{{#Wiki_filter:June 15, 2023
{{#Wiki_filter:
 
==SUBJECT:==
CALLAWAY PLANT - COMPREHENSIVE ENGINEERING TEAM INSPECTION (CETI) INSPECTION REPORT 05000483/2023011
 
==Dear Fadi Diya:==
On May 25, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Callaway Plant and discussed the results of this inspection with Brent Jungmann, Senior Director, Nuclear Engineering, and other members of your staff. The results of this inspection are documented in the enclosed report.
 
No findings or violations of more than minor significance were identified during this inspection.
 
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
 
Sincerely, Signed by Gaddy, Vincent on 06/15/23 Vincent G. Gaddy, Chief Engineering Branch 1 Division of Operating Reactor Safety Docket No. 05000483 License No. NPF-30
 
===Enclosure:===
As stated
 
==Inspection Report==
Docket Number: 05000483 License Number: NPF-30 Report Number: 05000483/2023011 Enterprise Identifier: I-2023-011-0006 Licensee: Ameren Missouri Facility: Callaway Plant Location: Steedman, MO Inspection Dates: May 08, 2023 to May 25, 2023 Inspectors: J. Braisted, Senior Reactor Inspector D. Bryen, Reactor Inspector W. Cullum, Senior Reactor Inspector C. Franklin, Reactor Inspector N. Okonkwo, Reactor Inspector D. Reinert, Senior Reactor Inspector F. Thomas, Reactor Inspector C. Young, Senior Reactor Analyst Approved By: Vincent G. Gaddy, Chief Engineering Branch 1 Division of Operating Reactor Safety Enclosure
 
=SUMMARY=
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection (CETI) inspection at Callaway Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
 
===List of Findings and Violations===
 
No findings or violations of more than minor significance were identified.
 
===Additional Tracking Items===
None.
 
=INSPECTION SCOPES=
 
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
 
==REACTOR SAFETY==
 
===71111.21M - Comprehensive Engineering Team Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, 10 CFR 50.59 evaluations/screens, and operating experience samples:
Structures, Systems, and Components (SSCs) (IP section 03.01) ===
{{IP sample|IP=IP 71111.21|count=10}}
: (1) CGD02A, Cooling Tower Electrical Room Supply Fan A Compliance with the updated final safety analysis report (UFSAR), technical specifications (TS), and TS bases Component modifications and associated evaluations Design calculations including fan motor minimum voltage, control logic, and heat transfer capacity/heat balance Visual inspection of fan, dampers, and instruments during walkdown Vendor and design requirements Applicable operating experience relevant to sample
: (2) EFHV0066, Essential Service Water Cooling Tower Train B Bypass Valve Design basis documents System level procedures Visual inspection of component during walkdown System calculations Logic for valve operation Corrective action program documents Preventative maintenance tasks and procedures
: (3) NB0113, Feeder Breaker to NG01 Control Building Load Center Compliance with the UFSAR, TS, and TS bases Design calculations including voltage analysis and short circuit calculations Visual inspection of equipment and surrounding area Electrical drawings Component maintenance history and corrective action program documents Procedures for circuit breaker inspection, maintenance, and testing
: (4) NG01B, A Train 480 VAC Auxiliary Building Motor Control Center Compliance with the UFSAR, TS, and TS bases Design calculations including voltage analysis and short circuit calculations Visual inspection of equipment and surrounding area Vendor and design requirements Thermography procedure and results
: (5) NK01, 125 VDC Distribution Panel Class IE Group 1 Compliance with UFSAR, TS, and TS bases and plant procedures Visual inspection of charger and associated system during walkdown Environmental conditions of equipment Surveillance procedure, testing, operations and maintenance records Protection setting and coordination study Design basis document Vendor manual for conformance with manufacturer instructions for installation and maintenance Preventive maintenance and periodic verification testing and post-test analyses Schematic and wiring drawings System health report Corrective action program documents
: (6) NK21, 125 VDC Vital Battery Charger 1 Compliance with UFSAR, TS, and TS bases and plant procedures Visual inspection of charger and associated system during walkdown Environmental conditions of equipment Design basis document Preventive maintenance and periodic verification testing and post-test analyses Surveillance procedure, testing, operations and maintenance records Vendor manual for conformance with manufacturer instructions for installation and maintenance Schematic and wiring drawings reviews Corrective action program documents Thermography inspection results of equipment internals System health report Protective settings and coordination study Load test data study of batteries
: (7) PEF01A, Essential Service Water Pump A Design basis documents System level procedures Visual inspection of component during walkdown System calculations Water hammer analysis Thermal-hydraulic ultimate heat sink analysis Preventative maintenance tasks and procedures
: (8) SGL10A, Residual Heat Removal Room Cooler A Heat exchanger testing procedures and performance history to assure consistency with vendor and industry recommendations Room cooler maintenance history to verify the monitoring of potential degradation Design calculations including required heat capacity, maximum tube plugging limits, and limiting flows and temperature inputs Corrective action program documents
: (9) TEG01A, Component Cooling Water Surge Tank A Compliance with the UFSAR, TS, and TS bases Calibration procedures and acceptance criteria calculations for level instrumentation Component modifications and associated evaluations Design calculations including minimum usable safety related inventory and tank level setpoints Visual inspection of tank, valves, and instruments during walkdown Review of vendor and design requirements Evaluation of applicable operating experience relevant to sample
: (10) XNG01, Transformer Load Center NG01 Load Center Thermography procedure and results Voltage analysis and short circuit calculations Visual inspection during equipment walkdown Review of vendor manual and plant design drawings
 
===Modifications (IP section 03.02) (5 Samples)===
: (1) MP 18-0045, Approve Changes to NK Battery Connection System Required for RF23
: (2) MP 19-0002, Thermocouple Core Cooling Monitor Replacement
: (3) MP 19-0012, Setpoint Re-Adjustment (Lower Level) For Control Building Sump
: (4) MP 19-0018, Ultimate Heat Sink Cooling Tower Return to Ultimate Heat Sink Pond
: (5) RFR 170223, Gas Void in Containment Spray Pump Suction from Emergency
 
===Recirculation Sump 10 CFR 50.59 Evaluations/Screening (IP section 03.03) (20 Samples)===
: (1) CA2511-00892, MP 13-0001, Replace Essential Service Water Supply Fans CGD01A&B
: (2) CA2511-00936, MP 13-0037, Polar Crane Bridge and Trolley Motor Controls Upgrade
: (3) CA2511-01196, MP 19-0002, Thermocouple Core Cooling Monitor Replacement
: (4) CA2511-01221, MP 19-0085, Cooling Tower Basin Level Indication Phase 2
: (5) CA2511-01266, MP 19-0124, Replace KJV0820A/B, Diesel Generator Auxiliary Lube Oil Pump Pressure Relief Valves
: (6) CA2511-01267, MP 20-0006, UHS Cooling Tower Fan Motor Circuits Relay Replacement
: (7) CA2511-01271, MP 20-0015, XMB01 Exciter Transformer Replacement
: (8) CA2511-01272, MP-19-0018, Ultimate Heat Sink Cooling Tower Return to Ultimate Heat Sink Pond
: (9) CA2511-01318, MP 21-0009, Improve the Ground Fault Relaying on the C Phase of MA01
: (10) CA2511-01344, MP 21-0001, Eliminate the Main Feedwater Regulating Valve Single Point Vulnerability and Improve Reliability
: (11) CA2511-01363, MP 21-0020, Replace Batteries PK11 and PK12
: (12) CA2511/TABLE 8-8B, Maximum Allowable Number of Fuel Assemblies Offloaded to the Spent Fuel Pool vs. Time after Shutdown Refuel Outage 26 and Spent Fuel Pool Water Temperature Limit for Fuel Handling Operations
: (13) CA2512-00032, MP 19-0088, Atmospheric Steam Dump Valves Environmental Qualification
: (14) CA2512-00034, Reduction in Containment Passive Heat Sinks
: (15) CA2512-00036, MP 20-0012, Obsolete Transmitter - Vendor Cannot Quote Replacement Without Addition Information
: (16) MP 19-0012, Setpoint Re-Adjustment (Lower Level) For Control Building Sump
: (17) MP 19-0088, Atmospheric Steam Dump Valves Environmental Qualification
: (18) MP 19-0116, Evaluate and Approve Electromagnetic Interference Improvements for New EGS Connectors/Connections
: (19) MP 21-0021, RFR 210061, Reconfigure Select Intermediate Range Instruments
: (20) MP 22-0018, Replacement of Protective Relay PA0210211F
 
===Operating Experience Samples (IP section 03.04) (3 Samples)===
: (1) CR 201906202, Part 21 Fisher Information Notice 2019-01, Mechanical Setting of Disk/Stem Taper Pins for Fisher Type 7600, 7700, 7800, 9100, 9200, and 9500 Series Butterfly Valves
: (2) CR 202101555, Adverse to Quality Condition Found From Cook Unit 2 Operating Experience Review
: (3) CR 202104699, Wolf Creek DBAI Minor Violation of 10CFR50.65(a)(4) For Inadequate Model of the Startup Time of the NSAFWP Risk Value in PRA
 
==INSPECTION RESULTS==
No findings were identified.
 
==EXIT MEETINGS AND DEBRIEFS==
The inspectors verified no proprietary information was retained or documented in this report.
 
On May 25, 2023, the inspectors presented the comprehensive engineering team inspection (CETI) inspection results to Brent Jungmann, Senior Director, Nuclear Engineering, and other members of the licensee staff.
 
=DOCUMENTS REVIEWED=
 
Inspection Type              Designation      Description or Title                                    Revision or
Procedure                                                                                              Date
71111.21M Calculations      CN-CRA-19-5      Callaway Steam Tunnel GOTHIC Modeling Upgrade            0
E-B-13          Voltage Analysis                                        0
EDP-ZZ-01113    Infrared Thermography Program Guide                      12
EF-45            Acceptance Criteria Used in Essential Service Water Flow 8
Balance Procedures
GD-342          Cooling Tower Electrical Room Ventilation                0
GK-05            Short Circuit Calculation                                0
GL-137          SGL10A/B Room Cooler Heat Removal Capabilities          0
J-UEF03          Instrument Loop Uncertainty Estimate: UHS Cooling Tower  2
Fan Speed and Bypass Valve Control
M-EF-52          Heat Exchanger Performance Based on Reduced ESW          1
Temperature and Flow
M-EG-05 ADD 2    NPSH Available to the CCW Pumps with the Surge Tank      0
Empty
M-GK-370        Post-Accident Battery Room H2 Concentration Levels      001
NAI-2114-001    Evaluation of Gas Accumulation in Callaway Containment  0
Spray Suction Piping
NAI-2163-001    Callaway Energy Center UHS Thermal Performance          0
Analysis Using GOTHIC
NB-05            System NB Protective Relay Setpoints                    004
NK-05            Class 1E Battery Capacity                                010
NK-06            Class 1E DC Power System Fault Tree Model                000
NK-06 ADD 1      Class IE DC Power System Fault Tree Model                10/20/1998
NK-10            NK System DC Voltage Drop                                002
NK-10            Attachments C, D, E, F, G, and K for NK-10 Calculation  002
ZZ-214          MOV Voltage Drop Calculation                            10
ZZ-534          Quarter-turn MOV Capability and Margin Calculation      1
ZZ-62            Plant Load Flow Calculation                              10
Corrective Action Condition Report 201904041, 201701094, 201901943, 201905148,
Documents                          201906023, 202203343, 202203419, 201601612,
2002721, 202003059, 202003062, 202004888,
2100215, 202100247, 202101093, 202101766,
Inspection Type              Designation      Description or Title                                        Revision or
Procedure                                                                                                Date
2200624, 202201540, 202001783, 202100910,
2101555, 202102021, 202102548, 202201363,
2300457, 200701515, 202007410, 201803185,
200408670, 200002868, 200409206, 202000763,
2201665, 200800976, 200901546, 201000245,
201004897, 201706920, 201803958, 201904646,
2005745, 202203112, 202204558, 202204863,
201901616, 201803185, 201802828, 201300761,
200801763, 202303127, 202302551, 202300381,
201806334, 201806919, 201905572, 201906202,
201905708, 202101276, 202103720, 201108964,
200803462, 201203653, 201305408, 202203151
Corrective Action Condition Report 202303237, 202303240, 202303241, 202303254,
Documents                          202303269, 202303325, 202303400, 202303497,
Resulting from                    202303510, 202303592, 202303596, 202303615,
Inspection                        202303621, 202303622, 202303623, 202303634,
2303643, 202303645, 202303676
Drawings          10466-M-619.2-  1UEWOC Fan Curves                                          04/07/1978
23-01
E-009-00023      Metal-Clad Switchgear - Power & Control Circuits Electrical 11
Diagram - NB0113
E-050-00006      Batteries NK11 & NK14 60 Cell NCN-23S Layout ON-2-S07-      014
074530-816 Racks
E-050-00009      Batteries NK12 & NK13 - 60 Cell NCN-13S Layout ON-2-        013
S07-07 520-816 Racks
E-050-00032      Batteries - NCN & NCX Typical Termination Assemblies        003
E-051-00058      3PH SRC Controller Battery Charger Schematics              012
E-051-00079      Battery Chargers Wiring Diagram                            009
E-051-00090      3 Phase Thyristor Control Class 1E 130V Battery Charger    011
NK21, NK22, NK23, NK24, NK25
E-21005(Q)      List of Loads Supplied by Emergency Diesel Generator.      038
E-21NB01(Q)      Lower Medium Voltage System Class 1E 4.16KV Single Line    11
Meter and Relay Diagram
E-21NG01        Single Line Diagram                                        28
Inspection Type          Designation  Description or Title                                      Revision or
Procedure                                                                                        Date
E-21NK01(Q)  Class IE 125V DC System Meter & Relay Diagram              018
E-23NK10      125 Volt DC Class 1E Power System Schematic                029
E-23NN01      Class 1E Instrument AC Schematic                          014
E-U3EF05A(Q)  Schematic Diagram Cooling Tower Inlet Bypass Valve        2
E-U3GD02      Schematic Diagram ESW Elect. Room Supply Fan              9
M-105A-00002  Component Cooling Water Surge Tank                        6
M-105A-003-02 Support Leg Cross Bracing Detail                          01/04/1978
M-105A-009-02 Support Leg Detail                                        03/24/1977
M-1184-00015  Crosby Pressure Relief Valves                              0
M-22EG01      P&ID Component Cooling Water System                        11
M-22KJ03      P&ID Standby Diesel Generator "A" Lube Oil System          20
M-22KJ06      P&ID Standby Diesel Generator "B" Lube Oil System          20
M-619.2-00144 Fan Assembly drawing Buffalo Forge Co. Fan 330 BL ARR      6
9l Class 1
M-U2GD01      P&ID ESW Pumphouse & UHS Elec. Rm. HVAC                    12
M-UG082      UHS Cooling Tower Arrangement                              8
Engineering  EC-46        Fuel Cycle 26 Decay Heat Load Calculation                  0
Changes      MP 13-0037    Polar Crane Bridge and Trolley Motor Controls Upgrade      002
MP 19-0002    Thermocouple Core Cooling Monitor Replacement              1
MP 19-0018    UHS Cooling Tower Return to UHS Pond                      2
MP 19-0085    Cooling Tower Basin Level Indication Phase 2              2
MP 19-0088    Atmospheric Steam Dump Valves Environmental                003
Qualification
MP 19-0116    Electromagnetic Interference Improvements for New EGS      001
Connectors/Connections
MP 19-0124    Replace KJV0820A/B, DG Aux Lube Oil Pump Pressure          0
Relief Valves
MP 21-0001    Eliminate the Main Feedwater Regulating Valve Single Point 003
Vulnerability and Improve Reliability
Miscellaneous 19508715.500  Clean and Inspect Battery Charger NK21                    000
19511729 NK21 Thermography Inspection Control Building. EL. 2016        000
2508001.500  Thermography Inspection - Control Building EL. 2016        000
ARC-1599      Independent Review of Crosby Engineering Calculation EC-  06/04/2020
Inspection Type Designation    Description or Title                                      Revision or
Procedure                                                                                Date
24, R0
CA2507        Curve Book Evaluation Table 8-8B                          20
CA2510        Screening for MP 08-0010                                  000
CA2510-01463  Improve the Ground Fault Relaying on the C Phase of MA01  000
50.59 review CA2510-01463 - MP 21-0009
CA2510eB      Screening for MP 18-0045 R001                              001
CA2511-01318  50.59 Screen for MP 21-0009                                000
CA2511-eB      50.59 Screening for MP 18-0045 Approve changes to NK      000
battery connection system required for RF23
CA2512-00034  Reduction in Containment Passive Heat Sinks                0
E-009-00319    Instruction Manual for SEL-251D Distribution Relay        000
E-050-00016    IM Batteries and Battery Packs Gould Inc, System: NK      017
Manual
E-27000A      Termination List Notes                                    033
GEH-262IC      General Electric Installation and Maintenance Instructions 06/01/1973
for AV-Line Switchboards
GEK-7320F      General Electric Instructions for Types AM-4.16-350-2C &  02/01/1980
AM-4.16-350-2H Magne Blast Circuit Breaker
GNB Industrial  March 14, 2012-03-14 letter from Paul Mattaliano of GNB  03/14/2012
Power Letter  industrial Power to Nicole Weber of Ameren Missouri -
Callaway Energy Center on NCN Hydrogen Generation
Rates
HI 2004101    Health Risk and Solution Option Ranking -Thermocouple      0
Core Cooling Monitor (TCCM) Obsolescence Issues (OBS)
J-2049-00000  Thermocouple Core Cooling Monitor Operations and          0
Maintenance Manual
J-601B-00074  IM Atmosphere Relief Valve - Masoneilan International      055
LDCN 19-0011  FSAR Markup/ LDCR CR# 201901616                            0
FSAR SP SEC 9.3.3.5 for MP 19-0012,
M-2024-00001  IM Nitrogen Isolation - Velan Engineering Company          000
M-612-00062    IM Air Handling Units (Room Coolers) Carrier Corporation  23
M-619.2-00136  Instruction Manual for Safety Related Fans                10
M-924          Specification For Safety Related Fans CGD01A & B /        0
CGM01A & B
Inspection Type Designation  Description or Title                                        Revision or
Procedure                                                                                Date
M-U0GD      System Description Essential Service Water Pump House        5
Ventilation System and UHS Cooling Tower Electrical Room
Ventilation System
MP 08-0010  50.59 Screening for Setpoint adjustment for Control Building 001
CA2511      Sump
MP 18-0045  Approve changes to NK battery connection system required    003
for RF23
MP 19-0012  Setpoint re-adjustment (lower level) for Control Building    001
Sump
MP 21-0009  Improve the Ground Fault Relaying on the C Phase of MA01    002
MP 21-0020  RFR 200020 - Replace Batteries PK11 & PK12                  001
N/A          SEL-351A, -1 Relay Distribution Protection System            09/08/2019
Instruction Manual
NG-22        NK21CB1 Feeder Breaker Application Sheet                    001
OTA-RK-00024 Miscellaneous Sumps Level High                              005
Addendum 94F
RFR          AK Correction Factors on Room Coolers                        B
RFR 004371B  Interstep Cable Connector Part Numbers                      B
RFR 007519  Eval. NK Battery Interstep Cable material Equiv.            A
RFR 017225A  Material Equiv. for a different Subtier on a GNB lug        A
RFR 020132A  Update E-050 I/M'S Due NK Battery Replacement                A
RFR 170208  Approve Part Number Change for GNB Batteries (NCN and        000
NCX Series)
RFR 170223  Gas Void in CTMT Spray Pump Suction from Emergency          0
Recirculation Sump
RFR 170223  Gas Void in CTMT Spray Pump Suction from Emergency          0
Recirculation Sump
RFR 180078  Approve changes to NK battery connection system required    000
for RF23 and the battery swap out being done during refuel
RFR 200135  Retire Installed Hydrogen Analyzers in the NK, PK and        000
Comm. Corridor Battery Rooms
RFR 20115    Evaluate NK Battery Interstep Cable Material Equiv          000
RFR 210110  External Indication of Ventilation Status For Communications 000
Corridor Battery Room No. 1
Inspection Type      Designation  Description or Title                                          Revision or
Procedure                                                                                        Date
RFR 210112  Evaluate If NK Battery Room Hydrogen Monitors Are            000
Required
RFR 210113  Evaluate if Communications Corridor Radio Room/Battery        000
Room Hydrogen Monitor Can Be Retired
ULDBD-EG-001 Component Cooling Water                                      1
ULDBD-GD-001 Essential Service Water Pumphouse and Ultimate Heat Sink      1
Ventilation Systems
ULDBD-GL-001 Auxiliary Building Ventilation System                        3
ULDBD-NB-001 Lower Medium Voltage (Class 1E 4.16KV)                        1
ULDBD-NG-001 Low Voltage (480V) - Class 1E                                2
Procedures APA-ZZ-00143 10 CFR 50.59 AND 10 CFR 72.48 Reviews                        022
APA-ZZ-00320 Work Execution                                                082
APA-ZZ-00330 Preventive Maintenance Program Administrative Correction      059
APA-ZZ-00395 Significant Operator Response Timing                          033
APA-ZZ-00396 Gas Intrusion Program                                        4
APA-ZZ-00500 Corrective Action Program                                    075
APA-ZZ-00604 Requests For Resolution                                      042
E-017-00397  IM Load Center Unit Substations General Electric Company,    028
System: NG
E-050-00038  Seismic Qualification Report of Cable Clamps                  000
E-051-00090  3 Phase Thyristor Control Class 1E 130V Battery Charger      011
NK21, NK22, NK23, NK24, NK25
E-051B-00002 Instruction Manual for Installation and Operation pf Class 1E 000
Electrically Operated Manually controlled Transfer Switches,
NK71- Thru NK78
E-1          Loss of Reactor or Secondary Coolant                          023
E-1052-00017 IM FOR LGSB13 AND LGSB2 Circuit Breakers, Nuclear            003
Logistics Inc. System: PG
E-2          Faulted Steam Generator Isolation                            012
E-21013      Installation, Inspection, and Testing Details For Electrical  057
Equipment and Cable
E-25000A    Cable and Raceway Notes, Details, and Tables                  055
E-3          Steam Generator Tube Rupture                                  025
Inspection Type Designation  Description or Title                                      Revision or
Procedure                                                                              Date
ECA-0.0      Loss of All AC Power                                      032
EDP-ZZ-00396 Gas Intrusion Program Implementation                      1
EDP-ZZ-01112 Heat Exchanger Predictive Performance Manual              27
EDP-ZZ-01113 Infrared Thermography Program Guide                      012
EDP-ZZ-01133 Air Operated Valve Program Guide                          026
ISF-EG-000L1 CCW Surge TK 'A' Level Channel OP Test                    26
ISP-NF-0001A LSELS Train A ESW and CCW Pump Start Inhibit Test        5
ITL-EG-00R09 CCW HX 'A' Inlet Process Rad Monitor Loop Cal            19
ITL-GD-00T51 LOOP-TMP; UHS Cooling Tower Elec. Rm Sply Fan            19
                            (CGD02A) Temp
ITM-ZZ-VT001 Diagnostic Calibration and Testing of Modulating Air      025
Operated Valves
MP 08-0010  Setpoint adjustment for Control Building Sump            001
MPE-NK-QB004 NK CLASS 1E Battery Charger Inspection                    013
MPE-ZZ-QS003 Cleaning and Inspection of 120 VAC Distribution Panels,  014
25 VDC and 250 VDC Switchboards and Miscellaneous
Electrical Panels
MPE-ZZ-QS005 General Electric 4.16KV Breaker PM                        034
MPE-ZZ-QS006 GE Magne Blast Breaker Overhaul                          015
MPE-ZZ-QS008 G.E. 480 VOLT Load Center PM                              029
MPM-ZZ-QH001 Inspection and Maintenance of Tornado Dampers            5
MPM-ZZ-QV009 Fisher Controls Nuclear Carbon Steel Butterfly Valves -  10
Disassembly Inspection and Reassembly
MPM-ZZ-QW002 Safety-Related Fan Belt Replacement/Tensioning            6
MPM-ZZ-QW002 Safety-Related Fan Belt Replacement/Tensioning            5
MSE-NK-QB002 Quarterly Surveillance on NK Quarterly Surveillance on NK 016
Large Station Batteries
MSE-NK-QB011 Inspection and Surveillance of NK11 Battery and Battery  027
Chargers NK21/NK25
MTE-ZZ-QB002 Battery Charger Maintenance, Field Adjustments, and      020
Troubleshooting
MTE-ZZ-QN005 Electrical Scheme Checkout                                011
MTM-ZZ-QA002 Limitorque SMB-00 MOV Inspection and Overhaul            020
Inspection Type Designation  Description or Title                              Revision or
Procedure                                                                        Date
MTT-ZZ-00001  HVAC System Air Balancing                          8
OSP-EJ-P001A  RHR Train A Inservice Test - Group A              69
OSP-EN-00002  Containment Spray System Venting                  5
OTA-NK-00001, Switchboard Bus Under Voltage                      0
Addendum 3A
OTN-EG-00001  Component Cooling Water System                    62
OTN-EG-00001  Transferring Water Between Surge Tanks            4
ADDENDUM 1
OTN-LF-00001  Control Building Floor/Equipment Sump level High  004
Addendum 9
OTO-EG-00001  CCW System Malfunction                            18
ULNRC-05504  Three-Month Response to NRC Generic Letter 2008-  04/10/2008
01,"Managing Gas Accumulation In Emergency Core
Cooling, Decay Heat Removal, and Containment Spray
Systems" (TAC NO. MD7806)
ULNRC-05551  Three-Month Response to NRC Generic Letter 2008-  10/13/2008
01,"Managing Gas Accumulation In Emergency Core
Cooling, Decay Heat Removal, and Containment Spray
Systems" (TAC NO. MD7806)
ULNRC-05590  Three-Month Response to NRC Generic Letter 2008-  02/04/2009
01,"Managing Gas Accumulation In Emergency Core
Cooling, Decay Heat Removal, and Containment Spray
Systems" (TAC NO. MD7806)
ULNRC-06164  Supplemental Response to NRC Generic Letter 2008-  12/15/2014
01,"Managing Gas Accumulation In Emergency Core
Cooling, Decay Heat Removal, and Containment Spray
Systems" (TAC NO. MD7806)
71111.21M Work Orders Job 07510763.250, 10507443.250, 10507443.550,
11512464.500, 17004271.550, 20511173, 21502427,
2509934, 22500698, 20000796, 20002095, 13505629.500,
19508715.500, 19509000.500, 18000362.900,
18000363.900, 18000364.505, 18000365.520,
19003551.940, 21001642, 20511648, 14504618, 20509118,
21500183.500, 22001102.350, 22502362, 18512211.500
15
}}
}}

Revision as of 09:17, 17 July 2023

Comprehensive Engineering Team Inspection (Ceti) Inspection Report 05000483/2023011
ML23158A092
Person / Time
Site: Callaway Ameren icon.png
Issue date: 06/15/2023
From: Vincent Gaddy
NRC/RGN-IV/DORS/EB1
To: Diya F
Ameren Missouri
References
IR 2023011
Download: ML23158A092 (1)


Text