Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 17, 2011 Mr. John Conway Senior Vice President, Generation and Chief Nuclear Officer Pacific Gas and Electric Company 77 Beale Street, MC B32 San Francisco, CA 94105 SUB~IECT: REVISION OF SCHEDULE FOR THE REVIEW OF THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. Conway:

Enclosed is a revised schedule for the review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, license renewal application. The schedule has been updated to reflect a change in the date for the issuance of the Draft Supplemental Environmental Impact Statement (SEIS) and subsequent milestones.

The U.S. Nuclear Regulatory Commission (NRC or the staff) plans to issue the Draft SEIS in May 2011. This change will also affect the date of the public meeting to receive comments on the Draft SEIS, which will now be scheduled for the JunelJuly timeframe, with a specific date yet to be determined. The NRC staff requires this additional time to complete our review of severe accident mitigation alternatives and to allow for internal review of the SEIS in a manner which balances the internal workload across numerous ongoing reviews. At this point, the staff has extended the date for issuance of the Final SEIS to January 2012.

If you have any questions on the reviseq schedule, please contact Drew Stuyvenberg at 301-415-4006 or bye-mail at andrew.stuyvenberg@nrc.gov.

Sincerely, Brian E. Holian Division of licensE-' Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323

Enclosure:

Revised Schedule cc w/encl: Distribution via Listserv

DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 11/24/2009 11/24/2009 Publish Federal Register Notice (FRN) - LRA availability 12/11/2009 12/11/2009 Publish FRN - acceptance/rejection and opportunity for hearing 01/21/2010 01/21/2010 Publish FRN Intent to conduct Environmental Scoping 01/21/2010 01/27/2010 Public Meeting -license renewal overview ~O10 02/09/2010 Public Meeting - environmental scoping meeting 010 03/03/2010 Deadline for filing hearing requests and petitions for intervention 03/22/2010 03/22/2010 Audit - Scoping & Screening Methodology 03/15/2010 03/15/2010 Environmental scoping period ends 04/12/2010 04/12/2010 Audit - Aging Management Programs 04/12/2010 04/12/2010 Audit - Environmental 04/19/2010 04/19/2010 Issue environmental requests for additional information (RAls) 05/03/2010 07106/2010 Receive responses for environmental RAls 06/03/2010 08/05/2010 Issue safety RAls 06/23/2010 05/18/2010 Receive responses for safety RAls

~10 06/03/2010 Inspection - Regional 10 09/13/2010 Issue safety evaluation report (SER) with open items 12/10/2010 01/09/2011 Advisory Committee on Reactor Safeguards (ACRS) 02/2011 02/09/2011 meeting R 05/23/2011 Issue draft supplemental environmental impact statement OS/2011 (SEIS)

Publish EPA FRN - draft SEIS available for comments 1 Public Meeting - draft SEIS meeting 06/2011 or 07/2011 ACRS Full Committee meeting 07/2011 End of draft SEIS comment period 08/2011 Issue final SEIS 01/2012 Publish EPA FRN - availability of final SEIS 01/2012 License Renewal decision TBD*

  • Pendlng outcome of adjudicatory heanngs and Coastal Zone Management Act consistency certification ENCLOSURE

ML110140904 *concurred via e-mail OFFICE n *. ono'):DLR LA:DLR* BC:RPB2:DLR OGC (NLO)* D:DLR NAME AStuyvenberg SFigueroa DWrona SUttal BHolian DATE 2/11/11 F 2/15111 2/16/11

Letter to J. Conway from B. Holian dated February 17. 2011 SUB..IECT: REVISION OF SCHEDULE FOR THE REVIEW OF THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARDCOPY:

DLRRF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsOgcMailCenter Resource NFerrer DWrona AStuyvenberg KGreen AWang GMiller, RIV NO'Keefe, RIV GPick, RIV CCasto, RIV ICouret, OPA VDricks, OPA WMaier, RIV JWeil,OCA EWilliamson, OGC SUttal,OGC RRihm, EDO TBrown, RIV MPeck, RIV