NEXTera ENERGY.
POINT BEACH February 21, 2023 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 NRC 2023-0005 10 CFR 50.54(q) 10 CFR 72.44(f)
Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 Report of Changes to Emergency Plan In accordance with 10 CFR 50.54(q)(5) and 10 CFR 72.44(f), NextEra Energy Point Beach, LLC (NextEra) hereby submits a description of changes to the Point Beach Nuclear Plant (PBNP)
Emergency Plan and a summary of the analysis demonstrating that the changes do not reduce the effectiveness of the plan. The plan continues to meet the requirements in 10 CFR 50 Appendix E and the planning standards of 10 CFR 50.47(b). The changes were incorporated in the following procedures issued February 10, 2023 at PBNP:
EP 8.0, Maintaining Emergency Preparedness, Revision 59 EP Appendix A, Emergency Response Organization Personnel Function and Responsibility, Revision 36 EP Appendix K, NUREG-0654 Cross Reference Matrix, Revision 7 EP Appendix M, Matrix for Emergency Preparedness Equipment, Revision 13 Description of Changes and Summary of Analysis EP 8.0 was revised to remove PASS and Chemistry Drills.
EP Appendix A replaced Post Accident sampling to contingency sampling.
EP Appendix K replaced EPIP 8.4.1 with CAMP 611 and EPIP 8.4.2 with CAMP 612.
EP Appendix M replaced Post Accident sampling to contingency sampling.
These changes were driven by LAR 296, Eliminate Requirements for Post-Accident Sampling Systems, via NRG Safety Evaluation dated September 12, 2022 that approved the "Elimination of Requirements for Post-Accident Sampling System (PASS)."
These changes were evaluated in accordance with 10 CFR 50.54(q)(3). These changes were determined to not reduce the effectiveness of the PBNP Emergency Plan.
This letter contains no new regulatory commitments or revisions to existing commitments. If you have any questions, please contact Denny Smith at 920-755-6001.
NextEra Energy Point Beach, LLC 6610 Nuclear Road, Two Rivers, WI 54241
NRC 2023-0005 Document Control Desk Page 2 Sincerely, NextEra Energy Point Beach, LLC Eric Schultz Regulatory Affairs Manager cc:
Incident Response Center, Region Ill Resident Inspector, Point Beach Nuclear Plant, USNRC