IR 05000255/2012301: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(6 intermediate revisions by the same user not shown)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352
{{#Wiki_filter:ber 27, 2012


November 27, 2012
==SUBJECT:==
PALISADES NUCLEAR PLANT NRC INITIAL LICENSE EXAMINATION REPORT 05000255/2012301


Mr. Anthony Vitale Vice-President, Operations Entergy Nuclear Operations, Inc. Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530
==Dear Mr. Vitale:==
On October 24, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed the initial operator licensing examination process for license applicants employed at your Palisades Nuclear Plant. The enclosed report documents the results of those examinations. Preliminary observations noted during the examination process were discussed on October 11, 2012, with Mr. J. Dills and other members of your staff. An exit meeting was conducted by telephone on November 7, 2012, between Mr. B. Nixon of your staff and Mr. R. K. Walton, Chief Operator Licensing Examiner, to review the proposed final grading of the written examination for the license applicants. During the telephone conversation, NRC resolutions of the station=s post-examination comments, initially received by the NRC on October 24, 2012, were discussed.


SUBJECT: PALISADES NUCLEAR PLANT NRC INITIAL LICENSE EXAMINATION REPORT 05000255/2012301
The NRC examiners administered an initial license examination operating test during the weeks of October 1 and October 9, 2012. The written examination was administered by Palisades Nuclear Plant Training Department personnel on October 12, 2012. Six Senior Reactor Operator and five Reactor Operator applicants were administered license examinations. The results of the examinations were finalized on November 15, 2012. One applicant failed one or more sections of the administered examination and was issued a proposed license denial letter.


==Dear Mr. Vitale:==
Ten applicants passed all sections of their respective examinations and six were issued senior operator licenses and three were issued operator licenses. In accordance with NRC policy, the license for the remaining one applicant is being withheld pending the outcome of any written examination appeal that may be initiated.
On October 24, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed the initial operator licensing examination process for license applicants employed at your Palisades Nuclear Plant. The enclosed report documents the results of those examinations. Preliminary observations noted during the examination process were discussed on October 11, 2012, with Mr. J. Dills and other members of your staff. An exit meeting was conducted by telephone on November 7, 2012, between Mr. B. Nixon of your staff and Mr. R. K. Walton, Chief Operator Licensing Examiner, to review the proposed final grading of the written examination for the license applicants. During the telephone conversation, NRC resolutions of the station
=s post-examination comments, initially received by the NRC on October 24, 2012, were discussed. The NRC examiners administered an initial license examination operating test during the weeks of October 1 and October 9, 2012. The written examination was administered by Palisades Nuclear Plant Training Department personnel on October 12, 2012. Six Senior Reactor


Operator and five Reactor Operator applicants were administered license examinations. The results of the examinations were finalized on November 15, 2012. One applicant failed one or more sections of the administered examination and was issued a proposed license denial letter. Ten applicants passed all sections of their respective examinations and six were issued senior operator licenses and three were issued operator licenses. In accordance with NRC policy, the license for the remaining one applicant is being withheld pending the outcome of any written examination appeal that may be initiated. The written examination will be withheld from public disclosure for 24 months per your request. However, since an applicant received a proposed license denial letter because of a written examination grade that is less than 80 percent, the applicant will be provided a copy of the written examination. For examination security purposes, your staff should consider that written examination uncontrolled and exposed to the public. In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be ava ilable electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
The written examination will be withheld from public disclosure for 24 months per your request.


Sincerely,/RA/ Hironori Peterson, Chief Operations Branch
However, since an applicant received a proposed license denial letter because of a written examination grade that is less than 80 percent, the applicant will be provided a copy of the written examination. For examination security purposes, your staff should consider that written examination uncontrolled and exposed to the public. In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's
"Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).


Division of Reactor Safety Docket Nos. 50-255; 72-007 License No. DPR-20  
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-255; 72-007 License No. DPR-20


===Enclosures:===
===Enclosures:===
1. Operator Licensing Examination Report 05000255/2012301  
1. Operator Licensing Examination Report 05000255/2012301 w/Attachment: Supplemental Information 2. Simulation Facility Report 3. Written Examination Post-Examination Comment Resolution


===w/Attachment:===
REGION III==
Supplemental Information 2. Simulation Facility Report 3. Written Examination Post-Examination Comment Resolution cc w/encl: Distribution via ListServŽ
Docket No: 50-255 License No: DPR-20 Report No: 05000255/2012301 Licensee: Entergy Nuclear Operations, Inc.


Enclosure 1 U.S. NUCLEAR REGULATORY COMMISSION REGION III Docket No: 50-255 License No: DPR-20 Report No: 05000255/2012301 Licensee: Entergy Nuclear Operations, Inc. Facility: Palisades Nuclear Plant Location: Covert, Michigan Dates: October 1 to October 24, 2012 Inspectors: R. K. Walton, Chief Examiner C. Moore, Examiner J. Kellum, Examiner  
Facility: Palisades Nuclear Plant Location: Covert, Michigan Dates: October 1 to October 24, 2012 Inspectors: R. K. Walton, Chief Examiner C. Moore, Examiner J. Kellum, Examiner Approved by: H. Peterson, Chief Operations Branch Division of Reactor Safety Enclosure 1


Approved by: H. Peterson, Chief Operations Branch Division of Reactor Safety
=SUMMARY OF FINDINGS=
ER 05000255/2012301; 10/01/2012 - 10/24/2012; Entergy Nuclear Operations, Inc.,


1 Enclosure 1
Palisades Nuclear Plant; Initial License Examination Report.


=SUMMARY OF FINDINGS=
The announced initial operator licensing examination was conducted by regional U.S. Nuclear Regulatory Commission (NRC) examiners in accordance with the guidance of NUREG-1021,
ER 05000255/2012301; 10/01/2012 - 10/24/2012; Entergy Nuclear Operations, Inc., Palisades Nuclear Plant; Initial License Examination Report. The announced initial operator licensing examination was conducted by regional U.S. Nuclear Regulatory Commission (NRC) examiners in accordance with the guidance of NUREG-1021, A Operator Licensing Examination Standards for Power Reactors,@ Revision 9, Supplement 1. Examination Summary Ten of eleven applicants passed all sections of their respective examinations. Six applicants were issued senior operator licenses and four applicants were issued operator licenses. One applicant failed one or more sections of the administered examination and was issued proposed license denial. The license(s) for the remaining applicant is being held and may be issued pending the outcome of any written examination appeal.  (Section 4OA5.1) 
AOperator Licensing Examination Standards for Power Reactors,@ Revision 9, Supplement 1.
 
Examination Summary Ten of eleven applicants passed all sections of their respective examinations. Six applicants were issued senior operator licenses and four applicants were issued operator licenses.


1
One applicant failed one or more sections of the administered examination and was issued proposed license denial. The license(s) for the remaining applicant is being held and may be issued pending the outcome of any written examination appeal. (Section 4OA5.1)


=REPORT DETAILS=
=REPORT DETAILS=
Line 61: Line 67:


====a. Examination Scope====
====a. Examination Scope====
The NRC examiners and members of the facility licensee's staff used the guidance prescribed in NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 9, Supplement 1, to develop, validate, administer, and grade the written examination and operating test. Members of the facility licensee's staff prepared  
The NRC examiners and members of the facility licensees staff used the guidance prescribed in NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9, Supplement 1, to develop, validate, administer, and grade the written examination and operating test. Members of the facility licensees staff prepared the outline and developed the written examination and operating test. The NRC examiners validated the proposed examination during the week of September 4, 2012, with the assistance of members of the facility licensees staff. During the on-site validation week, the examiners audited three license applications for accuracy.


the outline and developed the written ex amination and operating test. The NRC examiners validated the proposed examination during the week of September 4, 2012, with the assistance of members of the facility licensee's staff. During the on-site validation week, the examiners audited three license applications for accuracy. The NRC examiners, with the assistance of members of the facility licensee's staff, administered the operating test, consisting of job performance measures (JPMs) and dynamic simulator scenarios, during the period of October 1 through October 11, 2012. The facility licensee administered the written examination on October 12, 2012.
The NRC examiners, with the assistance of members of the facility licensees staff, administered the operating test, consisting of job performance measures (JPMs) and dynamic simulator scenarios, during the period of October 1 through October 11, 2012.
 
The facility licensee administered the written examination on October 12, 2012.


====b. Findings====
====b. Findings====
(1) Written Examination The NRC examiners determined that the written examination, as proposed by the licensee, was within the range of acceptability expected for a proposed examination.
: (1) Written Examination The NRC examiners determined that the written examination, as proposed by the licensee, was within the range of acceptability expected for a proposed examination.


Less than 20 percent of the proposed examination questions were determined to be unsatisfactory and required modification or replacement.
Less than 20 percent of the proposed examination questions were determined to be unsatisfactory and required modification or replacement.


On October 24, 2012, the licensee submitted documentation noting that there were three post-examination comments for consideration by the NRC examiners when grading the written examination. The post-examination comments and the NRC resolution for the post-examination comments are included in Enclosure 3 of this report. The final as-administered examination and answer key (ADAMS Accession Numbers ML12324A288 and ML12324A291) will be available in 24 months electronically in the NRC Public Document Room or from the Agencywide Documents Access and Management System (ADAMS). All changes made to the proposed written examination, were made in accordance with NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," and documented on Form ES-401-9, "Written Examination Review Worksheet.The NRC examiners graded the written examination on November 7, 2012, and conducted a review of each missed question to determine the accuracy and validity of the examination questions.
On October 24, 2012, the licensee submitted documentation noting that there were three post-examination comments for consideration by the NRC examiners when grading the written examination. The post-examination comments and the NRC resolution for the post-examination comments are included in Enclosure 3 of this report.
 
The final as-administered examination and answer key (ADAMS Accession Numbers ML12324A288 and ML12324A291) will be available in 24 months electronically in the NRC Public Document Room or from the Agencywide Documents Access and Management System (ADAMS). All changes made to the proposed written examination, were made in accordance with NUREG-1021, "Operator Licensing Examination Standards for Power Reactors, and documented on Form ES-401-9, Written Examination Review Worksheet.
 
The NRC examiners graded the written examination on November 7, 2012, and conducted a review of each missed question to determine the accuracy and validity of the examination questions.
: (2) Operating Test The NRC examiners determined that the operating test, as originally proposed by the licensee, was within the range of acceptability expected for a proposed examination.


(2) Operating Test The NRC examiners determined that the operating test, as originally proposed by the licensee, was within the range of acceptability expected for a proposed examination. Changes made to the operating test, documented in a document titled, A Operating Test Comments,@ as well as the final as-administered dynamic simulator scenarios and JPMs are available electronically in the NRC Public Document Room or from ADAMS.
Changes made to the operating test, documented in a document titled, AOperating Test Comments,@ as well as the final as-administered dynamic simulator scenarios and JPMs are available electronically in the NRC Public Document Room or from ADAMS.


The NRC examiners completed operating test grading on November 7, 2012.
The NRC examiners completed operating test grading on November 7, 2012.
: (3) Examination Results Six applicants at the Senior Reactor Operator (SRO) level and five applicants at the Reactor Operator (RO) level were administered written examinations and operating tests. Nine applicants passed all portions of their examinations and were issued their respective operating licenses. One applicant failed the written section of the administered examination and was issued a proposed license denial. One applicant passed all portions of the license examination, but received a written test grade of 82 percent. In accordance with NRC policy, the applicant=s license will be withheld until any written examination appeal possibilities by other applicants have been resolved.


(3) Examination Results Six applicants at the Senior Reactor Operator (SRO) level and five applicants at the Reactor Operator (RO) level were administered written examinations and operating tests. Nine applicants passed all portions of their examinations and were issued their respective operating licenses. One applicant failed the written section of the administered examination and was issued a proposed license denial. One applicant passed all portions of the license examination, but received a written test grade of 82 percent. In accordance with NRC policy, the applicant
If the applicant=s grade is still equal to or greater than 80 percent after any appeal resolution, the applicant will be issued an operating license. If the applicant=s grade has declined below 80 percent, the applicant will be issued a proposed license denial letter and offered the opportunity to appeal any questions the applicant feels were graded incorrectly.
=s license will be withheld until any written examination appeal possibilities by other applicants have been resolved.
 
If the applicant
=s grade is still equal to or greater than 80 percent after any appeal resolution, the applicant will be issued an operating license. If the applicant
=s grade has declined below 80 percent, the applicant will be issued a proposed license denial letter and offered the opportunity to appeal any questions the applicant feels were graded incorrectly.


===.2 Examination Security===
===.2 Examination Security===


====a. Scope====
====a. Scope====
The NRC examiners reviewed and observed the licensee's implementation of examination security requirements during the examination validation and administration to assure compliance with Title 10 of the Code of Federal Regulations, Section 55.49, AIntegrity of Examinations and Tests.
The NRC examiners reviewed and observed the licensee's implementation of examination security requirements during the examination validation and administration to assure compliance with Title 10 of the Code of Federal Regulations, Section 55.49, AIntegrity of Examinations and Tests.@ The examiners used the guidelines provided in NUREG-1021, "Operator Licensing Examination Standards for Power Reactors,@
 
to determine acceptability of the licensee=s examination security activities.
@ The examiners used the guidelines provided in NUREG-1021, "Operator Licensing Exam ination Standards for Power Reactors,@ to determine acceptability of the licensee
=s examination security activities.


====b. Findings====
====b. Findings====
No findings were identified.
No findings were identified.
 
{{a|4OA6}}
{{a|4OA6}}
==4OA6 Management Meetings==
==4OA6 Management Meetings==


===.1 Debrief===
===.1 Debrief===


The chief examiner presented the examinat ion team's preliminary observations and findings on October 11, 2012, to Mr. J. Dills, Operations, and other members of the Palisades Nuclear Plant Operations and Training Department staff.
The chief examiner presented the examination team's preliminary observations and findings on October 11, 2012, to Mr. J. Dills, Operations, and other members of the Palisades Nuclear Plant Operations and Training Department staff.


===.2 Exit Meeting===
===.2 Exit Meeting===


The chief examiner conducted an exit meeting on November 7, 2012, with Mr. B. Nixon, Training Manager, by telephone. The NRC
The chief examiner conducted an exit meeting on November 7, 2012, with Mr. B. Nixon, Training Manager, by telephone. The NRC=s final disposition of the Palisades Nuclear Plant's post-examination comments were disclosed and discussed with Mr. Nixon and his staff during the telephone exit meeting. The examiners asked the licensee whether any of the material used to develop or administer the examination should be considered proprietary. No proprietary or sensitive information was identified during the examination or debrief/exit meetings.
=s final disposition of the Palisades Nuclear Plant's post-examination comments were disclosed and discussed with Mr. Nixon and his staff during the telephone exit meeting. The examiners asked the licensee whether any of the material used to develop or administer the examination should be considered proprietary. No proprietary or sensitive information was identified during the examination or debrief/exit meetings.


ATTACHMENT:
ATTACHMENT:  


=SUPPLEMENTAL INFORMATION=
=SUPPLEMENTAL INFORMATION=


SUPPLEMENTAL INFORMATION KEY POINTS OF CONTACT
Enclosure 1
Licensee  
SUPPLEMENTAL INFORMATION
: [[contact::J. Dills]], Operations Manager  
KEY POINTS OF CONTACT
: [[contact::B. Nixon]], Training Manager  
Licensee
: [[contact::T. Mulford]], Assistant Operations Manager  
: [[contact::J. Dills]], Operations Manager
: [[contact::D. Corbin]], Assistant Operations Manager  
: [[contact::B. Nixon]], Training Manager
: [[contact::T. Mulford]], Assistant Operations Manager
: [[contact::D. Corbin]], Assistant Operations Manager
: [[contact::J. Iliff]], Operations Training Superintendent
: [[contact::J. Iliff]], Operations Training Superintendent
NRC
NRC
: [[contact::T. Taylor]], Senior Resident Inspector  
: [[contact::T. Taylor]], Senior Resident Inspector
: [[contact::R. K. Walton]], Chief Examiner
: [[contact::R. K. Walton]], Chief Examiner
ITEMS OPENED, CLOSED, AND DISCUSSED
ITEMS OPENED, CLOSED, AND DISCUSSED
Opened/Closed
Opened/Closed
None LIST OF ACRONYMS USED ADAMS Agencywide Document Access and Management System CFR Code of Federal Regulations
None
ER Examination Report
LIST OF ACRONYMS USED
JPM Job Performance Measure
ADAMS             Agencywide Document Access and Management System
NRC U.S. Nuclear Regulatory Commission PARS Publicly Available Records System PCP Primary Coolant Pump
CFR               Code of Federal Regulations
PCS Primary Coolant System
ER               Examination Report
PZR Pressurizer
JPM               Job Performance Measure
RO Reactor Operator
NRC               U.S. Nuclear Regulatory Commission
SRO Senior Reactor Operator
PARS             Publicly Available Records System
Enclosure 2 SIMULATION FACILITY REPORT Facility Licensee:   Palisades Nuclear Plant Facility Docket No:   50-255
PCP               Primary Coolant Pump
Operating Tests Administered: October 1 - 11, 2012
PCS               Primary Coolant System
The following documents observations made by the NRC examination team during the initial operator license examination. These observations do not constitute audit or inspection findings and are not, without further verification and review, indicative of non-compliance with 10 CFR
PZR               Pressurizer
RO               Reactor Operator
SRO               Senior Reactor Operator
SIMULATION FACILITY REPORT
Facility Licensee:                     Palisades Nuclear Plant
Facility Docket No:                     50-255
Operating Tests Administered:           October 1 - 11, 2012
The following documents observations made by the NRC examination team during the initial
operator license examination. These observations do not constitute audit or inspection findings
and are not, without further verification and review, indicative of non-compliance with 10 CFR
55.45(b). These observations do not affect NRC certification or approval of the simulation
55.45(b). These observations do not affect NRC certification or approval of the simulation
facility other than to provide information which may be used in future evaluations. No licensee action is required in response to these observations. During the conduct of the simulator portion of the operating tests, the following items were
facility other than to provide information which may be used in future evaluations. No licensee
observed:   ITEM DESCRIPTION Annunciator Bell Alarm would come in, but bell would not sound. Bell fixture repaired between Job Performance Measures (JPMs).
action is required in response to these observations.
Turbine Operator
During the conduct of the simulator portion of the operating tests, the following items were
Computer Plant Process Computer would produce output to Turbine Operator Computer, but computer locked up. Computer was replaced between
observed:
JPMs. RVLIS OPERATE
ITEM                                         DESCRIPTION
PB light out. The bulb illuminating the RVLIS OPERATE light failed. The broken bulb was identified after the crew took the watch for a scenario, but could not
Annunciator Bell       Alarm would come in, but bell would not sound. Bell fixture repaired
be repaired until after scenarios were completed for the day. This issue had no effect to exam administration.  
between Job Performance Measures (JPMs).
 
Turbine Operator       Plant Process Computer would produce output to Turbine Operator
Computer                Computer, but computer locked up. Computer was replaced between
JPMs.
RVLIS OPERATE           The bulb illuminating the RVLIS OPERATE light failed. The broken bulb
PB light out.          was identified after the crew took the watch for a scenario, but could not
be repaired until after scenarios were completed for the day. This issue
had no effect to exam administration.
Enclosure 2
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
Enclosure 3 RO Question 4:
RO Question 4:
Which one of the following correctly completes the statement below?
Which one of the following correctly completes the statement below?
Per EOP-4.0, "Loss of Coolant Accident Recovery," the indication that the Control Room team
Per EOP-4.0, Loss of Coolant Accident Recovery, the indication that the Control Room team
uses to determine when to trip the last two Primary Coolant Pumps (PCPs) is          (1)
uses to determine when to trip the last two Primary Coolant Pumps (PCPs) is          (1)     and
and the reason for tripping all PCPs under these conditions is to         (2)         . a. (1) Primary Coolant System (PCS) subcooling less than 25
the reason for tripping all PCPs under these conditions is to       (2)     .
°F (2) prevent damaging a PCP
a. (1)     Primary Coolant System (PCS) subcooling less than 25°F
b. (1) PCS subcooling less than 25
    (2)   prevent damaging a PCP
°F (2) minimize PCS inventory loss  
b. (1)     PCS subcooling less than 25°F
 
    (2)   minimize PCS inventory loss
c. (1) Pressurizer (PZR) pressure less than minimum for PCP operation (2) prevent damaging a PCP
c. (1)     Pressurizer (PZR) pressure less than minimum for PCP operation
d. (1) PZR pressure less than minimum for PCP operation  
    (2)   prevent damaging a PCP
(2) minimize PCS inventory loss  
d. (1)     PZR pressure less than minimum for PCP operation
 
    (2)   minimize PCS inventory loss
ANSWER: B Applicant's Contention
ANSWER: B
: Question #4 is not valid. There is not enough information in the stem to correctly answer the question. The student needs to know the value of Primary Coolant System temperature and they must have a copy of EOP Supplement 1, "Pressure Temperature Limit Curves," to determine the correct criteria for securing the last two PCPs. Facility Position
Applicant's Contention:
: The facility agrees with the applicant's contention. Question #4 is not valid and has no correct answer because there is not enough information in the stem for the applicant to correctly
Question #4 is not valid. There is not enough information in the stem to correctly answer the
answer the question. EOP-4.0, "Loss of Coolant Accident Recovery," steps 6 and 8 require
question. The student needs to know the value of Primary Coolant System temperature and
Primary Coolant Pumps (PCPs) be monitored and secured during a LOCA if any of the following three conditions are met: (1) Pressurizer Pressure lowers to less than 1300 psia (first two PCPs only), (2) PCS subcooling lowers to less than 25°F and (3) PCP operating limits are not met with per EOP Supplement 1, "Pressure and Temperature Limit Curves.With PCS temperature
they must have a copy of EOP Supplement 1, Pressure Temperature Limit Curves, to
determine the correct criteria for securing the last two PCPs.
Facility Position:
The facility agrees with the applicant's contention. Question #4 is not valid and has no correct
answer because there is not enough information in the stem for the applicant to correctly
answer the question. EOP-4.0, Loss of Coolant Accident Recovery, steps 6 and 8 require
Primary Coolant Pumps (PCPs) be monitored and secured during a LOCA if any of the following
three conditions are met: (1) Pressurizer Pressure lowers to less than 1300 psia (first two PCPs
only), (2) PCS subcooling lowers to less than 25°F and (3) PCP operating limits are not met with
per EOP Supplement 1, Pressure and Temperature Limit Curves. With PCS temperature
above 500°F, the 25°F subcooling criteria applies. If PCS temperature is less than 500°F, the
above 500°F, the 25°F subcooling criteria applies. If PCS temperature is less than 500°F, the
minimum pressure for PCP operating criteria applies. Furthermore, even if PCS temperature
minimum pressure for PCP operating criteria applies. Furthermore, even if PCS temperature
was supplied in the stem, the student would need the curve supplied from EOP Supplement 1
was supplied in the stem, the student would need the curve supplied from EOP Supplement 1
as a reference to determine the correct criteria to apply because knowing the point at which minimum pressure for pump operation becomes more limiting (500°F) is not required knowledge. Based on these issues, the facility recommends that Question #4 be removed from the exam.  
as a reference to determine the correct criteria to apply because knowing the point at which
 
minimum pressure for pump operation becomes more limiting (500°F) is not required
knowledge. Based on these issues, the facility recommends that Question #4 be removed from
the exam.
Enclosure 3
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
Enclosure 3
References:
References
EOP-4.0, Loss of Coolant Accident Recovery, Rev. 21.
EOP-4.0, "Loss of Coolant Accident Recovery," Rev. 21.
EOP Supplement 1, Rev. 5.
EOP Supplement 1, Rev. 5.  
NRC Resolution:
 
The K/A for this question was to test the applicants knowledge of the reasons for tripping PCPs
NRC Resolution
during a Large Break LOC
The K/A for this question was to test the applicant's knowledge of the reasons for tripping PCPs during a Large Break LOC
: [[contact::A. During such an event]], PCS pressure would drop quickly and
: [[contact::A. During such an event]], PCS pressure would drop quickly and
eventually result in a temperature/pressure condition that would require tripping the PCPs,
eventually result in a temperature/pressure condition that would require tripping the PCPs,
either upon exceeding the 25°F subcooling line or exceeding the minimum pressure for PCP
either upon exceeding the 25°F subcooling line or exceeding the minimum pressure for PCP
operation. EOP Supplement 1, "Pressure Temperature Limit Curves," revealed an inflection point at 500°F for both of these curves. Above this point, PCPs must be tripped due to exceeding the 25°F subcooling line to minimize PCS inventory loss. Below 500°F, PCPs must
operation. EOP Supplement 1, Pressure Temperature Limit Curves, revealed an inflection
point at 500°F for both of these curves. Above this point, PCPs must be tripped due to
exceeding the 25°F subcooling line to minimize PCS inventory loss. Below 500°F, PCPs must
be tripped for pump protection (exceeding minimum pressure for PCP operation). The question
be tripped for pump protection (exceeding minimum pressure for PCP operation). The question
stem did not provide temperature/pressure conditions so the applicant would not know what
stem did not provide temperature/pressure conditions so the applicant would not know what
curve would be crossed first.
curve would be crossed first.
The applicants did not need any references to know that there are only two reasons for tripping
The applicants did not need any references to know that there are only two reasons for tripping
the last two PCPs. Independent of PCS temperature or pressure conditions, EOP-4.0, "Loss of
the last two PCPs. Independent of PCS temperature or pressure conditions, EOP-4.0, Loss of
Coolant Accident Recovery," recognized only two reasons for tripping the last two PCPs. Step 6
Coolant Accident Recovery, recognized only two reasons for tripping the last two PCPs. Step 6
has the operators trip the last two PCPs due to subcooling issues, and Step 8 has the operators
has the operators trip the last two PCPs due to subcooling issues, and Step 8 has the operators
trip the last two PCPs due to not satisfying the PCP operating limits.
trip the last two PCPs due to not satisfying the PCP operating limits.
Since there were no PCS pressure/temperature conditions provided in the stem of the question,
Since there were no PCS pressure/temperature conditions provided in the stem of the question,
there was no one correct answer. Without references, Distracter "B" would be considered correct for EOP -4.0, Step 6. Distracter "C" would be considered correct for EOP-4.0, Step 8.
there was no one correct answer. Without references, Distracter B would be considered
In accordance with NUREG-1021, ES 403, step D.1.c, the NRC will accept two correct answers. Both distracters "B" and "C" were determined to be correct answers to Q4.  
correct for EOP -4.0, Step 6. Distracter C would be considered correct for EOP-4.0, Step 8.
 
In accordance with NUREG-1021, ES 403, step D.1.c, the NRC will accept two correct answers.
Both distracters B and C were determined to be correct answers to Q4.
Enclosure 3
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
Enclosure 3 RO Question 14:
RO Question 14:
Given the following with the Plant at full power:  
Given the following with the Plant at full power:
* A manual Reactor trip occurs in response to a Steam Line Break inside Containment  
    *   A manual Reactor trip occurs in response to a Steam Line Break inside Containment
* During the transient, Y40, Preferred AC Bus, de-energizes  
    *   During the transient, Y40, Preferred AC Bus, de-energizes
* Pressurizer pressure is 1725 psia and lowering slowly  
    *   Pressurizer pressure is 1725 psia and lowering slowly
* Containment pressure is 4.2 psig and rising  
    *   Containment pressure is 4.2 psig and rising
* The following alarms annunciate:
    *   The following alarms annunciate:
o EK-1126, CIS INITIATED
o EK-1126, CIS INITIATED
o EK-1342, SAFETY INJ INITIATED
o EK-1342, SAFETY INJ INITIATED
Which one of the following describes the action(s) required, if any, based on the above
Which one of the following describes the action(s) required, if any, based on the above
conditions for the Right Channel of Containment Spray and Safety Injection?  
conditions for the Right Channel of Containment Spray and Safety Injection?
 
a. Containment Spray and Safety Injection must be manually initiated.
a. Containment Spray and Safety Injection must be manually initiated.
b. Containment Spray must be manually initiated only.
b. Containment Spray must be manually initiated only.
c. Safety Injection must be manually initiated only.
c. Safety Injection must be manually initiated only.
d. No actions required; Containment Spray and Safety Injection will automatically initiate.
d. No actions required; Containment Spray and Safety Injection will automatically initiate.
ANSWER: A Applicant's Contention
ANSWER: A
: Question #14 is not valid. There is no correct answer because there is information in the stem that conflicts with all correct answers. If Preferred AC Bus, Y40, is de-energized, it is not possible for EK1342 to be alarming. Facility Position
Applicant's Contention:
:
Question #14 is not valid. There is no correct answer because there is information in the stem
that conflicts with all correct answers. If Preferred AC Bus, Y40, is de-energized, it is not
possible for EK1342 to be alarming.
Facility Position:
The facility agrees with the applicant's contention. Question #14 has no correct answer
The facility agrees with the applicant's contention. Question #14 has no correct answer
because of conflicting information given in the stem of the question. EK-1342, "SAFETY INJ INITIATED" alarm and a loss of Y40, Preferred AC Bus, cannot exist at the same time. EK-1342 actuates when both trains of Safety Injection actuate via SIS Relays SIS-1 and SIS-6.
because of conflicting information given in the stem of the question. EK-1342, SAFETY INJ
INITIATED alarm and a loss of Y40, Preferred AC Bus, cannot exist at the same time. EK-
1342 actuates when both trains of Safety Injection actuate via SIS Relays SIS-1 and SIS-6.
If Y40 is de-energized, then SIS-6 relay will not actuate because relay 5P-8 does not have
If Y40 is de-energized, then SIS-6 relay will not actuate because relay 5P-8 does not have
power. If SIS-6 relay does not actuate, EK1342 will not alarm because both trains must receive
power. If SIS-6 relay does not actuate, EK1342 will not alarm because both trains must receive
an actuation signal. If the applicant sees that EK-1342 is alarming in the stem, he/she would
an actuation signal. If the applicant sees that EK-1342 is alarming in the stem, he/she would
believe that the Safety Injection Equipment actuated and 'B' would be the correct answer. Therefore, the presence of EK-1342 in the stem makes this question operationally invalid and no answers are correct. The facility proposes that Question #14 be removed from the exam.
believe that the Safety Injection Equipment actuated and B would be the correct answer.
References
Therefore, the presence of EK-1342 in the stem makes this question operationally invalid and
ARP-7, Window 42, Rev. 71. E-Prints E-17, Sheet 3 (Rev. 18), and Sheet 4 (Rev. 17).  
no answers are correct. The facility proposes that Question #14 be removed from the exam.
 
References:
ARP-7, Window 42, Rev. 71.
E-Prints E-17, Sheet 3 (Rev. 18), and Sheet 4 (Rev. 17).
Enclosure 3
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
Enclosure 3
NRC Resolution:
NRC Resolution
The applicant argued that a loss of AC Bus Y40 cannot coexist with EK-1342 being in alarm.
The applicant argued that a loss of AC Bus Y40 cannot coexist with EK-1342 being in alarm.
Specifically, EK-1342 cannot alarm since the AC Bus Y40 provided power to one of the two
Specifically, EK-1342 cannot alarm since the AC Bus Y40 provided power to one of the two inputs of the alarm circuit and the logic required both inputs to cause the alarm condition to
inputs of the alarm circuit and the logic required both inputs to cause the alarm condition to
occur. The question does not provide any specific information as to the sequence of events for the given conditions. Regarding the loss of AC Bus Y40, the question only stated, a loss of Bus Y40 occurred "during the transient.There was no timeline relating the loss of Bus Y40 to the annunciator alarms. NUREG-1021, "Operator Licensing Examination Standards for Power
occur. The question does not provide any specific information as to the sequence of events for
Reactors," does not have any convention on how to read bulleted conditions in the context of time sequencing. There were, however, precedences for time sequencing events during exams by adding relative times to events (e.g., t = 0 reactor trip; t = +10 seconds, bus de-energized) or connecting related events to one another, (e.g., the loss of the bus occurred at the time of the reactor trip). Neither of these methods for time sequencing were employed for this question.
the given conditions. Regarding the loss of AC Bus Y40, the question only stated, a loss of Bus
Y40 occurred during the transient. There was no timeline relating the loss of Bus Y40 to the
annunciator alarms. NUREG-1021, Operator Licensing Examination Standards for Power
Reactors, does not have any convention on how to read bulleted conditions in the context of
time sequencing. There were, however, precedences for time sequencing events during exams
by adding relative times to events (e.g., t = 0 reactor trip; t = +10 seconds, bus de-energized) or
connecting related events to one another, (e.g., the loss of the bus occurred at the time of the
reactor trip). Neither of these methods for time sequencing were employed for this question.
The applicants did not ask any questions during the written exam for Q14 indicating there was
The applicants did not ask any questions during the written exam for Q14 indicating there was
no confusion with the conditions given, including the apparent conflict between a loss of power to one of EK-1342 inputs with the loss of AC Bus Y40. The applicants chose Distracters "A" or "B" indicating that they recognized that the loss of Y40 would require a manual start of Right Channel safety equipment. This also indicated that the applicants evidently answered the
no confusion with the conditions given, including the apparent conflict between a loss of power
to one of EK-1342 inputs with the loss of AC Bus Y40. The applicants chose Distracters A or
B indicating that they recognized that the loss of Y40 would require a manual start of Right
Channel safety equipment. This also indicated that the applicants evidently answered the
question not knowing the relationship between EK-1342 and AC Bus Y40.
question not knowing the relationship between EK-1342 and AC Bus Y40.
Condition 1: If the applicants read the question as written, and assumed that all the
Condition 1: If the applicants read the question as written, and assumed that all the
conditions in the stem of the question were true, then the applicants must have assumed that the annunciators alarmed before the loss of AC Bus Y40. This condition would result in a successful actuation of safety train equipment with distracter "D" being the
conditions in the stem of the question were true, then the applicants must have assumed
correct answer. However, none of the applicants chose distracter "D.
that the annunciators alarmed before the loss of AC Bus Y40. This condition would
 
result in a successful actuation of safety train equipment with distracter D being the
Condition 2: Independent of the annunciators, and with a failure of Y40, the applicants should know that with containment pressure at 4.2 psig and rising, containment spray must be manually initiated. Then "B" distracter would be correct.
correct answer. However, none of the applicants chose distracter  
: [[contact::D.
Condition 2: Independent of the annunciators]], and with a failure of Y40, the applicants
should know that with containment pressure at 4.2 psig and rising, containment spray
must be manually initiated. Then B distracter would be correct.
Since both conditions 1 and 2 above are logical explanations for the conditions given in the
Since both conditions 1 and 2 above are logical explanations for the conditions given in the
question and since both answers are opposite from each other ("B" distracter - manually actuate
question and since both answers are opposite from each other (B distracter - manually actuate
equipment and "D" distracter - successful automatic actuation of equipment occurred - take no manual actions), then there are two conflicting answers. As such, in accordance with NUREG-1021, ES-403, D.1.c, Q14 is deleted from the exam.
equipment and D distracter - successful automatic actuation of equipment occurred - take no
manual actions), then there are two conflicting answers. As such, in accordance with
NUREG-1021, ES-403, D.1.c, Q14 is deleted from the exam.
Enclosure 3
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
Enclosure 3
RO Question 33:
RO Question 33:
Which one of the following correctly completes the statement below describing the minimum
Which one of the following correctly completes the statement below describing the minimum
required level and source of makeup water for T-73, Quench Tank?  
required level and source of makeup water for T-73, Quench Tank?
 
The Quench Tank is maintained at a minimum water level of         (1)   by adding makeup water
The Quench Tank is maintained at a minimum
using             (2)         .
water level of     (1)
a. (1)   70%
by adding makeup water using                 (2)               . a. (1) 70%  
    (2)   P-90A or P-90B, Primary Makeup Tank Pumps
(2) P-90A or P-90B, Primary Makeup Tank Pumps  
b. (1)   70%
 
    (2)   P-79A or P-79B, Primary System Makeup Transfer Pumps
b. (1) 70% (2) P-79A or P-79B, Primary System Makeup Transfer Pumps
c. (1)   40%
c. (1) 40%  
    (2)   P-90A or P-90B
(2) P-90A or P-90B
d. (1)   40%
d. (1) 40% (2) P-79A or P-79B
    (2)   P-79A or P-79B
ANSWER: A Applicant's Contention
ANSWER: A
: Question #33 has two correct answers. Choices 'A' and 'B' are both correct because the Quench Tank makeup supply can be lined up from P-79A/B Primary System Makeup Transfer
Applicant's Contention:
Pumps, per procedure RWSO-1, "Transfer of Water from Primary Makeup Storage Tank (T-81)
Question #33 has two correct answers. Choices A and B are both correct because the
for T-90 Loads." Facility Position
Quench Tank makeup supply can be lined up from P-79A/B Primary System Makeup Transfer
: The facility agrees with the applicant that Q#33 has two correct answers. The Quench Tanks is
Pumps, per procedure RWSO-1, Transfer of Water from Primary Makeup Storage Tank (T-81)
normally supplied makeup water from P-90A/B, Primary Makeup Tank Pumps, but is capable of being supplied by P-79A/B, Primary System Makeup Transfer Pumps, per procedure RWSO-1, "Transfer of Water from Primary Makeup Storage Tank (T-81) for T-90 Loads.This procedure has been performed recently (August 2011) while the P-90A/B pumps were out of service. Both P-90A/B have been cautioned tagged "OFF" since June 2010 due to a leaking boric acid flow
for T-90 Loads.
Facility Position:
The facility agrees with the applicant that Q#33 has two correct answers. The Quench Tanks is
normally supplied makeup water from P-90A/B, Primary Makeup Tank Pumps, but is capable of
being supplied by P-79A/B, Primary System Makeup Transfer Pumps, per procedure RWSO-1,
Transfer of Water from Primary Makeup Storage Tank (T-81) for T-90 Loads. This procedure
has been performed recently (August 2011) while the P-90A/B pumps were out of service. Both
P-90A/B have been cautioned tagged OFF since June 2010 due to a leaking boric acid flow
path to the SIRW Tank (WO #228532). The pumps were left off until required to be used for
path to the SIRW Tank (WO #228532). The pumps were left off until required to be used for
makeup. Also, P-90A was out of service from May 2012 until September 2012 due to a failed
makeup. Also, P-90A was out of service from May 2012 until September 2012 due to a failed
seal. Based on the combination of the problems the plant has experienced with P-90A/B pumps and the fact that P79A/B is capable of, and routinely is, used to supply P-90A/B loads, it is easy to understand why 3 of 11 applicants selected 'B' as the correct answer.
seal. Based on the combination of the problems the plant has experienced with P-90A/B pumps
References
and the fact that P79A/B is capable of, and routinely is, used to supply P-90A/B loads, it is easy
:
to understand why 3 of 11 applicants selected B as the correct answer.
RWSO-1, "Transfer of Water from Primary Makeup Storage Tank (T-81) for T-90 Loads."
References:
RWSO-1, Transfer of Water from Primary Makeup Storage Tank (T-81) for T-90 Loads.
WO 228532, MV-CV2157 valve Leaks by, Replace valve (Weld)
WO 228532, MV-CV2157 valve Leaks by, Replace valve (Weld)
P&ID M-220, Makeup Domestic Water & Chemical Injection Systems, Rev. 94. P&ID M-652, Primary System Make-up Water Utility Water & Oil Waste System, Rev. 70.
P&ID M-220, Makeup Domestic Water & Chemical Injection Systems, Rev. 94.
P&ID M-652, Primary System Make-up Water Utility Water & Oil Waste System, Rev. 70.
Enclosure 3
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION
Enclosure 3
NRC Resolution:
NRC Resolution
The Primary System Make-Up Water Pumps, P-90A/B, are normally aligned with one pump
The Primary System Make-Up Water Pumps, P-90A/B, are normally aligned with one pump continuously running to provide water to various primary plant components including the pressurizer quench tank and to the chemical volume control system. However, the plant has
continuously running to provide water to various primary plant components including the
pressurizer quench tank and to the chemical volume control system. However, the plant has
had problems with these pumps including pump seal leakage and leakage past a valve seat.
had problems with these pumps including pump seal leakage and leakage past a valve seat.
As previously mentioned, both P-90A/B pumps were out of service for a time requiring the licensee to install a spool piece and use water from an alternate source, the Primary System Makeup Transfer Pumps P-79A/B, to supply the loads that would normally be serviced by
As previously mentioned, both P-90A/B pumps were out of service for a time requiring the
licensee to install a spool piece and use water from an alternate source, the Primary System
Makeup Transfer Pumps P-79A/B, to supply the loads that would normally be serviced by
P-90A/
P-90A/
: [[contact::B. A licensee procedure]], RWSO-1, allowed the use of the P-79A/B pumps to supply
: [[contact::B. A licensee procedure]], RWSO-1, allowed the use of the P-79A/B pumps to supply
these loads. This condition existed in August 2011, a time when the applicants were collecting
these loads. This condition existed in August 2011, a time when the applicants were collecting
in-plant experience. It would be reasonable to assume that some of the applicants believed that the P-79A/B pumps were the 'normal' method for supply water to the pressurizer quench tank. But this would be incorrect, since the P-90A/B pumps were the 'normal' method for supplying
in-plant experience. It would be reasonable to assume that some of the applicants believed that
water to the pressurizer quench tank. Pumps P-79A/B were an 'alternate' flow path to fill the
the P-79A/B pumps were the normal method for supply water to the pressurizer quench tank.
But this would be incorrect, since the P-90A/B pumps were the normal method for supplying
water to the pressurizer quench tank. Pumps P-79A/B were an alternate flow path to fill the
quench tank, via a normally removed spoolpiece.
quench tank, via a normally removed spoolpiece.
NUREG-1021, Appendix E, "Policies and Guidelines for Taking NRC Examinations," stated in Part B7, "When answering a question, do not make assumptions regarding conditions that are
NUREG-1021, Appendix E, Policies and Guidelines for Taking NRC Examinations, stated in
Part B7, When answering a question, do not make assumptions regarding conditions that are
not specified in the question unless they occur as a consequence of other conditions that are
not specified in the question unless they occur as a consequence of other conditions that are
stated in the question.There were no other conditions stated in the question that would lead
stated in the question. There were no other conditions stated in the question that would lead
the applicants to believe that the normal P-90A/B pumps were unavailable, nor was there any
the applicants to believe that the normal P-90A/B pumps were unavailable, nor was there any
statement about the status of a spool-piece that tied the alternate source to the normal source of water to the quench tank. If the applicants had any concerns about the initial conditions of the question, they should have asked a clarifying question during the exam. However, no
statement about the status of a spool-piece that tied the alternate source to the normal source
questions were asked by the applicants during the exam for Q33.  
of water to the quench tank. If the applicants had any concerns about the initial conditions of
 
the question, they should have asked a clarifying question during the exam. However, no
The alternate method was in use during a period when the applicants were 'on shift', however, the applicants should still have known that the normal source of fill to the quench tank was P-90A/B and they should have known that the use of the P79A/B pumps was an abnormal,
questions were asked by the applicants during the exam for Q33.
temporary condition. Therefore, distracter "B" was considered an incorrect answer.
The alternate method was in use during a period when the applicants were on shift, however,
Distracter "A" was considered the only correct answer for Q33.  
the applicants should still have known that the normal source of fill to the quench tank was
 
P-90A/B and they should have known that the use of the P79A/B pumps was an abnormal,
A. Vitale     -2-
temporary condition. Therefore, distracter B was considered an incorrect answer.
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely, /RA/   Hironori Peterson, Chief Operations Branch
Distracter A was considered the only correct answer for Q33.
Division of Reactor Safety Docket Nos. 50-255; 72-007 License No. DPR-20
Enclosure 3
Enclosures:   1. Operator Licensing Examination Report 05000255/2012301 w/Attachment: Supplemental Information 2. Simulation Facility Report
A. Vitale                                               -2-
3. Written Examination Post-Examination Comment Resolution cc w/encl: Distribution via ListServŽ
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's "Rules of
DISTRIBUTION w/encl
Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the
: Cayetano Santos RidsNrrPMPalisades Resource RidsNrrDorlLpl3-1 Resource
NRC Public Document Room or from the Publicly Available Records System (PARS) component of
RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson
NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from
Steven Orth
the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Jared Heck
Sincerely,
                                                        /RA/
Hironori Peterson, Chief
Operations Branch
Division of Reactor Safety
Docket Nos. 50-255; 72-007
License No. DPR-20
Enclosures:
1. Operator Licensing Examination Report 05000255/2012301
w/Attachment: Supplemental Information
2. Simulation Facility Report
3. Written Examination Post-Examination Comment Resolution
cc w/encl:         Distribution via ListServ'
DISTRIBUTION w/encl:
Cayetano Santos                                                   Christine Lipa
RidsNrrPMPalisades Resource                                       Carole Ariano
RidsNrrDorlLpl3-1 Resource                                       Linda Linn
RidsNrrDirsIrib Resource                                         DRPIII
Chuck Casto                                                       DRSIII
Cynthia Pederson                                                 Tammy Tomczak
Steven Orth                                                       John McHale, NRR
Jared Heck                                                       Janet Kweiser, DRS
Allan Barker
Allan Barker
Christine Lipa
DOCUMENT NAME: PAL 2012 301.docx
Carole Ariano Linda Linn
Publicly Available               Non-Publicly Available         Sensitive         Non-Sensitive
DRPIII DRSIII Tammy Tomczak
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with
John McHale, NRR Janet Kweiser, DRS
attach/encl "N" = No copy
 
OFFICE         RIII                       RIII                     RIII                     RIII
DOCUMENT NAME: PAL 2012 301.docx
NAME           RKWalton:cs               HPeterson
Publicly Available Non-Publicly Available
DATE           11/21/12                   11/27/12
Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICIAL RECORD COPY
OFFICE RIII RIII RIII RIII NAME RKWalton:cs HPeterson   DATE 11/21/12 11/27/12   OFFICIAL RECORD COPY
}}
}}

Latest revision as of 19:43, 20 December 2019

Er 05000255-12-301; Entergy Nuclear Operations, Inc; 10/01/2012 - 10/24/2012; Palisades Nuclear Plant, Initial License Examination Report
ML12332A142
Person / Time
Site: Palisades  Entergy icon.png
Issue date: 11/27/2012
From: Hironori Peterson
Operations Branch III
To: Vitale A
Entergy Nuclear Operations
References
ER-12-301
Download: ML12332A142 (16)


Text

ber 27, 2012

SUBJECT:

PALISADES NUCLEAR PLANT NRC INITIAL LICENSE EXAMINATION REPORT 05000255/2012301

Dear Mr. Vitale:

On October 24, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed the initial operator licensing examination process for license applicants employed at your Palisades Nuclear Plant. The enclosed report documents the results of those examinations. Preliminary observations noted during the examination process were discussed on October 11, 2012, with Mr. J. Dills and other members of your staff. An exit meeting was conducted by telephone on November 7, 2012, between Mr. B. Nixon of your staff and Mr. R. K. Walton, Chief Operator Licensing Examiner, to review the proposed final grading of the written examination for the license applicants. During the telephone conversation, NRC resolutions of the station=s post-examination comments, initially received by the NRC on October 24, 2012, were discussed.

The NRC examiners administered an initial license examination operating test during the weeks of October 1 and October 9, 2012. The written examination was administered by Palisades Nuclear Plant Training Department personnel on October 12, 2012. Six Senior Reactor Operator and five Reactor Operator applicants were administered license examinations. The results of the examinations were finalized on November 15, 2012. One applicant failed one or more sections of the administered examination and was issued a proposed license denial letter.

Ten applicants passed all sections of their respective examinations and six were issued senior operator licenses and three were issued operator licenses. In accordance with NRC policy, the license for the remaining one applicant is being withheld pending the outcome of any written examination appeal that may be initiated.

The written examination will be withheld from public disclosure for 24 months per your request.

However, since an applicant received a proposed license denial letter because of a written examination grade that is less than 80 percent, the applicant will be provided a copy of the written examination. For examination security purposes, your staff should consider that written examination uncontrolled and exposed to the public. In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's

"Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-255;72-007 License No. DPR-20

Enclosures:

1. Operator Licensing Examination Report 05000255/2012301 w/Attachment: Supplemental Information 2. Simulation Facility Report 3. Written Examination Post-Examination Comment Resolution

REGION III==

Docket No: 50-255 License No: DPR-20 Report No: 05000255/2012301 Licensee: Entergy Nuclear Operations, Inc.

Facility: Palisades Nuclear Plant Location: Covert, Michigan Dates: October 1 to October 24, 2012 Inspectors: R. K. Walton, Chief Examiner C. Moore, Examiner J. Kellum, Examiner Approved by: H. Peterson, Chief Operations Branch Division of Reactor Safety Enclosure 1

SUMMARY OF FINDINGS

ER 05000255/2012301; 10/01/2012 - 10/24/2012; Entergy Nuclear Operations, Inc.,

Palisades Nuclear Plant; Initial License Examination Report.

The announced initial operator licensing examination was conducted by regional U.S. Nuclear Regulatory Commission (NRC) examiners in accordance with the guidance of NUREG-1021,

AOperator Licensing Examination Standards for Power Reactors,@ Revision 9, Supplement 1.

Examination Summary Ten of eleven applicants passed all sections of their respective examinations. Six applicants were issued senior operator licenses and four applicants were issued operator licenses.

One applicant failed one or more sections of the administered examination and was issued proposed license denial. The license(s) for the remaining applicant is being held and may be issued pending the outcome of any written examination appeal. (Section 4OA5.1)

REPORT DETAILS

4OA5 Other Activities

.1 Initial Licensing Examinations

a. Examination Scope

The NRC examiners and members of the facility licensees staff used the guidance prescribed in NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9, Supplement 1, to develop, validate, administer, and grade the written examination and operating test. Members of the facility licensees staff prepared the outline and developed the written examination and operating test. The NRC examiners validated the proposed examination during the week of September 4, 2012, with the assistance of members of the facility licensees staff. During the on-site validation week, the examiners audited three license applications for accuracy.

The NRC examiners, with the assistance of members of the facility licensees staff, administered the operating test, consisting of job performance measures (JPMs) and dynamic simulator scenarios, during the period of October 1 through October 11, 2012.

The facility licensee administered the written examination on October 12, 2012.

b. Findings

(1) Written Examination The NRC examiners determined that the written examination, as proposed by the licensee, was within the range of acceptability expected for a proposed examination.

Less than 20 percent of the proposed examination questions were determined to be unsatisfactory and required modification or replacement.

On October 24, 2012, the licensee submitted documentation noting that there were three post-examination comments for consideration by the NRC examiners when grading the written examination. The post-examination comments and the NRC resolution for the post-examination comments are included in Enclosure 3 of this report.

The final as-administered examination and answer key (ADAMS Accession Numbers ML12324A288 and ML12324A291) will be available in 24 months electronically in the NRC Public Document Room or from the Agencywide Documents Access and Management System (ADAMS). All changes made to the proposed written examination, were made in accordance with NUREG-1021, "Operator Licensing Examination Standards for Power Reactors, and documented on Form ES-401-9, Written Examination Review Worksheet.

The NRC examiners graded the written examination on November 7, 2012, and conducted a review of each missed question to determine the accuracy and validity of the examination questions.

(2) Operating Test The NRC examiners determined that the operating test, as originally proposed by the licensee, was within the range of acceptability expected for a proposed examination.

Changes made to the operating test, documented in a document titled, AOperating Test Comments,@ as well as the final as-administered dynamic simulator scenarios and JPMs are available electronically in the NRC Public Document Room or from ADAMS.

The NRC examiners completed operating test grading on November 7, 2012.

(3) Examination Results Six applicants at the Senior Reactor Operator (SRO) level and five applicants at the Reactor Operator (RO) level were administered written examinations and operating tests. Nine applicants passed all portions of their examinations and were issued their respective operating licenses. One applicant failed the written section of the administered examination and was issued a proposed license denial. One applicant passed all portions of the license examination, but received a written test grade of 82 percent. In accordance with NRC policy, the applicant=s license will be withheld until any written examination appeal possibilities by other applicants have been resolved.

If the applicant=s grade is still equal to or greater than 80 percent after any appeal resolution, the applicant will be issued an operating license. If the applicant=s grade has declined below 80 percent, the applicant will be issued a proposed license denial letter and offered the opportunity to appeal any questions the applicant feels were graded incorrectly.

.2 Examination Security

a. Scope

The NRC examiners reviewed and observed the licensee's implementation of examination security requirements during the examination validation and administration to assure compliance with Title 10 of the Code of Federal Regulations, Section 55.49, AIntegrity of Examinations and Tests.@ The examiners used the guidelines provided in NUREG-1021, "Operator Licensing Examination Standards for Power Reactors,@

to determine acceptability of the licensee=s examination security activities.

b. Findings

No findings were identified.

4OA6 Management Meetings

.1 Debrief

The chief examiner presented the examination team's preliminary observations and findings on October 11, 2012, to Mr. J. Dills, Operations, and other members of the Palisades Nuclear Plant Operations and Training Department staff.

.2 Exit Meeting

The chief examiner conducted an exit meeting on November 7, 2012, with Mr. B. Nixon, Training Manager, by telephone. The NRC=s final disposition of the Palisades Nuclear Plant's post-examination comments were disclosed and discussed with Mr. Nixon and his staff during the telephone exit meeting. The examiners asked the licensee whether any of the material used to develop or administer the examination should be considered proprietary. No proprietary or sensitive information was identified during the examination or debrief/exit meetings.

ATTACHMENT:

SUPPLEMENTAL INFORMATION

Enclosure 1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

J. Dills, Operations Manager
B. Nixon, Training Manager
T. Mulford, Assistant Operations Manager
D. Corbin, Assistant Operations Manager
J. Iliff, Operations Training Superintendent

NRC

T. Taylor, Senior Resident Inspector
R. K. Walton, Chief Examiner

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened/Closed

None

LIST OF ACRONYMS USED

ADAMS Agencywide Document Access and Management System

CFR Code of Federal Regulations

ER Examination Report

JPM Job Performance Measure

NRC U.S. Nuclear Regulatory Commission

PARS Publicly Available Records System

PCP Primary Coolant Pump

PCS Primary Coolant System

PZR Pressurizer

RO Reactor Operator

SRO Senior Reactor Operator

SIMULATION FACILITY REPORT

Facility Licensee: Palisades Nuclear Plant

Facility Docket No: 50-255

Operating Tests Administered: October 1 - 11, 2012

The following documents observations made by the NRC examination team during the initial

operator license examination. These observations do not constitute audit or inspection findings

and are not, without further verification and review, indicative of non-compliance with 10 CFR 55.45(b). These observations do not affect NRC certification or approval of the simulation

facility other than to provide information which may be used in future evaluations. No licensee

action is required in response to these observations.

During the conduct of the simulator portion of the operating tests, the following items were

observed:

ITEM DESCRIPTION

Annunciator Bell Alarm would come in, but bell would not sound. Bell fixture repaired

between Job Performance Measures (JPMs).

Turbine Operator Plant Process Computer would produce output to Turbine Operator

Computer Computer, but computer locked up. Computer was replaced between

JPMs.

RVLIS OPERATE The bulb illuminating the RVLIS OPERATE light failed. The broken bulb

PB light out. was identified after the crew took the watch for a scenario, but could not

be repaired until after scenarios were completed for the day. This issue

had no effect to exam administration.

Enclosure 2

WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION

RO Question 4:

Which one of the following correctly completes the statement below?

Per EOP-4.0, Loss of Coolant Accident Recovery, the indication that the Control Room team

uses to determine when to trip the last two Primary Coolant Pumps (PCPs) is (1) and

the reason for tripping all PCPs under these conditions is to (2) .

a. (1) Primary Coolant System (PCS) subcooling less than 25°F

(2) prevent damaging a PCP

b. (1) PCS subcooling less than 25°F

(2) minimize PCS inventory loss

c. (1) Pressurizer (PZR) pressure less than minimum for PCP operation

(2) prevent damaging a PCP

d. (1) PZR pressure less than minimum for PCP operation

(2) minimize PCS inventory loss

ANSWER: B

Applicant's Contention:

Question #4 is not valid. There is not enough information in the stem to correctly answer the

question. The student needs to know the value of Primary Coolant System temperature and

they must have a copy of EOP Supplement 1, Pressure Temperature Limit Curves, to

determine the correct criteria for securing the last two PCPs.

Facility Position:

The facility agrees with the applicant's contention. Question #4 is not valid and has no correct

answer because there is not enough information in the stem for the applicant to correctly

answer the question. EOP-4.0, Loss of Coolant Accident Recovery, steps 6 and 8 require

Primary Coolant Pumps (PCPs) be monitored and secured during a LOCA if any of the following

three conditions are met: (1) Pressurizer Pressure lowers to less than 1300 psia (first two PCPs

only), (2) PCS subcooling lowers to less than 25°F and (3) PCP operating limits are not met with

per EOP Supplement 1, Pressure and Temperature Limit Curves. With PCS temperature

above 500°F, the 25°F subcooling criteria applies. If PCS temperature is less than 500°F, the

minimum pressure for PCP operating criteria applies. Furthermore, even if PCS temperature

was supplied in the stem, the student would need the curve supplied from EOP Supplement 1

as a reference to determine the correct criteria to apply because knowing the point at which

minimum pressure for pump operation becomes more limiting (500°F) is not required

knowledge. Based on these issues, the facility recommends that Question #4 be removed from

the exam.

Enclosure 3

WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION

References:

EOP-4.0, Loss of Coolant Accident Recovery, Rev. 21.

EOP Supplement 1, Rev. 5.

NRC Resolution:

The K/A for this question was to test the applicants knowledge of the reasons for tripping PCPs

during a Large Break LOC

A. During such an event, PCS pressure would drop quickly and

eventually result in a temperature/pressure condition that would require tripping the PCPs,

either upon exceeding the 25°F subcooling line or exceeding the minimum pressure for PCP

operation. EOP Supplement 1, Pressure Temperature Limit Curves, revealed an inflection

point at 500°F for both of these curves. Above this point, PCPs must be tripped due to

exceeding the 25°F subcooling line to minimize PCS inventory loss. Below 500°F, PCPs must

be tripped for pump protection (exceeding minimum pressure for PCP operation). The question

stem did not provide temperature/pressure conditions so the applicant would not know what

curve would be crossed first.

The applicants did not need any references to know that there are only two reasons for tripping

the last two PCPs. Independent of PCS temperature or pressure conditions, EOP-4.0, Loss of

Coolant Accident Recovery, recognized only two reasons for tripping the last two PCPs. Step 6

has the operators trip the last two PCPs due to subcooling issues, and Step 8 has the operators

trip the last two PCPs due to not satisfying the PCP operating limits.

Since there were no PCS pressure/temperature conditions provided in the stem of the question,

there was no one correct answer. Without references, Distracter B would be considered

correct for EOP -4.0, Step 6. Distracter C would be considered correct for EOP-4.0, Step 8.

In accordance with NUREG-1021, ES 403, step D.1.c, the NRC will accept two correct answers.

Both distracters B and C were determined to be correct answers to Q4.

Enclosure 3

WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION

RO Question 14:

Given the following with the Plant at full power:

  • During the transient, Y40, Preferred AC Bus, de-energizes
  • Pressurizer pressure is 1725 psia and lowering slowly
  • Containment pressure is 4.2 psig and rising
  • The following alarms annunciate:

o EK-1126, CIS INITIATED

o EK-1342, SAFETY INJ INITIATED

Which one of the following describes the action(s) required, if any, based on the above

conditions for the Right Channel of Containment Spray and Safety Injection?

a. Containment Spray and Safety Injection must be manually initiated.

b. Containment Spray must be manually initiated only.

c. Safety Injection must be manually initiated only.

d. No actions required; Containment Spray and Safety Injection will automatically initiate.

ANSWER: A

Applicant's Contention:

Question #14 is not valid. There is no correct answer because there is information in the stem

that conflicts with all correct answers. If Preferred AC Bus, Y40, is de-energized, it is not

possible for EK1342 to be alarming.

Facility Position:

The facility agrees with the applicant's contention. Question #14 has no correct answer

because of conflicting information given in the stem of the question. EK-1342, SAFETY INJ

INITIATED alarm and a loss of Y40, Preferred AC Bus, cannot exist at the same time. EK-

1342 actuates when both trains of Safety Injection actuate via SIS Relays SIS-1 and SIS-6.

If Y40 is de-energized, then SIS-6 relay will not actuate because relay 5P-8 does not have

power. If SIS-6 relay does not actuate, EK1342 will not alarm because both trains must receive

an actuation signal. If the applicant sees that EK-1342 is alarming in the stem, he/she would

believe that the Safety Injection Equipment actuated and B would be the correct answer.

Therefore, the presence of EK-1342 in the stem makes this question operationally invalid and

no answers are correct. The facility proposes that Question #14 be removed from the exam.

References:

ARP-7, Window 42, Rev. 71.

E-Prints E-17, Sheet 3 (Rev. 18), and Sheet 4 (Rev. 17).

Enclosure 3

WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION

NRC Resolution:

The applicant argued that a loss of AC Bus Y40 cannot coexist with EK-1342 being in alarm.

Specifically, EK-1342 cannot alarm since the AC Bus Y40 provided power to one of the two

inputs of the alarm circuit and the logic required both inputs to cause the alarm condition to

occur. The question does not provide any specific information as to the sequence of events for

the given conditions. Regarding the loss of AC Bus Y40, the question only stated, a loss of Bus

Y40 occurred during the transient. There was no timeline relating the loss of Bus Y40 to the

annunciator alarms. NUREG-1021, Operator Licensing Examination Standards for Power

Reactors, does not have any convention on how to read bulleted conditions in the context of

time sequencing. There were, however, precedences for time sequencing events during exams

by adding relative times to events (e.g., t = 0 reactor trip; t = +10 seconds, bus de-energized) or

connecting related events to one another, (e.g., the loss of the bus occurred at the time of the

reactor trip). Neither of these methods for time sequencing were employed for this question.

The applicants did not ask any questions during the written exam for Q14 indicating there was

no confusion with the conditions given, including the apparent conflict between a loss of power

to one of EK-1342 inputs with the loss of AC Bus Y40. The applicants chose Distracters A or

B indicating that they recognized that the loss of Y40 would require a manual start of Right

Channel safety equipment. This also indicated that the applicants evidently answered the

question not knowing the relationship between EK-1342 and AC Bus Y40.

Condition 1: If the applicants read the question as written, and assumed that all the

conditions in the stem of the question were true, then the applicants must have assumed

that the annunciators alarmed before the loss of AC Bus Y40. This condition would

result in a successful actuation of safety train equipment with distracter D being the

correct answer. However, none of the applicants chose distracter

D.

Condition 2: Independent of the annunciators, and with a failure of Y40, the applicants

should know that with containment pressure at 4.2 psig and rising, containment spray

must be manually initiated. Then B distracter would be correct.

Since both conditions 1 and 2 above are logical explanations for the conditions given in the

question and since both answers are opposite from each other (B distracter - manually actuate

equipment and D distracter - successful automatic actuation of equipment occurred - take no

manual actions), then there are two conflicting answers. As such, in accordance with

NUREG-1021, ES-403, D.1.c, Q14 is deleted from the exam.

Enclosure 3

WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION

RO Question 33:

Which one of the following correctly completes the statement below describing the minimum

required level and source of makeup water for T-73, Quench Tank?

The Quench Tank is maintained at a minimum water level of (1) by adding makeup water

using (2) .

a. (1) 70%

(2) P-90A or P-90B, Primary Makeup Tank Pumps

b. (1) 70%

(2) P-79A or P-79B, Primary System Makeup Transfer Pumps

c. (1) 40%

(2) P-90A or P-90B

d. (1) 40%

(2) P-79A or P-79B

ANSWER: A

Applicant's Contention:

Question #33 has two correct answers. Choices A and B are both correct because the

Quench Tank makeup supply can be lined up from P-79A/B Primary System Makeup Transfer

Pumps, per procedure RWSO-1, Transfer of Water from Primary Makeup Storage Tank (T-81)

for T-90 Loads.

Facility Position:

The facility agrees with the applicant that Q#33 has two correct answers. The Quench Tanks is

normally supplied makeup water from P-90A/B, Primary Makeup Tank Pumps, but is capable of

being supplied by P-79A/B, Primary System Makeup Transfer Pumps, per procedure RWSO-1,

Transfer of Water from Primary Makeup Storage Tank (T-81) for T-90 Loads. This procedure

has been performed recently (August 2011) while the P-90A/B pumps were out of service. Both

P-90A/B have been cautioned tagged OFF since June 2010 due to a leaking boric acid flow

path to the SIRW Tank (WO #228532). The pumps were left off until required to be used for

makeup. Also, P-90A was out of service from May 2012 until September 2012 due to a failed

seal. Based on the combination of the problems the plant has experienced with P-90A/B pumps

and the fact that P79A/B is capable of, and routinely is, used to supply P-90A/B loads, it is easy

to understand why 3 of 11 applicants selected B as the correct answer.

References:

RWSO-1, Transfer of Water from Primary Makeup Storage Tank (T-81) for T-90 Loads.

WO 228532, MV-CV2157 valve Leaks by, Replace valve (Weld)

P&ID M-220, Makeup Domestic Water & Chemical Injection Systems, Rev. 94.

P&ID M-652, Primary System Make-up Water Utility Water & Oil Waste System, Rev. 70.

Enclosure 3

WRITTEN EXAMINATION POST-EXAMINATION COMMENT RESOLUTION

NRC Resolution:

The Primary System Make-Up Water Pumps, P-90A/B, are normally aligned with one pump

continuously running to provide water to various primary plant components including the

pressurizer quench tank and to the chemical volume control system. However, the plant has

had problems with these pumps including pump seal leakage and leakage past a valve seat.

As previously mentioned, both P-90A/B pumps were out of service for a time requiring the

licensee to install a spool piece and use water from an alternate source, the Primary System

Makeup Transfer Pumps P-79A/B, to supply the loads that would normally be serviced by

P-90A/

B. A licensee procedure, RWSO-1, allowed the use of the P-79A/B pumps to supply

these loads. This condition existed in August 2011, a time when the applicants were collecting

in-plant experience. It would be reasonable to assume that some of the applicants believed that

the P-79A/B pumps were the normal method for supply water to the pressurizer quench tank.

But this would be incorrect, since the P-90A/B pumps were the normal method for supplying

water to the pressurizer quench tank. Pumps P-79A/B were an alternate flow path to fill the

quench tank, via a normally removed spoolpiece.

NUREG-1021, Appendix E, Policies and Guidelines for Taking NRC Examinations, stated in

Part B7, When answering a question, do not make assumptions regarding conditions that are

not specified in the question unless they occur as a consequence of other conditions that are

stated in the question. There were no other conditions stated in the question that would lead

the applicants to believe that the normal P-90A/B pumps were unavailable, nor was there any

statement about the status of a spool-piece that tied the alternate source to the normal source

of water to the quench tank. If the applicants had any concerns about the initial conditions of

the question, they should have asked a clarifying question during the exam. However, no

questions were asked by the applicants during the exam for Q33.

The alternate method was in use during a period when the applicants were on shift, however,

the applicants should still have known that the normal source of fill to the quench tank was

P-90A/B and they should have known that the use of the P79A/B pumps was an abnormal,

temporary condition. Therefore, distracter B was considered an incorrect answer.

Distracter A was considered the only correct answer for Q33.

Enclosure 3

A. Vitale -2-

In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's "Rules of

Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records System (PARS) component of

NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from

the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Hironori Peterson, Chief

Operations Branch

Division of Reactor Safety

Docket Nos. 50-255;72-007

License No. DPR-20

Enclosures:

1. Operator Licensing Examination Report 05000255/2012301

w/Attachment: Supplemental Information

2. Simulation Facility Report

3. Written Examination Post-Examination Comment Resolution

cc w/encl: Distribution via ListServ'

DISTRIBUTION w/encl:

Cayetano Santos Christine Lipa

RidsNrrPMPalisades Resource Carole Ariano

RidsNrrDorlLpl3-1 Resource Linda Linn

RidsNrrDirsIrib Resource DRPIII

Chuck Casto DRSIII

Cynthia Pederson Tammy Tomczak

Steven Orth John McHale, NRR

Jared Heck Janet Kweiser, DRS

Allan Barker

DOCUMENT NAME: PAL 2012 301.docx

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with

attach/encl "N" = No copy

OFFICE RIII RIII RIII RIII

NAME RKWalton:cs HPeterson

DATE 11/21/12 11/27/12

OFFICIAL RECORD COPY