UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 11, 2014 Mr. Dean Curtland Site Vice President Seabrook Station NextEra Energy 626 Lafayette Road Seabrook, NH 03874

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE SEABROOK STATION NUCLEAR PLANT LICENSE, RENEWAL APPLICATION (TAC NO. ME4028)

Dear Mr. Curtland:

By letter dated May 25, 2010, NextEra Energy Seabrook, LLC submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew the Operating License No. NPF-86 for Seabrook Station, Unit 1 (Seabrook), for review by the U.S. Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the schedule for the Seabrook license renewal review.

Regarding the staffs safety review, by letter dated May 31, 2012, the staff issued a letter revising the environmental and safety review schedules. The safety review schedule was modified with TBD (To Be Determined) as the milestone dates for issuing a final Safety Evaluation Report (SER) and convening the Advisory Committee on Reactor Safeguards (ACRS) full committee meeting, due to the uncertainty in the amount of time required to fully resolve the alkali-silica reaction (ASR) open item. By letter dated December 16, 2013, the staff issued a letter again revising the environmental and safety review schedules. This revision established a milestone for a second ACRS sub-committee meeting to discuss resolution of the ASR open item, also with TBD as its milestone date.

In the interests of greater transparency and planning, achievable milestone dates have been set for the second ACRS sub-committee meeting, SER publication and ACRS full committee meetings. These dates assume timely and adequate responses to staff RAIs and the staffs determination that the proposed activities to manage the effects of aging due to ASR, as well as all other open items, comply with 10 CFR Part 54.

Regarding the staffs environmental review, by letter dated July 2, 2014, the staff issued a letter revising the environmental review schedule. This revision established an October 2014 issuance date for the final Supplemental Environmental Impact Statement (SEIS). In finalizing the final SEIS, the staff has been reviewing all of the comments submitted on the draft SEIS issued in 2011 and has determined that more time is needed to ensure complete and up-to-date responses are provided. The new issuance date for the final SEIS is February 2015.

D. Curtland Enclosed is the NRC staff's revised review schedule for the Seabrook license renewal application. If you have any questions related to this revised safety schedule, please contact Jeffrey Mitchell at 301-415-3019 or by e-mail at Jeffrey.Mitchell2@nrc.gov. If you have any questions related to the revised environmental schedule, please contact Lois James at 301-415-3306 or by e-mail at Lois.James@nrc.gov.

Sincerely,

/RA/

John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-443

Enclosure:

Revised Schedule cc w/encl: Listserv

ML14223B144 *Concurred via e-mail OFFICE LA:DLR PM:RPB2:DLR PM:RPB1:DLR BC:RPB2:DLR BC:RPB1:DLR D:DLR NAME *YEdmonds LJames (EGettys for) RPlasse BWittick YDiaz-Sanabria JLubinski DATE 8/20/2014 9/10/14 8/20/14 9/11/14 9/11/14 9/11/14

SEABROOK STATION NUCLEAR PLANT LICENSE RENEWAL APPLICATION SCHEDULE REVISION Milestone Schedule Actual Receive license renewal application (LRA) 6/01/10 6/01/10 Publish Federal Register notice (FRN) - LRA availability 6/14/10 6/16/10 Publish FRN - acceptance/rejection and opportunity for hearing 7/23/10 7/21/10 Publish FRN - intent to conduct environmental scoping 7/23/10 7/10/10 Public Meeting - License Renewal Overview and Environmental Scoping 8/19/10 8/19/10 Meeting Deadline for filing hearing requests and petitions for intervention 9/20/10 10/20/10 Environmental scoping period ends 9/21/10 9/21/10 Audit - environmental 10/04/10 10/05/10 Issue draft supplemental environmental impact statement (SEIS) 8/2011 8/01/11 Publish FRN - draft SEIS available for comments 8/2011 8/12/11 Public Meeting - draft SEIS meeting 9/2011 9/15/11 End of draft SEIS comment period 11/2011 10/26/11 Issue safety evaluation report (SER) with open items 6/2012 6/08/12 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee 7/2012 7/10/12 Meeting Issue draft supplement to the Seabrook Station (Seabrook) draft SEIS 4/2013 4/2013 Publish FRN - draft supplement to the Seabrook draft SEIS available 4/2013 4/2013 for comments.

End of comment period on the draft supplement to the Seabrook draft SEIS 6/2013 6/2013 Issue final SEIS 2/2015 Proposed Second ACRS Subcommittee Meeting 6/2015 Issue Final SER 11/2015 ACRS Full Committee Meeting 1/2016 Decision - Director, Office of Nuclear Reactor Regulation 3/2016 ENCLOSURE

Letter to D. Curtland from J. Lubinski dated September 11, 2014

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE SEABROOK STATION NUCLEAR PLANT LICENSE, RENEWAL APPLICATION (TAC NO. ME4028)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource Listserv


Jeffrey.Mitchell2@nrc.gov Lois.James@nrc.gov Richard.Plasse@nrc.gov Brian.Wittick@nrc.gov Yoira.Diaz-Sanabria@nrc.gov John.Lamb@nrc.gov David.McIntyre@nrc.gov Eugene.Dacus@nrc.gov Brian.Harris@nrc.gov Glenn.Dental@nrc.gov Paul.Cataldo@nrc.gov Chris.Newport@nrc.gov Jasmine.Gilliam@nrc.gov Nancy.McNamara@nrc.gov Doug.Tiff@nrc.gov Neil.Sheehan@nrc.gov Diane.Screnci@nrc.gov