NRC 2012-0081, Notification of Readiness for NRC 95001 Inspection
ML12262A468 | |
Person / Time | |
---|---|
Site: | Point Beach |
Issue date: | 09/17/2012 |
From: | Meyer L Point Beach |
To: | NRC/RGN-III, Document Control Desk |
References | |
IR-12-504, NRC 2012-0081 | |
Download: ML12262A468 (1) | |
Similar Documents at Point Beach | |
---|---|
Category:Letter type:NRC
MONTHYEARNRC 2023-0013, Response to Regulatory Information Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-07-0707 July 2023
[Table view]Response to Regulatory Information Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations NRC 2023-0006, Post-Exam Submittal Cover Letter2023-03-0101 March 2023 Post-Exam Submittal Cover Letter NRC 2023-0005, Report of Changes to Emergency Plan2023-02-21021 February 2023 Report of Changes to Emergency Plan NRC 2022-0032, Sixth 10-Year Interval Inservice Testing (1ST) Program Plan2022-09-30030 September 2022 Sixth 10-Year Interval Inservice Testing (1ST) Program Plan NRC 2022-0025, License Amendment Request 295, Beacon Power Distribution Monitoring System2022-09-26026 September 2022 License Amendment Request 295, Beacon Power Distribution Monitoring System NRC 2022-0019, Report of Changes to Emergency Plan2022-07-13013 July 2022 Report of Changes to Emergency Plan NRC 2022-0022, Response to Request for Supplemental Information (Rsi) Regarding License Amendment Request (LAR) 297, Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2,2022-07-11011 July 2022 Response to Request for Supplemental Information (Rsi) Regarding License Amendment Request (LAR) 297, Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, NRC 2022-0015, Fall 2021 Unit 2 (U2R38) Steam Generator Tube Inspection Report2022-04-27027 April 2022 Fall 2021 Unit 2 (U2R38) Steam Generator Tube Inspection Report NRC 2022-0014, 2021 Annual Monitoring Report2022-04-14014 April 2022 2021 Annual Monitoring Report NRC 2021-0012, Core Operating Limits Report (COLR) Unit 1 Cycle 41 (U 1 C41)2022-04-0707 April 2022 Core Operating Limits Report (COLR) Unit 1 Cycle 41 (U 1 C41) NRC 2022-0003, License Amendment Request 296, Application for Technical Specification Improvement to Eliminate Requirements for Post-Accident Systems Using the Consolidated Line Item Improvement Process2022-03-25025 March 2022 License Amendment Request 296, Application for Technical Specification Improvement to Eliminate Requirements for Post-Accident Systems Using the Consolidated Line Item Improvement Process NRC 2022-0006, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2022-02-22022 February 2022 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections NRC 2022-0004, Report of Changes to Emergency Plan2022-02-0909 February 2022 Report of Changes to Emergency Plan NRC 2022-0005, Refueling Outage U2R38 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2022-02-0101 February 2022 Refueling Outage U2R38 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2022-0001, Report of Changes to Emergency Plan2022-01-11011 January 2022 Report of Changes to Emergency Plan NRC 2021-0046, Core Operating Limits Report (COLR) Unit 2 Cycle 39 (U2C39) and Changes to Unit 1 COLR Unit 1 Cycle 40 (U1C40)2021-10-28028 October 2021 Core Operating Limits Report (COLR) Unit 2 Cycle 39 (U2C39) and Changes to Unit 1 COLR Unit 1 Cycle 40 (U1C40) NRC 2021-0031, Registration of Holtec Hi STORM Casks HI-STORM-37-054, HI-STORM-37-055, and HI-STORM-37-0562021-07-15015 July 2021 Registration of Holtec Hi STORM Casks HI-STORM-37-054, HI-STORM-37-055, and HI-STORM-37-056 NRC 2021-0027, Registration of Holtec Historm Casks HISTORM-37-051, HISTORM-37-052, and HISTORM-37-0532021-06-30030 June 2021 Registration of Holtec Historm Casks HISTORM-37-051, HISTORM-37-052, and HISTORM-37-053 NRC 2021-0028, Generic Letter 2004-02 Containment Sump Debris Transport Calculation Non-Conservatism2021-06-23023 June 2021 Generic Letter 2004-02 Containment Sump Debris Transport Calculation Non-Conservatism NRC 2021-0021, 2020 Annual Monitoring Report2021-04-29029 April 2021 2020 Annual Monitoring Report NRC 2021-0019, Response to Regulatory Information Summary 2021-01 Preparation and Scheduling of Operator Licensing Examinations2021-04-22022 April 2021 Response to Regulatory Information Summary 2021-01 Preparation and Scheduling of Operator Licensing Examinations NRC-2021-0010, CFR 50.59 Evaluation and Commitment Change Summary Report2021-04-0202 April 2021 CFR 50.59 Evaluation and Commitment Change Summary Report NRC-2021-0011, Technical Specification Bases and Technical Requirement Manual Change Summary2021-04-0202 April 2021 Technical Specification Bases and Technical Requirement Manual Change Summary NRC 2021-0006, Report of Changes to Emergency Plan2021-03-18018 March 2021 Report of Changes to Emergency Plan NRC 2021-0005, Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 2004-022021-02-11011 February 2021 Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 2004-02 NRC 2021-0002, Refueling Outage U1 R39 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2021-01-21021 January 2021 Refueling Outage U1 R39 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2021-0003, Refueling 39 (U1 R39) Reactor Coolant Pump Analytical Evaluation Report2021-01-21021 January 2021 Refueling 39 (U1 R39) Reactor Coolant Pump Analytical Evaluation Report NRC 2021-0001, Report of Changes to Emergency Plan2021-01-13013 January 2021 Report of Changes to Emergency Plan NRC 2020-0044, Response to Request for Additional Information Request for Exemption from 10 CFR 73, Appendix B, Section VI Regarding Annual Force-On-Force Exercise2020-12-0808 December 2020 Response to Request for Additional Information Request for Exemption from 10 CFR 73, Appendix B, Section VI Regarding Annual Force-On-Force Exercise NRC 2020-0032, Application for Subsequent Renewed Facility Operating Licenses2020-11-16016 November 2020 Application for Subsequent Renewed Facility Operating Licenses NRC 2020-0039, Core Operating Limits Report (COLR) Unit 1 Cycle 40 (U1 C40)2020-11-0202 November 2020 Core Operating Limits Report (COLR) Unit 1 Cycle 40 (U1 C40) NRC 2020-0031, NextEra Energy Point Beach, LLC Response to Apparent Violation in NRC Inspection Report 05000266/2020012, 05000301/2020012: EA-20-0812020-10-0505 October 2020 NextEra Energy Point Beach, LLC Response to Apparent Violation in NRC Inspection Report 05000266/2020012, 05000301/2020012: EA-20-081 NRC 2020-0029, Supplement to License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss2020-09-15015 September 2020 Supplement to License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss NRC 2020-0024, Response to Request for Additional Information Request for Exemption from Certain Operator Requalification Requirements2020-08-17017 August 2020 Response to Request for Additional Information Request for Exemption from Certain Operator Requalification Requirements NRC 2020-0020, License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss2020-08-13013 August 2020 License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss NRC 2020-0023, NextEra Energy Point Beach, LLC - Revised Response to Regulatory Information Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations2020-08-12012 August 2020 NextEra Energy Point Beach, LLC - Revised Response to Regulatory Information Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations NRC 2020-0021, Response to NRC Inspection Report and Preliminary White Finding2020-08-12012 August 2020 Response to NRC Inspection Report and Preliminary White Finding NRC 2020-0018, Report of Changes to Emergency Plan2020-07-15015 July 2020 Report of Changes to Emergency Plan NRC-2020-0016, Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic2020-06-12012 June 2020 Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic NRC 2020-0012, Refueling Outage U2R37 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2020-05-20020 May 2020 Refueling Outage U2R37 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2020-0008, Report of Changes to Emergency Plan2020-04-0606 April 2020 Report of Changes to Emergency Plan NRC 2020-0007, Core Operating Limits Report (COLR) Unit 2 Cycle 28 (U2C38)2020-03-27027 March 2020 Core Operating Limits Report (COLR) Unit 2 Cycle 28 (U2C38) NRC 2020-0003, License Amendment Request 289: Tornado Missile Protection Licensing Basis2020-02-0606 February 2020 License Amendment Request 289: Tornado Missile Protection Licensing Basis NRC 2020-0001, Pressure Temperature Limits Report (PTLR)2020-01-0909 January 2020 Pressure Temperature Limits Report (PTLR) NRC 2019-0044, Report of Changes to Emergency Plan2019-11-0101 November 2019 Report of Changes to Emergency Plan NRC 2019-0036, Submittal of 2018 Update to Final Safety Analysis Report2019-10-18018 October 2019 Submittal of 2018 Update to Final Safety Analysis Report NRC 2019-0037, Technical Specification Bases Change Summary2019-10-18018 October 2019 Technical Specification Bases Change Summary NRC 2019-0034, Technical Requirements Manual Change Summary2019-10-18018 October 2019 Technical Requirements Manual Change Summary NRC 2019-0032, CFR 50.59 Evaluation and Commitment Change Summary Report2019-10-18018 October 2019 CFR 50.59 Evaluation and Commitment Change Summary Report NRC 2019-0042, NextEra Energy Point Beach, LLC, Relief Request 1-RR-13 and 2-RR-13, Response to Request for Additional Information2019-10-17017 October 2019 NextEra Energy Point Beach, LLC, Relief Request 1-RR-13 and 2-RR-13, Response to Request for Additional Information 2023-07-07 Category:Inspection Plan MONTHYEARML24036A2652024-02-0505 February 2024
[Table view]Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 IR 05000266/20220062023-03-0101 March 2023 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022006 and 05000301/2022006) ML23003A8022023-01-0303 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22256A3182022-09-13013 September 2022 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection Report 05000266/2023010 05000301/2023010 IR 05000266/20220052022-08-26026 August 2022 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022005 and 05000301/2022005) ML22175A2002022-06-27027 June 2022 Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information: Inspection Report 05000266/2022004: 05000301/2022004 ML22172A2132022-06-22022 June 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML22173A0172022-06-22022 June 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Point Beach Nuclear Plant IR 05000266/20210062022-03-0202 March 2022 Annual Assessment Letter for Point Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021006 and 05000301/2021006) ML22041B0752022-02-10010 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000266/2022002 ML21253A1672021-09-10010 September 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000266/2022010 05000301/2022010 IR 05000266/20210052021-09-0101 September 2021 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021005 and 05000301/2021005) ML21214A2812021-08-0202 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21180A2302021-06-29029 June 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2021004 and 05000301/2021004 ML21074A3962021-03-15015 March 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000266/2021010; 05000301/2021010 IR 05000266/20200062021-03-0404 March 2021 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020006 and 05000301/2020006) IR 05000266/20200052020-09-0101 September 2020 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020005 and 05000301/2020005) ML20218A4322020-08-0505 August 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2020004 ML20168A8912020-06-15015 June 2020 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20190062020-03-0303 March 2020 Annual Assessment Letter for Point Beach Nuclear Plants, Units 1 and 2 (Report 05000266/2019006 and 05000301/2019006) IR 05000266/20190052019-08-28028 August 2019 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2019005 and 05000301/2019005) ML19190A1532019-07-0909 July 2019 Ltr. 07/09/19 Point Beach Nuclear Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000266/2019012; 05000301/2019012 (DRS-G.Hausman) ML19136A1402019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19094B1182019-04-0404 April 2019 Ltr. 04/04/19 Point Beach Nuclear Plant, Units 1 and 2 - Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the EQ Program; Inspection Report 05000266/2019013 and 05000301/2019013 (DRS-B.Jose) IR 05000266/20180062019-03-0404 March 2019 Annual Assessment Letter for Point Beach Nuclear Plant (Report 05000266/2018006 and 05000301/2018006) ML19037A3102019-02-0505 February 2019 Ltr. 02/05/19 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection; Inspection Report 05000266/2019412; 05000301/2019412 (DRS-G.Hausman) ML19024A2772019-01-24024 January 2019 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2019001 (DRS-M.Domke) IR 05000266/20180052018-08-28028 August 2018 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2018005 and 05000301/2018005) IR 05000266/20170062018-03-0202 March 2018 Annual Assessment Letter for Point Beach Plant, Units 1 and 2 (Report 05000266/2017006 and 05000301/2017006) IR 05000266/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000266/2017005 and 05000301/2017005) ML17088A7242017-03-29029 March 2017 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000266/2017007; 05000301/2017007 IR 05000266/20160062017-03-0101 March 2017 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2016006 and 05000301/2016006) ML17039B0182017-02-0808 February 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Point Beach Nuclear Plant, Units 1 and 2 - Inspection Report 05000266/2017008; 05000301/2017008 IR 05000266/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant Units 1 and 2 (Report 05000266/2016005; 05000301/2016005) IR 05000266/20150062016-03-0202 March 2016 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Inspection Report 05000266/2015006 and 05000301/2015006) IR 05000266/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2015005; 05000301/2015005) ML15131A3132015-05-0808 May 2015 Ltr. 05/08/15 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for an NRC Triennial Permanent Modifications and 10 CFR 50.59 (Mod/50.59) Baseline Inspection 05000266/2015010; 05000301/2015010 (Jjc) ML15124A9012015-05-0101 May 2015 Ltr. 05/01/15 Point Beach Nuclear Plant, Unit 2 - Notification of NRC Inspection and Request for Information (Msh) IR 05000266/20140012015-03-0404 March 2015 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2014001; 05000301/2014001) ML15050A2702015-02-19019 February 2015 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 ML14245A1662014-09-0202 September 2014 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20130012014-03-0404 March 2014 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2013001; 05000301/2013001) ML14038A3472014-02-0606 February 2014 ISI Request for Information ML13246A2212013-09-0303 September 2013 2013 Point Beach MOC Letter Combined ML13172A4072013-06-20020 June 2013 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000266-13-010; 05000301-13-010 ML13129A1952013-05-0909 May 2013 Ltr 5/9/13 Point Beach Ti 2515-182 Phase 2 Request for Information IR 05000266/20120012013-03-0404 March 2013 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (05000266/2012001; 05000301/2012001) 2024-02-05 |
Text
/ POINT BEACH September 17,2012 NRC 2012-0081 10 CFR 50.4 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 Notification of Readiness for NRC 95001 Inspection
Reference:
NRC letter to NextEra Energy Point Beach, LLC, dated July 24, 2012, Final Significance Determination of a White Finding with Assessment Followup and Notice of Violation; NRC lnspection Report Nos. 05000266/2012504 and 05000301/2012504; Point Beach Nuclear Plant, Units 1 and 2 (MLI 2206A514)
By letter dated July 24,2012 (Reference), the Nuclear Regulatory Commission (NRC) informed NextEra Energy Point Beach, LLC (NextEra) of plans for a future inspection of Point Beach Nuclear Plant (PBNP), in accordance with lnspection Procedure 95001, "Supplemental lnspection for One or Two White Inputs in a Strategic Performance Area," for the logic error in a NextEra Emergency Plan Implementing Procedure. Additionally, the NRC determined that NextEra did not initiate protective action recommendations when the projected dose to an individual was 1 rem beyond the 10-mile plume exposure pathway.
This letter is to notify the NRC that PBNP will be ready for the 95001 inspection on January 7,2013. Accordingly, NextEra requests the NRC to commence the 95001 inspection on January 7,2013.
This letter contains no new Regulatory Commitments and no revisions to existing Regulatory Commitments.
Very truly yours, NextEra Energy Point Beach, LLC d//ite Vice President cc: Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241