MONTHYEARML24295A0862024-10-21021 October 2024 Notification of NRC Baseline Inspection and Request for Information Inspection Report 0500026/2025002 IR 05000266/20240052024-08-21021 August 2024 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2024005 and 05000301/2024005) IR 05000266/20230062024-02-28028 February 2024 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2023006 and 05000301/2023006) ML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 IR 05000266/20220062023-03-0101 March 2023 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022006 and 05000301/2022006) ML23003A8022023-01-0303 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22256A3182022-09-13013 September 2022 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection Report 05000266/2023010 05000301/2023010 IR 05000266/20220052022-08-26026 August 2022 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022005 and 05000301/2022005) ML22175A2002022-06-27027 June 2022 Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information: Inspection Report 05000266/2022004: 05000301/2022004 ML22173A0172022-06-22022 June 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Point Beach Nuclear Plant ML22172A2132022-06-22022 June 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000266/20210062022-03-0202 March 2022 Annual Assessment Letter for Point Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021006 and 05000301/2021006) ML22041B0752022-02-10010 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000266/2022002 ML21253A1672021-09-10010 September 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000266/2022010 05000301/2022010 IR 05000266/20210052021-09-0101 September 2021 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021005 and 05000301/2021005) ML21214A2812021-08-0202 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21180A2302021-06-29029 June 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2021004 and 05000301/2021004 ML21074A3962021-03-15015 March 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000266/2021010; 05000301/2021010 IR 05000266/20200062021-03-0404 March 2021 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020006 and 05000301/2020006) IR 05000266/20200052020-09-0101 September 2020 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020005 and 05000301/2020005) ML20218A4322020-08-0505 August 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2020004 ML20168A8912020-06-15015 June 2020 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20190062020-03-0303 March 2020 Annual Assessment Letter for Point Beach Nuclear Plants, Units 1 and 2 (Report 05000266/2019006 and 05000301/2019006) IR 05000266/20190052019-08-28028 August 2019 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2019005 and 05000301/2019005) ML19190A1532019-07-0909 July 2019 Ltr. 07/09/19 Point Beach Nuclear Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000266/2019012; 05000301/2019012 (DRS-G.Hausman) ML19136A1402019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19094B1182019-04-0404 April 2019 Ltr. 04/04/19 Point Beach Nuclear Plant, Units 1 and 2 - Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the EQ Program; Inspection Report 05000266/2019013 and 05000301/2019013 (DRS-B.Jose) IR 05000266/20180062019-03-0404 March 2019 Annual Assessment Letter for Point Beach Nuclear Plant (Report 05000266/2018006 and 05000301/2018006) ML19037A3102019-02-0505 February 2019 Ltr. 02/05/19 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection; Inspection Report 05000266/2019412; 05000301/2019412 (DRS-G.Hausman) ML19024A2772019-01-24024 January 2019 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2019001 (DRS-M.Domke) IR 05000266/20180052018-08-28028 August 2018 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2018005 and 05000301/2018005) IR 05000266/20170062018-03-0202 March 2018 Annual Assessment Letter for Point Beach Plant, Units 1 and 2 (Report 05000266/2017006 and 05000301/2017006) IR 05000266/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000266/2017005 and 05000301/2017005) ML17088A7242017-03-29029 March 2017 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000266/2017007; 05000301/2017007 IR 05000266/20160062017-03-0101 March 2017 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2016006 and 05000301/2016006) ML17039B0182017-02-0808 February 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Point Beach Nuclear Plant, Units 1 and 2 - Inspection Report 05000266/2017008; 05000301/2017008 IR 05000266/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant Units 1 and 2 (Report 05000266/2016005; 05000301/2016005) IR 05000266/20150062016-03-0202 March 2016 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Inspection Report 05000266/2015006 and 05000301/2015006) IR 05000266/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2015005; 05000301/2015005) ML15131A3132015-05-0808 May 2015 Ltr. 05/08/15 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for an NRC Triennial Permanent Modifications and 10 CFR 50.59 (Mod/50.59) Baseline Inspection 05000266/2015010; 05000301/2015010 (Jjc) ML15124A9012015-05-0101 May 2015 Ltr. 05/01/15 Point Beach Nuclear Plant, Unit 2 - Notification of NRC Inspection and Request for Information (Msh) IR 05000266/20140012015-03-0404 March 2015 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2014001; 05000301/2014001) ML15050A2702015-02-19019 February 2015 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 ML14245A1662014-09-0202 September 2014 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20130012014-03-0404 March 2014 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2013001; 05000301/2013001) ML14038A3472014-02-0606 February 2014 ISI Request for Information ML13246A2212013-09-0303 September 2013 2013 Point Beach MOC Letter Combined 2024-08-21
[Table view] Category:Letter
MONTHYEARML24295A1142024-10-31031 October 2024 Suppl Env Audit Summary Letter W/Enclosure 1 ML24295A0862024-10-21021 October 2024 Notification of NRC Baseline Inspection and Request for Information Inspection Report 0500026/2025002 L-2024-160, Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41)2024-10-21021 October 2024 Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41) L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-120, LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization2024-10-0808 October 2024 LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000266/2024011 and 05000301/2024011 L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-145, Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency2024-09-0909 September 2024 Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency ML24207A0202024-08-28028 August 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Point Beach Nuclear Plant, Units 1 and 2 (Docket Numbers: 50-0266 and 50-0301) IR 05000266/20240052024-08-21021 August 2024 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2024005 and 05000301/2024005) IR 05000266/20240022024-08-13013 August 2024 Integrated Inspection Report 05000266/2024002 and 05000301/2024002 L-2024-131, Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-08-0909 August 2024 Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review ML24214A3092024-08-0202 August 2024 Confirmation of Initial License Examination L-2024-113, License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections2024-07-24024 July 2024 License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections ML24194A1802024-07-24024 July 2024 – Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20244012024-07-23023 July 2024 Public - Point Beach Nuclear Plant Cyber Security Inspection Report 05000266/2024401 and 05000301/2024401 ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-116, Preparation and Scheduling of Operator Licensing Examinations2024-07-11011 July 2024 Preparation and Scheduling of Operator Licensing Examinations L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal IR 05000266/20240102024-07-10010 July 2024 Age-Related Degradation Inspection Report 05000266/2024010 and 05000301/2024010 L-2024-105, License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-06-26026 June 2024 License Amendment Request 300, Modify Containment Average Air Temperature Requirements L-2024-107, Schedule for Subsequent License Renewal Environmental Review2024-06-25025 June 2024 Schedule for Subsequent License Renewal Environmental Review ML24176A2242024-06-24024 June 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-093, Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision2024-06-10010 June 2024 Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision IR 05000266/20244202024-06-0505 June 2024 Security Baseline Inspection Report 05000266/2024420 and 05000301/2024420 ML24149A1922024-05-28028 May 2024 Notification of NRC Baseline Inspection and Request for Information ML24141A1382024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection.Docx ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000266/2024301; 05000301/2024301 L-2024-067, Annual Monitoring Report2024-04-26026 April 2024 Annual Monitoring Report ML24116A0402024-04-23023 April 2024 Periodic Update of the Updated Final Safety Analysis Report ML24071A0912024-04-22022 April 2024 Issuance of Relief Request I6-RR-03 - Extension of the Unit 2 Steam Generator Primary Nozzle Dissimilar Metal Welds Sixth 10-Year Inservice Inspection Program Interval IR 05000266/20240012024-04-11011 April 2024 Integrated Inspection Report 05000266/2024001 and 05000301/2024001 L-2024-030, Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-03-27027 March 2024 Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-043, Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules2024-03-25025 March 2024 Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules L-2024-011, and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications IR 05000266/20230062024-02-28028 February 2024 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2023006 and 05000301/2023006) L-2024-020, Refueling Outage Owners Activity Report (OAR-1) Unit 1 for Inservice Inspections2024-02-22022 February 2024 Refueling Outage Owners Activity Report (OAR-1) Unit 1 for Inservice Inspections ML24053A3732024-02-22022 February 2024 Operator Licensing Examination Approval Point Beach, March 2024 ML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-2024-001, Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-01-26026 January 2024 Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24005A3242024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0040 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 September 2, 2014 Mr. Eric McCartney Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2
Dear Mr. McCartney:
On August 6, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Point Beach Nuclear Plant, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2013, through June 30, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined the performance at Point Beach Nuclear Plant, Unit 1, during the most recent quarter was within the Degraded Cornerstone Column (Column 3) of the NRCs Reactor Oversight Process (ROP) Action Matrix because of two inspection findings classified as having low to moderate safety significance (i.e. White) in the Mitigating Systems Cornerstone. One White finding was associated with a coupling failure on the Unit 1 turbine-driven auxiliary feedwater pump that was identified in the fourth quarter of 2012. The other White finding was associated with your failure to implement external flooding wave run-up protection design features as described in the Final Safety Analysis Report (FSAR) and was identified in the first quarter of 2013. This finding was associated with Unit 1 and Unit 2. By letter dated August 9, 2013, NRC Inspection Report 05000266/2013012 and 05000301/2013012, (ML13221A187) the NRC notified you of the final significance of the failure to implement external flooding features and advised you that Unit 1 was assessed to be in the Degraded Cornerstone column.
The NRC determined the performance at Point Beach Nuclear Plant, Unit 2, during the most recent quarter was within the Regulatory Response Column (Column 2) of the NRCs ROP Action Matrix because of one inspection finding classified as having low to moderate safety significance. (i.e. White) in the Mitigating Systems Cornerstone associated with your failure to implement external flooding wave run-up protection design features as described in the FSAR as of the first quarter of 2013.
E. McCartney By letter dated April 16, 2013 (ML13108A121), you notified the NRC that you had completed the evaluation of the circumstances surrounding the degraded performance associated with the Unit 1 coupling failure and were ready for the NRC to assess your evaluation and subsequent corrective actions. On August 9, 2013, the NRC completed a supplemental inspection pursuant to Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area. The NRC Inspection Report 05000266/2013009 (ML13262A523) was transmitted by letter dated September 19, 2013, and stated that although the turbine driven auxiliary feedwater pump finding would not be considered in the Action Matrix after the third quarter of 2013, closure of the finding did not change the status of Unit 1; Unit 1 would remain in the Degraded Cornerstone Column of the ROP Action Matrix until successful completion of an NRC supplemental inspection using Inspection Procedure 95002, Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area.
By letter dated October 29, 2013 (ML13303B690), your staff advised the NRC of your readiness for an NRC Supplemental Inspection using Inspection Procedure 95002. On March 6, 2014, the NRC completed a follow-up supplemental inspection pursuant to Inspection Procedure 95002. On March 28, 2014, the NRC issued a supplemental inspection report 05000266/2014007 and 05000301/2014007 (ML14087A366) which stated that the performance issues associated with the identified flooding finding will remain open beyond the normal four quarters and will not be removed from consideration in the NRCs assessment program until the identified weaknesses are addressed and corrected. When your staff notifies the NRC of your readiness to resume the supplemental inspection, the NRC will re-perform the supplemental inspection in accordance with Inspection Procedure 95002. Point Beach Nuclear Plant, Unit 2 remains in the Regulatory Response Column of the NRCs ROP Action Matrix and will also be assessed as part of the supplemental inspection. The objective of this supplemental inspection will be to verify that your staff adequately evaluated the root causes, contributing causes, extent-of-condition, or extent-of-cause of the safety-significant finding, and that have or plan to implement adequate corrective actions to address the root causes, contributing causes, extent-of-condition, or extent-of-cause and to prevent recurrence of the safety-significant finding.
During this assessment period, the NRC identified a cross-cutting theme in the Problem Identification and Resolution component. Specifically, there were three findings during the current assessment period in addition to the first quarter 2013 White finding (held open) with the cross-cutting aspect of Evaluation (P.2). The NRC determined that a substantive cross-cutting issue associated with P.2 does not exist because the NRC does not have a concern with your staffs scope of effort and current progress in addressing the cross-cutting theme. All of the findings associated with the P.2 aspect are associated with the White flooding finding and our supplemental inspection of your original efforts to address that finding. Also, you are aware of the issues, have a cause analysis that also considered evaluation issues across the plant, have recently identified corrective actions, and are working to address the identified issues. The NRC will continue to monitor your staffs effort and progress in addressing the theme until the theme criteria are no longer met.
E. McCartney As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 reflect this revision to Inspection Manual Chapter (IMC) 0310.
Cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
The enclosed inspection plan lists the inspections scheduled through December 31, 2015.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last 9 months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
The enclosed plan does include a triennial Evaluations of Changes, Tests and Experiments and Permanent Plant Modifications inspection per procedure 71111.17T; a biennial problem Identification and Resolution, inspection per procedure 71152; and a triennial Component and Design Basis inspection per procedure 7111.21.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
E. McCartney In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Jamnes Cameron at 630-829-9833 with any questions you have regarding this letter.
Sincerely,
/RA/
Cynthia D. Pederson Regional Administrator Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27
Enclosure:
Point Beach Nuclear Plant Inspection/Activity Plan cc w/encl: Distribution via LISTSERV
E. McCartney In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Jamnes Cameron at 630-829-9833 with any questions you have regarding this letter.
Sincerely,
/RA/
Cynthia D. Pederson Regional Administrator Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27
Enclosure:
Point Beach Nuclear Plant Inspection/Activity Plan cc w/encl: Distribution via LISTSERV DISTRIBUTION w/encl:
Anthony Bowers RidsNrrDorlLpl3-1 Resource RidsNrrPMPointBeach RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Carmen Olteanu ROPassessment.Resource@nrc.gov DOCUMENT NAME: Point Beach 2014 Mid-Cycle Assessment Letter Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII NAME BBartlett:mt JCameron ABoland CPederson DATE 08/21/14 08/25/14 08/22/14 08/26/14 OFFICIAL RECORD COPY
Page 1 of 2 Point Beach 08/22/2014 09:43:49 Inspection / Activity Plan Report 22 09/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site BI EPR - EP ROUTINE INSPECTION / PI VERIFICATION 2 1 09/08/2014 09/12/2014 IP 7111402 Alert and Notification System Testing 1 09/08/2014 09/12/2014 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 09/08/2014 09/12/2014 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 09/08/2014 09/12/2014 IP 71151 Performance Indicator Verification ISFSI - ISFSI OPERATION AT A SITE INSPECTION 2 1, 2 09/01/2014 09/30/2014 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 1 10/06/2014 10/10/2014 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 10/06/2014 10/10/2014 IP 71124.04 Occupational Dose Assessment ISI BI - INSERVICE INSPECTION UNIT 1 1 1 10/05/2014 10/29/2014 IP 7111108P Inservice Inspection Activities - PWR BI EPX - EP EXERCISE INSPECTION / PI VERIFICATION 2 1 10/06/2014 12/12/2014 IP 7111408 Exercise Evaluation - Scenario Review 1 12/08/2014 12/12/2014 IP 7111401 Exercise Evaluation 1 12/08/2014 12/12/2014 IP 71151 Performance Indicator Verification OL PREP - INIT EXAM/FEB 2015 3 1 01/26/2015 01/30/2015 W90334 OL - INITIAL EXAM - 2015 JAN-FEB - POINT BEACH OL EXAM - INIT EXAM/FEB 2015 3 1 02/23/2015 03/06/2015 W90334 OL - INITIAL EXAM - 2015 JAN-FEB - POINT BEACH BI ENG - COMPONENT DESIGN BASIS INSPECTION 6 1, 2 02/23/2015 03/27/2015 IP 7111121 Component Design Bases Inspection BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 1 03/23/2015 03/27/2015 IP 71124.02 Occupational ALARA Planning and Controls BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 1 05/18/2015 05/22/2015 IP 71124.07 Radiological Environmental Monitoring Program 1 05/18/2015 05/22/2015 IP 71151-BI01 1 05/18/2015 05/22/2015 IP 71151-OR01 1 05/18/2015 05/22/2015 IP 71151-PR01 71152B - BIENNIAL PI&R 4 1, 2 06/22/2015 07/10/2015 IP 71152B Problem Identification and Resolution BI EPEX - EMERGENCY PREPAREDNESS EXERCISE EVAL 2 1, 2 07/15/2015 09/18/2015 IP 7111408 Exercise Evaluation - Scenario Review This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Point Beach 08/22/2014 09:43:49 Inspection / Activity Plan Report 22 09/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site BI EPEX - EMERGENCY PREPAREDNESS EXERCISE EVAL 2 1, 2 09/14/2015 09/18/2015 IP 7111407 Exercise Evaluation - Hostile Action (HA) Event 1 09/14/2015 09/18/2015 IP 71151 Performance Indicator Verification BI MODS - MODIFICATIONS / 50.59 INSPECTION 3 1, 2 08/10/2015 08/28/2015 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 1 08/17/2015 08/21/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation BI OLRQ - BIENNIAL REQUAL PROGRAM INSPECTION 2 1, 2 08/17/2015 08/21/2015 IP 7111111B Licensed Operator Requalification Program BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 1 10/05/2015 10/09/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls BI ISI - ISI UNIT 2 INSPECTION 1 2 10/07/2015 11/10/2015 IP 7111108P Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.