Press Release-IV-19-006, NRC Proposes $14,500 Fine to Team Industrial Service, Inc
ML19067A209 | |
Person / Time | |
---|---|
Issue date: | 03/08/2019 |
From: | Office of Public Affairs Region IV |
To: | |
Category:Press Release | |
References | |
Press Release-IV-19-006 | |
Download: ML19067A209 (1) | |
Similar Documents from Office of Public Affairs Region IV | |
---|---|
Category:Press Release
MONTHYEARML24276A1792024-09-10010 September 2024
[Table view]Some use of "" in your query was not closed by a matching "".News Release-IV-24-015: NRC Names New Resident Inspector at Diablo Canyon Nuclear Power Plant ML24276A1782024-09-0909 September 2024 News Release-IV-24-014: NRC Begins Special Inspection at South Texas Project Nuclear Power Plant ML24276A1772024-09-0909 September 2024 News Release-IV-24-013: NRC Names New Resident Inspector at Waterford Nuclear Power Plant ML24214A2372024-07-18018 July 2024 News Release-IV-24-012: NRC Names New Resident Inspector at the Wolf Creek Nuclear Power Plant ML24214A2342024-07-0101 July 2024 News Release-IV-24-011: NRC Names New Resident Inspector at Arkansas Nuclear One ML24184B5242024-06-17017 June 2024 News Release-IV-24-010: NRC Names New Senior Resident Inspector at Arkansas Nuclear One ML24064A0992024-02-12012 February 2024 News Release-IV-24-007: NRC Names New Senior Resident Inspector at the Columbia Generating Station ML24058A2762024-01-30030 January 2024 News Release-IV-24-006: NRC to Hold a Regulatory Conference with Empire Wireline on Feb. 20 to Discuss a Proposed Violation ML24058A2792024-01-12012 January 2024 News Release-IV-24-003: NRC Proposes $35,000 Civil Penalty to Radiation Solutions ML24058A2782024-01-0808 January 2024 News Release-IV-24-002: NRC Names Henry Strittmatter as Resident Inspector at the Comanche Peak Nuclear Power Plant ML24058A2772024-01-0303 January 2024 News Release-IV-24-001: NRC Names New Senior Resident Inspector at South Texas Project Nuclear Power Plant ML24052A3282023-12-14014 December 2023 News Release-IV-23-012: NRC to Hold Virtual Meeting Dec. 21 to Seek Public Comments on Draft Environmental Report for Comanche Peak License Renewal ML24052A2902023-11-20020 November 2023 News Release-IV-23-010: NRC Names Jason Brodlowicz Resident Inspector at the Columbia Generating Station ML24052A0562023-08-15015 August 2023 News Release-IV-23-009: NRC Names Eric Powell Resident Inspector at River Bend Nuclear Power Plant ML24052A0552023-08-15015 August 2023 News Release-IV-23-008: NRC Names New Resident Inspector at Cooper Nuclear Power Plant ML24047A3052023-07-10010 July 2023 News Release-IV-23-007: NRC Names Nathan Brown Resident Inspector at Callaway Nuclear Power Plant ML24047A2672023-06-30030 June 2023 News Release-IV-23-006: NRC Names Leanne Flores Resident Inspector at South Texas Project Nuclear Power Plant ML24047A2662023-06-21021 June 2023 News Release-IV-23-005: NRC Schedules a Regulatory Conference with Entergy Operations ML24045A2592023-04-13013 April 2023 News Release-IV-23-004: NRC Schedules Public Meeting to Discuss Diablo Canyon Nuclear Power Plant Performance and the License Renewal Process ML24045A2602023-04-11011 April 2023 News Release-IV-23-003: NRC to Conduct Open House to Discuss 2022 Performance of Columbia Generating Station ML23163A0512023-02-27027 February 2023 News Release-IV-23-002: NRC Names Scott Schwind Senior Resident Inspector at Callaway Nuclear Power Plant ML23052A1082023-01-12012 January 2023 News Release-IV-23-001: NRC Proposes $16,000 Civil Penalty to the Hawaii Agriculture Research Center ML22270A0812022-09-13013 September 2022 News Release-IV-22-012: NRC Finalizes White Finding at the Waterford Nuclear Power Plant ML22215A2112022-07-20020 July 2022 News Release-IV-22-011: NRC Schedules a Regulatory Conference with Entergy Operations ML22199A0712022-06-15015 June 2022 News Release-IV-22-009: NRC Proposes $8,000 Fine to Advanced Inspection Technologies Inc ML22199A0692022-06-13013 June 2022 News Release-IV-22-007: NRC Names New Senior Resident Inspector at the Diablo Canyon Nuclear Power Plant ML22199A0702022-06-13013 June 2022 News Release-IV-22-008: NRC Begins Special Inspection at Grand Gulf Nuclear Power Plant ML22199A0682022-06-0606 June 2022 News Release-IV-22-006: NRC Names New Resident Inspector at the Grand Gulf Nuclear Power Plant ML22153A1322022-05-23023 May 2022 News Release-IV-22-005: NRC Issues Confirmatory Order to Avera Mckennan ML22131A1542022-05-0404 May 2022 News Release-IV-22-004: NRC to Hold Virtual Meeting to Discuss 2021 Performance of 12 Nuclear Power Plants ML22131A1532022-04-25025 April 2022 News Release-IV-22-003-: NRC Names New Resident Inspector at Callaway Nuclear Power Plant Press Release-II-22-001, NRC Proposes $7,000 Fine to Marian Medical Services2022-02-17017 February 2022 Press Release-II-22-001: NRC Proposes $7,000 Fine to Marian Medical Services Press Release-IV-22-002, NRC Schedules a Regulatory Conference with Energy Northwest2022-02-17017 February 2022 Press Release-IV-22-002: NRC Schedules a Regulatory Conference with Energy Northwest Press Release-IV-21-014, NRC Proposes $45,000 Fine to Terracon Consultants, Inc2021-10-0101 October 2021 Press Release-IV-21-014: NRC Proposes $45,000 Fine to Terracon Consultants, Inc Press Release-IV-21-013, NRC Proposes $150,000 Civil Penalty to Entergy Operations, Inc2021-10-0101 October 2021 Press Release-IV-21-013: NRC Proposes $150,000 Civil Penalty to Entergy Operations, Inc Press Release-IV-21-012, NRC to Hold Virtual Regulatory Performance Meeting to Discuss Supplemental Inspection Results for Grand Gulf Nuclear Power Plant2021-09-30030 September 2021 Press Release-IV-21-012: NRC to Hold Virtual Regulatory Performance Meeting to Discuss Supplemental Inspection Results for Grand Gulf Nuclear Power Plant Press Release-IV-21-011, NRC Names New Resident Inspector at the Cooper Nuclear Station2021-08-17017 August 2021 Press Release-IV-21-011: NRC Names New Resident Inspector at the Cooper Nuclear Station Press Release-IV-21-010, NRC Proposes $45,000 Fine to Idaho State University for Agency Requirement Violations2021-07-26026 July 2021 Press Release-IV-21-010: NRC Proposes $45,000 Fine to Idaho State University for Agency Requirement Violations Press Release-IV-21-009, NRC to Hold Virtual Meeting to Discuss 2020 Performance of Callaway Nuclear Power Plant2021-07-13013 July 2021 Press Release-IV-21-009: NRC to Hold Virtual Meeting to Discuss 2020 Performance of Callaway Nuclear Power Plant Press Release-IV-21-008, NRC Names New Senior Resident Inspector at the Palo Verde Nuclear Generating Station2021-06-0707 June 2021 Press Release-IV-21-008: NRC Names New Senior Resident Inspector at the Palo Verde Nuclear Generating Station Press Release-IV-21-007, NRC Names New Senior Resident Inspector at the Columbia Generating Station2021-05-25025 May 2021 Press Release-IV-21-007: NRC Names New Senior Resident Inspector at the Columbia Generating Station Press Release-IV-21-006, NRC Names New Resident Inspector at the Columbia Generating Station2021-05-18018 May 2021 Press Release-IV-21-006: NRC Names New Resident Inspector at the Columbia Generating Station Press Release-IV-21-005, NRC to Hold Virtual Meeting to Discuss 2020 Performance of 10 Region IV Nuclear Power Plants2021-04-30030 April 2021 Press Release-IV-21-005: NRC to Hold Virtual Meeting to Discuss 2020 Performance of 10 Region IV Nuclear Power Plants Press Release-IV-21-004, NRC Schedules a Pre-Decisional Enforcement Teleconference with Idaho State University2021-04-30030 April 2021 Press Release-IV-21-004: NRC Schedules a Pre-Decisional Enforcement Teleconference with Idaho State University Press Release-IV-21-003, NRC to Hold Virtual Meeting to Discuss 2020 Performance of Grand Gulf Nuclear Power Plant2021-03-19019 March 2021 Press Release-IV-21-003: NRC to Hold Virtual Meeting to Discuss 2020 Performance of Grand Gulf Nuclear Power Plant Press Release-IV-21-002, NRC Schedules Regulatory Teleconference with Palo Verde Nuclear Generating Station2021-01-26026 January 2021 Press Release-IV-21-002: NRC Schedules Regulatory Teleconference with Palo Verde Nuclear Generating Station Press Release-IV-21-001, NRC Names New Resident Inspector at the Palo Verde Nuclear Generating Station2021-01-19019 January 2021 Press Release-IV-21-001: NRC Names New Resident Inspector at the Palo Verde Nuclear Generating Station Press Release-IV-20-023, NRC Names New Resident Inspector at Arkansas Nuclear One2020-12-16016 December 2020 Press Release-IV-20-023: NRC Names New Resident Inspector at Arkansas Nuclear One Press Release-IV-20-027, NRC Schedules Regulatory Teleconference with Entergy Operations2020-12-0202 December 2020 Press Release-IV-20-027: NRC Schedules Regulatory Teleconference with Entergy Operations Press Release-IV-20-026, NRC Names New Senior Resident Inspector at the Waterford Nuclear Power Plant2020-11-23023 November 2020 Press Release-IV-20-026: NRC Names New Senior Resident Inspector at the Waterford Nuclear Power Plant 2024-09-09 |
Text
No: IV-19-006 March 8, 2019
Contact:
Victor Dricks, 817-200-1128 NRC Proposes $14,500 Fine to Team Industrial Service, Inc.
The Nuclear Regulatory Commission is proposing a $14,500 fine to Team Industrial Service, Inc., of Alvin, Texas, for failing to lock a radiography device before bringing it aboard a U.S. Navy vessel to examine pipe welds.
The NRC considers the violation significant because a safety barrier was not in place while the device was being hand-carried aboard a U.S. Navy ship, which could have resulted in an inadvertent exposure. NRC investigators concluded the violation was willful, as described in a Jan. 4, 2019, inspection report.
Company officials responded to the NRCs preliminary finding in a letter dated Feb. 6, 2019.
The company has 30 days to dispute the fine or request involvement of a neutral third-party mediator to resolve the issue.