ML102300092
| ML102300092 | |
| Person / Time | |
|---|---|
| Site: | Indian Point |
| Issue date: | 08/31/2010 |
| From: | David Wrona License Renewal Projects Branch 2 |
| To: | Joseph E Pollock Entergy Nuclear Operations |
| Stuyvenberg, A L, NRR/DLR, 415-4006 | |
| References | |
| Download: ML102300092 (4) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 August 31,2010 Mr. Joseph E. Pollock Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249
SUBJECT:
REVISION OF SCHEDULE FOR REVIEW OF THE INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3, LICENSE RENEWAL APPLICATION
Dear Mr. Pollock:
Enclosed is a revised schedule for the review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, license renewal application. The schedule has been updated to reflect a change in the date for the issuance of the Final Supplemental Environmental Impact Statement (SEIS).
The staff plans to issue the Final SEIS by November 19, 2010. This delay is a result of the staff time necessary to finalize the document. As you are aware, the U.S. Nuclear Regulatory Commission has received sjgnificantly more comments from stakeholders during the course of this environmental review than in any other license renewal review to date.
If you have any questions on the revised schedule, please contact me at 301-415-2292. For questions on the environmental review, please contact Drew Stuyvenberg at 301-415-4006 or bye-mail at andrew.stuyvenberg@nrc.gov.
Sincerely,
- \\UJ 9-o/~
David J. Wrona, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286
Enclosure:
Revised Schedule cc w/encl: Distribution via Listserv
INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 LICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestone Schedule Actual Receive License Renewal Application (LRA) 4/30/07 4/30/07 Federal Register Notice (FRN) Published - Receipt & Availability 5114/07 5/11/07 Public Meeting - License Renewal Overview 6/27/07 6/27/07 FRN Published - Acceptability/Opportunity for Hearing & Intent 8/1107 8/1/07 FRN Published - Notice of Intent to Conduct Environmental Scoping 8/10/07 8/10/07 Audit - Aging Management Programs (AMPs) and Time-Limited Aging Analyses (TLAAs) 8/27-31/07 8/27-31/07 Audit - Environmental 9/10-14/07 9/10-14/07 9/24-26/07 9/24-26/07 Public Meeting - Environmental Scoping 9/19/07 9/19/07 Audit - Scoping & Screening Methodology 10/9-12/07 10/9-12/07 Environmental Scoping Period Ends 10/12107 10112107 Audit - Aging Management Reviews (AMRs) 10/22-26/07 10/22-26/07 Audit - AMPITLAAlAMR 11127-29/07 11127-29107 Deadline for Filing Hearing Requests and Petitions for Intervention 11/30/07 11/30107 Environmental Requests for Additional Information (RAls) Issued 12/10107 =
1215/07 Environmental RAls - Response Received 1/14/08 3/7108 Inspection - Regional 1/28-2/1/08 2/11-15/08 1/28-2/1/08 2/11-15/08 Audit - 4th Optional AMPffLAAlAMR 2/19-21/08 2/19-21/08 Safety RAls - Issued 3/28/08 5/28/08 Safety RAls - Responses Received 4/~~
6/27/08 Public Exit Meeting - Regional Inspections 6/18/08 6/18/08 Draft Supplemental Environmental Impact Statement (SEIS) issued 12/12/08 12/22/08 FRN Published - Availability 1Comment on draft SEIS 12/19/08 12/31/08 Safety Evaluation Report (SER) with Open Item(s) - Issued 1/5/09 1/15/09 Public Meeting - draft SEIS 2/09 2/12109 End of draft SEIS Comment Period 3/18/09 3/18/09 ACRS Subcommittee Meeting on SER with Open Item(s) 3/4/09 3/4/09 SER Open Item(s) - Response(s) Received 3/16/09 3/12/09 Inspection-Final Optional TBD N/A SER - Issued 7/27/09 8/11/09 ACRS Full Committee Meeting on SER 9/10/09 9/10109 Final SEIS - Issued 11/19/10 FRN Published - Availability of Final SEIS 12/3110 Commission Decision (hearing pending)
TBD ENCLOSURE
ML102300092 I OFFICE PM:RPB2:DLR LA:DLR BC:RPB2:DLR OGC D:DLR BC:RPB2:DLR NAME AStuyvenberg IKing DWrona STurk BHolian (MGalioway for)
DWrona DATE 08/19/10 08/19/10 108/19/10 8130110 8/31/10 8/31/10
Letter to Joseph E. Pollock from David J. Wrona dated August 31, 2010
SUBJECT:
REVISION OF SCHEDULE FOR REVIEW OF THE INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3, LICENSE RENEWAL APPLICATION DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDraAfpb Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource DWrona EDacus,OCA BPham GMeyer, RI KGreen RConte, RI AStuyvenberg JBoska RAuluck DScrenci, RI OPA JDozier NSheehan, RI OPA MKowal PCataldo, RI STurk,OGC CHott, RI DJackson, RI NMcNamara, RI BMizuno,OGC BWelling, RI SBumell,OPA ECobey, RI DMclntyre, OPA TKoonce, RI TMensah, OEDO GMalone, RI