ML13172A407

From kanterella
Jump to navigation Jump to search
Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000266-13-010; 05000301-13-010
ML13172A407
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 06/20/2013
From: Robert Daley
Engineering Branch 3
To: Meyer L
Point Beach
Dariusz Szwarc
References
IR-13-010
Download: ML13172A407 (10)


See also: IR 05000266/2013010

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210

LISLE, IL 60532-4352

June 20, 2013

Mr. Larry Meyer

Site Vice President

NextEra Energy Point Beach, LLC

6610 Nuclear Road

Two Rivers, WI 54241

SUBJECT: POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - NOTIFICATION OF NRC

TRIENNIAL FIRE PROTECTION BASELINE INSPECTION REQUEST FOR

INFORMATION 05000266/2013010; 05000301/2013010

Dear Mr. Meyer:

On October 7, 2013, the U.S. Nuclear Regulatory Commission (NRC) will begin a Triennial Fire

Protection Baseline Inspection at your Point Beach Nuclear Plant, Units 1 and 2. This

inspection will be performed in accordance with Inspection Procedure (IP) 71111.05T, the

NRCs baseline fire protection inspection procedure.

Changes were made to the IP which now requires the fire protection inspection to review your

actions to mitigate postulated events that could potentially cause loss of large areas of power

reactor facilities due to explosions or fires. This requirement was implemented by the issuance

of the Interim Compensatory Measures Order EA-02-026, Section B.5.b and the subsequent

requirements of 10 CFR 50.54(hh)(2), which are collectively referred to as B.5.b requirements.

During this inspection, the B.5.b requirements review will be performed during the first onsite

week of the inspection, starting on October 9, 2013.

The schedule for the onsite inspection activity is as follows:

  • Information Gathering Visit: October 7 - 9, 2013;
  • B.5.b Requirements: October 9 - 11, 2013; and
  • Fire Protection Inspection: October 21 - 25, 2013 and November 4 - 8, 2013.

The purpose of the information gathering visit is: (1) to obtain information and documentation

needed to support the inspection; (2) to become familiar with the Point Beach Nuclear Plant Fire

Protection Program, fire protection features, post-fire safe shutdown capabilities, and plant

layout; and (3) to arrange administrative details, such as office space, availability of

knowledgeable office personnel and to ensure unescorted site access privileges.

Experience has shown that the baseline fire protection inspections are extremely resource

intensive both for the NRC inspectors and the licensee staff. In order to minimize the inspection

impact on the site and to ensure a productive inspection for both organizations, we have

enclosed a request for documents needed for the inspection. These documents have been

divided into four groups. The first group lists information necessary to aid the inspection team in

L. Meyer -2-

choosing specific focus areas for the inspection. It is requested that this information be

provided to the lead inspector via mail or electronically no later than (September 23, 2013). The

second group also lists information and areas for discussion necessary to aid the inspection

team in choosing specific fire protection focus areas for the inspection and to ensure that the

inspection team is adequately prepared for the inspection. It is requested that this information

be available during the information gathering visit (October 7, 2013). The third group of

requested documents consists of those items that the team will review, or need access to,

during the inspection. Please have this information available by the first day of the second

onsite inspection week (October 21, 2013). The fourth group lists the information necessary to

aid the inspection team in tracking issues identified as a result of the inspection. It is requested

that this information be provided to the lead inspector as the information is generated during the

inspection. It is important that all of these documents are up-to-date and complete in order

to minimize the number of additional documents requested during the preparation and/or the

onsite portions of the inspection.

The lead inspector for this inspection is Mr. Dariusz Szwarc. We understand that our regulatory

contact for this inspection is Ms. Kim Locke of your organization. If there are any questions

about the inspection or the material requested, please contact the lead inspector at

(630) 829-9803 or via e-mail at dariusz.szwarc@nrc.gov.

This letter does not contain new or amended information collection requirements subject to

the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget Control Number

3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to a

request for information or an information collection requirement unless the requesting document

displays a currently valid Office of Management and Budget Control Number.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records System (PARS)

component of NRC's Agencywide Document Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA/

Robert C. Daley, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos. 50-266; 50-301

License Nos. DPR-24; DPR-27

Enclosure: Fire Protection Inspection Document Request

cc w/encl: Distribution via ListServ'

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

Inspection Report: 05000266/2013010; 05000301/2013010

Onsite Inspection Dates: October 7 - 9, 2013, (Information Gathering Visit)

October 9 - 11, 2013, (B.5.b Requirements)

October 21 - 25, 2013, (Fire Protection Inspection)

November 4 - 8, 2013, (Fire Protection Inspection)

Inspection Procedures: Inspection Procedure 71111.05T, Fire Protection (Triennial)

Inspection Procedure 71152, "Identification and Resolution of

Problems"

Inspectors: Dariusz Szwarc

(630) 829-9803

dariusz.szwarc@nrc.gov

Mohammad Munir Robert Winter

(630) 829-9797 (630) 829-9758

mohammad.munir@nrc.gov robert.winter@nrc.gov

I. Information Requested Prior to the Information Gathering Visit

The following information is requested by September 23, 2013. If you have any

questions regarding this request, please call the lead inspector as soon as possible.

All information should be sent to Mr. Dariusz Szwarc (e-mail address

dariusz.szwarc@nrc.gov). Electronic media is preferred. The preferred file format is a

searchable pdf file on a compact disk (CD). The CD should be indexed and hyper-

linked to facilitate ease of use, if possible. Please provide three copies of each CD

submitted (one for each inspector).

1. The most risk-significant fire areas as determined by probabilistic risk-analyses, if

available. Otherwise, the reactor plant's Individual Plant Examination for External

Events (IPEEE) for fire and results of any post-IPEEE reviews for fire.

2. A copy of the current version of the Fire Protection Program (FPP), Fire Hazards

Analysis (FHA), Safe Shutdown Analysis (SSA), Updated Safety Analysis Report

(USAR), Technical Specifications, license (including the fire protection license

condition), and Technical Requirements Manual (TRM) or equivalent for fire

protection structures, systems, and components.

3. A list of fire areas requiring alternative shutdown capability, (i.e., those areas for

which 10 CFR Part 50, Appendix R, Section III G, requirements are satisfied

under Section III.G.3), or where both safe shutdown trains can be affected.

4. Plant operating procedures which would be used and describe shutdown for a

postulated fire (for both areas requiring alternative shutdown and areas which do

not require alternative shutdown). Only those procedures with actions specific to

shutdown in the event of a fire need be included. In addition, please include

those procedures which operators would use for initial response to a fire, such as

annunciator or alarm response procedures, the procedure used for activating the

fire brigade, and the procedure which directs operators to the applicable safe

shutdown procedure.

1 Enclosure

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

II. Information Requested During the Information Gathering Visit (October 7, 2013)

The following information is requested to be provided to the inspection team during the

onsite information gathering visit. Except for Item 8, it is requested that the following

information be provided on three sets of CDs (searchable, if possible) with the B.5.b

Mitigating Strategies information (Items 8.a through 8.h) provided on one separate CD. In

addition, one set of hard copy drawings are requested for Items 4.a. through 4.d.

1. One set of hard-copy documents for facility layout drawings which identify plant fire area

delineation; areas protected by automatic fire suppression and detection; and locations

of fire protection equipment.

2. Licensing Information:

a. All Nuclear Regulatory Commission (NRC) Safety Evaluation Reports (SERs)

applicable to fire protection (specifically including those SERs referenced by

the plant fire protection license condition) and all licensing correspondence

referenced by the SERs;

b. All licensing correspondence associated with the comparison to Standard Review

Plan (NUREG-0800), Section 9.5.1 or equivalent for licensing purposes;

c. Exemptions from 10 CFR 50.48 and 10 CFR Part 50, Appendix R, and associated

licensing correspondence;

d. All licensing correspondence associated with those sections of 10 CFR Part 50,

Appendix R, that are not applicable to the plant under 10 CFR 50.48(b)(1).

Specifically, the licensing correspondence associated with those fire protection

features proposed or implemented by the licensee that have been accepted by the

NRC staff as satisfying the provisions of Appendix A to Branch Technical

Position (BTP) APCSB 9.5-1 reflected in the NRC fire protection SERs issued

before February 19, 1981, (10 CFR 50.48(b)(1)(i)); or those fire protection features,

which were accepted by the NRC staff in comprehensive fire protection SERs

issued before Appendix A to BTP APCSB 9.5-1 was published in August 1976,

(10 CFR 50.48(b)(1)(ii)); and

e. The Final Safety Analysis Report (FSAR) sections applicable to fire protection,

FHA, and SSA in effect at the time of original licensing.

3. Fire Protection Program:

a. A listing of changes made to the FPP since the last Triennial Fire Protection

Inspection;

b. A listing of the protection methodologies identified under 10 CFR Part 50,

Appendix R,Section III.G used to achieve compliance for selected fire zones/areas

(to be determined during information gathering visit). That is, please specify

whether 3-hour rated fire barriers; (Section III.G.2.a), 20 foot separation along with

detection and suppression; (Section III.G.2.b), 1-hour rated fire barriers with

detection and suppression; (Section III.G.2.c), or alternative shutdown capability;

(Section III.G.3) is used as a strategy for each selected fire zone/area;

2 Enclosure

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

c. A list of Generic Letter 86-10 evaluations (i.e., a list of adverse to safe-shutdown

evaluations);

d. A list of applicable codes and standards related to the design of plant fire

protection features. The list should include National Fire Protection Association

(NFPA) code versions committed to (i.e., the NFPA Codes of Record); and

e. List of plant deviations from code commitments and associated evaluations.

4. Facility Information:

a. Piping and instrumentation (flow) diagrams showing the components used to

achieve and maintain hot standby and cold shutdown for fires outside the control

room, those components used for those areas requiring alternative shutdown

capability, and systems relied upon for B.5.b mitigation strategies. These can be

of the type that are used for training;

b. One-line schematic drawings of the electrical distribution system for 4160 Volts

alternating current (Vac) down to 480Vac;

c. One-line schematic drawings of the electrical distribution system for 250 Volts

direct current (Vdc) and 125Vdc systems as applicable;

d. Logic diagrams showing the components used to achieve and maintain hot

standby and cold shutdown; and

e. Safe shutdown cable routing database (requested electronically such as on

compact disc, if available.

5. Operations Response for Fire Protection:

a. Pre-fire plans for selected fire zones/areas (to be determined during information

gathering visit);

b. Plant operating procedures which specify the initial operations response to a fire

alarm or annunciator; and

c. Procedure for calling out the fire brigade and requesting off-site assistance.

6. Corrective Actions:

a. Listing of open and closed fire protection condition reports (i.e., problem

identification forms and their resolution reports) since the date of the last Triennial

Fire Protection Inspection; and

b. List of current fire impairments, including duration.

7. General Information:

a. A listing of abbreviations and/or designators for plant systems;

b. Organization charts of site personnel down to the level of fire protection staff

personnel; and

3 Enclosure

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

c. A phone list for onsite licensee personnel.

8. B.5.b Mitigating Strategies:

a. A list of all modifications to regulatory commitments made to meet the

requirements of Section B.5.b of the ICM Order, EA-02-026, dated

February 25, 2002, the subsequently imposed license conditions, and

10 CFR 50.54(hh)(2);

b. Copies of procedures/guidelines that were revised or generated to implement the

mitigation strategies. These could be Extensive Damage Mitigation Guidelines

(EDMGs), Severe Accident Management Guidelines (SAMGs), emergency

operating procedures (EOPs), and Abnormal Operating Procedures (AOPs), etc.;

c. A matrix that shows the correlation between the mitigation strategies identified in

Nuclear Energy Institute 06-12 and the site-specific procedures or guidelines that

are used to implement each strategy;

d. A listing of engineering evaluations/calculations that were used to verify

engineering bases for the mitigation strategies;

e. Copies of procedures used to inventory equipment (e.g., hoses, fittings, pumps,

etc.) required to be used to implement the mitigation strategies;

f. A list of B.5.b mitigating strategies, if any, which have implementing details that

differ from that documented in the submittals and the safety evaluation report;

g. Copies of Memoranda of Understanding (MOU) (e.g., with local fire departments)

required to implement any mitigating strategies; and

h. A list of changes made to B.5.b mitigating strategies and associated procedures

since the previous NRC inspection of B.5.b mitigating strategies (May 28, 2010).

9. Onsite Discussions:

In addition, during the information gathering visit, it is requested that licensee staff be

available for the following:

a. Informal discussion on plant procedures that operators would use in the event of

fire or explosion (including B.5.b mitigation strategies) and under what conditions

would the plant be shutdown using alternative shutdown methodology;

b. Informal discussion on the plants safe shutdown cable routing database and the

plant-wide cable routing database, as applicable;

c. Informal discussion on the status of NFPA-805 transition and associated risk

insights identified;

d. A tour of alternative shutdown and risk-significant fire areas; and

e. A discussion of scheduling of fire drills which may occur during the inspection so

that the inspectors may be able to observe a fire drill.

4 Enclosure

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

III. Information Requested to be Available on First Day of the Second Onsite Inspection

Week (October 21, 2013)

The following information is requested to be provided on the first day of inspection. It is

requested that this information be provided on three sets of CDs (searchable, if possible).

1. Program Procedures:

a. Procedures for:

i. Administrative controls (such as allowed out of service times and compensatory

measures) for fire protection systems and components

ii. Control of transient combustibles

iii. Control of hot work;

b. List of maintenance and surveillance testing procedures for alternative shutdown

capability and fire barriers, detectors, pumps, and suppression systems; and

c. List of maintenance procedures which routinely verify fuse breaker coordination

in accordance with the post-fire safe shutdown coordination analysis.

2. Design and Equipment Information:

a. Coordination calculations and/or justifications that verify fuse/breaker coordination for

selected fire zones/areas (to be determined during information gathering visit)

that are fed off of the same electrical buses as components in the protected safe

shutdown train;

b. Copies of significant fire protection and post-fire safe shutdown related design

change package descriptions (including their associated 10 CFR 50.59 evaluations)

and Generic Letter (GL) 86-10 (or adverse to safe shutdown) evaluations;

c. Gaseous suppression system pre-operational testing, if applicable, for selected fire

zones/areas (to be determined during information gathering visit);

d. Hydraulic calculations and supporting test data which demonstrate operability for

water suppression systems, if applicable, for selected fire zones/areas (to be

determined during information gathering visit);

e. Alternating current (ac) coordination calculations for 4160Vac down to 480Vac

electrical systems; and

f. List of all fire protection or Appendix R calculations.

3. Assessment and Corrective Actions:

The three most recent fire protection Quality Assurance (QA) audits and/or fire

protection self-assessments.

4. Any updates to information previously provided.

5 Enclosure

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

IV. Information Requested to be Provided Throughout the Inspection

1. Copies of any corrective action documents generated as a result of the inspection

teams questions or queries during this inspection.

2. Copies of the list of questions submitted by the inspection team members and the

status/resolution of the information requested (provided daily during the inspection to

each inspection team member).

If you have questions regarding the information requested, please contact the lead inspector.

6 Enclosure

L. Meyer -2-

choosing specific focus areas for the inspection. It is requested that this information be provided to the lead inspector

via mail or electronically no later than (September 23, 2013). The second group also lists information and areas for

discussion necessary to aid the inspection team in choosing specific fire protection focus areas for the inspection and

to ensure that the inspection team is adequately prepared for the inspection. It is requested that this information be

available during the information gathering visit (October 7, 2013). The third group of requested documents consists

of those items that the team will review, or need access to, during the inspection. Please have this information

available by the first day of the second onsite inspection week (October 21, 2013). The fourth group lists the

information necessary to aid the inspection team in tracking issues identified as a result of the inspection. It is

requested that this information be provided to the lead inspector as the information is generated during the

inspection. It is important that all of these documents are up-to-date and complete in order to minimize the number of

additional documents requested during the preparation and/or the onsite portions of the inspection.

The lead inspector for this inspection is Mr. Dariusz Szwarc. We understand that our regulatory contact for this

inspection is Ms. Kim Locke of your organization. If there are any questions about the inspection or the material

requested, please contact the lead inspector at (630) 829-9803 or via e-mail at dariusz.szwarc@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction

Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of

Management and Budget Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not

required to respond to a request for information or an information collection requirement unless the requesting

document displays a currently valid Office of Management and Budget Control Number.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your

response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records System (PARS) component of NRC's Agencywide Document Access and Management

System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA/

Robert C. Daley, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos. 50-266; 50-301

License Nos. DPR-24; DPR-27

Enclosure: Fire Protection Inspection Document Request

cc w/encl: Distribution via ListServ'

DISTRIBUTION:

See next page

DOCUMENT NAME: Ltr 62013 Point Beach FP3 RFI Letter DXS4.docx

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy

OFFICE RIII RIII

NAME DSzwarc:ls RCDaley

DATE 06/19/13 06/20/13

OFFICIAL RECORD COPY

Letter to Mr. Larry Meyer from Mr. Robert C. Daley dated June 20, 2013.

SUBJECT: POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - NOTIFICATION OF NRC

TRIENNIAL FIRE PROTECTION BASELINE INSPECTION REQUEST FOR

INFORMATION 05000266/2013010; 05000301/2013010

DISTRIBUTION:

Vivian Campbell

RidsNrrDorlLpl3-1 Resource

RidsNrrPMPointBeach

RidsNrrDirsIrib Resource

Chuck Casto

Cynthia Pederson

Steven Orth

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Patricia Buckley

Tammy Tomczak