IR 05000277/2018010: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 May 9, 2018 Mr. Bryan C. Hanson Senior Vice President, Exelon Generation, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 SUBJECT: PEACH BOTTOM ATOMIC POWER STATION UNITS 2 AND 3
{{#Wiki_filter:May 9, 2018
- TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000 277/20 18010 AND 05000 278/20 18010 Dear Mr. Hanson
 
: On April 20, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Peach Bottom Atomic Power Station (Peach Bottom), Units 2 and The NRC inspectors discussed the results of this inspection with Mr. Pat Navin, Site Vice President, and other members of your staf The results of this inspection are documented in the enclosed repor NRC inspectors documented two findings of very low safety significance (Green) in this repor One of these findings involved a violation of NRC requirement Further, inspectors documented a licensee-identified violation which was determined to be of very low safety significance in this repor The NRC is treating the se violations as non-cited violations (NCVs)
==SUBJECT:==
, consistent with Section 2.3.2.a of the Enforcement Polic If you contest the violation s or significance of t he s e NCV s, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
PEACH BOTTOM ATOMIC POWER STATION UNITS 2 AND 3 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000277/2018010 AND 05000278/2018010
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Peach Botto In addition, if you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN:
 
Document Control Desk, Washington, DC, 20555-0001; with copies to the Regional Administrator, Region I, and the NRC Resident Inspector at Peach Botto B. Hanson 2 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NR C's Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR ), Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."
==Dear Mr. Hanson:==
On April 20, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Peach Bottom Atomic Power Station (Peach Bottom), Units 2 and 3. The NRC inspectors discussed the results of this inspection with Mr. Pat Navin, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
 
NRC inspectors documented two findings of very low safety significance (Green) in this report.
 
One of these findings involved a violation of NRC requirements. Further, inspectors documented a licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is treating these violations as non-cited violations (NCVs),
consistent with Section 2.3.2.a of the Enforcement Policy.
 
If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Peach Bottom. In addition, if you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC, 20555-0001; with copies to the Regional Administrator, Region I, and the NRC Resident Inspector at Peach Bottom. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRCs Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR ), Part 2.390, Public Inspections, Exemptions, Requests for Withholding.


Sincerely,
Sincerely,
/RA/ Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Docket No and 50-278 License No DPR-44 and DPR-56  
/RA/
Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-277 and 50-278 License Nos. DPR-44 and DPR-56


===Enclosure:===
===Enclosure:===
Inspection Report 05000 277/20 18010 and 05000 278/2018010  
Inspection Report 05000277/2018010 and 05000278/2018010


==Inspection Report==
==Inspection Report==
Docket Numbers: 50-277 and 50-278 License Numbers: DPR-44 and DPR-56 Report Numbers: 05000 277/20 18010 and 05000 278/20 18010 Enterprise Identifier:
Docket Numbers: 50-277 and 50-278 License Numbers: DPR-44 and DPR-56 Report Numbers: 05000277/2018010 and 05000278/2018010 Enterprise Identifier: I-2018-010-0059 Licensee: Exelon Generation Company, LLC Facility: Peach Bottom Atomic Power Station, Units 2 and 3 Location: Delta, PA Inspection Dates: April 2 - 20, 2018 Inspectors: C. Bickett, Senior Reactor Inspector (Team Lead)
I-2018-010-0059 Licensee: Exelon Generation Company, LLC Facility: Peach Bottom Atomic Power Station, Units 2 and 3 Location: Delta, PA Inspection Dates: April 2 - 20, 2018 Inspectors:
E. DiPaolo, Senior Reactor Inspector P. Ott, Operations Engineer J. Patel, Reactor Inspector C. Cahill, Senior Reactor Analyst Approved By: G. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Enclosure
C. Bickett , Senior Reactor Inspector (Team Lead)
E. DiPaolo, Senior Reactor Inspector P. Ott, Operations Engineer J. Patel, Reactor Inspector C. Cahill, Senior Reactor Analyst Approved By:
G. Dentel , Chief Engineering Branch 2 Division of Reactor Safety 2


=SUMMARY=
=SUMMARY=
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Exelons performance at
 
Peach Bottom Atomic Power Station, Units 2 and 3 by conducting the triennial fire protection team inspection in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.


Exelon's performance at Peach Bottom Atomic Power Station, Units 2 and 3 by conducting the triennial fire protection team inspection in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRC's program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC and self-revealed findings, violations, and additional items are summarized in the table s below. A license e-identified non-cited violation (NCV) is documented in report section 71111.05T. List of Findings and Violations Failure to Identify Time-Critical Action Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green FIN 05000277, 05000278/2018010
NRC and self-revealed findings, violations, and additional items are summarized in the tables below. A licensee-identified non-cited violation (NCV) is documented in report section 71111.05T.
-01 Closed P.2 - Problem Identification and Resolution, Evaluation 71111.05T The inspectors identified a green finding because Exelon did not identify, validate, and incorporate a time-critical action referenced in calculation PF
-0016-025, "Fire Area 025
- Fire Safe Shutdown Analysis," in accordance with Sections 4.2 and 4.3 of OP
-AA-102-106, "Operator Response Time Program."  Specifically, Exelon did not identify a 10
-minute time-critical action to take the "transfer/isolation" switch for the high pressure coolant injection (HPCI) inboard steam isolation valve (MO
-2(3)-23-015), to the "EMERG" position.


Failure to Develop and Maintain Mitigating Strategy Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green NCV 05000277, 05000278/2018010
List of Findings and Violations Failure to Identify Time-Critical Action Cornerstone           Significance                                 Cross-cutting       Report Aspect             Section Mitigating             Green                                        P.2 - Problem      71111.05T Systems               FIN 05000277, 05000278/2018010-01            Identification and Closed                                       Resolution,
-02 Closed None 71111.05T The inspectors identified a Green non-cited violation of 10 CFR 50.54(hh)(2), "Conditions of Licenses," and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11), "Mitigation Strategy License Condition," because Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Specifically, Exelon did not adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves in the event of a challenge to the reactor due to a postulated large fire and/or explosion.
Evaluation The inspectors identified a green finding because Exelon did not identify, validate, and incorporate a time-critical action referenced in calculation PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106,
Operator Response Time Program. Specifically, Exelon did not identify a 10-minute time-critical action to take the transfer/isolation switch for the high pressure coolant injection (HPCI) inboard steam isolation valve (MO-2(3)-23-015), to the EMERG position.


3
Failure to Develop and Maintain Mitigating Strategy Cornerstone            Significance                                  Cross-cutting      Report Aspect              Section Mitigating            Green                                        None                71111.05T Systems                NCV 05000277, 05000278/2018010-02 Closed The inspectors identified a Green non-cited violation of 10 CFR 50.54(hh)(2), Conditions of Licenses, and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11), Mitigation Strategy License Condition, because Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Specifically, Exelon did not adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves in the event of a challenge to the reactor due to a postulated large fire and/or explosion.


=INSPECTION SCOPE=
=INSPECTION SCOPE=


This inspection was conducted using the appropriate portions of the inspection procedure (IP) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading
===This inspection was conducted using the appropriate portions of the inspection procedure (IP) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
-rm/doc-collections/insp
-manual/inspection
-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, "Light
-Water Reactor Inspection Program
- Operations Phase."


The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Exelon performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Exelon performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.


==REACTOR SAFETY==
==REACTOR SAFETY==
71111.05T  
 
- Fire Protection (Triennial)
===71111.05T - Fire Protection (Triennial)
The inspectors evaluated the following from April 2 - 20, 2018: Fire Protection Inspection Requirements (4 Samples
The inspectors evaluated the following from April 2 - 20, 2018:
The inspectors evaluated fire protection program implementation in the following selected areas and/or fire zones
Fire Protection Inspection Requirements ===
:
{{IP sample|IP=IP 71111.05|count=4}}
The inspectors evaluated fire protection program implementation in the following selected areas and/or fire zones:
: (1) Fire Area 25: Cable Spreading Room (Zone 78H) and Fan Room (Zone 108A)
: (1) Fire Area 25: Cable Spreading Room (Zone 78H) and Fan Room (Zone 108A)
: (2) Fire Area 36: Unit 2 E42 Emergency Switchgear Room (Zone 123)
: (2) Fire Area 36: Unit 2 E42 Emergency Switchgear Room (Zone 123)
Line 78: Line 77:
: (1) MO-4487, Reactor Core Isolation Cooling System Turbine Trip and Throttle Valve
: (1) MO-4487, Reactor Core Isolation Cooling System Turbine Trip and Throttle Valve
: (2) 2-152-1704, E3 Emergency Diesel Generator Breaker to E32 Emergency Switchgear (20A17)
: (2) 2-152-1704, E3 Emergency Diesel Generator Breaker to E32 Emergency Switchgear (20A17)
: (3) LT-8456 and LI
: (3) LT-8456 and LI-8456, Suppression Pool Level Transmitter and Indicator
-8456, Suppression Pool Level Transmitter and Indicator
: (4) MO3-23-017, High Pressure Coolant Injection (HPCI) System Pump Suction from Condensate Storage Tank
: (4) MO3-23-017, High Pressure Coolant Injection (HPCI) System Pump Suction from Condensate Storage Tank
: (5) MO3-10-013A, Residual Heat Removal System Suction Isolation Valve From Suppression Pool
: (5) MO3-10-013A, Residual Heat Removal System Suction Isolation Valve From Suppression Pool
: (6) MO3-10-89B, Residual Heat Removal System Heat Exchanger High Pressure Service Water Discharge Valve B.5.b Inspection Activities (1 Sample) The inspectors evaluated feasibility of the following B.5.b Mitigating Strateg y: Extensive Damage Mitigation Guideline (EDMG) 2.0, Attachment 15 , "Alternate 125 VDC Power Supply for Safety Relief Valve Operation," Revision 8
: (6) MO3-10-89B, Residual Heat Removal System Heat Exchanger High Pressure Service Water Discharge Valve B.5.b Inspection Activities (1 Sample)===
The inspectors evaluated feasibility of the following B.5.b Mitigating Strategy:
Extensive Damage Mitigation Guideline (EDMG) 2.0, Attachment 15, Alternate 125 VDC Power Supply for Safety Relief Valve Operation, Revision 8


==INSPECTION RESULTS==
==INSPECTION RESULTS==
Failure to Identify Time
Failure to Identify Time-Critical Action Cornerstone           Significance                                 Cross-cutting     Report Aspect             Section Mitigating             Green                                        P.2 - Problem      71111.05T Systems               FIN 05000277, 05000278/2018010-01 Identification Closed                                       and Resolution, Evaluation The inspectors identified a green finding because Exelon did not identify, validate, and incorporate a time-critical action referenced in calculation PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106, Operator Response Time Program. Specifically, Exelon did not identify a 10-minute time-critical action to take the transfer/isolation switch for the high pressure coolant injection (HPCI) inboard steam isolation valve (MO-2(3)-23-015), to the EMERG position.
-Critical Action Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green  FIN 05000277, 05000278/2018010
 
-01 Closed P.2 - Problem Identification and Resolution, Evaluation 71111.05T The inspectors identified a green finding because Exelon did not identify, validate, and incorporate a time
=====Description:=====
-critical action referenced in calculation PF
Operators use procedure SE-10, Alternative Shutdown, to control the plant from the alternate shutdown panels in the event of a fire that results in evacuation of the main control room. SE-10, Attachment 6, Part A, directs the transfer/isolation of safety relief valve control and the setup and control of necessary 4KV and emergency diesel generator equipment at the alternate shutdown panels. This is in direct support of AC power restoration for MO-2(3)-23-015, and subsequent opening of the valve, as HPCI is the credited water makeup source for this scenario. These actions are required if the valve has shut due to a fire-induced spurious operation, and offsite power is not available.
-0016-025, "Fire Area 025  
- Fire Safe Shutdown Analysis,"
in accordance with Sections 4.2 and 4.3 of OP
-AA-102-106, "Operator Response Time Program.Specifically, Exelon did not identify a 10
-minute time-critical action to take the "transfer/isolation" switch for the high pressure coolant injection (HPCI) inboard steam isolation valve (MO-2(3)-23-015), to the "EMERG" position.


Description
Issue report (IR) 2661579, dated 2016, documented that the station could not complete SE-10, Attachment 6, Part A, in 28 minutes, as required by fire safe shutdown calculation PF-0016-025. IR 2661579 identified that worst case, the actions took 93 minutes. Removing certain contingencies in the procedure, Exelon was able to complete the actions in 54 minutes. The inspectors noted that Exelon did not implement any compensatory measures to address this issue, and planned to revise the procedure to resequence actions such that they could be completed in the required time. On April 6, 2018, the inspectors questioned Exelon since they did not demonstrate that the required manual operator action time of 28 minutes could be met, and the procedure revision had yet to be issued. In response, Exelon performed a walkdown of the existing procedure and determined that the actions up to including energization of the E-22 and E-23 buses via the E-2 emergency diesel generator could be completed in 26 minutes and 28 seconds. Exelon then completed a temporary procedure change to ensure the actions to restore power with the E-2 emergency diesel generator were moved to earlier in the procedure attachment for expediency, and a second operator was added as a requirement to implement the actions. The inspectors noted that one of the reasons that the station could not meet the 28-minute time was likely due a procedure revision that added corrective actions to swap fuses in response to a previous unrelated issue.
: Operators use procedure SE-10, "Alternative Shutdown,"
to control the plant from the alternate shutdown panels in the event of a fire that results in evacuation of the main control room.


SE-10, Attachment 6, Part A, directs the transfer/isolation of safety relief valve control and the setup and control of necessary 4KV and emergency diesel generator equipment at the alternate shutdown panels. This is in direct support of AC power restoration for MO-2(3)-23-015, and subsequent opening of the valve, as HPCI is the credited water makeup source for this scenario. These actions are required if the valve has shut due to a fire-induced spurious operation, and offsite power is not available.
During this inspection, Exelon issued a revision to calculation PF-0016-025, which updated the manual operator action list and the corresponding required action times per the most recent thermal hydraulic analysis, which included the measurement uncertainty recapture uprate implemented in January 2018. The revised time to complete the actions required to provide power to MO-2(3)-23-015 was lowered from 28 to 24 minutes. The inspectors questioned whether the station would have been able to meet this revised time prior to the temporary procedure change. Exelon stated in the revised calculation, operator action is provided to re-open HPCI Inboard Isolation Valve MO-2(3)-23-015 should it spuriously close prior to transfer of control from the main control room.


Issue report (IR) 2661579, dated 2016, documented that the station could not complete SE
This prompt action is treated as a defense-in-depth action, as a specific sequence of failures must occur (spurious valve closure prior to transfer and subsequent loss of the primary source of power before transfer of control), and is not required for Appendix R compliance.
-10, Attachment 6, Part A, in 28 minutes, as required by fire safe shutdown calculation PF
-0016-025. IR 2661579 identified that worst case, the actions took 93 minutes. Removing certain contingencies in the procedure, Exelon was able to complete the actions in 54 minutes. The inspectors noted that Exelon did not implement any compensatory measures to address this issue, and planned to revise the procedure to resequence actions such that they could be completed in the required time. On April 6, 2018, the inspectors questioned Exelon since they did not demonstrate that the required manual operator action time of 28 minutes could be met, and the procedure revision had yet to be issued. In response, Exelon performed a walkdown of the existing procedure and determined that the actions up to including energization of the E
-22 and E-23 buses via the E
-2 emergency diesel generator could be completed in 26 minutes and 28 seconds. Exelon then completed a temporary procedure change to ensure the actions to restore power with the E
-2 emergency diesel generator were moved to earlier in the procedure attachment for expediency, and a second operator was added as a requirement to implement the actions. The inspectors noted that one of the reasons that the station could not meet the 28
-minute time was likely due a procedure revision that added corrective actions to swap fuses in response to a previous unrelated issue.


During th is inspection, Exelon issued a revision to calculation PF-0016-025, which updated the manual operator action list and the corresponding required action times per the most recent thermal hydraulic analysis , which included the measurement uncertainty recapture uprate implemented in January 2018. The revised time to complete the actions required to provide power to MO-2(3)-23-015 was lowered from 28 to 24 minutes. The inspectors questioned whether the station would have been able to meet this revised time prior to the temporary procedure change. Exelon stated in the revised calculation , "operator action is provided to re-open HPCI Inboard Isolation Valve MO
Exelon referenced a docketed August 16, 1984 letter to the NRC as justification for this conclusion.
-2(3)-23-015 should it spuriously close prior to transfer of control from the main control room.


This prompt action is treated as a defense
The inspectors reviewed this licensing basis letter and noted that the justification was based on the assumption that within 10 minutes, operators would man the HPCI alternate control station and isolate the control circuit for this valve. This would leave a maximum of 10 minutes for the specific sequence of events to occur that would result in spurious closure of MO-2(3)-23-105, thus making this scenario unlikely. The inspectors noted Exelon did not thoroughly evaluate this letter to ensure that any conditions and/or assumptions were translated into the fire safe shutdown calculations and other station processes. As such, Exelon did not identify the 10-minute action as a prompt action. The inspectors determined that operators will likely be able to meet this 10-minute action with the current procedure.
-in-depth action
, as a specific sequence of failures must occur (spurious valve closure prior to transfer and subsequent loss of the primary source of power before transfer of control), and is not required for Appendix R compliance."


Exelon reference d a docketed August 16, 1984 letter to the NRC as justification for this conclusion.
However, there are no administrative controls in place to ensure that future changes to the procedure will not challenge this time. Additionally, because the 10-minute action requirement is not documented in the operator time response program, the Operations Training department does not know to incorporate the requirement into training, and the operators do not recognize the need to expeditiously complete the procedure steps.


The inspectors reviewed this licensing basis letter and noted that the justification was based on the assumption that within 10 minutes, operators would man the HPCI alternate control station and isolate the control circuit for this valve.
The inspectors also noted other weaknesses in the stations evaluation and resolution of this issue. The inspectors concluded that Exelon incorrectly stated in IR 2661579 that these actions are only necessary in the event of multiple spurious operations and as such, are not required to be satisfied to maintain plant operations within design or licensing bases. This is incorrect because this is a single spurious operation scenario, which is required to be mitigated per 10 CFR 50 Appendix R requirements. Also of note, even though this issue was documented in their 2017 self-assessment for this inspection, Exelon still had not issued the revised procedure, nor implemented any compensatory actions prior to this inspection.


This would leave a maximum of 10 minutes for the specific sequence of events to occur that would result in spurious closure of MO-2(3)-23-105, thus making this scenario unlikely. The inspectors noted Exelon did not thoroughly evaluate this letter to ensure that any conditions and/or assumptions were translated into the fire safe shutdown calculations and other station processes. As such, Exelon did not identify th e 10-minute action as a prompt action. The inspectors determined that operators will likely be able to meet this 10
Corrective Actions: The stations planned corrective actions include updating Peach Bottoms time-critical operator action program to include the 10-minute action to take the transfer/isolation switch for MO-2(3)-23-015 to the EMERG position.
-minute action with the current procedure. However, there are no administrative controls in place to ensure that future changes to the procedure will not challenge this time.


Additionally, because the 10-minute action requirement is not documented in the operator time response program, the Operations Training department does not know to incorporate the requirement into training, and the operators do not recognize the need to expeditiously complete the procedure step s. The inspectors also noted other weaknesses in the station's evaluation and resolution of this issue. The inspectors concluded that Exelon incorrectly stated in IR 2661579 that "these actions are only necessary in the event of multiple spurious operations and as such, are not required to be satisfied to maintain plant operations within design or licensing bases."  This is incorrect because this is a single spurious operation scenario, which is required to be mitigated per 10 CFR 50 Appendix R requirements. Also of note, even though this issue was documented in their 2017 self
Corrective Action Reference: IR 4127608
-assessment for this inspection, Exelon still had not issued the revised procedure, nor implemented any compensatory actions prior to this inspection.


Corrective Actions: The station's planned corrective actions include updating Peach Bottom's time-critical operator action program to include the 10
=====Performance Assessment:=====
-minute action to take the "transfer/isolation" switch for MO
Performance Deficiency: The failure to identify, validate, and incorporate a time-critical action referenced in calculation PF-0016-025, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106, Operator Response Time Program is a performance deficiency.
-2(3)-23-015 to the "EMERG" position.


Corrective Action Reference:
Screening: The performance deficiency was more than minor because if left uncorrected, the performance deficiency would have the potential to lead to a more significant safety concern.
IR 4127608 Performance Assessment
:  Performance Deficiency: The failure to identify, validate, and incorporate a time
-critical action referenced in calculation PF
-0016-025, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106, "Operator Response Time Program" is a performance deficiency.


Screening:  The performance deficiency was more than minor because if left uncorrected, the performance deficiency would have the potential to lead to a more significant safety concern. The 10-minute requirement is not documented in the operator time response program
The 10-minute requirement is not documented in the operator time response program; therefore, training has not been conducted, operators did not recognize the time-critical action, and future changes to the SE-10 procedure could result in challenging the 10-minute requirement.
; therefore, training has not been conducted, operators did not recognize the time
-critical action, and future changes to the SE
-10 procedure could result in challenging the 10
-minute requirement.


Significance: The inspectors assessed the significance of the finding using IMC 0609, Appendix F, "Fire Protection SDP.This issue screened to very low safety significance (Green) in Phase 1, Step 1.3 as the procedure as currently written does not impact the ability to achieve safe shutdown.
Significance: The inspectors assessed the significance of the finding using IMC 0609, Appendix F, Fire Protection SDP. This issue screened to very low safety significance (Green) in Phase 1, Step 1.3 as the procedure as currently written does not impact the ability to achieve safe shutdown.


Cross-cutting Aspect
Cross-cutting Aspect: This finding had a cross-cutting aspect in the area of Problem Identification and Resolution, Evaluation, because although Exelon included a reference to the 1984 letter in the latest revision to the fire safe shutdown calculation, they did not thoroughly evaluate the letter to ensure that any conditions and/or assumptions were translated into the fire safe shutdown calculations and other station processes [P.2].
: This finding had a cross
-cutting aspect in the area of Problem Identification and Resolution, Evaluation, because although Exelon included a reference to the 1984 letter in the latest revision to the fire safe shutdown calculation, they did not thoroughly evaluate the letter to ensure that any conditions and/or assumptions were translated into the fire safe shutdown calculations and other station processes [P.2].


=====Enforcement:=====
=====Enforcement:=====
Inspectors did not identify a violation of regulatory requirements associated with this finding.
Inspectors did not identify a violation of regulatory requirements associated with this finding.


Failure to Develop and Maintain Mitigating Strategy Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green  NCV 05000277, 05000278/2018010
Failure to Develop and Maintain Mitigating Strategy Cornerstone           Significance                                 Cross-cutting     Report Aspect           Section Mitigating           Green                                        None              71111.05T Systems               NCV 05000277, 05000278/2018010-02 Closed The inspectors identified a Green non-cited violation of 10 CFR 50.54(hh)(2), Conditions of Licenses, and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11), Mitigation Strategy License Condition, because Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Specifically, Exelon did not adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves in the event of a challenge to the reactor due to a postulated large fire and/or explosion.
-02 Closed None 71111.05T The inspectors identified a Green non
-cited violation of 10 CFR 50.54(hh)(2), "Conditions of Licenses," and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C
.(11), "Mitigation Strategy License Condition," because Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Specifically, Exelon did not adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves in the event of a challenge to the reactor due to a postulated large fire and/or explosion.


Description
=====Description:=====
: Exelon procedure EDMG 2.0, "Peach Bottom Operational Contingency Guidelines," provides the methods for implementation of strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Exelon procedure EDMG 2.0, Attachment 15, "Alternate 125 VDC Power Supply for Safety Relief Valve Operation," describes the station's strategy for supplying alternate power to the five automatic depressurization system safety relief valves. Figure 1 of this attachment describes which terminal points are to be used to accomplish this task.
Exelon procedure EDMG 2.0, Peach Bottom Operational Contingency Guidelines, provides the methods for implementation of strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Exelon procedure EDMG 2.0, Attachment 15, Alternate 125 VDC Power Supply for Safety Relief Valve Operation, describes the stations strategy for supplying alternate power to the five automatic depressurization system safety relief valves. Figure 1 of this attachment describes which terminal points are to be used to accomplish this task.


Since April 2008, Figure 1 has listed the incorrect terminal points for the  
Since April 2008, Figure 1 has listed the incorrect terminal points for the G and K safety relief valves on both Unit 2 and Unit 3. Therefore, when an individual reached the step in the procedure to connect the jumpers for the G and K safety relief valves, they would be directed to terminal locations that did not exist. As a result, step 19 of the procedure, Verify all five safety relief valve jumpers are connected at both ends, THEN continue, would not be able to be completed, and operators would likely not continue on with subsequent steps in the procedure. Because of this issue, inspectors determined that the procedure was not adequate to ensure that the strategy could be completed.
'G' and 'K' safety relief valves on both Unit 2 and Unit 3. Therefore, when an individual reached the step in the procedure to connect the jumpers for the  
'G' and 'K' safety relief valves, they would be directed to terminal locations that did not exist. As a result, step 19 of the procedure, "Verify all five safety relief valve jumpers are connected at both ends, THEN continue," would not be able to be completed, and operators would likely not continue on with subsequent steps in the procedure. Because of this issue, inspectors determined that the procedure was not adequate to ensure that the strategy could be completed.


Corrective Actions: Exelon documented this issue in the corrective action program and implemented a revision to the procedure to correct the error.
Corrective Actions: Exelon documented this issue in the corrective action program and implemented a revision to the procedure to correct the error.


Corrective Action Reference: IR 4125405 Performance Assessment
Corrective Action Reference: IR 4125405
: Performance Deficiency: Exelon's failure to adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves, as required by 10 CFR 50.54(hh)(2) and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11), was a performance deficiency.
 
=====Performance Assessment:=====
Performance Deficiency: Exelons failure to adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves, as required by 10 CFR 50.54(hh)(2) and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11), was a performance deficiency.
 
Screening: This performance deficiency was more than minor because it is associated with the procedure quality attribute of the mitigating systems cornerstone and adversely affected the cornerstone objective to assure the availability, reliability, and capability of the automatic depressurization system safety relief valves to respond to an event. Specifically, failure to provide an adequate procedure to provide alternate power to the safety relief valves would impact the stations ability to open those valves to manually depressurize the reactor during an event.


Screening: This performance deficiency was more than minor because it is associated with the procedure quality attribute of the mitigating systems cornerstone and adversely affected the cornerstone objective to assure the availability, reliability, and capability of the automatic depressurization system safety relief valves to respond to an event. Specifically, failure to provide an adequate procedure to provide alternate power to the safety relief valves would impact the station's ability to open those valves to manually depressurize the reactor during an event. Significance:
Significance: The inspectors assessed the significance of this issue using IMC 0609, Appendix L, B.5.b. Significance Determination Process, Table 2. The inspectors determined that the finding did not meet the criteria listed in Table 2 for greater than green significance, and therefore screened this finding as Green.
The inspectors assessed the significance of this issue using IMC 0609, Appendix L, "B.5.b. Significance Determination Process," Table 2. The inspectors determined that the finding did not meet the criteria listed in Table 2 for greater than green significance, and therefore screened this finding as Green.


Cross-cutting Aspect:
Cross-cutting Aspect: No cross-cutting aspect was assigned to this finding because the inspectors determined that the finding did not reflect current plant performance.
No cross-cutting aspect was assigned to this finding because the inspectors determined that the finding did not reflect current plant performance.


Enforcement
=====Enforcement:=====
: Violation: 10 CFR 50.54(hh)(2) requires, in part, that each licensee shall develop and implement guidance and strategies intended to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities under the circumstances associated with loss of large areas of the plant due to explosions or fire. Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C
Violation: 10 CFR 50.54(hh)(2) requires, in part, that each licensee shall develop and implement guidance and strategies intended to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities under the circumstances associated with loss of large areas of the plant due to explosions or fire. Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11) requires that Exelon develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Exelon procedure EDMG 2.0, Peach Bottom Operational Contingency Guidelines, provides the methods for implementation of these strategies. EDMG 2.0, Attachment 15, Alternate 125VDC Power Supply for Safety Relief Valve Operation, is the procedure for providing alternate power to the automatic depressurization system safety relief valves.
.(11) requires that Exelon develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Exelon procedure EDMG 2.0, "Peach Bottom Operational Contingency Guidelines," provides the methods for implementation of these strategies. EDMG 2.0, Attachment 15, "Alternate 125VDC Power Supply for Safety Relief Valve Operation," is the procedure for providing alternate power to the automatic depressurization system safety relief valves.


Contrary to the above, since April 2008, Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Specifically, EDMG 2.0, Attachment 15, was inadequate to ensure that the station would be able to open the automatic depressurization system relief valves from the containment penetrations via an alternate power supply to allow manual depressurization in the event of a challenge to the reactor due to a postulated large fire and/or explosion.
Contrary to the above, since April 2008, Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage.


Disposition: This violation is being treated as a non
Specifically, EDMG 2.0, Attachment 15, was inadequate to ensure that the station would be able to open the automatic depressurization system relief valves from the containment penetrations via an alternate power supply to allow manual depressurization in the event of a challenge to the reactor due to a postulated large fire and/or explosion.
-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.


Licensee Identified Non
Disposition: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
-Cited Violation 71111.05T This violation of very low safety significan ce was identified by Exelon and has been entered into Exelon's corrective action program and is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.


Violation: Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(4) requires, in part, Exelon to implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Repor t.  "Fire Protection Program, Peach Bottom Atomic Power Station, Units 2 and 3," is incorporated by reference into the Updated Final Safety Analysis Report, as discussed in Section 10.12 , "Fire Protection Program
Licensee Identified Non-Cited Violation                                                 71111.05T This violation of very low safety significance was identified by Exelon and has been entered into Exelons corrective action program and is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.
."  Fire Protection Program Chapter 5.1, "Methodology," assumes that two or more circuit failures resulting in spurious operation of two or more valves in series at a high/low pressure interface may occur due to a postulated fire in any given area.


Fire Protection Program Chapter 6.2, "Analysis of High/Low Pressure Interfaces," requires Exelon to address the situations for which the isolation valves at a given interface point consists of two electrically controlled valves in series and where the potential may exist for a single fire to cause damage to cables associated with both valves.
Violation: Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(4) requires, in part, Exelon to implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report.


Contrary to above, as of March 14, 2018, Exelon identified they failed to evaluate two motor
Fire Protection Program, Peach Bottom Atomic Power Station, Units 2 and 3, is incorporated by reference into the Updated Final Safety Analysis Report, as discussed in Section 10.12, Fire Protection Program. Fire Protection Program Chapter 5.1, Methodology, assumes that two or more circuit failures resulting in spurious operation of two or more valves in series at a high/low pressure interface may occur due to a postulated fire in any given area.
-operated valves in series, MO 06-2663 and MO 06-038B for Unit 2, and MO 06-3663 and MO-3-06-038B for Unit 3, where the potential may exist for a single fire to cause damage to cables associated with both valves. Specifically, a postulated fire scenario could cause spurious opening of the valves, which may potentially result in a fire
-induced loss of coolant accident through the high/low pressure system interface. Exelon's evaluation identified the affected valves' cables are routed through Fire Area 6N for the Unit 2 valves, and Fire Area 13N for the Unit 3 valves, and thus, a possibility exists for a single fire to cause damage to cables associated with both valves.


This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.
Fire Protection Program Chapter 6.2, Analysis of High/Low Pressure Interfaces, requires Exelon to address the situations for which the isolation valves at a given interface point consists of two electrically controlled valves in series and where the potential may exist for a single fire to cause damage to cables associated with both valves.


Significance/Severity: The inspectors performed a Phase 2 Significance Determination Process screening for this issue, in accordance with IMC 0609, Appendix F, "Fire Protection Significance Determination Process."  This finding affected the post
Contrary to above, as of March 14, 2018, Exelon identified they failed to evaluate two motor-operated valves in series, MO-2-06-2663 and MO-2-06-038B for Unit 2, and MO-3-06-3663 and MO-3-06-038B for Unit 3, where the potential may exist for a single fire to cause damage to cables associated with both valves. Specifically, a postulated fire scenario could cause spurious opening of the valves, which may potentially result in a fire-induced loss of coolant accident through the high/low pressure system interface. Exelons evaluation identified the affected valves cables are routed through Fire Area 6N for the Unit 2 valves, and Fire Area 13N for the Unit 3 valves, and thus, a possibility exists for a single fire to cause damage to cables associated with both valves. This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.
-fire safe shutdown category because of spurious operations of safe shutdown components. Based on a walkdown of Fire Areas 6N and 13N, the inspectors did not identify any credible fire ignition source scenarios that could affect both Unit 2 motor
-operated valves or both Unit 3 motor operated valves.


Therefore, based upon task number 2.3.5, the inspectors determined that this finding screened to very low safety significance (Green).
Significance/Severity: The inspectors performed a Phase 2 Significance Determination Process screening for this issue, in accordance with IMC 0609, Appendix F, Fire Protection Significance Determination Process. This finding affected the post-fire safe shutdown category because of spurious operations of safe shutdown components. Based on a walkdown of Fire Areas 6N and 13N, the inspectors did not identify any credible fire ignition source scenarios that could affect both Unit 2 motor-operated valves or both Unit 3 motor operated valves. Therefore, based upon task number 2.3.5, the inspectors determined that this finding screened to very low safety significance (Green).


Corrective Action References
Corrective Action References: IR 04115309, EC 623585, EC 623586
: IR 04115309, EC 623585, EC 623586


==EXIT MEETING S AND DEBRIEFS==
==EXIT MEETINGS AND DEBRIEFS==
The inspectors verified no proprietary information was retained or documented in this report.
The inspectors verified no proprietary information was retained or documented in this report.


Line 213: Line 172:
=DOCUMENTS REVIEWED=
=DOCUMENTS REVIEWED=


71111.05T Fire Protection Licensing and Design Basis Documents
71111.05T
Fire Protection Licensing and Design Basis Documents
Letter from PECO (
Letter from PECO (
: [[contact::V.S. Boyer) to USNRC (Darrell Eisenhut)]], Peach Bottom Atomic Power Station Alternate Shutdown, dated 8/16/84 NE-00296, Post
: [[contact::V.S. Boyer) to USNRC (Darrell Eisenhut)]], Peach Bottom Atomic
-Fire Safe Shutdown Program Requirements at PBAPS, Revision 4
Power Station Alternate Shutdown, dated 8/16/84
NE-00296, Post-Fire Safe Shutdown Program Requirements at PBAPS, Revision 4
NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 10/3/91
NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 10/3/91
NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 3/13/85
NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 3/13/85
NRC Safety Evaluation Report, Fire Protection Program, dated 5/23/79
NRC Safety Evaluation Report, Fire Protection Program, dated 5/23/79
NRC Safety Evaluation Report, Fire Protection Program, Supplement 1, dated 8/14/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 1, dated 8/14/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 2, dated 9/15/80 NRC Safety Evaluation Report, Fire Protection Program, Supplement 3, dated 10/10/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 2, dated 9/15/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 3, dated 10/10/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 4, dated 11/24/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 4, dated 11/24/80
Peach Bottom Atomic Power Station Fire Protection Program, Revision 17
Peach Bottom Atomic Power Station Fire Protection Program, Revision 17
Peach Bottom Atomic Power Station, Units 2 and 3  
Peach Bottom Atomic Power Station, Units 2 and 3 - Issuance of Amendment
- Issuance of Amendment
RE: Fire Protection Program Changes, dated 6/24/05
RE: Fire Protection Program Changes, dated 6/24/05
P-T-10, Fire Safe Shutdown, Revision 13
P-T-10, Fire Safe Shutdown, Revision 13
Safety Evaluation by the Office of Nuclear Reactor Regulation Related to Order No. EA
Safety Evaluation by the Office of Nuclear Reactor Regulation Related to Order No. EA-02-026,
-02-026, Exelon Generation Company, LLC, Peach Bottom Atomic Power Station, Units 2 and 3, dated 8/9/07 Calculations, Analysis, and Engineering Evaluations
Exelon Generation Company, LLC, Peach Bottom Atomic Power Station, Units 2 and 3,
CFR 50.59 Safety Review for Modification P00680, Fire Detection and Suppression System for Switchgear and Battery Rooms, Revision 1
dated 8/9/07
EC 623620, Alternate Compensatory Measure for IR 4115309 Hi/Lo Interface Not Evaluated for Appendix R, dated 3/22/18
Calculations, Analysis, and Engineering Evaluations
Fire Endurance Test on Silicone Foam Penetration Seal in a Masonry Floor, Design FC
CFR 50.59 Safety Review for Modification P00680, Fire Detection and Suppression System
-270, dated 12/14/78
for Switchgear and Battery Rooms, Revision 1
EC 623620, Alternate Compensatory Measure for IR 4115309 Hi/Lo Interface Not Evaluated for
Appendix R, dated 3/22/18
Fire Endurance Test on Silicone Foam Penetration Seal in a Masonry Floor, Design FC-270,
dated 12/14/78
PEAF-EPU-001, T0611 Appendix R Fire Protection, Revision 5
PEAF-EPU-001, T0611 Appendix R Fire Protection, Revision 5
PEAM-MUR-0611, Appendix R Fire Protection T0611, Revision 0
PEAM-MUR-0611, Appendix R Fire Protection T0611, Revision 0
PF-0007, Combustible Loading Analysis, Revision 0
PF-0007, Combustible Loading Analysis, Revision 0
PF-0007, Combustible Loading Analysis, Revision 4
PF-0007, Combustible Loading Analysis, Revision 4
PF-0016-002, Fire Area 002  
PF-0016-002, Fire Area 002 - Fire Safe Shutdown Analysis, Revision 1
- Fire Safe Shutdown Analysis, Revision 1
PF-0016-013N, Fire Area 013N - Fire Safe Shutdown Analysis, Revision 1
PF-0016-013N, Fire Area 013N  
PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 000V
- Fire Safe Shutdown Analysis, Revision 1
PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 1
PF-0016-025, Fire Area 025  
PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 2
- Fire Safe Shutdown Analysis, Revision 000V
PF-0016-036, Fire Area 036 - Fire Safe Shutdown Analysis, Revision 1
PF-0016-025, Fire Area 025  
PF-0019, Fire Protection Hydraulic Calculation - Units 2 and 3 Sprinkler System for the 4
- Fire Safe Shutdown Analysis, Revision 1
PF-0016-025, Fire Area
25 - Fire Safe Shutdown Analysis, Revision 2
PF-0016-036, Fire Area 036  
- Fire Safe Shutdown Analysis, Revision 1
PF-0019, Fire Protection Hydraulic Calculation
- Units 2 and 3 Sprinkler System for the
Kilo-Volt Switchgear Rooms, Battery Rooms, and Access Corridor, Revision 0
Kilo-Volt Switchgear Rooms, Battery Rooms, and Access Corridor, Revision 0
PF-0020, Fire Protection Hydraulic Calculation
PF-0020, Fire Protection Hydraulic Calculation - Units 2 and 3 Main Fan Room (#381)
- Units 2 and 3 Main Fan Room (#381) Hydraulic Calculation, Revision 0
Hydraulic Calculation, Revision 0
T-061-VC-1, Assessment of the Fire Protection Sprinkler and Hose Station Supply Piping, Revision 0
T-061-VC-1, Assessment of the Fire Protection Sprinkler and Hose Station Supply Piping,
 
Revision 0
Drawings and Wiring Diagrams
Drawings and Wiring Diagrams
280-E-2890, Emergency DC Lighting Layout Alternate Control Stations, Revision 1
280-E-2890, Emergency DC Lighting Layout Alternate Control Stations, Revision 1
280-M-318, Piping and Instrumentation Drawing, Fire Protection System, Revision 70
280-M-318, Piping and Instrumentation Drawing, Fire Protection System, Revision 70
280-M-359, Sheet 1, Piping and Instrumentation Drawing
280-M-359, Sheet 1, Piping and Instrumentation Drawing Reactor Core Isolation Cooling
Reactor Core Isolation Cooling System, Revision 50
System, Revision 50
280-M-359, Sheet 2, Piping and Instrumentation Drawing
280-M-359, Sheet 2, Piping and Instrumentation Drawing Reactor Core Isolation Cooling
Reactor Core Isolation Cooling System, Revision 48
System, Revision 48
280-NE-75-1, Penetration Seal Details NE
280-NE-75-1, Penetration Seal Details NE-378545, Revision 1
-378545, Revision 1
280-NE-75-1, Sheet 19, Pipe or Conduit through 3-Hour Rated Fire Barrier, Revision 1
280-NE-75-1, Sheet 19, Pipe or Conduit through 3
737-D-VC-72, Thermo-Lag Upgrade Fire Barrier 78H-02, Revision 0
-Hour Rated Fire Barrier, Revision 1
A-484, Barrier Plans, Elevation 91 6, Revision 8
737-D-VC-72, Thermo
A-485, Barrier Plans, Elevation 116 0 Sheets 1 and 2, Revisions 8 and 4
-Lag Upgrade Fire Barrier 78H
A-486, Barrier Plans, Elevation 135 0 Sheets 1 and 2, Revisions 11 and 1
-02, Revision 0
A-487, Barrier Plans, Elevation 165 0 Sheets 1 and 2, Revisions 13 and 1
A-484, Barrier Plans, Elevation 91' 6", Revision 8
A-485, Barrier Plans, Elevation 116' 0" Sheets 1 and 2, Revisions 8 and 4
A-486, Barrier Plans, Elevation 135' 0" Sheets 1 and 2, Revisions 11 and 1
A-487, Barrier Plans, Elevation 165' 0" Sheets 1 and 2, Revisions 13 and 1
C-49, Fire System Underground Yard Plan, Revision 25
C-49, Fire System Underground Yard Plan, Revision 25
E-1, Sheet 1, Single Line Diagram Station, Revision 57
E-1, Sheet 1, Single Line Diagram Station, Revision 57
E-12, Sheet 1, 4160 V Emergency Power System Unit 3, Revision 11
E-12, Sheet 1, 4160 V Emergency Power System Unit 3, Revision 11
E-1321, Sheet 3, Electrical Secondary and Control Connections Drywell Penetrations N
E-1321, Sheet 3, Electrical Secondary and Control Connections Drywell Penetrations N-106A,
-106A, B, C, D - Indication and Control, Unit 2, Revision 31
B, C, D - Indication and Control, Unit 2, Revision 31
E-1715, Sheet 1, E134 & E234 Emer. L.C., Revision 83
E-1715, Sheet 1, E134 & E234 Emer. L.C., Revision 83
E-1717, Sheet 1, E334 & E434
E-1717, Sheet 1, E334 & E434 Emer. L.C., Revision 72
Emer. L.C., Revision 72
E-184, Sheet 2, Electrical Schematic Diagram RHR Pump 4.16 kV Circuit Breaker, Revision 27
E-184, Sheet 2, Electrical Schematic Diagram RHR Pump 4.16 kV Circuit Breaker, Revision 27
E-193, Sheet 3, Electrical Schematic Diagram Emergency Auxiliary Switchgear Diesel
E-193, Sheet 3, Electrical Schematic Diagram Emergency Auxiliary Switchgear Diesel-
-Generator 4160V Circuit Breaker, Revision 32
Generator 4160V Circuit Breaker, Revision 32
E-2371, Sheet 1, Riser Diagram Distributed Antenna System, Revision 4
E-2371, Sheet 1, Riser Diagram Distributed Antenna System, Revision 4
E-2903, Sheet 1, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 6
E-2903, Sheet 1, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 6
E-2903, Sheet 3, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 0
E-2903, Sheet 3, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 0
E-8, Sheet 1, 4160V Emergency Power System Unit 2, Revision 20
E-8, Sheet 1, 4160V Emergency Power System Unit 2, Revision 20
M-1-S-36, Sheet 20, Electrical Schematic Diagram High Pressure Coolant Injection System, Revision 78
M-1-S-36, Sheet 20, Electrical Schematic Diagram High Pressure Coolant Injection System,
M-1-S-42, Sheet 13, Electrical Schematic Diagram Reactor Core Isolation Cooling System, Revision 74
Revision 78
M-1-S-42, Sheet 18, Electrical Schematic Diagram Reactor Core Isolation Cooling System, Revision 79
M-1-S-42, Sheet 13, Electrical Schematic Diagram Reactor Core Isolation Cooling System,
M-1-S-42, Sheet 5, Electrical Schematic Diagram Reactor Core Isolation Cooling System, Revision 87
Revision 74
M-1-S-42, Sheet 7, Electrical Schematic Diagram Reactor Core Isolation Cooling System, Revision 76
M-1-S-42, Sheet 18, Electrical Schematic Diagram Reactor Core Isolation Cooling System,
Revision 79
M-1-S-42, Sheet 5, Electrical Schematic Diagram Reactor Core Isolation Cooling System,
Revision 87
M-1-S-42, Sheet 7, Electrical Schematic Diagram Reactor Core Isolation Cooling System,
Revision 76
M-1-S-65, Sheet 45, Electrical Schematic Diagram Residual Heat Removal System, Revision 97
M-1-S-65, Sheet 45, Electrical Schematic Diagram Residual Heat Removal System, Revision 97
M-1-S-65, Sheet 53, Electrical Schematic Diagram Residual Heat Removal System, Revision 99
M-1-S-65, Sheet 53, Electrical Schematic Diagram Residual Heat Removal System, Revision 99
M-1-S-65, Sheet 62, Electrical Schematic Diagram Residual Heat Removal System, Revision 103 PD-27, Sheet 1, Typical Penetration Seal Detail Grout Seal, Revision 1
M-1-S-65, Sheet 62, Electrical Schematic Diagram Residual Heat Removal System,
PD-5, Sheet 1, Typical Penetration Seal Detail External Pipe or Conduit Seal (SF
Revision 103
-20), Revision
PD-27, Sheet 1, Typical Penetration Seal Detail Grout Seal, Revision 1
PD-7, Typical Penetration Seal Detail, Cable Tray Wall Seal (SF
PD-5, Sheet 1, Typical Penetration Seal Detail External Pipe or Conduit Seal (SF-20), Revision
-20), Revision 1
PD-7, Typical Penetration Seal Detail, Cable Tray Wall Seal (SF-20), Revision 1
PD-9, Typical Penetration Seal Detail, Penetration through Barrier Less Than Required Thickness, Revision 0
PD-9, Typical Penetration Seal Detail, Penetration through Barrier Less Than Required
PS-301, Penetration Seal Locations, Controlled Barriers
Thickness, Revision 0
-Room No. 301, Units 2 and 3, Area 3, Elevation 150' 0", Revision 1
PS-301, Penetration Seal Locations, Controlled Barriers-Room No. 301, Units 2 and 3, Area 3,
PS-302, Penetration Seal Locations, Controlled Barriers
Elevation 150 0, Revision 1
-Room No. 302, Units 2 and 3, Area 3, Elevation 150' 0", Revision 2
PS-302, Penetration Seal Locations, Controlled Barriers-Room No. 302, Units 2 and 3, Area 3,
 
Elevation 150 0, Revision 2
PS-444, Sheet 1, Penetration Seal Locations Controlled Barriers  
PS-444, Sheet 1, Penetration Seal Locations Controlled Barriers - Room No. 444 Unit 3,
- Room No. 444 Unit 3, Revision 0
Revision 0
PS-444, Sheet 2, Penetration Seal Locations Controlled Barriers  
PS-444, Sheet 2, Penetration Seal Locations Controlled Barriers - Room No. 444 Unit 3,
- Room No. 444 Unit 3, Revision 1
Revision 1
Fire Protection Evaluations of Modifications and Design Changes
Fire Protection Evaluations of Modifications and Design Changes
2321, Generic Letter 86
2321, Generic Letter 86-10 Evaluation - Post Fire Operation of Manual Valves
-10 Evaluation  
23620, Alternate Compensatory Measure for IR 4115309, HI/LO Interface Not Evaluated for
- Post Fire Operation of Manual Valves
Appendix R
23620, Alternate Compensatory Measure for IR 4115309, HI/LO Interface Not Evaluated for Appendix R
3968258, Generic Letter 86-10 Evaluation Supporting Configuration of Penetration
3968258, Generic Letter
RW2-116-105-3039
86-10 Evaluation Supporting Configuration of Penetration
Quality Assurance Audits and Self Assessments
RW 2-116-105-3039 Quality Assurance Audits and Self Assessments
AR 3994319, 2018 Triennial Fire Protection Inspection Preparatory Self-Assessment
AR 3994319, 2018 Triennial Fire Protection Inspection Preparatory Self
-Assessment
Procedures
Procedures
AO 54.2, 4KV Breaker Manual Operation, Revision 0
AO 54.2, 4KV Breaker Manual Operation, Revision 0
CC-AA-209-1001, Guidelines for Performing Fire Protection Program Configuration Change Review, Revision 2
CC-AA-209-1001, Guidelines for Performing Fire Protection Program Configuration Change
Review, Revision 2
CC-AA-211, Fire Protection Program, Revision 8
CC-AA-211, Fire Protection Program, Revision 8
CC-AA-211-1001, Fire Protection Engineering Evaluations, Revision 2
CC-AA-211-1001, Fire Protection Engineering Evaluations, Revision 2
EDMG-1.0, Extensive Damage Mitigation Guideline for Loss of Large Area of the Plant, Revision 1
EDMG-1.0, Extensive Damage Mitigation Guideline for Loss of Large Area of the Plant,
Revision 1
EDMG-2.0, Peach Bottom Operational Contingency Guidelines, Revision 8
EDMG-2.0, Peach Bottom Operational Contingency Guidelines, Revision 8
ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump, Inner Screen or Emergency Cooling Tower Structures, Revision 21
ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump,
ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump, Inner Screen or Emergency Cooling Tower Structures  
Inner Screen or Emergency Cooling Tower Structures, Revision 21
- Bases, Revision 20
ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump,
ON-115, Loss of Normal Main Control Room Ventilation  
Inner Screen or Emergency Cooling Tower Structures - Bases, Revision 20
- Bases, Revision 19
ON-115, Loss of Normal Main Control Room Ventilation - Bases, Revision 19
ON-115, Loss of Normal Main Control Room Ventilation  
ON-115, Loss of Normal Main Control Room Ventilation - Procedure, Revision 22
- Procedure, Revision 22
OP-AA-102-106, Operator Response Time Program, Revision 4
OP-AA-102-106, Operator Response Time Program, Revision 4
OP-AA-201-003, Fire Drill Performance, Revision 16
OP-AA-201-003, Fire Drill Performance, Revision 16
Line 356: Line 313:
SE-10, Alternate Shutdown, Attachment 6, Revision 8A
SE-10, Alternate Shutdown, Attachment 6, Revision 8A
SE-10, Alternate Shutdown, Attachment 9, Revision 3
SE-10, Alternate Shutdown, Attachment 9, Revision 3
SE-10, Plant Shutdown from the Alternate Shutdown Panels  
SE-10, Plant Shutdown from the Alternate Shutdown Panels - Bases, Revision 29
- Bases, Revision 29
T-100, Scram - Bases, Revision 15
 
T-100, Scram, Revision 11
T-100, Scram  
T-302-2, Area 02 Fire Guide, Revision 10
- Bases, Revision 15
T-100, Scram, Revision 11 T-302-2, Area 02 Fire Guide, Revision 10
T-302-3, Area 02 Fire Guide, Revision 9
T-302-3, Area 02 Fire Guide, Revision 9
T-313N-2, Area 13N Fire Guide, Revision 4
T-313N-2, Area 13N Fire Guide, Revision 4
Line 367: Line 322:
T-325-2, Area 25 Fire Guide, Revision 1
T-325-2, Area 25 Fire Guide, Revision 1
T-325-3, Area 25 Fire Guide, Revision 1
T-325-3, Area 25 Fire Guide, Revision 1
T-3 36-2, Area 36 Fire Guide, Revision 4
T-336-2, Area 36 Fire Guide, Revision 4
T-336-3, Area 36 Fire Guide, Revision 4
T-336-3, Area 36 Fire Guide, Revision 4
TSG 4.1, Attachment 15, Alternate 125VDC Power Supply for SRV Operation, Revision 6
TSG 4.1, Attachment 15, Alternate 125VDC Power Supply for SRV Operation, Revision 6
Line 373: Line 328:
Operator Safe Shutdown Training
Operator Safe Shutdown Training
DBIG PNLO-3106, SE-10, Plant Shutdown from the Alternate Shutdown Panels, Revision 3
DBIG PNLO-3106, SE-10, Plant Shutdown from the Alternate Shutdown Panels, Revision 3
JPM PLOR-047C, Take Action for Control Room Evacuation (SE
JPM PLOR-047C, Take Action for Control Room Evacuation (SE-10 Attachment 6), Revision 11
-10 Attachment 6), Revision 11
JPM PLOR-057P, Plant Shutdown from Alternate Shutdown Panel - HPCI Operations,
JPM PLOR-057P, Plant Shutdown from Alternate Shutdown Pa
Revision 8
nel - HPCI Operations, Revision 8 PLORT-1605A, Fire Protection and Appendix R, Revision 0
PLORT-1605A, Fire Protection and Appendix R, Revision 0
PLOT-1565, PBAPS Transient Response Implementation Procedures (T
PLOT-1565, PBAPS Transient Response Implementation Procedures (T-300 Series), Revision 2
-300 Series), Revision 2
PLOT-5037X, Remote Shutdown Panel & Fire Safe Shutdown/Alternate Panel Controls,
PLOT-5037X, Remote Shutdown Panel & Fire Safe Shutdown/Alternate Panel Controls, Revision 4
Revision 4
PLOT-6000, Licensed Operator Initial Qualification Manual, Revision 22
PLOT-6000, Licensed Operator Initial Qualification Manual, Revision 22
PLOT-6000A, Licensed Operator Initial OJT Module (RO Tasks), Revision 1
PLOT-6000A, Licensed Operator Initial OJT Module (RO Tasks), Revision 1
PLOT-6000B, Licensed Operator Initial OJT Module (EO Tasks), Revision 1
PLOT-6000B, Licensed Operator Initial OJT Module (EO Tasks), Revision 1
PLOT-6000C, Licensed Operator
PLOT-6000C, Licensed Operator Initial OJT Module (SRO Tasks) Revision 1
Initial OJT Module (SRO Tasks) Revision 1
PNLO-2215, Effects of Fire on Safe Shutdown Equipment, Revision 5
PNLO-2215, Effects of Fire on Safe Shutdown Equipment, Revision 5
PNLO-6000E, Equipment Operator Initial Qualification Manual, Revision 3
PNLO-6000E, Equipment Operator Initial Qualification Manual, Revision 3
Simulator Exercise Guide PSEG
Simulator Exercise Guide PSEG-0409R-03, Fire in Cable Spreading Room, Revision 0
-0409R-03, Fire in Cable Spreading Room, Revision 0 Pre-Fire Plans
Pre-Fire Plans
FF-01, Fire Fighting Plan, Revision 23
FF-01, Fire Fighting Plan, Revision 23
PF-0, Pre-Fire Strategy Plan Area and Location Index, Revision 9
PF-0, Pre-Fire Strategy Plan Area and Location Index, Revision 9
PF-108, Pre-Fire Plan, Radioactive Waste Building, Fan Room, Elevation 165' 0", Revision PF-127, Pre-Fire Plan, Unit 2 Turbine Building, Emergency Battery Switchgear Rooms, Elevation 135' 0", Revision 10
PF-108, Pre-Fire Plan, Radioactive Waste Building, Fan Room, Elevation 165 0,
PF-12B, Pre-Fire Plan, Unit 2 Reactor Building Closed Loop Cooling Water Room, Elevation 116' 0", Revision 8
Revision PF-127, Pre-Fire Plan, Unit 2 Turbine Building, Emergency Battery Switchgear
PF-13J, Pre-Fire Plan, Unit 2 Reactor Building General Area, Elevation 165' 0", Revision 3
Rooms, Elevation 135 0, Revision 10
PF-12B, Pre-Fire Plan, Unit 2 Reactor Building Closed Loop Cooling Water Room,
Elevation 116 0, Revision 8
PF-13J, Pre-Fire Plan, Unit 2 Reactor Building General Area, Elevation 165 0, Revision 3
Fire Brigade Training
Fire Brigade Training
FBP04, Fire Behavior and Essentials, Revision 8
FBP04, Fire Behavior and Essentials, Revision 8
Line 400: Line 357:
Fire Brigade Member Qualification Status Report, dated 4/5/18
Fire Brigade Member Qualification Status Report, dated 4/5/18
FPB11, Tactics and Strategy, Revision 7
FPB11, Tactics and Strategy, Revision 7
FPB15, Pre
FPB15, Pre-Fire Plans, Revision 6
-Fire Plans, Revision 6
IMS-01, Incident Management System, Revision 2
IMS-01, Incident Management System, Revision 2
PNLOC 1612A, 4
PNLOC 1612A, 4th Quarter Fire Brigade Meeting, Revision 0
th Quarter Fire Brigade Meeting, Revision 0
 
Fire Brigade Drills and Critiques
Fire Brigade Drills and Critiques
Fire Brigade Drill Third Party Observation Report, performed on 12/7/17
Fire Brigade Drill Third Party Observation Report, performed on 12/7/17
N-PB-OPS-EO-FB-DRILL1, PS01 4
N-PB-OPS-EO-FB-DRILL1, PS01 4th Quarter Fire Drill and Critique, performed on 12/13/17
th Quarter Fire Drill and Critique, performed on 12/13/17
N-PB-OPS-EO-FB-DRILL1, PS02 4th Quarter Fire Drill and Critique, performed on 12/15/17
N-PB-OPS-EO-FB-DRILL1, PS02 4
N-PB-OPS-EO-FB-DRILL1, PS04 4th Quarter Fire Drill and Critique, performed on 12/7/17
th Quarter Fire Drill and Critique, performed on 12/15/17
N-PB-OPS-EO-FB-DRILL1, PS05 1st Quarter Unannounced, Backshift Fire Drill and Critique,
N-PB-OPS-EO-FB-DRILL1, PS04 4
performed on 3/22/17
th Quarter Fire Drill and Critique, performed on 12/7/17
N-PB-OPS-EO-FB-DRILL1, PS05 4th Quarter Fire Drill and Critique, performed on 12/22/17
N-PB-OPS-EO-FB-DRILL1, PS05 1
st Quarter Unannounced, Backshift Fire Drill and Critique, performed on 3/22/17
N-PB-OPS-EO-FB-DRILL1, PS05 4
th Quarter Fire Drill and Critique, performed on 12/22/17
Transient Combustible, Hot Work, and Ignition Source Permits and Evaluations
Transient Combustible, Hot Work, and Ignition Source Permits and Evaluations
Hot Work Permit 0611, RTV
Hot Work Permit 0611, RTV-2-14-29010A, Rework Valve/Replace Bonnet, dated 3/1/18
-2-14-29010A, Rework Valve/Replace Bonnet, dated 3/1/18
Hot Work Permit 0680, Install New Heat Exchanger, dated 12/11/18
Hot Work Permit 0680, Install New Heat Exchanger, dated 12/11/18
Transient Combustible Permit 1070, Units 2 and 3 Turbine Building, Fire Zone 50
Transient Combustible Permit 1070, Units 2 and 3 Turbine Building, Fire Zone 50-78A,
-78A, Temporary Power
Temporary Power
Transient Combustible Permit 1071, Unit 3 Turbine Building, Fire Zone 50
Transient Combustible Permit 1071, Unit 3 Turbine Building, Fire Zone 50-78T, Temporary
-78T, Temporary Power Transient Combustible Permit 1072, Unit 2 Reactor Building, Fire Zone 1
Power
-2, Temporary Power
Transient Combustible Permit 1072, Unit 2 Reactor Building, Fire Zone 1-2, Temporary Power
Transient Combustible Permit 1073, Emergency Cooling Tower, Fire Zone 51
Transient Combustible Permit 1073, Emergency Cooling Tower, Fire Zone 51-136, Test
-136, Test Equipment Transient Combustible Permit 1075, E
Equipment
-42 Switchgear Room, Fire Zone 36
Transient Combustible Permit 1075, E-42 Switchgear Room, Fire Zone 36-123, Temporary
-123, Temporary Instrumentation and Cabling
Instrumentation and Cabling
Completed Tests and Surveillances
Completed Tests and Surveillances
R1302419-01, Calibration Check of Alternative Shutdown Panel Reactor Vessel Level Instruments, completed 10/25/16
R1302419-01, Calibration Check of Alternative Shutdown Panel Reactor Vessel Level
Instruments, completed 10/25/16
RT-0-052-750-2, E2 Diesel Alternative Shutdown Control Functional, completed 3/21/16
RT-0-052-750-2, E2 Diesel Alternative Shutdown Control Functional, completed 3/21/16
RT-M-57E-700-2, Main Control Room Emergency Lighting Battery Yearly Inspection (20 D 304-2), completed 1/24/17
RT-M-57E-700-2, Main Control Room Emergency Lighting Battery Yearly Inspection
RT-M-57E-700-3, Main Control Room Emergency Lighting Battery Yearly Inspection  
        (20D304-2), completed 1/24/17
(30 D 304-2), completed 1/24/17
RT-M-57E-700-3, Main Control Room Emergency Lighting Battery Yearly Inspection
RT-M-57E-710-2, Main Control Room Emergency Lighting Battery Discharge Performance Test (20D304-2), completed 8/11/17
        (30D304-2), completed 1/24/17
R T-M-57E-710-3, Main Control Room Emergency Lighting Battery Discharge Performance Test (30D304-2), completed 1/22/18
RT-M-57E-710-2, Main Control Room Emergency Lighting Battery Discharge Performance Test
RT-O-037-375-2, In-Plant Fire Brigade Equipment Inventory and Inspection, completed 2/5/2018 RT-O-037-376-2, Outside Fire Brigade Equipment Inventory and Inspection, completed 2/10/2018 RT-O-037-710-2, Complete Safe Shutdown Emergency Lighting Battery Pack Inspection , completed 2/10/18
        (20D304-2), completed 8/11/17
RT-O-037-719-2, Emergency Lighting Inspection (Alternate Shutdown Control Station Access
RT-M-57E-710-3, Main Control Room Emergency Lighting Battery Discharge Performance Test
/ Egress Lights), completed 11/2/16
        (30D304-2), completed 1/22/18
RT-O-037-719-3, Emergency Lighting Inspection (Alternate Shutdown Control Station Access
RT-O-037-375-2, In-Plant Fire Brigade Equipment Inventory and Inspection, completed
/ Egress Lights), completed 11/6/17
2/5/2018
RT-O-037-376-2, Outside Fire Brigade Equipment Inventory and Inspection, completed
2/10/2018
RT-O-037-710-2, Complete Safe Shutdown Emergency Lighting Battery Pack Inspection,
completed 2/10/18
RT-O-037-719-2, Emergency Lighting Inspection (Alternate Shutdown Control Station Access/
Egress Lights), completed 11/2/16
RT-O-037-719-3, Emergency Lighting Inspection (Alternate Shutdown Control Station Access/
Egress Lights), completed 11/6/17
RT-O-100-505-2, Emergency Operating Procedure Tool Inventory, completed 12/6/17
RT-O-100-505-2, Emergency Operating Procedure Tool Inventory, completed 12/6/17
RT-O-100-580-2, B.5.b Tool and Material Inventory, completed 8/2/2017
RT-O-100-580-2, B.5.b Tool and Material Inventory, completed 8/2/2017
ST-I-037-223-2, Unit 2 4 Kilo
ST-I-037-223-2, Unit 2 4 Kilo-Volt Switchgear and Battery Room and Radwaste 135 Corridor
-Volt Switchgear and Battery Room and Radwaste 135' Corridor Smoke Detectors Functional Test, completed 6/3/15
Smoke Detectors Functional Test, completed 6/3/15
ST-I-037-223-2, Unit 2 4 Kilo
ST-I-037-223-2, Unit 2 4 Kilo-Volt Switchgear and Battery Room and Radwaste 135 Corridor
-Volt Switchgear and Battery Room and Radwaste 135' Corridor Smoke Detectors Functional Test, completed 8/3/17
Smoke Detectors Functional Test, completed 8/3/17
ST-I-037-276-3, Reactor Building Elevation 165' Smoke Detectors Functional Test, completed 1/27/15
ST-I-037-276-3, Reactor Building Elevation 165 Smoke Detectors Functional Test, completed
ST-I-037-276-3, Reactor Building Elevation 165' Smoke Detectors Functional Test, completed 7/28/1 7 ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional Test, completed 6/23/15
1/27/15
ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional Test, completed 1/13/17
ST-I-037-276-3, Reactor Building Elevation 165 Smoke Detectors Functional Test, completed
7/28/17
ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional
Test, completed 6/23/15
ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional
Test, completed 1/13/17
ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 10/20/16
ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 10/20/16
ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 6/22/17
ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 6/22/17
ST-I-037-293-2, Recirculation Motor
ST-I-037-293-2, Recirculation Motor-Generator Set Lube Oil Pump 116 Smoke Detectors
-Generator Set Lube Oil Pump 116' Smoke Detectors Functional Test, completed 5/11/17
Functional Test, completed 5/11/17
ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air Flow Test, completed 10/10/17
ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air
ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air Flow Test, completed 5/31/16
Flow Test, completed 10/10/17
ST-I-0 37A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air Flow Test, completed 10/10/17
ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air
ST-M-037-311-2, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire Barriers, completed 6/8/12
Flow Test, completed 5/31/16
ST-M-037-311-3, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire Barriers, completed 12/21/17
ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air
Flow Test, completed 10/10/17
ST-M-037-311-2, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire
Barriers, completed 6/8/12
ST-M-037-311-3, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire
Barriers, completed 12/21/17
ST-M-037-314-2, Visual Inspection of Encapsulated Electrical Raceways, completed 6/14/16
ST-M-037-314-2, Visual Inspection of Encapsulated Electrical Raceways, completed 6/14/16
ST-M-037D-380-2, Diesel Driven Fire Pump Inspection, completed 1/1/17 ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165') Sprinkler System Actuation, completed 3/14/16
ST-M-037D-380-2, Diesel Driven Fire Pump Inspection, completed 1/1/17
ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165') Sprinkler System Actuation, completed 3/25/18
ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165) Sprinkler System
ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Ki
Actuation, completed 3/14/16
lo-Volt Switchgear Rooms, and Radwaste Corridor Area Sprinkler System Actuation, completed 7/10/14
ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165) Sprinkler System
ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Kilo
Actuation, completed 3/25/18
-Volt Switchgear Rooms, and Radwaste Corridor Area Sprinkler System Actuation, completed 7/9/16
ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Kilo-Volt Switchgear Rooms, and Radwaste Corridor
Area Sprinkler System Actuation, completed 7/10/14
ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Kilo-Volt Switchgear Rooms, and Radwaste Corridor
Area Sprinkler System Actuation, completed 7/9/16
ST-O-037B-381-2, Underground Fire Main Flow Test, completed 6/10/15
ST-O-037B-381-2, Underground Fire Main Flow Test, completed 6/10/15
ST-O-037B-381-2, Underground Fire Main Flow Test, completed 8/8/14
ST-O-037B-381-2, Underground Fire Main Flow Test, completed 8/8/14
ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, completed 8/6/15
ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, completed 8/6/15
ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, complete
ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, completed 12/13/16
d 12/13/16 ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 1/23/18
ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 1/23/18
ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 2/21/18
ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 2/21/18
ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 11/25/15
ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 11/25/15
ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 1/17/17
ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 1/17/17
ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed 1/9/18
ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed 1/9/18
ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed
ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed 2/7/18
2/7/18 Issue Reports
Issue Reports (* written as a result of the NRC inspection)
(* written as a result of the NRC inspection
00450846           01109076             01275720         01492237           01521603
) 00450846 01109076 01275720 01492237 01521603 01581135 02386737 02421301 02451017 02451647 02478057 02661579 02697843 02699896 02718710 03962962 03980676 04000043 04080702 04082065 04084069 04084077 04102768 04115309 04118443 04122474* 04122883* 04122970* 04127608* 04128972* 04129171*
01581135           02386737             02421301         02451017           02451647
2478057            02661579             02697843         02699896           02718710
03962962           03980676             04000043         04080702           04082065
04084069           04084077             04102768         04115309           04118443
04122474*           04122883*           04122970*         04127608*         04128972*
04129171*
Work Orders
Work Orders
4319703 4595771 4648804 R1298970 R1326279 Operating Experience
4319703             4595771           4648804             R1298970           R1326279
NRC Information Notice
Operating Experience
1997-48, Inadequate or Inappropriate Interim Fire Protection Compensatory Measures
NRC Information Notice 1997-48, Inadequate or Inappropriate Interim Fire Protection
NRC Information
Compensatory Measures
Notice 2013
NRC Information Notice 2013-02, Issues Potentially Affecting Nuclear Facility Fire Safety
-02, Issues Potentially Affecting Nuclear Facility Fire Safety
NRC Information Notice 2013-06, Corrosion in Fire Protection Piping Due to Air and Water
NRC Information Notice 2013
Interaction
-06, Corrosion in Fire Protection Piping Due to Air and Water Interaction
NRC Information Notice 2013-09, Compressed Flammable Gas Cylinders and Associated
NRC Information Notice 2013
Hazards
-09, Compressed Flammable Gas Cylinders and Associate
NRC Information Notice 2014-10, Potential Circuit Failure-Induced Secondary Fires or
d Hazards NRC Information Notice 2014
Equipment Damage
-10, Potential Circuit Failure
NRC Information Notice 2014-15, Inadequate Controls of Respiratory Protection Accessibility,
-Induced Secondary Fires or Equipment Damage
Training, and Maintenance
NRC Information Notice 2014
NRC Information Notice 2015-02, Anti-Freeze Agents in Fire Water Sprinkler Systems
-15, Inadequate Controls of Respiratory Protection Accessibility, Training, and Maintenance
NRC Regulatory Issue Summary 2005-07, Compensatory Measures to Satisfy the Fire
NRC Information Notice
Protection Program Requirements
2015-02, Anti-Freeze Agents in Fire Water Sprinkler Systems
NRC Regulatory Issue Summary 2005
-07, Compensatory Measures to Satisfy the Fire Protection Program Requirements
Miscellaneous Documents
Miscellaneous Documents
Bisco Report #748
Bisco Report #748-49, Fire Test Configuration for a Three-Hour Rated Fire Seal Utilizing Bisco
-49, Fire Test Configuration for a Three
-Hour Rated Fire Seal Utilizing Bisco
SF-20 Where a Steel Sleeve Condition with Pipe Penetrant Exists, dated 7/9/81
SF-20 Where a Steel Sleeve Condition with Pipe Penetrant Exists, dated 7/9/81
NLO B.5.b. Task List
NLO B.5.b. Task List
NUMARC 93-01, Industry Guideline for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants, Revision 4A
NUMARC 93-01, Industry Guideline for Monitoring the Effectiveness of Maintenance at
NUREG 1552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants, January 1999 PLORT 1610E, Extensive Damage Mitigation Guidelines, Revision 0
Nuclear Power Plants, Revision 4A
NUREG 1552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants,
January 1999
PLORT 1610E, Extensive Damage Mitigation Guidelines, Revision 0
PLOT 2305, Extensive Damage Mitigation Guidelines 1.0 and 2.0, Revision 1
PLOT 2305, Extensive Damage Mitigation Guidelines 1.0 and 2.0, Revision 1
PM-1120, Evaluation of B.5.b Mitigation Strategies, Revision 0
PM-1120, Evaluation of B.5.b Mitigation Strategies, Revision 0
Units 2 and 3 Fire Protection System 37 Health Reports, dated 4/4/18
Units 2 and 3 Fire Protection System 37 Health Reports, dated 4/4/18
UNITED STATES
UNITED STATES
NUCLEAR REGULATORY COMMISSION
NUCLEAR REGULATORY COMMISSION
REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100
REGION I
KING OF PRUSSIA, PA 19406
2100 RENAISSANCE BOULEVARD, SUITE 100
-2713 May 9, 2018
KING OF PRUSSIA, PA 19406-2713
May 9, 2018
Mr. Bryan C. Hanson
Mr. Bryan C. Hanson
Senior Vice President, Exelon Generation, LLC
Senior Vice President, Exelon Generation, LLC
President and Chief Nuclear Officer, Exelon Nuclear
President and Chief Nuclear Officer, Exelon Nuclear
4300 Winfield Road
4300 Winfield Road
Warrenville, IL 60555
Warrenville, IL 60555
SUBJECT: PEACH BOTTOM ATOMIC POWER STATION UNITS 2 AND 3
SUBJECT: PEACH BOTTOM ATOMIC POWER STATION UNITS 2 AND 3 - TRIENNIAL
- TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000
FIRE PROTECTION INSPECTION REPORT 05000277/2018010 AND
277/20 18010 AND 05000 278/20 18010  Dear Mr. Hanson
05000278/2018010
On April 20, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Peach Bottom Atomic Power Station
Dear Mr. Hanson:
(Peach Bottom), Units 2 and 3. The NRC inspectors discussed the results of this inspection with Mr. Pat Navin, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
On April 20, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at
NRC inspectors documented two findings of very low safety significance (Green) in this report. One of these findings involved a violation of NRC requirements. Further, inspectors documented a licensee
Peach Bottom Atomic Power Station (Peach Bottom), Units 2 and 3. The NRC inspectors
-identified violation which was determined to be of very low safety significance in this report. The NRC is treating the se violations as non
discussed the results of this inspection with Mr. Pat Navin, Site Vice President, and other
-cited violations (NCVs)
members of your staff. The results of this inspection are documented in the enclosed report.
, consistent with Section
NRC inspectors documented two findings of very low safety significance (Green) in this report.
2.3.2.a of the Enforcement Policy.
One of these findings involved a violation of NRC requirements. Further, inspectors
If you contest the violation
documented a licensee-identified violation which was determined to be of very low safety
s or significance of t
significance in this report. The NRC is treating these violations as non-cited violations (NCVs),
he s e NCV s, you should provide a response within
consistent with Section 2.3.2.a of the Enforcement Policy.
days of the date of this inspection report, with the basis for your denial, to the  
If you contest the violations or significance of these NCVs, you should provide a response within
: [[contact::U.S. Nuclear Regulatory Commission]], ATTN:
days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear
Document Control Desk, Washington, DC 20555
Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with
-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Peach Bottom. In addition, if you disagree with a cross
copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC
-cutting aspect assignment
Resident Inspector at Peach Bottom. In addition, if you disagree with a cross-cutting aspect
or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the  
assignment or a finding not associated with a regulatory requirement in this report, you should
: [[contact::U.S. Nuclear Regulatory Commission]], ATTN:
provide a response within 30 days of the date of this inspection report, with the basis for your
Document Control Desk, Washington, DC, 20555
disagreement, to the  
-0001; with copies to the Regional Administrator, Region I, and the NRC Resident Inspector at Peach Bottom.
: [[contact::U.S. Nuclear Regulatory Commission]], ATTN: Document Control Desk,
: [[contact::B. Hanson 2   This letter]], its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading
Washington, DC, 20555-0001; with copies to the Regional Administrator, Region I, and the NRC
-rm/adams.html
Resident Inspector at Peach Bottom.
and the NR
B. Hanson                                         2
C's Public Document Room in accordance with Title 10 of the Code of Federal Regulations  
This letter, its enclosure, and your response (if any) will be made available for public inspection
(10 CFR ), Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."
and copying at http://www.nrc.gov/reading-rm/adams.html and the NRCs Public Document
Sincerely, /RA/   Glenn  
Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR ), Part 2.390,
: [[contact::T. Dentel]], Chief Engineering Branch 2
Public Inspections, Exemptions, Requests for Withholding.
Division of Reactor Safety Docket Nos.
Sincerely,
50-277 and 50
                                              /RA/
-278 License Nos.
Glenn  
DPR-44 and DPR
: [[contact::T. Dentel]], Chief
-56 Enclosure:
Engineering Branch 2
Inspection Report 05000
Division of Reactor Safety
277/20 18010    and 05000 278/2018010 cc w/encl:
Docket Nos. 50-277 and 50-278
License Nos. DPR-44 and DPR-56
Enclosure:
Inspection Report 05000277/2018010
and 05000278/2018010
cc w/encl:
Distribution via ListServ
Distribution via ListServ
ML18130A299
SUNSI Review            Non-Sensitive                    Publicly Available
Sensitive                          Non-Publicly Available
OFFICE          RI/DRS        RI/DRP            RI/DRS            RI/DRS
NAME            CBickett      JKrafty          CCahill          GDentel
DATE            05/03/18      05/08/18          05/08/18          05/09/18


ML18130A299
U.S. NUCLEAR REGULATORY COMMISSION
SUNSI Review
Non-Sensitive  Sensitive    Publicly Available
Non-Publicly Available
OFFICE RI/DR S RI/DR P RI/DR S RI/DR S  NAME CBickett JKrafty CCahill GDentel  DATE 05/03/18 05/08/18 05/08/18 05/09/18
Enclosure U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Inspection Report
Docket Numbers: 50-277 and 50
Docket Numbers:             50-277 and 50-278
-278   License Numbers: DPR-44 and DPR
License Numbers:           DPR-44 and DPR-56
-56   Report Numbers: 05000 277/20 18010 and 05000 278/20 18010  Enterprise Identifier:
Report Numbers:             05000277/2018010 and 05000278/2018010
I-2018-010-0059   Licensee: Exelon Generation Company, LLC
Enterprise Identifier:     I-2018-010-0059
Facility: Peach Bottom Atomic Power Station, Units 2 and 3
Licensee:                   Exelon Generation Company, LLC
Location: Delta, PA   Inspection Dates: April 2 - 20, 2018   Inspectors:
Facility:                   Peach Bottom Atomic Power Station, Units 2 and 3
: [[contact::C. Bickett ]], Senior Reactor Inspector
Location:                   Delta, PA
(Team Lead)
Inspection Dates:           April 2 - 20, 2018
Inspectors:                
: [[contact::C. Bickett]], Senior Reactor Inspector (Team Lead)
: [[contact::E. DiPaolo]], Senior Reactor Inspector
: [[contact::E. DiPaolo]], Senior Reactor Inspector
: [[contact::P. Ott]], Operations Engineer  
: [[contact::P. Ott]], Operations Engineer
: [[contact::J. Patel]], Reactor Inspector
: [[contact::J. Patel]], Reactor Inspector
: [[contact::C. Cahill]], Senior Reactor Analyst
: [[contact::C. Cahill]], Senior Reactor Analyst
Approved By:
Approved By:              
: [[contact::G. Dentel ]], Chief   Engineering Branch 2   Division of Reactor Safety
: [[contact::G. Dentel]], Chief
SUMMARY The U.S. Nuclear Regulatory Commission (NRC) continued monitoring
Engineering Branch 2
Exelon's performance at Peach Bottom Atomic Power Station, Units 2 and 3
Division of Reactor Safety
by conducting the triennial fire protection team inspection
 
in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRC's program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html
SUMMARY
for more information. NRC and self
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Exelons performance at
-revealed findings, violations, and additional items are summarized in the table
Peach Bottom Atomic Power Station, Units 2 and 3 by conducting the triennial fire protection
s below. A license e-identified non
team inspection in accordance with the Reactor Oversight Process. The Reactor Oversight
-cited violation
Process is the NRCs program for overseeing the safe operation of commercial nuclear power
(NCV) is documented in report section 71111.05T. List of Findings and Violations
reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
Failure to Identify Time
NRC and self-revealed findings, violations, and additional items are summarized in the tables
-Critical Action
below. A licensee-identified non-cited violation (NCV) is documented in report section
Cornerstone
71111.05T.
Significance
List of Findings and Violations
Cross-cutting Aspect Report Section Mitigating Systems Green FIN 05000277, 05000278/2018010
Failure to Identify Time-Critical Action
-01 Closed P.2 - Problem Identification and Resolution, Evaluation
Cornerstone           Significance                                 Cross-cutting       Report
71111.05T The inspectors identified a green finding because Exelon did not identify, validate, and incorporate a time
Aspect             Section
-critical action referenced in
Mitigating             Green                                        P.2 - Problem      71111.05T
calculation PF
Systems               FIN 05000277, 05000278/2018010-01             Identification and
-0016-025, "Fire Area 025  
Closed                                        Resolution,
- Fire Safe Shutdown Analysis," in accordance with Sections 4.2 and 4.3 of OP
Evaluation
-AA-102-106, "Operator Response Time Program.Specifically, Exelon did not identify a 10
The inspectors identified a green finding because Exelon did not identify, validate, and
-minute time
incorporate a time-critical action referenced in calculation PF-0016-025, Fire Area 025 - Fire
-critical action to take the "transfer/isolation" switch for the high pressure coolant injection (HPCI) inboard steam isolation valve (MO
Safe Shutdown Analysis, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106,
-2(3)-23-015), to the "EMERG" position.
Operator Response Time Program. Specifically, Exelon did not identify a 10-minute time-
critical action to take the transfer/isolation switch for the high pressure coolant injection
  (HPCI) inboard steam isolation valve (MO-2(3)-23-015), to the EMERG position.
Failure to Develop and Maintain Mitigating Strategy
Failure to Develop and Maintain Mitigating Strategy
Cornerstone
Cornerstone           Significance                                 Cross-cutting       Report
Significance
Aspect             Section
Cross-cutting Aspect Report Section Mitigating Systems Green NCV 05000277, 05000278/2018010
Mitigating             Green                                        None                71111.05T
-02 Closed None 71111.05T The inspectors identified a Green non
Systems               NCV 05000277, 05000278/2018010-02
-cited violation of 10 CFR 50.54(hh)(2), "Conditions of Licenses," and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition
Closed
2.C.(11), "Mitigation Strategy License Condition," because Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Specifically, Exelon did not adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves in the event of a challenge to the reactor due to a postulated large fire and/or explosion.
The inspectors identified a Green non-cited violation of 10 CFR 50.54(hh)(2), Conditions of
 
Licenses, and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition
2.C.(11), Mitigation Strategy License Condition, because Exelon did not develop and
maintain strategies for addressing large fires and explosions that include operations to mitigate
fuel damage. Specifically, Exelon did not adequately develop and maintain procedures to
manually depressurize the reactor using the automatic depressurization system safety relief
valves in the event of a challenge to the reactor due to a postulated large fire and/or explosion.
INSPECTION SCOPE
INSPECTION SCOPE
This inspection was conducted using the appropriate portions of the inspection procedure (IP) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at
This inspection was conducted using the appropriate portions of the inspection procedure (IP) in
http://www.nrc.gov/reading
effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with
-rm/doc-collections/insp
their attached revision histories are located on the public website at
-manual/inspection
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, "Light
Samples were declared complete when the IP requirements most appropriate to the inspection
-Water Reactor Inspection Program  
activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor
- Operations Phase."
Inspection Program - Operations Phase. The inspectors reviewed selected procedures and
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Exelon performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
records, observed activities, and interviewed personnel to assess Exelon performance and
compliance with Commission rules and regulations, license conditions, site procedures, and
standards.
REACTOR SAFETY
REACTOR SAFETY
71111.05T  
71111.05T - Fire Protection (Triennial)
- Fire Protection (Triennial)
The inspectors evaluated the following from April 2 - 20, 2018:
The inspectors evaluated the following from April 2 - 20, 2018: Fire Protection Inspection Requirements
Fire Protection Inspection Requirements (4 Samples)
(4 Samples
The inspectors evaluated fire protection program implementation in the following
The inspectors evaluated fire protection program implementation in the following selected areas
selected areas and/or fire zones:
and/or fire zones
        (1) Fire Area 25: Cable Spreading Room (Zone 78H) and Fan Room (Zone 108A)
(1) Fire Area 25: Cable Spreading Room (Zone 78H) and Fan Room (Zone 108A)
        (2) Fire Area 36: Unit 2 E42 Emergency Switchgear Room (Zone 123)
(2) Fire Area 36: Unit 2 E42 Emergency Switchgear Room (Zone 123)
        (3) Fire Area 2: Unit 3 Reactor Building Closed Cooling Water Room (Zone 12B)
(3) Fire Area 2: Unit 3 Reactor Building Closed Cooling Water Room (Zone 12B)
        (4) Fire Area 13N: Unit 3 Reactor Building Operating Area (Zone 13J)
(4) Fire Area 13N: Unit 3 Reactor Building Operating Area (Zone 13J)
In performing this review, the inspectors performed an analysis of the following electrical
In performing this review, the inspectors performed an analysis
circuits:
of the following electrical circuits: (1) MO-4487, Reactor Core Isolation Cooling System
        (1) MO-4487, Reactor Core Isolation Cooling System Turbine Trip and Throttle Valve
Turbine Trip and Throttle Valve
        (2) 2-152-1704, E3 Emergency Diesel Generator Breaker to E32 Emergency Switchgear
(2) 2-152-1704, E3 Emergency Diesel Generator
            (20A17)
Breaker to E32 Emergency Switchgear (20A17) (3) LT-8456 and LI
        (3) LT-8456 and LI-8456, Suppression Pool Level Transmitter and Indicator
-8456, Suppression Pool Level Transmitter and Indicator
        (4) MO3-23-017, High Pressure Coolant Injection (HPCI) System Pump Suction from
(4) MO3-23-017, High Pressure Coolant Injection (HPCI) System
Condensate Storage Tank
Pump Suction
        (5) MO3-10-013A, Residual Heat Removal System Suction Isolation Valve From
from Condensate Storage Tank
Suppression Pool
(5) MO3-10-013A, Residual Heat Removal System
        (6) MO3-10-89B, Residual Heat Removal System Heat Exchanger High Pressure
Suction Isolation Valve From Suppression Pool
Service Water Discharge Valve
(6) MO3-10-89B, Residual Heat Removal System
B.5.b Inspection Activities (1 Sample)
Heat Exchanger High Pressure Service Water
The inspectors evaluated feasibility of the following B.5.b Mitigating Strategy:
Discharge Valve
Extensive Damage Mitigation Guideline (EDMG) 2.0, Attachment 15, Alternate 125 VDC
B.5.b Inspection Activities
Power Supply for Safety Relief Valve Operation, Revision 8
(1 Sample) The inspectors evaluated feasibility of the following B.5.b Mitigating Strateg
y:  Extensive Damage Mitigation Guideline (EDMG) 2.0, Attachment  
, "Alternate 125 VDC Power Supply for Safety Relief Valve Operation," Revision 8
 
INSPECTION RESULTS
INSPECTION RESULTS
Failure to Identify Time
Failure to Identify Time-Critical Action
-Critical Action
Cornerstone           Significance                                 Cross-cutting     Report
Cornerstone
Aspect             Section
Significance
Mitigating             Green                                        P.2 - Problem      71111.05T
Cross-cutting Aspect Report Section Mitigating Systems Green  FIN 05000277, 05000278/2018010
Systems               FIN 05000277, 05000278/2018010-01 Identification
-01 Closed P.2 - Problem Identification and Resolution, Evaluation
Closed                                       and Resolution,
71111.05T The inspectors
Evaluation
identified a green finding because Exelon did not identify, validate, and incorporate a time
The inspectors identified a green finding because Exelon did not identify, validate, and
-critical action referenced in calculation PF
incorporate a time-critical action referenced in calculation PF-0016-025, Fire Area 025 - Fire
-0016-025, "Fire Area 025  
Safe Shutdown Analysis, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106,
- Fire Safe Shutdown Analysis,"
Operator Response Time Program. Specifically, Exelon did not identify a 10-minute time-
in accordance with Sections 4.2 and 4.3 of OP
critical action to take the transfer/isolation switch for the high pressure coolant injection
-AA-102-106, "Operator Response Time Program.Specifically, Exelon did not identify a 10
(HPCI) inboard steam isolation valve (MO-2(3)-23-015), to the EMERG position.
-minute time-critical action to take the "transfer/isolation" switch for the high pressure coolant injection (HPCI) inboard steam isolation valve (MO-2(3)-23-015), to the "EMERG" position.
Description: Operators use procedure SE-10, Alternative Shutdown, to control the plant from
Description
the alternate shutdown panels in the event of a fire that results in evacuation of the main
: Operators use procedure
control room. SE-10, Attachment 6, Part A, directs the transfer/isolation of safety relief valve
SE-10, "Alternative Shutdown,"
control and the setup and control of necessary 4KV and emergency diesel generator
to control the plant from the alternate shutdown panels in the event of a fire that results in evacuation of the main control room.
equipment at the alternate shutdown panels. This is in direct support of AC power restoration
SE-10, Attachment 6, Part A, directs the transfer/isolation
for MO-2(3)-23-015, and subsequent opening of the valve, as HPCI is the credited water
of safety relief valve control and the setup and control of necessary 4KV and emergency diesel generator equipment at the alternate shutdown panels. This is in direct support of AC power restoration for MO-2(3)-23-015, and subsequent opening of the valve, as HPCI is the credited water makeup source for this scenario. These actions are
makeup source for this scenario. These actions are required if the valve has shut due to a
required if the valve has shut due to a fire-induced spurious operation, and offsite power is not available.
fire-induced spurious operation, and offsite power is not available.
Issue report (IR) 2661579, dated 2016, documented that the station could not complete SE
Issue report (IR) 2661579, dated 2016, documented that the station could not complete SE-
-10, Attachment 6, Part A, in 28 minutes, as required by fire safe shutdown calculation PF
10, Attachment 6, Part A, in 28 minutes, as required by fire safe shutdown calculation PF-
-0016-025. IR 2661579 identified that worst case, the actions took 93 minutes. Removing certain contingencies in the procedure, Exelon was able to complete the actions in 54 minutes. The inspectors
0016-025. IR 2661579 identified that worst case, the actions took 93 minutes. Removing
noted that Exelon did not implement any compensatory measures to address this issue, and planned to revise the procedure to resequence
certain contingencies in the procedure, Exelon was able to complete the actions in 54
actions such that they could be completed in the required time. On April 6, 2018, the inspectors
minutes. The inspectors noted that Exelon did not implement any compensatory measures to
questioned
address this issue, and planned to revise the procedure to resequence actions such that they
Exelon since they did not demonstrate that the required manual operator action time of 28 minutes could be met, and the procedure revision had yet to be issued. In response, Exelon performed a walkdown of the existing procedure and determined that the actions up to including energization of the E
could be completed in the required time. On April 6, 2018, the inspectors questioned Exelon
-22 and E-23 buses via the E
since they did not demonstrate that the required manual operator action time of 28 minutes
-2 emergency diesel generator could be completed in 26 minutes and 28 seconds. Exelon then completed a temporary procedure change to ensure the actions to restore power with the E
could be met, and the procedure revision had yet to be issued. In response, Exelon
-2 emergency diesel generator were moved to earlier in the procedure attachment for expediency, and a second operator was added as a requirement to implement the actions. The inspectors
performed a walkdown of the existing procedure and determined that the actions up to
noted that one of the reasons that the station could not meet the 28
including energization of the E-22 and E-23 buses via the E-2 emergency diesel generator
-minute time was likely due a procedure revision that added corrective actions to swap fuses in response to a previous unrelated issue.
could be completed in 26 minutes and 28 seconds. Exelon then completed a temporary
During th is inspection, Exelon issued a revision to calculation
procedure change to ensure the actions to restore power with the E-2 emergency diesel
PF-0016-025, which updated the manual operator action list and the corresponding required action times per the most recent thermal hydraulic analysis , which included the measurement uncertainty recapture uprate implemented in January 2018. The revised time to complete the actions required to provide power
generator were moved to earlier in the procedure attachment for expediency, and a second
to MO-2(3)-23-015 was lowered from 28 to 24 minutes. The inspectors questioned whether the station would have been able to meet this revised time prior to the temporary procedure change. Exelon stated in the revised
operator was added as a requirement to implement the actions. The inspectors noted that
calculation , "operator action is provided to re-open HPCI Inboard Isolation Valve MO
one of the reasons that the station could not meet the 28-minute time was likely due a
-2(3)-23-015 should it spuriously close prior to transfer of control from the main control room.  
procedure revision that added corrective actions to swap fuses in response to a previous
 
unrelated issue.
This prompt action is treated as a defense
During this inspection, Exelon issued a revision to calculation PF-0016-025, which updated
-in-depth action
the manual operator action list and the corresponding required action times per the most
, as a specific sequence of failures must occur (spurious
recent thermal hydraulic analysis, which included the measurement uncertainty recapture
valve closure prior to transfer and subsequent loss of the primary source of power before transfer of control), and is not required for Appendix R compliance."
uprate implemented in January 2018. The revised time to complete the actions required to
Exelon reference d a docketed August 16, 1984 letter to the NRC as justification for this conclusion. The inspectors
provide power to MO-2(3)-23-015 was lowered from 28 to 24 minutes. The inspectors
reviewed this licensing basis letter and noted that the justification was based on the assumption that within 10 minutes, operators would man the HPCI alternate control station and isolate the control circuit for this valve.
questioned whether the station would have been able to meet this revised time prior to the
This would leave a maximum of
temporary procedure change. Exelon stated in the revised calculation, operator action is
minutes for the specific sequence of events to occur that would result in spurious closure of MO-2(3)-23-105, thus making this scenario unlikely. The inspectors noted Exelon did not thoroughly evaluate this letter
provided to re-open HPCI Inboard Isolation Valve MO-2(3)-23-015 should it spuriously close
to ensure that any conditions and/or assumptions were translated into the fire safe shutdown calculations and other station processes. As such, Exelon did not identify th
prior to transfer of control from the main control room.
e 10-minute action as a prompt action. The inspectors
This prompt action is treated as a defense-in-depth action, as a specific sequence of failures
determined that operators will
must occur (spurious valve closure prior to transfer and subsequent loss of the primary
likely be able to meet this 10
source of power before transfer of control), and is not required for Appendix R compliance.
-minute action with the current procedure. However, there are no administrative controls in place to ensure that future changes to the procedure will not challenge this time.
Exelon referenced a docketed August 16, 1984 letter to the NRC as justification for this
Additionally, because the 10-minute action requirement is not documented in the operator time response program, the Operations Training department does not know to incorporate the requirement into training, and the operators do not recognize the need to expeditiously complete the procedure step
conclusion.
s. The inspectors also noted other weaknesses in the station's evaluation and resolution of this issue. The inspectors concluded that Exelon incorrectly stated in IR 2661579 that "these actions are only necessary in the event of multiple spurious operations and as such, are not required to be satisfied to maintain plant operations within design or licensing bases.This is incorrect because this is a single spurious operation scenario, which is required to be mitigated per 10 CFR 50 Appendix R requirements. Also
The inspectors reviewed this licensing basis letter and noted that the justification was based
of note, even though this issue was documented in their 2017 self
on the assumption that within 10 minutes, operators would man the HPCI alternate control
-assessment for this inspection, Exelon still had not issued the revised procedure, nor implemented any compensatory actions prior to this inspection.
station and isolate the control circuit for this valve. This would leave a maximum of
Corrective Actions: The station's planned corrective actions
minutes for the specific sequence of events to occur that would result in spurious closure
include updating Peach Bottom's time-critical operator action program to include the 10
of MO-2(3)-23-105, thus making this scenario unlikely. The inspectors noted Exelon did not
-minute action
thoroughly evaluate this letter to ensure that any conditions and/or assumptions were
to take the "transfer/isolation" switch for MO
translated into the fire safe shutdown calculations and other station processes. As such,
-2(3)-23-015 to the "EMERG" position.
Exelon did not identify the 10-minute action as a prompt action. The inspectors determined
Corrective Action Reference:
that operators will likely be able to meet this 10-minute action with the current procedure.
IR 4127608
However, there are no administrative controls in place to ensure that future changes to the
Performance Assessment
procedure will not challenge this time. Additionally, because the 10-minute action requirement
Performance Deficiency: The failure to identify, validate, and incorporate a time
is not documented in the operator time response program, the Operations Training
-critical action referenced in calculation PF
department does not know to incorporate the requirement into training, and the operators do
-0016-025, in accordance with
not recognize the need to expeditiously complete the procedure steps.
Sections 4.2 and 4.3 of OP-AA-102-106, "Operator Response Time Program" is a performance deficiency.
The inspectors also noted other weaknesses in the stations evaluation and resolution of this
Screening: The performance deficiency was more than minor because if left uncorrected, the performance deficiency would have the potential to lead to a more significant safety concern. The 10-minute requirement is not documented in the operator time response program
issue. The inspectors concluded that Exelon incorrectly stated in IR 2661579 that these
; therefore, training has not been conducted, operators did not recognize the time
actions are only necessary in the event of multiple spurious operations and as such, are not
-critical action, and future changes to the SE
required to be satisfied to maintain plant operations within design or licensing bases. This is
-10 procedure could result in challenging the 10
incorrect because this is a single spurious operation scenario, which is required to be
-minute requirement.
mitigated per 10 CFR 50 Appendix R requirements. Also of note, even though this issue was
Significance: The inspectors assessed the significance of the finding using IMC 0609, Appendix F, "Fire Protection SDP.This issue screened to very low safety significance (Green) in Phase 1, Step 1.3 as the procedure as currently written does not impact the ability to achieve safe shutdown.
documented in their 2017 self-assessment for this inspection, Exelon still had not issued the
 
revised procedure, nor implemented any compensatory actions prior to this inspection.
Cross-cutting Aspect
Corrective Actions: The stations planned corrective actions include updating Peach Bottoms
: This finding had a cross
time-critical operator action program to include the 10-minute action to take the
-cutting aspect in the area of Problem Identification and Resolution, Evaluation, because although Exelon included a reference to the 1984 letter in the latest revision to the fire safe shutdown calculation, they did not thoroughly evaluate the letter to ensure that any conditions and/or assumptions were translated into the fire safe shutdown calculations and other station processes [P.2].
transfer/isolation switch for MO-2(3)-23-015 to the EMERG position.
Enforcement: Inspectors did not identify a violation of regulatory requirements associated with this finding.
Corrective Action Reference: IR 4127608
Performance Assessment:
Performance Deficiency: The failure to identify, validate, and incorporate a time-critical action
referenced in calculation PF-0016-025, in accordance with Sections 4.2 and 4.3 of
OP-AA-102-106, Operator Response Time Program is a performance deficiency.
Screening: The performance deficiency was more than minor because if left uncorrected, the
performance deficiency would have the potential to lead to a more significant safety concern.
The 10-minute requirement is not documented in the operator time response program;
therefore, training has not been conducted, operators did not recognize the time-critical
action, and future changes to the SE-10 procedure could result in challenging the 10-minute
requirement.
Significance: The inspectors assessed the significance of the finding using IMC 0609,
Appendix F, Fire Protection SDP. This issue screened to very low safety significance
(Green) in Phase 1, Step 1.3 as the procedure as currently written does not impact the ability
to achieve safe shutdown.
Cross-cutting Aspect: This finding had a cross-cutting aspect in the area of
Problem Identification and Resolution, Evaluation, because although Exelon included a
reference to the 1984 letter in the latest revision to the fire safe shutdown calculation, they did
not thoroughly evaluate the letter to ensure that any conditions and/or assumptions were
translated into the fire safe shutdown calculations and other station processes [P.2].
Enforcement: Inspectors did not identify a violation of regulatory requirements associated
with this finding.
Failure to Develop and Maintain Mitigating Strategy
Failure to Develop and Maintain Mitigating Strategy
Cornerstone
Cornerstone           Significance                                 Cross-cutting     Report
Significance
Aspect           Section
Cross-cutting Aspect Report Section Mitigating Systems Green  NCV 05000277, 05000278/2018010
Mitigating           Green                                        None              71111.05T
-02 Closed None 71111.05T The inspectors identified a Green non
Systems               NCV 05000277, 05000278/2018010-02
-cited violation of 10 CFR 50.54(hh)(2), "Conditions of Licenses," and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C
Closed
.(11), "Mitigation Strategy License Condition," because Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Specifically, Exelon did not adequately develop and maintain
The inspectors identified a Green non-cited violation of 10 CFR 50.54(hh)(2), Conditions of
procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves in the event of a challenge to the reactor due to a postulated large fire and/or explosion.
Licenses, and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License
Description
Condition 2.C.(11), Mitigation Strategy License Condition, because Exelon did not develop
: Exelon procedure EDMG 2.0, "Peach Bottom Operational Contingency Guidelines," provides the methods for implementation of strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Exelon procedure EDMG 2.0, Attachment 15, "Alternate 125 VDC Power Supply for Safety Relief Valve Operation," describes the station's strategy for supplying alternate power to the five automatic depressurization system safety relief valves. Figure 1 of this attachment
and maintain strategies for addressing large fires and explosions that include operations to
describes which
mitigate fuel damage. Specifically, Exelon did not adequately develop and maintain
procedures to manually depressurize the reactor using the automatic depressurization system
safety relief valves in the event of a challenge to the reactor due to a postulated large fire
and/or explosion.
Description: Exelon procedure EDMG 2.0, Peach Bottom Operational Contingency
Guidelines, provides the methods for implementation of strategies for addressing large fires
and explosions that include operations to mitigate fuel damage. Exelon procedure EDMG
2.0, Attachment 15, Alternate 125 VDC Power Supply for Safety Relief Valve Operation,
describes the stations strategy for supplying alternate power to the five automatic
depressurization system safety relief valves. Figure 1 of this attachment describes which
terminal points are to be used to accomplish this task.
terminal points are to be used to accomplish this task.
Since April 2008, Figure 1 has listed the incorrect terminal points for the  
Since April 2008, Figure 1 has listed the incorrect terminal points for the G and K safety
'G' and 'K' safety relief valves on both Unit 2 and Unit 3. Therefore, when an individual reached the step in the procedure to connect the jumpers for the  
relief valves on both Unit 2 and Unit 3. Therefore, when an individual reached the step in the
'G' and 'K' safety relief valves, they would be directed to terminal locations that did not exist. As a result, step 19 of the procedure, "Verify all five safety relief valve jumpers are connected at both ends, THEN continue," would not be able to be completed, and operators would likely not continue on with subsequent steps in the procedure. Because of this issue, inspectors determined that the procedure was not adequate to ensure that the strategy could be completed.
procedure to connect the jumpers for the G and K safety relief valves, they would be
Corrective Actions: Exelon documented this issue in the corrective action program and implemented a revision to the procedure to correct the error.
directed to terminal locations that did not exist. As a result, step 19 of the procedure,
Verify all five safety relief valve jumpers are connected at both ends, THEN continue,
would not be able to be completed, and operators would likely not continue on with
subsequent steps in the procedure. Because of this issue, inspectors determined that the
procedure was not adequate to ensure that the strategy could be completed.
Corrective Actions: Exelon documented this issue in the corrective action program and
implemented a revision to the procedure to correct the error.
Corrective Action Reference: IR 4125405
Corrective Action Reference: IR 4125405
Performance Assessment
Performance Assessment:
: Performance Deficiency: Exelon's failure to adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves, as required by 10 CFR 50.54(hh)(2) and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11), was a performance deficiency.
Performance Deficiency: Exelons failure to adequately develop and maintain procedures to
 
manually depressurize the reactor using the automatic depressurization system safety relief
Screening: This performance deficiency was more than minor because it is associated with the procedure quality attribute of the mitigating systems cornerstone and adversely affected the cornerstone objective
valves, as required by 10 CFR 50.54(hh)(2) and Peach Bottom Unit 2 and Unit 3 Renewed
to assure the availability, reliability, and capability of the automatic depressurization system safety relief valves to respond to an event. Specifically, failure to provide an adequate procedure to provide alternate power to the safety relief valves would impact the station's ability to open those valves to manually depressurize the reactor during an event. Significance:
Facility Operating License Condition 2.C.(11), was a performance deficiency.
The inspectors assessed the significance of this issue using IMC 0609, Appendix L, "B.5.b. Significance Determination Process," Table 2. The inspectors determined that the finding did not meet the criteria listed in Table 2 for greater than green significance, and therefore screened this finding as Green.
Screening: This performance deficiency was more than minor because it is associated with
Cross-cutting Aspect:
the procedure quality attribute of the mitigating systems cornerstone and adversely affected
No cross-cutting aspect was assigned to this finding because the inspectors determined that the finding did not reflect current plant performance.
the cornerstone objective to assure the availability, reliability, and capability of the automatic
Enforcement
depressurization system safety relief valves to respond to an event. Specifically, failure to
: Violation: 10 CFR 50.54(hh)(2) requires, in part, that each licensee shall develop
provide an adequate procedure to provide alternate power to the safety relief valves would
and implement guidance and strategies intended to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities under the circumstances associated with loss of large areas of the plant due to explosions or fire. Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C
impact the stations ability to open those valves to manually depressurize the reactor during
.(11) requires that Exelon develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Exelon procedure EDMG 2.0, "Peach Bottom Operational Contingency Guidelines," provides the methods for implementation of these strategies. EDMG 2.0, Attachment 15, "Alternate 125VDC Power Supply for Safety Relief Valve Operation," is the procedure for providing alternate power to the automatic depressurization system safety relief valves.
an event.
Contrary to the above, since April 2008, Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Specifically, EDMG 2.0, Attachment 15, was inadequate to ensure that the station would be able to open the automatic depressurization system relief valves from the containment penetrations via an alternate power supply to allow manual depressurization in the event of a challenge to the reactor due to a postulated large fire and/or explosion.
Significance: The inspectors assessed the significance of this issue using IMC 0609,
Disposition: This violation is being treated as a non
Appendix L, B.5.b. Significance Determination Process, Table 2. The inspectors determined
-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
that the finding did not meet the criteria listed in Table 2 for greater than green significance,
Licensee Identified Non
and therefore screened this finding as Green.
-Cited Violation
Cross-cutting Aspect: No cross-cutting aspect was assigned to this finding because the
71111.05T This violation of very low safety significan
inspectors determined that the finding did not reflect current plant performance.
ce was identified by Exelon and has been entered into Exelon's corrective action program and is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.
Enforcement:
Violation: Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(4) requires, in part, Exelon to implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Repor
Violation: 10 CFR 50.54(hh)(2) requires, in part, that each licensee shall develop and
t.  "Fire Protection Program, Peach Bottom Atomic Power Station, Units 2 and 3," is incorporated by reference
implement guidance and strategies intended to maintain or restore core cooling, containment,
into the Updated Final Safety Analysis Report, as discussed in Section 10.12 , "Fire Protection Program
and spent fuel pool cooling capabilities under the circumstances associated with loss of large
.Fire Protection Program Chapter 5.1, "Methodology," assumes that two or more circuit failures resulting in spurious operation of two or more valves in series at a high/low pressure interface may occur due to a postulated fire in any given area.
areas of the plant due to explosions or fire. Peach Bottom Unit 2 and Unit 3 Renewed Facility
Fire Protection Program Chapter 6.2, "Analysis of High/Low Pressure Interfaces," requires Exelon to address the situations for which the isolation valves at a given interface point consists of two electrically controlled valves in series and where the potential may
Operating License Condition 2.C.(11) requires that Exelon develop and maintain strategies for
exist for a single fire to cause damage to cables associated with both valves.
addressing large fires and explosions that include operations to mitigate fuel damage. Exelon
 
procedure EDMG 2.0, Peach Bottom Operational Contingency Guidelines, provides the
Contrary to above, as of March 14, 2018, Exelon identified they failed to evaluate two motor
methods for implementation of these strategies. EDMG 2.0, Attachment 15, Alternate
-operated valves in series, MO
25VDC Power Supply for Safety Relief Valve Operation, is the procedure for providing
-2-06-2663 and MO
alternate power to the automatic depressurization system safety relief valves.
-2-06-038B for Unit 2, and MO
Contrary to the above, since April 2008, Exelon did not develop and maintain strategies for
-3-06-3663 and MO-3-06-038B for Unit 3, where the potential may exist for a single fire to cause damage to cables associated with both valves. Specifically, a postulated fire scenario
addressing large fires and explosions that include operations to mitigate fuel damage.
could cause
Specifically, EDMG 2.0, Attachment 15, was inadequate to ensure that the station would be
spurious opening of the valves, which may potentially result in a fire
able to open the automatic depressurization system relief valves from the containment
-induced loss of coolant accident through the high/low pressure system interface. Exelon's evaluation identified the affected valves' cables are routed through Fire Area 6N for the Unit 2 valves, and Fire Area 13N for the Unit
penetrations via an alternate power supply to allow manual depressurization in the event of a
valves, and thus, a possibility exists for a single fire to cause damage to cables associated with both valves.
challenge to the reactor due to a postulated large fire and/or explosion.
This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.
Disposition: This violation is being treated as a non-cited violation, consistent with
Significance/Severity: The inspectors performed a Phase 2 Significance Determination Process screening for this issue, in accordance with IMC 0609, Appendix F, "Fire Protection Significance Determination Process.This finding affected the post
Section 2.3.2 of the Enforcement Policy.
-fire safe shutdown category because of spurious operations of safe shutdown components. Based on a walkdown of Fire Areas 6N and 13N, the inspectors did not identify any credible fire ignition source scenarios that could affect both Unit 2 motor
Licensee Identified Non-Cited Violation                                                 71111.05T
-operated valves or both Unit 3 motor operated valves.
This violation of very low safety significance was identified by Exelon and has been entered
Therefore, based upon task number 2.3.5, the inspectors determined that this finding screened to very low safety significance (Green).
into Exelons corrective action program and is being treated as an NCV, consistent with
Corrective Action References
Section 2.3.2 of the Enforcement Policy.
: IR 04115309, EC 623585, EC 623586
Violation: Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition
EXIT MEETING S AND DEBRIEFS
2.C.(4) requires, in part, Exelon to implement and maintain in effect all provisions of the
approved fire protection program as described in the Updated Final Safety Analysis Report.
Fire Protection Program, Peach Bottom Atomic Power Station, Units 2 and 3, is incorporated
by reference into the Updated Final Safety Analysis Report, as discussed in Section 10.12,
Fire Protection Program. Fire Protection Program Chapter 5.1, Methodology, assumes
that two or more circuit failures resulting in spurious operation of two or more valves in series
at a high/low pressure interface may occur due to a postulated fire in any given area.
Fire Protection Program Chapter 6.2, Analysis of High/Low Pressure Interfaces, requires
Exelon to address the situations for which the isolation valves at a given interface point
consists of two electrically controlled valves in series and where the potential may exist for a
single fire to cause damage to cables associated with both valves.
Contrary to above, as of March 14, 2018, Exelon identified they failed to evaluate two motor-
operated valves in series, MO-2-06-2663 and MO-2-06-038B for Unit 2, and MO-3-06-3663
and MO-3-06-038B for Unit 3, where the potential may exist for a single fire to cause damage
to cables associated with both valves. Specifically, a postulated fire scenario could cause
spurious opening of the valves, which may potentially result in a fire-induced loss of coolant
accident through the high/low pressure system interface. Exelons evaluation identified the
affected valves cables are routed through Fire Area 6N for the Unit 2 valves, and Fire Area
13N for the Unit 3 valves, and thus, a possibility exists for a single fire to cause damage to
cables associated with both valves. This violation is being treated as an NCV, consistent with
Section 2.3.2 of the Enforcement Policy.
Significance/Severity: The inspectors performed a Phase 2 Significance Determination
Process screening for this issue, in accordance with IMC 0609, Appendix F, Fire Protection
Significance Determination Process. This finding affected the post-fire safe shutdown
category because of spurious operations of safe shutdown components. Based on a
walkdown of Fire Areas 6N and 13N, the inspectors did not identify any credible fire ignition
source scenarios that could affect both Unit 2 motor-operated valves or both Unit 3 motor
operated valves. Therefore, based upon task number 2.3.5, the inspectors determined that
this finding screened to very low safety significance (Green).
Corrective Action References: IR 04115309, EC 623585, EC 623586
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
The inspectors verified no proprietary information was retained or documented in this report.
On April 20, 2018, the inspector presented the triennial fire protection team
On April 20, 2018, the inspector presented the triennial fire protection team inspection results to
inspection results to Mr. Pat Navin, Site Vice President, and other members of the Exelon staff.
Mr. Pat Navin, Site Vice President, and other members of the Exelon staff.
DOCUMENTS REVIEWED
DOCUMENTS REVIEWED
71111.05T Fire Protection Licensing and Design Basis Documents
71111.05T
Fire Protection Licensing and Design Basis Documents
Letter from PECO (
Letter from PECO (
: [[contact::V.S. Boyer) to USNRC (Darrell Eisenhut)]], Peach Bottom Atomic Power Station Alternate Shutdown, dated 8/16/84 NE-00296, Post
: [[contact::V.S. Boyer) to USNRC (Darrell Eisenhut)]], Peach Bottom Atomic
-Fire Safe Shutdown Program Requirements at PBAPS, Revision 4
Power Station Alternate Shutdown, dated 8/16/84
NE-00296, Post-Fire Safe Shutdown Program Requirements at PBAPS, Revision 4
NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 10/3/91
NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 10/3/91
NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 3/13/85
NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 3/13/85
NRC Safety Evaluation Report, Fire Protection Program, dated 5/23/79
NRC Safety Evaluation Report, Fire Protection Program, dated 5/23/79
NRC Safety Evaluation Report, Fire Protection Program, Supplement 1, dated 8/14/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 1, dated 8/14/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 2, dated 9/15/80 NRC Safety Evaluation Report, Fire Protection Program, Supplement 3, dated 10/10/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 2, dated 9/15/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 3, dated 10/10/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 4, dated 11/24/80
NRC Safety Evaluation Report, Fire Protection Program, Supplement 4, dated 11/24/80
Peach Bottom Atomic Power Station Fire Protection Program, Revision 17
Peach Bottom Atomic Power Station Fire Protection Program, Revision 17
Peach Bottom Atomic Power Station, Units 2 and 3  
Peach Bottom Atomic Power Station, Units 2 and 3 - Issuance of Amendment
- Issuance of Amendment
RE: Fire Protection Program Changes, dated 6/24/05
RE: Fire Protection Program Changes, dated 6/24/05
P-T-10, Fire Safe Shutdown, Revision 13
P-T-10, Fire Safe Shutdown, Revision 13
Safety Evaluation by the Office of Nuclear Reactor Regulation Related to Order No. EA
Safety Evaluation by the Office of Nuclear Reactor Regulation Related to Order No. EA-02-026,
-02-026, Exelon Generation Company, LLC, Peach Bottom Atomic Power Station, Units 2 and 3, dated 8/9/07 Calculations, Analysis, and Engineering Evaluations
Exelon Generation Company, LLC, Peach Bottom Atomic Power Station, Units 2 and 3,
CFR 50.59 Safety Review for Modification P00680, Fire Detection and Suppression System for Switchgear and Battery Rooms, Revision 1
dated 8/9/07
EC 623620, Alternate Compensatory Measure for IR 4115309 Hi/Lo Interface Not Evaluated for Appendix R, dated 3/22/18
Calculations, Analysis, and Engineering Evaluations
Fire Endurance Test on Silicone Foam Penetration Seal in a Masonry Floor, Design FC
CFR 50.59 Safety Review for Modification P00680, Fire Detection and Suppression System
-270, dated 12/14/78
for Switchgear and Battery Rooms, Revision 1
EC 623620, Alternate Compensatory Measure for IR 4115309 Hi/Lo Interface Not Evaluated for
Appendix R, dated 3/22/18
Fire Endurance Test on Silicone Foam Penetration Seal in a Masonry Floor, Design FC-270,
dated 12/14/78
PEAF-EPU-001, T0611 Appendix R Fire Protection, Revision 5
PEAF-EPU-001, T0611 Appendix R Fire Protection, Revision 5
PEAM-MUR-0611, Appendix R Fire Protection T0611, Revision 0
PEAM-MUR-0611, Appendix R Fire Protection T0611, Revision 0
PF-0007, Combustible Loading Analysis, Revision 0
PF-0007, Combustible Loading Analysis, Revision 0
PF-0007, Combustible Loading Analysis, Revision 4
PF-0007, Combustible Loading Analysis, Revision 4
PF-0016-002, Fire Area 002  
PF-0016-002, Fire Area 002 - Fire Safe Shutdown Analysis, Revision 1
- Fire Safe Shutdown Analysis, Revision 1
PF-0016-013N, Fire Area 013N - Fire Safe Shutdown Analysis, Revision 1
PF-0016-013N, Fire Area 013N  
PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 000V
- Fire Safe Shutdown Analysis, Revision 1
PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 1
PF-0016-025, Fire Area 025  
PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 2
- Fire Safe Shutdown Analysis, Revision 000V
PF-0016-036, Fire Area 036 - Fire Safe Shutdown Analysis, Revision 1
PF-0016-025, Fire Area 025  
PF-0019, Fire Protection Hydraulic Calculation - Units 2 and 3 Sprinkler System for the 4
- Fire Safe Shutdown Analysis, Revision 1
PF-0016-025, Fire Area
25 - Fire Safe Shutdown Analysis, Revision 2
PF-0016-036, Fire Area 036  
- Fire Safe Shutdown Analysis, Revision 1
PF-0019, Fire Protection Hydraulic Calculation
- Units 2 and 3 Sprinkler System for the
Kilo-Volt Switchgear Rooms, Battery Rooms, and Access Corridor, Revision 0
Kilo-Volt Switchgear Rooms, Battery Rooms, and Access Corridor, Revision 0
PF-0020, Fire Protection Hydraulic Calculation
PF-0020, Fire Protection Hydraulic Calculation - Units 2 and 3 Main Fan Room (#381)
- Units 2 and 3 Main Fan Room (#381) Hydraulic Calculation, Revision 0
Hydraulic Calculation, Revision 0
T-061-VC-1, Assessment of the Fire Protection Sprinkler and Hose Station Supply Piping, Revision 0
T-061-VC-1, Assessment of the Fire Protection Sprinkler and Hose Station Supply Piping,
 
Revision 0
Drawings and Wiring Diagrams
Drawings and Wiring Diagrams
280-E-2890, Emergency DC Lighting Layout Alternate Control Stations, Revision 1
280-E-2890, Emergency DC Lighting Layout Alternate Control Stations, Revision 1
280-M-318, Piping and Instrumentation Drawing, Fire Protection System, Revision 70
280-M-318, Piping and Instrumentation Drawing, Fire Protection System, Revision 70
280-M-359, Sheet 1, Piping and Instrumentation Drawing
280-M-359, Sheet 1, Piping and Instrumentation Drawing Reactor Core Isolation Cooling
Reactor Core Isolation Cooling System, Revision 50
System, Revision 50
280-M-359, Sheet 2, Piping and Instrumentation Drawing
280-M-359, Sheet 2, Piping and Instrumentation Drawing Reactor Core Isolation Cooling
Reactor Core Isolation Cooling System, Revision 48
System, Revision 48
280-NE-75-1, Penetration Seal Details NE
280-NE-75-1, Penetration Seal Details NE-378545, Revision 1
-378545, Revision 1
280-NE-75-1, Sheet 19, Pipe or Conduit through 3-Hour Rated Fire Barrier, Revision 1
280-NE-75-1, Sheet 19, Pipe or Conduit through 3
737-D-VC-72, Thermo-Lag Upgrade Fire Barrier 78H-02, Revision 0
-Hour Rated Fire Barrier, Revision 1
A-484, Barrier Plans, Elevation 91 6, Revision 8
737-D-VC-72, Thermo
A-485, Barrier Plans, Elevation 116 0 Sheets 1 and 2, Revisions 8 and 4
-Lag Upgrade Fire Barrier 78H
A-486, Barrier Plans, Elevation 135 0 Sheets 1 and 2, Revisions 11 and 1
-02, Revision 0
A-487, Barrier Plans, Elevation 165 0 Sheets 1 and 2, Revisions 13 and 1
A-484, Barrier Plans, Elevation 91' 6", Revision 8
A-485, Barrier Plans, Elevation 116' 0" Sheets 1 and 2, Revisions 8 and 4
A-486, Barrier Plans, Elevation 135' 0" Sheets 1 and 2, Revisions 11 and 1
A-487, Barrier Plans, Elevation 165' 0" Sheets 1 and 2, Revisions 13 and 1
C-49, Fire System Underground Yard Plan, Revision 25
C-49, Fire System Underground Yard Plan, Revision 25
E-1, Sheet 1, Single Line Diagram Station, Revision 57
E-1, Sheet 1, Single Line Diagram Station, Revision 57
E-12, Sheet 1, 4160 V Emergency Power System Unit 3, Revision 11
E-12, Sheet 1, 4160 V Emergency Power System Unit 3, Revision 11
E-1321, Sheet 3, Electrical Secondary and Control Connections Drywell Penetrations N
E-1321, Sheet 3, Electrical Secondary and Control Connections Drywell Penetrations N-106A,
-106A, B, C, D - Indication and Control, Unit 2, Revision 31
B, C, D - Indication and Control, Unit 2, Revision 31
E-1715, Sheet 1, E134 & E234 Emer. L.C., Revision 83
E-1715, Sheet 1, E134 & E234 Emer. L.C., Revision 83
E-1717, Sheet 1, E334 & E434
E-1717, Sheet 1, E334 & E434 Emer. L.C., Revision 72
Emer. L.C., Revision 72
E-184, Sheet 2, Electrical Schematic Diagram RHR Pump 4.16 kV Circuit Breaker, Revision 27
E-184, Sheet 2, Electrical Schematic Diagram RHR Pump 4.16 kV Circuit Breaker, Revision 27
E-193, Sheet 3, Electrical Schematic Diagram Emergency Auxiliary Switchgear Diesel
E-193, Sheet 3, Electrical Schematic Diagram Emergency Auxiliary Switchgear Diesel-
-Generator 4160V Circuit Breaker, Revision 32
Generator 4160V Circuit Breaker, Revision 32
E-2371, Sheet 1, Riser Diagram Distributed Antenna System, Revision 4
E-2371, Sheet 1, Riser Diagram Distributed Antenna System, Revision 4
E-2903, Sheet 1, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 6
E-2903, Sheet 1, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 6
E-2903, Sheet 3, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 0
E-2903, Sheet 3, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 0
E-8, Sheet 1, 4160V Emergency Power System Unit 2, Revision 20
E-8, Sheet 1, 4160V Emergency Power System Unit 2, Revision 20
M-1-S-36, Sheet 20, Electrical Schematic Diagram High Pressure Coolant Injection System, Revision 78
M-1-S-36, Sheet 20, Electrical Schematic Diagram High Pressure Coolant Injection System,
M-1-S-42, Sheet 13, Electrical Schematic Diagram Reactor Core Isolation Cooling System, Revision 74
Revision 78
M-1-S-42, Sheet 18, Electrical Schematic Diagram Reactor Core Isolation Cooling System, Revision 79
M-1-S-42, Sheet 13, Electrical Schematic Diagram Reactor Core Isolation Cooling System,
M-1-S-42, Sheet 5, Electrical Schematic Diagram Reactor Core Isolation Cooling System, Revision 87
Revision 74
M-1-S-42, Sheet 7, Electrical Schematic Diagram Reactor Core Isolation Cooling System, Revision 76
M-1-S-42, Sheet 18, Electrical Schematic Diagram Reactor Core Isolation Cooling System,
Revision 79
M-1-S-42, Sheet 5, Electrical Schematic Diagram Reactor Core Isolation Cooling System,
Revision 87
M-1-S-42, Sheet 7, Electrical Schematic Diagram Reactor Core Isolation Cooling System,
Revision 76
M-1-S-65, Sheet 45, Electrical Schematic Diagram Residual Heat Removal System, Revision 97
M-1-S-65, Sheet 45, Electrical Schematic Diagram Residual Heat Removal System, Revision 97
M-1-S-65, Sheet 53, Electrical Schematic Diagram Residual Heat Removal System, Revision 99
M-1-S-65, Sheet 53, Electrical Schematic Diagram Residual Heat Removal System, Revision 99
M-1-S-65, Sheet 62, Electrical Schematic Diagram Residual Heat Removal System, Revision 103 PD-27, Sheet 1, Typical Penetration Seal Detail Grout Seal, Revision 1
M-1-S-65, Sheet 62, Electrical Schematic Diagram Residual Heat Removal System,
PD-5, Sheet 1, Typical Penetration Seal Detail External Pipe or Conduit Seal (SF
Revision 103
-20), Revision
PD-27, Sheet 1, Typical Penetration Seal Detail Grout Seal, Revision 1
PD-7, Typical Penetration Seal Detail, Cable Tray Wall Seal (SF
PD-5, Sheet 1, Typical Penetration Seal Detail External Pipe or Conduit Seal (SF-20), Revision
-20), Revision 1
PD-7, Typical Penetration Seal Detail, Cable Tray Wall Seal (SF-20), Revision 1
PD-9, Typical Penetration Seal Detail, Penetration through Barrier Less Than Required Thickness, Revision 0
PD-9, Typical Penetration Seal Detail, Penetration through Barrier Less Than Required
PS-301, Penetration Seal Locations, Controlled Barriers
Thickness, Revision 0
-Room No. 301, Units 2 and 3, Area 3, Elevation 150' 0", Revision 1
PS-301, Penetration Seal Locations, Controlled Barriers-Room No. 301, Units 2 and 3, Area 3,
PS-302, Penetration Seal Locations, Controlled Barriers
Elevation 150 0, Revision 1
-Room No. 302, Units 2 and 3, Area 3, Elevation 150' 0", Revision 2
PS-302, Penetration Seal Locations, Controlled Barriers-Room No. 302, Units 2 and 3, Area 3,
 
Elevation 150 0, Revision 2
PS-444, Sheet 1, Penetration Seal Locations Controlled Barriers  
PS-444, Sheet 1, Penetration Seal Locations Controlled Barriers - Room No. 444 Unit 3,
- Room No. 444 Unit 3, Revision 0
Revision 0
PS-444, Sheet 2, Penetration Seal Locations Controlled Barriers  
PS-444, Sheet 2, Penetration Seal Locations Controlled Barriers - Room No. 444 Unit 3,
- Room No. 444 Unit 3, Revision 1
Revision 1
Fire Protection Evaluations of Modifications and Design Changes
Fire Protection Evaluations of Modifications and Design Changes
2321, Generic Letter 86
2321, Generic Letter 86-10 Evaluation - Post Fire Operation of Manual Valves
-10 Evaluation  
23620, Alternate Compensatory Measure for IR 4115309, HI/LO Interface Not Evaluated for
- Post Fire Operation of Manual Valves
Appendix R
23620, Alternate Compensatory Measure for IR 4115309, HI/LO Interface Not Evaluated for Appendix R
3968258, Generic Letter 86-10 Evaluation Supporting Configuration of Penetration
3968258, Generic Letter
RW2-116-105-3039
86-10 Evaluation Supporting Configuration of Penetration
Quality Assurance Audits and Self Assessments
RW 2-116-105-3039 Quality Assurance Audits and Self Assessments
AR 3994319, 2018 Triennial Fire Protection Inspection Preparatory Self-Assessment
AR 3994319, 2018 Triennial Fire Protection Inspection Preparatory Self
-Assessment
Procedures
Procedures
AO 54.2, 4KV Breaker Manual Operation, Revision 0
AO 54.2, 4KV Breaker Manual Operation, Revision 0
CC-AA-209-1001, Guidelines for Performing Fire Protection Program Configuration Change Review, Revision 2
CC-AA-209-1001, Guidelines for Performing Fire Protection Program Configuration Change
Review, Revision 2
CC-AA-211, Fire Protection Program, Revision 8
CC-AA-211, Fire Protection Program, Revision 8
CC-AA-211-1001, Fire Protection Engineering Evaluations, Revision 2
CC-AA-211-1001, Fire Protection Engineering Evaluations, Revision 2
EDMG-1.0, Extensive Damage Mitigation Guideline for Loss of Large Area of the Plant, Revision 1
EDMG-1.0, Extensive Damage Mitigation Guideline for Loss of Large Area of the Plant,
Revision 1
EDMG-2.0, Peach Bottom Operational Contingency Guidelines, Revision 8
EDMG-2.0, Peach Bottom Operational Contingency Guidelines, Revision 8
ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump, Inner Screen or Emergency Cooling Tower Structures, Revision 21
ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump,
ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump, Inner Screen or Emergency Cooling Tower Structures  
Inner Screen or Emergency Cooling Tower Structures, Revision 21
- Bases, Revision 20
ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump,
ON-115, Loss of Normal Main Control Room Ventilation  
Inner Screen or Emergency Cooling Tower Structures - Bases, Revision 20
- Bases, Revision 19
ON-115, Loss of Normal Main Control Room Ventilation - Bases, Revision 19
ON-115, Loss of Normal Main Control Room Ventilation  
ON-115, Loss of Normal Main Control Room Ventilation - Procedure, Revision 22
- Procedure, Revision 22
OP-AA-102-106, Operator Response Time Program, Revision 4
OP-AA-102-106, Operator Response Time Program, Revision 4
OP-AA-201-003, Fire Drill Performance, Revision 16
OP-AA-201-003, Fire Drill Performance, Revision 16
Line 941: Line 992:
SE-10, Alternate Shutdown, Attachment 6, Revision 8A
SE-10, Alternate Shutdown, Attachment 6, Revision 8A
SE-10, Alternate Shutdown, Attachment 9, Revision 3
SE-10, Alternate Shutdown, Attachment 9, Revision 3
SE-10, Plant Shutdown from the Alternate Shutdown Panels  
SE-10, Plant Shutdown from the Alternate Shutdown Panels - Bases, Revision 29
- Bases, Revision 29
T-100, Scram - Bases, Revision 15
 
T-100, Scram, Revision 11
T-100, Scram  
T-302-2, Area 02 Fire Guide, Revision 10
- Bases, Revision 15
T-100, Scram, Revision 11 T-302-2, Area 02 Fire Guide, Revision 10
T-302-3, Area 02 Fire Guide, Revision 9
T-302-3, Area 02 Fire Guide, Revision 9
T-313N-2, Area 13N Fire Guide, Revision 4
T-313N-2, Area 13N Fire Guide, Revision 4
Line 952: Line 1,001:
T-325-2, Area 25 Fire Guide, Revision 1
T-325-2, Area 25 Fire Guide, Revision 1
T-325-3, Area 25 Fire Guide, Revision 1
T-325-3, Area 25 Fire Guide, Revision 1
T-3 36-2, Area 36 Fire Guide, Revision 4
T-336-2, Area 36 Fire Guide, Revision 4
T-336-3, Area 36 Fire Guide, Revision 4
T-336-3, Area 36 Fire Guide, Revision 4
TSG 4.1, Attachment 15, Alternate 125VDC Power Supply for SRV Operation, Revision 6
TSG 4.1, Attachment 15, Alternate 125VDC Power Supply for SRV Operation, Revision 6
Line 958: Line 1,007:
Operator Safe Shutdown Training
Operator Safe Shutdown Training
DBIG PNLO-3106, SE-10, Plant Shutdown from the Alternate Shutdown Panels, Revision 3
DBIG PNLO-3106, SE-10, Plant Shutdown from the Alternate Shutdown Panels, Revision 3
JPM PLOR-047C, Take Action for Control Room Evacuation (SE
JPM PLOR-047C, Take Action for Control Room Evacuation (SE-10 Attachment 6), Revision 11
-10 Attachment 6), Revision 11
JPM PLOR-057P, Plant Shutdown from Alternate Shutdown Panel - HPCI Operations,
JPM PLOR-057P, Plant Shutdown from Alternate Shutdown Pa
Revision 8
nel - HPCI Operations, Revision 8 PLORT-1605A, Fire Protection and Appendix R, Revision 0
PLORT-1605A, Fire Protection and Appendix R, Revision 0
PLOT-1565, PBAPS Transient Response Implementation Procedures (T
PLOT-1565, PBAPS Transient Response Implementation Procedures (T-300 Series), Revision 2
-300 Series), Revision 2
PLOT-5037X, Remote Shutdown Panel & Fire Safe Shutdown/Alternate Panel Controls,
PLOT-5037X, Remote Shutdown Panel & Fire Safe Shutdown/Alternate Panel Controls, Revision 4
Revision 4
PLOT-6000, Licensed Operator Initial Qualification Manual, Revision 22
PLOT-6000, Licensed Operator Initial Qualification Manual, Revision 22
PLOT-6000A, Licensed Operator Initial OJT Module (RO Tasks), Revision 1
PLOT-6000A, Licensed Operator Initial OJT Module (RO Tasks), Revision 1
PLOT-6000B, Licensed Operator Initial OJT Module (EO Tasks), Revision 1
PLOT-6000B, Licensed Operator Initial OJT Module (EO Tasks), Revision 1
PLOT-6000C, Licensed Operator
PLOT-6000C, Licensed Operator Initial OJT Module (SRO Tasks) Revision 1
Initial OJT Module (SRO Tasks) Revision 1
PNLO-2215, Effects of Fire on Safe Shutdown Equipment, Revision 5
PNLO-2215, Effects of Fire on Safe Shutdown Equipment, Revision 5
PNLO-6000E, Equipment Operator Initial Qualification Manual, Revision 3
PNLO-6000E, Equipment Operator Initial Qualification Manual, Revision 3
Simulator Exercise Guide PSEG
Simulator Exercise Guide PSEG-0409R-03, Fire in Cable Spreading Room, Revision 0
-0409R-03, Fire in Cable Spreading Room, Revision 0 Pre-Fire Plans
Pre-Fire Plans
FF-01, Fire Fighting Plan, Revision 23
FF-01, Fire Fighting Plan, Revision 23
PF-0, Pre-Fire Strategy Plan Area and Location Index, Revision 9
PF-0, Pre-Fire Strategy Plan Area and Location Index, Revision 9
PF-108, Pre-Fire Plan, Radioactive Waste Building, Fan Room, Elevation 165' 0", Revision PF-127, Pre-Fire Plan, Unit 2 Turbine Building, Emergency Battery Switchgear Rooms, Elevation 135' 0", Revision 10
PF-108, Pre-Fire Plan, Radioactive Waste Building, Fan Room, Elevation 165 0,
PF-12B, Pre-Fire Plan, Unit 2 Reactor Building Closed Loop Cooling Water Room, Elevation 116' 0", Revision 8
Revision PF-127, Pre-Fire Plan, Unit 2 Turbine Building, Emergency Battery Switchgear
PF-13J, Pre-Fire Plan, Unit 2 Reactor Building General Area, Elevation 165' 0", Revision 3
Rooms, Elevation 135 0, Revision 10
PF-12B, Pre-Fire Plan, Unit 2 Reactor Building Closed Loop Cooling Water Room,
Elevation 116 0, Revision 8
PF-13J, Pre-Fire Plan, Unit 2 Reactor Building General Area, Elevation 165 0, Revision 3
Fire Brigade Training
Fire Brigade Training
FBP04, Fire Behavior and Essentials, Revision 8
FBP04, Fire Behavior and Essentials, Revision 8
Line 985: Line 1,036:
Fire Brigade Member Qualification Status Report, dated 4/5/18
Fire Brigade Member Qualification Status Report, dated 4/5/18
FPB11, Tactics and Strategy, Revision 7
FPB11, Tactics and Strategy, Revision 7
FPB15, Pre
FPB15, Pre-Fire Plans, Revision 6
-Fire Plans, Revision 6
IMS-01, Incident Management System, Revision 2
IMS-01, Incident Management System, Revision 2
PNLOC 1612A, 4
PNLOC 1612A, 4th Quarter Fire Brigade Meeting, Revision 0
th Quarter Fire Brigade Meeting, Revision 0
 
Fire Brigade Drills and Critiques
Fire Brigade Drills and Critiques
Fire Brigade Drill Third Party Observation Report, performed on 12/7/17
Fire Brigade Drill Third Party Observation Report, performed on 12/7/17
N-PB-OPS-EO-FB-DRILL1, PS01 4
N-PB-OPS-EO-FB-DRILL1, PS01 4th Quarter Fire Drill and Critique, performed on 12/13/17
th Quarter Fire Drill and Critique, performed on 12/13/17
N-PB-OPS-EO-FB-DRILL1, PS02 4th Quarter Fire Drill and Critique, performed on 12/15/17
N-PB-OPS-EO-FB-DRILL1, PS02 4
N-PB-OPS-EO-FB-DRILL1, PS04 4th Quarter Fire Drill and Critique, performed on 12/7/17
th Quarter Fire Drill and Critique, performed on 12/15/17
N-PB-OPS-EO-FB-DRILL1, PS05 1st Quarter Unannounced, Backshift Fire Drill and Critique,
N-PB-OPS-EO-FB-DRILL1, PS04 4
performed on 3/22/17
th Quarter Fire Drill and Critique, performed on 12/7/17
N-PB-OPS-EO-FB-DRILL1, PS05 4th Quarter Fire Drill and Critique, performed on 12/22/17
N-PB-OPS-EO-FB-DRILL1, PS05 1
st Quarter Unannounced, Backshift Fire Drill and Critique, performed on 3/22/17
N-PB-OPS-EO-FB-DRILL1, PS05 4
th Quarter Fire Drill and Critique, performed on 12/22/17
Transient Combustible, Hot Work, and Ignition Source Permits and Evaluations
Transient Combustible, Hot Work, and Ignition Source Permits and Evaluations
Hot Work Permit 0611, RTV
Hot Work Permit 0611, RTV-2-14-29010A, Rework Valve/Replace Bonnet, dated 3/1/18
-2-14-29010A, Rework Valve/Replace Bonnet, dated 3/1/18
Hot Work Permit 0680, Install New Heat Exchanger, dated 12/11/18
Hot Work Permit 0680, Install New Heat Exchanger, dated 12/11/18
Transient Combustible Permit 1070, Units 2 and 3 Turbine Building, Fire Zone 50
Transient Combustible Permit 1070, Units 2 and 3 Turbine Building, Fire Zone 50-78A,
-78A, Temporary Power
Temporary Power
Transient Combustible Permit 1071, Unit 3 Turbine Building, Fire Zone 50
Transient Combustible Permit 1071, Unit 3 Turbine Building, Fire Zone 50-78T, Temporary
-78T, Temporary Power Transient Combustible Permit 1072, Unit 2 Reactor Building, Fire Zone 1
Power
-2, Temporary Power
Transient Combustible Permit 1072, Unit 2 Reactor Building, Fire Zone 1-2, Temporary Power
Transient Combustible Permit 1073, Emergency Cooling Tower, Fire Zone 51
Transient Combustible Permit 1073, Emergency Cooling Tower, Fire Zone 51-136, Test
-136, Test Equipment Transient Combustible Permit 1075, E
Equipment
-42 Switchgear Room, Fire Zone 36
Transient Combustible Permit 1075, E-42 Switchgear Room, Fire Zone 36-123, Temporary
-123, Temporary Instrumentation and Cabling
Instrumentation and Cabling
Completed Tests and Surveillances
Completed Tests and Surveillances
R1302419-01, Calibration Check of Alternative Shutdown Panel Reactor Vessel Level Instruments, completed 10/25/16
R1302419-01, Calibration Check of Alternative Shutdown Panel Reactor Vessel Level
Instruments, completed 10/25/16
RT-0-052-750-2, E2 Diesel Alternative Shutdown Control Functional, completed 3/21/16
RT-0-052-750-2, E2 Diesel Alternative Shutdown Control Functional, completed 3/21/16
RT-M-57E-700-2, Main Control Room Emergency Lighting Battery Yearly Inspection (20 D 304-2), completed 1/24/17
RT-M-57E-700-2, Main Control Room Emergency Lighting Battery Yearly Inspection
RT-M-57E-700-3, Main Control Room Emergency Lighting Battery Yearly Inspection  
        (20D304-2), completed 1/24/17
(30 D 304-2), completed 1/24/17
RT-M-57E-700-3, Main Control Room Emergency Lighting Battery Yearly Inspection
RT-M-57E-710-2, Main Control Room Emergency Lighting Battery Discharge Performance Test (20D304-2), completed 8/11/17
        (30D304-2), completed 1/24/17
R T-M-57E-710-3, Main Control Room Emergency Lighting Battery Discharge Performance Test (30D304-2), completed 1/22/18
RT-M-57E-710-2, Main Control Room Emergency Lighting Battery Discharge Performance Test
RT-O-037-375-2, In-Plant Fire Brigade Equipment Inventory and Inspection, completed 2/5/2018 RT-O-037-376-2, Outside Fire Brigade Equipment Inventory and Inspection, completed 2/10/2018 RT-O-037-710-2, Complete Safe Shutdown Emergency Lighting Battery Pack Inspection , completed 2/10/18
        (20D304-2), completed 8/11/17
RT-O-037-719-2, Emergency Lighting Inspection (Alternate Shutdown Control Station Access
RT-M-57E-710-3, Main Control Room Emergency Lighting Battery Discharge Performance Test
/ Egress Lights), completed 11/2/16
        (30D304-2), completed 1/22/18
RT-O-037-719-3, Emergency Lighting Inspection (Alternate Shutdown Control Station Access
RT-O-037-375-2, In-Plant Fire Brigade Equipment Inventory and Inspection, completed
/ Egress Lights), completed 11/6/17
2/5/2018
RT-O-037-376-2, Outside Fire Brigade Equipment Inventory and Inspection, completed
2/10/2018
RT-O-037-710-2, Complete Safe Shutdown Emergency Lighting Battery Pack Inspection,
completed 2/10/18
RT-O-037-719-2, Emergency Lighting Inspection (Alternate Shutdown Control Station Access/
Egress Lights), completed 11/2/16
RT-O-037-719-3, Emergency Lighting Inspection (Alternate Shutdown Control Station Access/
Egress Lights), completed 11/6/17
RT-O-100-505-2, Emergency Operating Procedure Tool Inventory, completed 12/6/17
RT-O-100-505-2, Emergency Operating Procedure Tool Inventory, completed 12/6/17
RT-O-100-580-2, B.5.b Tool and Material Inventory, completed 8/2/2017
RT-O-100-580-2, B.5.b Tool and Material Inventory, completed 8/2/2017
ST-I-037-223-2, Unit 2 4 Kilo
ST-I-037-223-2, Unit 2 4 Kilo-Volt Switchgear and Battery Room and Radwaste 135 Corridor
-Volt Switchgear and Battery Room and Radwaste 135' Corridor Smoke Detectors Functional Test, completed 6/3/15
Smoke Detectors Functional Test, completed 6/3/15
ST-I-037-223-2, Unit 2 4 Kilo
ST-I-037-223-2, Unit 2 4 Kilo-Volt Switchgear and Battery Room and Radwaste 135 Corridor
-Volt Switchgear and Battery Room and Radwaste 135' Corridor Smoke Detectors Functional Test, completed 8/3/17
Smoke Detectors Functional Test, completed 8/3/17
ST-I-037-276-3, Reactor Building Elevation 165' Smoke Detectors Functional Test, completed 1/27/15
ST-I-037-276-3, Reactor Building Elevation 165 Smoke Detectors Functional Test, completed
ST-I-037-276-3, Reactor Building Elevation 165' Smoke Detectors Functional Test, completed 7/28/1 7 ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional Test, completed 6/23/15
1/27/15
ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional Test, completed 1/13/17
ST-I-037-276-3, Reactor Building Elevation 165 Smoke Detectors Functional Test, completed
7/28/17
ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional
Test, completed 6/23/15
ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional
Test, completed 1/13/17
ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 10/20/16
ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 10/20/16
ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 6/22/17
ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 6/22/17
ST-I-037-293-2, Recirculation Motor
ST-I-037-293-2, Recirculation Motor-Generator Set Lube Oil Pump 116 Smoke Detectors
-Generator Set Lube Oil Pump 116' Smoke Detectors Functional Test, completed 5/11/17
Functional Test, completed 5/11/17
ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air Flow Test, completed 10/10/17
ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air
ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air Flow Test, completed 5/31/16
Flow Test, completed 10/10/17
ST-I-0 37A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air Flow Test, completed 10/10/17
ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air
ST-M-037-311-2, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire Barriers, completed 6/8/12
Flow Test, completed 5/31/16
ST-M-037-311-3, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire Barriers, completed 12/21/17
ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air
Flow Test, completed 10/10/17
ST-M-037-311-2, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire
Barriers, completed 6/8/12
ST-M-037-311-3, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire
Barriers, completed 12/21/17
ST-M-037-314-2, Visual Inspection of Encapsulated Electrical Raceways, completed 6/14/16
ST-M-037-314-2, Visual Inspection of Encapsulated Electrical Raceways, completed 6/14/16
ST-M-037D-380-2, Diesel Driven Fire Pump Inspection, completed 1/1/17 ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165') Sprinkler System Actuation, completed 3/14/16
ST-M-037D-380-2, Diesel Driven Fire Pump Inspection, completed 1/1/17
ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165') Sprinkler System Actuation, completed 3/25/18
ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165) Sprinkler System
ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Ki
Actuation, completed 3/14/16
lo-Volt Switchgear Rooms, and Radwaste Corridor Area Sprinkler System Actuation, completed 7/10/14
ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165) Sprinkler System
ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Kilo
Actuation, completed 3/25/18
-Volt Switchgear Rooms, and Radwaste Corridor Area Sprinkler System Actuation, completed 7/9/16
ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Kilo-Volt Switchgear Rooms, and Radwaste Corridor
Area Sprinkler System Actuation, completed 7/10/14
ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Kilo-Volt Switchgear Rooms, and Radwaste Corridor
Area Sprinkler System Actuation, completed 7/9/16
ST-O-037B-381-2, Underground Fire Main Flow Test, completed 6/10/15
ST-O-037B-381-2, Underground Fire Main Flow Test, completed 6/10/15
ST-O-037B-381-2, Underground Fire Main Flow Test, completed 8/8/14
ST-O-037B-381-2, Underground Fire Main Flow Test, completed 8/8/14
ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, completed 8/6/15
ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, completed 8/6/15
ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, complete
ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, completed 12/13/16
d 12/13/16 ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 1/23/18
ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 1/23/18
ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 2/21/18
ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 2/21/18
ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 11/25/15
ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 11/25/15
ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 1/17/17
ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 1/17/17
ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed 1/9/18
ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed 1/9/18
ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed
ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed 2/7/18
2/7/18 Issue Reports
Issue Reports (* written as a result of the NRC inspection)
(* written as a result of the NRC inspection
00450846           01109076             01275720         01492237           01521603
) 00450846 01109076 01275720 01492237 01521603 01581135 02386737 02421301 02451017 02451647 02478057 02661579 02697843 02699896 02718710 03962962 03980676 04000043 04080702 04082065 04084069 04084077 04102768 04115309 04118443 04122474* 04122883* 04122970* 04127608* 04128972* 04129171*
01581135           02386737             02421301         02451017           02451647
2478057            02661579             02697843         02699896           02718710
03962962           03980676             04000043         04080702           04082065
04084069           04084077             04102768         04115309           04118443
04122474*           04122883*           04122970*         04127608*         04128972*
04129171*
Work Orders
Work Orders
4319703 4595771 4648804 R1298970 R1326279 Operating Experience
4319703             4595771           4648804             R1298970           R1326279
NRC Information Notice
Operating Experience
1997-48, Inadequate or Inappropriate Interim Fire Protection Compensatory Measures
NRC Information Notice 1997-48, Inadequate or Inappropriate Interim Fire Protection
NRC Information
Compensatory Measures
Notice 2013
NRC Information Notice 2013-02, Issues Potentially Affecting Nuclear Facility Fire Safety
-02, Issues Potentially Affecting Nuclear Facility Fire Safety
NRC Information Notice 2013-06, Corrosion in Fire Protection Piping Due to Air and Water
NRC Information Notice 2013
Interaction
-06, Corrosion in Fire Protection Piping Due to Air and Water Interaction
NRC Information Notice 2013-09, Compressed Flammable Gas Cylinders and Associated
NRC Information Notice 2013
Hazards
-09, Compressed Flammable Gas Cylinders and Associate
NRC Information Notice 2014-10, Potential Circuit Failure-Induced Secondary Fires or
d Hazards NRC Information Notice 2014
Equipment Damage
-10, Potential Circuit Failure
NRC Information Notice 2014-15, Inadequate Controls of Respiratory Protection Accessibility,
-Induced Secondary Fires or Equipment Damage
Training, and Maintenance
NRC Information Notice 2014
NRC Information Notice 2015-02, Anti-Freeze Agents in Fire Water Sprinkler Systems
-15, Inadequate Controls of Respiratory Protection Accessibility, Training, and Maintenance
NRC Regulatory Issue Summary 2005-07, Compensatory Measures to Satisfy the Fire
NRC Information Notice
Protection Program Requirements
2015-02, Anti-Freeze Agents in Fire Water Sprinkler Systems
NRC Regulatory Issue Summary 2005
-07, Compensatory Measures to Satisfy the Fire Protection Program Requirements
Miscellaneous Documents
Miscellaneous Documents
Bisco Report #748
Bisco Report #748-49, Fire Test Configuration for a Three-Hour Rated Fire Seal Utilizing Bisco
-49, Fire Test Configuration for a Three
-Hour Rated Fire Seal Utilizing Bisco
SF-20 Where a Steel Sleeve Condition with Pipe Penetrant Exists, dated 7/9/81
SF-20 Where a Steel Sleeve Condition with Pipe Penetrant Exists, dated 7/9/81
NLO B.5.b. Task List
NLO B.5.b. Task List
NUMARC 93-01, Industry Guideline for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants, Revision 4A
NUMARC 93-01, Industry Guideline for Monitoring the Effectiveness of Maintenance at
NUREG 1552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants, January 1999 PLORT 1610E, Extensive Damage Mitigation Guidelines, Revision 0
Nuclear Power Plants, Revision 4A
NUREG 1552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants,
January 1999
PLORT 1610E, Extensive Damage Mitigation Guidelines, Revision 0
PLOT 2305, Extensive Damage Mitigation Guidelines 1.0 and 2.0, Revision 1
PLOT 2305, Extensive Damage Mitigation Guidelines 1.0 and 2.0, Revision 1
PM-1120, Evaluation of B.5.b Mitigation Strategies, Revision 0
PM-1120, Evaluation of B.5.b Mitigation Strategies, Revision 0
Units 2 and 3 Fire Protection System 37 Health Reports, dated 4/4/18
Units 2 and 3 Fire Protection System 37 Health Reports, dated 4/4/18
}}
}}

Revision as of 05:19, 21 October 2019

Triennial Fire Protection Inspection Report 05000277/2018010 and 05000278/2018010
ML18130A299
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 05/09/2018
From: Glenn Dentel
Engineering Region 1 Branch 2
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Bickett C
References
IR 2018010
Download: ML18130A299 (18)


Text

May 9, 2018

SUBJECT:

PEACH BOTTOM ATOMIC POWER STATION UNITS 2 AND 3 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000277/2018010 AND 05000278/2018010

Dear Mr. Hanson:

On April 20, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Peach Bottom Atomic Power Station (Peach Bottom), Units 2 and 3. The NRC inspectors discussed the results of this inspection with Mr. Pat Navin, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

NRC inspectors documented two findings of very low safety significance (Green) in this report.

One of these findings involved a violation of NRC requirements. Further, inspectors documented a licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is treating these violations as non-cited violations (NCVs),

consistent with Section 2.3.2.a of the Enforcement Policy.

If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Peach Bottom. In addition, if you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC, 20555-0001; with copies to the Regional Administrator, Region I, and the NRC Resident Inspector at Peach Bottom. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRCs Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR ), Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-277 and 50-278 License Nos. DPR-44 and DPR-56

Enclosure:

Inspection Report 05000277/2018010 and 05000278/2018010

Inspection Report

Docket Numbers: 50-277 and 50-278 License Numbers: DPR-44 and DPR-56 Report Numbers: 05000277/2018010 and 05000278/2018010 Enterprise Identifier: I-2018-010-0059 Licensee: Exelon Generation Company, LLC Facility: Peach Bottom Atomic Power Station, Units 2 and 3 Location: Delta, PA Inspection Dates: April 2 - 20, 2018 Inspectors: C. Bickett, Senior Reactor Inspector (Team Lead)

E. DiPaolo, Senior Reactor Inspector P. Ott, Operations Engineer J. Patel, Reactor Inspector C. Cahill, Senior Reactor Analyst Approved By: G. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Exelons performance at

Peach Bottom Atomic Power Station, Units 2 and 3 by conducting the triennial fire protection team inspection in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

NRC and self-revealed findings, violations, and additional items are summarized in the tables below. A licensee-identified non-cited violation (NCV) is documented in report section 71111.05T.

List of Findings and Violations Failure to Identify Time-Critical Action Cornerstone Significance Cross-cutting Report Aspect Section Mitigating Green P.2 - Problem 71111.05T Systems FIN 05000277,05000278/2018010-01 Identification and Closed Resolution,

Evaluation The inspectors identified a green finding because Exelon did not identify, validate, and incorporate a time-critical action referenced in calculation PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106,

Operator Response Time Program. Specifically, Exelon did not identify a 10-minute time-critical action to take the transfer/isolation switch for the high pressure coolant injection (HPCI) inboard steam isolation valve (MO-2(3)-23-015), to the EMERG position.

Failure to Develop and Maintain Mitigating Strategy Cornerstone Significance Cross-cutting Report Aspect Section Mitigating Green None 71111.05T Systems NCV 05000277,05000278/2018010-02 Closed The inspectors identified a Green non-cited violation of 10 CFR 50.54(hh)(2), Conditions of Licenses, and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11), Mitigation Strategy License Condition, because Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Specifically, Exelon did not adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves in the event of a challenge to the reactor due to a postulated large fire and/or explosion.

INSPECTION SCOPE

===This inspection was conducted using the appropriate portions of the inspection procedure (IP) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Exelon performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.05T - Fire Protection (Triennial)

The inspectors evaluated the following from April 2 - 20, 2018:

Fire Protection Inspection Requirements ===

The inspectors evaluated fire protection program implementation in the following selected areas and/or fire zones:

(1) Fire Area 25: Cable Spreading Room (Zone 78H) and Fan Room (Zone 108A)
(2) Fire Area 36: Unit 2 E42 Emergency Switchgear Room (Zone 123)
(3) Fire Area 2: Unit 3 Reactor Building Closed Cooling Water Room (Zone 12B)
(4) Fire Area 13N: Unit 3 Reactor Building Operating Area (Zone 13J)

In performing this review, the inspectors performed an analysis of the following electrical circuits:

(1) MO-4487, Reactor Core Isolation Cooling System Turbine Trip and Throttle Valve
(2) 2-152-1704, E3 Emergency Diesel Generator Breaker to E32 Emergency Switchgear (20A17)
(3) LT-8456 and LI-8456, Suppression Pool Level Transmitter and Indicator
(4) MO3-23-017, High Pressure Coolant Injection (HPCI) System Pump Suction from Condensate Storage Tank
(5) MO3-10-013A, Residual Heat Removal System Suction Isolation Valve From Suppression Pool
(6) MO3-10-89B, Residual Heat Removal System Heat Exchanger High Pressure Service Water Discharge Valve B.5.b Inspection Activities (1 Sample)===

The inspectors evaluated feasibility of the following B.5.b Mitigating Strategy:

Extensive Damage Mitigation Guideline (EDMG) 2.0, Attachment 15, Alternate 125 VDC Power Supply for Safety Relief Valve Operation, Revision 8

INSPECTION RESULTS

Failure to Identify Time-Critical Action Cornerstone Significance Cross-cutting Report Aspect Section Mitigating Green P.2 - Problem 71111.05T Systems FIN 05000277,05000278/2018010-01 Identification Closed and Resolution, Evaluation The inspectors identified a green finding because Exelon did not identify, validate, and incorporate a time-critical action referenced in calculation PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106, Operator Response Time Program. Specifically, Exelon did not identify a 10-minute time-critical action to take the transfer/isolation switch for the high pressure coolant injection (HPCI) inboard steam isolation valve (MO-2(3)-23-015), to the EMERG position.

Description:

Operators use procedure SE-10, Alternative Shutdown, to control the plant from the alternate shutdown panels in the event of a fire that results in evacuation of the main control room. SE-10, Attachment 6, Part A, directs the transfer/isolation of safety relief valve control and the setup and control of necessary 4KV and emergency diesel generator equipment at the alternate shutdown panels. This is in direct support of AC power restoration for MO-2(3)-23-015, and subsequent opening of the valve, as HPCI is the credited water makeup source for this scenario. These actions are required if the valve has shut due to a fire-induced spurious operation, and offsite power is not available.

Issue report (IR) 2661579, dated 2016, documented that the station could not complete SE-10, Attachment 6, Part A, in 28 minutes, as required by fire safe shutdown calculation PF-0016-025. IR 2661579 identified that worst case, the actions took 93 minutes. Removing certain contingencies in the procedure, Exelon was able to complete the actions in 54 minutes. The inspectors noted that Exelon did not implement any compensatory measures to address this issue, and planned to revise the procedure to resequence actions such that they could be completed in the required time. On April 6, 2018, the inspectors questioned Exelon since they did not demonstrate that the required manual operator action time of 28 minutes could be met, and the procedure revision had yet to be issued. In response, Exelon performed a walkdown of the existing procedure and determined that the actions up to including energization of the E-22 and E-23 buses via the E-2 emergency diesel generator could be completed in 26 minutes and 28 seconds. Exelon then completed a temporary procedure change to ensure the actions to restore power with the E-2 emergency diesel generator were moved to earlier in the procedure attachment for expediency, and a second operator was added as a requirement to implement the actions. The inspectors noted that one of the reasons that the station could not meet the 28-minute time was likely due a procedure revision that added corrective actions to swap fuses in response to a previous unrelated issue.

During this inspection, Exelon issued a revision to calculation PF-0016-025, which updated the manual operator action list and the corresponding required action times per the most recent thermal hydraulic analysis, which included the measurement uncertainty recapture uprate implemented in January 2018. The revised time to complete the actions required to provide power to MO-2(3)-23-015 was lowered from 28 to 24 minutes. The inspectors questioned whether the station would have been able to meet this revised time prior to the temporary procedure change. Exelon stated in the revised calculation, operator action is provided to re-open HPCI Inboard Isolation Valve MO-2(3)-23-015 should it spuriously close prior to transfer of control from the main control room.

This prompt action is treated as a defense-in-depth action, as a specific sequence of failures must occur (spurious valve closure prior to transfer and subsequent loss of the primary source of power before transfer of control), and is not required for Appendix R compliance.

Exelon referenced a docketed August 16, 1984 letter to the NRC as justification for this conclusion.

The inspectors reviewed this licensing basis letter and noted that the justification was based on the assumption that within 10 minutes, operators would man the HPCI alternate control station and isolate the control circuit for this valve. This would leave a maximum of 10 minutes for the specific sequence of events to occur that would result in spurious closure of MO-2(3)-23-105, thus making this scenario unlikely. The inspectors noted Exelon did not thoroughly evaluate this letter to ensure that any conditions and/or assumptions were translated into the fire safe shutdown calculations and other station processes. As such, Exelon did not identify the 10-minute action as a prompt action. The inspectors determined that operators will likely be able to meet this 10-minute action with the current procedure.

However, there are no administrative controls in place to ensure that future changes to the procedure will not challenge this time. Additionally, because the 10-minute action requirement is not documented in the operator time response program, the Operations Training department does not know to incorporate the requirement into training, and the operators do not recognize the need to expeditiously complete the procedure steps.

The inspectors also noted other weaknesses in the stations evaluation and resolution of this issue. The inspectors concluded that Exelon incorrectly stated in IR 2661579 that these actions are only necessary in the event of multiple spurious operations and as such, are not required to be satisfied to maintain plant operations within design or licensing bases. This is incorrect because this is a single spurious operation scenario, which is required to be mitigated per 10 CFR 50 Appendix R requirements. Also of note, even though this issue was documented in their 2017 self-assessment for this inspection, Exelon still had not issued the revised procedure, nor implemented any compensatory actions prior to this inspection.

Corrective Actions: The stations planned corrective actions include updating Peach Bottoms time-critical operator action program to include the 10-minute action to take the transfer/isolation switch for MO-2(3)-23-015 to the EMERG position.

Corrective Action Reference: IR 4127608

Performance Assessment:

Performance Deficiency: The failure to identify, validate, and incorporate a time-critical action referenced in calculation PF-0016-025, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106, Operator Response Time Program is a performance deficiency.

Screening: The performance deficiency was more than minor because if left uncorrected, the performance deficiency would have the potential to lead to a more significant safety concern.

The 10-minute requirement is not documented in the operator time response program; therefore, training has not been conducted, operators did not recognize the time-critical action, and future changes to the SE-10 procedure could result in challenging the 10-minute requirement.

Significance: The inspectors assessed the significance of the finding using IMC 0609, Appendix F, Fire Protection SDP. This issue screened to very low safety significance (Green) in Phase 1, Step 1.3 as the procedure as currently written does not impact the ability to achieve safe shutdown.

Cross-cutting Aspect: This finding had a cross-cutting aspect in the area of Problem Identification and Resolution, Evaluation, because although Exelon included a reference to the 1984 letter in the latest revision to the fire safe shutdown calculation, they did not thoroughly evaluate the letter to ensure that any conditions and/or assumptions were translated into the fire safe shutdown calculations and other station processes [P.2].

Enforcement:

Inspectors did not identify a violation of regulatory requirements associated with this finding.

Failure to Develop and Maintain Mitigating Strategy Cornerstone Significance Cross-cutting Report Aspect Section Mitigating Green None 71111.05T Systems NCV 05000277,05000278/2018010-02 Closed The inspectors identified a Green non-cited violation of 10 CFR 50.54(hh)(2), Conditions of Licenses, and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11), Mitigation Strategy License Condition, because Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Specifically, Exelon did not adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves in the event of a challenge to the reactor due to a postulated large fire and/or explosion.

Description:

Exelon procedure EDMG 2.0, Peach Bottom Operational Contingency Guidelines, provides the methods for implementation of strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Exelon procedure EDMG 2.0, Attachment 15, Alternate 125 VDC Power Supply for Safety Relief Valve Operation, describes the stations strategy for supplying alternate power to the five automatic depressurization system safety relief valves. Figure 1 of this attachment describes which terminal points are to be used to accomplish this task.

Since April 2008, Figure 1 has listed the incorrect terminal points for the G and K safety relief valves on both Unit 2 and Unit 3. Therefore, when an individual reached the step in the procedure to connect the jumpers for the G and K safety relief valves, they would be directed to terminal locations that did not exist. As a result, step 19 of the procedure, Verify all five safety relief valve jumpers are connected at both ends, THEN continue, would not be able to be completed, and operators would likely not continue on with subsequent steps in the procedure. Because of this issue, inspectors determined that the procedure was not adequate to ensure that the strategy could be completed.

Corrective Actions: Exelon documented this issue in the corrective action program and implemented a revision to the procedure to correct the error.

Corrective Action Reference: IR 4125405

Performance Assessment:

Performance Deficiency: Exelons failure to adequately develop and maintain procedures to manually depressurize the reactor using the automatic depressurization system safety relief valves, as required by 10 CFR 50.54(hh)(2) and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11), was a performance deficiency.

Screening: This performance deficiency was more than minor because it is associated with the procedure quality attribute of the mitigating systems cornerstone and adversely affected the cornerstone objective to assure the availability, reliability, and capability of the automatic depressurization system safety relief valves to respond to an event. Specifically, failure to provide an adequate procedure to provide alternate power to the safety relief valves would impact the stations ability to open those valves to manually depressurize the reactor during an event.

Significance: The inspectors assessed the significance of this issue using IMC 0609, Appendix L, B.5.b. Significance Determination Process, Table 2. The inspectors determined that the finding did not meet the criteria listed in Table 2 for greater than green significance, and therefore screened this finding as Green.

Cross-cutting Aspect: No cross-cutting aspect was assigned to this finding because the inspectors determined that the finding did not reflect current plant performance.

Enforcement:

Violation: 10 CFR 50.54(hh)(2) requires, in part, that each licensee shall develop and implement guidance and strategies intended to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities under the circumstances associated with loss of large areas of the plant due to explosions or fire. Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(11) requires that Exelon develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage. Exelon procedure EDMG 2.0, Peach Bottom Operational Contingency Guidelines, provides the methods for implementation of these strategies. EDMG 2.0, Attachment 15, Alternate 125VDC Power Supply for Safety Relief Valve Operation, is the procedure for providing alternate power to the automatic depressurization system safety relief valves.

Contrary to the above, since April 2008, Exelon did not develop and maintain strategies for addressing large fires and explosions that include operations to mitigate fuel damage.

Specifically, EDMG 2.0, Attachment 15, was inadequate to ensure that the station would be able to open the automatic depressurization system relief valves from the containment penetrations via an alternate power supply to allow manual depressurization in the event of a challenge to the reactor due to a postulated large fire and/or explosion.

Disposition: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Licensee Identified Non-Cited Violation 71111.05T This violation of very low safety significance was identified by Exelon and has been entered into Exelons corrective action program and is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition 2.C.(4) requires, in part, Exelon to implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report.

Fire Protection Program, Peach Bottom Atomic Power Station, Units 2 and 3, is incorporated by reference into the Updated Final Safety Analysis Report, as discussed in Section 10.12, Fire Protection Program. Fire Protection Program Chapter 5.1, Methodology, assumes that two or more circuit failures resulting in spurious operation of two or more valves in series at a high/low pressure interface may occur due to a postulated fire in any given area.

Fire Protection Program Chapter 6.2, Analysis of High/Low Pressure Interfaces, requires Exelon to address the situations for which the isolation valves at a given interface point consists of two electrically controlled valves in series and where the potential may exist for a single fire to cause damage to cables associated with both valves.

Contrary to above, as of March 14, 2018, Exelon identified they failed to evaluate two motor-operated valves in series, MO-2-06-2663 and MO-2-06-038B for Unit 2, and MO-3-06-3663 and MO-3-06-038B for Unit 3, where the potential may exist for a single fire to cause damage to cables associated with both valves. Specifically, a postulated fire scenario could cause spurious opening of the valves, which may potentially result in a fire-induced loss of coolant accident through the high/low pressure system interface. Exelons evaluation identified the affected valves cables are routed through Fire Area 6N for the Unit 2 valves, and Fire Area 13N for the Unit 3 valves, and thus, a possibility exists for a single fire to cause damage to cables associated with both valves. This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

Significance/Severity: The inspectors performed a Phase 2 Significance Determination Process screening for this issue, in accordance with IMC 0609, Appendix F, Fire Protection Significance Determination Process. This finding affected the post-fire safe shutdown category because of spurious operations of safe shutdown components. Based on a walkdown of Fire Areas 6N and 13N, the inspectors did not identify any credible fire ignition source scenarios that could affect both Unit 2 motor-operated valves or both Unit 3 motor operated valves. Therefore, based upon task number 2.3.5, the inspectors determined that this finding screened to very low safety significance (Green).

Corrective Action References: IR 04115309, EC 623585, EC 623586

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On April 20, 2018, the inspector presented the triennial fire protection team inspection results to Mr. Pat Navin, Site Vice President, and other members of the Exelon staff.

DOCUMENTS REVIEWED

71111.05T

Fire Protection Licensing and Design Basis Documents

Letter from PECO (

V.S. Boyer) to USNRC (Darrell Eisenhut), Peach Bottom Atomic

Power Station Alternate Shutdown, dated 8/16/84

NE-00296, Post-Fire Safe Shutdown Program Requirements at PBAPS, Revision 4

NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 10/3/91

NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 3/13/85

NRC Safety Evaluation Report, Fire Protection Program, dated 5/23/79

NRC Safety Evaluation Report, Fire Protection Program, Supplement 1, dated 8/14/80

NRC Safety Evaluation Report, Fire Protection Program, Supplement 2, dated 9/15/80

NRC Safety Evaluation Report, Fire Protection Program, Supplement 3, dated 10/10/80

NRC Safety Evaluation Report, Fire Protection Program, Supplement 4, dated 11/24/80

Peach Bottom Atomic Power Station Fire Protection Program, Revision 17

Peach Bottom Atomic Power Station, Units 2 and 3 - Issuance of Amendment

RE: Fire Protection Program Changes, dated 6/24/05

P-T-10, Fire Safe Shutdown, Revision 13

Safety Evaluation by the Office of Nuclear Reactor Regulation Related to Order No. EA-02-026,

Exelon Generation Company, LLC, Peach Bottom Atomic Power Station, Units 2 and 3,

dated 8/9/07

Calculations, Analysis, and Engineering Evaluations

CFR 50.59 Safety Review for Modification P00680, Fire Detection and Suppression System

for Switchgear and Battery Rooms, Revision 1

EC 623620, Alternate Compensatory Measure for IR 4115309 Hi/Lo Interface Not Evaluated for

Appendix R, dated 3/22/18

Fire Endurance Test on Silicone Foam Penetration Seal in a Masonry Floor, Design FC-270,

dated 12/14/78

PEAF-EPU-001, T0611 Appendix R Fire Protection, Revision 5

PEAM-MUR-0611, Appendix R Fire Protection T0611, Revision 0

PF-0007, Combustible Loading Analysis, Revision 0

PF-0007, Combustible Loading Analysis, Revision 4

PF-0016-002, Fire Area 002 - Fire Safe Shutdown Analysis, Revision 1

PF-0016-013N, Fire Area 013N - Fire Safe Shutdown Analysis, Revision 1

PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 000V

PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 1

PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 2

PF-0016-036, Fire Area 036 - Fire Safe Shutdown Analysis, Revision 1

PF-0019, Fire Protection Hydraulic Calculation - Units 2 and 3 Sprinkler System for the 4

Kilo-Volt Switchgear Rooms, Battery Rooms, and Access Corridor, Revision 0

PF-0020, Fire Protection Hydraulic Calculation - Units 2 and 3 Main Fan Room (#381)

Hydraulic Calculation, Revision 0

T-061-VC-1, Assessment of the Fire Protection Sprinkler and Hose Station Supply Piping,

Revision 0

Drawings and Wiring Diagrams

280-E-2890, Emergency DC Lighting Layout Alternate Control Stations, Revision 1

280-M-318, Piping and Instrumentation Drawing, Fire Protection System, Revision 70

280-M-359, Sheet 1, Piping and Instrumentation Drawing Reactor Core Isolation Cooling

System, Revision 50

280-M-359, Sheet 2, Piping and Instrumentation Drawing Reactor Core Isolation Cooling

System, Revision 48

280-NE-75-1, Penetration Seal Details NE-378545, Revision 1

280-NE-75-1, Sheet 19, Pipe or Conduit through 3-Hour Rated Fire Barrier, Revision 1

737-D-VC-72, Thermo-Lag Upgrade Fire Barrier 78H-02, Revision 0

A-484, Barrier Plans, Elevation 91 6, Revision 8

A-485, Barrier Plans, Elevation 116 0 Sheets 1 and 2, Revisions 8 and 4

A-486, Barrier Plans, Elevation 135 0 Sheets 1 and 2, Revisions 11 and 1

A-487, Barrier Plans, Elevation 165 0 Sheets 1 and 2, Revisions 13 and 1

C-49, Fire System Underground Yard Plan, Revision 25

E-1, Sheet 1, Single Line Diagram Station, Revision 57

E-12, Sheet 1, 4160 V Emergency Power System Unit 3, Revision 11

E-1321, Sheet 3, Electrical Secondary and Control Connections Drywell Penetrations N-106A,

B, C, D - Indication and Control, Unit 2, Revision 31

E-1715, Sheet 1, E134 & E234 Emer. L.C., Revision 83

E-1717, Sheet 1, E334 & E434 Emer. L.C., Revision 72

E-184, Sheet 2, Electrical Schematic Diagram RHR Pump 4.16 kV Circuit Breaker, Revision 27

E-193, Sheet 3, Electrical Schematic Diagram Emergency Auxiliary Switchgear Diesel-

Generator 4160V Circuit Breaker, Revision 32

E-2371, Sheet 1, Riser Diagram Distributed Antenna System, Revision 4

E-2903, Sheet 1, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 6

E-2903, Sheet 3, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 0

E-8, Sheet 1, 4160V Emergency Power System Unit 2, Revision 20

M-1-S-36, Sheet 20, Electrical Schematic Diagram High Pressure Coolant Injection System,

Revision 78

M-1-S-42, Sheet 13, Electrical Schematic Diagram Reactor Core Isolation Cooling System,

Revision 74

M-1-S-42, Sheet 18, Electrical Schematic Diagram Reactor Core Isolation Cooling System,

Revision 79

M-1-S-42, Sheet 5, Electrical Schematic Diagram Reactor Core Isolation Cooling System,

Revision 87

M-1-S-42, Sheet 7, Electrical Schematic Diagram Reactor Core Isolation Cooling System,

Revision 76

M-1-S-65, Sheet 45, Electrical Schematic Diagram Residual Heat Removal System, Revision 97

M-1-S-65, Sheet 53, Electrical Schematic Diagram Residual Heat Removal System, Revision 99

M-1-S-65, Sheet 62, Electrical Schematic Diagram Residual Heat Removal System,

Revision 103

PD-27, Sheet 1, Typical Penetration Seal Detail Grout Seal, Revision 1

PD-5, Sheet 1, Typical Penetration Seal Detail External Pipe or Conduit Seal (SF-20), Revision

PD-7, Typical Penetration Seal Detail, Cable Tray Wall Seal (SF-20), Revision 1

PD-9, Typical Penetration Seal Detail, Penetration through Barrier Less Than Required

Thickness, Revision 0

PS-301, Penetration Seal Locations, Controlled Barriers-Room No. 301, Units 2 and 3, Area 3,

Elevation 150 0, Revision 1

PS-302, Penetration Seal Locations, Controlled Barriers-Room No. 302, Units 2 and 3, Area 3,

Elevation 150 0, Revision 2

PS-444, Sheet 1, Penetration Seal Locations Controlled Barriers - Room No. 444 Unit 3,

Revision 0

PS-444, Sheet 2, Penetration Seal Locations Controlled Barriers - Room No. 444 Unit 3,

Revision 1

Fire Protection Evaluations of Modifications and Design Changes

2321, Generic Letter 86-10 Evaluation - Post Fire Operation of Manual Valves

23620, Alternate Compensatory Measure for IR 4115309, HI/LO Interface Not Evaluated for

Appendix R

3968258, Generic Letter 86-10 Evaluation Supporting Configuration of Penetration

RW2-116-105-3039

Quality Assurance Audits and Self Assessments

AR 3994319, 2018 Triennial Fire Protection Inspection Preparatory Self-Assessment

Procedures

AO 54.2, 4KV Breaker Manual Operation, Revision 0

CC-AA-209-1001, Guidelines for Performing Fire Protection Program Configuration Change

Review, Revision 2

CC-AA-211, Fire Protection Program, Revision 8

CC-AA-211-1001, Fire Protection Engineering Evaluations, Revision 2

EDMG-1.0, Extensive Damage Mitigation Guideline for Loss of Large Area of the Plant,

Revision 1

EDMG-2.0, Peach Bottom Operational Contingency Guidelines, Revision 8

ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump,

Inner Screen or Emergency Cooling Tower Structures, Revision 21

ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump,

Inner Screen or Emergency Cooling Tower Structures - Bases, Revision 20

ON-115, Loss of Normal Main Control Room Ventilation - Bases, Revision 19

ON-115, Loss of Normal Main Control Room Ventilation - Procedure, Revision 22

OP-AA-102-106, Operator Response Time Program, Revision 4

OP-AA-201-003, Fire Drill Performance, Revision 16

OP-AA-201-004, Fire Prevention for Hot Work, Revision 14

OP-AA-201-009, Control of Transient Combustible Material, Revision 20

OP-PB-102-106, Operator Response Time Program at Peach Bottom, Revision 9

RT-H-099-990-2, One Hour SCBA Pack Inspection and Functional Test, Revision 19

RT-O-037-375-2, In-Plant Fire Brigade Equipment Inventory and Inspection, Revision 7

RT-O-037-376-2, Outside Fire Brigade Equipment Inventory and Inspection, Revision 17

SE-10, Alternate Shutdown Sheet 1, Revision 21

SE-10, Alternate Shutdown Sheet 2, Revision 22

SE-10, Alternate Shutdown Sheet 3, Revision 1

SE-10, Alternate Shutdown Sheet 4, Revision 1

SE-10, Alternate Shutdown, Attachment 12, Revision 2

SE-10, Alternate Shutdown, Attachment 13, Revision 2

SE-10, Alternate Shutdown, Attachment 14, Revision 3

SE-10, Alternate Shutdown, Attachment 22, Revision 0

SE-10, Alternate Shutdown, Attachment 3, Revision 8

SE-10, Alternate Shutdown, Attachment 6, Revision 8

SE-10, Alternate Shutdown, Attachment 6, Revision 8A

SE-10, Alternate Shutdown, Attachment 9, Revision 3

SE-10, Plant Shutdown from the Alternate Shutdown Panels - Bases, Revision 29

T-100, Scram - Bases, Revision 15

T-100, Scram, Revision 11

T-302-2, Area 02 Fire Guide, Revision 10

T-302-3, Area 02 Fire Guide, Revision 9

T-313N-2, Area 13N Fire Guide, Revision 4

T-313N-3, Area 13N Fire Guide, Revision 7

T-325-2, Area 25 Fire Guide, Revision 1

T-325-3, Area 25 Fire Guide, Revision 1

T-336-2, Area 36 Fire Guide, Revision 4

T-336-3, Area 36 Fire Guide, Revision 4

TSG 4.1, Attachment 15, Alternate 125VDC Power Supply for SRV Operation, Revision 6

TSG 4.1, Attachment 15, Alternate 125VDC Power Supply for SRV Operation, Revision 7

Operator Safe Shutdown Training

DBIG PNLO-3106, SE-10, Plant Shutdown from the Alternate Shutdown Panels, Revision 3

JPM PLOR-047C, Take Action for Control Room Evacuation (SE-10 Attachment 6), Revision 11

JPM PLOR-057P, Plant Shutdown from Alternate Shutdown Panel - HPCI Operations,

Revision 8

PLORT-1605A, Fire Protection and Appendix R, Revision 0

PLOT-1565, PBAPS Transient Response Implementation Procedures (T-300 Series), Revision 2

PLOT-5037X, Remote Shutdown Panel & Fire Safe Shutdown/Alternate Panel Controls,

Revision 4

PLOT-6000, Licensed Operator Initial Qualification Manual, Revision 22

PLOT-6000A, Licensed Operator Initial OJT Module (RO Tasks), Revision 1

PLOT-6000B, Licensed Operator Initial OJT Module (EO Tasks), Revision 1

PLOT-6000C, Licensed Operator Initial OJT Module (SRO Tasks) Revision 1

PNLO-2215, Effects of Fire on Safe Shutdown Equipment, Revision 5

PNLO-6000E, Equipment Operator Initial Qualification Manual, Revision 3

Simulator Exercise Guide PSEG-0409R-03, Fire in Cable Spreading Room, Revision 0

Pre-Fire Plans

FF-01, Fire Fighting Plan, Revision 23

PF-0, Pre-Fire Strategy Plan Area and Location Index, Revision 9

PF-108, Pre-Fire Plan, Radioactive Waste Building, Fan Room, Elevation 165 0,

Revision PF-127, Pre-Fire Plan, Unit 2 Turbine Building, Emergency Battery Switchgear

Rooms, Elevation 135 0, Revision 10

PF-12B, Pre-Fire Plan, Unit 2 Reactor Building Closed Loop Cooling Water Room,

Elevation 116 0, Revision 8

PF-13J, Pre-Fire Plan, Unit 2 Reactor Building General Area, Elevation 165 0, Revision 3

Fire Brigade Training

FBP04, Fire Behavior and Essentials, Revision 8

FBP07, Hose Streams, Appliances, and Tools, Revision 6

Fire Brigade Leader Qualification Status Report, date 4/5/18

Fire Brigade Member Qualification Status Report, dated 4/5/18

FPB11, Tactics and Strategy, Revision 7

FPB15, Pre-Fire Plans, Revision 6

IMS-01, Incident Management System, Revision 2

PNLOC 1612A, 4th Quarter Fire Brigade Meeting, Revision 0

Fire Brigade Drills and Critiques

Fire Brigade Drill Third Party Observation Report, performed on 12/7/17

N-PB-OPS-EO-FB-DRILL1, PS01 4th Quarter Fire Drill and Critique, performed on 12/13/17

N-PB-OPS-EO-FB-DRILL1, PS02 4th Quarter Fire Drill and Critique, performed on 12/15/17

N-PB-OPS-EO-FB-DRILL1, PS04 4th Quarter Fire Drill and Critique, performed on 12/7/17

N-PB-OPS-EO-FB-DRILL1, PS05 1st Quarter Unannounced, Backshift Fire Drill and Critique,

performed on 3/22/17

N-PB-OPS-EO-FB-DRILL1, PS05 4th Quarter Fire Drill and Critique, performed on 12/22/17

Transient Combustible, Hot Work, and Ignition Source Permits and Evaluations

Hot Work Permit 0611, RTV-2-14-29010A, Rework Valve/Replace Bonnet, dated 3/1/18

Hot Work Permit 0680, Install New Heat Exchanger, dated 12/11/18

Transient Combustible Permit 1070, Units 2 and 3 Turbine Building, Fire Zone 50-78A,

Temporary Power

Transient Combustible Permit 1071, Unit 3 Turbine Building, Fire Zone 50-78T, Temporary

Power

Transient Combustible Permit 1072, Unit 2 Reactor Building, Fire Zone 1-2, Temporary Power

Transient Combustible Permit 1073, Emergency Cooling Tower, Fire Zone 51-136, Test

Equipment

Transient Combustible Permit 1075, E-42 Switchgear Room, Fire Zone 36-123, Temporary

Instrumentation and Cabling

Completed Tests and Surveillances

R1302419-01, Calibration Check of Alternative Shutdown Panel Reactor Vessel Level

Instruments, completed 10/25/16

RT-0-052-750-2, E2 Diesel Alternative Shutdown Control Functional, completed 3/21/16

RT-M-57E-700-2, Main Control Room Emergency Lighting Battery Yearly Inspection

(20D304-2), completed 1/24/17

RT-M-57E-700-3, Main Control Room Emergency Lighting Battery Yearly Inspection

(30D304-2), completed 1/24/17

RT-M-57E-710-2, Main Control Room Emergency Lighting Battery Discharge Performance Test

(20D304-2), completed 8/11/17

RT-M-57E-710-3, Main Control Room Emergency Lighting Battery Discharge Performance Test

(30D304-2), completed 1/22/18

RT-O-037-375-2, In-Plant Fire Brigade Equipment Inventory and Inspection, completed

2/5/2018

RT-O-037-376-2, Outside Fire Brigade Equipment Inventory and Inspection, completed

2/10/2018

RT-O-037-710-2, Complete Safe Shutdown Emergency Lighting Battery Pack Inspection,

completed 2/10/18

RT-O-037-719-2, Emergency Lighting Inspection (Alternate Shutdown Control Station Access/

Egress Lights), completed 11/2/16

RT-O-037-719-3, Emergency Lighting Inspection (Alternate Shutdown Control Station Access/

Egress Lights), completed 11/6/17

RT-O-100-505-2, Emergency Operating Procedure Tool Inventory, completed 12/6/17

RT-O-100-580-2, B.5.b Tool and Material Inventory, completed 8/2/2017

ST-I-037-223-2, Unit 2 4 Kilo-Volt Switchgear and Battery Room and Radwaste 135 Corridor

Smoke Detectors Functional Test, completed 6/3/15

ST-I-037-223-2, Unit 2 4 Kilo-Volt Switchgear and Battery Room and Radwaste 135 Corridor

Smoke Detectors Functional Test, completed 8/3/17

ST-I-037-276-3, Reactor Building Elevation 165 Smoke Detectors Functional Test, completed

1/27/15

ST-I-037-276-3, Reactor Building Elevation 165 Smoke Detectors Functional Test, completed

7/28/17

ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional

Test, completed 6/23/15

ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional

Test, completed 1/13/17

ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 10/20/16

ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 6/22/17

ST-I-037-293-2, Recirculation Motor-Generator Set Lube Oil Pump 116 Smoke Detectors

Functional Test, completed 5/11/17

ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air

Flow Test, completed 10/10/17

ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air

Flow Test, completed 5/31/16

ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air

Flow Test, completed 10/10/17

ST-M-037-311-2, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire

Barriers, completed 6/8/12

ST-M-037-311-3, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire

Barriers, completed 12/21/17

ST-M-037-314-2, Visual Inspection of Encapsulated Electrical Raceways, completed 6/14/16

ST-M-037D-380-2, Diesel Driven Fire Pump Inspection, completed 1/1/17

ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165) Sprinkler System

Actuation, completed 3/14/16

ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165) Sprinkler System

Actuation, completed 3/25/18

ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Kilo-Volt Switchgear Rooms, and Radwaste Corridor

Area Sprinkler System Actuation, completed 7/10/14

ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Kilo-Volt Switchgear Rooms, and Radwaste Corridor

Area Sprinkler System Actuation, completed 7/9/16

ST-O-037B-381-2, Underground Fire Main Flow Test, completed 6/10/15

ST-O-037B-381-2, Underground Fire Main Flow Test, completed 8/8/14

ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, completed 8/6/15

ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, completed 12/13/16

ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 1/23/18

ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 2/21/18

ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 11/25/15

ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 1/17/17

ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed 1/9/18

ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed 2/7/18

Issue Reports (* written as a result of the NRC inspection)

00450846 01109076 01275720 01492237 01521603

01581135 02386737 02421301 02451017 02451647

2478057 02661579 02697843 02699896 02718710

03962962 03980676 04000043 04080702 04082065

04084069 04084077 04102768 04115309 04118443

04122474* 04122883* 04122970* 04127608* 04128972*

04129171*

Work Orders

4319703 4595771 4648804 R1298970 R1326279

Operating Experience

NRC Information Notice 1997-48, Inadequate or Inappropriate Interim Fire Protection

Compensatory Measures

NRC Information Notice 2013-02, Issues Potentially Affecting Nuclear Facility Fire Safety

NRC Information Notice 2013-06, Corrosion in Fire Protection Piping Due to Air and Water

Interaction

NRC Information Notice 2013-09, Compressed Flammable Gas Cylinders and Associated

Hazards

NRC Information Notice 2014-10, Potential Circuit Failure-Induced Secondary Fires or

Equipment Damage

NRC Information Notice 2014-15, Inadequate Controls of Respiratory Protection Accessibility,

Training, and Maintenance

NRC Information Notice 2015-02, Anti-Freeze Agents in Fire Water Sprinkler Systems

NRC Regulatory Issue Summary 2005-07, Compensatory Measures to Satisfy the Fire

Protection Program Requirements

Miscellaneous Documents

Bisco Report #748-49, Fire Test Configuration for a Three-Hour Rated Fire Seal Utilizing Bisco

SF-20 Where a Steel Sleeve Condition with Pipe Penetrant Exists, dated 7/9/81

NLO B.5.b. Task List

NUMARC 93-01, Industry Guideline for Monitoring the Effectiveness of Maintenance at

Nuclear Power Plants, Revision 4A

NUREG 1552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants,

January 1999

PLORT 1610E, Extensive Damage Mitigation Guidelines, Revision 0

PLOT 2305, Extensive Damage Mitigation Guidelines 1.0 and 2.0, Revision 1

PM-1120, Evaluation of B.5.b Mitigation Strategies, Revision 0

Units 2 and 3 Fire Protection System 37 Health Reports, dated 4/4/18

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BOULEVARD, SUITE 100

KING OF PRUSSIA, PA 19406-2713

May 9, 2018

Mr. Bryan C. Hanson

Senior Vice President, Exelon Generation, LLC

President and Chief Nuclear Officer, Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT: PEACH BOTTOM ATOMIC POWER STATION UNITS 2 AND 3 - TRIENNIAL

FIRE PROTECTION INSPECTION REPORT 05000277/2018010 AND

05000278/2018010

Dear Mr. Hanson:

On April 20, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

Peach Bottom Atomic Power Station (Peach Bottom), Units 2 and 3. The NRC inspectors

discussed the results of this inspection with Mr. Pat Navin, Site Vice President, and other

members of your staff. The results of this inspection are documented in the enclosed report.

NRC inspectors documented two findings of very low safety significance (Green) in this report.

One of these findings involved a violation of NRC requirements. Further, inspectors

documented a licensee-identified violation which was determined to be of very low safety

significance in this report. The NRC is treating these violations as non-cited violations (NCVs),

consistent with Section 2.3.2.a of the Enforcement Policy.

If you contest the violations or significance of these NCVs, you should provide a response within

days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with

copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC

Resident Inspector at Peach Bottom. In addition, if you disagree with a cross-cutting aspect

assignment or a finding not associated with a regulatory requirement in this report, you should

provide a response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the

U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC, 20555-0001; with copies to the Regional Administrator, Region I, and the NRC

Resident Inspector at Peach Bottom.

B. Hanson 2

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and the NRCs Public Document

Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR ), Part 2.390,

Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Glenn

T. Dentel, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos. 50-277 and 50-278

License Nos. DPR-44 and DPR-56

Enclosure:

Inspection Report 05000277/2018010

and 05000278/2018010

cc w/encl:

Distribution via ListServ

ML18130A299

SUNSI Review Non-Sensitive Publicly Available

Sensitive Non-Publicly Available

OFFICE RI/DRS RI/DRP RI/DRS RI/DRS

NAME CBickett JKrafty CCahill GDentel

DATE 05/03/18 05/08/18 05/08/18 05/09/18

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers: 50-277 and 50-278

License Numbers: DPR-44 and DPR-56

Report Numbers: 05000277/2018010 and 05000278/2018010

Enterprise Identifier: I-2018-010-0059

Licensee: Exelon Generation Company, LLC

Facility: Peach Bottom Atomic Power Station, Units 2 and 3

Location: Delta, PA

Inspection Dates: April 2 - 20, 2018

Inspectors:

C. Bickett, Senior Reactor Inspector (Team Lead)
E. DiPaolo, Senior Reactor Inspector
P. Ott, Operations Engineer
J. Patel, Reactor Inspector
C. Cahill, Senior Reactor Analyst

Approved By:

G. Dentel, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Exelons performance at

Peach Bottom Atomic Power Station, Units 2 and 3 by conducting the triennial fire protection

team inspection in accordance with the Reactor Oversight Process. The Reactor Oversight

Process is the NRCs program for overseeing the safe operation of commercial nuclear power

reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

NRC and self-revealed findings, violations, and additional items are summarized in the tables

below. A licensee-identified non-cited violation (NCV) is documented in report section

71111.05T.

List of Findings and Violations

Failure to Identify Time-Critical Action

Cornerstone Significance Cross-cutting Report

Aspect Section

Mitigating Green P.2 - Problem 71111.05T

Systems FIN 05000277,05000278/2018010-01 Identification and

Closed Resolution,

Evaluation

The inspectors identified a green finding because Exelon did not identify, validate, and

incorporate a time-critical action referenced in calculation PF-0016-025, Fire Area 025 - Fire

Safe Shutdown Analysis, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106,

Operator Response Time Program. Specifically, Exelon did not identify a 10-minute time-

critical action to take the transfer/isolation switch for the high pressure coolant injection

(HPCI) inboard steam isolation valve (MO-2(3)-23-015), to the EMERG position.

Failure to Develop and Maintain Mitigating Strategy

Cornerstone Significance Cross-cutting Report

Aspect Section

Mitigating Green None 71111.05T

Systems NCV 05000277,05000278/2018010-02

Closed

The inspectors identified a Green non-cited violation of 10 CFR 50.54(hh)(2), Conditions of

Licenses, and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition

2.C.(11), Mitigation Strategy License Condition, because Exelon did not develop and

maintain strategies for addressing large fires and explosions that include operations to mitigate

fuel damage. Specifically, Exelon did not adequately develop and maintain procedures to

manually depressurize the reactor using the automatic depressurization system safety relief

valves in the event of a challenge to the reactor due to a postulated large fire and/or explosion.

INSPECTION SCOPE

This inspection was conducted using the appropriate portions of the inspection procedure (IP) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at

http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection

activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor

Inspection Program - Operations Phase. The inspectors reviewed selected procedures and

records, observed activities, and interviewed personnel to assess Exelon performance and

compliance with Commission rules and regulations, license conditions, site procedures, and

standards.

REACTOR SAFETY

71111.05T - Fire Protection (Triennial)

The inspectors evaluated the following from April 2 - 20, 2018:

Fire Protection Inspection Requirements (4 Samples)

The inspectors evaluated fire protection program implementation in the following

selected areas and/or fire zones:

(1) Fire Area 25: Cable Spreading Room (Zone 78H) and Fan Room (Zone 108A)

(2) Fire Area 36: Unit 2 E42 Emergency Switchgear Room (Zone 123)

(3) Fire Area 2: Unit 3 Reactor Building Closed Cooling Water Room (Zone 12B)

(4) Fire Area 13N: Unit 3 Reactor Building Operating Area (Zone 13J)

In performing this review, the inspectors performed an analysis of the following electrical

circuits:

(1) MO-4487, Reactor Core Isolation Cooling System Turbine Trip and Throttle Valve

(2) 2-152-1704, E3 Emergency Diesel Generator Breaker to E32 Emergency Switchgear

(20A17)

(3) LT-8456 and LI-8456, Suppression Pool Level Transmitter and Indicator

(4) MO3-23-017, High Pressure Coolant Injection (HPCI) System Pump Suction from

Condensate Storage Tank

(5) MO3-10-013A, Residual Heat Removal System Suction Isolation Valve From

Suppression Pool

(6) MO3-10-89B, Residual Heat Removal System Heat Exchanger High Pressure

Service Water Discharge Valve

B.5.b Inspection Activities (1 Sample)

The inspectors evaluated feasibility of the following B.5.b Mitigating Strategy:

Extensive Damage Mitigation Guideline (EDMG) 2.0, Attachment 15, Alternate 125 VDC

Power Supply for Safety Relief Valve Operation, Revision 8

INSPECTION RESULTS

Failure to Identify Time-Critical Action

Cornerstone Significance Cross-cutting Report

Aspect Section

Mitigating Green P.2 - Problem 71111.05T

Systems FIN 05000277,05000278/2018010-01 Identification

Closed and Resolution,

Evaluation

The inspectors identified a green finding because Exelon did not identify, validate, and

incorporate a time-critical action referenced in calculation PF-0016-025, Fire Area 025 - Fire

Safe Shutdown Analysis, in accordance with Sections 4.2 and 4.3 of OP-AA-102-106,

Operator Response Time Program. Specifically, Exelon did not identify a 10-minute time-

critical action to take the transfer/isolation switch for the high pressure coolant injection

(HPCI) inboard steam isolation valve (MO-2(3)-23-015), to the EMERG position.

Description: Operators use procedure SE-10, Alternative Shutdown, to control the plant from

the alternate shutdown panels in the event of a fire that results in evacuation of the main

control room. SE-10, Attachment 6, Part A, directs the transfer/isolation of safety relief valve

control and the setup and control of necessary 4KV and emergency diesel generator

equipment at the alternate shutdown panels. This is in direct support of AC power restoration

for MO-2(3)-23-015, and subsequent opening of the valve, as HPCI is the credited water

makeup source for this scenario. These actions are required if the valve has shut due to a

fire-induced spurious operation, and offsite power is not available.

Issue report (IR) 2661579, dated 2016, documented that the station could not complete SE-

10, Attachment 6, Part A, in 28 minutes, as required by fire safe shutdown calculation PF-

0016-025. IR 2661579 identified that worst case, the actions took 93 minutes. Removing

certain contingencies in the procedure, Exelon was able to complete the actions in 54

minutes. The inspectors noted that Exelon did not implement any compensatory measures to

address this issue, and planned to revise the procedure to resequence actions such that they

could be completed in the required time. On April 6, 2018, the inspectors questioned Exelon

since they did not demonstrate that the required manual operator action time of 28 minutes

could be met, and the procedure revision had yet to be issued. In response, Exelon

performed a walkdown of the existing procedure and determined that the actions up to

including energization of the E-22 and E-23 buses via the E-2 emergency diesel generator

could be completed in 26 minutes and 28 seconds. Exelon then completed a temporary

procedure change to ensure the actions to restore power with the E-2 emergency diesel

generator were moved to earlier in the procedure attachment for expediency, and a second

operator was added as a requirement to implement the actions. The inspectors noted that

one of the reasons that the station could not meet the 28-minute time was likely due a

procedure revision that added corrective actions to swap fuses in response to a previous

unrelated issue.

During this inspection, Exelon issued a revision to calculation PF-0016-025, which updated

the manual operator action list and the corresponding required action times per the most

recent thermal hydraulic analysis, which included the measurement uncertainty recapture

uprate implemented in January 2018. The revised time to complete the actions required to

provide power to MO-2(3)-23-015 was lowered from 28 to 24 minutes. The inspectors

questioned whether the station would have been able to meet this revised time prior to the

temporary procedure change. Exelon stated in the revised calculation, operator action is

provided to re-open HPCI Inboard Isolation Valve MO-2(3)-23-015 should it spuriously close

prior to transfer of control from the main control room.

This prompt action is treated as a defense-in-depth action, as a specific sequence of failures

must occur (spurious valve closure prior to transfer and subsequent loss of the primary

source of power before transfer of control), and is not required for Appendix R compliance.

Exelon referenced a docketed August 16, 1984 letter to the NRC as justification for this

conclusion.

The inspectors reviewed this licensing basis letter and noted that the justification was based

on the assumption that within 10 minutes, operators would man the HPCI alternate control

station and isolate the control circuit for this valve. This would leave a maximum of

minutes for the specific sequence of events to occur that would result in spurious closure

of MO-2(3)-23-105, thus making this scenario unlikely. The inspectors noted Exelon did not

thoroughly evaluate this letter to ensure that any conditions and/or assumptions were

translated into the fire safe shutdown calculations and other station processes. As such,

Exelon did not identify the 10-minute action as a prompt action. The inspectors determined

that operators will likely be able to meet this 10-minute action with the current procedure.

However, there are no administrative controls in place to ensure that future changes to the

procedure will not challenge this time. Additionally, because the 10-minute action requirement

is not documented in the operator time response program, the Operations Training

department does not know to incorporate the requirement into training, and the operators do

not recognize the need to expeditiously complete the procedure steps.

The inspectors also noted other weaknesses in the stations evaluation and resolution of this

issue. The inspectors concluded that Exelon incorrectly stated in IR 2661579 that these

actions are only necessary in the event of multiple spurious operations and as such, are not

required to be satisfied to maintain plant operations within design or licensing bases. This is

incorrect because this is a single spurious operation scenario, which is required to be

mitigated per 10 CFR 50 Appendix R requirements. Also of note, even though this issue was

documented in their 2017 self-assessment for this inspection, Exelon still had not issued the

revised procedure, nor implemented any compensatory actions prior to this inspection.

Corrective Actions: The stations planned corrective actions include updating Peach Bottoms

time-critical operator action program to include the 10-minute action to take the

transfer/isolation switch for MO-2(3)-23-015 to the EMERG position.

Corrective Action Reference: IR 4127608

Performance Assessment:

Performance Deficiency: The failure to identify, validate, and incorporate a time-critical action

referenced in calculation PF-0016-025, in accordance with Sections 4.2 and 4.3 of

OP-AA-102-106, Operator Response Time Program is a performance deficiency.

Screening: The performance deficiency was more than minor because if left uncorrected, the

performance deficiency would have the potential to lead to a more significant safety concern.

The 10-minute requirement is not documented in the operator time response program;

therefore, training has not been conducted, operators did not recognize the time-critical

action, and future changes to the SE-10 procedure could result in challenging the 10-minute

requirement.

Significance: The inspectors assessed the significance of the finding using IMC 0609,

Appendix F, Fire Protection SDP. This issue screened to very low safety significance

(Green) in Phase 1, Step 1.3 as the procedure as currently written does not impact the ability

to achieve safe shutdown.

Cross-cutting Aspect: This finding had a cross-cutting aspect in the area of

Problem Identification and Resolution, Evaluation, because although Exelon included a

reference to the 1984 letter in the latest revision to the fire safe shutdown calculation, they did

not thoroughly evaluate the letter to ensure that any conditions and/or assumptions were

translated into the fire safe shutdown calculations and other station processes [P.2].

Enforcement: Inspectors did not identify a violation of regulatory requirements associated

with this finding.

Failure to Develop and Maintain Mitigating Strategy

Cornerstone Significance Cross-cutting Report

Aspect Section

Mitigating Green None 71111.05T

Systems NCV 05000277,05000278/2018010-02

Closed

The inspectors identified a Green non-cited violation of 10 CFR 50.54(hh)(2), Conditions of

Licenses, and Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License

Condition 2.C.(11), Mitigation Strategy License Condition, because Exelon did not develop

and maintain strategies for addressing large fires and explosions that include operations to

mitigate fuel damage. Specifically, Exelon did not adequately develop and maintain

procedures to manually depressurize the reactor using the automatic depressurization system

safety relief valves in the event of a challenge to the reactor due to a postulated large fire

and/or explosion.

Description: Exelon procedure EDMG 2.0, Peach Bottom Operational Contingency

Guidelines, provides the methods for implementation of strategies for addressing large fires

and explosions that include operations to mitigate fuel damage. Exelon procedure EDMG

2.0, Attachment 15, Alternate 125 VDC Power Supply for Safety Relief Valve Operation,

describes the stations strategy for supplying alternate power to the five automatic

depressurization system safety relief valves. Figure 1 of this attachment describes which

terminal points are to be used to accomplish this task.

Since April 2008, Figure 1 has listed the incorrect terminal points for the G and K safety

relief valves on both Unit 2 and Unit 3. Therefore, when an individual reached the step in the

procedure to connect the jumpers for the G and K safety relief valves, they would be

directed to terminal locations that did not exist. As a result, step 19 of the procedure,

Verify all five safety relief valve jumpers are connected at both ends, THEN continue,

would not be able to be completed, and operators would likely not continue on with

subsequent steps in the procedure. Because of this issue, inspectors determined that the

procedure was not adequate to ensure that the strategy could be completed.

Corrective Actions: Exelon documented this issue in the corrective action program and

implemented a revision to the procedure to correct the error.

Corrective Action Reference: IR 4125405

Performance Assessment:

Performance Deficiency: Exelons failure to adequately develop and maintain procedures to

manually depressurize the reactor using the automatic depressurization system safety relief

valves, as required by 10 CFR 50.54(hh)(2) and Peach Bottom Unit 2 and Unit 3 Renewed

Facility Operating License Condition 2.C.(11), was a performance deficiency.

Screening: This performance deficiency was more than minor because it is associated with

the procedure quality attribute of the mitigating systems cornerstone and adversely affected

the cornerstone objective to assure the availability, reliability, and capability of the automatic

depressurization system safety relief valves to respond to an event. Specifically, failure to

provide an adequate procedure to provide alternate power to the safety relief valves would

impact the stations ability to open those valves to manually depressurize the reactor during

an event.

Significance: The inspectors assessed the significance of this issue using IMC 0609,

Appendix L, B.5.b. Significance Determination Process, Table 2. The inspectors determined

that the finding did not meet the criteria listed in Table 2 for greater than green significance,

and therefore screened this finding as Green.

Cross-cutting Aspect: No cross-cutting aspect was assigned to this finding because the

inspectors determined that the finding did not reflect current plant performance.

Enforcement:

Violation: 10 CFR 50.54(hh)(2) requires, in part, that each licensee shall develop and

implement guidance and strategies intended to maintain or restore core cooling, containment,

and spent fuel pool cooling capabilities under the circumstances associated with loss of large

areas of the plant due to explosions or fire. Peach Bottom Unit 2 and Unit 3 Renewed Facility

Operating License Condition 2.C.(11) requires that Exelon develop and maintain strategies for

addressing large fires and explosions that include operations to mitigate fuel damage. Exelon

procedure EDMG 2.0, Peach Bottom Operational Contingency Guidelines, provides the

methods for implementation of these strategies. EDMG 2.0, Attachment 15, Alternate

25VDC Power Supply for Safety Relief Valve Operation, is the procedure for providing

alternate power to the automatic depressurization system safety relief valves.

Contrary to the above, since April 2008, Exelon did not develop and maintain strategies for

addressing large fires and explosions that include operations to mitigate fuel damage.

Specifically, EDMG 2.0, Attachment 15, was inadequate to ensure that the station would be

able to open the automatic depressurization system relief valves from the containment

penetrations via an alternate power supply to allow manual depressurization in the event of a

challenge to the reactor due to a postulated large fire and/or explosion.

Disposition: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Licensee Identified Non-Cited Violation 71111.05T

This violation of very low safety significance was identified by Exelon and has been entered

into Exelons corrective action program and is being treated as an NCV, consistent with

Section 2.3.2 of the Enforcement Policy.

Violation: Peach Bottom Unit 2 and Unit 3 Renewed Facility Operating License Condition

2.C.(4) requires, in part, Exelon to implement and maintain in effect all provisions of the

approved fire protection program as described in the Updated Final Safety Analysis Report.

Fire Protection Program, Peach Bottom Atomic Power Station, Units 2 and 3, is incorporated

by reference into the Updated Final Safety Analysis Report, as discussed in Section 10.12,

Fire Protection Program. Fire Protection Program Chapter 5.1, Methodology, assumes

that two or more circuit failures resulting in spurious operation of two or more valves in series

at a high/low pressure interface may occur due to a postulated fire in any given area.

Fire Protection Program Chapter 6.2, Analysis of High/Low Pressure Interfaces, requires

Exelon to address the situations for which the isolation valves at a given interface point

consists of two electrically controlled valves in series and where the potential may exist for a

single fire to cause damage to cables associated with both valves.

Contrary to above, as of March 14, 2018, Exelon identified they failed to evaluate two motor-

operated valves in series, MO-2-06-2663 and MO-2-06-038B for Unit 2, and MO-3-06-3663

and MO-3-06-038B for Unit 3, where the potential may exist for a single fire to cause damage

to cables associated with both valves. Specifically, a postulated fire scenario could cause

spurious opening of the valves, which may potentially result in a fire-induced loss of coolant

accident through the high/low pressure system interface. Exelons evaluation identified the

affected valves cables are routed through Fire Area 6N for the Unit 2 valves, and Fire Area

13N for the Unit 3 valves, and thus, a possibility exists for a single fire to cause damage to

cables associated with both valves. This violation is being treated as an NCV, consistent with

Section 2.3.2 of the Enforcement Policy.

Significance/Severity: The inspectors performed a Phase 2 Significance Determination

Process screening for this issue, in accordance with IMC 0609, Appendix F, Fire Protection

Significance Determination Process. This finding affected the post-fire safe shutdown

category because of spurious operations of safe shutdown components. Based on a

walkdown of Fire Areas 6N and 13N, the inspectors did not identify any credible fire ignition

source scenarios that could affect both Unit 2 motor-operated valves or both Unit 3 motor

operated valves. Therefore, based upon task number 2.3.5, the inspectors determined that

this finding screened to very low safety significance (Green).

Corrective Action References: IR 04115309, EC 623585, EC 623586

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On April 20, 2018, the inspector presented the triennial fire protection team inspection results to

Mr. Pat Navin, Site Vice President, and other members of the Exelon staff.

DOCUMENTS REVIEWED

71111.05T

Fire Protection Licensing and Design Basis Documents

Letter from PECO (

V.S. Boyer) to USNRC (Darrell Eisenhut), Peach Bottom Atomic

Power Station Alternate Shutdown, dated 8/16/84

NE-00296, Post-Fire Safe Shutdown Program Requirements at PBAPS, Revision 4

NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 10/3/91

NRC Exemption from the Requirements of 10 CFR Part 50, Appendix R, dated 3/13/85

NRC Safety Evaluation Report, Fire Protection Program, dated 5/23/79

NRC Safety Evaluation Report, Fire Protection Program, Supplement 1, dated 8/14/80

NRC Safety Evaluation Report, Fire Protection Program, Supplement 2, dated 9/15/80

NRC Safety Evaluation Report, Fire Protection Program, Supplement 3, dated 10/10/80

NRC Safety Evaluation Report, Fire Protection Program, Supplement 4, dated 11/24/80

Peach Bottom Atomic Power Station Fire Protection Program, Revision 17

Peach Bottom Atomic Power Station, Units 2 and 3 - Issuance of Amendment

RE: Fire Protection Program Changes, dated 6/24/05

P-T-10, Fire Safe Shutdown, Revision 13

Safety Evaluation by the Office of Nuclear Reactor Regulation Related to Order No. EA-02-026,

Exelon Generation Company, LLC, Peach Bottom Atomic Power Station, Units 2 and 3,

dated 8/9/07

Calculations, Analysis, and Engineering Evaluations

CFR 50.59 Safety Review for Modification P00680, Fire Detection and Suppression System

for Switchgear and Battery Rooms, Revision 1

EC 623620, Alternate Compensatory Measure for IR 4115309 Hi/Lo Interface Not Evaluated for

Appendix R, dated 3/22/18

Fire Endurance Test on Silicone Foam Penetration Seal in a Masonry Floor, Design FC-270,

dated 12/14/78

PEAF-EPU-001, T0611 Appendix R Fire Protection, Revision 5

PEAM-MUR-0611, Appendix R Fire Protection T0611, Revision 0

PF-0007, Combustible Loading Analysis, Revision 0

PF-0007, Combustible Loading Analysis, Revision 4

PF-0016-002, Fire Area 002 - Fire Safe Shutdown Analysis, Revision 1

PF-0016-013N, Fire Area 013N - Fire Safe Shutdown Analysis, Revision 1

PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 000V

PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 1

PF-0016-025, Fire Area 025 - Fire Safe Shutdown Analysis, Revision 2

PF-0016-036, Fire Area 036 - Fire Safe Shutdown Analysis, Revision 1

PF-0019, Fire Protection Hydraulic Calculation - Units 2 and 3 Sprinkler System for the 4

Kilo-Volt Switchgear Rooms, Battery Rooms, and Access Corridor, Revision 0

PF-0020, Fire Protection Hydraulic Calculation - Units 2 and 3 Main Fan Room (#381)

Hydraulic Calculation, Revision 0

T-061-VC-1, Assessment of the Fire Protection Sprinkler and Hose Station Supply Piping,

Revision 0

Drawings and Wiring Diagrams

280-E-2890, Emergency DC Lighting Layout Alternate Control Stations, Revision 1

280-M-318, Piping and Instrumentation Drawing, Fire Protection System, Revision 70

280-M-359, Sheet 1, Piping and Instrumentation Drawing Reactor Core Isolation Cooling

System, Revision 50

280-M-359, Sheet 2, Piping and Instrumentation Drawing Reactor Core Isolation Cooling

System, Revision 48

280-NE-75-1, Penetration Seal Details NE-378545, Revision 1

280-NE-75-1, Sheet 19, Pipe or Conduit through 3-Hour Rated Fire Barrier, Revision 1

737-D-VC-72, Thermo-Lag Upgrade Fire Barrier 78H-02, Revision 0

A-484, Barrier Plans, Elevation 91 6, Revision 8

A-485, Barrier Plans, Elevation 116 0 Sheets 1 and 2, Revisions 8 and 4

A-486, Barrier Plans, Elevation 135 0 Sheets 1 and 2, Revisions 11 and 1

A-487, Barrier Plans, Elevation 165 0 Sheets 1 and 2, Revisions 13 and 1

C-49, Fire System Underground Yard Plan, Revision 25

E-1, Sheet 1, Single Line Diagram Station, Revision 57

E-12, Sheet 1, 4160 V Emergency Power System Unit 3, Revision 11

E-1321, Sheet 3, Electrical Secondary and Control Connections Drywell Penetrations N-106A,

B, C, D - Indication and Control, Unit 2, Revision 31

E-1715, Sheet 1, E134 & E234 Emer. L.C., Revision 83

E-1717, Sheet 1, E334 & E434 Emer. L.C., Revision 72

E-184, Sheet 2, Electrical Schematic Diagram RHR Pump 4.16 kV Circuit Breaker, Revision 27

E-193, Sheet 3, Electrical Schematic Diagram Emergency Auxiliary Switchgear Diesel-

Generator 4160V Circuit Breaker, Revision 32

E-2371, Sheet 1, Riser Diagram Distributed Antenna System, Revision 4

E-2903, Sheet 1, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 6

E-2903, Sheet 3, Electrical Schematic Diagram Alternative Control Instrumentation, Revision 0

E-8, Sheet 1, 4160V Emergency Power System Unit 2, Revision 20

M-1-S-36, Sheet 20, Electrical Schematic Diagram High Pressure Coolant Injection System,

Revision 78

M-1-S-42, Sheet 13, Electrical Schematic Diagram Reactor Core Isolation Cooling System,

Revision 74

M-1-S-42, Sheet 18, Electrical Schematic Diagram Reactor Core Isolation Cooling System,

Revision 79

M-1-S-42, Sheet 5, Electrical Schematic Diagram Reactor Core Isolation Cooling System,

Revision 87

M-1-S-42, Sheet 7, Electrical Schematic Diagram Reactor Core Isolation Cooling System,

Revision 76

M-1-S-65, Sheet 45, Electrical Schematic Diagram Residual Heat Removal System, Revision 97

M-1-S-65, Sheet 53, Electrical Schematic Diagram Residual Heat Removal System, Revision 99

M-1-S-65, Sheet 62, Electrical Schematic Diagram Residual Heat Removal System,

Revision 103

PD-27, Sheet 1, Typical Penetration Seal Detail Grout Seal, Revision 1

PD-5, Sheet 1, Typical Penetration Seal Detail External Pipe or Conduit Seal (SF-20), Revision

PD-7, Typical Penetration Seal Detail, Cable Tray Wall Seal (SF-20), Revision 1

PD-9, Typical Penetration Seal Detail, Penetration through Barrier Less Than Required

Thickness, Revision 0

PS-301, Penetration Seal Locations, Controlled Barriers-Room No. 301, Units 2 and 3, Area 3,

Elevation 150 0, Revision 1

PS-302, Penetration Seal Locations, Controlled Barriers-Room No. 302, Units 2 and 3, Area 3,

Elevation 150 0, Revision 2

PS-444, Sheet 1, Penetration Seal Locations Controlled Barriers - Room No. 444 Unit 3,

Revision 0

PS-444, Sheet 2, Penetration Seal Locations Controlled Barriers - Room No. 444 Unit 3,

Revision 1

Fire Protection Evaluations of Modifications and Design Changes

2321, Generic Letter 86-10 Evaluation - Post Fire Operation of Manual Valves

23620, Alternate Compensatory Measure for IR 4115309, HI/LO Interface Not Evaluated for

Appendix R

3968258, Generic Letter 86-10 Evaluation Supporting Configuration of Penetration

RW2-116-105-3039

Quality Assurance Audits and Self Assessments

AR 3994319, 2018 Triennial Fire Protection Inspection Preparatory Self-Assessment

Procedures

AO 54.2, 4KV Breaker Manual Operation, Revision 0

CC-AA-209-1001, Guidelines for Performing Fire Protection Program Configuration Change

Review, Revision 2

CC-AA-211, Fire Protection Program, Revision 8

CC-AA-211-1001, Fire Protection Engineering Evaluations, Revision 2

EDMG-1.0, Extensive Damage Mitigation Guideline for Loss of Large Area of the Plant,

Revision 1

EDMG-2.0, Peach Bottom Operational Contingency Guidelines, Revision 8

ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump,

Inner Screen or Emergency Cooling Tower Structures, Revision 21

ON-114, Actual Fire Reported in the Power Block, Diesel Generator Building, Emergency Pump,

Inner Screen or Emergency Cooling Tower Structures - Bases, Revision 20

ON-115, Loss of Normal Main Control Room Ventilation - Bases, Revision 19

ON-115, Loss of Normal Main Control Room Ventilation - Procedure, Revision 22

OP-AA-102-106, Operator Response Time Program, Revision 4

OP-AA-201-003, Fire Drill Performance, Revision 16

OP-AA-201-004, Fire Prevention for Hot Work, Revision 14

OP-AA-201-009, Control of Transient Combustible Material, Revision 20

OP-PB-102-106, Operator Response Time Program at Peach Bottom, Revision 9

RT-H-099-990-2, One Hour SCBA Pack Inspection and Functional Test, Revision 19

RT-O-037-375-2, In-Plant Fire Brigade Equipment Inventory and Inspection, Revision 7

RT-O-037-376-2, Outside Fire Brigade Equipment Inventory and Inspection, Revision 17

SE-10, Alternate Shutdown Sheet 1, Revision 21

SE-10, Alternate Shutdown Sheet 2, Revision 22

SE-10, Alternate Shutdown Sheet 3, Revision 1

SE-10, Alternate Shutdown Sheet 4, Revision 1

SE-10, Alternate Shutdown, Attachment 12, Revision 2

SE-10, Alternate Shutdown, Attachment 13, Revision 2

SE-10, Alternate Shutdown, Attachment 14, Revision 3

SE-10, Alternate Shutdown, Attachment 22, Revision 0

SE-10, Alternate Shutdown, Attachment 3, Revision 8

SE-10, Alternate Shutdown, Attachment 6, Revision 8

SE-10, Alternate Shutdown, Attachment 6, Revision 8A

SE-10, Alternate Shutdown, Attachment 9, Revision 3

SE-10, Plant Shutdown from the Alternate Shutdown Panels - Bases, Revision 29

T-100, Scram - Bases, Revision 15

T-100, Scram, Revision 11

T-302-2, Area 02 Fire Guide, Revision 10

T-302-3, Area 02 Fire Guide, Revision 9

T-313N-2, Area 13N Fire Guide, Revision 4

T-313N-3, Area 13N Fire Guide, Revision 7

T-325-2, Area 25 Fire Guide, Revision 1

T-325-3, Area 25 Fire Guide, Revision 1

T-336-2, Area 36 Fire Guide, Revision 4

T-336-3, Area 36 Fire Guide, Revision 4

TSG 4.1, Attachment 15, Alternate 125VDC Power Supply for SRV Operation, Revision 6

TSG 4.1, Attachment 15, Alternate 125VDC Power Supply for SRV Operation, Revision 7

Operator Safe Shutdown Training

DBIG PNLO-3106, SE-10, Plant Shutdown from the Alternate Shutdown Panels, Revision 3

JPM PLOR-047C, Take Action for Control Room Evacuation (SE-10 Attachment 6), Revision 11

JPM PLOR-057P, Plant Shutdown from Alternate Shutdown Panel - HPCI Operations,

Revision 8

PLORT-1605A, Fire Protection and Appendix R, Revision 0

PLOT-1565, PBAPS Transient Response Implementation Procedures (T-300 Series), Revision 2

PLOT-5037X, Remote Shutdown Panel & Fire Safe Shutdown/Alternate Panel Controls,

Revision 4

PLOT-6000, Licensed Operator Initial Qualification Manual, Revision 22

PLOT-6000A, Licensed Operator Initial OJT Module (RO Tasks), Revision 1

PLOT-6000B, Licensed Operator Initial OJT Module (EO Tasks), Revision 1

PLOT-6000C, Licensed Operator Initial OJT Module (SRO Tasks) Revision 1

PNLO-2215, Effects of Fire on Safe Shutdown Equipment, Revision 5

PNLO-6000E, Equipment Operator Initial Qualification Manual, Revision 3

Simulator Exercise Guide PSEG-0409R-03, Fire in Cable Spreading Room, Revision 0

Pre-Fire Plans

FF-01, Fire Fighting Plan, Revision 23

PF-0, Pre-Fire Strategy Plan Area and Location Index, Revision 9

PF-108, Pre-Fire Plan, Radioactive Waste Building, Fan Room, Elevation 165 0,

Revision PF-127, Pre-Fire Plan, Unit 2 Turbine Building, Emergency Battery Switchgear

Rooms, Elevation 135 0, Revision 10

PF-12B, Pre-Fire Plan, Unit 2 Reactor Building Closed Loop Cooling Water Room,

Elevation 116 0, Revision 8

PF-13J, Pre-Fire Plan, Unit 2 Reactor Building General Area, Elevation 165 0, Revision 3

Fire Brigade Training

FBP04, Fire Behavior and Essentials, Revision 8

FBP07, Hose Streams, Appliances, and Tools, Revision 6

Fire Brigade Leader Qualification Status Report, date 4/5/18

Fire Brigade Member Qualification Status Report, dated 4/5/18

FPB11, Tactics and Strategy, Revision 7

FPB15, Pre-Fire Plans, Revision 6

IMS-01, Incident Management System, Revision 2

PNLOC 1612A, 4th Quarter Fire Brigade Meeting, Revision 0

Fire Brigade Drills and Critiques

Fire Brigade Drill Third Party Observation Report, performed on 12/7/17

N-PB-OPS-EO-FB-DRILL1, PS01 4th Quarter Fire Drill and Critique, performed on 12/13/17

N-PB-OPS-EO-FB-DRILL1, PS02 4th Quarter Fire Drill and Critique, performed on 12/15/17

N-PB-OPS-EO-FB-DRILL1, PS04 4th Quarter Fire Drill and Critique, performed on 12/7/17

N-PB-OPS-EO-FB-DRILL1, PS05 1st Quarter Unannounced, Backshift Fire Drill and Critique,

performed on 3/22/17

N-PB-OPS-EO-FB-DRILL1, PS05 4th Quarter Fire Drill and Critique, performed on 12/22/17

Transient Combustible, Hot Work, and Ignition Source Permits and Evaluations

Hot Work Permit 0611, RTV-2-14-29010A, Rework Valve/Replace Bonnet, dated 3/1/18

Hot Work Permit 0680, Install New Heat Exchanger, dated 12/11/18

Transient Combustible Permit 1070, Units 2 and 3 Turbine Building, Fire Zone 50-78A,

Temporary Power

Transient Combustible Permit 1071, Unit 3 Turbine Building, Fire Zone 50-78T, Temporary

Power

Transient Combustible Permit 1072, Unit 2 Reactor Building, Fire Zone 1-2, Temporary Power

Transient Combustible Permit 1073, Emergency Cooling Tower, Fire Zone 51-136, Test

Equipment

Transient Combustible Permit 1075, E-42 Switchgear Room, Fire Zone 36-123, Temporary

Instrumentation and Cabling

Completed Tests and Surveillances

R1302419-01, Calibration Check of Alternative Shutdown Panel Reactor Vessel Level

Instruments, completed 10/25/16

RT-0-052-750-2, E2 Diesel Alternative Shutdown Control Functional, completed 3/21/16

RT-M-57E-700-2, Main Control Room Emergency Lighting Battery Yearly Inspection

(20D304-2), completed 1/24/17

RT-M-57E-700-3, Main Control Room Emergency Lighting Battery Yearly Inspection

(30D304-2), completed 1/24/17

RT-M-57E-710-2, Main Control Room Emergency Lighting Battery Discharge Performance Test

(20D304-2), completed 8/11/17

RT-M-57E-710-3, Main Control Room Emergency Lighting Battery Discharge Performance Test

(30D304-2), completed 1/22/18

RT-O-037-375-2, In-Plant Fire Brigade Equipment Inventory and Inspection, completed

2/5/2018

RT-O-037-376-2, Outside Fire Brigade Equipment Inventory and Inspection, completed

2/10/2018

RT-O-037-710-2, Complete Safe Shutdown Emergency Lighting Battery Pack Inspection,

completed 2/10/18

RT-O-037-719-2, Emergency Lighting Inspection (Alternate Shutdown Control Station Access/

Egress Lights), completed 11/2/16

RT-O-037-719-3, Emergency Lighting Inspection (Alternate Shutdown Control Station Access/

Egress Lights), completed 11/6/17

RT-O-100-505-2, Emergency Operating Procedure Tool Inventory, completed 12/6/17

RT-O-100-580-2, B.5.b Tool and Material Inventory, completed 8/2/2017

ST-I-037-223-2, Unit 2 4 Kilo-Volt Switchgear and Battery Room and Radwaste 135 Corridor

Smoke Detectors Functional Test, completed 6/3/15

ST-I-037-223-2, Unit 2 4 Kilo-Volt Switchgear and Battery Room and Radwaste 135 Corridor

Smoke Detectors Functional Test, completed 8/3/17

ST-I-037-276-3, Reactor Building Elevation 165 Smoke Detectors Functional Test, completed

1/27/15

ST-I-037-276-3, Reactor Building Elevation 165 Smoke Detectors Functional Test, completed

7/28/17

ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional

Test, completed 6/23/15

ST-I-037-284-2, Fan Room (Room #381, Radwaste, Elevation 165) Smoke Detectors Functional

Test, completed 1/13/17

ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 10/20/16

ST-I-037-288-2, Cable Spreading Room Smoke Detectors Functional Test, completed 6/22/17

ST-I-037-293-2, Recirculation Motor-Generator Set Lube Oil Pump 116 Smoke Detectors

Functional Test, completed 5/11/17

ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air

Flow Test, completed 10/10/17

ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air

Flow Test, completed 5/31/16

ST-I-037A-310-2, Cable Spreading and Computer Room Cardox Simulated Actuation and Air

Flow Test, completed 10/10/17

ST-M-037-311-2, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire

Barriers, completed 6/8/12

ST-M-037-311-3, Detailed Visual Inspection of Penetration Seals and Difficult to View Fire

Barriers, completed 12/21/17

ST-M-037-314-2, Visual Inspection of Encapsulated Electrical Raceways, completed 6/14/16

ST-M-037D-380-2, Diesel Driven Fire Pump Inspection, completed 1/1/17

ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165) Sprinkler System

Actuation, completed 3/14/16

ST-O-037B-314-2, Fan Room (Room #381, Radwaste Elevation 165) Sprinkler System

Actuation, completed 3/25/18

ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Kilo-Volt Switchgear Rooms, and Radwaste Corridor

Area Sprinkler System Actuation, completed 7/10/14

ST-O-037B-323-2, Unit 2 Battery Rooms, 4 Kilo-Volt Switchgear Rooms, and Radwaste Corridor

Area Sprinkler System Actuation, completed 7/9/16

ST-O-037B-381-2, Underground Fire Main Flow Test, completed 6/10/15

ST-O-037B-381-2, Underground Fire Main Flow Test, completed 8/8/14

ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, completed 8/6/15

ST-O-037C-330-2, Motor Driven Fire Pump Flow Rate Test, completed 12/13/16

ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 1/23/18

ST-O-037C-360-2, Motor Driven Fire Pump Operability Test, completed 2/21/18

ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 11/25/15

ST-O-037D-340-2, Diesel Driven Fire Pump Flow Rate Test, completed 1/17/17

ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed 1/9/18

ST-O-037D-370-2, Diesel Driven Fire Pump Operability Test, completed 2/7/18

Issue Reports (* written as a result of the NRC inspection)

00450846 01109076 01275720 01492237 01521603

01581135 02386737 02421301 02451017 02451647

2478057 02661579 02697843 02699896 02718710

03962962 03980676 04000043 04080702 04082065

04084069 04084077 04102768 04115309 04118443

04122474* 04122883* 04122970* 04127608* 04128972*

04129171*

Work Orders

4319703 4595771 4648804 R1298970 R1326279

Operating Experience

NRC Information Notice 1997-48, Inadequate or Inappropriate Interim Fire Protection

Compensatory Measures

NRC Information Notice 2013-02, Issues Potentially Affecting Nuclear Facility Fire Safety

NRC Information Notice 2013-06, Corrosion in Fire Protection Piping Due to Air and Water

Interaction

NRC Information Notice 2013-09, Compressed Flammable Gas Cylinders and Associated

Hazards

NRC Information Notice 2014-10, Potential Circuit Failure-Induced Secondary Fires or

Equipment Damage

NRC Information Notice 2014-15, Inadequate Controls of Respiratory Protection Accessibility,

Training, and Maintenance

NRC Information Notice 2015-02, Anti-Freeze Agents in Fire Water Sprinkler Systems

NRC Regulatory Issue Summary 2005-07, Compensatory Measures to Satisfy the Fire

Protection Program Requirements

Miscellaneous Documents

Bisco Report #748-49, Fire Test Configuration for a Three-Hour Rated Fire Seal Utilizing Bisco

SF-20 Where a Steel Sleeve Condition with Pipe Penetrant Exists, dated 7/9/81

NLO B.5.b. Task List

NUMARC 93-01, Industry Guideline for Monitoring the Effectiveness of Maintenance at

Nuclear Power Plants, Revision 4A

NUREG 1552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants,

January 1999

PLORT 1610E, Extensive Damage Mitigation Guidelines, Revision 0

PLOT 2305, Extensive Damage Mitigation Guidelines 1.0 and 2.0, Revision 1

PM-1120, Evaluation of B.5.b Mitigation Strategies, Revision 0

Units 2 and 3 Fire Protection System 37 Health Reports, dated 4/4/18