Letter Sequence Approval |
---|
TAC:ME4028, Steam Generator Tube Integrity (Approved, Closed) |
Results
Other: ML103620318, ML110270026, ML110280424, ML110970260, ML11280A045, ML11304A002, ML11304A109, ML12009A007, ML12164A756, ML12164A759, ML12214A607, ML12242A198, ML12264A648, ML13261A145, ML15149A280, ML15149A282, ML15183A020, ML15287A017, ML15307A022, ML15310A102, ML15337A047, ML15343A186, ML15349A918, ML19205A362, ML19205A365, ML19205A389, SBK-L-15073, Responses to Applicant/Licensee Action Items for the Inspection and Evaluation Guidelines for Pressurized Water Reactor Vessel Internals (MRP-227-A)
|
MONTHYEARML1036203182010-01-21021 January 2010 Attachment 2, Document SEA-FLU-001-R-004, Rev 0, Non-Proprietary Version of Seabrook Station Reactor Pressure Vessel Fluence Evaluation at 55 EFPY Project stage: Other ML1022205712010-08-10010 August 2010 License Renewal Process Overview and Scoping Public Meeting Slides Project stage: Meeting ML1025202222010-09-20020 September 2010 Summary of Public License Renewal Overview and Environmental Scoping Meeting Related to the Review of the Seabrook Station License Renewal Application (TAC No. ME3959 and ME4028) Project stage: Meeting ML11307A1392010-10-28028 October 2010 2010/10/28 Seabrook Lr - FW: Seabrook Station, Unit No. 1 - Fire Protection Request for Additional Information Regarding License Renewal Application Project stage: RAI SBK-L-10192, Supplement 2 to License Renewal Application2010-11-15015 November 2010 Supplement 2 to License Renewal Application Project stage: Supplement ML1030905582010-11-18018 November 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application - Aging Management Programs Project stage: RAI ML1030903082010-11-18018 November 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application Project stage: RAI ML1031301592010-11-18018 November 2010 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1032605542010-12-14014 December 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application (TAC No. ME4028) Aging-Management Programs Project stage: RAI ML1034202732010-12-14014 December 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application (TAC No. ME4028) - Aging Management Programs Project stage: RAI SBK-L-10204, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs2010-12-17017 December 2010 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs Project stage: Response to RAI SBK-L-10203, Response to Request for Additional Information Set 2 Related to the Review of the License Renewal Application2010-12-22022 December 2010 Response to Request for Additional Information Set 2 Related to the Review of the License Renewal Application Project stage: Response to RAI ML1034205872011-01-0505 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1034205852011-01-0505 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1034205832011-01-0505 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11003, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 52011-01-13013 January 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 5 Project stage: Response to RAI SBK-L-11002, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 42011-01-13013 January 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 4 Project stage: Response to RAI ML1100701282011-01-21021 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11015, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Sets 6, 7 and 82011-02-0303 February 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Sets 6, 7 and 8 Project stage: Response to RAI ML1102700262011-02-0404 February 2011 Scoping and Screening Audit Summary Regarding the Seabrook Station License Renewal Application (TAC Number ME4028) Project stage: Other SBK-L-11027, Response to Request for Additional Information, License Renewal Application, Request for Additional Information - Set 92011-02-18018 February 2011 Response to Request for Additional Information, License Renewal Application, Request for Additional Information - Set 9 Project stage: Response to RAI ML1102602662011-02-24024 February 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1105509202011-03-0707 March 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1103506302011-03-17017 March 2011 Letter Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1102804242011-03-21021 March 2011 Audit Report Regarding the Seabrook Station License Renewal Application Project stage: Other ML1109702602011-03-28028 March 2011 Nwt 817, Chemistry Control in the Seabrook Thermal Barrier Loop, Final Project stage: Other ML1107000182011-03-30030 March 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11062, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Request for Additional Information - Set 112011-04-0505 April 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Request for Additional Information - Set 11 Project stage: Response to RAI SBK-L-11069, Response to Request for Additional Information - Set 12 and Associated License Renewal Application Changes2011-04-22022 April 2011 Response to Request for Additional Information - Set 12 and Associated License Renewal Application Changes Project stage: Response to RAI ML11132A0072011-05-23023 May 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11123, Response to Request for Additional Information, NextEra Energy Seabrook License Renewal Application, Request for Additional Information - Set 142011-06-0202 June 2011 Response to Request for Additional Information, NextEra Energy Seabrook License Renewal Application, Request for Additional Information - Set 14 Project stage: Response to RAI ML11139A1462011-06-0909 June 2011 Summary of Telephone Conference Call Held Between the NRC and Nextera Energy Seabrook, LLC, to Clarify Responses to RAI and Draft Requests for Additional Information Pertaining to the Seabrook Station LRA Project stage: Draft RAI ML11143A1652011-06-15015 June 2011 5/18/11, Summary of Telephone Conference Call Held Between NRC and Nextera Energy Seabrook, LLC, Concerning the D-RAI Pertaining to the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11133, Response to Request for Additional Information - Set 14 RAI B.1.4-12011-06-24024 June 2011 Response to Request for Additional Information - Set 14 RAI B.1.4-1 Project stage: Response to RAI ML11178A3652011-07-12012 July 2011 Schedule Revision for the Safety Review of the Seabrook Station License Renewal Application Project stage: Approval ML11284A0202011-10-14014 October 2011 Summary of Telephone Conf Call Held on August 4, 2011 Between the USNRC and Nextera Energy Seabrook, Llc., Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Response Project stage: RAI ML11280A0452011-10-17017 October 2011 Summary of Telephone Conference Call Held on May 5, 2011, Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook, LLC, Concerning Clarification of Information Pertaining to the Seabrook Station LRA Project stage: Other ML11304A0022011-11-0404 November 2011 Summary of Tele Conf Call Held on 3/18/11, Between the USNRC and NextEra Energy Seabrook, Llc., Concerning Clarification of Information Pertaining to the Seabrook Station License Renewal Application Project stage: Other ML11304A1092011-11-0404 November 2011 Summary of Tele Conf Call Held on 5/31/11, Between the USNRC and Nextera Energy Seabrook, Llc., Concerning Clarification of Information Pertaining to the Seabrook LRA Project stage: Other ML11304A1512011-11-0404 November 2011 Summary of Tele Conf Call Held on 4/8/11 Between USNRC and NextEra Energy Seabrook, Llc. Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Responses Project stage: RAI ML11304A1662011-11-0404 November 2011 Summary of Tele Conf Call Held on 3/3/11, Between the USNRC and NextEra Energy Seabrook, Llc. Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Responses Project stage: RAI ML12009A0072012-01-25025 January 2012 Project Manager Change for the License Renewal of Seabrook Station Project stage: Other ML12054A7662012-03-26026 March 2012 022312, Telecon Summary Between NRC and NextEra Seabrook, Discussing RAIs Response Project stage: RAI ML12160A3742012-06-0808 June 2012 Safety Evaluation Report with Open Items Related to the License Renewal of Seabrook Station Project stage: Approval ML12053A1922012-06-0808 June 2012 Safety Evaluation Report with Open Items Related to the License Renewal of Seabrook Station (TAC No. ME4028). Seabrook SER with Open Items Transmittal Letter Project stage: Approval ML12165A7422012-06-21021 June 2012 Summary of Telephone Conference Call Held on April 10, 2012, Between NRC and Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA Project stage: RAI ML12165A5952012-06-22022 June 2012 Summary of Telephone Conference Call Held on May 16, 2012, Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA Project stage: RAI ML12164A9012012-06-22022 June 2012 Summary of Telephone Conference Call Held on 5/24/12, Between the NRC and NextEra Energy Seabrook, LLC Concerning the Drai Pertaining to the Seabrook Station LRA Project stage: RAI ML12164A7562012-06-22022 June 2012 Summary of Telephone Conference Call Between NRC and NextEra Seabrook Project stage: Other ML12164A7592012-07-0303 July 2012 041912, Telecon Summary Between NRC and NextEra Seabrook Project stage: Other 2011-02-04
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000443/20240032024-10-30030 October 2024 Integrated Inspection Report 05000443/2024003 L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums ML24303A0352024-10-29029 October 2024 Operator Licensing Examination Approval IR 05000443/20244022024-10-17017 October 2024 Material Control and Accounting Program Inspection Report 05000443/2024402 (Cover Letter Only) L-2024-159, Core Operating Limits Report for Reload Cycle 242024-10-15015 October 2024 Core Operating Limits Report for Reload Cycle 24 L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes ML24254A2552024-09-25025 September 2024 Alternative Request No. 4A-01 for the Fourth 10-Year Inservice Inspection Interval L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24239A5382024-09-20020 September 2024 Issuance of Amendment No. 175 One-Time Allowable Outage Time Extension to the Technical Specification 3.8.1.1, A.C. Sources – Operating, Limiting Condition for Operation L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000443/20240052024-08-29029 August 2024 Updated Inspection Plan for Seabrook Station (Report 05000443/2024005) ML24232A1142024-08-21021 August 2024 Correction to Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves L-2024-141, Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit2024-08-15015 August 2024 Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Be L-2024-137, Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent .2024-08-12012 August 2024 Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent . IR 05000443/20240022024-08-0606 August 2024 Integrated Inspection Report 05000443/2024002 and Independent Spent Fuel Storage Installation Inspection Report 07200063/2024001 L-2024-127, Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent2024-08-0505 August 2024 Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite.2024-07-16016 July 2024 Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite. ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-098, Preparation and Scheduling of Operator Licensing Examinations2024-06-12012 June 2024 Preparation and Scheduling of Operator Licensing Examinations L-2024-084, Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-05-30030 May 2024 Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld IR 05000443/20240102024-05-29029 May 2024 Biennial Problem Identification and Resolution Inspection Report 05000443/2024010 IR 05000443/20240112024-05-24024 May 2024 Age-Related Degradation Inspection Report 05000443/2024011 IR 05000443/20240012024-05-13013 May 2024 Integrated Inspection Report 05000443/2024001 L-2024-061, NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distribut2024-05-10010 May 2024 NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distributio ML24046A0512024-05-0707 May 2024 Issuance of Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-078, 2023 Annual Radioactive Effluent Release Report2024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report L-2024-077, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000443/20245012024-04-22022 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000443/2024501 05000443/LER-2024-001, Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources2024-04-19019 April 2024 Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources SBK-L-24030, 2023 Annual Environmental Operating Report2024-04-12012 April 2024 2023 Annual Environmental Operating Report L-2024-011, And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications L-2024-038, To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0808 March 2024 To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24067A2622024-03-0808 March 2024 Issuance of Amendment No. 173 Revise Technical Specification 3/4.8.1 to Allow Replacement of Reserve Auxiliary Transformer (Emergency Circumstances) L-2024-037, To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0606 March 2024 To Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24065A2522024-03-0505 March 2024 Notice of Enforcement Discretion for Seabrook Station, Unit No. 1 (EPID: L-2024-033) L-2024-035, Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0505 March 2024 Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-033, Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B2024-03-0404 March 2024 Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B L-2024-032, Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0404 March 2024 Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source IR 05000443/20230062024-02-28028 February 2024 Annual Assessment Letter for Seabrook Station (Report 05000443/2023006) L-2024-019, Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-02-28028 February 2024 Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld L-2024-016, Radiological Emergency Plan (Ssrep), Revision 822024-02-13013 February 2024 Radiological Emergency Plan (Ssrep), Revision 82 IR 05000443/20230042024-02-12012 February 2024 Integrated Inspection Report 05000443/2023004 ML24009A1152024-01-29029 January 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) 2024-09-25
[Table view] Category:Schedule and Calendars
MONTHYEARL-2023-104, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations SBK-L-20043, Response to RIS 2020-01 Preparation and Scheduling of Operator Licensing Examinations2020-03-20020 March 2020 Response to RIS 2020-01 Preparation and Scheduling of Operator Licensing Examinations ML16074A2462016-03-31031 March 2016 Schedule Revision for the Review of the Seabrook Station, Unit 1, License Renewal Application ML15293A1572015-11-19019 November 2015 Schedule Revision for the Review of the Seabrook Station, License Renewal Application ML14223B1442014-09-11011 September 2014 Schedule Revision for the Review of the Seabrook, License Renewal Application SBK-L-14116, Response to RIS 2014-05, Preparation and Scheduling of Operator Licensing Examinations2014-06-12012 June 2014 Response to RIS 2014-05, Preparation and Scheduling of Operator Licensing Examinations SBK-L-13179, Preliminary Schedule for GSI-191 Resolution2013-09-30030 September 2013 Preliminary Schedule for GSI-191 Resolution ML12074A0962012-03-22022 March 2012 Schedule Revision for the Environmental Review of the Seabrook Station License Renewal Application ML11178A3652011-07-12012 July 2011 Schedule Revision for the Safety Review of the Seabrook Station License Renewal Application SBK-L-06197, Response to Regulatory Issue Summary 2006-152006-10-0909 October 2006 Response to Regulatory Issue Summary 2006-15 2023-08-03
[Table view] |
Text
c,"
",,,II REG(f
("
UNITED STATES
- t':'~,,"~"0':P...
- ... (">
NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001
~ 0 t; !:
~ ~ July 12, 2011
~~/) ~O
!
Mr. Paul Freeman, Site Vice President c/o Mr. Michael O'Keefe NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874
SUBJECT:
SCHEDULE REVISION FOR THE SAFETY REVIEW OF THE SEABROOK STATION LICENSE RENEWAL APPLICATION (TAC NO. ME4028)
Dear Mr. Freeman:
By letter dated May 25, 2010, NextEra Energy Seabrook, LLC (NextEra) submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the Operating License NPF-86 for Seabrook Station, Unit 1 (Seabrook) for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). By letter dated April 14, 2011, NextEra provided responses to staff requests for additional information (RAls) related to the aging management of the alkali-silica reaction (ASR) affected structures. Based on this RAI response, the staff notes that the analysis of the ASR issue is ongoing. Specifically, NextEra provided a schedule to complete an engineering evaluation of the ASR of concrete at Seabrook in March 2012. NextEra noted that the content of the evaluation will include: discussion of degradation mechanisms in concrete, identification of areas susceptible to ASR, results of in-situ testing of concrete and impact on current licensing basis calculations and analyses, results of lab testing to establish ASR degradation rates in concrete, and mitigation techniques.
In addition, NextEra plans to update the structures monitoring program, as appropriate, to manage aging related to ASR in concrete structures based on the engineering evaluation results.
Since NextEra has delayed providing aging management programs that include the evaluation of ASR, the NRC is revising the review schedule. The staff is revising the proposed license renewal schedule so that the staff can complete a thorough review of NextEra's aging management programs for the ASR-affected structures. This change to the schedule has been discussed with Rich Cliche of your staff. Enclosed is the staff's revised review schedule for the Seabrook license renewal application. You will note that environmental review milestone dates remain on schedule.
P. Freeman -2 If you have any questions on the revised schedule, please contact Mr. Richard Plasse, Project Manager for the review of the Seabrook LRA, by telephone at 301-415-1427 or bye-mail at richard. plasse@nrc.gov.
Sincerely,
---s~~~
Brian E. Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosure:
As stated cc w/encl: Listserv
SEABROOK STATION LICENSE RENEWAL APPLICATION UPDATED SAFETY REVIEW SCHEDULE Schedule Actual Milestones Date Date Receive license renewal application (LRA) 6/1/10 6/1/10 Publish Federal Register Notice (FRN) - LRA availability 6/14/10 6/16/10 Publish FRN - acceptance/rejection and opportunity for hearing 7/23/10 7/21/10 Publish FRN - environmental scoping meeting 7/23/10 7/20/10 Public Meeting - License Renewal Overview and Environmental 8/19/10 8/19/10 Scoping Meeting Audit - Scoping & Screening Audit Methodology 9/20/10 9/20/10 Deadline for filing hearing requests and petitions for intervention 9/20/10* 10/20/10 Environmental scoping period ends 9/21/10 9/21/10 Audit - Environmental 10/04/10 10/05/10 Audit - Aging Management Programs 10/12/10 10/12/10 Issue safety evaluation report (SER) with open items 5/2012**
Issue draft supplemental environmental impact statement (SEIS) 8/2011 Publish FRN - draft SEIS available for comments 8/2011 Public Meeting - draft SEIS meeting 9/2011 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee 7/2012**
meeting End of draft SEIS comment period 10/2011 Issue final SER 12/2012**
ACRS full committee meeting 1/2013**
Issue final SEIS 3/2012 U.S. Environmental Protection Agency FRN Published - availability 3/2012 of final SEIS Commission decision TBD
- Pending acceptable submission of additional information related to the aging management of structures affected by alkali-silica reaction.
ENCLOSURE
P. Freeman -2 If you have any questions on the revised schedule, please contact Mr. Richard Plasse, Project Manager for the review of the Seabrook LRA, by telephone at 301-415-1427 or bye-mail at richard.plasse@nrc.gov.
Sincerely, IRA!
Brian E. Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosure:
As stated cc w/encl: Listserv DISTRIBUTION:
See next page ADAMS Accession No.: ML11178A365 *concurrence via e-mail OFFICE LA: DLR/RPB1* PM: DLR/RPB1 Be: DLR/RPB2 LA: DLR/RPB1 D:DLR NAME SFigueroa RPlasse DWrona SFigueroa BHolian I DATE 06/29/2011 07/06/2011 07/06/2011 07/06/2011 07/12/2011 OFFICIAL RECORD COpy
Letter to Paul Freeman from Brian E. Holian dated July 12, 2011
SUBJECT:
SCHEDULE REVISION FOR THE SAFETY REVIEW OF THE SEABROOK STATION LICENSE RENEWAL APPLICATION (TAC NO. ME3959)
DISTRIBUTION:
HARD COPY:
DLR R/F E-MAil:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource MWentzel BPham EMiller ICouret, OPA EDacus,OCA MSpencer, OGC WRaymond, RI DTifft, RI NMcNamara, RI NSheehan, RI DScrenci, RI JJohnson, RI ABurritt, RI