UNITED STATES rch 1, 2017

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 (REPORT 05000266/2016006 AND 05000301/2016006)

Dear Mr. Coffey:

The NRC has completed its end-of-cycle performance assessment of Point Beach Nuclear Plant, Units 1 and 2, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2016, through December 31, 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.

The NRC determined the performance at Point Beach Nuclear Plant, Units 1 and 2, during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2018.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.

The enclosed inspection plan includes, among other items, a team inspection in May 2017 under Temporary Instruction 191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/

Staffing/Multi-Unit Dose Assessment Plans. In June and July 2017 the NRC will conduct a team triennial inspection using inspection procedure 71111.21M, Design Bases Assurance Inspection (Team). In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630-829-9833 with any questions you have regarding this letter.

Sincerely,

/RA/

Jamnes Cameron, Chief Branch 4 Division of Reactor Projects Docket Nos: 50-266; 50-301 License Nos: DPR-24; DPR-27 Enclosure:

Inspection Plan cc: Distribution via LISTSERV