:
The graph above tracks, by month, the number of ITAAC inspections completed and the number of ITAAC inspections not completed for ITAAC Closure Notifications (ICNs) that had been received. For each ITAAC, there are predetermined inspections to be completed in order to provide assurance that the licensee has met the design commitments and that the ITAAC acceptance criteria are met.
The graph above tracks, by month, the number of ITAAC inspections completed and the number of ITAAC inspections not completed for ITAAC Closure Notifications (ICNs) that had been received. For each ITAAC, there are predetermined inspections to be completed in order to provide assurance that the licensee has met the design commitments and that the ITAAC acceptance criteria are met.
An ITAAC inspection is comprised of multiple inspection activities that may be performed over days, weeks, or months. For this graph, the term ITAAC inspection complete means that all the associated NRC inspection activities tied to that ITAAC have been completed, verified, and marked Inspection Complete in the NRC database. The term ITAAC Inspection Not Complete represents the number of ITAACs for which the completed box in the NRC database has not been checked for ICNs that had been submitted by the licensee. The three items that were not completed for January were due to a Unit 4 construction activity that had not been completed and two ICNs that were submitted at the end of January for which the 97
An ITAAC inspection is comprised of multiple inspection activities that may be performed over days, weeks, or months. For this graph, the term ITAAC inspection complete means that all the associated NRC inspection activities tied to that ITAAC have been completed, verified, and marked Inspection Complete in the NRC database. The term ITAAC Inspection Not Complete represents the number of ITAACs for which the completed box in the NRC database has not been checked for ICNs that had been submitted by the licensee. The three items that were not completed for January were due to a Unit 4 construction activity that had not been completed and two ICNs that were submitted at the end of January for which the 0
1 8
3 0
2 4
6 8
10 12 14 Nov-17 Dec-17 Jan-18 Total Number ITAAC Inspections Completion Status ITAAC Inspections Completed ITAAC Inspections Not Complete for ICNs Submitted 2
13


associated inspections were not completed. Those two inspections have since been completed.
98 associated inspections were not completed. Those two inspections have since been completed.
Because of the coordination between the NRCs inspections and the licensees construction activities, the majority of the required inspections are scheduled and completed prior to the ICN submittal. The completion of these ITAAC-related inspections closely mirrors the completion status of the licensees (Southern Nuclear Operating Company) associated work activities. Changes to the licensees construction schedule due to weather conditions, work sequencing, and other factors impact when NRC inspections can be performed.
Because of the coordination between the NRCs inspections and the licensees construction activities, the majority of the required inspections are scheduled and completed prior to the ICN submittal. The completion of these ITAAC-related inspections closely mirrors the completion status of the licensees (Southern Nuclear Operating Company) associated work activities. Changes to the licensees construction schedule due to weather conditions, work sequencing, and other factors impact when NRC inspections can be performed.
ITAAC Closure Notifications Reviews:
ITAAC Closure Notifications Reviews:
The NRCs goal is to complete 90% of ICN reviews within 60 days. However, some ICN reviews may be completed in significantly less time. Conversely, complex ICN reviews may require more than 60 days to complete. For this reason, it is difficult for the NRC to forecast in which month a specific ICN review will be completed based on its submittal date. Therefore, the NRC relies on the metrics reported in its response to question 45.b.
The NRCs goal is to complete 90% of ICN reviews within 60 days. However, some ICN reviews may be completed in significantly less time. Conversely, complex ICN reviews may require more than 60 days to complete. For this reason, it is difficult for the NRC to forecast in which month a specific ICN review will be completed based on its submittal date. Therefore, the NRC relies on the metrics reported in its response to question 45.b.
: b. The percentage of NRC inspections and the percentage of ITAAC reviews completed within 30 days and within two months; New Reactor Inspection Status:
: b. The percentage of NRC inspections and the percentage of ITAAC reviews completed within 30 days and within two months; New Reactor Inspection Status:
Comments:
This graph represents the percentage of NRC inspections associated with ITAAC that have been completed since the start of construction with respect to the total number of inspections required for the Vogtle facility.
20.8%
20.8%
20.8%
37.0%
37.4%
37.5%
0%
10%
20%
30%
40%
50%
50%
AP1000 Construction Inspection Completion Progress 40%                    37.0%                        37.4%                        37.5%
Nov-17 Dec-17 Jan-18 AP1000 Construction Inspection Completion Progress Vogtle 3 & 4 Program Inspections Completed Vogtle 3 & 4 ITAAC Inspections Completed
30%
20.8%                        20.8%                        20.8%
20%
10%
0%
Nov-17                       Dec-17                       Jan-18 Vogtle 3 & 4 Program Inspections Completed       Vogtle 3 & 4 ITAAC Inspections Completed Comments:
This graph represents the percentage of NRC inspections associated with ITAAC that have been completed since the start of construction with respect to the total number of inspections required for the Vogtle facility.
98


The ITAAC completion status is updated once inspections are completed, approved, and marked Inspection Complete in the NRC database. Planned inspection activities are evaluated and updated to ensure they align with licensees work activities.
99 The ITAAC completion status is updated once inspections are completed, approved, and marked Inspection Complete in the NRC database. Planned inspection activities are evaluated and updated to ensure they align with licensees work activities.
This graph also reports the percentage of completed program inspections since the start of construction for the Vogtle facility, which include both programs required for construction and programs required for operation of Units 3 & 4. There are a total of five construction programs, which include Quality Assurance, Fitness for Duty, and ITAAC Management. In addition, there are a total of 20 operational programs, which include Fire Protection, Emergency Preparedness, Reactor Operator Training, and Security. The graph depicts the percentage of planned inspections that are completed, and does not account for the level of effort required for inspections.
This graph also reports the percentage of completed program inspections since the start of construction for the Vogtle facility, which include both programs required for construction and programs required for operation of Units 3 & 4. There are a total of five construction programs, which include Quality Assurance, Fitness for Duty, and ITAAC Management. In addition, there are a total of 20 operational programs, which include Fire Protection, Emergency Preparedness, Reactor Operator Training, and Security. The graph depicts the percentage of planned inspections that are completed, and does not account for the level of effort required for inspections.
Timeliness of ITAAC Closure Notification Reviews:
Timeliness of ITAAC Closure Notification Reviews:
Line 1,003: Line 1,303:
This bar chart shows the percentage of ICNs reviews completed each month within 30 days and within 60 days. Some of the months shown on the bar chart reflect that the ICN reviews are not meeting the review metric of 90% complete within 60 days. The majority of the delays in these reviews were due to coordination issues between the NRC and the licensee resulting in equipment or activities not being available for scheduled inspections. We are engaging with the licensee to bring attention to those ICNs that require inspection accessibility for timely closure of the ICNs. As the NRC has implemented efficiencies into the process and enhanced communication, the NRC has noticed an improvement in the completion rate. The NRC expects this trend to continue as we move forward.
This bar chart shows the percentage of ICNs reviews completed each month within 30 days and within 60 days. Some of the months shown on the bar chart reflect that the ICN reviews are not meeting the review metric of 90% complete within 60 days. The majority of the delays in these reviews were due to coordination issues between the NRC and the licensee resulting in equipment or activities not being available for scheduled inspections. We are engaging with the licensee to bring attention to those ICNs that require inspection accessibility for timely closure of the ICNs. As the NRC has implemented efficiencies into the process and enhanced communication, the NRC has noticed an improvement in the completion rate. The NRC expects this trend to continue as we move forward.
: c. For ITAAC reviews completed during the reporting period, please provide the date when the NRC received the ITAAC closure notice and the date when the review was completed.
: c. For ITAAC reviews completed during the reporting period, please provide the date when the NRC received the ITAAC closure notice and the date when the review was completed.
For the current reporting period of January 2018, a total of seven ICNs were completed.
For the current reporting period of January 2018, a total of seven ICNs were completed.  
99


Received        Approval Month               Unit       ITAAC Date           Date
100 Month Unit ITAAC Received Date Approval Date
: 46. For reactors under construction, please provide:
: 46. For reactors under construction, please provide:
: a. The number of license amendment reviews forecast to be completed in the reporting period;
: a. The number of license amendment reviews forecast to be completed in the reporting period;
: b. The number completed in the reporting period; and
: b. The number completed in the reporting period; and
: c. The number of those that were completed within 30 days.
: c. The number of those that were completed within 30 days.
Number of License Amendment Reviews                                       Number of Those that Reporting                                Number Completed in the Forecast to be                                       were Completed Period                                        Reporting Period Completed in the                                       within 30 Days Reporting Period January 2018                   5                         2                         1
Reporting Period Number of License Amendment Reviews Forecast to be Completed in the Reporting Period Number Completed in the Reporting Period Number of Those that were Completed within 30 Days January 2018 5
2 1
: 47. For reactors under construction, please provide the budgeted resources versus actual expenditures each month for the last 24 months.
: 47. For reactors under construction, please provide the budgeted resources versus actual expenditures each month for the last 24 months.
The NRC does not formulate the budget on a monthly basis. The annual budget for construction resources is provided below. The monthly budgeted resources provided below are calculated as 1/12th of the annual budgeted construction resources.
The NRC does not formulate the budget on a monthly basis. The annual budget for construction resources is provided below. The monthly budgeted resources provided below are calculated as 1/12th of the annual budgeted construction resources.
FY 2016 Enacted Budget ($K)         $17,169 FY 2017 Enacted Budget ($K)         $14,191 FY 2018 Estimated Budget ($K)       $15,526 Budgeted           Total Month      Resources         Expended
FY 2016 Enacted Budget ($K)  
($K)             ($K)
$17,169 FY 2017 Enacted Budget ($K)  
Feb-2016       $1,431           $750 Mar-2016       $1,431           $823 Apr-2016       $1,431           $764 May-2016       $1,431           $844 Jun-2016       $1,431           $857 Jul-2016       $1,431           $946 Aug-2016       $1,431           $1,005 100
$14,191 FY 2018 Estimated Budget ($K)  
$15,526 Month Budgeted Resources
($K)
Total Expended
($K)
Feb-2016  
$1,431  
$750 Mar-2016  
$1,431  
$823 Apr-2016  
$1,431  
$764 May-2016  
$1,431  
$844 Jun-2016  
$1,431  
$857 Jul-2016  
$1,431  
$946 Aug-2016  
$1,431  
$1,005  


FY 2016 Enacted Budget ($K)             $17,169 FY 2017 Enacted Budget ($K)             $14,191 FY 2018 Estimated Budget ($K)           $15,526 Budgeted             Total Month        Resources           Expended
101 FY 2016 Enacted Budget ($K)  
($K)               ($K)
$17,169 FY 2017 Enacted Budget ($K)  
Sep-2016         $1,431             $921 Oct-2016         $1,183             $829 Nov-2016         $1,183             $882 Dec-2016         $1,183             $935 Jan-2017         $1,183             $983 Feb-2017         $1,183             $845 Mar-2017         $1,183           $1,048 Apr-2017         $1,183             $859 May-2017         $1,183             $990 Jun-2017         $1,183           $1,058 Jul-2017         $1,183           $1,129 Aug-2017         $1,183             $886 Sep-2017         $1,183             $808 Oct-2017         $1,294             $837 Nov-2017         $1,294             $926 Dec-2017         $1,294             $882 Jan-2018         $1,294             $878
$14,191 FY 2018 Estimated Budget ($K)  
$15,526 Month Budgeted Resources
($K)
Total Expended
($K)
Sep-2016  
$1,431  
$921 Oct-2016  
$1,183  
$829 Nov-2016  
$1,183  
$882 Dec-2016  
$1,183  
$935 Jan-2017  
$1,183  
$983 Feb-2017  
$1,183  
$845 Mar-2017  
$1,183  
$1,048 Apr-2017  
$1,183  
$859 May-2017  
$1,183  
$990 Jun-2017  
$1,183  
$1,058 Jul-2017  
$1,183  
$1,129 Aug-2017  
$1,183  
$886 Sep-2017  
$1,183  
$808 Oct-2017  
$1,294  
$837 Nov-2017  
$1,294  
$926 Dec-2017  
$1,294  
$882 Jan-2018  
$1,294  
$878
: 48. Please provide a concise summary of the status of licensing and inspection for Vogtle 3 & 4, including any challenges to the timely resolution of: licensing issues, 10 CFR Part 52 interpretations, completion of inspections, or completion of ITAAC reviews.
: 48. Please provide a concise summary of the status of licensing and inspection for Vogtle 3 & 4, including any challenges to the timely resolution of: licensing issues, 10 CFR Part 52 interpretations, completion of inspections, or completion of ITAAC reviews.
The NRC issued COLs to SNC and several co-owners on February 10, 2012, for two AP1000 units at the Vogtle site near Augusta, GA. As construction progresses, the NRC has increased the pace of construction inspections to verify compliance with the agencys regulations and to ensure that the new plants are constructed in accordance with their COLs. A summary of the license amendment inventory for Vogtle 3 & 4 is included in response to question 13. There are currently no challenges with timely resolution of licensing issues for Vogtle 3 & 4.
The NRC issued COLs to SNC and several co-owners on February 10, 2012, for two AP1000 units at the Vogtle site near Augusta, GA. As construction progresses, the NRC has increased the pace of construction inspections to verify compliance with the agencys regulations and to ensure that the new plants are constructed in accordance with their COLs. A summary of the license amendment inventory for Vogtle 3 & 4 is included in response to question 13. There are currently no challenges with timely resolution of licensing issues for Vogtle 3 & 4.
The graphs provided in Item 45 of this report represent the completion status of ITAAC inspections and ICN reviews. The completion of these ITAAC-related inspections closely mirrors the completion status of the licensees work activities associated with the ITAAC. The graphs also display the percentage of completed program inspections, which are separate from the ITAAC-related inspections, and include both construction and operational programs. For ITAAC reviews, the NRC tracks the timeliness of ICNs reviewed and closed. In the past year the NRC has increased communication with the licensee and other external stakeholders through various public meetings and workshops to improve processes that support ICN closure, including inspection related activities. With the improvements identified to the processes and increased communication with the licensee, the staff does not foresee any major challenges for 2018.
The graphs provided in Item 45 of this report represent the completion status of ITAAC inspections and ICN reviews. The completion of these ITAAC-related inspections closely mirrors the completion status of the licensees work activities associated with the ITAAC. The graphs also display the percentage of completed program inspections, which are separate from the ITAAC-related inspections, and include both construction and operational programs. For ITAAC reviews, the NRC tracks the timeliness of ICNs reviewed and closed. In the past year the NRC has increased communication with the licensee and other external stakeholders through various public meetings and workshops to improve processes that support ICN closure, including inspection related activities. With the improvements identified to the processes and increased communication with the licensee, the staff does not foresee any major challenges for 2018.  
101
 
102
: 49. Please describe any actions taken in the past 3 years or planned to improve the efficiency of new plant reviews, including milestone schedules to implement efficiency improvements.
: 49. Please describe any actions taken in the past 3 years or planned to improve the efficiency of new plant reviews, including milestone schedules to implement efficiency improvements.
Please include any concerns arising from review experience in the past 3 years.
Please include any concerns arising from review experience in the past 3 years.
Line 1,032: Line 1,391:
NRO has also incorporated many of the lessons-learned from previous new reactor reviews into its review activities for the active DC and ESP applications. As described in response to question 24, NRO implemented an initiative in 2016 to improve the focus of RAIs, which has improved the quality and safety focus of information requests. The staff is also enhancing use of the regulatory audit tool.
NRO has also incorporated many of the lessons-learned from previous new reactor reviews into its review activities for the active DC and ESP applications. As described in response to question 24, NRO implemented an initiative in 2016 to improve the focus of RAIs, which has improved the quality and safety focus of information requests. The staff is also enhancing use of the regulatory audit tool.
NRO has instituted an Enhanced Safety Focus Review initiative for the NuScale design certification review. This initiative focuses the staffs review on first-of-a-kind or high safety, high risk areas of the design, and simplifies the review of lower safety or risk significant areas.
NRO has instituted an Enhanced Safety Focus Review initiative for the NuScale design certification review. This initiative focuses the staffs review on first-of-a-kind or high safety, high risk areas of the design, and simplifies the review of lower safety or risk significant areas.
In addition, the NRC has made significant progress on initiatives to enhance the regulatory framework for non-light water reactors (non-LWRs). For example, in December 2017, the NRC issued the Regulatory Review Roadmap for Non-Light Water Reactors, which described flexible review options including the use of a staged-review process and the use of conceptual design assessments during the pre-application period. The actions for advanced reactor reviews are described more fully in response to question 52.
In addition, the NRC has made significant progress on initiatives to enhance the regulatory framework for non-light water reactors (non-LWRs). For example, in December 2017, the NRC issued the Regulatory Review Roadmap for Non-Light Water Reactors, which described flexible review options including the use of a staged-review process and the use of conceptual design assessments during the pre-application period. The actions for advanced reactor reviews are described more fully in response to question 52.  
102
 
103
: 50. Please provide a list of any unresolved policy issues with regard to the licensing of small modular light-water reactors (SMRs). Please include an approximate date for when each issue was first raised, any actions taken or planned to resolve the issue, the milestone scheduled for resolution, and the projected date for resolution.
: 50. Please provide a list of any unresolved policy issues with regard to the licensing of small modular light-water reactors (SMRs). Please include an approximate date for when each issue was first raised, any actions taken or planned to resolve the issue, the milestone scheduled for resolution, and the projected date for resolution.
Issue Title/Applicability   Status                                               References I. Appropriate Source       In the December 29, 2011, memorandum to the         Staff Draft Term, Dose              Commission, the staff stated it would remain         White Paper Calculations, and        engaged with SMR stakeholders regarding             (11/29/17)
Issue Title/Applicability Status References I. Appropriate Source Term, Dose Calculations, and Siting for SMRs Applicability: SMRs and non-LWRs In the December 29, 2011, memorandum to the Commission, the staff stated it would remain engaged with SMR stakeholders regarding applications of mechanistic source term (MST) methods, review of pre-application white papers and topical reports it receives from potential SMR applicants concerning source term issues that discuss design-specific proposals to address MST, and considerations of research and development in this area. If necessary, the staff would propose revised review guidance or regulations, or propose new guidance to support reviews of SMRs.
Siting for SMRs          applications of mechanistic source term (MST) methods, review of pre-application white papers     SECY-16-0012 Applicability: SMRs and      and topical reports it receives from potential       (02/07/16) non-LWRs                    SMR applicants concerning source term issues         Commission that discuss design-specific proposals to           Memo address MST, and considerations of research         (06/20/14) and development in this area. If necessary, the     Commission staff would propose revised review guidance or       Memo regulations, or propose new guidance to support     (05/30/13) reviews of SMRs.                                     Commission Memo In Commission Memoranda dated May 30,               (12/29/11) 2013, and June 20, 2014, the staff provided updates on interactions with DOE and nuclear industry organizations regarding MST. On February 7, 2016, the staff provided the Commission SECY 16-0012, which addressed this item. The paper concluded that (1) SMR and non-light water reactor (non-LWR) applicants can employ modern analysis tools to demonstrate quantitatively the safety features of those designs, and (2) MST analysis methods can also be used by applicants to demonstrate the ability of the enhanced safety features of plant designs to mitigate accident releases, allow future COL applicants to consider reduced distances to Exclusion Area Boundaries and Low Population Zones and potentially increase proximity to population centers.
In Commission Memoranda dated May 30, 2013, and June 20, 2014, the staff provided updates on interactions with DOE and nuclear industry organizations regarding MST. On February 7, 2016, the staff provided the Commission SECY 16-0012, which addressed this item. The paper concluded that (1) SMR and non-light water reactor (non-LWR) applicants can employ modern analysis tools to demonstrate quantitatively the safety features of those designs, and (2) MST analysis methods can also be used by applicants to demonstrate the ability of the enhanced safety features of plant designs to mitigate accident releases, allow future COL applicants to consider reduced distances to Exclusion Area Boundaries and Low Population Zones and potentially increase proximity to population centers.
Disposition: The staff has engaged with interested stakeholders on this issue in 2017.
Disposition: The staff has engaged with interested stakeholders on this issue in 2017.
The staff developed a draft white paper summarizing the assessment of current siting regulations, guidance, and Commission policy and discussed it in a public meeting on December 14, 2017. The staff will consider insights obtained from stakeholder discussions and determine whether clarifications to siting guidance or other actions would be beneficial to address siting criteria for SMRs and non-LWRs.
The staff developed a draft white paper summarizing the assessment of current siting regulations, guidance, and Commission policy and discussed it in a public meeting on December 14, 2017. The staff will consider insights obtained from stakeholder discussions and determine whether clarifications to siting guidance or other actions would be beneficial to address siting criteria for SMRs and non-LWRs.
The staff will report to the Commission on any 103
The staff will report to the Commission on any Staff Draft White Paper (11/29/17)
SECY-16-0012 (02/07/16)
Commission Memo (06/20/14)
Commission Memo (05/30/13)
Commission Memo (12/29/11)


Issue Title/Applicability Status                                               References proposed actions, as described in SECY                           0012.
104 Issue Title/Applicability Status References proposed actions, as described in SECY 0012.
II. Offsite Emergency     In SECY-11-0152, staff identified a possible         Final Planning (EP)        approach for a scalable emergency planning           Regulatory Requirements for      zone for SMRs. The NRO staff is working with         Basis SMRs and other new    NSIR and NRR on an internal working group to         (10/16/17) technology.          review these issues further. As part of the approach, the staff would liaise with other           SRM-SECY Applicability: SMRs and  stakeholders (Department of Homeland                 0069 (06/22/16) non-LWRs                  Security/Federal Emergency Management                 SECY-16-0069 Agency, the Environmental Protection Agency,         (05/31/16)
II. Offsite Emergency Planning (EP)
Department of State, Department of Commerce,         SRM-SECY                          NEI, American Nuclear Society, and the public),       0077 (08/04/15) consider industry position papers on this topic       SECY-15-0077 and develop recommendations.                         (05/29/15)
Requirements for SMRs and other new technology.
NEI Response to NRC In a May 30, 2013, Commission Memorandum, Questions on the staff provided updates on its EP activities.
Applicability: SMRs and non-LWRs In SECY-11-0152, staff identified a possible approach for a scalable emergency planning zone for SMRs. The NRO staff is working with NSIR and NRR on an internal working group to review these issues further. As part of the approach, the staff would liaise with other stakeholders (Department of Homeland Security/Federal Emergency Management Agency, the Environmental Protection Agency, Department of State, Department of Commerce, NEI, American Nuclear Society, and the public),
White Paper The staff stated that it would not propose new       (11/19/14) policy or revise guidance for specific changes to    NRC Letter to EP requirements absent specific proposals from       NEI (R. Bell) the industry.                                         (06/11/14)
consider industry position papers on this topic and develop recommendations.
NEI White Paper On December 23, 2013, NEI submitted a white           (12/23/13) paper on this topic. The staff conducted a public     Commission meeting to discuss the white paper on                 Memo April 8, 2014, issued follow-up questions to NEI     (05/30/13) on June 11, 2014, and received NEI responses         SECY-11-0152 in November 2014. On May 29, 2015, staff             (10/28/11) issued SECY-15-0077 regarding EP for SMRs and non-LWRs. On August 4, 2015, the Commission approved the staff's recommendation to initiate a rulemaking. Staff developed SECY-16-0069, which discussed the rulemaking plan and schedule. On June 22, 2016, the Commission approved the staff's plan and schedule for the rulemaking.
In a May 30, 2013, Commission Memorandum, the staff provided updates on its EP activities.
The staff stated that it would not propose new policy or revise guidance for specific changes to EP requirements absent specific proposals from the industry.
On December 23, 2013, NEI submitted a white paper on this topic. The staff conducted a public meeting to discuss the white paper on April 8, 2014, issued follow-up questions to NEI on June 11, 2014, and received NEI responses in November 2014. On May 29, 2015, staff issued SECY-15-0077 regarding EP for SMRs and non-LWRs. On August 4, 2015, the Commission approved the staff's recommendation to initiate a rulemaking. Staff developed SECY-16-0069, which discussed the rulemaking plan and schedule. On June 22, 2016, the Commission approved the staff's plan and schedule for the rulemaking.
Disposition: The rulemaking will address EP issues for future SMRs, non-LWR, and other new design technologies such as isotope producing facilities. The Commission directed the staff to utilize exemptions in the interim (e.g.,
Disposition: The rulemaking will address EP issues for future SMRs, non-LWR, and other new design technologies such as isotope producing facilities. The Commission directed the staff to utilize exemptions in the interim (e.g.,
for the TVA ESP) until completion of the EP rulemaking. The draft regulatory basis was published for public comment in the Federal Register on April 13, 2017. A public meeting was held May 10, 2017, to discuss the draft regulatory basis. The public comment period closed on June 27, 2017. After considering the 104
for the TVA ESP) until completion of the EP rulemaking. The draft regulatory basis was published for public comment in the Federal Register on April 13, 2017. A public meeting was held May 10, 2017, to discuss the draft regulatory basis. The public comment period closed on June 27, 2017. After considering the Final Regulatory Basis (10/16/17)
SRM-SECY 0069 (06/22/16)
SECY-16-0069 (05/31/16)
SRM-SECY 0077 (08/04/15)
SECY-15-0077 (05/29/15)
NEI Response to NRC Questions on White Paper (11/19/14)
NRC Letter to NEI (R. Bell)
(06/11/14)
NEI White Paper (12/23/13)
Commission Memo (05/30/13)
SECY-11-0152 (10/28/11)


Issue Title/Applicability   Status                                             References public comments, the staff issued the final regulatory basis on October 16, 2017. The proposed rule is scheduled to be provided to the Commission for its consideration in October 2018.
105 Issue Title/Applicability Status References public comments, the staff issued the final regulatory basis on October 16, 2017. The proposed rule is scheduled to be provided to the Commission for its consideration in October 2018.
III. Insurance and         In SECY-11-0178, the staff identified a potential   SECY-11-0178 Liability for SMRs    inequity between the insurance requirements for     (12/22/11) power reactors producing electrical power equal Applicability: SMRs and    or greater than 100 MWe per unit and those non-LWRs                    SMR designs with individual modules producing less than 100 MWe. Specifically, staff raised the question of whether there would be insurance and indemnity coverage sufficient to pay all public claims in the case of an insurable event for an SMR with an individual module sized at less than 100 MWe under the current Price-Anderson Act and associated regulatory language.
III. Insurance and Liability for SMRs Applicability: SMRs and non-LWRs In SECY-11-0178, the staff identified a potential inequity between the insurance requirements for power reactors producing electrical power equal or greater than 100 MWe per unit and those SMR designs with individual modules producing less than 100 MWe. Specifically, staff raised the question of whether there would be insurance and indemnity coverage sufficient to pay all public claims in the case of an insurable event for an SMR with an individual module sized at less than 100 MWe under the current Price-Anderson Act and associated regulatory language.
Since completing that paper, staff prepared a comparative analysis of different SMR designs to further explore the potential inequity. Staff is using this analysis, and other inputs, to develop a SECY paper for this topic. In the paper, staff will identify whether rulemaking or a change to the current interpretation of the definitions given in the Price-Anderson Act is recommended.
Since completing that paper, staff prepared a comparative analysis of different SMR designs to further explore the potential inequity. Staff is using this analysis, and other inputs, to develop a SECY paper for this topic. In the paper, staff will identify whether rulemaking or a change to the current interpretation of the definitions given in the Price-Anderson Act is recommended.
Disposition: In accordance with the latest version of the Price-Anderson Act, the NRC will prepare a report to Congress, and an associated SECY paper, recommending the need for continuation or modification of the provisions of the Price-Anderson Act by December 31, 2021.
Disposition: In accordance with the latest version of the Price-Anderson Act, the NRC will prepare a report to Congress, and an associated SECY paper, recommending the need for continuation or modification of the provisions of the Price-Anderson Act by December 31, 2021.
Any changes that may be needed for non-LWRs and SMRs will be addressed by the staff in that report and SECY paper.
Any changes that may be needed for non-LWRs and SMRs will be addressed by the staff in that report and SECY paper.
The staff engaged stakeholders on this topic during a November 2, 2017, public meeting and is awaiting feedback.
The staff engaged stakeholders on this topic during a November 2, 2017, public meeting and is awaiting feedback.
IV. Security and           In SECY-11-0184, staff informed the                 Staff Draft Safeguards            Commission of its determination that the current   White Paper Requirements for      regulatory framework is adequate to certify,       (11/29/17)
SECY-11-0178 (12/22/11)
SMRs                  approve, and license light-water SMRs, the manufacturing of SMR fuel, transportation of       NEI White Applicability: SMRs and special nuclear material and irradiated fuel, and   Paper non-LWRs                the interim storage of irradiated fuel proposed     (12/14/16) for light-water SMRs under 10 CFR Parts 50, 52, 70, 71, and 72, respectively. The staff also 105
IV. Security and Safeguards Requirements for SMRs Applicability: SMRs and non-LWRs In SECY-11-0184, staff informed the Commission of its determination that the current regulatory framework is adequate to certify, approve, and license light-water SMRs, the manufacturing of SMR fuel, transportation of special nuclear material and irradiated fuel, and the interim storage of irradiated fuel proposed for light-water SMRs under 10 CFR Parts 50, 52, 70, 71, and 72, respectively. The staff also Staff Draft White Paper (11/29/17)
NEI White Paper (12/14/16)


Issue Title/Applicability Status                                             References determined that security and material control       SECY-11-0184 and accounting requirements in 10 CFR Parts         (12/29/11) 72, 73, and 74, respectively, are also adequate.
106 Issue Title/Applicability Status References determined that security and material control and accounting requirements in 10 CFR Parts 72, 73, and 74, respectively, are also adequate.
In the case of non-LWRs, the staff's preliminary conclusion is that the current security regulatory framework is comprehensive and sufficiently robust to certify, approve, and license non-LWRs. Sufficient provisions are available to provide flexibility for designers and applicants to meet performance-based and prescriptive security requirements and to apply methods or approaches to achieve the objective of high assurance that activities involving special nuclear materials are not inimical to the common defense and security and do not constitute an unreasonable risk to public health. On December 14, 2016, NEI submitted a white paper on a "Proposed Consequence-Based Physical Security Framework for Small Modular Reactors and Other New Technologies." This paper "... proposes an approach to security that considers the enhanced safety and security incorporated into these designs and provides a more effective and efficient means to protect the public health and safety." In the transmittal letter, NEI requests that "... the NRC establish regulatory positions on this approach and the associated policy and technical issues." NEI submitted a fee waiver request for NRCs review of this white paper.
In the case of non-LWRs, the staff's preliminary conclusion is that the current security regulatory framework is comprehensive and sufficiently robust to certify, approve, and license non-LWRs. Sufficient provisions are available to provide flexibility for designers and applicants to meet performance-based and prescriptive security requirements and to apply methods or approaches to achieve the objective of high assurance that activities involving special nuclear materials are not inimical to the common defense and security and do not constitute an unreasonable risk to public health. On December 14, 2016, NEI submitted a white paper on a "Proposed Consequence-Based Physical Security Framework for Small Modular Reactors and Other New Technologies." This paper "... proposes an approach to security that considers the enhanced safety and security incorporated into these designs and provides a more effective and efficient means to protect the public health and safety." In the transmittal letter, NEI requests that "... the NRC establish regulatory positions on this approach and the associated policy and technical issues." NEI submitted a fee waiver request for NRCs review of this white paper.
Disposition: The NRC has approved NEI's fee waiver request and met with NEI on May 3, 2017, to discuss the review of their submittal.
Disposition: The NRC has approved NEI's fee waiver request and met with NEI on May 3, 2017, to discuss the review of their submittal.
Line 1,065: Line 1,442:
The staff discussed this white paper with NEI and other stakeholders on December 13, 2017.
The staff discussed this white paper with NEI and other stakeholders on December 13, 2017.
The staff will consider stakeholder feedback and plans to prepare a SECY paper in 2018 to address this issue.
The staff will consider stakeholder feedback and plans to prepare a SECY paper in 2018 to address this issue.
V. Functional             In SECY-93-0092, Issues Pertaining to the         Staff Draft Containment            Advanced Reactor (PRISM, MHGTR, and PIUS)           White Paper Performance            and Candu 3 Designs and their Relationship to       (11/27/17)
SECY-11-0184 (12/29/11)
Current Regulatory Requirements, the staff        SECY-93-092 Applicability: Non-LWRs  proposed to evaluate the acceptability of          dated 04/08/93 proposed designs using a standard based upon 106
V. Functional Containment Performance Applicability: Non-LWRs In SECY-93-0092, Issues Pertaining to the Advanced Reactor (PRISM, MHGTR, and PIUS) and Candu 3 Designs and their Relationship to Current Regulatory Requirements, the staff proposed to evaluate the acceptability of proposed designs using a standard based upon Staff Draft White Paper (11/27/17)
SECY-93-092 dated 04/08/93  


Issue Title/Applicability Status                                           References containment functional performance rather than   SRM-SECY                          to rely exclusively on prescriptive containment   092, dated design criteria. The staff also informed the     07/30/93 Commission that it intended to approach this by comparing containment performance with the       SECY-03-0047, accident evaluation criteria. In SRM-SECY     dated 03/28/03 0092, the Commission approved the staff's         SRM-SECY                          recommendation.                                   0047, dated 06/26/03 Subsequently, in SECY-03-0047, the staff         SECY-05-0006, recommended that the Commission approve the       dated 01/07/05 use of functional performance requirements to establish the acceptability of a containment or confinement structure (i.e., a non-pressure retaining building may be acceptable provided the performance requirements can be met) and the staff proposed that functional performance requirements be developed. In SRM-SECY                           0047, the Commission disapproved the staffs recommendation stating that there was insufficient information at the time for the Commission to prejudge the best options and make a decision on the viability of a confinement building. The Commission directed the staff to develop performance requirements and criteria working closely with industry experts (e.g.,
107 Issue Title/Applicability Status References containment functional performance rather than to rely exclusively on prescriptive containment design criteria. The staff also informed the Commission that it intended to approach this by comparing containment performance with the accident evaluation criteria. In SRM-SECY 0092, the Commission approved the staff's recommendation.
Subsequently, in SECY-03-0047, the staff recommended that the Commission approve the use of functional performance requirements to establish the acceptability of a containment or confinement structure (i.e., a non-pressure retaining building may be acceptable provided the performance requirements can be met) and the staff proposed that functional performance requirements be developed. In SRM-SECY 0047, the Commission disapproved the staffs recommendation stating that there was insufficient information at the time for the Commission to prejudge the best options and make a decision on the viability of a confinement building. The Commission directed the staff to develop performance requirements and criteria working closely with industry experts (e.g.,
designers, EPRI, etc.) and other stakeholders regarding options in this area, taking into account such features as core, fuel, and cooling systems design. The Commission also directed the staff to pursue the development of functional performance standards and then submit options and recommendations to the Commission.
designers, EPRI, etc.) and other stakeholders regarding options in this area, taking into account such features as core, fuel, and cooling systems design. The Commission also directed the staff to pursue the development of functional performance standards and then submit options and recommendations to the Commission.
In SECY-05-0006, the staff discussed many of the concepts developed in previous communications between the staff and Commission on the topic of functional containment performance and, as directed in SRM-SECY-03-0047, outlined the attributes for a functional containment. The topic of functional containment was also addressed as part of the next-generation nuclear plant (NGNP) project in the context of high-temperature gas-cooled reactors. More recently, in light of the broad range of non-light water designs under consideration, the staff has determined that it would be beneficial to seek Commission direction to support development and possible deployment of advanced reactor technologies.
In SECY-05-0006, the staff discussed many of the concepts developed in previous communications between the staff and Commission on the topic of functional containment performance and, as directed in SRM-SECY-03-0047, outlined the attributes for a functional containment. The topic of functional containment was also addressed as part of the next-generation nuclear plant (NGNP) project in the context of high-temperature gas-cooled reactors. More recently, in light of the broad range of non-light water designs under consideration, the staff has determined that it would be beneficial to seek Commission direction to support development and possible deployment of advanced reactor technologies.
107
SRM-SECY 092, dated 07/30/93 SECY-03-0047, dated 03/28/03 SRM-SECY 0047, dated 06/26/03 SECY-05-0006, dated 01/07/05


Issue Title/Applicability   Status                                               References The staff plans to engage the Commission to confirm whether the Commission direction in SRM-93-0092 should be applied more broadly to additional advanced reactor designs and to propose a risk-informed, performance-based approach to establishing performance criteria for structures, systems, and components and corresponding programs to limit the release of radioactive materials from advanced reactors.
108 Issue Title/Applicability Status References The staff plans to engage the Commission to confirm whether the Commission direction in SRM-93-0092 should be applied more broadly to additional advanced reactor designs and to propose a risk-informed, performance-based approach to establishing performance criteria for structures, systems, and components and corresponding programs to limit the release of radioactive materials from advanced reactors.
Disposition: The staff has engaged stakeholders on this topic at several public meetings. The staff prepared a draft white paper on functional containment performance to facilitate stakeholder interactions. The staff discussed this white paper with stakeholders on December 14, 2017, and February 1, 2018, and with the ACRS on February 22, 2018. The staff will consider ACRS and stakeholder feedback and plans to prepare a SECY paper in 2018 to address this issue.
Disposition: The staff has engaged stakeholders on this topic at several public meetings. The staff prepared a draft white paper on functional containment performance to facilitate stakeholder interactions. The staff discussed this white paper with stakeholders on December 14, 2017, and February 1, 2018, and with the ACRS on February 22, 2018. The staff will consider ACRS and stakeholder feedback and plans to prepare a SECY paper in 2018 to address this issue.
: 51. Please provide a list of any unresolved policy issues with regard to the licensing of advanced non-light water reactors. Please include an approximate date for when each issue was first raised, any actions taken or planned to resolve the issue, the milestone schedule, and the projected date for resolution.
: 51. Please provide a list of any unresolved policy issues with regard to the licensing of advanced non-light water reactors. Please include an approximate date for when each issue was first raised, any actions taken or planned to resolve the issue, the milestone schedule, and the projected date for resolution.
Line 1,079: Line 1,458:
: 52. Please describe the status of preparations to review non-light water reactor applications including a milestone schedule and completion dates.
: 52. Please describe the status of preparations to review non-light water reactor applications including a milestone schedule and completion dates.
The agency has developed a vision and strategy to assure NRC readiness to conduct its mission for these technologies effectively and efficiently as described in NRC Vision and Strategy: Safely Achieving Effective and Efficient Non-Light Water Reactor Mission Readiness, which was published in the Federal Register on July 21, 2016, for stakeholder input. The NRC updated this document (ADAMS Accession No. ML16356A670) to reflect stakeholder feedback and made it publicly available in December of 2016.
The agency has developed a vision and strategy to assure NRC readiness to conduct its mission for these technologies effectively and efficiently as described in NRC Vision and Strategy: Safely Achieving Effective and Efficient Non-Light Water Reactor Mission Readiness, which was published in the Federal Register on July 21, 2016, for stakeholder input. The NRC updated this document (ADAMS Accession No. ML16356A670) to reflect stakeholder feedback and made it publicly available in December of 2016.
The NRCs non- LWR vision and strategy has three strategic objectivesenhancing technical readiness, optimizing regulatory readiness, and optimizing communication. The NRC has developed implementation action plans (IAPs) to identify the specific activities the NRC will conduct in the near-term (0-5 years), mid-term (5-10 years), and long-term (beyond 10 years) timeframes to achieve non-LWR readiness. In the fall of 2016, the NRC released its draft near-term IAPs to obtain stakeholder feedback. The staff also developed draft mid- and long-term IAPs, which were released to the public in February of 2017. The staff updated its IAPs to reflect stakeholder feedback in July of 2017 (ADAMS Accession Nos. ML17165A069 and ML17164A173).
The NRCs non-LWR vision and strategy has three strategic objectivesenhancing technical readiness, optimizing regulatory readiness, and optimizing communication. The NRC has developed implementation action plans (IAPs) to identify the specific activities the NRC will conduct in the near-term (0-5 years), mid-term (5-10 years), and long-term (beyond 10 years) timeframes to achieve non-LWR readiness. In the fall of 2016, the NRC released its draft near-term IAPs to obtain stakeholder feedback. The staff also developed draft mid-and long-term IAPs, which were released to the public in February of 2017. The staff updated its IAPs to reflect stakeholder feedback in July of 2017 (ADAMS Accession Nos. ML17165A069 and ML17164A173).  
108


There are 6 individual strategies addressed in the near-term IAPs. These strategies, and the activities in support of each strategy, are discussed below.
109 There are 6 individual strategies addressed in the near-term IAPs. These strategies, and the activities in support of each strategy, are discussed below.
Strategy                           Activities in support of the strategy
Strategy Activities in support of the strategy
: 1) Acquire/develop sufficient
: 1) Acquire/develop sufficient knowledge, technical skills, and capacity to perform non-LWR regulatory activities NRC contracted with the Oak Ridge National Laboratory to develop a 12-module training course on Molten Salt Reactors (MSRs). The course provided background on various MSR concepts presently under development, including history of earlier MSR projects, descriptions of conceptual designs, and expected technical and regulatory challenges. About 90 NRC staff attended the training along with several DOE staff in three separate 2-day sessions in May, August, and November 2017.
* NRC contracted with the Oak Ridge National knowledge, technical                  Laboratory to develop a 12-module training course on skills, and capacity to                Molten Salt Reactors (MSRs). The course provided perform non-LWR                        background on various MSR concepts presently under regulatory activities                  development, including history of earlier MSR projects, descriptions of conceptual designs, and expected technical and regulatory challenges. About 90 NRC staff attended the training along with several DOE staff in three separate 2-day sessions in May, August, and November 2017.
NRC developed models of the competencies required for reviewing advanced reactor designs. Project managers and technical reviewers in NRO are currently in the process of assessing their skills against the models. Supervisors will also be able to complete an independent assessment of their employees skills. Based on assessment results, any skill gaps that may exist can be identified and the system will help the employee identify developmental activities and create an individual development plan to close those gaps.
* NRC developed models of the competencies required for reviewing advanced reactor designs. Project managers and technical reviewers in NRO are currently in the process of assessing their skills against the models. Supervisors will also be able to complete an independent assessment of their employees skills. Based on assessment results, any skill gaps that may exist can be identified and the system will help the employee identify developmental activities and create an individual development plan to close those gaps.
: 2) Acquire/develop sufficient computer codes and tools to perform non-LWR regulatory reviews Staff attended DOE and NRC-sponsored workshops and technology working groups, sought additional information through pre-application interactions, and focused its training efforts to better understand the reactor systems under development. In the near-term, these efforts are focused on the following areas:
: 2) Acquire/develop sufficient
* Staff attended DOE and NRC-sponsored workshops computer codes and tools              and technology working groups, sought additional to perform non-LWR                    information through pre-application interactions, and regulatory reviews                    focused its training efforts to better understand the reactor systems under development. In the near-term, these efforts are focused on the following areas:
Reactor Kinetics and Criticality, Fuel Performance, Thermal-Fluid Phenomena, Severe Accident Phenomena, Offsite Consequence Analysis, Materials and Component Integrity, and PRA.
Reactor Kinetics and Criticality, Fuel Performance, Thermal-Fluid Phenomena, Severe Accident Phenomena, Offsite Consequence Analysis, Materials and Component Integrity, and PRA.
* An initial screening of analysis codes for design-basis and beyond-design-basis event simulation was completed, and a suite of tools for further examination and consideration has been identified. The code suite comprises both NRC-developed and DOE-developed codes. Future efforts will evaluate codes in the code suite against analysis requirements.
An initial screening of analysis codes for design-basis and beyond-design-basis event simulation was completed, and a suite of tools for further examination and consideration has been identified. The code suite comprises both NRC-developed and DOE-developed codes. Future efforts will evaluate codes in the code suite against analysis requirements.
* A Phenomena Identification and Ranking Table (PIRT) exercise was conducted for molten salt reactors. The PIRT focused attention on fuel salt MSRs due to their novel and unique feature of fuel being part of the 109
A Phenomena Identification and Ranking Table (PIRT) exercise was conducted for molten salt reactors. The PIRT focused attention on fuel salt MSRs due to their novel and unique feature of fuel being part of the  


Strategy                     Activities in support of the strategy coolant. The PIRT is considered preliminary in that design specifics are not available, but it is useful in that several phenomena requiring simulation could be identified based on existing information.
110 Strategy Activities in support of the strategy coolant. The PIRT is considered preliminary in that design specifics are not available, but it is useful in that several phenomena requiring simulation could be identified based on existing information.
* Staff completed a PRA report that summarizes previous work and issues for non-LWRs and identifies several policy decisions that may need to be made for non-LWRs.
Staff completed a PRA report that summarizes previous work and issues for non-LWRs and identifies several policy decisions that may need to be made for non-LWRs.
: 3) Develop guidance for a
: 3) Develop guidance for a flexible non-LWR regulatory review process within the bounds of existing regulations, including the use of conceptual design reviews and staged-review processes In October 2017, the staff issued a preliminary draft of A Regulatory Review Roadmap for Non-Light Water Reactors (ADAMS Accession No. ML17279B177),
* In October 2017, the staff issued a preliminary draft of flexible non-LWR                  A Regulatory Review Roadmap for Non-Light Water regulatory review process        Reactors (ADAMS Accession No. ML17279B177),
and discussed it with stakeholders on November 2, 2017. The NRC issued the final regulatory review roadmap on December 26, 2017.
within the bounds of              and discussed it with stakeholders on November 2, existing regulations,            2017. The NRC issued the final regulatory review including the use of              roadmap on December 26, 2017.
In June 2017, the NRC issued a preliminary draft document, "Nuclear Power Reactor Testing Needs and Prototype Plants for Advanced Reactor Designs,"
conceptual design reviews and staged-
* In June 2017, the NRC issued a preliminary draft review processes                  document, "Nuclear Power Reactor Testing Needs and Prototype Plants for Advanced Reactor Designs,"
to solicit stakeholder feedback (ADAMS Accession No. ML17025A353). This document describes the relevant regulations governing the testing requirements for advanced reactors, describes the process for determining testing needs to meet the NRC's regulatory requirements, clarifies when a prototype plant might be needed and how it might differ from the proposed standard plant design, and describes licensing strategies and options that include the use of a prototype plant to meet the NRC's testing requirements. The NRC addressed stakeholder feedback and issued the final prototype document as part of the Regulatory Review Roadmap on December 26, 2017.
to solicit stakeholder feedback (ADAMS Accession No. ML17025A353). This document describes the relevant regulations governing the testing requirements for advanced reactors, describes the process for determining testing needs to meet the NRC's regulatory requirements, clarifies when a prototype plant might be needed and how it might differ from the proposed standard plant design, and describes licensing strategies and options that include the use of a prototype plant to meet the NRC's testing requirements. The NRC addressed stakeholder feedback and issued the final prototype document as part of the Regulatory Review Roadmap on December 26, 2017.
* On February 3, 2017, the NRC issued draft regulatory guide DG-1330, "Guidance for Developing Principal Design Criteria for Non-Light Water Reactors" for formal public comment. The staff briefed the ACRS subcommittee on the draft final regulatory guide on February 7, 2018, and will brief the ACRS full Committee in March 2018. The NRC then plans to issue the final regulatory guide in the spring of 2018.
On February 3, 2017, the NRC issued draft regulatory guide DG-1330, "Guidance for Developing Principal Design Criteria for Non-Light Water Reactors" for formal public comment. The staff briefed the ACRS subcommittee on the draft final regulatory guide on February 7, 2018, and will brief the ACRS full Committee in March 2018. The NRC then plans to issue the final regulatory guide in the spring of 2018.
* The NRC is supporting activities related to the Licensing Modernization Project (LMP) being led by Southern Company, coordinated by the NEI, and cost-shared by DOE. The LMP's objective is to develop technology-inclusive, risk-informed, and performance based regulatory guidance for licensing non-LWRs for 110
The NRC is supporting activities related to the Licensing Modernization Project (LMP) being led by Southern Company, coordinated by the NEI, and cost-shared by DOE. The LMP's objective is to develop technology-inclusive, risk-informed, and performance based regulatory guidance for licensing non-LWRs for  


Strategy                     Activities in support of the strategy the NRCs consideration and possible endorsement.
111 Strategy Activities in support of the strategy the NRCs consideration and possible endorsement.
The NRC has reviewed four LMP white papers and provided feedback to industry stakeholders:
The NRC has reviewed four LMP white papers and provided feedback to industry stakeholders:
Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors -
Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors -
Selection of Licensing Basis Events (ADAMS Accession No. ML17104A254), Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors - Probabilistic Risk Assessment Approach (ADAMS Accession No.
Selection of Licensing Basis Events (ADAMS Accession No. ML17104A254), Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors - Probabilistic Risk Assessment Approach (ADAMS Accession No. ML17158B543), Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors: Safety Classification and Performance Criteria for Structures, Systems, and Components (ADAMS Accession No. ML17290A463), and Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors: Risk-Informed and Performance-Based Evaluation of Defense-in-Depth Adequacy (ADAMS Accession No. ML17354B174). The staff is expecting NEI to submit a consolidated guidance document for NRC review and possible endorsement.
ML17158B543), Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors: Safety Classification and Performance Criteria for Structures, Systems, and Components (ADAMS Accession No.
: 4) Facilitate industry codes and standards needed to support the non-LWR life cycle (including fuels and materials)
ML17290A463), and Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors: Risk-Informed and Performance-Based Evaluation of Defense-in-Depth Adequacy (ADAMS Accession No. ML17354B174). The staff is expecting NEI to submit a consolidated guidance document for NRC review and possible endorsement.
The NRC staff is actively participating in subgroups and working groups associated with the development of ASME Boiler and Pressure Vessel (B&PV) Code, Section III, Division 5. NRC staff is also participating in the Task Group on ASME/NRC Liaison for Division 5 that seeks NRC, DOE, and industry input in identifying gaps in ASME B&PV Code Section III, Division 5, which need to be resolved prior to considering endorsement in 10 CFR 50.55a. The staff discussed this topic during a public meeting on December 14, 2017. ASME plans to send a letter to the staff confirming that advanced reactor developers support NRC endorsement of the 2017 edition of ASME Section III, Division 5, rather than waiting for a later edition. ASME also plans to submit a technical basis document for the 2017 edition.
: 4) Facilitate industry codes
The staff is actively participating on several American Nuclear Society (ANS) standards working groups and consensus committees related to non-LWR safety standards and the joint ASME/ANS non-LWR PRA standard.
* The NRC staff is actively participating in subgroups and standards needed to            and working groups associated with the development support the non-LWR life          of ASME Boiler and Pressure Vessel (B&PV) Code, cycle (including fuels and        Section III, Division 5. NRC staff is also participating materials)                        in the Task Group on ASME/NRC Liaison for Division 5 that seeks NRC, DOE, and industry input in identifying gaps in ASME B&PV Code Section III, Division 5, which need to be resolved prior to considering endorsement in 10 CFR 50.55a. The staff discussed this topic during a public meeting on December 14, 2017. ASME plans to send a letter to the staff confirming that advanced reactor developers support NRC endorsement of the 2017 edition of ASME Section III, Division 5, rather than waiting for a later edition. ASME also plans to submit a technical basis document for the 2017 edition.
On September 26, 2017, the NRC held the second annual NRC Standards Forum, which was attended by representatives from many standards development  
* The staff is actively participating on several American Nuclear Society (ANS) standards working groups and consensus committees related to non-LWR safety standards and the joint ASME/ANS non-LWR PRA standard.
* On September 26, 2017, the NRC held the second annual NRC Standards Forum, which was attended by representatives from many standards development 111


Strategy                     Activities in support of the strategy organizations, representatives from industry (NEI, the Electric Power Research Institute, and Technology Working Groups for non-LWRs), and representatives from DOE and DOE national labs. A portion of this years standards forum was devoted to non-LWRs with the intent of working with stakeholders to identify new codes and standards needed for non-LWR development and to facilitate the codes and standards development and eventual endorsement by the NRC, as appropriate. A follow-up workshop on advanced reactor standards development is planned for May 2018.
112 Strategy Activities in support of the strategy organizations, representatives from industry (NEI, the Electric Power Research Institute, and Technology Working Groups for non-LWRs), and representatives from DOE and DOE national labs. A portion of this years standards forum was devoted to non-LWRs with the intent of working with stakeholders to identify new codes and standards needed for non-LWR development and to facilitate the codes and standards development and eventual endorsement by the NRC, as appropriate. A follow-up workshop on advanced reactor standards development is planned for May 2018.
: 5) Identify and resolve
: 5) Identify and resolve technology-inclusive (not specific to a particular non-LWR design or category) policy issues that impact regulatory reviews, siting, permitting, and/or licensing of non-LWR nuclear power plants The NRCs key activities related to the resolution of policy issues in support of near-term IAP strategy 5 are discussed in response to questions 50 and 51 above.
* The NRCs key activities related to the resolution of technology-inclusive (not         policy issues in support of near-term IAP strategy 5 specific to a particular           are discussed in response to questions 50 and 51 non-LWR design or                 above.
: 6) Develop and implement a structured, integrated strategy to communicate with internal and external stakeholders having interests in non-LWR technologies The NRC is conducting public meetings with stakeholders every 4 to 6 weeks. The NRC uses these stakeholder meetings to solicit input on policy and process issues related to the possible licensing and regulation of non-LWR technologies.
category) policy issues that impact regulatory reviews, siting, permitting, and/or licensing of non-LWR nuclear power plants
The NRC and DOE hosted a series of three Advanced Non-LWR Workshops. The most recent workshop was held on April 25 and 26, 2017. This series of workshops focused on opening a dialogue between key stakeholders to discuss challenges in the commercialization of non-LWR technologies and to discuss possible solutions.
: 6) Develop and implement a
On November 10, 2016, the NRC and DOE signed a MOU (ADAMS Accession No. ML16215A382) on the Gateway for Accelerated Innovation in Nuclear (GAIN)
* The NRC is conducting public meetings with structured, integrated            stakeholders every 4 to 6 weeks. The NRC uses strategy to communicate            these stakeholder meetings to solicit input on policy with internal and external        and process issues related to the possible licensing stakeholders having                and regulation of non-LWR technologies.
Initiative. GAIN is an initiative that is intended to provide the nuclear energy community with increased access to the technical, regulatory, and financial support necessary to move new or advanced nuclear reactor designs toward commercialization while ensuring the continued safe, reliable, and economic operation of the existing nuclear fleet. As described in the MOU, the NRC is responsible for providing DOE and the nuclear energy community with accurate,  
interests in non-LWR technologies
* The NRC and DOE hosted a series of three Advanced Non-LWR Workshops. The most recent workshop was held on April 25 and 26, 2017. This series of workshops focused on opening a dialogue between key stakeholders to discuss challenges in the commercialization of non-LWR technologies and to discuss possible solutions.
* On November 10, 2016, the NRC and DOE signed a MOU (ADAMS Accession No. ML16215A382) on the Gateway for Accelerated Innovation in Nuclear (GAIN)
Initiative. GAIN is an initiative that is intended to provide the nuclear energy community with increased access to the technical, regulatory, and financial support necessary to move new or advanced nuclear reactor designs toward commercialization while ensuring the continued safe, reliable, and economic operation of the existing nuclear fleet. As described in the MOU, the NRC is responsible for providing DOE and the nuclear energy community with accurate, 112


Strategy Activities in support of the strategy current information on the NRCs regulations and licensing processes.
113 Strategy Activities in support of the strategy current information on the NRCs regulations and licensing processes.
* The NRC will continue to share information with various international groups, including the Organization for Economic Co-operation and Developments Nuclear Energy Agency (NEA), the International Atomic Energy Agency, the Generation IV International Forum, and the NRCs international regulatory counterparts. The NRC chairs NEAs ad hoc group for international regulators of non-LWRs known as the Group on the Safety of Advanced Reactors. The purpose of the group is to bring interested regulators together to discuss common interests, practices, and problems, and address both the regulatory interests and research needs.
The NRC will continue to share information with various international groups, including the Organization for Economic Co-operation and Developments Nuclear Energy Agency (NEA), the International Atomic Energy Agency, the Generation IV International Forum, and the NRCs international regulatory counterparts. The NRC chairs NEAs ad hoc group for international regulators of non-LWRs known as the Group on the Safety of Advanced Reactors. The purpose of the group is to bring interested regulators together to discuss common interests, practices, and problems, and address both the regulatory interests and research needs.}}
113}}

Latest revision as of 09:30, 6 January 2025

Status Report on the Licensing Activities and Regulatory Duties of the U.S. Nuclear Regulatory Commission (for the Reporting Period Through January 2018) (Enclosure)
ML18053A115
Person / Time
Issue date: 03/07/2018
From:
NRC/Chairman
To:
US SEN (Senate)
R. Rihm, EDO
Shared Package
ML18030A693 List:
References
CORR-18-0018, SRM-LTR-17-0416
Download: ML18053A115 (113)


Text

Enclosure STATUS REPORT ON THE LICENSING ACTIVITIES AND REGULATORY DUTIES OF THE U.S. NUCLEAR REGULATORY COMMISSION For the Reporting Period through January 2018

i Table of Contents RESOURCES

1. Status of Project Aim and additional activities 1
2. Incorporation of five-year workload planning into policies and procedures 2
3. Staffing 3
4. Actions taken or planned to reduce corporate support costs, including efforts to reduce office space 16
5. Status of efforts to provide greater transparency, timeliness, and itemization in invoices to applicants and licensees, including any progress toward electronic invoicing and payment 18
6. Research activities initiated during the reporting period 19 URANIUM RECOVERY
7. Information regarding major uranium recovery licensing application reviews 20
8. Status of major uranium recovery licensing actions 21
9. Status of minor uranium recovery licensing actions 24
10. Status of Wyoming Agreement State application 25
11. Specific actions planned to improve the efficiency of reviews conducted for compliance with the National Historic Preservation Act 26
12. Progress of the pilot project on flat fees for uranium recovery licensees 27 LICENSING
13. Information regarding license amendment reviews for operating reactors, new reactors, and uranium recovery licensees 29
14. Information regarding decommissioning transition reviews 38
15. List of Technical Specifications Task Force travelers under review 38
16. Actions planned and/or taken to ensure that the Technical Specifications Task Force traveler process achieves the regulatory efficiencies that were initially projected 39
17. Information regarding license renewal review applications 39
18. Status of ongoing license renewal reviews 44

ii

19. Status of NRCs readiness to review applications for subsequent license renewal 46
20. Status of subsequent license renewal reviews 47
21. Information regarding power uprate application reviews 47
22. Status of power uprate application reviews 47
23. Information regarding requests for additional information (RAIs) issued by various offices/programs 47
24. Status of specific actions taken or planned to ensure greater discipline, management oversight, and transparency in the RAI process 54
25. Actions taken to enhance the integration of risk information across the agencys activities to improve the technical basis for regulatory activities, to increase efficiency, and to improve effectiveness 57
26. Status of power reactor transition from analog to digital instrumentation 61
27. Actions taken and planned to prepare to review industry requests to use accident tolerant fuel in existing reactors 63
28. Actions taken and planned to improve the quality of cost benefit analyses conducted in association with new requirements, backfit analyses, or rulemaking 64
29. Status of the revised guidance to clarify the use of qualitative factors 65
30. List of all final generic regulatory actions issued in the last three years 67
31. List and brief description of all facility-specific backfits issued during the reporting period 75
32. Twelve-month and three-year rolling averages for CRGR formal and informal reviews 76
33. Status of the application of the backfit rule in licensing and inspection programs across the agency 76
34. Actions taken and planned to address recommendations made by the CRGR in its report U.S. Nuclear Regulatory Commissions Implementation of Backfitting and Issue Finality Requirements 78 REACTOR INSPECTION
35. Reactor Oversight Process findings for year-to-date and three-year rolling metrics 80

iii

36. Percentage of Final Significance Determinations made within 90 days for all potentially greater-than-green findings, monthly for one-year rolling metrics and annually for the past 10 years 81
37. Instances where Inspection Manual Chapter 609, Appendix M, Significance Determination Process Using Qualitative Criteria, has been applied in the Reactor Oversight Process Significance Determination Process 81
38. Status of potential changes to the Reactor Oversight Process and identification of any changes that may require Commission approval prior to implementation 82
39. Progress toward utilizing an industry consensus document as a means of accomplishing predictability and consistency in operability determinations 82
40. Information regarding Design Basis Assurance Inspections completed in the last three years 82
41. Status of the holistic review of engineering inspection procedures and any actions taken and/or planned because of the review 86 NEW REACTORS
42. Funds budgeted, resources spent, and total Part 170 fees billed each year for the past ten years for the Office of New Reactors 87
43. Information regarding each design certification, combined license, and early site permit application reviewed since 2007 87
44. Summary of the status of ongoing design certification, combined license, and early site permit application reviews 94
45. Information on ITAAC reviews for reactors under construction 97
46. License amendments for reactors under construction 100
47. Budgeted resources and actual expenditures each month for the past 24 months for reactors under construction 100
48. Summary of the status of licensing and inspection for Vogtle Units 3 and 4 101
49. Actions taken in the past three years or planned to improve the efficiency of new plant reviews 102
50. Unresolved policy issues regarding the licensing of small modular light-water reactors 103
51. Unresolved policy issues regarding the licensing of advanced non-light water reactors 108
52. Status of preparations to review non-light water reactor applications 108

1 RESOURCES

1. Will Project Aim 2020 conclude in early 2018, or will it continue pursuing additional improvements? If Project Aim will continue, please describe any new or additional actions taken or planned, including milestones for completion of such actions.

In June 2015, the Commission approved 19 discrete Project Aim tasks intended to improve NRCs efficiency and agility, as well as right size the agencys workforce to its workload, while retaining employees with the skills necessary to accomplish its safety and security mission and streamline processes. In 2017, the NRC completed the major deliverables for each of the 19 Project Aim tasks. The deliverables for some of the tasks entailed full implementation of the task, while others included detailed proposals and implementation plans for activities to be implemented in the future. The NRC staff is completing follow-on actions to implement recommendations, which will continue to affect and shape NRCs line organizations going forward. The NRC staff continues to provide a quarterly Project Aim status report to the Commission. A copy will be transmitted with this report each quarter.

The NRC Chairmans June 29, 2017, and October 25, 2017, letters to Senators Cochran and Leahy, on the progress of certain licensing actions and right-sizing commitments indicated that one of the 19 completed tasks implemented a re-baselining effort, which identified 150 activities to be shed, deferred, or performed with fewer resources.

The NRC continues to institutionalize the actions related to Project Aim and pursue additional activities. The table below describes two such activities that continue the objectives of Project Aim and demonstrate the NRCs continued commitment to effectiveness and efficiency. These and other Project Aim initiatives are now integrated with the NRC agency reform plan, developed in response to OMB requirements.

Initiative Milestones Notes Develop an agency-level Idea Greenhouse program and Innovation Forum to capture and refine staff recommendations to improve NRC operations Project initiation: April 20, 2017 January 26, 2018: Develop Draft Communication Strategy February 2, 2018: Launch SharePoint site for idea submittals for evaluation and tracking the status of the ideas February 23, 2018: Implement Communications Strategy on Agency-wide Implementation of Innovation Programs March 30, 2018: Operation of Office/Region-Level Innovation Program Completed Completed

2 Initiative Milestones Notes March 30, 2018: Finalize Processes for Agency Innovation Forum to evaluate ideas and present recommendations to Senior Leadership Implement an enhanced strategic workforce planning (SWP) process that will improve workforce management by focusing on strategic human capital management and longer-term planning Project initiation 07/29/2017 Train supervisors in SWP concepts and process 10/11/17 Pilot offices deliver workload forecast (execution year+1 and execution year+5) 12/12/17 Deliverable: Workforce Demand Analysis 01/31/18 Deliverable: Workforce Supply Analysis 03/09/18 Deliverable: Prioritized list of gaps and surpluses 05/07/18 Deliverable: Strategies to address gaps and surpluses 06/22/18 Pilot Report to the Executive Director for Operations (EDO) 07/13/18 Piloting the process with three offices to test a variety of guidance, templates, and tools, and to refine the process before launching agencywide.

Completed Completed Completed Final report will include a determination of strengths, challenges, and scalability of the process.

2. Consistent with the workload forecast done under Project Aim 2020, to what extent has the NRC incorporated five-year workload planning into its policies and procedures, e.g.,

strategic planning and budget formulation? Please describe the actions taken or planned.

On July 5, 2017, the NRCs EDO initiated a three-office pilot of an enhanced SWP process that better integrates workload projection, skills identification, human capital management, individual development, and workforce management activities (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17178A284). The pilot implements the process described in an April 19, 2017, memo, Proposed Enhancements to NRCS Strategic Workforce Planning (ADAMS Accession No. ML17109A319). As currently envisioned, the enhanced SWP has an annual cycle that ensures the insights from both one-year and five-year workload forecasts are considered in NRC strategic planning, human capital management, and

3 budget formulation activities. The actions taken and planned for the SWP pilot are outlined in the table in the response to Question 1, above. Depending on the results of the pilot, the agency expects to adopt the enhanced strategic workforce planning process agencywide in 2018, which will fully incorporate five-year workload planning into other established processes.

3. Please provide the total number of staff and corporate support staff (FTE), budgeted vs actual, for the agency and in each of the following offices: Nuclear Reactor Regulation, New Reactors, Nuclear Material Safety and Safeguards, Nuclear Security and Incident Response, Nuclear Regulatory Research, Uranium Recovery, Decommissioning, and each regional office. Please provide this information for the current month, each of the previous eleven months, and projections for each of the twelve months going forward. Please do not divide by twelve.

U.S. Nuclear Regulatory Commission Agency Level FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 251.5 1270.8 02/19/2017 - 03/18/2017 251.0 1521.8 03/19/2017 - 04/15/2017 250.3 1772.1 04/16/2017 - 05/13/2017 247.9 2020.0 05/14/2017 - 06/10/2017 245.6 2265.6 06/11/2017 - 07/08/2017 245.1 2510.7 07/09/2017 - 08/05/2017 244.2 2754.9 08/06/2017 - 09/02/2017 243.2 2998.1 09/03/2017 - 09/30/2017 242.8 3240.9 3405 FY 2017 10/01/2017 - 10/28/2017 241.3 241.3 10/29/2017 - 11/25/2017 240.8 482.1 11/26/2017 - 12/23/2017 240.4 722.5 12/24/2017 - 01/20/2018 238.2 960.7 01/21/2018 - 02/17/2018 237.2 1197.9 02/18/2018 - 03/17/2018 236.8 1434.7 03/18/2018 - 04/14/2018 236.8 1671.5 04/15/2018 - 05/12/2018 236.5 1908.0 05/13/2018 - 06/09/2018 236.4 2144.4 06/10/2018 - 07/07/2018 236.5 2380.9 07/08/2018 - 08/04/2018 236.4 2617.3 08/05/2018 - 09/01/2018 236.4 2853.7 09/02/2018 - 09/29/2018 236.5 3090.2 3293 FY 2018 09/30/2018 - 10/27/2018 236.7 236.7

4 10/28/2018 - 11/24/2018 236.7 473.4 11/25/2018 - 12/22/2018 236.8 710.2 12/23/2018 - 01/19/2019 236.8 947.0 3255 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes staff in the Office of the Inspector General.

5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.

6 FY 2018 and FY 2019 FTE include FTE associated with the High-Level Waste Program (HLW) activities.

The Office Level tables do not include the annual budgeted FTE for the HLW program; FTE will be allocated at the Office Level in future reports, if funds are enacted.

U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 37.8 191.0 02/19/2017 - 03/18/2017 37.6 228.6 03/19/2017 - 04/15/2017 37.5 266.1 04/16/2017 - 05/13/2017 37.2 303.3 05/14/2017 - 06/10/2017 36.6 339.9 06/11/2017 - 07/08/2017 36.5 376.4 07/09/2017 - 08/05/2017 36.4 412.8 08/06/2017 - 09/02/2017 36.4 449.2 09/03/2017 - 09/30/2017 36.1 485.3 488 FY 2017 10/01/2017 - 10/28/2017 35.9 35.9 10/29/2017 - 11/25/2017 34.7 70.6 11/26/2017 - 12/23/2017 34.5 105.1 12/24/2017 - 01/20/2018 34.5 139.6 01/21/2018 - 02/17/2018 34.5 174.1 02/18/2018 - 03/17/2018 34.6 208.7 03/18/2018 - 04/14/2018 34.6 243.3 04/15/2018 - 05/12/2018 34.5 277.8 05/13/2018 - 06/09/2018 34.6 312.4 06/10/2018 - 07/07/2018 34.6 347.0 07/08/2018 - 08/04/2018 34.6 381.6 08/05/2018 - 09/01/2018 34.6 416.2 09/02/2018 - 09/29/2018 34.6 450.8 461 FY 2018 09/30/2018 - 10/27/2018 34.6 34.6

5 10/28/2018 - 11/24/2018 34.6 69.2 11/25/2018 - 12/22/2018 34.6 103.8 12/23/2018 - 01/19/2019 34.6 138.4 451 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes all staff in NRR.

5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.

U.S. Nuclear Regulatory Commission Office of New Reactors FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 22.7 116.9 02/19/2017 - 03/18/2017 22.5 139.4 03/19/2017 - 04/15/2017 22.7 162.1 04/16/2017 - 05/13/2017 22.4 184.5 05/14/2017 - 06/10/2017 22.3 206.8 06/11/2017 - 07/08/2017 22.4 229.2 07/09/2017 - 08/05/2017 22.2 251.4 08/06/2017 - 09/02/2017 22.1 273.5 09/03/2017 - 09/30/2017 22.0 295.5 313 FY 2017 10/01/2017 - 10/28/2017 22.0 22.0 10/29/2017 - 11/25/2017 21.9 43.9 11/26/2017 - 12/23/2017 21.6 65.5 12/24/2017 - 01/20/2018 20.8 86.3 01/21/2018 - 02/17/2018 20.8 107.1 02/18/2018 - 03/17/2018 20.6 127.7 03/18/2018 - 04/14/2018 20.6 148.3 04/15/2018 - 05/12/2018 20.5 168.8 05/13/2018 - 06/09/2018 20.5 189.3 06/10/2018 - 07/07/2018 20.5 209.8 07/08/2018 - 08/04/2018 20.5 230.3 08/05/2018 - 09/01/2018 20.5 250.8 09/02/2018 - 09/29/2018 20.5 271.3 303 FY 2018 09/30/2018 - 10/27/2018 20.6 20.6 10/28/2018 - 11/24/2018 20.6 41.2 11/25/2018 - 12/22/2018 20.6 61.8 12/23/2018 - 01/19/2019 20.6 82.4 263 FY 2019

6 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes all staff in NRO.

5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.

U.S. Nuclear Regulatory Commission Office of Nuclear Materials Safety and Safeguards FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 22.2 112.5 02/19/2017 - 03/18/2017 22.2 134.7 03/19/2017 - 04/15/2017 22.1 156.8 04/16/2017 - 05/13/2017 21.9 178.7 05/14/2017 - 06/10/2017 21.7 200.4 06/11/2017 - 07/08/2017 22.0 222.4 07/09/2017 - 08/05/2017 21.9 244.3 08/06/2017 - 09/02/2017 21.9 266.2 09/03/2017 - 09/30/2017 21.9 288.1 297 FY 2017 10/01/2017 - 10/28/2017 21.5 21.5 10/29/2017 - 11/25/2017 23.1 44.6 11/26/2017 - 12/23/2017 23.2 67.8 12/24/2017 - 01/20/2018 23.3 91.1 01/21/2018 - 02/17/2018 23.4 114.5 02/18/2018 - 03/17/2018 23.4 137.9 03/18/2018 - 04/14/2018 23.4 161.3 04/15/2018 - 05/12/2018 23.4 184.7 05/13/2018 - 06/09/2018 23.4 208.1 06/10/2018 - 07/07/2018 23.4 231.5 07/08/2018 - 08/04/2018 23.4 254.9 08/05/2018 - 09/01/2018 23.4 278.3 09/02/2018 - 09/29/2018 23.4 301.7 295 FY 2018 09/30/2018 - 10/27/2018 23.4 23.4 10/28/2018 - 11/24/2018 23.4 46.8 11/25/2018 - 12/22/2018 23.4 70.2 12/23/2018 - 01/19/2019 23.4 93.6 292 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

7 3

Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 5

Provides all staff in NMSS, including FTE for Uranium Recovery and Reactor Decommissioning.

Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.

U.S. Nuclear Regulatory Commission Office of Nuclear Regulatory Research FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 15.9 80.6 02/19/2017 - 03/18/2017 15.8 96.4 03/19/2017 - 04/15/2017 15.6 112.0 04/16/2017 - 05/13/2017 15.4 127.4 05/14/2017 - 06/10/2017 15.3 142.7 06/11/2017 - 07/08/2017 15.3 158.0 07/09/2017 - 08/05/2017 15.3 173.3 08/06/2017 - 09/02/2017 15.3 188.6 09/03/2017 - 09/30/2017 15.1 203.7 197 FY 2017 10/01/2017 - 10/28/2017 15.0 15.0 10/29/2017 - 11/25/2017 14.9 29.9 11/26/2017 - 12/23/2017 15.1 45.0 12/24/2017 - 01/20/2018 15.3 60.3 01/21/2018 - 02/17/2018 15.2 75.5 02/18/2018 - 03/17/2018 15.2 90.7 03/18/2018 - 04/14/2018 15.3 106.0 04/15/2018 - 05/12/2018 15.4 121.4 05/13/2018 - 06/09/2018 15.4 136.8 06/10/2018 - 07/07/2018 15.4 152.2 07/08/2018 - 08/04/2018 15.4 167.6 08/05/2018 - 09/01/2018 15.4 183.0 09/02/2018 - 09/29/2018 15.4 198.4 197 FY 2018 09/30/2018 - 10/27/2018 15.4 15.4 10/28/2018 - 11/24/2018 15.4 30.8 11/25/2018 - 12/22/2018 15.4 46.2 12/23/2018 - 01/19/2019 15.4 61.6 208 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes all staff in RES.

8 5

Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.

U.S. Nuclear Regulatory Commission Office of Nuclear Security and Incident Response FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 13.5 68.5 02/19/2017 - 03/18/2017 13.5 82.0 03/19/2017 - 04/15/2017 13.6 95.6 04/16/2017 - 05/13/2017 13.4 109.0 05/14/2017 - 06/10/2017 13.3 122.3 06/11/2017 - 07/08/2017 13.0 135.3 07/09/2017 - 08/05/2017 12.9 148.2 08/06/2017 - 09/02/2017 12.9 161.1 09/03/2017 - 09/30/2017 12.9 174.0 182 FY 2017 10/01/2017 - 10/28/2017 13.0 13.0 10/29/2017 - 11/25/2017 13.1 26.1 11/26/2017 - 12/23/2017 13.2 39.3 12/24/2017 - 01/20/2018 13.1 52.4 01/21/2018 - 02/17/2018 13.0 65.4 02/18/2018 - 03/17/2018 13.0 78.4 03/18/2018 - 04/14/2018 13.1 91.5 04/15/2018 - 05/12/2018 13.1 104.6 05/13/2018 - 06/09/2018 13.1 117.7 06/10/2018 - 07/07/2018 13.2 130.9 07/08/2018 - 08/04/2018 13.2 144.1 08/05/2018 - 09/01/2018 13.2 157.3 09/02/2018 - 09/29/2018 13.2 170.5 176 FY 2018 09/30/2018 - 10/27/2018 13.2 13.2 10/28/2018 - 11/24/2018 13.2 26.4 11/25/2018 - 12/22/2018 13.2 39.6 12/23/2018 - 01/19/2019 13.2 52.8 168 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 5

Includes all staff in NSIR.

Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.

9 U.S. Nuclear Regulatory Commission Uranium Recovery FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 1.7 8.5 02/19/2017 - 03/18/2017 1.7 10.2 03/19/2017 - 04/15/2017 1.7 11.9 04/16/2017 - 05/13/2017 1.7 13.6 05/14/2017 - 06/10/2017 1.7 15.3 06/11/2017 - 07/08/2017 1.7 17.0 07/09/2017 - 08/05/2017 1.7 18.7 08/06/2017 - 09/02/2017 1.7 20.4 09/03/2017 - 09/30/2017 1.6 22.0 31 FY 2017 10/01/2017 - 10/28/2017 1.6 1.6 10/29/2017 - 11/25/2017 1.6 3.2 11/26/2017 - 12/23/2017 1.6 4.8 12/24/2017 - 01/20/2018 1.5 6.3 01/21/2018 - 02/17/2018 1.5 7.8 02/18/2018 - 03/17/2018 1.5 9.3 03/18/2018 - 04/14/2018 1.5 10.8 04/15/2018 - 05/12/2018 1.5 12.3 05/13/2018 - 06/09/2018 1.5 13.8 06/10/2018 - 07/07/2018 1.5 15.3 07/08/2018 - 08/04/2018 1.5 16.8 08/05/2018 - 09/01/2018 1.5 18.3 09/02/2018 - 09/29/2018 1.5 19.8 30 FY 2018 09/30/2018 - 10/27/2018 1.5 1.5 10/28/2018 - 11/24/2018 1.5 3.0 11/25/2018 - 12/22/2018 1.5 4.5 12/23/2018 - 01/19/2019 1.5 6.0 15 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes all staff in the Uranium Recovery Branch of the Office of Nuclear Material Safety and Safeguards (NMSS), and relevant staff in the following:

Environmental Review Branch, NMSS; Division of Materials Safety, State, Tribal, and Rulemaking Programs, NMSS; Fuel Cycle and Decommissioning Branch, Region IV; Office of General Counsel (OGC); and Atomic Safety Licensing Board Panel (ASLB).

10 U.S. Nuclear Regulatory Commission Decommissioning FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 3.3 16.6 02/19/2017 - 03/18/2017 3.3 19.9 03/19/2017 - 04/15/2017 3.3 23.2 04/16/2017 - 05/13/2017 3.3 26.5 05/14/2017 - 06/10/2017 3.4 29.9 06/11/2017 - 07/08/2017 3.4 33.3 07/09/2017 - 08/05/2017 3.5 36.8 08/06/2017 - 09/02/2017 3.5 40.3 09/03/2017 - 09/30/2017 3.5 43.8 37 FY 2017 10/01/2017 - 10/28/2017 3.5 3.5 10/29/2017 - 11/25/2017 3.5 7.0 11/26/2017 - 12/23/2017 3.5 10.5 12/24/2017 - 01/20/2018 3.5 14.0 01/21/2018 - 02/17/2018 3.5 17.5 02/18/2018 - 03/17/2018 3.4 20.9 03/18/2018 - 04/14/2018 3.4 24.3 04/15/2018 - 05/12/2018 3.4 27.7 05/13/2018 - 06/09/2018 3.4 31.1 06/10/2018 - 07/07/2018 3.4 34.5 07/08/2018 - 08/04/2018 3.4 37.9 08/05/2018 - 09/01/2018 3.4 41.3 09/02/2018 - 09/29/2018 3.4 44.7 37 FY 2018 09/30/2018 - 10/27/2018 3.4 3.4 10/28/2018 - 11/24/2018 3.4 6.8 11/25/2018 - 12/22/2018 3.4 10.2 12/23/2018 - 01/19/2019 3.4 13.6 35 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes all staff in the Reactor and Materials Decommissioning Branches of NMSS, plus relevant contributions from staff in OGC, R-I, and R-III. No mission support staff, second level and above supervisory staff, or staff support from other offices is included.

11 U.S. Nuclear Regulatory Commission Region I FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 15.6 79.1 02/19/2017 - 03/18/2017 15.4 94.5 03/19/2017 - 04/15/2017 15.4 109.9 04/16/2017 - 05/13/2017 15.2 125.1 05/14/2017 - 06/10/2017 15.3 140.4 06/11/2017 - 07/08/2017 15.5 155.9 07/09/2017 - 08/05/2017 15.7 171.6 08/06/2017 - 09/02/2017 15.6 187.2 09/03/2017 - 09/30/2017 15.5 202.7 209 FY 2017 10/01/2017 - 10/28/2017 15.4 15.4 10/29/2017 - 11/25/2017 15.5 30.9 11/26/2017 - 12/23/2017 15.4 46.3 12/24/2017 - 01/20/2018 15.1 61.4 01/21/2018 - 02/17/2018 14.9 76.3 02/18/2018 - 03/17/2018 14.7 91.0 03/18/2018 - 04/14/2018 14.7 105.7 04/15/2018 - 05/12/2018 14.8 120.5 05/13/2018 - 06/09/2018 14.8 135.3 06/10/2018 - 07/07/2018 14.7 150.0 07/08/2018 - 08/04/2018 14.6 164.6 08/05/2018 - 09/01/2018 14.6 179.2 09/02/2018 - 09/29/2018 14.6 193.8 198 FY 2018 09/30/2018 - 10/27/2018 14.6 14.6 10/28/2018 - 11/24/2018 14.6 29.2 11/25/2018 - 12/22/2018 14.6 43.8 12/23/2018 - 01/19/2019 14.6 58.4 195 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes all staff in R-I.

12 U.S. Nuclear Regulatory Commission Region II FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 20.2 100.8 02/19/2017 - 03/18/2017 20.3 121.1 03/19/2017 - 04/15/2017 20.3 141.4 04/16/2017 - 05/13/2017 20.2 161.6 05/14/2017 - 06/10/2017 20.3 181.9 06/11/2017 - 07/08/2017 20.0 201.9 07/09/2017 - 08/05/2017 19.9 221.8 08/06/2017 - 09/02/2017 19.8 241.6 09/03/2017 - 09/30/2017 19.8 261.4 274 FY 2017 10/01/2017 - 10/28/2017 19.7 19.7 10/29/2017 - 11/25/2017 19.6 39.3 11/26/2017 - 12/23/2017 19.6 58.9 12/24/2017 - 01/20/2018 19.4 78.3 01/21/2018 - 02/17/2018 19.5 97.8 02/18/2018 - 03/17/2018 19.5 117.3 03/18/2018 - 04/14/2018 19.5 136.8 04/15/2018 - 05/12/2018 19.5 156.3 05/13/2018 - 06/09/2018 19.3 175.6 06/10/2018 - 07/07/2018 19.3 194.9 07/08/2018 - 08/04/2018 19.3 214.2 08/05/2018 - 09/01/2018 19.3 233.5 09/02/2018 - 09/29/2018 19.3 252.8 272 FY 2018 09/30/2018 - 10/27/2018 19.3 19.3 10/28/2018 - 11/24/2018 19.3 38.6 11/25/2018 - 12/22/2018 19.3 57.9 12/23/2018 - 01/19/2019 19.3 77.2 249 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes all staff in R-II.

13 U.S. Nuclear Regulatory Commission Region III FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 14.3 71.1 02/19/2017 - 03/18/2017 14.3 85.4 03/19/2017 - 04/15/2017 14.3 99.7 04/16/2017 - 05/13/2017 14.3 114.0 05/14/2017 - 06/10/2017 14.3 128.3 06/11/2017 - 07/08/2017 14.5 142.8 07/09/2017 - 08/05/2017 14.4 157.2 08/06/2017 - 09/02/2017 14.2 171.4 09/03/2017 - 09/30/2017 14.2 185.6 197 FY 2017 10/01/2017 - 10/28/2017 14.3 14.3 10/29/2017 - 11/25/2017 14.3 28.6 11/26/2017 - 12/23/2017 14.3 42.9 12/24/2017 - 01/20/2018 14.1 57.0 01/21/2018 - 02/17/2018 14.0 71.0 02/18/2018 - 03/17/2018 14.0 85.0 03/18/2018 - 04/14/2018 14.0 99.0 04/15/2018 - 05/12/2018 13.8 112.8 05/13/2018 - 06/09/2018 13.8 126.6 06/10/2018 - 07/07/2018 13.8 140.4 07/08/2018 - 08/04/2018 13.8 154.2 08/05/2018 - 09/01/2018 13.8 168.0 09/02/2018 - 09/29/2018 13.8 181.8 184 FY 2018 09/30/2018 - 10/27/2018 13.8 13.8 10/28/2018 - 11/24/2018 13.8 27.6 11/25/2018 - 12/22/2018 13.8 41.4 12/23/2018 - 01/19/2019 13.8 55.2 182 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes all staff in R-III.

14 U.S. Nuclear Regulatory Commission Region IV FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE Annual Budget 01/22/2017 - 02/18/2017 13.6 69.7 02/19/2017 - 03/18/2017 13.5 83.2 03/19/2017 - 04/15/2017 13.4 96.6 04/16/2017 - 05/13/2017 13.2 109.8 05/14/2017 - 06/10/2017 13.0 122.8 06/11/2017 - 07/08/2017 13.0 135.8 07/09/2017 - 08/05/2017 13.0 148.8 08/06/2017 - 09/02/2017 13.0 161.8 09/03/2017 - 09/30/2017 12.8 174.6 187 FY 2017 10/01/2017 - 10/28/2017 12.6 12.6 10/29/2017 - 11/25/2017 12.6 25.2 11/26/2017 - 12/23/2017 12.7 37.9 12/24/2017 - 01/20/2018 12.8 50.7 01/21/2018 - 02/17/2018 13.0 63.7 02/18/2018 - 03/17/2018 13.0 76.7 03/18/2018 - 04/14/2018 13.0 89.7 04/15/2018 - 05/12/2018 13.0 102.7 05/13/2018 - 06/09/2018 13.0 115.7 06/10/2018 - 07/07/2018 13.0 128.7 07/08/2018 - 08/04/2018 13.0 141.7 08/05/2018 - 09/01/2018 13.0 154.7 09/02/2018 - 09/29/2018 13.0 167.7 175 FY 2018 09/30/2018 - 10/27/2018 13.0 13.0 10/28/2018 - 11/24/2018 13.0 26.0 11/25/2018 - 12/22/2018 13.0 39.0 12/23/2018 - 01/19/2019 13.0 52.0 169 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes all staff in R-IV.

15 U.S. Nuclear Regulatory Commission Corporate Support Functions FTE Actuals and Projections 11 Months Prior and 12 Months Future Data as of 01/20/2018 Period Actual/

Projected FTE for the Period Fiscal Year to Date FTE 01/22/2017 - 02/18/2017 40.5 204.8 02/19/2017 - 03/18/2017 40.4 245.2 03/19/2017 - 04/15/2017 40.1 285.3 04/16/2017 - 05/13/2017 39.3 324.6 05/14/2017 - 06/10/2017 38.4 363.0 06/11/2017 - 07/08/2017 38.2 401.2 07/09/2017 - 08/05/2017 37.9 439.1 08/06/2017 - 09/02/2017 37.4 476.5 09/03/2017 - 09/30/2017 37.3 513.8 594 FY 2017 10/01/2017 - 10/28/2017 36.9 36.9 10/29/2017 - 11/25/2017 36.0 72.9 11/26/2017 - 12/23/2017 35.8 108.7 12/24/2017 - 01/20/2018 35.3 144.0 01/21/2018 - 02/17/2018 35.2 179.2 02/18/2018 - 03/17/2018 35.2 214.4 03/18/2018 - 04/14/2018 35.2 249.6 04/15/2018 - 05/12/2018 35.2 284.8 05/13/2018 - 06/09/2018 35.2 320.0 06/10/2018 - 07/07/2018 35.3 355.3 07/08/2018 - 08/04/2018 35.3 390.6 08/05/2018 - 09/01/2018 35.3 425.9 09/02/2018 - 09/29/2018 35.3 461.2 510 FY 2018 09/30/2018 - 10/27/2018 35.3 35.3 10/28/2018 - 11/24/2018 35.3 70.6 11/25/2018 - 12/22/2018 35.3 105.9 12/23/2018 - 01/19/2019 35.3 141.2 506 FY 2019 Notes:

1 2

Data are reported in two-pay-period groups because of the biweekly payroll cycle.

Actual/projected FTE for the period reflects FTE utilization (or projected utilization).

3 Projection is approximately 1/12th of total year FTE expenditures, adjusted for known future gains and losses through the end of the fiscal year.

4 Includes all staff in the following corporate support offices: Office of the Chief Financial Officer, Office of the Chief Information Officer, Office of Administration, Office of Small Business and Civil Rights, and Office of the Chief Human Capital Officer.

5 Includes reimbursable FTE for work performed for other Federal agencies and non-Federal organizations.

16

4. Please describe the status of actions taken or planned to reduce corporate support costs, including efforts to reduce office space in the Three While Flint North building and in the regional offices. Please include goals for space reductions and cost savings, as well as the estimated date to achieve those goals.

The NRC remains committed to identifying and achieving efficiencies in the corporate support area. The agencys FY 2017 enacted budget for corporate support activities was $300.1 million.

The FY 2017 enacted budget included resources for the following five overhead activities:

acquisitions, real property, human capital, financial management, and information technology.

Additionally, the corporate support budget includes the NRCs small business outreach efforts, as well as resources to support the Commission offices.

In the SRM to the Project Aim Report, the Commission directed the staff to re-baseline the agencys workloadfocusing on statutory mandates, as well as work pertaining to the agencys safety and security mission. In SRM-SECY-16-0009, Recommendations Resulting from the Integrated Prioritization and Re-baselining of Agency Activities, the Commission subsequently approved a total of $8.4 million, including 24.3 FTE, in reductions from the corporate support area by the end of FY 2017. Re-baselining reductions totaling $4.8 million, including 13.0 FTE, were taken from corporate support in the FY 2017 request, as detailed in the FY 2017 Congressional Budget Justification (CBJ). The agencys FY 2017 enacted budget reflected the balance of $3.6 million in re-baselining reductions, including 11.3 FTE.

In addition to the above re-baselining reductions, in SECY-16-0035, Additional Re-baselining Items, the NRC staff identified other actions that could provide additional efficiencies in the long-term. For example, efforts to reduce office space in NRC headquarters and the regional offices will continue. A detailed discussion of these activities follows the summary table below.

The NRC remains committed to identifying and achieving efficiencies in the corporate support area that will lead to reduced costs, such as the following:

Product Line Description Total $

(M)*

FTE Status Fiscal Year Additional Re-baselining Items (SECY-16-0035)

Administrative Services Reduce Office Space in Three White Flint North

-4.0 0

In process FY 2018 -

FY 2021 Administrative Services Reduce Office Space in the Regions

-1.2 0

In process FY 2018 -

FY 2021 Financial Management Standardize Budget Formulation and Execution across Business Lines TBD TBD In process FY 2019 Financial Management Use a Federal Shared Service Provider for Accounts Payable TBD TBD In process FY 2019 Administrative Services and Information Technology Workstation Efficiencies TBD TBD In process FY 2019 Subtotal - Additional Re-baselining Reductions

-$5.2 TBD Other Corporate Support Reductions Information Technology IT Infrastructure Support - the agency expects to realize a 10 to 15 percent drop in contract

-3.6 0

In process FY 2018

17 Product Line Description Total $

(M)*

FTE Status Fiscal Year expenses resulting from a new acquisition strategy.

Subtotal - Other Corporate Support

-$3.6 0

Total

-$8.8 0

  • Total includes any FTE cost.

Reduction of Office Space.

NRC office space is currently comprised of a Headquarters Campus in Rockville, MD (One White Flint North (OWFN), Two White Flint North (TWFN), and partial space in Three White Flint North (3WFN)), a warehouse, four regional office buildings, and a technical training center.

From FY 2013 through FY 2015, NRC relinquished a net total of 364,997 useable square feet (USF) at its headquarters by shedding a total of eight floors in the 3WFN building and four temporary satellite locations. As a result, the agencys headquarters now consists of OWFN, TWFN, and five floors and the B1 level of 3WFN. NRC plans to relinquish an additional 139,244 USF of office space at its headquarters location and four regional office locations, from FY 2018 through FY 2021. This space consists of four floors in 3WFN totaling 93,244 USF, and approximately 46,000 USF at the regional locations, by consolidating at headquarters and within each regional office location. NRCs proposed agency-wide total space reduction goals by fiscal year are shown in the table below.

NRC Square Foot Reduction Goals FY 2018 - FY 2021 FY 2018 FY 2019 FY 2020 FY 2021 Office Target (Net SF Reduction) 33,561 42,561 29,561 33,561 Significantly reducing costs by releasing the space will be a challenge due to the non-cancelable terms of many of the occupancy agreements and leases, including the terms of 3WFN. However, NRC is working with the General Services Administration (GSA) to identify potential tenants for both 3WFN and the regional office locations. The Food and Drug Administration (FDA) has expressed an interest in acquiring an additional floor in 3WFN in FY 2018 and the National Institutes of Health (NIH) has expressed an interest in acquiring the remaining three floors as NRC continues to consolidate at headquarters and the space becomes available in the FY 2019 through FY 2021 timeframe. Regional office space reductions can be achieved by reconfiguring the existing space to use fewer square feet, thereby allowing for unused blocks of space to be released. However, with the exception of NRCs Region III office in Lisle, IL, rent savings will not be achieved until GSA identifies and places a new tenant into the released space, or until such time as the terms of the NRCs current leases allow. The timing and scope of the regional reductions are as follows: Region III, Lisle, IL, 11,000 USF in FY 2018; Region II, Atlanta, GA,17,000 USF in FY 2019; Region I, King of Prussia, PA, 7,000 USF in FY 2020; and Region IV, Arlington, TX, 11,000 USF in FY 2021.

At headquarters, the amount and timing of rent reductions for 3WFN are contingent upon GSAs ability to identify and place a new tenant into the relinquished floors; however, NRC anticipates an annual reduction of $1 million per floor for each floor relinquished upon a new tenant taking the space. The agency anticipates rent costs to begin decreasing in July 2018 when FDA has

18 agreed to occupy the 2nd floor of 3WFN, and again by early FY 2020 as NIH begins to occupy the remaining three floors. Once the release of NRCs space is complete in FY 2021, the agency will realize a total reduction of $4 million in office space costs going forward. Cost reductions for the regional locations are likewise dependent upon successful and timely leasing of the space to new tenants. The annual reduction in costs for the regional office space is anticipated to average approximately $300,000 per regional office. As a result of the planned space reductions, NRC anticipates an annual total rent reduction of $5.2 million from FY 2022 forward, as compared to FY 2018.

5. Please describe the status of efforts to provide greater transparency, timeliness, and itemization in invoices to applicants and licensees, including any progress toward electronic invoicing and payment. Please include near-term (within 6 months), medium-term (6 to 12 months), and long-term (greater than 12 months) milestones.

Improvements to invoices showing itemized charges by standard codes for greater transparency and timeliness.

Complete:

In January 2018 the NRC issued the first redesigned quarterly invoices that improve transparency of the costs. Enhancements include:

Invoice charges are grouped by project (Enterprise Project Identifier (EPID)), which is a new data element on the invoice, and for each EPID further itemized by activity (Cost Activity Code (CAC)).

Invoices include standard CAC titles to provide consistent descriptions for the same type of work performed for all projects.

The names of NRC staff and contractor companies appear on the invoice for each itemized CAC.

The invoices were sent with a document, Content Updates to your NRC Invoice, which describes the improvements to the invoice. The document can be found here:

https://www.nrc.gov/about-nrc/regulatory/licensing/sample-invoice.pdf Near-Term:

The NRC will have a booth at the Regulatory Information Conference (RIC) on March 13 and 14, 2018 to further communicate changes to the invoices as well as solicit stakeholder feedback on the changes.

The NRC will be holding a public meeting on March 15, 2018, to further communicate changes to the invoices as well as solicit stakeholder feedback.

The NRC will continue to evaluate feedback on the changes to the invoices.

Medium-Term:

The Office of the Chief Financial Officer (OCFO) is working with an intra-agency working group during FY 2018 to implement a standardized 10 CFR Part 170 (fees for service) fee billing validation process, and establish standardized roles and responsibilities. The working group will develop, pilot, and finalize the process. OCFO will provide training to all staff involved in the billing process. OCFO is on target for a completion date of October 1, 2018.

19 Progress towards electronic invoicing and payment.

The NRC is currently in the planning phase of the electronic invoicing (eBilling) project, which includes the following tasks:

Near-Term:

Document the initial "as-is" fee billing processes and fee billing information technology systems (complete).

Update the current as-is fee billing processes and fee billing information technology systems for OCFO acceptance (in progress).

Continue to perform requirements analysis on items that may impact the fee billing process and systems (in progress).

Interview other Federal agencies that recently implemented electronic invoicing for lessons-learned opportunities (in progress).

Conduct market research for eBilling tool selection (in progress).

Select an eBilling tool.

Medium-Term:

Establish the initial eBilling solution based on the eBilling tool selected, outreach activities, lesson learned opportunities, and a requirements analysis.

Reach out to stakeholders for input on the initial eBilling proposed solution and to identify licensees to participate in phased-approach implementation pilot.

Develop a phased-approach and corresponding project plan to implement the eBilling solution based on stakeholder feedback.

Long-Term:

Execute the eBilling solution. The initial phased approach deployment is planned to occur on or about October 2019.

Continue to perform outreach activities with stakeholders.

6. Please provide a list of alI new research initiated during the reporting period. For each new project, please provide the estimated timeframe and resources necessary for completion, and a description of the safety significance of the research.

During the month of January 2018, the Office of Nuclear Regulatory Research (RES) initiated research on or substantially revised the following research:

Comments:

Name of New or Revised Project Estimated Completion Estimated Resources Safety Significance of Research Activity No New or Revised Research Activities to Report for January 2018

20 The table above provides projects that were reviewed and approved during the monthly reporting period for projects that exceed 300 staff hours or $500K of program support.

URANIUM RECOVERY

7. For major uranium recovery licensing actions, please provide a table including the date the application was filed, the duration of the application review, the originally forecasted completion date, the currently forecasted completion date, and the total current amount of fees billed to the licensee/applicant for the review.

Major Uranium Recovery Licensing Actions (1)

Licensee Site/Facility Name Licensing Action Type Date of Submittal Duration of Review (2)

(months)

Originally Forecasted Completion Date Currently Forecasted Completion Date Total Current Fees Billed (through December 23, 2017)

Uranium One (3)

Ludeman Expansion 12/06/2011 69.0 08/14/2013 08/31/2018

$2,210,317.74 Kennecott Sweetwater Renewal 09/08/2014 38.5 12/31/2016 08/31/2018

$1,780,312.25 Crow Butte Resources (4)

Marsland Expansion 06/20/2012 64.0 02/14/2015 05/25/2018

$3,896,953.70 Cameco Resources (5)

Smith Ranch Renewal 02/01/2012 67.0 07/05/2015 09/27/2018

$2,510,994.99 Lost

Creek, ISR (6)

KM Horizon/LC East Expansion 02/27/2017 9.0 08/07/2018 08/07/2018

$1,409,796.95 Notes:

1.

NRC staff completed a self-assessment of the uranium recovery licensing process in 2017. The review compared the uranium recovery licensing process to other licensing groups within the NRC to identify best practices. The review identified several recommendations for improvements to the uranium recovery licensing process. A number of these recommendations, such as the use of schedule letters to communicate changes in review schedules and developing tools to better track project status have already been implemented. In addition, in 2016, the uranium recovery program established an agency metric that tracks the percentage of major milestones completed on schedule. The uranium recovery staff anticipates that implementing these changes will result in future efficiencies in the uranium recovery licensing process.

2.

The duration of review is the total amount of time the application has been under consideration, starting when the application was accepted for review by the NRC staff. The NRCs goal is to complete major reviews within 36 months from acceptance of the application. The duration of review includes periods of delay that could be attributed to the NRC staff, the licensee, or both.

21

3.

The duration of review has been primarily impacted by the applicants change in the design of the facility during the review process. The duration of review has also been impacted by a prior limited availability of health physics reviewers.

4.

The duration review has been impacted by the applicants timeliness in responding to NRC staffs RAI.

5.

The duration review has been primarily impacted by delays in applicant providing adequate responses to NRC staffs RAI.

6.

Currently forecasted completion date represents completion of NRC safety evaluation report. The NRC staff continues to coordinate with the U.S. Bureau of Land Management (BLM) in its preparation of the environmental impact statement (EIS) in accordance with the BLM/NRC Memorandum of Understanding (MOU) and the letter of December 4, 2014, designating BLM as the lead agency and the NRC as a cooperating agency. The BLM is scheduled to publish the final EIS in December 2018.

8. For major uranium recovery licensing actions, please provide a brief description of the status of each review, including* projected budget and timeline for both the environmental impact statement and the safety evaluation report.

The table below provides the status of major uranium recovery licensing actions currently under review, the timeline for completing the associated EISs and SERs, and the total projected budget per project.

The NRC does not formulate its budget at the project level. The budget for the Uranium Recovery Program is formulated at a higher level using budget models for the number, type, and complexity of reviews anticipated. The projected budget information reported below includes the program staff and contract support resource estimates to perform the safety and environmental reviews from submittal to licensing decision, excluding resources for OGCs reviews, hearings, mission support, supervisory support, travel, and allocated agency corporate support resources. The estimates are based on budget models for different types (such as expansions, renewals, and new licenses) and complexities of major licensing action reviews.

The NRC staffs goal is to complete the review of major licensing actions within 3 years; however, the staff estimates that smaller, less complex applications may be reviewed in 2 years, while larger, more complex, applications may require up to 4 years to review.

Uranium Recovery Applicant Application Accepted for Review Review Status and Projected Budget Cameco North Trend Expansion 08/28/07 The licensee requested the NRC staff to stop its review of the North Trend application and to instead focus its efforts on the review of the Marsland expansion. The SER for the North Trend expansion was completed in July 2013.

The NRC staff has suspended its work related to the development of the draft Environmental Assessment (EA) and conduct of Section 106 consultations pursuant to the National Historic Preservation Act. In addition, the hearing to address contentions related to groundwater is on hold, pending completion of the NRC staffs environmental review. The current schedule for remaining milestones will be determined after the NRC staff has completed its review for the Marsland expansion.

The projected total budget to conduct the review is 3.0 FTE and $600K.

22 Uranium Recovery Applicant Application Accepted for Review Review Status and Projected Budget Uranium One Ludeman Expansion 05/16/12 NRC environmental and safety reviews are in progress for this expansion of the existing Willow Creek project. The licensee is resolving safety and environmental issues.

NRC met with the licensee on February 22, 2017, to discuss these issues and the licensees plan to submit an amended application that addresses a major change of design. On March 28, 2017, the NRC staff issued a letter to the licensee requesting an updated schedule of when it would submit the required information necessary for the staff to complete its review. In April 2017, the licensee provided all information except for the amended application. The staff received the amended technical report in June 2017, and the amended environmental report in August 2017. The NRC staff is on schedule to complete the SER by March 2018. Based on the amended environmental report, the cultural resources review can now be completed. The NRC staff is on schedule to issue the final EA by August 3, 2018, and reach a decision on the license amendment on August 31, 2018.

The projected total budget to conduct the review is 3.0 FTE and $600K.

Cameco Smith Ranch License Renewal 07/05/12 Environmental and safety reviews are in progress. Open issues are currently being addressed. On May 2, 2013, the NRC staff issued an RAI on safety and environmental aspects of the renewal request. On April 21, 2015, the licensee submitted its responses to the RAI. The NRC staff is working with the licensee to close remaining open issues. On May 2, 2016, the staff communicated to the licensee that its responses to the RAIs were incomplete. In December 2016 the staff requested the licensee to provide a schedule for completing its response to the remaining aspects of the RAI. On January 10, 2017, the licensee provided an update on when it expects to respond to part, but not all, of the NRC staffs RAI. The NRC staff responded to Camecos letter on April 14, 2017.

The NRC staff and Cameco also had several public meetings to address Camecos development of sufficient RAI responses. The NRC staffs SER and EA completion dates in September 2018 were based on receipt of Camecos RAI responses by January 19, 2018. The NRC staff will reassess the schedule for completion of the SER and EA, when the responses are received.

The projected total budget to conduct the review is 3.5 FTE.

23 Uranium Recovery Applicant Application Accepted for Review Review Status and Projected Budget Crow Butte Marsland Expansion 10/05/12 The NRC staff issued RAIs in July 2013. The licensee responded in November 2015. After reviewing the responses, the NRC determined that additional information was required to resolve the RAIs. Cameco submitted responses to the open issues in June and August 2017. The NRC staff completed its safety review for the final SER on January 29, 2018. The staff plans to complete the final EA in April 2018, and make a final licensing decision in May 2018. The Marsland expansion review has an admitted contention that will go to hearing after completion of the NRC staffs review.

The projected total budget to conduct the review is 3.0 FTE and $600K.

Hydro Resources, Inc. (HRI)

License Renewal 06/24/13 The sites, located very close to Navajo Nation lands, were licensed in 1998. Construction has not yet commenced.

The license renewal review was placed in abeyance on November 13, 2014, while HRI continues its work with the Navajo Nation Council. In March 2016 the NRC approved the transfer of control of the license from the HRI parent company, Uranium Resources, Inc., to Laramide Resources. The parties finalized the transaction in January 2017. The schedule for remaining milestones associated with the licensing review is to be determined.

The projected total budget to conduct the review is 2.6 FTE.

Kennecott Sweetwater License Renewal 11/25/14 The licensee has maintained the facility in stand-by since 1983, waiting on better market conditions to resume operations. Environmental and safety reviews are in progress. On October 18, 2016, the licensee submitted supplemental information related to groundwater detection monitoring. On November 14, 2016, the licensee submitted revised environmental information. The NRC staff issued RAIs to Kennecott on June 29, 2017, and received the licensees response on October 2, 2017.

The staff plans to complete its SER in February 2018 and final EA in July 2018, and is on schedule to reach a licensing decision in August 2018.

The projected total budget to conduct the review is 0.5 FTE.

24 Uranium Recovery Applicant Application Accepted for Review Review Status and Projected Budget Strata Kendrick Expansion 01/14/16 On May 27, 2016, and September 14, 2016, the NRC staff issued RAIs for the environmental review and for the safety review, respectively. On December 15, 2016, the licensee requested that the NRC cease all activities related to this review. As a result of the licensees request, the NRC staff is no longer reviewing this licensing action. The staffs safety and environmental reviews, including development of the Supplemental EIS, are on hold.

The projected total budget to conduct the review is 3.5 FTE and $1500K, which includes completing the EIS.

Lost Creek KM Horizon/East Expansion 05/02/17 By letter dated February 27, 2017, the licensee resubmitted a revised application. The NRC staff has accepted the application for review on May 2, 2017. The NRC staff continues to coordinate with the BLM in its preparation of the EIS in accordance with the BLM/NRC MOU and the letter of December 4, 2014, designating BLM as the lead agency and NRC as a cooperating agency. BLM is scheduled to publish the final EIS in December 2018. The NRC staff is submitting its RAIs in batches in order to support BLMs schedule for issuing the EIS. The NRC staff issued its initial set of RAIs on July 27, 2017, its second set of RAIs on August 28, 2017, and its third set of RAIs on October 30, 2017. The final safety evaluation report is scheduled to be completed in August 2018.

The projected total budget to conduct the review is 3.0 FTE.

Cameco Three Crow Expansion Three Crow is an expansion of the operating Crow Butte facility located in Crawford, NE. The NRC staff started its acceptance review on March 3, 2011, and was waiting for the licensee to complete changes in its design prior to acceptance. However, in November 2014, the licensee requested that the NRC staff place the review on hold and instead focus efforts on the review of the Marsland expansion. The acceptance review remains on hold.

9. For minor uranium recovery licensing actions, please provide the following information each reporting period, including any months previously reported, in this format:
a. Size of inventory;
b. Number of acceptance reviews completed on time;
c. The number of items completed in the period being reported; and
d. Of the items completed in the reporting period, the number completed within the forecasted schedule.

25

e. Please identify any unusually complex items omitted from the inventory and provide the age of the item, a brief description of the item, the justification for omitting it from the inventory size, and an explanation for any review exceeding its original schedule by 125 percent.

Month/Year Size of Inventory Number of Acceptance Reviews Completed on Time(1)

Number of Items Completed During Month Number of Items Completed Within Forecasted Schedule(2)

Unusually Complex Items Omitted from Inventory Nov-2017 21 NA 2

1 0

Dec-2017 21 1

0 0

0 Jan-2018 22 1

1 1

0 Notes:

1. NA means no acceptance reviews were due.
2. This column represents the total number of minor licensing actions completed within the staffs forecasted schedule in a particular month. At times, the uranium recovery staff has to divert resources from minor licensing actions to address oversight of operating sites, emergent issues, and major licensing actions. When this occurs, the NRC staff tries to accommodate the licensees priorities for completion of minor licensing actions.

However, this has impacted the staffs ability to complete minor licensing actions within the forecasted schedule.

10. Please provide a concise summary of the status of the process for the State of Wyoming to become an Agreement State.

On February 27, 2015, Governor Matt Meade of Wyoming submitted a letter of intent for the State of Wyoming to become an Agreement State, under a limited agreement to regulate source and byproduct material (as defined in § 11e.(2) of the Atomic Energy Act (AEA)). A limited agreement is an agreement where a State assumes regulatory authority for a subset of the types and quantities of radioactive material that a State could assume authority for under the AEA. This agreement would authorize the State of Wyoming to assume regulatory authority over uranium and thorium milling (e.g., conventional and in-situ uranium recovery activities), the possession and use of source material involved in the extraction and concentration of uranium and thorium in source material and ores at milling facilities, and the management and disposal of byproduct material as defined in Section 11e.(2) of the AEA.

The NRC and the Wyoming Department of Environmental Quality (DEQ) have worked closely to facilitate the timely completion of the Agreement through biweekly conference calls, in-person meetings, emails, and letters. As an interim step, the NRC staff, on July 5, 2016, requested Commission approval of the State of Wyomings proposed approach to submit a draft application for a limited agreement. Under this approach six Uranium Mill Tailings Radiation Control Act (UMTRCA) sites would have been transferred to Wyoming under the Agreement.

On August 3, 2016, the Commission approved this approach in SRM-SECY-16-0084.

On October 28, 2016, the State of Wyoming submitted a draft application for a limited agreement. The draft application proposed that the NRC retain jurisdiction over the six

26 UMTRCA sites. In response to the draft application, the NRC staff had lengthy discussions with the State of Wyoming, after which the State of Wyoming proposed to include five UMTRCA sites in its final application. On August 16, 2017, the NRC staff recommended that the Commission approve the retention of NRCs regulatory authority over one of the six UMTRCA sites excluded in the State of Wyomings draft application (i.e., the American Nuclear Corporation (ANC) site in Gas Hills, Wyoming). On October 4, 2017, the Commission approved the staffs proposal in SRM-SECY-17-0081.

In parallel with resolving the jurisdiction of the six UMTRCA sites, the NRC staff provided comments to Wyoming DEQ on the draft application in an April 20, 2017, letter. On June 22, July 17, and August 16, 2017, Wyoming DEQ provided written responses to address NRCs comments.

On November 14, 2017, the State of Wyoming submitted its formal request for an Agreement.

The NRC staff continues to work with Wyoming DEQ to resolve the remaining issues related to the overall compatibility of the proposed program. The NRC staff is completing the assessment of the Wyoming Agreement State application and plans to request Commission approval to publish the draft agreement and staffs assessment for public comment in early spring 2018.

11. Please provide a concise summary of the specific actions planned to improve the efficiency of reviews conducted for compliance with the National Historic Preservation Act, including implementation dates for completion. Please describe any progress made during the reporting period.

The Section 106 process under the National Historic Preservation Act (NHPA) requires Federal agencies to take into account the effects of their undertakings on historic properties and afford the Advisory Council on Historic Preservation (ACHP) a reasonable opportunity to comment.

Based on lessons learned in the uranium recovery licensing functional area, the NRC has taken a number of actions to facilitate and enhance its Section 106 reviews. Because each licensing or regulatory action differs in scope, the specific activities identified to carry out NRCs obligations under NHPA differ from one licensing or regulatory action to another. The following specific actions have been identified and are being carried out to improve and facilitate compliance with the Section 106 process of the NHPA.

For efficiency, the NRC conducts the Section 106 process in coordination with the National Environmental Policy Act (NEPA) review process. To the extent possible, the NRCs completion date for its NHPA Section 106 review for a specific licensing action aligns with the date for publishing the final NEPA environmental review document.

In fiscal year 2013, the NRC entered into an interagency agreement with the ACHP, under which the ACHP established a dedicated liaison to provide the NRC with technical assistance with Section 106 reviews of specific licensing actions, as well as relevant training and guidance.

In June 2014, the NRC published its draft Interim Staff Guidance (ISG) for conducting the Section 106 process specific to uranium recovery licensing actions, Guidance for Conducting the Section 106 Process of the National Historic Preservation Act for Uranium Recovery Licensing Actions (FSME-ISG-02). Due to workload, resources, and other priorities, the NRC has had to delay completion of the ISG until calendar year 2018.

The NRC staff continues to attend and participate in the National Mining Associations (NMAs) annual uranium recovery workshops. The NRC staffs participation includes presentations or

27 panel discussions of the NRCs activities to carry out its NHPA Section 106 obligations, including challenges and potential solutions related to the NHPA Section 106 reviews.

To further improve the agencys NHPA and NEPA processes for licensing activities, the NRC has updated several documents regarding tribal consultation. The NRC published the final Tribal Policy Statement in the Federal Register on January 9, 2017 (82 FR 2402), and revised its Tribal Protocol Manual. The Tribal Protocol Manual is intended to facilitate effective consultations and interactions between the NRC and Tribes.

Consistent with NRCs MOU with BLM, in FY 2017, the NRC staff continued its coordination of NEPA and NHPA Section 106 reviews related to such facilities that require an NRC license to possess and use source and byproduct materials, and are located on public lands under BLMs regulatory authority. The goal of the MOU is to limit, to the extent possible, duplication of consultation, review, and evaluation efforts on a project.

In the past few years, the number of uranium recovery licensing reviews has increased. In addition, the complexity of the Section 106 reviews associated with these licensing actions has grown significantly and, as a result, NRCs consultation efforts with respect to its obligations under Section 106 process have also increased. The NRC acknowledges that implementation of the Section 106 process continues to be a challenge affecting the licensing review schedule.

The NRC staff will continue to evaluate the Section 106 process to identify additional activities that could be taken to continue to facilitate the process.

12. Please provide a concise summary of the progress of the pilot project to establish flat fees for uranium recovery licensees, including specific near-term (6 months), medium-term (6 - 12 months), and long-term (greater than 10 months) milestones necessary to complete the pilot program.

As directed by the Commission, the NRC staff will conduct a flat fee pilot program for routine uranium recovery licensing actions. As described in the staff paper SECY-16-0097, Fee Setting Improvements and Fiscal Year 2017 Proposed Fee Rule, this pilot will involve evaluation of data to collect a representative sample of the costs for various licensing reviews. The staff believes that using data from the previous data recording structure that had less granularity could result in a proposed flat fee that is skewed either high or low for the work delivered. Collecting representative sample of data under the new data recording structure, described in the response to question five, will allow NRC to determine a flat fee that is fair and equitable.

As of June 30, 2017, the agency completed development of a new data recording structure. By September 30, 2017, the NRC trained staff to record the data using the new structure.

Concurrently, the staff began outreach to Agreement States with uranium recovery licensees to understand their fee schedule development process. The new data structure was deployed on October 1, 2017.

Near-Term:

The NRC staff will record time and attendance, which indicates the hours spent on specific work products, using the new data structure.

The NRC staff will continue to follow-up with the Agreement States in order to gain additional facts to inform the staffs analysis regarding a flat fee structure.

28 Medium-Term:

After a year of recording data using the new data structure, by November 1, 2018, the staff will begin analysis of the data to develop recommendations.

Long-Term:

Beginning in January 2019, the staff will engage with stakeholders to solicit for comments and concerns. The analysis and draft recommendations will be completed by the end of April 2019. The recommendations will be included in the FY 2020 fee rule SECY paper due to the Commission on August 15, 2019. These recommendations will continue to address requirements under the Omnibus Budget Reconciliation Act of 1990 to collect approximately 90 percent of the NRCs annual budget through fees, and under the Independent Offices Appropriation Act, 1952 to assess user fees that are fair and based on the costs to the government and certain other factors. The Commission is expected to report its decision to Congress by the end of December 2019. The FY 2020 proposed fee rule is expected to be published in January 2020. The FY 2020 final fee rule is expected to be published by May 2020 and would be effective 60 days thereafter.

29 LICENSING

13. For operating reactors, new reactors, and uranium recovery licensees, please provide the following information regarding license amendment reviews:

13.a Please provide the following information for the current reporting period, including any information previously reported in the last six months:

i.

Size of inventory; ii. The number of items completed in the period being reported; iii. Percentage of acceptance reviews completed on time; iv. The percentage of these items completed within the forecasted schedule;

v. The percentage of these items completed within 125 percent of the forecasted schedule; vi. The percentage of items completed within ten months; vii. The average age for items completed during the month being reported; viii. The ages of the quickest three items completed; and ix. The ages of the slowest three items completed.

Operating Reactors Month/Year Size of Inventory (Note 1)

No. of Items Completed in the Report Period Percentage of Acceptance Reviews Completed on Time Percentage of Items Completed within the Forecasted Schedule (Note 2)

Percentage of Items Completed within 125%

of Forecasted Schedule (Note 3)

Percentage of Items Completed within 10 Months Average Age for Items Completed During Report Period (months)

Ages of the Quickest Three Items Completed (months)

Ages of the Slowest Three Items Completed (months)

Nov-2017 588 46 100%

94%

94%

85%

6.9

<1

<1

<1 21 21 21 Dec-2017 579 93 100%

94%

94%

91%

9.2

<1

<1 1

12 12 12 Jan-2018 495 105 100%

100%

100%

84%

5.7

<1

<1 1

12 12 11 Note 1:

Similar to the licensing actions reported in the yearly CBJ, the inventory does not include unusually complex or Fukushima related licensing actions.

Note 2:

Internal processes track licensing action completions within forecasted scheduled (+ 1 month) [this percentage does not include unusually complex or Fukushima related licensing actions].

30 Note 3:

Internal processes track licensing action completions within 125 percent of the forecasted schedule [this percentage does not include unusually complex or Fukushima related licensing actions].

New Reactors Month/Year Size of Inventory No. of Items Completed in the Report Period Percentage of Acceptance Reviews Completed on Time Percentage of Items Completed within the Forecasted Schedule Percentage of Items Completed within 125%

of Forecasted Schedule Percentage of Items Completed within 10 Months Average Age for Items Completed During Report Period (months)

Ages of the Quickest Three Items Completed (months)

Ages of the Slowest Three Items Completed (months)

Nov-2017 38 7

100%

86%

100%

100%

6.4 5

5 5

6 7

8 Dec-2017 35 4

75%

50%

100%

100%

4.5 2

4 5

4 5

7 Jan-2018 30 2

50%

50%

100%

50%

8.5 5

12 N/A 12 5

N/A Uranium Recovery Month/Year Size of Inventory Number of Items Completed in the Report Period Percentage of Acceptance Reviews Completed on Time Percentage of Items Completed within Forecasted Schedule Percentage of Items Completed within 125%

of Forecasted Schedule Percent age of Items Comple ted within 10 Months Average Age for Items Completed during Report Period (months)(1)

Ages of the Quickest Three Items Completed (months)

Ages of the Slowest Three Items Completed (months)

Nov-2017 24 2

N/A 50%

50%

50%

24.5 48(2) 1 N/A 48(2) 1 N/A Dec-2017 24 0

0 0%

0%

0%

N/A N/A N/A N/A N/A N/A N/A Jan-2018 25 1

100%

100%

100%

100%

10 10 N/A N/A 10 N/A N/A Note 1: The uranium recovery staffs goal is to complete major licensing actions within 36 months of acceptance and minor licensing actions within 12 months of acceptance. At times, the uranium recovery staff has to divert resources from minor

31 licensing actions to address oversight of operating sites, emergent issues, and major licensing actions. When this occurs, the NRC staff tries to accommodate the licensees priorities when determining which minor licensing actions to complete first.

Note 2: One review of a minor licensing action completed in November 2017 required 48 months to complete. This review was low priority for the licensee; therefore, the uranium recovery staff focused on higher priority work until sufficient resources were available to complete the review.

13.b For the reporting period, please also provide the following for license amendment requests:

i.

The number not accepted for review; and ii. A list of the requests that were withdrawn or denied after being accepted for review including the age of the request at the time it was withdrawn or denied.

Operating Reactors Month/Year No. of License Amendment Requests Not Accepted for Review List the Requests that were Withdrawn or Denied after Being Accepted for Review Age of the Request at the Time it was Withdrawn or Denied (months)

Jan-2018 8

None N/A New Reactors Month/Year No. of License Amendment Requests Not Accepted for Review List the Requests that were Withdrawn or Denied after Being Accepted for Review Age of the Request at the Time it was Withdrawn or Denied (months)

Jan-2018 0

Withdrawn: Vogtle Electric Generating Plant Units 3 and 4:

Addition of Interim Amendment Process to license condition 2.D.(1) (LAR 16-015) 16

32 Uranium Recovery Month/Year Number of Amendment Requests Not Accepted for Review List of the Requests that were Withdrawn or Denied after being Accepted for Review Age of the Request at the Time it was Withdrawn or Denied (months)

Jan-2018 0

None N/A 13.c Please identify items considered unusually complex items (e.g. criticality reviews, NFPA 805 reviews) and omitted from the

[licensing amendment] inventory including: the age of the item, a brief description of the item, the justification for omitting it from the inventory size and an explanation for any review exceeding its original schedule by 125 percent.

Operating Reactors Note:

Unusually complex license amendments are not included in the internal performance measures and their nature does not allow for realistic forecasted schedule development. Rather, they are given escalated management attention to ensure progress is being made towards resolving outstanding issues and completing the reviews in a timely manner.

Technical Specification Task Force (TSTF)-505 Reviews o

Description:

These submittals request changes to Technical Specifications (TSs) for the adoption of Risk-Informed Technical Specification Task Force (RITSTF) Initiative 4b, specifically "TSTF-505 Revision 1, Provide Risk-Informed Extended Completion Times." This effort is associated with NEI 06-09, "Risk-Informed Technical Specifications Initiative 4b, Risk-Managed Technical Specifications Guidelines,"

o Justification: During review of the Vogtle pilot license amendment requests (LAR) for a risk-informed TS Completion time (RICT) program, a number of issues were raised by NRC staff. These issues resulted in the suspension of TSTF-505 to allow necessary revisions to the process. The NRC has been working with the TSTF group and other stakeholders to resolve the issues and lift the suspension. The five LARs currently under review are being reviewed on a plant-specific basis in parallel with revision of TSTF-505. Four of the five LARs have been supplemented to address the issues raised with TSTF-505. The supplements represent significant additional information and modifications to the licensee implementation of a RICT program. Although not a complete reset of the review, the additional information and changes to the LARs have added time to the review schedule and may result in the need for additional clarification requests. One licensee (Diablo Canyon) has yet to supplement its submittals to address the issues.

33 Current Reviews Age (Months)

Turkey Point Units 3 & 4 38 Saint Lucie Units 1 & 2 38 Calvert Cliffs Unit 1 & 2 24 Palo Verde Units 1, 2, & 3 31 Diablo Canyon Units 1 & 2 51 National Fire Protection Association (NFPA) 805 Reviews o

Description:

NFPA Standards Council approved NFPA Standard 805, "Performance-Based Standard for Fire Protection for Light-Water Reactor Electric Generating Plants, 2001 Edition," on January 13, 2001, as a risk-informed, performance-based standard for existing light-water nuclear power plants. The NRC staff cooperatively participated in the development of NFPA 805 as an alternative to the rules in Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix R.

Each submittal requesting implementation of NFPA 805 is over 1000 pages, requires five different technical disciplines to review, and has reviews staggered in an overlapping fashion. At any one time, 30 technical reviewers were active in the NFPA 805 LAR review process. Each NFPA 805 LAR requires at least one regulatory on-site audit; some required return regulatory audits to review on-site documentation and walk-down plant fire areas.

o Justification: The NFPA 805 reviews are voluminous and technically challenging, have unique site-specific issues, have utilized unreviewed analysis methods (UAMs), and required additional response time for RAIs. Some licensees used UAMs that deviated from the acceptable NUREG/CR-6850 methods, and had to be reviewed in-depth by the staff for the first time. To resolve these UAMs, the licensees either perform a sensitivity analysis or redo their fire probabilistic risk assessment (PRA). Due to the complexity of these methods, a great deal of time is required for the staff to prepare initial RAIs, significant time may be required for licensees to provide responses, and several rounds of RAIs may be needed to resolve issues. In some cases, licensees required up to 180 days to respond to the more complex RAIs. This complexity adds greatly to the length of the review.

Current Reviews Age (Months)

Davis-Besse Unit 1 26 Sequoyah Units 1 & 2 - Updated Final Safety Analysis Reports (UFSARs) Regarding Changes to Hydrologic Analysis o

Description:

Tennessee Valley Authority (TVA or the licensee) submitted LARs on July 19, 2012, for Watts Bar, Unit 1, and August 10, 2012, for Sequoyah, Units 1 and 2, that proposed to revise the respective UFSAR, Section 2.4, Hydrologic Engineering, to reflect new probable maximum flood (PMF) levels and the associated changes.

o Justification: The schedule has been challenged by issues with analysis and calculations, or reference to industry standards (e.g., Federal Energy Regulatory Commission, United States Army Corps of Engineers, and TVA River

34 Operations), that support the UFSAR changes using a factor of safety greater than 1.0 for sliding. The licensee has not resolved dam stability issues associated with these LARs. The LAR cannot be withdrawn since it is tied to a plant confirmatory action.

o Current Age: 65 months Saint Lucie Units 1 & 2 and McGuire Units 1 & 2 - Reactor Vessel Internals (RVI) Aging Management Plan License Renewal Commitment o

Description:

Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guidelines, MRP-227-A, provides a generic program for aging management of pressurized water reactor (PWR) RVI. Many applicants made commitments during the license renewal process to implement the industry program (which became MRP-227-A) when it was completed. During calendar year 2012, the owners of seven PWRs, as part of their license renewal commitments, submitted Aging Management Programs (AMP) consistent with the MRP-227-A guidelines for RVI components and/or inspection plans.

o Justification: Since 2013, considerable progress has been made towards resolving technical issues related to the NRC review of the plant-specific MRP-227-A inspection plans. However, responding to the RAIs related to such items as cold-worked components and core design/fuel management requires review of the fabrication records, which are usually held by the original equipment manufacturer (OEM). There is a backlog of licensee requests for the OEM to provide this information, resulting in delays of several months to a year.

Current Reviews Age (Months)

Saint Lucie Units 1 & 2 29 McGuire Units 1 & 2 2

Palo Verde Units 1, 2 & 3 - Implementation of Next Generation Fuel (NGF) License Amendment Review and Exemption o

Description:

The licensee is requesting exemption from certain requirements of 10 CFR 50.46, Acceptance Criteria for Emergency Core Cooling Systems [ECCS] for Light-Water Nuclear Power Reactors, and 10 CFR Part 50, Appendix K, ECCS Evaluation Models, for the use of Optimized ZIRLOTM cladding.

o Justification: The review is an extensive first-of-a-kind review of the application of several analysis methodologies that have not been previously approved by NRC staff. The verification of the analyses for full cores of NGF, and transition cores of NGF and existing fuel is a significantly time-consuming complex review.

o Current Age: 19 months Columbia Generating Station - Reclassification of Portions of Reactor Water Cleanup System

35 o

Description:

The licensee is requesting approval to revise the Quality Group designation for the piping, valves, pumps, and mechanical modules located in low temperature portions of the reactor water cleanup (RWCU) system, which is located in the radwaste building, from Quality Group C to Quality Group D.

o Justification: No previous boiling-water reactor license amendment precedent exists for this reclassification; therefore, regulatory documentation and a basis from which to review and consider this amendment are not readily available.

Collecting this documentation will take significant effort.

o Current Age: 18 months Seabrook - Alkali-Silica Reaction (ASR) Licensing Basis Amendment o

Description:

The licensee is requesting revising the current licensing basis to adopt a methodology for the analysis of seismic Category I structures with concrete affected by ASR.

o Justification: Seabrook is the first US nuclear facility to exhibit ASR in concrete structures. As such, this LAR is a first-of-a-kind amendment to a plants licensing basis to include the effects of ASR. In addition, the LAR references licensee conducted research to justify an analysis methodology that has never been used before.

o Current Age: 18 months Brunswick Units 1 & 2 - Maximum Extended Load Line Limit Analysis Plus (MELLLA)+ Core Flow Operating Range Expansion o

Description:

The licensee is requesting to revise its technical specifications to allow operation in the MELLLA+ expanded operating domain. This domain increases operating flexibility by allowing control of reactivity at maximum power by changing flow, rather than by control rod insertion and withdrawal.

o Justification: Due to the complexity of the subject, the review involves eight technical branches, and conducting Advisory Committee on Reactor Safeguards (ACRS) subcommittee and full committee meetings. The current proposed schedule for completing the review is approximately 18 to 20 months. The Monticello Nuclear Generating Plant was the first commercial plant to submit an LAR to adopt the MELLLA+ operating domain and required more than 4 years to complete.

Based on the considerations above, the Brunswick MELLLA+ LAR is especially voluminous.

o Current Age: 17 months Shearon Harris Unit 1 - Spent Fuel Pool Criticality Analysis o

Description:

The licensee is requesting to revise the TSs for fuel storage criticality to account for the use of Metamic neutron absorbing spent fuel pool rack inserts and soluble boron for the purpose of criticality control in the Boiling Water Reactor (BWR) storage racks that currently credit Boraflex. This license amendment request is required to resolve a current operable but degraded condition.

o Justification: Precedents have shown that a review related to spent fuel pool criticality analyses is complex. Further, this review is considered a first-of-a-kind due to the unique configuration of the Shearon Harris spent fuel pool (SFP).

36 Specifically, the SFP configuration is the only one in the United States that contains both pressurized water reactor fuel racks and boiling water reactor fuel racks.

o Current Age: 4 months Point Beach Units 1 & 2 - Risk-Informed Approach to Resolve Construction Truss Design Code Non-conformances o

Description:

The licensee is requesting approval of a risk-informed strategy to resolve low risk, legacy design code non-conformances associated with construction trusses in the containment building.

o Justification: Established risk-informed applications follow endorsed guidance for the technical content that needs to be submitted. Such endorsed technical guidance is not available for this first-of-a-kind application and extra review effort is needed to determine the acceptability of the proposed technical approach.

o Current Age: 9 months New Reactors None.

Uranium Recovery None.

13.d Please describe any steps taken to provide transparency into the progress of license amendment reviews, such as publicly available, real-time tracking of the completion of review schedule milestones.

Operating Reactors The routine interactions between licensees/applicants and the NRC project manager provide the same information, and possibly more insights, to a licensee regarding the status of an individual licensing review than would a tracking system. Therefore, the NRC does not consider such a tracking system necessary to facilitate these communications with licensees.

Project managers and licensees have routine communications regarding the status and schedules of licensing actions. During these conversations, the schedules for each licensing action are discussed, including schedule expectations, when to expect requests for additional information, and when to expect the safety evaluation, if approved. In addition, the project managers and their direct supervisors are accessible to the licensees by phone or e-mail if any other issues arise.

The NRC staff will begin publishing monthly performance metrics on the NRC public website in the first quarter of 2018. While metrics do not provide insight into specific licensing amendment reviews, the metrics will provide information on the age of the existing inventory as a whole along with the number of reviews completed. Information will also be provided on average adherence to initial schedules and resource estimates.

37 The NRC continues to refine its licensing process for operating reactors. Through the use of controls and metrics, the staff is currently meeting the Congressionally-reported metrics for the quantity of licensing actions reviewed annually, and the percentage of actions completed within one year. The NRC considers the current performance metrics appropriate to balance efficiency with safety. These measures recognize that schedule performance can be affected by applicant, licensee, or NRC performance, and may need fluidity to account for emerging safety or security issues, or changes in licensee plans.

The NRC has launched several initiatives to focus on leveraging existing licensing processes to enhance efficiency, effectiveness, and predictability as a regulator, while maintaining a continued strong safety focus. For example, an initiative analyzed the issues that caused the backlog in processing amendment requests for reactor licensees, including issues related to the request for information (RAI) process, and provided recommendations to Office of Nuclear Reactor Regulation management regarding enhancements to the licensing review process. Such efforts resulted in reducing the inventory of licensing actions greater than one year old by more than 95 percent over the past years and enabled the staff to maintain this inventory at historically low levels. The staffs continual efforts in this area have significantly improved the NRCs ability to monitor safety reviews and improve predictability.

New Reactors For NRO license amendment reviews, only the final safety evaluation report (FSER) completion date is tracked as a milestone. In the amendment request, the licensee provides a date by which the amendment would need to be issued in order to facilitate the desired construction schedule. Occasionally, the staff works with the licensee to identify an alternate agreed-upon date, which is provided in a supplement or revision to the amendment request. These letters containing the requested or alternate agreed-upon date for the license amendment issuance are publicly available.

Uranium Recovery To ensure transparency in the process of licensing reviews, the NRCs uranium recovery staff provides the status of major licensing actions on the agencys public web page. For minor licensing actions, staff discusses these schedules during phone calls with licensees. In addition, for major licensing action reviews, the uranium recovery staff issues schedule letters at the beginning of each review and subsequent letters are issued, if the schedule changes.

38

14. For decommissioning transition reviews, please provide the following information for the reporting period, including any months previously reported:
a. Size of inventory;
b. The number of items completed in the reporting period;
c. Of the items completed in the reporting period, the number completed within the originally forecasted schedule;
d. The number of items completed within 125 percent of the forecasted schedule;
e. Please identify any unusually complex items omitted from the inventory including:

the age of the item, a brief description of the item, the justification for omitting it from the inventory size and an explanation for any review exceeding its original schedule by 125 percent.

Decommissioning Transition Open Inventory and Closed Reviews Month Open Inventory Total (Note 1)

Closed Reviews Total November 2017 19 1

December 2017 15 4

January 2018 14 1

Note 1: The inventory includes licensing actions and other licensing tasks specifically related to an operating reactor plant transitioning into a decommissioning plant.

Information responsive to #14c-e is included in the response to #13 above.

15. Please provide a list of Technical Specifications Task Force (TSTF) "travelers" under review, including the date filed, the milestone schedule for completing the review, and the estimated date for final agency action. Please provide an explanation for any review exceeding the original schedule by 125 percent.

Traveler Under Review Date Filed Milestone Schedule (Draft SE)

Estimated Completion (Final SE)

TSTF-567, Add Containment Sump TS to Address GSI-191 Issues 03/30/2017 02/02/2018 04/04/2018 TSTF-541. Add Exceptions to Surveillance Requirements When the Safety Function is Being Performed 09/10/2013*

01/31/2019 07/31/2019 TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program 05/10/2017 03/03/2018 05/17/2018 TSTF-565, Clarify the Term Operational Convenience in the LCO 3.0.2 Bases 05/10/2017 04/23/2018 07/31/2018 TSTF-564, Safety Limit MCPR 08/28/2017 05/30/2018 07/31/2018 TSTF-568, "Clarify Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2" 12/19/2017**

TBD TBD TSTF-557, Revision 1, "Spent Fuel Storage Rack Neutron Absorber Monitoring Program" 12/19/2017**

TBD TBD

  • Industry is currently drafting a revision for NRC review following a recent public meeting.

None of the reviews exceeded the original schedule by 125 percent.

39

16. Please describe the actions planned and/or taken to ensure that the TSTF traveler process achieves the regulatory efficiencies that were initially projected. Please include progress reports with regard to any TSTF travelers adopted by the industry.

Industry, through the TSTF, proposes changes to the Standard Technical Specifications (STS) via a traveler submitted for NRC review and approval. The traveler process was collaboratively developed between NRC and the nuclear industry 20 years ago as a means to revise the STS to gain regulatory efficiencies and enhance safety. Since then, the NRC has approved over 340 travelers, and has a mature process for review and approval of plant-specific license amendment requests to adopt approved STS changes.

Over the last several years NRC introduced two enhancements to the traveler review process:

(1) increased transparency and documentation through publication of safety evaluations; and (2) ensuring that all appropriate technical branches are involved early and working as a team to ensure consistency. More recently, NRC and the TSTF adopted two additional best practices to make reviews more efficient and effective: (1) establishing teams of reviewers who develop expertise on a given traveler; and (2) leveraging the staff expertise on a particular traveler through timely submission of plant specific requests for adoption. The NRC is seeing early successes from these enhancements in the reviews of licensees adoption of TSTF-542, Reactor Pressure Vessel Water Inventory Control. Average review times for recent traveler adoptions have dropped to 10 months, in part as a result of these above efficiencies.

The NRC will continue working with the TSTF to make improvements to the STS. In recent years, requested changes from industry have become more complex (e.g., risk-informed STS changes). To ensure the traveler process achieves the regulatory efficiencies that were initially intended, and to align on priorities, the NRC holds quarterly public meetings and monthly status calls with the TSTF. Additionally, the status of travelers is discussed by both NRC and industry senior management at the quarterly Regulatory Issues Task Force meeting.

In 2017, two travelers were approved by the NRC. Currently seven travelers are under review by the NRC staff. The latest status report of travelers currently under review is available (ADAMS Accession No. ML17317A424).

17. For each ongoing license renewal review, please provide the date each application was filed, the duration of the review, the original milestone schedule based on 22 months for uncontested applications and 30 months for contested applications, the actual completion dates for milestones, and the scheduled date for completion of the review. Please provide an explanation for any review exceeding the original schedule by 125 percent.

Indian Point 2&3 Application Review Time from Acceptance Review Date (Months) 125 Milestone Original Schedule Current Schedule Completion Date License Renewal Application Receipt 04/30/2007 04/30/2007 Publish FRN-Acceptance/rejection and opportunity for hearing 08/01/2007 08/01/2007 Public Meeting - Environmental Scoping 09/19/2007 09/19/2007 Issue draft Supplemental Environmental Impact Statement (SEIS) 07/25/2008 12/22/2008 Issue SER with open items 09/05/2008 01/15/2009 1st ACRS Subcommittee meeting 10/2008 03/18/2009

40 Indian Point 2&3 Application Review Time from Acceptance Review Date (Months) 125 Milestone Original Schedule Current Schedule Completion Date Issue final SER 03/27/2009 08/11/2009 ACRS Full Committee meeting 05/2009 09/10/2009 Issue final SEIS 04/03/2009 12/03/2010 1st Supplement to SER N/A*

08/30/2011 Issue Draft 1st Supplement to final SEIS N/A*

06/26/2012 Issue Final 1st Supplement to final SEIS N/A*

06/13/2013 FRN - Notice of Intent to Prepare Supplemental Environmental Impact Statement N/A*

09/04/2014 2nd ACRS Subcommittee meeting N/A*

04/23/2015 Issue 2nd Supplement to SER N/A*

07/07/2015 Issue Draft 2nd Supplement to final SEIS N/A*

01/2016 12/22/2015 End of Comment Period for Draft 2nd Supplement to final supplemental environmental impact statement (FSEIS)

N/A*

03/2016 03/04/2016 Issue Final 2nd Supplement to FSEIS N/A*

03/2018 Issue 3rd Supplement to SER N/A*

04/2018 Decision-Director, NRR (no hearing) 07/2009 09/2018 Commission decision (if hearing is granted)

TBD N/A

  • The NRC did not issue an official schedule for the first supplement to the final SEIS.

The Indian Point License Renewal Application schedule letters are publicly available in ADAMS at Accession Nos. ML071900365, ML080230115, ML081000441, ML082400214, ML100110063, ML101260536, ML102300092, ML14254A207, ML15147A199 and ML16153A351.

The delays in the review of the Indian Point application were associated with complex adjudicatory issues, audits, reviews of substantial new information submitted by the licensee, review of the severe accident mitigation alternatives (SAMA) analyses and review of extensive public comments on NRC staff environmental review documents. In 2012, the issuance of renewed licenses was suspended pending completion of the continued storage rulemaking; the licensing reviews continued to move forward. On August 26, 2014, the Continued Storage rule was approved and the Commission lifted the suspension on issuing renewed licenses. The parties to the legal proceedings reached an agreement that resulted in the withdrawal of all contentions on the license renewal application. Thus on March 13, 2017, all pending adjudicatory actions were voluntarily dismissed. A decision regarding the renewal of the operating licenses for both units is expected to be issued in the 4th quarter of FY 2018.

Diablo Canyon 1 & 2 Application Review Time from Acceptance Review Date (Months) 77 Milestone Original Schedule Completion Date License Renewal Application Receipt 11/23/2009 11/23/2009 Publish FRN-Acceptance/rejection and opportunity for hearing 01/21/2010 01/21/2010 Public Meeting-Environmental Scoping meeting 03/03/2010 03/03/2010 Deadline for filing hearing requests and petitions for intervention 03/22/2010 03/22/2010 Issue draft SEIS 10/15/2010 Issue SER with Open Items 12/10/2010 01/10/2011

41 Diablo Canyon 1 & 2 Application Review Time from Acceptance Review Date (Months) 77 Milestone Original Schedule Completion Date ACRS Subcommittee meeting 02/2011 02/09/2011 Request by applicant for delay in final processing of the license renewal review 04/10/2011 Issue final SER 05/23/2011 06/02/2011 ACRS Full Committee meeting 07/2011 Issue final SEIS 08/12/2011 NRR Director Decision (no hearing) 09/26/2011 Commission Decision (if hearing is granted) 05/25/2012 NRC Letter to Pacific Gas and Electric (PG&E) regarding information to be submitted if the license renewal review process where to restart 05/02/2014 PG&E letter to NRC to inform that PG&E will provide some information in December 2014 and will coordinate with NRC later to discuss a schedule for providing additional information.

06/04/2014 PG&E submitted an annual update for the license renewal application 12/22/2014 PG&E submits a revised Environmental Report 02/25/2015 Publish FRN-of Notice of Intent to reinitiate the Scoping Process and Prepare an Environmental Impact Statement 07/2015 07/2015 Public Meeting-Environmental Scoping meeting 08/2015 08/05/2015 PG&E letter to NRC request to suspend NRC review 06/21/2016 NRC letter to PG&E, response to request to suspend license renewal application review 07/18/2016 Following the California Public Utility Commission decision on the PG&E Diablo Canyon closure proposal (issued 1/11/18), PG&E will notify the NRC Early 2018 The Diablo Canyon license renewal application schedule letters are publicly available in ADAMS at Accession Nos. ML093631560, ML102700490, ML110140904, ML11138A315, ML15104A509, and ML16193A599.

In October 2010, the schedule was updated to allow the staff additional time to complete a thorough review of the SAMA analyses and of the effects to marine ecology. In April 2011, PG&E requested the deferral of a final decision on the license renewal application until seismic studies were completed. In 2012, the issuance of renewed licenses was suspended pending completion of the continued storage rulemaking. On August 26, 2014, the Continued Storage rule was approved and the Commission lifted the suspension on issuing renewed licenses. The NRC staff resumed the review after PG&E submitted the annual update for the application in December 2014. Subsequently in June 2016, PG&E requested the NRC suspend the review and also requested approval from the California Public Utilities Commission (CPUC) not to proceed with license renewal. In July 2016, the NRC suspended the license renewal review.

The CPUC held a public meeting on January 11, 2018, where the CPUC approved PG&Es proposal to close Diablo Canyon in 2025. PG&E is expected to provide an update on its plans regarding withdrawal of the license renewal application; however, PG&E has not yet informed NRC of the projected submittal date.

42 Seabrook 1 Application Review Time from Acceptance Review Date (Months) 90 Milestone Original Schedule Current Schedule Completion Date License Renewal Application Receipt 06/01/2010 06/01/2010 Publish FRN-Acceptance/rejection and opportunity for hearing 07/23/2010 07/21/2010 Public Meeting-Environmental Scoping meeting 08/19/2010 08/19/2010 Deadline for filing hearing requests and petitions for intervention 09/21/2010 10/20/2010 Issue draft SEIS 05/13/11 08/01/2011 Issue SER with open items 07/2011 06/08/2012 1st ACRS Subcommittee meeting 09/2011 07/10/2012 Issue 2nd draft SEIS 12/2012 04/22/2013 Issue final SEIS 01/07/2012 07/29/2015 2nd ACRS Subcommittee meeting N/A Issue final SER 01/2012 ACRS full committee meeting 02/2012 NRR Director Decision (no hearing) 04/02/2012 04/2019 Commission Decision (if hearing is granted) 12/03/2012 NA The Seabrook LRA schedule letters are publicly available in ADAMS at Accession Nos.

ML101690417, ML110890319, ML11178A365, ML12074A096, ML12109A427, ML12352A075, ML13298A091, ML14148A218, ML14223B144, ML15041A449, ML15107A300, ML15293A157 and ML16074A246.

In 2011, the Seabrook schedule was updated to ensure that the applicant properly addressed SAMA analysis and technical issues related to the alkali silica reaction (ASR) of concrete. In 2012, subsequent to the NRC staff issuing the draft SEIS, the applicant made significant changes to the SAMA. Additional, in 2012, the issuance of new licenses was suspended pending completion of the Continued Storage rulemaking; the licensing reviews continued to move forward. The second draft SEIS was issued in April 2013 and in August 2013 an agreement regarding a contention associated with the SEIS was reached. On August 26, 2014, the Continued Storage rule was approved and the Commission lifted the suspension on issuing renewed licenses. The NRC staff issued the final SEIS in 2015.

In August 2016, NextEra submitted a LAR to the current license to adopt a methodology for the analysis of seismic Category I structures with concrete affected by ASR. This methodology is the basis for the aging management program being evaluated for the license renewal application review. On October 6, 2017, the ASLB admitted a contention on the ASR LAR.

After the NRC staff completes safety evaluation of the ASR LAR, the ASLB hearing will be held and the ACRS will also perform its review. The review of this amendment has a direct impact on the schedule for the license renewal review and a decision on the license renewal is currently projected to be made by April 2019.

Waterford 3 Application Review Time from Acceptance Review Date (Months) 19 Milestone Original Schedule Current Schedule Completion Date License Renewal Application Receipt 03/23/2016 03/23/2016

43 Waterford 3 Application Review Time from Acceptance Review Date (Months) 19 Milestone Original Schedule Current Schedule Completion Date Publish FRN-Acceptance/rejection and opportunity for hearing 05/20/2016 05/20/2016 Public Meeting-Environmental Scoping meeting 06/08/2016 06/08/2016 Deadline for filing hearing requests and petitions for intervention 08/01/2016 08/01/2016 Issue draft SEIS 05/2017 02/2018 Issue SER with open-items 06/2017 09/2018 ACRS Subcommittee meeting 07/2017 10/2018 Issue final SEIS 03/2018 05/2018 Issue final SER 01/2018 03/2019 ACRS full committee meeting 03/2018 04/2019 NRR Director Decision (no hearing) 04/2018 06/2019 Commission Decision (if hearing is granted)

TBD N/A The Waterford License Renewal Application schedule letters are publicly available in ADAMS at Accession Nos. ML16130A023 and ML17131A194.

The NRC staff continues work on the Waterford safety and environmental reviews. The applicant submitted an LAR in November 2017 that requests approval of their plant-specific neutron fluence methodology that is applied to the reactor vessel neutron fluence embrittlement analysis referred to in the license renewal application. The LAR acceptance review has been completed and the NRC staff safety review is currently underway. The review of the LAR is estimated to take approximately 1 year. The license renewal application fluence methodology review is dependent on the approval of the LAR. Therefore, the decision regarding the renewal of the operating license is expected to be issued in 3rd quarter of FY 2019.

River Bend Application Review Time from Acceptance Review Date (Months) 5 Milestone Original Schedule Completion Date License Renewal Application Receipt 05/31/2017 05/31/2017 Publish FRN-Acceptance/rejection and opportunity for hearing 08/2017 08/17/2017 Public Meeting-Environmental Scoping meeting 09/2017 09/19/2017 Deadline for filing hearing requests and petitions for intervention 10/2017 10/13/2017 Issue draft SEIS 04/2018 Issue final SER 07/2018 ACRS Subcommittee meeting 10/2018 Issue final SEIS 11/2018 ACRS full committee meeting 12/2018 NRR Director Decision (no hearing) 02/2019 Commission Decision (if hearing is granted)

TBD

44 The River Bend license renewal application review schedule is available in ADAMS at Accession No. ML17187A035.

18. Please provide the status of ongoing license renewal reviews.

Applicant Application Accepted for Review Review Status for Long-Term Application Reviews Indian Point 2&3 08/01/2007 The NRC staff has addressed the public comments received on its draft second supplement to the FSEIS, which was issued for comment in December 2015. The staffs response to the public comments will be documented in the FSEIS supplement, which is currently under final review. The initial SER was issued in November 2009, with supplements issued in August 2011 and July 2015. A third SER supplement will be issued in the second quarter of FY 2018 to address new information received by the staff concerning safety issues. In January 2017, the parties to the legal proceedings reached an agreement that resulted in the withdrawal of all contentions on the license renewal application. Under the agreement, Units 2 & 3 will cease operations in April 2020 and 2021, respectively, with possible extensions to operate until April 2024 and 2025, respectively. On February 8, 2017, the State of New York Department of Environmental Conservation (NYDEC) and Riverkeeper filed an unopposed motion to the ASLB to withdraw their contentions and terminate the adjudicatory proceeding. The Licensing Board granted that motion and terminated the adjudicatory proceeding on March 13, 2017. Recently the National Marine Fisheries Service (NMFS) designated critical habitat in the Hudson River for Atlantic Sturgeon. Ongoing interactions between the NRC staff, NMFS, NYDEC, and Entergy regarding this new designation and Entergys monitoring plan for sturgeon are expected to be completed in the second quarter of FY 2018. Resolution of this issue will be documented in the Record of Decision issued in conjunction with the renewed operating licenses for the units. A decision on the renewed operating licenses for both units is expected to be issued in the 4th quarter of FY 2018.

Diablo Canyon 1&2 01/21/2010 In June 2016, Pacific Gas and Electric requested a suspension of the license renewal review to allow it to seek approval from the CPUC of an agreement in principle not to proceed with license renewal for Diablo Canyon. In July 2016, the NRC suspended the license renewal review. The CPUC held a public meeting on January 11, 2018, during which it approved PG&Es proposal to close Diablo Canyon in 2025. PG&E is expected to provide an update on its plans regarding withdrawal of the license renewal application; however, PG&E has not yet provided a projected submittal date.

45 Applicant Application Accepted for Review Review Status for Long-Term Application Reviews Seabrook 1 07/21/2010 The NRC staff continues discussions with NextEra to ensure that technical issues related to the ASR open item in the SER are properly addressed. In August 2016, NextEra submitted a LAR to the current license to adopt a methodology for the analysis of seismic Category I structures with concrete affected by ASR. This methodology is the basis for the aging management program being evaluated under the license renewal application review. On October 6, 2017, the ASLB admitted a contention on the ASR LAR.

The review of this amendment has a direct impact on the schedule for the license renewal review. A decision on the license renewal, is currently projected to be made by April 2019.

Waterford 05/31/2016 The NRC staff continues their safety and environmental reviews, including the resolution of specific questions regarding the Waterford neutron fluence time-limited aging analysis. The applicant submitted a LAR in November 2017 that will request approval of their plant-specific neutron fluence methodology which is applied to the reactor vessel neutron fluence embrittlement analysis referred to in the license renewal application. The acceptance review of this LAR has been completed and NRC staff safety review is currently underway.

The review of the LAR is estimated to take approximately 1 year.

The license renewal application fluence methodology review is dependent on the approval of the LAR. Therefore, the decision on the renewed operating license is expected to be issued in the 3rd quarter of FY 2019.

River Bend 08/07/2017 The staff continues the safety and environmental reviews, which are expected to take approximately 18 months. The staff has completed its Operating Experience, Scoping and Screening, and Aging Management Program audits. The staff is in the process of issuing requests for additional information and drafting the SER.

A petition to intervene and request for hearing was filed in connection with this proceeding. The ASLB ruled the petitioners contentions inadmissible and denied the petition in January 2018; the Board's decision is subject to appeal before the Commission.

Turkey Point 3&4 1/30/2018 On January 30, 2018, Florida Power & Light Company submitted the first subsequent license renewal application for the Turkey Point Nuclear Generating Units 3 and 4. The NRC staff is currently performing a proprietary determination in accordance with 10 CFR 2.390. Once the proprietary determination is completed, the NRC staff will perform an acceptance review for docketing in accordance with the requirements of 10 CFR 2.101. Should the NRC staff determine that the application is acceptable for docketing, the NRC staff will issue the application review schedule.

46

19. Please provide the status of the NRCs readiness to review applications for Subsequent License Renewal (SLR).

In August 2014, the Commission affirmed that no revisions to either the safety or environmental regulations are needed to support the assessment of a SLR application. However, the Commission directed the staff to update license renewal guidance, as needed, to provide additional clarity on the implementation of the license renewal regulatory framework. The main guidance documents for initial license renewal are:

Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants (SRP-LR), Revision 2; Generic Aging Lessons Learned (GALL) Report, Revision 2; and Standard Review Plan for Environmental Reviews for Nuclear Power Plants, Supplement 1:

Operating License Renewal (Revision 1).

The guidance in these documents is based on plant operation up to 60 years. The staff evaluated this guidance to determine what, if any, revisions were necessary to address issues for plant operations up to 80 years under SLR. The staff determined that no revisions were needed to the NRC guidance document entitled, Standard Review Plans for Environmental Reviews for Nuclear Power Plants, to support environmental reviews from 60 to 80 years.

However, the staff determined that the GALL Report and the SRP-LR should be updated to facilitate more effective and efficient reviews of SLR applications.

On July 14, 2017, the NRC published Generic Aging Lessons Learned for Subsequent License Renewal (GALL-SLR) Report (NUREG-2191, Volumes 1 and 2), and Standard Review Plan for Review of Subsequent License Renewal Applications for Nuclear Power Plants (SRP-SLR)

(NUREG-2192). On December 29, 2017, the NRC staff published NUREG-2221, Technical Bases for Changes in the Subsequent License Renewal Guidance Documents NUREG-2191 and NUREG-2192, and NUREG-2222, Disposition of Public Comments on the Draft Subsequent License Renewal Guidance Documents NUREG-2191 and NUREG-2192.

On November 6, 2015, Dominion Virginia Power notified the NRC of its intent to submit an SLR application in the first quarter of 2019 for Surry Power Station. On June 7, 2016, Exelon Generation Company, LLC notified the NRC of its intent to submit an application for Peach Bottom Atomic Power Station in the third quarter of 2018. On November 9, 2017, Dominion Energy Virginia notified the NRC of its intent to pursue subsequent license renewal for North Anna Power Station Units 1 and 2 in the 4th quarter of 2020.

On December 20, 2017, the staff issued a letter to NEI providing interim approval for use of guidance documents NEI 17-01, Industry Guideline for Implementing the Requirements of 10 CFR Part 54 for Subsequent License Renewal [SLR], and NEI 17-04, Model SLR New and Significant Assessment Approach for SAMA, Revision 0. These documents will provide interim guidance to licensees that have notified the NRC of their intent to submit SLR applications while formal NRC endorsement of the NEI guidance document is considered. The NRC expects that issuance of formal revisions to Regulatory Guides 1.188, Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses, and 4.2, Preparation of Environmental Reports for Nuclear Power Plant License Renewal Applications, by December 31, 2019, will supersede the interim guidance.

47

20. Once Subsequent License Renewal reviews begin, please report progress similarly to current license renewal reviews, including: the date each application was filed, the duration of the review, the original milestone schedule based on an 18-month review, the actual completion dates for milestones, and the scheduled date for completion of the review.

By letter dated January 30, 2018, Florida Power & Light Company submitted an application for subsequent renewal for the operating license for Turkey Point Nuclear Generating Units 3 and 4 to the NRC. The NRC staff is currently performing a proprietary determination in accordance with the regulations (10 CFR 2.390). Once the proprietary determination is completed, the NRC staff will perform an acceptance review for docketing in accordance with the requirements of 10 CFR 2.101. Should the NRC staff determine that the application is acceptable for docketing, the NRC staff will issue the application review schedule.

21. For each ongoing power uprate review, please provide:
a. The date the application was filed;
b. The duration of the review;
c. The original milestone schedule;
d. The actual completion dates for the milestones; and
e. The scheduled date for completion of the review based on the metrics in SECY-13-0070.

Plant Name Uprate Type (Note 1)

Date Filed Planned Issue Date Actual Issue Date Planned Review Duration (Months)

(Note 2)

Actual Review Duration (Months)

Notes Hope Creek Generating Station MUR 07/12/17 04/30/18 9

Note 1: MUR = measurement uncertainty recapture power uprate EPU = extended power uprate Note 2: For licensing actions, with an application date of October 1, 2016, or later, the duration of the review of the licensing action will be measured starting when the acceptance review is complete.

22. Please provide a brief status of power uprate application reviews.

The NRC staff is reviewing one power uprate application. The Hope Creek Generating Station measurement uncertainty recapture uprate application was accepted for review on August 9, 2017. The staff is currently performing a safety evaluation of the application.

23. Please provide the following information below regarding Requests for Additional Information (RAI) issued by each of the following offices: Nuclear Reactor Regulation, New Reactors, Nuclear Security and Incident Response, Uranium Recovery, and Decommissioning. The number of RAIs includes the total number of questions or requests contained in a letter or email. For example, if a letter requests five items, the number of RAIs is five. For each office and for the period being reported, please provide:
a. Number of RAIs issued;
b. The number of RAIs issued prior to preparation of a draft safety evaluation with open items;
c. The number of RAIs issued in an additional round, subsequent to previous RAIs, in specific technical area or by a technical branch;

48

d. The percentage of RAI responses provided by licensees within 30 days of the date mutually agreed upon;
e. The number of RAIs prepared or responses reviewed by contractors; and
f.

The number of RAIs prepared or responses reviewed by NRC staff.

g. Once sufficient date becomes available please provide 12-month rolling average number of RAIs issued by each office.

NOTE: Information for the Office of Nuclear Security and Incident Response is included within each of the other entities or programs reporting below.

49 Office of Nuclear Reactor Regulation Month/Year Number of RAIs Issued Number of RAIs Issued Prior to the Preparation of a Draft Safety Evaluation with Open Items Number of RAIs Issued in an Additional

Round, Subsequent to Previous RAI's in Specific Technical Area or by a Technical Branch The Percentage of RAI Responses Provided by Licensees within 30 Days or the Date Mutually Agreed Upon The Number of RAIs prepared by NRC staff The Number of RAI Responses Reviewed by NRC Staff 12 Month Rolling
Average, Number of RAIs Issued by Each Office Jan 2018 205 Note 1 1

83%

205 Note 2 168 Note 3 Note 1:

The database systems do not have readily available information that distinguishes between item 23a and 23b. Accurately compiling the number of RAI questions issued prior to preparation of a draft safety evaluation with open items would require extensive manual document searches and analysis to cover the significant volume of project reviews. The count of RAIs is presented collectively under Item 23a.

Note 2:

The NRC employs contractors to supplement the staff in selected critical skill areas; however, all RAIs identified by contractors are evaluated by NRC staff to verify that they are necessary to support a regulatory finding. If the RAIs are necessary, they are formally prepared and issued by NRC staff. The NRC does not track the number of draft RAIs prepared by contractors. In addition, the NRC staff is responsible for making the final determination on the acceptability of all RAI responses.

Note 3:

A 12-month rolling average will not be available until November 2018.

50 Office of New Reactors Project Name Number of RAIs Issued in January 2018 Number of RAIs Issued Prior to Preparation of a Draft SER with Open Items in January 2018 Number of RAIs Issued in an Additional Round, Subsequent to Previous RAIs, in Specific Technical Area or by Technical Branch in January 2018 (Note 1)

Percentage of RAIs Responses Provided by the Applicant/Licensee within 30 Days or the Date Mutually Agreed Upon in January 2018 Number of RAIs Prepared or Responses Reviewed by Contractors in January 2018 (Note 2)

Number of RAIs Prepared or Responses Reviewed by NRC Staff in January 2018 (Note 2) 12-Month Rolling Average (Note 3)

APR1400 Design Certification (DC) 0 0

N/A 0%

0 0

N/A U.S. Advanced Pressurized Water Reactor (US-APWR) DC 1

0 N/A N/A 0

1 N/A Advanced Boiling Water Reactor (ABWR) DC Renewal (General Electric Hitachi (GEH))

0 0

N/A N/A 0

0 N/A Clinch River Early Site Permit (ESP) 0 0

N/A N/A 0

0 N/A NuScale Small Modular Reactor (SMR)

DC 76 76 N/A 39%

0 76 N/A NuScale Topical Reports 2

2 N/A 46%

0 2

N/A

51 Project Name Number of RAIs Issued in January 2018 Number of RAIs Issued Prior to Preparation of a Draft SER with Open Items in January 2018 Number of RAIs Issued in an Additional Round, Subsequent to Previous RAIs, in Specific Technical Area or by Technical Branch in January 2018 (Note 1)

Percentage of RAIs Responses Provided by the Applicant/Licensee within 30 Days or the Date Mutually Agreed Upon in January 2018 Number of RAIs Prepared or Responses Reviewed by Contractors in January 2018 (Note 2)

Number of RAIs Prepared or Responses Reviewed by NRC Staff in January 2018 (Note 2) 12-Month Rolling Average (Note 3)

Vogtle LARs 11 11 N/A 100%

0 11 N/A Note 1: NRO does not currently have an electronic system to track how many RAIs are issued in an additional round as a subsequent RAI to a previous RAI issued. To develop this capability within the current electronic system used to track RAIs would be labor and resource intensive.

Note 2: The NRC employs contractors to supplement the staff in selected critical skill areas; however, all RAIs identified by contractors are evaluated by NRC staff to verify that they are necessary to support a regulatory finding. If the RAIs are necessary, they are formally prepared and issued by NRC staff. The NRC does not track the number of draft RAIs prepared by contractors. In addition, the NRC staff is responsible for making the final determination on the acceptability of all RAI responses.

Note 3: A 12-month rolling average will not be available until November 2018.

52 Office of Nuclear Material Safety and Safeguards Uranium Recovery Month/Year Number of RAIs Issued Number of RAIs Issued Prior to the Preparation of a Draft Safety Evaluation with Open Items Number of RAIs Issued in an Additional

Round, Subsequent to Previous RAIs in Specific Technical Area or by a Technical Branch The Percentage of RAI Responses Provided by Licensees within 30 Days or the Date Mutually Agreed Upon The Number of RAIs prepared by Contractors The Number of RAI Responses Reviewed by Contractors The Number of RAIs prepared by NRC staff The Number of RAI Responses Reviewed by NRC Staff 12 Month Rolling
Average, Number of RAIs Issued by Each Office Jan 2018 1

1 0

N/A 0

0 1

0 N/A

53 Reactor Decommissioning Month/Year Number of RAIs Issued Number of RAIs Issued Prior to the Preparation of a Draft Safety Evaluation with Open Items Number of RAIs Issued in an Additional

Round, Subsequent to Previous RAIs in Specific Technical Area or by a Technical Branch The Percentage of RAI Responses Provided by Licensees within 30 Days or the Date Mutually Agreed Upon The Number of RAIs prepared by Contractors The Number of RAI Responses Reviewed by Contractors The Number of RAIs prepared by NRC staff The Number of RAI Responses Reviewed by NRC Staff 12 Month Rolling
Average, Number of RAIs Issued by Each Office Jan 2018 8

0 8

0 0

0 8

9 N/A

54

24. Please provide the status of specific actions taken or planned to ensure greater discipline, management oversight, and transparency in the use of the RAI process and to limit RAIs to those necessary for making regulatory decisions. The description should include:

management oversight and accountability, the training necessary to provide consistency and sustainable improvement across the applicable program business lines, efforts to establish consistent procedures in relevant offices, and any gaps or trends identified by management or through internal reviews including periodic internal RAI audits.

Efforts to establish consistent procedures throughout the agency are being initiated by the establishment of a working group to align, where appropriate, licensing strategies across the agency including the RAI process. This effort, which is in the initial stages, will include representatives from NMSS, NRR, NRO, the Office of Nuclear Security and Incident Response (NSIR), and the OGC.

NRR Activities NRR made great strides in reducing the backlog of licensing actions by reducing the inventory of licensing actions greater than one year old from 139 in September 2014, to 11 in October 2017. Through the use of strict controls and metrics, this inventory remains below 15 at any given time. This improvement has been possible, in large part, due to the office specific RAI-related improvements implemented over the last several years.

NRR launched several initiatives and to focus on leveraging or revising existing licensing processes to enhance agency efficiency, effectiveness, and predictability, while maintaining a continued strong safety focus. These initiatives have analyzed the issues that caused the previous licensing action backlog, including the RAI process, and recommended enhancements to the licensing review process. NRR management issued interim guidance to the staff in January 2015, and updated interim guidance in April 2016, providing expectations to help enhance consistency of the licensing review process, sound decision-making, and discipline of schedule. In January 2017, this interim guidance was incorporated into NRR procedures.

Some of the key items that have added discipline and management oversight to the RAI process include the following:

NRR staff review of an application will be limited to the scope of the licensing action and RAIs should only request information that is required to make a safety determination.

At the point when RAIs are transmitted from the technical staff to the NRR project manager, the technical staff is expected to have developed a draft safety evaluation (SE). In addition to ensuring that the RAIs contain a sound technical and regulatory basis, the technical staff should be able to correlate each RAI to a hole in the draft SE that the licensee response is expected to fill.

Prior to sending a second (and any subsequent) round of RAIs in a specific technical area, NRR division-level management will apply additional oversight to discuss the need for the RAIs and whether alternative methods, such as a public meeting or audit, may be more effective and efficient for obtaining the necessary information.

NRR project managers track licensee timeliness and adherence to RAI response schedules. Any significant delays in licensee responses will be brought to NRR management attention.

Training sessions were held with the technical and project management staff on RAI quality and the RAI process. Following the issuance of the finalized NRR guidance in this area in January 2017, online training was developed and provided to the NRR staff. This training covered expectations regarding added discipline and management oversight of the RAI process.

55 Other actions that provide a stable and sustainable improvement in the RAI process and add accountability to the process include the following:

In November 2014, NRR management began holding periodic meetings to discuss open licensing actions, develop alignment on the best approaches for completing those actions, and monitor licensing performance.

In October 2016, NRR replaced the existing software used to manage and monitor licensing reviews with a newly developed software package called the Reactor Program System - Licensing/Workload Management software. This system has the capability to better track RAI issuance and status.

NRR performed an internal audit of a sample of RAIs issued between April and December 2016 and found that the overall adherence to quality, timeliness, and process expectations was satisfactory. The audit team identified areas for continued improvement and recommended increased staff training on the RAI guidance, development of staff job aids, and consideration of modifications to staff guidance to better reflect the reactor license renewal and non-power utilization facilities licensing processes.

On January 2, 2018, in response to the recommendations from the internal audit, NRR management issued a tasking memorandum to the staff with four specific actions to address the audit findings: (1) provide mandatory RAI refresher training for applicable NRR, NSIR, and NRO staff and branch chiefs, (2) evaluate existing RAI job aid for applications to other divisions, (3) formalize use of NRR guidance, as applicable, for reactor license renewal and non-power utilization facilities, and (4) conduct subsequent RAI quality reviews. By the end of January 2018, three refresher training sessions were held for branch chiefs.

NRO Activities NRO has taken several steps to ensure that its RAIs are consistently of high quality and are necessary to make a safety finding. In 2016, senior managers in NRO undertook initiatives to examine licensing activities with a goal of promoting a continued strong safety focus, consistency, efficiency, and clarity in our reviews of new reactor licensing applications. These initiatives included revising the RAI process to promote the consistent generation of high quality RAIs.

In October 2016, the NRO RAI process was revised (ADAMS Accession No. ML16280A389) to include a new quality check audit process where, in addition to the technical branchs supervisor, the division management of both the technical and project management organizations review an RAI before it is issued to the applicant or licensee. In addition, the NRO Office Director reviews a sample of RAIs to keep abreast of high-priority issues identified in reviews and to support NROs emphasis on effectiveness and efficiency as it focuses on safety, security, and environmentally significant matters.

On October 7, 2016, the NRO Office Director issued a memorandum titled Effective Use of Request for Additional Information, Audit, and Confirmatory Analysis in New Reactor Licensing Review, to all NRO staff, which emphasized the goals of the RAI process, described the revised process, and included a job aid that contains best practices for preparing RAIs.

The staff has incorporated many lessons-learned into its review of the active DC and ESP applications. The 2016 initiative to improve the focus of RAIs has improved the quality and safety focus of these requests. The staff is also using the regulatory audit tool earlier in the process to better inform the staff about the bases supporting the applications and therefore,

56 better focus the staffs RAIs on information that directly relates to the staff reaching safety findings.

The staff is currently conducting an audit to assess the effectiveness of the revised NRO RAI process. The audit is expected to evaluate whether the revised RAI process has yielded tangible improvements to NROs licensing process; and if the revised RAI process should be maintained, modified or eliminated.

NMSS Activities In NMSS, internal guidance for uranium recovery and waste program reviews includes the expectation that RAIs will be developed in conjunction with the draft SER to ensure that each RAI is necessary to reach a safety finding. In addition, the guidance contains the expectation to include a reference in the RAI to the specific relevant requirement and encourages staff to conduct telephone conferences with licensees and applicants to efficiently resolve technical issues on RAIs. The NRC staff recently finalized an internal self-assessment that identifies possible efficiency improvements within the Uranium Recovery Program. The self-assessment includes recommendations for improving the efficiency of the RAI process, such as issuing RAIs as they are written rather than as a group, and reemphasizing the expectation that staff develop the draft safety evaluation and RAIs in concert.

NMSS is also in the process of studying RAI approaches used by other offices at the NRC, developing office procedures, revising guidance, and evaluating the development of job aids to incorporate applicable RAI approaches from other NRC branches, divisions and offices.

Following completion of this effort, NMSS will develop a training plan, as needed, to implement the resulting RAI process products.

In addition, NMSS is revising NUREG-1556, Volume 20, Guidance about Administrative Licensing Procedures. Information in this NUREG regarding requests for additional information for materials licensing actions is being updated to improve consistency and management oversight between NRC headquarters and regional materials licensing staff.

In August 2016, NMSSs Division of Spent Fuel Management (DSFM) issued Division Instruction (DI) 26, DSFM-26, Rev., 0, which provided management expectations and guidance to employees with regard to meeting division and business line goals of being an independent, transparent, and effective regulator. In DSFM-26, management has specifically indicated that DSFMs goal is one round of RAIs for a typical review and a maximum of two rounds of RAIs. RAIs and the applicants responses need to converge on the information needed for making a regulatory finding. As part of the management oversight process, the staff has been seeking concurrence by the division-level management, in-addition to branch-level, when a second round of RAIs is being considered during the review of an application. In addition, the staff has developed further guidance on preparing RAIs that are clear, complete, and specific with respect to the requested information, the justification for the request, and the associated regulatory basis. This guidance has been discussed with all the reviewers as part of continuous training, supplemented by a desk guide and a quick reference card. The division also is of preparing for a self-assessment on RAIs during FY 2018 - FY 2019 time frame.

The Division of Fuel Cycle Safety, Safeguards, and Environmental Review (FCSE) conducted a review of the FCSE RAI process during the second quarter of FY 2017. Staff reviewed audit reports from the NRCs Office of the Inspector General (OIG) and the U.S. Government Accountability Office (GAO) Statement of Facts (GAO Job Code 100910). The NRC staff assessment report is at ADAMS Accession Number ML17102A783. The NRC staff also reviewed the internal policies and interviewed subject matter experts in the Office of Nuclear

57 Reactor Regulation, the Office of New Reactors, and the Office of Nuclear Material Safety and Safeguards. The results of this assessment, including staffs recommendations and proposed actions for implementing recommended improvements, were documented in a report to FCSE management on May 25, 2017. The report proposed revisions to the FCSE Licensing Review Handbook, including:

Periodically reinforcing expectations of key aspects in the RAI process during licensing seminars or division meetings; Promoting a more consistent and uniform use and application of the guidance, particularly following the instructions on interactions with the licensee, drafting the safety evaluation report as a tool to identify any RAIs, having a sound regulatory basis for the RAIs, and maintaining licensing reviews aligned with its scope; The addition of clear instructions specifying that RAIs should not request information available elsewhere; and Continuing with current management oversight practice for RAIs process, such as elevating any challenges encountered during the RAI process to Division management for their awareness and involvement.

Based on recommendations, FCSE has conducted 2 licensing seminars on RAIs for Project Managers and Technical Reviewers, as well as a team meeting for those involved in the license renewal application review for Honeywell International. Tasks for updates to the guidance are scheduled for completion by the end of September 2018.

No adverse findings were identified in the Final GAO Report GAO-17-344, U.S. Nuclear Regulatory Commission: Efforts Intended to Improve Procedures for Requesting Additional Information for Licensing Action are Underway, dated May 25, 2017.

Efforts to establish consistent procedures throughout the agency are being initiated by the establishment of a working group to align, where appropriate, licensing strategies across the agency including the RAI process. This effort, which is in the initial stages, will include representatives from NMSS, NRR, NRO, NSIR, and OGC.

25. In keeping with the Commissions policy statement on the use of probabilistic risk assessment (PRA), please describe the agencys actions to enhance the integration of risk information across the agencys activities to improve the technical basis for regulatory activities, to increase efficiency, and to improve effectiveness. Please include actions taken or planned (including milestones, where appropriate) for improving the realism of PRA information used in regulatory decision-making, for training staff to more effectively apply risk information, for updating agency processes and procedures accordingly, and for improving consistency among NRC offices and regions.

As directed by the Commission in SRM-M170511, the staff recently issued SECY-17-0112, which summarizes its plans to increase staff capabilities to use risk information in decision-making activities. The paper describes five overarching strategies and summarizes associated staff actions and plans. Strategy I evaluates and updates risk-informed decision-making (RIDM) guidance to foster a collaborative review process and a broadened understanding of risk and risk insights. Strategy II develops a graded approach for using risk information in licensing reviews. Strategy III enhances training requirements related to RIDM for managers and staff.

Strategy IV advances NRC and industry risk-informed initiatives, and Strategy V enhances communication on risk-informed activities. To implement overarching strategies at a tactical level, the staff is also developing a detailed action plan for the reactor program. As directed by SRM-M170511, the staff will provide periodic updates to the Commission on its progress.

58 Each strategy with examples of specific actions taken or planned (including milestones, where appropriate) is summarized in the table below. Additional details are available in SECY-17-0112 and in an action plan that leverages best practices in RIDM from the operating and new reactor programs (initial issuance at ADAMS Accession No. ML17219A375). Though strategies and actions mainly focus on the reactor program, Strategies III and V will be coordinated across all agency offices and the regions, as appropriate. In addition, risk-informed approaches as applied in the materials safety and waste management arenas are described, along with reactor safety and cross cutting activities, on the Risk-Informed Activities page on the NRC public Web site (https://www.nrc.gov/about-nrc/regulatory/risk-informed/rpp.html).

Strategy Description/Background Actions/Milestones I. Evaluate and Update Guidance Updated or new guidance will be developed to more fully equip staff with the tools necessary to use quantitative or qualitative risk information in both traditionally deterministic and formal risk-informed reactor licensing reviews.

Importantly, all other strategies also involve guidance development activities.

A new revision to NUREG-1855, Treatment of Uncertainties Associated with PRAs in Risk-Informed Decision Making was published in March 2017 (ADAMS Accession No. ML17062A466).

A new revision to Regulatory Guide 1.174 An Approach for Using Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes to The Licensing Basis is nearing completion. Milestone: RG 1.174 is scheduled for March 2018 publication.

New and revised inspection procedures and field guides are being developed for risk-informed initiatives.

Action plan task 2 seeks to broaden the definition of risk [the understanding of risk and risk insights] beyond just a quantitative value.

Action plan task 4 includes a review of branch technical position (BTP) 8-8, Onsite (Emergency Diesel Generators) and Offsite Power Sources Allowed Outage Time Extensions, to determine if clarification is needed for use of a 14-day backstop for deterministic evaluations; applicability of the guidance to one-time and permanent extensions; and defense-in-depth considerations, particularly with respect to mitigating the consequences of a loss of offsite power coincident with a loss-of-coolant accident with a single failure.

Milestone: The staff will provide findings and recommended changes to office management by June 2018.

II. Develop a Graded Approach for Using Risk Information in Licensing Reviews A graded approach seeks to leverage risk insights across the spectrum of licensing review types (i.e.,

deterministic and formal risk-informed submittals). A framework that supports a graded risk-informed review approach is already described in NUREG-0800 The staff created a tool to guide technical reviewers to consider plant design features when formulating the scope and depth of new reactor review activities. This tool was successfully applied to the NuScale design certification review and is a critical element of the ongoing enhanced safety-focused review of this design.

Action plan task 3 involves developing a graded approach for using risk information more broadly in operating reactor licensing reviews. As part of this task, the staff is developing, assessing, and piloting a risk-screening tool to help determine the appropriate level of its review using risk insights with other relevant factors. Action plan task 1 seeks to expand the use of license review teams with enhanced collaboration between the engineering staff and the PRA practitioners.

59 Strategy Description/Background Actions/Milestones (ADAMS Accession Nos.

ML070630046 and ML13207A315).

III. Enhance Training Requirements Related to Risk-Informed Decision-Making (RIDM) for Managers and Staff The NRC provides over 30 formal staff training courses on technical and regulatory aspects associated with RIDM. Courses are available to all staff members; however, currently, only some NRC employees are required to take these courses.

Furthermore, many courses focus on the technical aspects of PRA as opposed to describing how risk information can be used to inform regulatory decisions.

A new course for NRC managers (Perspectives on Risk-Informed Decision-Making for NRC Managers) is being developed that will focus on practical applications of PRA and describe how risk insights can inform decision-making. If successfully piloted, the course will be made mandatory for all supervisors and senior managers in the reactor program.

Milestone: Conduct pilot course by spring 2018.

The staff continues to offer the newly developed Risk-Informed Thinking Workshop that provides participants with hands-on experience in applying RIDM using scenarios of practical agency work.

The staff plans to update position-specific qualification requirements to include the newly developed Risk-Informed Thinking Workshop for reactor program staff.

The staff is evaluating whether aspects of the Risk-Informed Thinking Workshop could be integrated with appropriate modules of the Fundamentals of Reactor Licensing Workshop for Technical Reviewers. Milestone: Complete evaluation by June 30, 2018.

IV. Advance Risk-Informed Initiatives The NRC primarily uses the Risk Informed Steering Committee (RISC) to advance risk-informed initiatives. RISC is a senior management committee with members from each of the program offices. The industry also has a RISC composed of senior managers. Since inception in 2014, the NRC and industry RISCs meet quarterly. The NRC RISCs objectives include the following: engage industry and listen to concerns relative to the use of PRA to support regulatory decision-making; communicate NRC actions in the area of risk-informed decision-making; Fire PRA realism: The staff is discussing with industry concerns related to fire PRA realism and potential updates to the fire PRA methods, where appropriate. In recent public meetings, industry representatives indicated that, if approved and implemented, some new methods will potentially reduce the calculated risk level at nuclear plant sites. Existing processes allow licensees to propose method improvements through the frequently asked question (FAQ) process, by submitting a license amendment request, or by a topical report. Following a recent workshop and meeting with industry stakeholders to discuss additional FAQs and research activities with the potential to affect Fire PRA realism (additional details at ADAMS Accession No. ML17312B370),

the staff proposed additional FAQs and research activities.

Realism in the Reactor Oversight Process (ROP): The NRC continuously maintains and improves guidance documents and NRC risk tools used to support ROP activities. One such tool is the Risk Assessment Standardization Project Handbook (RASP Handbook). In March 2017, the staff transmitted plans to discuss industry concerns associated with the RASP Handbook. As a result of public meetings, industry proposed pursuing the issue on common cause failure as the highest priority and discussed alternatives.

Industry provided a document regarding common cause failure (CCF) modeling for staff review on December 8, 2017.

60 Strategy Description/Background Actions/Milestones discuss what initiative can be taken by the NRC to incentivize industry to continue to develop PRAs to help both reduce uncertainty and provide a framework to make decisions in light of uncertainty; and discuss industry actions necessary to achieve the vision for future use of PRA to support regulatory decisions.

A brief summary of RISC actions to improve the realism of PRA information used in regulatory decision-making are provided here. SECY 17-0112 provides additional information on all active RISC initiatives including TS Initiative 4b, The Peer Review Facts and Observations Closure Process, 10 CFR 50.69, PRA Methods Vetting Process, and Risk Aggregation.

Activities supplemental to the RISC that also advance risk-informed initiatives are also briefly described here.

Following this review, the staff plans to develop additional guidance for addressing CCF for the Significance Determination Process.

Credit for Diverse and Flexible Coping Strategies (FLEX) in RIDM: FLEX is currently being credited in multiple risk-informed applications. The NRC staff has developed several guidance documents to promote consistency and efficiency in applications in these areas. The staff is continuing to monitor the licensees use of FLEX and is evaluating the need for additional guidance changes.

Additional activities that advance risk-informed initiatives outside the RISC include:

Cooperative Research Activities with the Electric Power Research Institute (EPRI). To conserve resources and to avoid unnecessary duplication of effort, both the NRC and EPRI have agreed to cooperate in selected research efforts and to share information and/or costs whenever such cooperation and cost sharing is appropriate and mutually beneficial. A Memorandum of Understanding with EPRI (ADAMS ML16223A497) currently covers a number of risk-related topics, including fire, seismic, PRA methods, and flooding.

  • Update to RG 1.200, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities. RG 1.200 is the agencys vehicle for endorsing the industry consensus PRA standards and related PRA peer review guidance. RG 1.200 will be revised to reflect the NRCs endorsement of pertinent industry documents.

Consensus Standards Development: The NRC actively participates in the development and maintenance of consensus standards for all levels of PRA, reactor operating modes, and hazards. This effort ensures NRC staff considers a range of industry views when developing regulatory guidance and industry stakeholders are kept informed of regulatory perspectives.

V. Enhance Communication on Risk-Informed Activities The NRC is enhancing communication to ensure that its stakeholders are aware of new and enhanced risk training courses and guidance, ongoing RIDM initiatives, and plans and experience using risk information.

Staff with risk/PRA expertise are sharing knowledge and experience through presentations at branch and division meetings across the offices on topics such as risk-informed screening tools for operating and new reactor reviews.

Seminars on RIDM for NRC inspectors and enhanced inclusion of RIDM topics at regional and senior reactor analyst counterpart meetings are planned.

61

26. The NRC has a long-standing effort to establish an efficient, reliable, and predictable licensing process for power reactors to transition from analog to digital instrumentation and control systems for safety-related applications. Please provide the date this effort began, a milestone schedule for implementation of the licensing process including the actual milestone completion dates, and the scheduled date for completion.

The NRC is implementing an integrated strategy plan to modernize the NRC regulatory infrastructure for digital instrumentation and controls (I&C), through strategic and tactical modernization plans (MPs). The plans focus on topics identified by industry that will provide confidence in transitioning from analog to digital control systems (Integrated Action Plan - ADAMS Accession No. ML17102B307)

MP #1A: Develop guidance for near term implementation of digital upgrades without prior NRC approval under 10 CFR 50.59 (limited scope of systems)(endorsement clarification of NEI 01-01 via RIS supplement)

Activity Actual or Projected Completion Date NRC begins effort:

Prepare preliminary drafts of RIS 2002-22, Supplement 1, clarifying the staffs previous endorsement of NEI 01-01 March 2017 Issue Draft RIS for Public Comment July 2017 Anticipate issuing the final RIS To be determined upon receipt and evaluation of industry stakeholder comments expected February 2018 MP #1B: NRC review and endorsement, as appropriate, of industry technical guidance for addressing common cause failure in digital I&C (NEI 16-16)

Activity Completion Date NRC begins effort:

Begin staff evaluation of the partial draft of NEI 16-16 received December 22, 2016, and develop staff comments and gap analysis December 2016 NEI submits complete NEI 16-16 to the NRC for review Review suspended per NEIs request to evaluate the pending changes to EPRI technical guidance that underpins NEI 16-16 NRC decision on technical adequacy and whether to issue a potential interim endorsement letter To be determined NRC formally enters NEI 16-16 into the Regulatory Guide development process (if decision is made to endorse)

To be determined

62 MP #1C: Modernize NRCs current position on defense against potential common cause failure in I&C systems and components Activity Completion Date NRC efforts begin:

Begin staff review to identify if there are policy issues that need to be taken to the Commission July 2017 Present SECY to Commission for consideration June 2018 Begin implementing resolutions as directed by the Commission September 2018 MP #2: Issue durable guidance for implementation of digital upgrades without NRC approval under 10 CFR 50.59 (full scope of systems)

- Endorsement review of NEI 96-07, Appendix D Activity Completion Date NRC efforts begin:

Initiate review and stakeholder interactions of NEI guidance document, NEI 96-07, Appendix D, Guidelines for 10 CFR 50.59 Evaluations April 2016 NRC decision on technical adequacy and s whether to issue a potential interim endorsement letter June 2018 NRC formally enters NEI 96-07 Appendix D into the Regulatory Guide development process (if decision is made to endorse)

December 2018 MP #3: Review Industrys process for using commercially available digital equipment Activity Completion Date NRC efforts begin:

Public Meeting to discuss resolution of RIS 2016-05 public comments April 2016 EPRI publishes research results October 2018 NEI Submits NEI 17-06 for NRC Review January 2019 NRC makes decision on technical adequacy April 2019 NRC staff completes audits of Safety Integrity Level certification organizations and accrediting entities June 2020 NRC formally enters NEI 17-06 into the Regulatory Guide development process (if decision is made to endorse)

July 2020

63

27. Please describe actions taken and/or planned to prepare to review industry requests to use Accident Tolerant Fuel in existing reactors, including but not limited to actions taken and/or planned for lead test assemblies and fuel loads. Please include a milestone schedule and brief project plan for both evolutionary and revolutionary designs.

The staff has finalized a draft project plan that outlines the strategy to efficiently and effectively license evolutionary and revolutionary accident tolerant fuel (ATF) designs. The draft plan covers all aspects of ATF, including fabrication, transportation, storage, and the regulatory framework for in-reactor performance (i.e., 10 CFR Parts 50, 70, 71, 72, and 100). The draft plan contains tasks covering regulatory and infrastructure needs (regulations and guidance),

tools and methods for safety evaluations, and accounts for interactions with both industry and the U.S. Department of Energy (DOE) regarding requisite experimental data and code capabilities. The draft plan (ADAMS Accession ML17325B771) was published in the Federal Register for public comment on December 21, 2017. The staff is scheduling a public meeting following the comment period to discuss any major comments received. The staff anticipates incorporating stakeholder feedback and finalizing the plan by April 2018.

The NRC has recently communicated its position on the use of ATF lead test assemblies (LTAs) at Hatch Unit 1 (the first plant to insert ATF LTAs) planned for the spring of 2018 (ML17150A443). The NRC found that no exemption from the NRC regulations would be necessary for the plant; the NRCs interpretation of the plants technical specifications would allow the use of LTAs and that the licensees intent to conduct a full evaluation of the activity in accordance with 10 CFR 50.59 would be appropriate.

The staff has chartered a steering committee and working group to explore the development of generic guidance regarding the use of LTAs in commercial operating nuclear reactors and plans to have a position by early 2018.

MP #4A: Streamline the licensing process guidance - update to Interim Staff Guidance ISG-06 Activity Completion Date NRC begins effort:

Conduct a series of public stakeholder meetings (e.g.,

public workshops) for additional feedback February 2017 Issue final Draft revision of ISG-06 for public comment July 2018 Issue final revision of ISG-06 December 2018 MP #4B: Develop strategic activities for long-term improvements to the regulatory infrastructure NRC begins effort to develop strategic plan to modernize overall regulatory infrastructure October 2017 Consider evaluation of lessons learned from MP 1-4A progress April 2018 Coordinate with stakeholders to identify potential regulatory gaps and potential options for improving the regulatory infrastructure June 2018 Develop additional detailed modernization plan for implementing tactical and strategic improvements to the regulatory infrastructure August 2018

64

28. Please describe actions taken and/or planned to improve the quality of cost benefit analyses conducted in association with new requirements, backfit analyses, or rulemaking, including the development of metrics for assessing the quality of cost-benefit analyses. Please include milestones for completing these actions and the guidance that is currently under revision.

The NRC has taken specific actions to improve the quality of cost-benefit analyses conducted in association with new requirements, backfit analyses, or rulemaking. The key milestones for these actions are described below.

On March 19, 2013, the Commission issued a staff requirements memorandum (SRM) regarding SECY-12-0157, Consideration of Additional Requirements for Containment Venting Systems for Boiling Water Reactors with Mark I and Mark II Containments (ADAMS Accession No. ML13078A017). The SRM directed the staff to seek detailed Commission guidance on the use of qualitative factors.

On March 20, 2013, the Commission issued SRM-SECY-12-0110, Staff Requirements -

SECY-12-0110 - Consideration of Economic Consequences within the U.S. Nuclear Regulatory Commissions Regulatory Framework, directing the staff to identify potential changes to current methodologies and tools to perform cost-benefit analysis in support of regulatory, backfit, and environmental analyses. The Commission also directed the staff to provide a regulatory gap analysis before developing new cost-benefit guidance.

On January 2, 2014, in response to SRM-SECY-12-0110, the staff submitted SECY-14-0002, Plan for Updating the U.S. Nuclear Regulatory Commissions Cost-Benefit Guidance. In SECY-14-0002, the staff identified potential changes to current methodologies and tools related to performing cost-benefit analysis in support of regulatory, backfit, and environmental analyses.

The staff informed the Commission of its planned two-phase approach for revising the content and structure of cost-benefit guidance documents. Phase 1 aligns regulatory guidance across NRCs business lines by restructuring and incorporating non-policy revisions to NRC cost-benefit guidance. This phase is underway, as described below. In Phase 2, staff will identify and analyze potential policy issues that could affect the NRCs cost-benefit guidance and present these issues to the Commission for consideration and approval. The staff then will incorporate final updates to guidance for conducting cost-benefit analyses that support backfitting decisions.

On August 14, 2014, in response to SRM-SECY-12-0157, the staff submitted SECY-14-0087, Qualitative Consideration of Factors in the Development of Regulatory Analyses and Backfit Analyses. In SECY-14-0087, the staff proposed updating the cost-benefit guidance to include a set of methods that could be used for the consideration of qualitative factors within a cost-benefit analysis for regulatory and backfit analyses.

On December 16, 2014, in response to Commission direction to provide a regulatory gap analysis before developing new cost-benefit guidance, the staff submitted SECY-14-0143, Regulatory Gap Analysis of the Nuclear Regulatory Commissions Cost Benefit Regulations, Guidance and Practices. In SECY-14-0143, the staff described the review of current NRC guidance, methodologies, and tools used for cost-benefit determinations. The staff also described the results of its review of the NRC regulatory analyses that had been completed and identified differences across NRC business lines (e.g., material users, fuel cycle facilities, new and operating reactors) and procedures (i.e., regulatory analyses, backfit analyses). Finally, SECY-14-0143 included staffs gap analysis, and identified where additional guidance is needed to ensure consistency across the agency.

65 On March 4, 2015, the Commission issued SRM-SECY-14-0087. The Commission approved the staffs plans for updating guidance regarding the use of qualitative factors, including the treatment of uncertainties, and directed the staff to focus the update on capturing best practices for the consideration of qualitative factors. The Commission also directed the staff to provide a toolkit for analysts regarding the consideration of qualitative factors.

In July 2015 and May 2017, the staff held two public meetings on the proposed cost-benefit guidance updates. The staff also held a public workshop in March 2016 to discuss proposed changes to the cost-benefit guidance. Meeting participants included industry representatives, government and nongovernment organizations, and other interested parties.

The Phase 1 update identified in SECY-14-0002 and described above is underway. In April 2017, the NRC issued draft NUREG/BR-0058, Revision 5, Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission, and published a notice requesting public comment in the Federal Register (82 FR 18163; April 17, 2017). The staff received three comment submissions with a total of 58 individual comments from industry and members of the public.

The NRC staff considered this input when revising the NUREG, which is under review by agency management.

The staff will submit NUREG/BR-0058, Revision 5, and five appendices to the Commission via a notation vote paper in early 2018 after completing management review. The following appendices will be included in this update:

Appendix A, Qualitative Factors Assessment Tools Appendix B, Cost Estimating and Best Practices Appendix C, Treatment of Uncertainty Appendix D, Guidance on Regulatory Analysis Related to ASME Rules Appendix E, Special Circumstances and Relationship to Other Procedural Requirements Metrics for assessing the quality of cost-benefit analyses are contained in NUREG/BR-0058, Appendix B. Enclosure B-4 to Appendix B discusses the expectations for quality cost estimates and details the steps to ensure high-quality cost-benefit analyses are developed and presented to agency management. Additionally, the enclosure describes the steps to verify the quality of a cost-benefit analysis through various techniques for checking accuracy.

Following Commission review and approval of Revision 5 of NUREG/BR-0058, the staff will publish this updated final guidance. The staff will also conduct Phase 2 of the activity, as described in SECY-14-0002.

29. Please provide the status of the revised guidance currently under development to clarify the use of qualitative factors, including milestones and the projected date for completion. In addition to this revised guidance, please list and briefly describe any actions taken and/or planned to improve the use of quantitative factors in regulatory analyses required for rulemaking, in the regulatory analyses required under the Backfit Rule, and in the Reactor Oversight Process Significance Determination Process.

NUREG/BR-0058, Revision 5, and five supporting appendices are under final review by agency management. The staff is scheduled to submit these documents to the Commission via a notation vote paper in early 2018.

66 Following Commission review and approval of Revision 5 of NUREG/BR-0058, the staff will publish this updated final guidance. A draft of the NUREG was issued for public comment and is available for interim staff use. In conducting its regulatory analyses, the staff is implementing the best practices and lessons learned that are contained within this draft revision of NUREG/BR-0058.

In revising this cost-benefit guidance, the staff focused on improving methods for quantitative analyses, including the treatment of uncertainty and the development of realistic estimates of the cost of implementing proposed requirements. Specifically, the staff developed two appendices to NUREG/BR-0058, Revision 5 to guide the staff in these areas.

Appendix B, Cost Estimating and Best Practices, provides expanded guidance on incorporating cost-estimating best practices, including estimating life-cycle costs.

Appendix C, The Treatment of Uncertainty, expands on the existing guidance for performing uncertainty and sensitivity analyses for cost-benefit analyses.

In addition to the improved methods for quantitative analyses, the revised cost-benefit guidance directs the staff to quantify the estimates of costs and benefits to the extent possible. However, the staff acknowledges that some attributes in regulatory analyses are difficult to quantify, and require additional resources to develop a strictly quantitative analysis. To address this gap, staff developed a toolkit to enable analysts to clearly present analyses of qualitative results in a transparent way that decision makers, and stakeholders can understand.

Appendix A, Qualitative Factors Assessment Tools, identifies best practices for the consideration of qualitative factors and describes a number of methods that can be used to support the NRCs evidence-based, quantitative, and analytical approach to decision-making. The guidance clearly states that these methods (1) should only be used when quantification may not be practical, (2) are not a substitute for collecting accurate information to develop realistic cost estimates, and (3) do not constitute an expansion of the consideration of qualitative factors in regulatory, backfit, or environmental analyses.

Revision 5 of NUREG/BR-0058 is intended to meet the following objectives:

Refocus and expand guidance on cost-benefit analysis across the agency Emphasize quantification and provides methods for creating realistic estimates Provide methods for assessing factors that are difficult to quantify Incorporate cost estimating best practices identified in U.S. Government Accountability Office (GAO) guidance and in recommendations from GAO in GAO-15-98, Nuclear Regulatory Commission: NRC Needs to Improve Its Cost Estimates by Incorporating More Best Practices, dated December 12, 2014 Expand guidance on the treatment of uncertainties Enhance transparency of analysis for the decision-maker With regard to the use of qualitative factors in the Reactor Oversight Process Significance Determination Process (SDP), the SRM for SECY-13-0137 directed the staff, in part, to evaluate the need to provide additional clarity on the use of qualitative factors for operating reactors to provide more transparency and predictability to the process. The staff expects to respond to this direction by mid-2018.

67

30. Please provide a list of all final generic regulatory actions issued in the last 3 years. Please include:
a. Whether the item was reviewed by Committee for the Review of Generic Requirements (CRGR);
b. Whether the CRGR review was formal or informal;
c. The CRGR recommendation; and
d. The NRCs conclusions with respect to compliance with the Backfitting Rule (i.e., no backfitting, cost-justified substantial increase, compliance exception, adequate protection exception).

The majority of the final generic regulatory actions that the NRC issues do not lead to backfitting. In addition, as discussed in response #34, the agency is working to enhance oversight to prevent unintended and unsupported backfits. The NRC issues many types of final generic regulatory actions, such as rules, orders, bulletins, generic letters (GLs), regulatory information summaries (RISs), regulatory guides (RGs), standard review plans (SRPs), and ISGs.

The CRGR Charter, Revision 8 clarifies which issues should be forwarded to the Committee for review where new or revised generic requirements could propose backfits or new staff positions.

Items for CRGR review are forwarded by the agencys program offices or are directed for review by the EDO. The table below illustrates that only a few final generic agency actions are reviewed by the CRGR to assess if generic backfitting concerns exist. Most backfitting issues are resolved during management review and legal review, or identified during interactions with external stakeholders.

Rules, orders, bulletins, GLs, and RISs are final generic regulatory actions that are reviewed and evaluated to screen for potential backfitting concerns and new staff positions. CRGR reviews these items when certain criteria are met, including:

Stakeholders or NRC staff identify concerns regarding backfitting or regulatory analysis The EDO directs the review or an office director requests review Use of the compliance exception or the adequate protection exceptions to justify backfitting For rulemaking, if there are finality concerns or possible backfitting qualitative factors were used to justify a rulemaking with significant costs, or substantial statistical uncertainty exists in the qualitative benefit determination in the backfit analysis.

For rulemaking, over the last 3 years CRGR reviews were not conducted because the criteria for requiring CRGR review were not met for any of the rulemakings listed in the table. However, under the revised criteria, the CRGR is now more actively reviewing rulemaking activities. For example, in June 2017, the CRGR reviewed a draft proposed rule on cybersecurity at fuel cycle facilities. This marked the first CRGR review using the new criteria and guidance. The draft proposed rule is currently with the Commission for its consideration. Also, on October 25, 2017, the CRGR reviewed the draft final rule on enhanced weapons, firearms background checks, and security event notifications. In reviewing both of these packages, the CRGR requested additional information to ensure that the staff was not unnecessarily imposing backfits on the licensees.

Regulatory guides, standard review plans, and interim staff guidance, are only reviewed by CRGR when concerns are raised during staff review regarding potential generic backfitting.

These documents are intended to provide acceptable approaches for licensees or applicants to meet NRC requirements, or for the NRC staff to confirm the adequacy of proposed approaches.

Additionally, adopting new regulatory guides is intended to be voluntary for licensees and

68 applicants. For limited instances where regulatory guides may result in potential backfits or new staff positions, the CRGR conducts a review.

The table below provides NRC final generic regulatory actions issued within the last 3 years.

For the response, the staff has included final rules, orders, bulletins, RISs, and GLs.

Summary of Final Generic Regulatory Actions over the Last 3 Years Item #

Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review RIS-18-01 Common Violations Cited During First 2 Years of 10 CFR Part 37, "Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material,"

Implementation and Guidance Documents Available to Support Rule Implementation 01/22/18 None NA No Backfitting 10 CFR Part 50 Approval of American Society of Mechanical Engineers' Code Cases 01/17/18 83 FR 2331 None NA No Backfitting 10 CFR 2 and 13 Adjustment of Civil Penalties for Inflation for Fiscal Year 2018 01/12/18 83 FR 1515 None NA No Backfitting RIS-17-08 Process for Scheduling and Allocating Resources for Fiscal Years 2020 Through 2022 for the Review of New Licensing Applications for Light-Water Reactors and Non-Light-Water Reactors 12/21/17 None NA No Backfitting 10 CFR Parts 2, 9, 40, 50, 61, 71, 73, and 110 Miscellaneous Corrections 11/15/17; 82 FR 52823 None NA No Backfitting 1 None - indicates that the item was administrative in nature or did not meet thresholds for CRGR backfitting review, informal reviews - were conducted by the members without a meeting. Formal Reviews - are these items that a meeting was conducted to assess potential backfitting concerns.

69 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #

Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review RIS-17-06 NRC Policy on Use of Combination Dosimetry Devices During Industrial Radiographic Operations 09/19/17 None NA No Backfitting RIS-17-05 Administration of 10 CFR Part 72 Certificate of Compliance Corrections and Revisions 09/13/17 None NA No Backfitting RIS-17-04 Clarification on the Implementation of Compensatory Measures for Protective Strategy Deficiencies or Degraded or Inoperable Security Systems, Equipment, or Components 08/30/17 Informal Review NA No Backfitting 10 CFR Part 50 American Society of Mechanical Engineers Codes and Code Cases 07/18/17; 82 FR 329034 None NA Two changes resulted in an adequate protection backfit exception (Code Case N-729-4 and Code Case N-770-2) 10 CFR Parts 170 and 171 Fee Recovery for Fiscal Year 2017 06/30/17; 82 FR 30682 None NA No Backfitting RIS-17-03 Preparation and Scheduling of Operator Licensing Examinations 04/05/17 None NA No Backfitting RIS-17-02 Applicability of Title 10 of the Code of Federal Regulations Part 37 to Non-Manufacturing and Distribution Service Provider Licensees 02/08/17 None NA No Backfitting RIS-17-01 Human Reliability and Human Performance Database 02/02/17 None NA No Backfitting

70 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #

Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review 10 CFR Parts 2 and 13 Adjustment of Civil Penalties for Inflation 01/24/17; 82 FR 8133 None NA No Backfitting 10 CFR Part 72 List of Approved Spent Fuel Storage Casks Published 6 Certificate of Compliance (COC) rules in 2017 None NA No Backfitting 10 CFR Part 140 Increase in the Maximum Amount of Primary Nuclear Liability Insurance 12/30/16; 81 FR 96347 None NA No Backfitting 10 CFR Parts 2 and 9 Update to Incorporate Freedom of Information Act Improvement Act of 2016 Requirements 12/30/16; 81 FR 96344 None NA No Backfitting RIS-16-12 NRC Employee Access to Switchyards at Licensee Facilities 11/22/16 None NA No Backfitting RIS-16-11 Requests to Dispose of Very Low-Level Radioactive Waste Pursuant to 10 CFR 20.2002 11/13/16 Informal Review Endorsed No Backfitting RIS 19, Rev 1 Decommissioning Timeliness Rule Implementation and Associated Regulatory Relief 09/27/16 None NA No Backfitting RIS-16-10 License Amendment Requests for Changes to Emergency Response Organization Staffing and Augmentation 08/05/16 Informal Review Endorsed No Backfitting 10 CFR Part 2 Update to Transcript Correction Procedures 07/20/16; 81 FR 47005 None NA No Backfitting

71 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #

Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review 10 CFR Parts 2 and 13 Adjustment of Civil Penalties for Inflation 07/01/16; 81 FR 43019 None NA No Backfitting 10 CFR Parts 9, 170, and 171 Fee Recovery for Fiscal Year 2016 06/24/16; 81 FR 41171 None NA No Backfitting RIS-16-09 Preparation and Scheduling of Operator Licensing Examinations 06/16/16 None NA No Backfitting RIS-16-08 Process for Scheduling and Allocating Resources in Fiscal Year 2019 for the Review of New Licensing Applications for Light-Water Reactors and Non-Light-Water Reactors 06/07/16 None NA No Backfitting 10 CFR Parts 170 and 171 Variable Annual Fee Structure for Small Modular Reactors 05/24/16; 81 FR 32617 None NA No Backfitting RIS-16-07 Containment Shell or Liner Moisture Barrier Inspection 05/09/16 Informal Review Endorsed No Backfitting RIS-16-06 NRC Regulation of Radium-226 Under Military Control and for Coordination on the Comprehensive Environmental

Response, Compensation, and Liability Act (CERCLA)

Response Actions at Department of Defense Sites with Radioactive Materials 05/09/16 None NA No Backfitting

72 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #

Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review RIS-16-05 Embedded Digital Devices in Safety-Related Systems 04/29/16 Informal Review Endorsed No Backfitting RIS-16-04 Clarification of 10 CFR 50.46 Reporting Requirements and Recent Issues with Related Guidance Not Approved for Use 04/19/16 Informal Review Endorsed No Backfitting RIS-16-03 10 CFR 50.59 Issues Identified in NRC's San Onofre Steam Generator Tube Degradation Lessons Learned Report 04/13/16 None NA No Backfitting GL-16-01 Monitoring of Neutron-Absorbing Materials in Spent Fuels Pools 04/07/16 Formal Endorsed No Backfitting RIS-16-02 Design Basis Issues Related to Tube-to-Tubesheet Joints in Pressurized-Water Reactor Steam Generators 03/23/16 None NA No Backfitting RIS-16-01 Nuclear Energy Institute Guidance for the Use of Accreditation in Lieu of Commercial Grade Surveys for Procurement of Laboratory Calibration and Test Services 03/16/16 Informal Review Endorsed No Backfitting RIS 16, Rev 1 Planned Licensing Action Submittals for All Power Reactor Licensees 01/15/16 None NA No Backfitting 10 CFR Part 72 List of Approved Spent Fuel Storage Casks Published 5 COC rules in 2016 None NA No Backfitting RIS-15-17 Review and Submission of Updates to Final Safety Analysis Reports, Emergency 12/23/15 None NA No Backfitting

73 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #

Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review Preparedness Documents, and Fire Protection Documents RIS 19, Rev 0 Decommissioning Timeliness Rule Implementation and Associated Regulatory Relief 12/21/15 None NA No Backfitting RIS-15-18 Sodium Iodide-131 (I-131) Patient Release Information Collection 12/14/15 None NA No Backfitting RIS-15-15 Information Regarding a Specific Exemption in the Requirements for the Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material 12/04/15 Informal Review Endorsed No Backfitting RIS 16, Rev 0 Planned Licensing Action Submittals for All Power Reactor Licensees 11/25/15 None NA No Backfitting RIS-15-13 Seismic Stability Analysis Methodologies for Spent Fuel Dry Cask 11/12/15 None NA No Backfitting RIS-15-11 Protective Action Recommendations for Members of the Public on Bodies of Water 11/05/15 Informal Review Endorsed No Backfitting 10 CFR Part 73 Cyber Security Event Notifications 11/02/15; 80 FR 67264 None NA No Backfitting RIS-15-14 Issuance of Enforcement Guidance Memorandum

- Emergency Plan and Emergency Plan Implementing Procedure Updates 10/30/15 None NA No Backfitting

74 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #

Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review 10 CFR Parts 2 and 150 Hearings on Challenges to the Immediate Effectiveness of Orders 10/20/15; 80 FR 63409 None NA No Backfitting 10 CFR Part 2 Revisions to the Petition for Rulemaking Process 10/07/15; 80 FR 60513 None NA No Backfitting 10 CFR Part 72 List of Approved Spent Fuel Storage Casks:

Holtec international HI-STORM 100 Cask System, Certificate of Compliance No. 1014, Amendment No. 8, Revision 1 08/18/15; 80 FR 49887 None NA No Backfitting RIS-15-10 Applicability of ASME Code Case N-770-1 As Conditioned in 10 CFR 50.55a, "Code and Standards," to Branch Connection Butt Welds 07/16/15 Formal Endorsed No Backfitting RIS-15-09 Implementation of Fingerprinting Requirements for Non-Power Reactors 07/09/15 None NA No Backfitting 10 CFR Parts 170 and 171 Fee Recovery for Fiscal Year 2015 06/30/15; 80 FR 37431 None NA No Backfitting RIS-15-08 Oversight of Counterfeit, Fraudulent and Suspect Items in the Nuclear Industry 06/24/15 None NA No Backfitting GL-15-01 Treatment of Natural Phenomena Hazards in Fuel Cycle Facilities 06/22/15 Formal Endorsed No Backfitting 10 CFR Part 71 Transportation Safety Requirements and Harmonization with International Atomic Energy Agency 06/12/15; 80 FR 33987 None NA No Backfitting

75 Summary of Final Generic Regulatory Actions over the Last 3 Years Item #

Title Issuance Date CRGR1 Review CRGR Recommen dation NRC Backfitting Review Transportation Requirements; Revisions RIS-15-06 Tornado Missile Protection 06/10/15 Formal Endorsed No Backfitting RIS-15-07 Process for Scheduling and Allocating Resources in FY 2017 for the Review of New Licensing Applications for Large Light-Water Reactors and Small Modular Reactors 05/11/15 None NA No Backfitting RIS-15-05 Preparation and Scheduling of Operator Licensing Examinations 04/20/15 None NA No Backfitting RIS-15-04 Withdrawal of Administrative Letter 93-01 04/14/15 None NA No Backfitting 10 CFR Part 72 List of Approved Spent Fuel Storage Casks:

Holtec international HI-STORM Underground Maximum Capacity Canister Storage System, Certificate of Compliance No. 1040 03/06/15; 80 FR 12073 None NA No Backfitting RIS-15-03 Identifying and Reporting Security Incidents Under 10CFR Part 37 02/24/15 None NA No Backfitting RIS-15-02 Reporting of H-3, C-14, Tc-99, and I-129 on the Uniform Waste Manifest 02/18/15 None NA No Backfitting

31. Please provide a list and brief description of all facility specific backfits issued in the reporting period.

None.

76

32. For matters reviewed by the CRGR, please provide 12-month and 3-year rolling averages for the following metrics:
a. For the number of issues reviewed formally: the percentage accepted for imposition on industry and the percentage rejected based on cost-benefit or Backfit concerns; and
b. For the number of issues reviewed informally: the percentage accepted for imposition on industry and the percentage rejected based on cost-benefit or Backfit concerns.

12-Month Summary of CRGR Review Decisions of Potential Backfit Issues Review Type &

Outcome Percentage Accepted or Endorsed with Backfitting Percentage Rejected Based on Backfit Concerns Percentage Endorsed without Backfitting Informal Reviews 0.0%

0.0%

100.0%

Formal Reviews 20.0%

20.0%

60.0%

3-Year Summary of CRGR Review Decisions of Potential Backfit Issues Review Type &

Outcome Percentage Accepted or Endorsed with Backfitting Percentage Rejected Based on Backfit Concerns Percentage Endorsed without Backfitting Informal Reviews 0.0%

0.0%

100.0%

Formal Reviews 18.2%

9.1%

72.7%

Comments:

1. As of January 31, 2018, for the rolling 3-year period, the CRGR has completed 28 reviews for potential backfits. Completed reviews include 17 informal reviews and 11 formal reviews.

These percentages omit ongoing CRGR reviews.

2. These tables provide summaries of CRGR review results for the rolling 12-month and 3-year periods. The percentage accepted includes CRGR endorsements of generic documents that may lead to licensee backfits, the percentage rejected are reviews in which the CRGR disapproved documents due to backfit concerns, and the percentage endorsed were reviews in which the CRGR found no backfit implications.
33. Please provide the status of the application of the Backfit Rule in the licensing and inspection programs across the agency, including:
a. The need for training on the requirements and application of 10 CFR 50.109;
b. The need for a process, training, and/or oversight in addressing inspection issues that may redefine or reinterpret the original licensing basis (e.g., unresolved issues, task interface agreements, disputed violations) to ensure that new requirements are not imposed through the inspection program;
c. A review of proposed regulatory changes that are currently in process to ensure that regulatory actions are appropriately informed by the requirements of 10 CFR 50.109.

Examples of such actions could include but are not limited to the following:

i.

The Draft Regulatory Issue Summary on Service Life addressing the treatment of vendor recommendations within the regulatory framework;

77 ii. 10 CFR 50.46(c) rulemaking for which the justification utilizes the adequate protection provisions of the backfit rule to obviate the need to compare the benefits of public health and safety with the cost of compliance for the three major portions of the rule; iii. Use of the compliance exception backfit as proposed by the NRC staff to address the "open phase condition (OPC)" issue; and iv. Possible alteration of the risk reduction credit given for Incipient Fire Protection after the modifications have been installed and received approval from the NRC crediting the technology.

d. Please describe the progress made during each reporting period.

a, b, & d. Consistent with the EDO approved milestones in Response 34, the agency developed and implemented refresher training for management, inspection staff, engineers, and project managers. The agency is currently developing enhanced backfit training that will be deployed in 2018 and 2019. As of January 31, 2018, the agency completed refresher training for NRC senior managers, NRC regional inspection staff, and applicable NRC headquarters offices.

More detailed backfitting guidance and procedures will be developed throughout FY 2018 and discussed in future reports.

c. The agency has incorporated the recent lessons learned from the Exelon backfit appeal decision and the Commissions direction in SRM-COMSECY-16-0020 into its reviews of proposed regulatory changes and decision making.

The table below provides a summary of the status of regulatory changes and issues as of January 31, 2018.

Status of Select Regulatory Activities Title Status of Regulatory Change Backfitting Considerations RIS on Service Life -

Disposition of Information Related to the Time Period That Safety-Related Structures, Systems, or Components are Installed RIS (ADAMS Accession No. ML17177A060) was issued for public comment and the public comments have been dispositioned.

RIS was reviewed by CRGR on September 12 and 14, 2017. CRGR Meeting Nos. #446,

  1. 447(ADAMS Accession No. ML17276B156).

While the CRGR found that the draft RIS did not contain any specific backfits or new staff positions, it did not endorse the RIS in its current form. The CRGR indicated that a RIS may not be appropriate for addressing these issues.

Currently, the staff is discussing its next steps forward.

10 CFR 50.46(c)

Rulemaking The NRC staff prepared a regulatory analysis for the 10 CFR 50.46c draft final rule (ADAMS Accession No. ML15323A122) to identify the benefits and costs of the particular regulatory approach for addressing emergency core cooling system performance. The regulatory analysis focuses on the marginal difference in benefits Based on established criteria at the time, the CRGR was not required to review the rulemaking to assess potential backfits. The rulemaking is currently with the

78 Status of Select Regulatory Activities Title Status of Regulatory Change Backfitting Considerations and costs for each alternative relative to the no action baseline alternative for the three major portions of the rule, which is consistent with the requirements of the backfit rule (10 CFR 50.109), Commission direction, and the ongoing revisions to the agencys cost-benefit guidance (e.g., NUREG/BR-0058, Revision 5).

Commission for its consideration.

RIS on AP1000 Certified Design Information Errors Discovered During Design Finalization and Construction Activities The purpose of this RIS is to provide guidance, to present and future applicants for a Combined License (COL) or COL renewal referencing the AP1000 DC, regarding previous applicant-identified errors contained in the AP1000 DC (DCD Revision 19) and how these errors may be addressed by current and future applicants.

This item has been closed. Staff no longer plans to issue the subject RIS.

Proposed Rule, 10 CFR 73.53, Requirements for Cyber Security at Nuclear Fuel Cycle Facilities and associated draft regulatory guidance, DG-5062 Cyber Security Programs for Nuclear Fuel Cycle Facilities The proposed rule (ADAMS Accession No. ML17145A342), if approved, would require certain Fuel Cycle Facility licensees to establish, implement, and maintain a cyber security program that can detect, protect against, and respond to a cyber-attack capable of causing one or more of the consequences of concern as defined in the proposed rule.

CRGR completed its review in two meetings, June 27 and July 12, 2017. This rule contained backfitting and was endorsed by the CRGR.

This rulemaking is currently with the Commission for its consideration.

Regulatory Guide 5.77, Revision 1, Insider Mitigation Program This regulatory guide describes an approach that the NRC staff considers acceptable for an insider mitigation program for nuclear power reactors that contain protected or vital areas.

This item has been closed. The staff did not identify a backfitting concern. This RG is currently being reviewed by the Commission.

34. Please provide a description of actions taken and/or planned to address recommendations made by the CRGR in their report "U.S. Nuclear Regulatory Commission's Implementation of Backfitting and Issue Finality Requirements," dated June 27, 2017. Please include a milestone schedule for completing action on each recommendation.

The actions identified in the CRGR Review Report and approved by the EDO in a memo dated July 19, 2017, have been organized into the following activities:

79 Backfitting Enhancement Tasks from the June 27, 2017, CRGR Review Report Item Task Lead Due Date Status 1

Update agency-level guidance on backfitting and issue finality to reflect Commission direction on the use of the compliance exception to the backfit rule and submit for Commission approval.

NRR 05/02/2018 On track 2

Update office-level implementing guidance on backfitting and issue finality, and the Enforcement Manual to reflect Commission-approved agencywide guidance.

NRR, NMSS, NRO, NSIR, RES, all Regions, OE 02/21/2019 On track 3

Develop and conduct "reset" training for managers and staff on backfitting and issue finality.

CRGR 02/28/2018 Completed 4

Update initial training on backfitting and issue finality for use in office and regional qualification programs.

CRGR 06/31/2018 On track 5

Develop or update refresher training and developmental activities on backfitting and issue finality, and revise office qualification procedures to require such training and developmental activities.

CRGR, NRR, NMSS, NRO, NSIR, RES, all Regions 09/31/2018 On track 6

Make available "just-in-time" training and references on backfitting and issue finality.

CRGR 10/31/2018 On track 7

Add backfitting information to agency knowledge management Web site.

CRGR 09/18/2017 Completed 8

Prepare a NUREG/Knowledge Management report on the history and activities of the Committee to Review Generic Requirements.

CRGR 08/31/2019 On track 9

Create a backfitting Community of Practice with office points of contact.

CRGR 08/31/2017 Completed 10 Conduct an effectiveness review of actions taken in response to the June 27, 2017, CRGR report.

CRGR 07/27/2020 On track 11 Propose a revision to the charter for the CRGR to reflect rulemaking criteria, incorporate recent Commission direction, and enhance rigor of CRGR assessments.

CRGR 03/19/2018 On track 12 Report on the availability of key docketed information categories and the resources needed to make information more readily retrievable.

OCIO 02/28/2018 On track 13 Report on the resources needed to implement the actions in the July 19, 2017, EDO tasking on backfitting.

CRGR 10/02/2017 Completed

80 REACTOR INSPECTION

35. Please provide the Reactor Oversight Process findings for year-to-date and 3-year rolling metrics, including the total number and for each region for green, white, yellow, and red findings.

Location

  1. of Findings 2014 2015 2016 2017(Note
1)

Nationally Total 824 821 704 505 NSIR (all regions) 18 26 19 N/A (Note 2)

RI Green 167 169 155 119 White 3

4 2

2 Yellow 0

1 0

0 Red 0

0 0

0 GTG Security 1

1 0

0 Total 171 175 157 121

  1. OP Units 26 25 25 25 R2 Green 148 159 151 104 White 4

1 0

3 Yellow 0

0 0

0 Red 0

0 0

0 GTG Security 0

0 1

2 Total 152 160 152 109

  1. OP Units 32 32 33 33 R3 Green 221 202 177 113 White 4

5 1

4 Yellow 0

0 0

0 Red 0

0 0

0 GTG Security 1

1 1

0 Total 226 208 179 117

  1. OP Units 23 23 23 23 R4 Green 249 248 196 154 White 5

2 1

2 Yellow 2

1 0

0 Red 0

0 0

0 GTG Security 1

1 0

2 Total 257 252 197 158

  1. OP Units 19 19 19 19 NSIR: Office of Nuclear Security and Incident Response*

GTG Security: Greater-than-green security;

  1. OP Units: Number of operating units; Notes:
1. Data are presented by calendar year. Some fourth quarter data are still being processed for CY 2017.
2. Starting in CY 2017, these finding are included in the findings for each region.

81

36. Please provide the percentage of Final Significance Determinations made within 90 Days for all potentially Greater-Than-Green findings, monthly for one-year rolling metrics and annually for the past 10 years.

1-Year Rolling Metric Month Percent Met February 2017 100 March 2017 N/A April 2017 100 May 2017 100 June 2017 N/A July 2017 100 August 2017 100 September 2017 N/A October 2017 100 November 2017 0

December 2017 100 January 2018 N/A 10-Year Annual Determinations Within 90 Days Year Percent Met 2008 100 2009 100 2010 93 2011 100 2012 100 2013 100 2014 86 2015 88 2016 100 2017 93 Comments:

This metric, reported in the NRCs CBJ, measures the time from the issuance date of the first official correspondence that describes the inspection finding, until the final significance determination letter is sent to the licensee, which is expected to be 90 days or less.

37. For each reporting period, please describe each instance where Inspection Manual Chapter 609 Appendix M, "Significance Determination Process Using Qualitative Criteria," has been applied in the Reactor Oversight Process Significance Determination Process, including the justification for doing so.

Appendix M was used to disposition three green inspection findings during this reporting period.

Two of these findings were associated with spent fuel pool water inventory and one was associated with post-Fukushima safety enhancements. In all three cases, the use of Appendix M was directed by another SDP appendix.

82

38. Please provide the status of potential changes to the Reactor Oversight Process, and identify any changes that may require Commission approval prior to implementation.

Significant potential changes to the ROP include the following:

IMC 0609, Significance Determination Process, Appendix M, Significance Determination Process Using Qualitative Criteria. Having received stakeholder feedback on its initially proposed changes to Appendix M, the NRC staff is preparing a revised approach, and will re-engage with stakeholders in the coming months to review the changes and next steps. Based on the changes contemplated, at the present time, the staff does not expect that Commission approval will be required.

39. Please describe the progress toward utilizing an industry consensus document as a means of accomplishing predictability and consistency in operability determinations.

The NRC is engaged with nuclear industry stakeholders on its effort to develop a consensus document for operability determinations. The agency held a public meeting on June 1, 2017, to discuss the fundamental concepts used to make operability determinations. The staff also participated in an operability panel at the NEI Licensing Forum on August 23, 2017. NRC expects to receive industrys draft guidance in early 2018. The NRC anticipates that this effort will inform a future revision of IMC 0326, Operability Determinations & Functionality Assessments for Conditions Adverse to Quality or Safety.

40. For each Design Bases Assurance Inspection (formerly known as the Component Design Basis Inspection) completed in the last three years, please list the duration, amount of fees billed, and percentage of fees used to reimburse contractors.

The fees are grouped per Design Bases Assurance (DBA) inspection in order to allow easier review by the reader and facilitate comparison between the costs of DBA inspections performed at each site. Monthly comparison of DBA inspection fees will not provide an accurate representation of each licensees charges due to the fact that the DBA inspections span 2 months.

83

84

85

86

41. Please provide the status of the holistic review of engineering inspection procedures and any actions taken and/or planned because of the review.

During January and February 2018, NRC management and staff are conducting internal briefings for NRC senior management to obtain their endorsement of the recommended changes to the suite of ROP engineering inspections proposed by the staffs engineering inspection working group. The potentially impacted ROP inspections include:

IP 71111.05T, Fire Protection (Triennial) or IP 71111.05XT, Fire Protection-NFPA 805 (Triennial)

IP 71111.07, Heat Sink Performance IP 71111.08, Inservice Inspection Activities IP 71111.12, Maintenance Effectiveness IP 71111.17T, Evaluations of Changes, Tests, and Experiments IP 71111.18, Plant Modifications IP 71111.21M, Design Bases Assurance Inspection (Team)

IP 71111.21N, Design Bases Assurance Inspection (Program)

The purpose of this review effort is to improve the effectiveness and efficiency of these ROP engineering inspections. The NRC held a public meeting on February 22, 2018, to inform industry stakeholders of the recommended changes. NRC staff plans to seek Commission approval for these changes in the summer of 2018 and, if approved by the Commission, the NRC plans to implement these changes starting in calendar year 2020.

87 NEW REACTORS

42. Please provide a table showing the funds budgeted, the resources spent, and the total Part 170 fees billed each year for the last ten years for the Office of New Reactors.

FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 FY 14 FY 15 FY 16 FY17 FY 18PB Enacted ($M) 137.08 110.46 109.81 110.71 102.53 100.87 112.61 96.08 91.63 72.03 76.49 Expended ($M) 82.57 81.16 90.55 89.75 76.06 89.16 67.03 61.46 62.63 54.84 17.61 Part 170 Billed ($M) 75.73 74.65 60.28 60.18 59.62 60.12 55.65 11.40 Enacted: Beginning in FY 2018, the NRC eliminated the allocation of mission indirect resources in the agency's budget request to increase transparency (see NRC FY 2018 Congressional Budget Justification page 161 for detailed explanation). To allow for comparison of historical budget data, FY 2008 - FY 2017 are presented in a consistent manner. FY 2018 expenditure and Part 170 billing is as of January 31, 2018.

Part 170 Billed: For FY 2008 - FY 2010, the data in the legacy billing system is not available at the office level.

43. For each design certification, Construction and Operating License (COL), and Early Site Permit (ESP) application reviewed since 2007, please provide:
a. The date of the first pre-application meeting;
b. The date the application was filed;
c. Whether the acceptance review was completed in 60 days;
d. The originally scheduled dates for completion of the safety evaluation report and environmental impact statement;
e. The actual dates for completion of the safety evaluation report and environmental impact statement;
f.

For ongoing reviews, the projected date for final agency action;

g. For terminated or suspended reviews, the dates of the termination or suspension; and
h. The total fees billed for each review.

88 Project Name Date of First Pre-Application Meeting Date the Application was Filed Acceptanc e Review Completed in 60 Days (Note 1)

Original Review Schedule Dates for FSER and FEIS (or EA)

Completion Actual FSER and FEIS (or EA)

Completion Dates Projected Date for Final NRC Action Date of Withdrawal or Suspension Request (for terminated projects only)

Total Fees Billed for Each Review (Note 4)

U.S. Advanced Pressurized Water Reactor (APWR) DC 05/12/2006 12/31/2007 Yes FSER: 06/2012 FEIS: N/A Application is currently under review Not Scheduled (Note 2)

N/A

$77,885,573 APR1400 DC 11/05/2009 12/23/2014 Yes FSER: 09/2018 FEIS: N/A Application is currently under review 09/2019 N/A

$54,236,631 ABWR DC Renewal (GEH) 02/23/2010 12/07/2010 Yes FSER: 03/2018 FEIS: N/A Application is currently under review Schedule currently under review N/A

$5,071,312 Turkey Point COL 02/10/2009 06/30/2009 Yes FSER: 12/2012 FEIS: 10/2012 FSER:

12/2016 FEIS: 10/2016 04/2018 N/A

$35,115,339 Clinch River ESP 12/14/2010 05/12/2016 No (Note 3)

FSER: 08/2019 FEIS: 06/2019 Application is currently under review 02/2020 N/A

$5,647,335 NuScale SMR DC 07/09/2008 01/06/2017 Yes FSER: 09/2020 FEIS: N/A Application is currently under review 01/2021 N/A

$16,643,723 North Anna ESP Information not known 09/25/2003 Yes FSER: 6/2005 FEIS: 6/2005 FSER:

08/2006 FEIS: 12/2006 ESP issued on 11/27/2007 N/A

$8,579,177 Vogtle ESP Information not known 08/15/2006 Yes FSER: 05/2008 FEIS: 05/2008 FSER:

02/2009 FEIS: 08/2008 ESP issued on 08/26/2009 N/A

$11,680,269 South Texas Project COL Information not known 09/20/2007 Yes FSER: 09/2011 FEIS: 03/2011 FSER:

09/2015 FEIS: 02/2011 COL issued on 02/12/2016

$58,463,244

89 Project Name Date of First Pre-Application Meeting Date the Application was Filed Acceptanc e Review Completed in 60 Days (Note 1)

Original Review Schedule Dates for FSER and FEIS (or EA)

Completion Actual FSER and FEIS (or EA)

Completion Dates Projected Date for Final NRC Action Date of Withdrawal or Suspension Request (for terminated projects only)

Total Fees Billed for Each Review (Note 4)

Bellefonte COL Information not known 10/30/2007 Yes FSER: 02/2011 FEIS: 01/2010 Application withdrawn by the applicant N/A 03/28/2016

$21,916,556 North Anna COL Information not known 11/26/2007 Yes FSER: 08/2010 FEIS: 12/2009 FSER:

01/2017 FSEIS:

02/2010 COL issued on 06/02/2017 N/A

$33,032,175 Lee COL Information not known 12/12/2007 Yes FSER: 02/2011 FEIS: 03/2010 FSER:

08/2016 FEIS: 12/2013 COL issued on 12/19/2016 N/A

$22,762,364 U.S. EPR DC 2/8/05 12/11/2007 Yes FSER: 05/2011 FEIS: N/A Application review is suspended at the applicants request N/A 02/25/2015 (suspension request)

$82,585,674 Shearon Harris COL Information not known 02/18/2008 Yes FSER: 04/2011 FEIS: 05/2010 Application review is suspended at the applicants request N/A 05/02/2013 (suspension request)

$10,106,258 Vogtle COL Information not known 03/28/2008 Yes FSER: 12/2010 FEIS: 01/2010 FSER:

08/2011 FEIS: 04/2011 COL issued on 02/10/2012 N/A

$29,770,625 V.C. Summer COL Information not known 03/27/2008 Yes FSER: 02/2011 FEIS: 02/2011 FSER:

08/2011 FEIS: 04/2011 COL issued on 03/30/2012 N/A

$28,057,913 Levy COL Information not known 07/30/2008 Yes FSER: 05/2011 FEIS: 09/2010 FSER:

05/2016 FEIS: 04/2012 COL issued on 10/26/2016 N/A

$27,398,694

90 Project Name Date of First Pre-Application Meeting Date the Application was Filed Acceptanc e Review Completed in 60 Days (Note 1)

Original Review Schedule Dates for FSER and FEIS (or EA)

Completion Actual FSER and FEIS (or EA)

Completion Dates Projected Date for Final NRC Action Date of Withdrawal or Suspension Request (for terminated projects only)

Total Fees Billed for Each Review (Note 4)

Fermi COL Information not known 09/18/2008 Yes FSER: 03/2012 FEIS: 08/2011 FSER:

11/2014 FEIS: 01/2013 COL issued on 05/01/2015 N/A

$26,413,206 Comanche Peak COL Information not known 09/18/2008 Yes FSER: 12/11 FEIS: 01/2011 FSER: N/A FEIS: 05/2011 Application review is suspended at the applicants request N/A 11/07/2013 (suspension request)

$23,278,377 River Bend COL Information not known 09/25/2008 Yes A review schedule was not developed for this application Application withdrawn by the applicant N/A 01/09/2009 (suspension request) 12/04/2015 (withdrawal request)

$1,350,316 Callaway COL Information not known 07/24/2008 No A review schedule was not developed for this application Application withdrawn by the applicant N/A 06/23/2009 (suspension request) 08/12/2015 (withdrawal request)

$4,066,138

91 Project Name Date of First Pre-Application Meeting Date the Application was Filed Acceptanc e Review Completed in 60 Days (Note 1)

Original Review Schedule Dates for FSER and FEIS (or EA)

Completion Actual FSER and FEIS (or EA)

Completion Dates Projected Date for Final NRC Action Date of Withdrawal or Suspension Request (for terminated projects only)

Total Fees Billed for Each Review (Note 4)

Bell Bend COL Information not known 10/10/2008 Yes FSER: 03/2012 FEIS: 03/2011 FSER: N/A FEIS: 04/2016 Application withdrawn by the applicant N/A 02/25/2015 (suspension request) 08/30/2016 (withdrawal request)

$20,026,574 PSEG ESP Information not known 05/25/2010 Yes FSER: 07/2013 FEIS: 03/2013 FSER:

09/2015 FEIS: 11/2015 ESP issued on 05/05/2016 N/A

$17,917,093 ABWR DC Renewal (Toshiba)

Information not known 10/27/2010 Yes A review schedule was not developed for this application Application withdrawn by the applicant N/A 06/09/2016 (withdrawal request)

$686,911 Victoria County ESP Information not known 03/25/2010 Yes FSER: 04/2013 FEIS: 08/2013 Application withdrawn by the applicant N/A 08/28/2012 (withdrawal request)

$6,146,248 Calvert Cliffs COL Information not known 07/13/2007 (Part 1 of application) 03/14/2008 (Part 2 of application)

No Yes FSER: 07/2012 FEIS: 03/2010 FSER: N/A FEIS: 05/2011 Application withdrawn by the applicant N/A 02/27/2015 (suspension request) 06/08/2015 (withdrawal request)

$31,400,772 Nine Mile Point COL Information not known 09/30/2008 Yes A review schedule was not developed for this Application withdrawn by the applicant N/A 12/01/2009 (suspension request) 11/26/2013

$2,687,822

92 Project Name Date of First Pre-Application Meeting Date the Application was Filed Acceptanc e Review Completed in 60 Days (Note 1)

Original Review Schedule Dates for FSER and FEIS (or EA)

Completion Actual FSER and FEIS (or EA)

Completion Dates Projected Date for Final NRC Action Date of Withdrawal or Suspension Request (for terminated projects only)

Total Fees Billed for Each Review (Note 4) application (withdrawal request)

Grand Gulf COL Information not known 02/27/2008 Yes FSER: 03/2011 FEIS: 05/2010 Application withdrawn by the applicant N/A 2/9/2015 (withdrawal request)

$4,719,505 Grand Gulf ESP Information not known 10/21/2003 Yes FSER: 10/2005 FEIS: 10/2005 FSER:

10/2005 FEIS: 04/2006 ESP issued on 04/05/2007 N/A

$5,352,875 Clinton ESP Information not known 09/25/2003 Yes FSER: 08/2005 FEIS: 08/2005 FSER:

02/2006 FEIS: 07/2006 ESP issued on 3/15/2007 N/A

$5,186,587 AP1000 DC Amendment Information not known 05/26/2007 Yes FSER: 08/2010 FEIS: N/A FSER:

08/2011 FEIS: N/A Final Rule published on 12/30/2011 N/A

$33,036,394 Economic Simplified Boiling Water Reactor (ESBWR) DC 6/20-21/2002 08/24/2005 No FSER: 06/2009 FEIS: N/A FSER:

03/2011 Supplement FSER: 9/2014 FEIS: N/A Final Rule published on 10/15/2014 N/A

$68,153,802 ABWR DC Amendment Information not known 06/30/2009 Yes FSER: 04/2010 FEIS: N/A FSER:

10/2010 FEIS: N/A Final Rule published on 12/16/2011 N/A

$1,145,852 Victoria County COL Information not known 09/03/2008 Yes A review schedule was not developed for this application Application withdrawn by the applicant N/A 06/11/2010 (withdrawal request)

$1,493,183

93 Note 1:

NROs acceptance review metric is to complete the acceptance review within 60 days and to issue a letter to the applicant documenting the staffs findings on acceptability within 75 days.

Note 2:

The NRC is performing the review of the US APWR at a very reduced pace at the request of the applicant and will continue at this pace until notified by the applicant of a change in its plans. Therefore, no completion date has been established.

Note 3: The acceptance review for the Clinch River ESP application was extended at the request of the applicant, TVA, by letter dated August 19, 2016.

Note 4:

The NRCs 10 CFR Part 170 charges are billed on a quarterly basis. Therefore, updates will be provided in this report to Question 43.h during the reporting periods for January, April, July, and October.

94

44.

Please provide a concise summary of the status of ongoing design certification, COL, and ESP application reviews. Please include a discussion of the issuance of RAls and receipt of responses.

In addition to the updates provided here, each of the DC, COL, and ESP milestone schedules that are under review are publicly available on the NRC website.

DC Applications The NRC employs a 6 Phase schedule to monitor progress towards completion of the safety review. These phases are:

Phase 1 - Preliminary SER with RAIs issued to applicant Phase 2 - SER with Open Items issued Phase 3 - Response to ACRS regarding SER with Open Items issued Phase 4 - Advanced SER with no Open Items issued Phase 5 - Response to ACRS regarding SER with no Open Items issued Phase 6 - Final SER issued US-APWR Mitsubishi Heavy Industries (MHI) submitted its US-APWR DC application on December 31, 2007. The staff is currently in Phase 2 of the review. By letter dated November 5, 2013, MHI initiated a coordinated slowdown of NRC licensing activities in order to focus its resources towards supporting the restart of the Mitsubishi-designed reactors in Japan following the Fukushima event. The NRC staff has been performing the review of the US-APWR DC application at a very reduced pace and will continue at this reduced pace until further notice from the applicant. As of January 31, 2018, the staff has issued 5,681 RAIs and the applicant has responded to 5,532 of them.

APR1400 On December 23, 2014, Korea Electric Power Corp. and Korea Hydro & Nuclear Power Co.,

Ltd. (KHNP), submitted to the NRC its application for the certification of the APR1400 standard plant design for use in the U.S. domestic energy market. The NRC completed the Phase 2 review for all chapters of the application in May 2017 and completed the Phase 3 review in June 2017. The staff is currently in Phases 4 and 5 of its review. As of January 31, 2018, the staff had issued 2,224 RAI questions and the applicant has responded to 2,223 of them. Of the RAI questions issued, 99.5% are closed or are considered confirmatory actions that the staff will verify, upon receipt of the updated final safety analysis report, that the applicant has incorporated all changes in accordance with the response approved by the staff.

On October 31, 2017, the staff issued an updated schedule letter to KHNP explaining that, although the NRC staff has made substantial progress toward completing both the remaining Phase 4 and Phase 5 reviews, issues related to the technical quality, completeness, or timeliness of the applicants submittals have resulted in delays that affected the milestone dates for completion of Phase 4 and Phase 5. Therefore, the staff revised the Phase 4 public milestone date from December 2017 to March 2018. While no change was made to the Phase 5 or Phase 6 milestone dates, the Phase 4 delay may also impact the completion of the review schedule within the 42 month schedule.

95 NuScale On January 6, 2017, NuScale submitted the first SMR DC application for review by the NRC.

On March 15, 2017, the NRC completed its acceptance review and docketed the application.

The staff issued the acceptance review letter to NuScale on March 23, 2017, and developed a full review schedule with public milestones that was transmitted to NuScale on May 22, 2017.

The staffs review is currently in Phase 1 and Phase 2. To date the NRC has identified 23 critical issues requiring resolution and that have the potential to adversely affect the review schedule. As of January 31, 2018, the staff has issued 357 RAIs, which included 994 RAI questions and the applicant has responded to 779 of the RAI questions. Of the 357 RAIs issued, 68 RAIs (19%) are now closed. This months report corrects the total number of RAIs that have been closed for the NuScale project.

DC Renewal Applications ABWR Renewal (General Electric-Hitachi (GEH))

On December 7, 2010, GEH submitted an application for renewal of the ABWR DC. The review is currently in Phase 2, safety evaluation with open items. The NRC staff issued a letter to GEH on July 20, 2012, describing 28 design changes that GEH should have included in the application. By letter dated September 17, 2012, GEH stated it planned to address the 28 items in its Revision 6 of the ABWR DCD. By letter dated February 19, 2016, GEH submitted its revised application incorporating the changes to the ABWR DCD. On August 30, 2016, the staff issued a schedule letter to GEH based on resolving all open items by January 2017. However, some open items associated with the review of the application remain unresolved. On August 3, 2017, the staff issued a letter to GEH stating that the NRC will not be able to meet the original schedule outlined in the August 30, 2016, letter due to unresolved issues with the application. The letter also stated that the NRC will issue a revised schedule letter to GEH after additional interactions with the applicant are held to resolve these issues and the staff receives complete responses to the NRCs RAIs. As of January 31, 2018, the staff has issued 37 RAIs and the applicant has responded to all of them.

COL Applications Turkey Point Units 6 and 7 On June 30, 2009, Florida Power & Light Company (FPL) submitted a COL application for two AP1000 units at the existing Turkey Point Nuclear Generating Station site in Miami-Dade County, FL. On September 4, 2009, the NRC staff issued a letter to FPL indicating the Turkey Point COL application was acceptable for docketing.

The NRC staff completed its safety review and presented the final SER to ACRS on August 19, 2016. The final SER for Turkey Point was issued on November 10, 2016. The NRC issued the final EIS on October 28, 2016. The Commission held the mandatory hearing on December 12, 2017.

On May 2-3, 2017, the ASLB conducted an evidentiary hearing in Homestead, FL, for the contested proceeding involving the Southern Alliance for Clean Energy, National Parks Conservation Association, and other joint intervenors. On July 10, 2017, the ASLB ruled in favor of the NRC staff and terminated the contested proceeding. No appeal was filed within the appeal deadline. On April 18, 2017, the City of Miami, City of South Miami, and Village of Pinecrest (petitioners) filed a new petition seeking a hearing. On July 31, 2017, the ASLB

96 rejected the pending contention and terminated the contested proceeding involving those petitioners. The Commission denied the petitioners appeal from that decision on December 11, 2017 (CLI-17-12).

ESP Applications The NRC employs a 4 Phase schedule to monitor the progress towards completion of the safety review. These phases are:

Phase A - Preliminary SER and RAIs issued to the applicant Phase B - Advanced SER with No Open Items Developed Phase C - ACRS meeting on Advanced SER Phase D - Final SER issued The NRC also employs a 4 Phase schedule to monitor completion of the environmental impact statement. These phases are:

Phase 1 - Scoping Summary Report issued Phase 2 - Draft EIS issued to the U.S. Environmental Protection Agency (EPA)

Phase 3 - Responses to DEIS comments completed Phase 4 - Final EIS issued to EPA Clinch River On May 12, 2016, TVA submitted an ESP application for the Clinch River Nuclear Site located in Oak Ridge, Tennessee. By letter dated August 11, 2016, TVA identified certain aspects of the application for which it intended to provide supplemental information. The NRC responded to TVA in a letter dated August 19, 2016, and informed TVA that its application would remain in a tendered but not docketed status until all of the supplemental information was provided to NRC. By December 15, 2016, TVA had provided the supplemental information in support of its application, and by letter dated January 5, 2017, the NRC staff informed TVA that its application, as supplemented, was acceptable for docketing and detailed technical review.

NRC staff began its detailed technical review of the ESP application in January 2017 and developed a full review schedule with public milestones that was transmitted to TVA on March 17, 2017. The Phase A review for all chapters of the application was completed by the staff on August 4, 2017 (consistent with the established schedule). The staff is currently in Phase B of its review, which is scheduled to conclude on October 29, 2018. As of January 31, 2018, the staff has issued 42 RAI questions and the applicant has responded to 34 RAI questions. Of the RAI questions issued, 81% are closed or are considered confirmatory items.

The final SER is projected to be issued in August 2019.

On June 12, 2017, the Southern Alliance for Clean Energy (SACE), Tennessee Environmental Coalition (TEC), and Blue Ridge Environmental Defense League filed petitions seeking a hearing. On September 12, 2017, the ASLB conducted oral argument on these petitions. On October 10, 2017, the Licensing Board issued a decision that denied the Blue Ridge Environmental Defense Leagues petition to intervene and granted the SACE and the TECs joint petition to intervene and admitted two contentions. SACE/TEC filed a motion for reconsideration of the Boards dismissal of the third contention and the motion was dismissed.

Separately, TVA appealed the admission of the two contentions to the Commission and that appeal is currently pending before the Commission. The Board is working to schedule the contested hearing for the two admitted contentions.

97

45. For reactors under construction, please provide:

Project Name Project Type Licensing Status Vogtle Unit 3 COL Holder COL issued on 02/10/2012 Vogtle Unit 4 COL Holder COL issued on 02/10/2012

a. The number of NRC inspections and ITAAC reviews forecast to be completed per month versus the number completed each month; NRC Inspections Test Analyses and Acceptance Criteria (ITAAC) Inspections:

Comments:

The graph above tracks, by month, the number of ITAAC inspections completed and the number of ITAAC inspections not completed for ITAAC Closure Notifications (ICNs) that had been received. For each ITAAC, there are predetermined inspections to be completed in order to provide assurance that the licensee has met the design commitments and that the ITAAC acceptance criteria are met.

An ITAAC inspection is comprised of multiple inspection activities that may be performed over days, weeks, or months. For this graph, the term ITAAC inspection complete means that all the associated NRC inspection activities tied to that ITAAC have been completed, verified, and marked Inspection Complete in the NRC database. The term ITAAC Inspection Not Complete represents the number of ITAACs for which the completed box in the NRC database has not been checked for ICNs that had been submitted by the licensee. The three items that were not completed for January were due to a Unit 4 construction activity that had not been completed and two ICNs that were submitted at the end of January for which the 0

1 8

3 0

2 4

6 8

10 12 14 Nov-17 Dec-17 Jan-18 Total Number ITAAC Inspections Completion Status ITAAC Inspections Completed ITAAC Inspections Not Complete for ICNs Submitted 2

13

98 associated inspections were not completed. Those two inspections have since been completed.

Because of the coordination between the NRCs inspections and the licensees construction activities, the majority of the required inspections are scheduled and completed prior to the ICN submittal. The completion of these ITAAC-related inspections closely mirrors the completion status of the licensees (Southern Nuclear Operating Company) associated work activities. Changes to the licensees construction schedule due to weather conditions, work sequencing, and other factors impact when NRC inspections can be performed.

ITAAC Closure Notifications Reviews:

The NRCs goal is to complete 90% of ICN reviews within 60 days. However, some ICN reviews may be completed in significantly less time. Conversely, complex ICN reviews may require more than 60 days to complete. For this reason, it is difficult for the NRC to forecast in which month a specific ICN review will be completed based on its submittal date. Therefore, the NRC relies on the metrics reported in its response to question 45.b.

b. The percentage of NRC inspections and the percentage of ITAAC reviews completed within 30 days and within two months; New Reactor Inspection Status:

Comments:

This graph represents the percentage of NRC inspections associated with ITAAC that have been completed since the start of construction with respect to the total number of inspections required for the Vogtle facility.

20.8%

20.8%

20.8%

37.0%

37.4%

37.5%

0%

10%

20%

30%

40%

50%

Nov-17 Dec-17 Jan-18 AP1000 Construction Inspection Completion Progress Vogtle 3 & 4 Program Inspections Completed Vogtle 3 & 4 ITAAC Inspections Completed

99 The ITAAC completion status is updated once inspections are completed, approved, and marked Inspection Complete in the NRC database. Planned inspection activities are evaluated and updated to ensure they align with licensees work activities.

This graph also reports the percentage of completed program inspections since the start of construction for the Vogtle facility, which include both programs required for construction and programs required for operation of Units 3 & 4. There are a total of five construction programs, which include Quality Assurance, Fitness for Duty, and ITAAC Management. In addition, there are a total of 20 operational programs, which include Fire Protection, Emergency Preparedness, Reactor Operator Training, and Security. The graph depicts the percentage of planned inspections that are completed, and does not account for the level of effort required for inspections.

Timeliness of ITAAC Closure Notification Reviews:

Comments:

This bar chart shows the percentage of ICNs reviews completed each month within 30 days and within 60 days. Some of the months shown on the bar chart reflect that the ICN reviews are not meeting the review metric of 90% complete within 60 days. The majority of the delays in these reviews were due to coordination issues between the NRC and the licensee resulting in equipment or activities not being available for scheduled inspections. We are engaging with the licensee to bring attention to those ICNs that require inspection accessibility for timely closure of the ICNs. As the NRC has implemented efficiencies into the process and enhanced communication, the NRC has noticed an improvement in the completion rate. The NRC expects this trend to continue as we move forward.

c. For ITAAC reviews completed during the reporting period, please provide the date when the NRC received the ITAAC closure notice and the date when the review was completed.

For the current reporting period of January 2018, a total of seven ICNs were completed.

100 Month Unit ITAAC Received Date Approval Date

46. For reactors under construction, please provide:
a. The number of license amendment reviews forecast to be completed in the reporting period;
b. The number completed in the reporting period; and
c. The number of those that were completed within 30 days.

Reporting Period Number of License Amendment Reviews Forecast to be Completed in the Reporting Period Number Completed in the Reporting Period Number of Those that were Completed within 30 Days January 2018 5

2 1

47. For reactors under construction, please provide the budgeted resources versus actual expenditures each month for the last 24 months.

The NRC does not formulate the budget on a monthly basis. The annual budget for construction resources is provided below. The monthly budgeted resources provided below are calculated as 1/12th of the annual budgeted construction resources.

FY 2016 Enacted Budget ($K)

$17,169 FY 2017 Enacted Budget ($K)

$14,191 FY 2018 Estimated Budget ($K)

$15,526 Month Budgeted Resources

($K)

Total Expended

($K)

Feb-2016

$1,431

$750 Mar-2016

$1,431

$823 Apr-2016

$1,431

$764 May-2016

$1,431

$844 Jun-2016

$1,431

$857 Jul-2016

$1,431

$946 Aug-2016

$1,431

$1,005

101 FY 2016 Enacted Budget ($K)

$17,169 FY 2017 Enacted Budget ($K)

$14,191 FY 2018 Estimated Budget ($K)

$15,526 Month Budgeted Resources

($K)

Total Expended

($K)

Sep-2016

$1,431

$921 Oct-2016

$1,183

$829 Nov-2016

$1,183

$882 Dec-2016

$1,183

$935 Jan-2017

$1,183

$983 Feb-2017

$1,183

$845 Mar-2017

$1,183

$1,048 Apr-2017

$1,183

$859 May-2017

$1,183

$990 Jun-2017

$1,183

$1,058 Jul-2017

$1,183

$1,129 Aug-2017

$1,183

$886 Sep-2017

$1,183

$808 Oct-2017

$1,294

$837 Nov-2017

$1,294

$926 Dec-2017

$1,294

$882 Jan-2018

$1,294

$878

48. Please provide a concise summary of the status of licensing and inspection for Vogtle 3 & 4, including any challenges to the timely resolution of: licensing issues, 10 CFR Part 52 interpretations, completion of inspections, or completion of ITAAC reviews.

The NRC issued COLs to SNC and several co-owners on February 10, 2012, for two AP1000 units at the Vogtle site near Augusta, GA. As construction progresses, the NRC has increased the pace of construction inspections to verify compliance with the agencys regulations and to ensure that the new plants are constructed in accordance with their COLs. A summary of the license amendment inventory for Vogtle 3 & 4 is included in response to question 13. There are currently no challenges with timely resolution of licensing issues for Vogtle 3 & 4.

The graphs provided in Item 45 of this report represent the completion status of ITAAC inspections and ICN reviews. The completion of these ITAAC-related inspections closely mirrors the completion status of the licensees work activities associated with the ITAAC. The graphs also display the percentage of completed program inspections, which are separate from the ITAAC-related inspections, and include both construction and operational programs. For ITAAC reviews, the NRC tracks the timeliness of ICNs reviewed and closed. In the past year the NRC has increased communication with the licensee and other external stakeholders through various public meetings and workshops to improve processes that support ICN closure, including inspection related activities. With the improvements identified to the processes and increased communication with the licensee, the staff does not foresee any major challenges for 2018.

102

49. Please describe any actions taken in the past 3 years or planned to improve the efficiency of new plant reviews, including milestone schedules to implement efficiency improvements.

Please include any concerns arising from review experience in the past 3 years.

The NRC proactively identifies ways to increase the effectiveness and efficiency of its new reactor reviews. For oversight of licensing activities at the Vogtle site, NRO senior managers have established quarterly meetings with the licensee executives to monitor progress of licensing activities supporting construction at the site. The Licensing Activities Readiness Meetings provide an opportunity for both the NRC and SNC to be strategic in identifying and resolving topics that are needed to support construction.

Similarly, for the NuScale review, the NRC senior managers meet with NuScale executives quarterly. These meetings provide executives from both organizations the opportunity to discuss progress on known review challenges, to identify emerging issues, and to establish timelines for resolving these emerging issues to keep the project review on schedule.

Starting in mid-2017, the NRO management team developed and implemented new internal metrics to better track the timeliness related to the review of license amendment requests supporting Vogtle licensing efforts. These metrics have identified license amendments that have been under lengthy reviews and have focused managements attention on the actions necessary to complete these reviews. The management and project managers meet biweekly to identify amendment requests that may require elevated management attention and to track the progress of license amendments, with particular attention to amendment requests that have been in review for 120 days or longer. NRO management has set an internal goal of completing all license amendment reviews within 180 days of their acceptance. With additional management attention and better use of pre-application meetings, NRO has been able to improve the timeliness of reviews.

NRO has also incorporated many of the lessons-learned from previous new reactor reviews into its review activities for the active DC and ESP applications. As described in response to question 24, NRO implemented an initiative in 2016 to improve the focus of RAIs, which has improved the quality and safety focus of information requests. The staff is also enhancing use of the regulatory audit tool.

NRO has instituted an Enhanced Safety Focus Review initiative for the NuScale design certification review. This initiative focuses the staffs review on first-of-a-kind or high safety, high risk areas of the design, and simplifies the review of lower safety or risk significant areas.

In addition, the NRC has made significant progress on initiatives to enhance the regulatory framework for non-light water reactors (non-LWRs). For example, in December 2017, the NRC issued the Regulatory Review Roadmap for Non-Light Water Reactors, which described flexible review options including the use of a staged-review process and the use of conceptual design assessments during the pre-application period. The actions for advanced reactor reviews are described more fully in response to question 52.

103

50. Please provide a list of any unresolved policy issues with regard to the licensing of small modular light-water reactors (SMRs). Please include an approximate date for when each issue was first raised, any actions taken or planned to resolve the issue, the milestone scheduled for resolution, and the projected date for resolution.

Issue Title/Applicability Status References I. Appropriate Source Term, Dose Calculations, and Siting for SMRs Applicability: SMRs and non-LWRs In the December 29, 2011, memorandum to the Commission, the staff stated it would remain engaged with SMR stakeholders regarding applications of mechanistic source term (MST) methods, review of pre-application white papers and topical reports it receives from potential SMR applicants concerning source term issues that discuss design-specific proposals to address MST, and considerations of research and development in this area. If necessary, the staff would propose revised review guidance or regulations, or propose new guidance to support reviews of SMRs.

In Commission Memoranda dated May 30, 2013, and June 20, 2014, the staff provided updates on interactions with DOE and nuclear industry organizations regarding MST. On February 7, 2016, the staff provided the Commission SECY 16-0012, which addressed this item. The paper concluded that (1) SMR and non-light water reactor (non-LWR) applicants can employ modern analysis tools to demonstrate quantitatively the safety features of those designs, and (2) MST analysis methods can also be used by applicants to demonstrate the ability of the enhanced safety features of plant designs to mitigate accident releases, allow future COL applicants to consider reduced distances to Exclusion Area Boundaries and Low Population Zones and potentially increase proximity to population centers.

Disposition: The staff has engaged with interested stakeholders on this issue in 2017.

The staff developed a draft white paper summarizing the assessment of current siting regulations, guidance, and Commission policy and discussed it in a public meeting on December 14, 2017. The staff will consider insights obtained from stakeholder discussions and determine whether clarifications to siting guidance or other actions would be beneficial to address siting criteria for SMRs and non-LWRs.

The staff will report to the Commission on any Staff Draft White Paper (11/29/17)

SECY-16-0012 (02/07/16)

Commission Memo (06/20/14)

Commission Memo (05/30/13)

Commission Memo (12/29/11)

104 Issue Title/Applicability Status References proposed actions, as described in SECY 0012.

II. Offsite Emergency Planning (EP)

Requirements for SMRs and other new technology.

Applicability: SMRs and non-LWRs In SECY-11-0152, staff identified a possible approach for a scalable emergency planning zone for SMRs. The NRO staff is working with NSIR and NRR on an internal working group to review these issues further. As part of the approach, the staff would liaise with other stakeholders (Department of Homeland Security/Federal Emergency Management Agency, the Environmental Protection Agency, Department of State, Department of Commerce, NEI, American Nuclear Society, and the public),

consider industry position papers on this topic and develop recommendations.

In a May 30, 2013, Commission Memorandum, the staff provided updates on its EP activities.

The staff stated that it would not propose new policy or revise guidance for specific changes to EP requirements absent specific proposals from the industry.

On December 23, 2013, NEI submitted a white paper on this topic. The staff conducted a public meeting to discuss the white paper on April 8, 2014, issued follow-up questions to NEI on June 11, 2014, and received NEI responses in November 2014. On May 29, 2015, staff issued SECY-15-0077 regarding EP for SMRs and non-LWRs. On August 4, 2015, the Commission approved the staff's recommendation to initiate a rulemaking. Staff developed SECY-16-0069, which discussed the rulemaking plan and schedule. On June 22, 2016, the Commission approved the staff's plan and schedule for the rulemaking.

Disposition: The rulemaking will address EP issues for future SMRs, non-LWR, and other new design technologies such as isotope producing facilities. The Commission directed the staff to utilize exemptions in the interim (e.g.,

for the TVA ESP) until completion of the EP rulemaking. The draft regulatory basis was published for public comment in the Federal Register on April 13, 2017. A public meeting was held May 10, 2017, to discuss the draft regulatory basis. The public comment period closed on June 27, 2017. After considering the Final Regulatory Basis (10/16/17)

SRM-SECY 0069 (06/22/16)

SECY-16-0069 (05/31/16)

SRM-SECY 0077 (08/04/15)

SECY-15-0077 (05/29/15)

NEI Response to NRC Questions on White Paper (11/19/14)

NRC Letter to NEI (R. Bell)

(06/11/14)

NEI White Paper (12/23/13)

Commission Memo (05/30/13)

SECY-11-0152 (10/28/11)

105 Issue Title/Applicability Status References public comments, the staff issued the final regulatory basis on October 16, 2017. The proposed rule is scheduled to be provided to the Commission for its consideration in October 2018.

III. Insurance and Liability for SMRs Applicability: SMRs and non-LWRs In SECY-11-0178, the staff identified a potential inequity between the insurance requirements for power reactors producing electrical power equal or greater than 100 MWe per unit and those SMR designs with individual modules producing less than 100 MWe. Specifically, staff raised the question of whether there would be insurance and indemnity coverage sufficient to pay all public claims in the case of an insurable event for an SMR with an individual module sized at less than 100 MWe under the current Price-Anderson Act and associated regulatory language.

Since completing that paper, staff prepared a comparative analysis of different SMR designs to further explore the potential inequity. Staff is using this analysis, and other inputs, to develop a SECY paper for this topic. In the paper, staff will identify whether rulemaking or a change to the current interpretation of the definitions given in the Price-Anderson Act is recommended.

Disposition: In accordance with the latest version of the Price-Anderson Act, the NRC will prepare a report to Congress, and an associated SECY paper, recommending the need for continuation or modification of the provisions of the Price-Anderson Act by December 31, 2021.

Any changes that may be needed for non-LWRs and SMRs will be addressed by the staff in that report and SECY paper.

The staff engaged stakeholders on this topic during a November 2, 2017, public meeting and is awaiting feedback.

SECY-11-0178 (12/22/11)

IV. Security and Safeguards Requirements for SMRs Applicability: SMRs and non-LWRs In SECY-11-0184, staff informed the Commission of its determination that the current regulatory framework is adequate to certify, approve, and license light-water SMRs, the manufacturing of SMR fuel, transportation of special nuclear material and irradiated fuel, and the interim storage of irradiated fuel proposed for light-water SMRs under 10 CFR Parts 50, 52, 70, 71, and 72, respectively. The staff also Staff Draft White Paper (11/29/17)

NEI White Paper (12/14/16)

106 Issue Title/Applicability Status References determined that security and material control and accounting requirements in 10 CFR Parts 72, 73, and 74, respectively, are also adequate.

In the case of non-LWRs, the staff's preliminary conclusion is that the current security regulatory framework is comprehensive and sufficiently robust to certify, approve, and license non-LWRs. Sufficient provisions are available to provide flexibility for designers and applicants to meet performance-based and prescriptive security requirements and to apply methods or approaches to achieve the objective of high assurance that activities involving special nuclear materials are not inimical to the common defense and security and do not constitute an unreasonable risk to public health. On December 14, 2016, NEI submitted a white paper on a "Proposed Consequence-Based Physical Security Framework for Small Modular Reactors and Other New Technologies." This paper "... proposes an approach to security that considers the enhanced safety and security incorporated into these designs and provides a more effective and efficient means to protect the public health and safety." In the transmittal letter, NEI requests that "... the NRC establish regulatory positions on this approach and the associated policy and technical issues." NEI submitted a fee waiver request for NRCs review of this white paper.

Disposition: The NRC has approved NEI's fee waiver request and met with NEI on May 3, 2017, to discuss the review of their submittal.

The NRC provided feedback on NEIs white paper in July 2017, and met with NEI again on October 12, 2017. The staff prepared a draft white paper to facilitate stakeholder interactions.

The staff discussed this white paper with NEI and other stakeholders on December 13, 2017.

The staff will consider stakeholder feedback and plans to prepare a SECY paper in 2018 to address this issue.

SECY-11-0184 (12/29/11)

V. Functional Containment Performance Applicability: Non-LWRs In SECY-93-0092, Issues Pertaining to the Advanced Reactor (PRISM, MHGTR, and PIUS) and Candu 3 Designs and their Relationship to Current Regulatory Requirements, the staff proposed to evaluate the acceptability of proposed designs using a standard based upon Staff Draft White Paper (11/27/17)

SECY-93-092 dated 04/08/93

107 Issue Title/Applicability Status References containment functional performance rather than to rely exclusively on prescriptive containment design criteria. The staff also informed the Commission that it intended to approach this by comparing containment performance with the accident evaluation criteria. In SRM-SECY 0092, the Commission approved the staff's recommendation.

Subsequently, in SECY-03-0047, the staff recommended that the Commission approve the use of functional performance requirements to establish the acceptability of a containment or confinement structure (i.e., a non-pressure retaining building may be acceptable provided the performance requirements can be met) and the staff proposed that functional performance requirements be developed. In SRM-SECY 0047, the Commission disapproved the staffs recommendation stating that there was insufficient information at the time for the Commission to prejudge the best options and make a decision on the viability of a confinement building. The Commission directed the staff to develop performance requirements and criteria working closely with industry experts (e.g.,

designers, EPRI, etc.) and other stakeholders regarding options in this area, taking into account such features as core, fuel, and cooling systems design. The Commission also directed the staff to pursue the development of functional performance standards and then submit options and recommendations to the Commission.

In SECY-05-0006, the staff discussed many of the concepts developed in previous communications between the staff and Commission on the topic of functional containment performance and, as directed in SRM-SECY-03-0047, outlined the attributes for a functional containment. The topic of functional containment was also addressed as part of the next-generation nuclear plant (NGNP) project in the context of high-temperature gas-cooled reactors. More recently, in light of the broad range of non-light water designs under consideration, the staff has determined that it would be beneficial to seek Commission direction to support development and possible deployment of advanced reactor technologies.

SRM-SECY 092, dated 07/30/93 SECY-03-0047, dated 03/28/03 SRM-SECY 0047, dated 06/26/03 SECY-05-0006, dated 01/07/05

108 Issue Title/Applicability Status References The staff plans to engage the Commission to confirm whether the Commission direction in SRM-93-0092 should be applied more broadly to additional advanced reactor designs and to propose a risk-informed, performance-based approach to establishing performance criteria for structures, systems, and components and corresponding programs to limit the release of radioactive materials from advanced reactors.

Disposition: The staff has engaged stakeholders on this topic at several public meetings. The staff prepared a draft white paper on functional containment performance to facilitate stakeholder interactions. The staff discussed this white paper with stakeholders on December 14, 2017, and February 1, 2018, and with the ACRS on February 22, 2018. The staff will consider ACRS and stakeholder feedback and plans to prepare a SECY paper in 2018 to address this issue.

51. Please provide a list of any unresolved policy issues with regard to the licensing of advanced non-light water reactors. Please include an approximate date for when each issue was first raised, any actions taken or planned to resolve the issue, the milestone schedule, and the projected date for resolution.

See response to question 50. All of the SMR policy issues listed in that response are also applicable to non-light water designs. In addition, there is one non-light water specific issue included on that list: functional containment performance.

52. Please describe the status of preparations to review non-light water reactor applications including a milestone schedule and completion dates.

The agency has developed a vision and strategy to assure NRC readiness to conduct its mission for these technologies effectively and efficiently as described in NRC Vision and Strategy: Safely Achieving Effective and Efficient Non-Light Water Reactor Mission Readiness, which was published in the Federal Register on July 21, 2016, for stakeholder input. The NRC updated this document (ADAMS Accession No. ML16356A670) to reflect stakeholder feedback and made it publicly available in December of 2016.

The NRCs non-LWR vision and strategy has three strategic objectivesenhancing technical readiness, optimizing regulatory readiness, and optimizing communication. The NRC has developed implementation action plans (IAPs) to identify the specific activities the NRC will conduct in the near-term (0-5 years), mid-term (5-10 years), and long-term (beyond 10 years) timeframes to achieve non-LWR readiness. In the fall of 2016, the NRC released its draft near-term IAPs to obtain stakeholder feedback. The staff also developed draft mid-and long-term IAPs, which were released to the public in February of 2017. The staff updated its IAPs to reflect stakeholder feedback in July of 2017 (ADAMS Accession Nos. ML17165A069 and ML17164A173).

109 There are 6 individual strategies addressed in the near-term IAPs. These strategies, and the activities in support of each strategy, are discussed below.

Strategy Activities in support of the strategy

1) Acquire/develop sufficient knowledge, technical skills, and capacity to perform non-LWR regulatory activities NRC contracted with the Oak Ridge National Laboratory to develop a 12-module training course on Molten Salt Reactors (MSRs). The course provided background on various MSR concepts presently under development, including history of earlier MSR projects, descriptions of conceptual designs, and expected technical and regulatory challenges. About 90 NRC staff attended the training along with several DOE staff in three separate 2-day sessions in May, August, and November 2017.

NRC developed models of the competencies required for reviewing advanced reactor designs. Project managers and technical reviewers in NRO are currently in the process of assessing their skills against the models. Supervisors will also be able to complete an independent assessment of their employees skills. Based on assessment results, any skill gaps that may exist can be identified and the system will help the employee identify developmental activities and create an individual development plan to close those gaps.

2) Acquire/develop sufficient computer codes and tools to perform non-LWR regulatory reviews Staff attended DOE and NRC-sponsored workshops and technology working groups, sought additional information through pre-application interactions, and focused its training efforts to better understand the reactor systems under development. In the near-term, these efforts are focused on the following areas:

Reactor Kinetics and Criticality, Fuel Performance, Thermal-Fluid Phenomena, Severe Accident Phenomena, Offsite Consequence Analysis, Materials and Component Integrity, and PRA.

An initial screening of analysis codes for design-basis and beyond-design-basis event simulation was completed, and a suite of tools for further examination and consideration has been identified. The code suite comprises both NRC-developed and DOE-developed codes. Future efforts will evaluate codes in the code suite against analysis requirements.

A Phenomena Identification and Ranking Table (PIRT) exercise was conducted for molten salt reactors. The PIRT focused attention on fuel salt MSRs due to their novel and unique feature of fuel being part of the

110 Strategy Activities in support of the strategy coolant. The PIRT is considered preliminary in that design specifics are not available, but it is useful in that several phenomena requiring simulation could be identified based on existing information.

Staff completed a PRA report that summarizes previous work and issues for non-LWRs and identifies several policy decisions that may need to be made for non-LWRs.

3) Develop guidance for a flexible non-LWR regulatory review process within the bounds of existing regulations, including the use of conceptual design reviews and staged-review processes In October 2017, the staff issued a preliminary draft of A Regulatory Review Roadmap for Non-Light Water Reactors (ADAMS Accession No. ML17279B177),

and discussed it with stakeholders on November 2, 2017. The NRC issued the final regulatory review roadmap on December 26, 2017.

In June 2017, the NRC issued a preliminary draft document, "Nuclear Power Reactor Testing Needs and Prototype Plants for Advanced Reactor Designs,"

to solicit stakeholder feedback (ADAMS Accession No. ML17025A353). This document describes the relevant regulations governing the testing requirements for advanced reactors, describes the process for determining testing needs to meet the NRC's regulatory requirements, clarifies when a prototype plant might be needed and how it might differ from the proposed standard plant design, and describes licensing strategies and options that include the use of a prototype plant to meet the NRC's testing requirements. The NRC addressed stakeholder feedback and issued the final prototype document as part of the Regulatory Review Roadmap on December 26, 2017.

On February 3, 2017, the NRC issued draft regulatory guide DG-1330, "Guidance for Developing Principal Design Criteria for Non-Light Water Reactors" for formal public comment. The staff briefed the ACRS subcommittee on the draft final regulatory guide on February 7, 2018, and will brief the ACRS full Committee in March 2018. The NRC then plans to issue the final regulatory guide in the spring of 2018.

The NRC is supporting activities related to the Licensing Modernization Project (LMP) being led by Southern Company, coordinated by the NEI, and cost-shared by DOE. The LMP's objective is to develop technology-inclusive, risk-informed, and performance based regulatory guidance for licensing non-LWRs for

111 Strategy Activities in support of the strategy the NRCs consideration and possible endorsement.

The NRC has reviewed four LMP white papers and provided feedback to industry stakeholders:

Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors -

Selection of Licensing Basis Events (ADAMS Accession No. ML17104A254), Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors - Probabilistic Risk Assessment Approach (ADAMS Accession No. ML17158B543), Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors: Safety Classification and Performance Criteria for Structures, Systems, and Components (ADAMS Accession No. ML17290A463), and Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors: Risk-Informed and Performance-Based Evaluation of Defense-in-Depth Adequacy (ADAMS Accession No. ML17354B174). The staff is expecting NEI to submit a consolidated guidance document for NRC review and possible endorsement.

4) Facilitate industry codes and standards needed to support the non-LWR life cycle (including fuels and materials)

The NRC staff is actively participating in subgroups and working groups associated with the development of ASME Boiler and Pressure Vessel (B&PV) Code,Section III, Division 5. NRC staff is also participating in the Task Group on ASME/NRC Liaison for Division 5 that seeks NRC, DOE, and industry input in identifying gaps in ASME B&PV Code Section III, Division 5, which need to be resolved prior to considering endorsement in 10 CFR 50.55a. The staff discussed this topic during a public meeting on December 14, 2017. ASME plans to send a letter to the staff confirming that advanced reactor developers support NRC endorsement of the 2017 edition of ASME Section III, Division 5, rather than waiting for a later edition. ASME also plans to submit a technical basis document for the 2017 edition.

The staff is actively participating on several American Nuclear Society (ANS) standards working groups and consensus committees related to non-LWR safety standards and the joint ASME/ANS non-LWR PRA standard.

On September 26, 2017, the NRC held the second annual NRC Standards Forum, which was attended by representatives from many standards development

112 Strategy Activities in support of the strategy organizations, representatives from industry (NEI, the Electric Power Research Institute, and Technology Working Groups for non-LWRs), and representatives from DOE and DOE national labs. A portion of this years standards forum was devoted to non-LWRs with the intent of working with stakeholders to identify new codes and standards needed for non-LWR development and to facilitate the codes and standards development and eventual endorsement by the NRC, as appropriate. A follow-up workshop on advanced reactor standards development is planned for May 2018.

5) Identify and resolve technology-inclusive (not specific to a particular non-LWR design or category) policy issues that impact regulatory reviews, siting, permitting, and/or licensing of non-LWR nuclear power plants The NRCs key activities related to the resolution of policy issues in support of near-term IAP strategy 5 are discussed in response to questions 50 and 51 above.
6) Develop and implement a structured, integrated strategy to communicate with internal and external stakeholders having interests in non-LWR technologies The NRC is conducting public meetings with stakeholders every 4 to 6 weeks. The NRC uses these stakeholder meetings to solicit input on policy and process issues related to the possible licensing and regulation of non-LWR technologies.

The NRC and DOE hosted a series of three Advanced Non-LWR Workshops. The most recent workshop was held on April 25 and 26, 2017. This series of workshops focused on opening a dialogue between key stakeholders to discuss challenges in the commercialization of non-LWR technologies and to discuss possible solutions.

On November 10, 2016, the NRC and DOE signed a MOU (ADAMS Accession No. ML16215A382) on the Gateway for Accelerated Innovation in Nuclear (GAIN)

Initiative. GAIN is an initiative that is intended to provide the nuclear energy community with increased access to the technical, regulatory, and financial support necessary to move new or advanced nuclear reactor designs toward commercialization while ensuring the continued safe, reliable, and economic operation of the existing nuclear fleet. As described in the MOU, the NRC is responsible for providing DOE and the nuclear energy community with accurate,

113 Strategy Activities in support of the strategy current information on the NRCs regulations and licensing processes.

The NRC will continue to share information with various international groups, including the Organization for Economic Co-operation and Developments Nuclear Energy Agency (NEA), the International Atomic Energy Agency, the Generation IV International Forum, and the NRCs international regulatory counterparts. The NRC chairs NEAs ad hoc group for international regulators of non-LWRs known as the Group on the Safety of Advanced Reactors. The purpose of the group is to bring interested regulators together to discuss common interests, practices, and problems, and address both the regulatory interests and research needs.