PY-CEI-NRR-0860, Advises That Temporary 10CFR50.54(p) Change to Security Plan Will Now Expire on 880715 to Due Extension of Const Schedule

From kanterella
Jump to navigation Jump to search
Advises That Temporary 10CFR50.54(p) Change to Security Plan Will Now Expire on 880715 to Due Extension of Const Schedule
ML20154M240
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 05/24/1988
From: Kaplan A
CLEVELAND ELECTRIC ILLUMINATING CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
PY-CEI-NRR-0860, PY-CEI-NRR-860, NUDOCS 8806010221
Download: ML20154M240 (1)


Text

TliE CLEVELAND ELECTRIC ILlUMIN ATING COMPANY P. O. BOX 97 a PEARY, OHIO 44081 a TELEPHONE (216) 259-3737 a ADDRESS-to CENTER ROAD Serving The Best Location in the Nation PERRY NUCLEAR POWER PLANT Al Kaplan m mse May 24, 1988 PY-CEI/NRR-0860 L U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Perry Nuclear Power Plant Docket No. 50-440 Extended Compensacory Measures Gentlemen:

By letters dated October 30, 1987 (PY-CEI/01E-0287 L) and November 20, 1987 (PY-CEI/NRR-0748 L), the Cleveland Electric Illuminating Company (CEI) notified the NRC of extended compensatory measures being implemented at the Perry Nuclear Power Plant during the construction of an addition to the existing Maintenance Building. This construction was scheduled to be completed by May 31, 1988. The construction schedule has since been e.v. tended beyond that date.

Therefore, the associated temporary 50.54(p) change to the security plan will now expire on July 15, 1988.

If you have any questions, please feel free to call.

Very truly yours, Q /r Al Kaplan Vice President Nuclear Group AK:njc cc: T. Colburn K. Connaughton USNRC Region III O Y I